Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-1
13 EFFECTS ON ALL TRAVELLERS
13.1 Introduction
13.1.1 The purpose of this chapter is to assess the potential effects of the
Scheme on vehicle travellers, as stipulated within Design Manual for
Roads and Bridges (“DMRB”), Volume 11, Section 3, Part 9, ‘Vehicle
Travellers’ (Ref 13-1); and for ‘Non-Motorised Users’ (“NMUs”)1, as
required by DMRB, Volume 11, Section 3, Part 8, ‘Pedestrians, Cyclists,
Equestrians and Community Effects’ (Ref 13-2).
13.1.2 As acknowledged in DMRB, the effects which are assessed are
qualitative, subjective assessments which cover the 'view from the road'
experienced by vehicle travellers and the potential for ‘driver stress’
caused by a number of factors, as described below.
13.1.3 NMUs, whilst not permitted to use motorways for safety reasons, may be
affected by the Scheme when travelling on the locally adopted highway
network and other Public Rights of Way (“PRoW”) surrounding or
interacting with the Scheme as shown on the Environmental Masterplan,
which can be found in Annex A of the Engineering and Design Report
(“EDR”) (Document Reference 7.4). These PRoW comprise footpaths and
bridleways, several of which cross the M4 on overbridges and
underbridges or via subways.
13.1.4 Due to the nature of the assessment of effects on all travellers, this
chapter reports the assessment as a Scheme wide assessment, rather
than on a link by link basis as with other chapters of this Environmental
Statement (“ES”). This chapter is structured under the following sections:
a) Methodology;
b) Baseline conditions;
c) Value (sensitivity) of resource;
d) Regulatory/policy framework;
e) Design, mitigation and enhancement measures, including
monitoring requirements;
f) Assessment of residual effects upon travellers;
1 DMRB Volume 11 Section 3, part 8 refers to NMUs in full as ‘pedestrians, cyclists, equestrians’ and
in short as ‘pedestrians and others’.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-2
g) Net effects of the Scheme on vehicle travellers in the Design Year
(2037);
h) Cumulative effects;
i) Limitations encountered in compiling the ES; and
j) Summary.
13.1.5 All drawings referenced within this chapter are presented in Document
Reference 6.2 (ES Figures), and all appendices referenced in this chapter
are presented in Document Reference 6.3 (ES Appendices).
13.2 Methodology
General approach
13.2.1 The methodology to assess the effects of the Scheme on all travellers is
qualitative, and taken from DMRB (Ref 13-1 and 13-2). The combined use
of these separate subject assessment frameworks is prescribed in Interim
Advice Note (“IAN”) 125/09 ‘Supplementary guidance for users of DMRB
Volume 11 ‘Environmental Assessment’’ (Ref 13-3), Section 2.2.
13.2.2 The assessments have also been undertaken in accordance with the
general principles and structure of assessment methodology contained
within DMRB Volume 11, Section 2, Part 5 HA 205/08 ‘Assessment and
Management of Environmental Effects’ (Ref 13-4), which has been
applied, as appropriate, and tailored to the context of the Scheme. These
include: the definition of assessment years and scenarios of assessment;
information assembly; identifying potential impacts, including permanent,
temporary and cumulative impacts; determining the significance of
environmental effects by combining the environmental value and
magnitude of impacts; determining the significance of cumulative effects;
and management of environmental effects.
Vehicle travellers
View from the road
13.2.3 Chapter 2 of DMRB Volume 11, Section 3, Part 9, entitled ‘View from the
Road’, suggests that benefits can be experienced by drivers as a result of
the construction of new roads in areas of ”high quality scenic landscapes”,
with “views ‘out from the road’ providing interest and helping to alleviate
driver stress.” Conversely, if a new road passes through heavily
industrialised or other visually unattractive areas, this can constitute an
adverse effect, and may cause an increase in driver stress. Whilst DMRB
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-3
refers to 'new roads', it is considered that the principles can be applied
appropriately to improvements to existing roads, such as those proposed
as part of the Scheme.
13.2.4 Paragraph 2.6 of DMRB (Volume 11, Section 3, Part 9) allows schemes to
be placed in one of four categories as part of the subjective review: ‘no
view’ (the road is deep in a cutting); ‘restricted view’ (frequent cutting or
structures cutting the view); ‘intermittent view’ (road at ground level but
with shallow cuttings or barriers at intervals); and ‘open view’ (the view
extending over many miles). These categories have been determined to
provide an assessment of the surrounding landscape (the view beyond the
confines of the highway), not the road or roadside infrastructure itself
(gantries, bridges, signage), which only temporarily affects views.
13.2.5 As the M4 already exists and the Scheme provides only minor highway
alignment modifications, together with additional driver information,
reallocation of carriageway space and minor carriageway widening, it is
considered that the view from the M4 will not change materially as a result
of the Scheme. However, additional gantries that are necessary for the
information system signs will provide intermittent interruptions to the view,
albeit ones that are consistent with typical motorway infrastructure.
13.2.6 DMRB does not require an assessment of views from a road for vehicle
travellers on local roads. Views from side roads do not change in the same
way as views on the road being improved, as set out above, save for
glimpsed views and minor additional infrastructure on collector roads. The
‘view from the road’ assessment has therefore not been deemed
appropriate or applicable on local roads, and as such has been scoped out
of assessment in this chapter. However, an assessment of the effect of the
Scheme on visual amenity from local roads and PRoWs which interact
with the Scheme is included in chapter 8 Landscape.
Driver stress
13.2.7 Chapter 3 of DMRB Volume 11, Section 3, Part 9 is entitled ‘Driver Stress’,
and centres around the assessment of driver stress, which is defined as
“the adverse mental and physiological effects experienced by a driver
traversing a road network” (paragraph 3.1), which could be influenced by
factors such as “road layout and geometry, surface riding characteristics,
junction frequency, and speed and flow”. DMRB also notes that drivers will
select routes “which they believe to give the shortest reliable journey time,
taking account of expected variability” (paragraph 3.3). In combination,
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-4
induced feelings of “discomfort, annoyance, frustration or fear, culminating
in physical and emotional tension” are said to potentially reduce the safety
of a journey. As such, the assessment of the effects of a scheme on driver
stress is an important part of the Environmental Impact Assessment
(“EIA”) process, requiring a qualitative and relative assessment between
the Do Something and Do Minimum options for the “worst year in the first
fifteen after opening”. In the case of the Scheme, this is taken as 2037 (the
‘Design Year’), as year on year traffic growth is assumed to occur.
13.2.8 It should be noted that despite the numerous elements contributing to
driver stress noted above, only speed and flow are used within the
assessment of driver stress under DMRB methodology.
13.2.9 The methodology and scenarios contained within the assessment are in
accordance with DMRB and are described below. These scenarios are
then subject to the analysis of driver stress.
13.2.10 DMRB suggests driver stress is comprised of three components:
a) Frustration, associated with a driver’s inability to drive at a
consistent speed, such as the speed limit (due to congestion), with
frustration increasing as traffic speeds fall, or at junctions and road
works. This could also apply to the journey time reliability
mentioned above, and the experience of drivers being caught in
severe congestion (such as gridlock caused by traffic flow
breakdown), etc;
b) Fear of potential accidents, which may be associated with the
presence and proximity of other vehicles, inadequate sight and
stopping distances, poor lighting, road works and poor surfacing,
with feelings compounded during adverse weather; and
c) Route uncertainty, primarily associated with inadequate signing and
information.
13.2.11 DMRB notes that the available research does not permit a detailed
assessment of driver stress, and instead the assessor should use a simple
three-point descriptive scale (low, moderate or high) to assess driver
stress, relatively comparing Do Something and Do Minimum options. It
also suggests that this should be applied to the ‘worst year’ in the first 15
years after opening.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-5
13.2.12 Table 13.1 reproduces the assessment framework for driver stress on
motorways from DMRB, with driver stress being considered to be a
function of purely average peak hourly flow per lane and average journey
speed. As noted above, no other elements which contribute to driver
stress, such as those mentioned in paragraph 13.2.10, are considered
within the assessment framework.
Table 13.1 Description of driver stress on motorways
Average peak hourly flow per lane (flow/hour)
Average journey speed (km/hr)
Under 75 75-95 Over 95
Under 1200 High Moderate Low
1200-1600 High Moderate Moderate
Over 1600 High High High
Source: DMRB, Volume 11, Section 3, Part 9
13.2.13 The simple and rigid framework summarised in the table equates slowing
speeds and increasing flow with elevated driver stress. In order to ensure
that the assessment of driver stress applied to the Scheme is appropriate,
assessors have had regard to the origin of the assessment methodology
and changes in circumstances in the intervening period.
13.2.14 The assessment methodology is based upon research from 19902 , at a
time when smart motorways had not yet been conceived in the United
Kingdom (Ref 13-5). Slower speeds and increased traffic flows are two
characteristics of smart motorways, which regulate (by reducing) traffic
speeds to prevent flow breakdown, which in turn increases total traffic
throughput thereby increasing flows. In the driver stress assessment, this
would result in an increase in driver stress.
13.2.15 However, since the development of DMRB methodology, understanding of
the principal factors which cause driver stress has developed, and
frustration at the inability to drive at a constant speed, as well as unreliable
journey times, are now considered to represent factors of increased
importance in assessing driver stress, both of which factors are addressed
by the introduction of a smart motorway.
2 Uncertainty and Driver Stress: A Review. Oxford University Transport Studies Unit: Bates, Davies, Goodwin,
Kenny, Parkes, Richardson, 1990.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-6
13.2.16 Similarly, the other known benefits which result from the introduction of
smart motorways, such as maintaining existing high safety standards, are
not factored into the assessment methodology for determining driver
stress. These benefits, which are discussed in DMRB (noted within
paragraph 13.2.10 above), but are excluded from the limited speed and
flow analysis assessment prescribed, are discussed in paragraphs 13.8.11
to 13.8.16 of this chapter.
13.2.17 In addition, journey time reliability, a factor considered to be extremely
important for both highway users and traffic managers3 in controlling
congestion and smoothing traffic flow (which could be said to reduce driver
stress), is omitted from the assessment methodology (Ref 13-6).
13.2.18 Consequently, this simple assessment methodology is not appropriate for
application to the Scheme. As such, the assessment of the effects of the
Scheme on drivers seeks to augment DMRB assessment methodology on
journey quality to address these omissions and develop understanding of
the effects of a smart motorway on driver stress. Professional judgement
is used where the assessment methodology has been augmented in this
way.
13.2.19 As noted above (paragraph 13.2.3), the assessment methodology in
DMRB focuses on the road being constructed or modified - the Scheme.
However, for a more robust assessment, distributor roads or roads
crossing the M4 within the Order limits, which may be used as alternative
routes during construction, or may have changes in traffic routeing as a
result of the operation of the Scheme, are also considered within this
assessment.
13.2.20 The assessment framework for driver stress on the non-motorway, local
road network, which consists of dual and single carriageways, is provided
in Tables 13.2 and 13.3. The roads that have been assessed on this basis
are presented in Tables 13.4 and 13.5.
3 http://www.tfl.gov.uk/cdn/static/cms/documents/technical-note-11-to-what-extent-is-congestion-and-
unreliability-on-the-road-network.pdf
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-7
Table 13.2 Description of driver stress on dual-carriageway roads
Average peak hourly flow per lane (flow/hour)
Average journey speed (km/hr)
Under 60 60-80 Over 80
Under 1200 High2 Moderate Low
1200-1600 High Moderate Moderate
Over 1600 High High High
Source: DMRB, Volume 11, Section 3, Part 9
2 ‘Moderate’ in urban areas.
Table 13.3 Description of driver stress on single-carriageway roads
Average peak hourly flow per lane (flow/hour)
Average journey speed (km/hr)
Under 50 50-70 Over 70
Under 600 High2 Moderate Low
600-800 High Moderate Moderate
Over 800 High High High
Source: DMRB, Volume 11, Section 3, Part 9
2 ‘Moderate’ in urban areas. Note: The figures given in the tables are considered to be for guidance only, and no similar tables are produced for roads operating under construction conditions. Using expert judgment they have been applied to the construction scenario for this assessment and this is explained below.
13.2.21 At this stage, the contractor, responsible for construction of the Scheme,
has not been appointed and, as such, it is not possible to provide detailed
information on the final construction and logistics plan, and therefore an
Outline Environmental Management Plan (“EMP”) has been developed to
accompany this ES (Appendix 4.2). An Outline Construction
Environmental Management Plan (“CEMP”) is contained in the Outline
EMP and will be finalised pursuant to a requirement attached to the DCO.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-8
13.2.22 However, support and construction advice has been sought from the
Agency contractors’ panel who have provided programme and
construction information. This advice has established traffic management
scenarios on which a simple assessment of the construction effects has
been developed. This is explained more fully below. The data used within
the assessments on driver stress, such as traffic flow (as Annual Average
Daily Traffic (“AADT”)), traffic speeds and the percentage of Heavy Goods
Vehicles (“HGVs”) are extracted from the Scheme traffic model.
13.2.23 DMRB stipulates that to establish the effect of the Scheme on driver
stress, the following assessment scenarios are required:
a) a base year - for the purposes of this assessment a 2013 base year
has been used, which is rebased to include traffic growth between
2009 and 2013 (2009 being the original base year, defined as the
year that traffic data were collected and traffic model construction
started);
b) a 2037 Do Minimum scenario - as noted above, DMRB requires a
scenario to be tested which is equivalent to the worst case year 15
years after scheme opening. As the Scheme is scheduled to be
operational in 2022, the Design Year for assessment purposes,
when traffic flows are at their highest, is assumed to be in 2037.
The 2037 Do Minimum scenario is equivalent to traffic conditions in
2037, which include traffic growth forecasts in accordance with
WebTAG, but assume the Scheme is not built;
c) 2037 Do Something - this scenario is the same as the Do Minimum
scenario in terms of traffic demand forecasts (i.e. traffic growth is
applied to 2037), but with the inclusion of the Scheme; and
d) in addition to these scenarios, a 2018 construction impact
assessment has been undertaken. 2018 was selected as this is
likely to be the time when traffic management has been introduced
to substantial portions of the Scheme to support the Scheme
construction works. This 2018 period4 is likely to have traffic
characteristics mid-way between the Do Minimum and Do
Something scenarios. In accordance with the EDR (Document
Reference 7.3), this assumes the Scheme is under construction (by
4 Traffic models exist for each year of the construction period years, with alternative construction sub-
options for each of these years. As the models each produce similar results, the mid-way point has been selected for reporting purposes and brevity.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-9
2018 the construction programme indicates part of the Scheme
between junction 8/9 and 12 is already open), and traffic
management will be in place with all running lanes operational with
narrower lanes and a reduced speed limit of 50 mph in place on the
eastern portion of the Scheme.
13.2.24 Unlike in other environmental assessment chapters of DMRB, such as
those prescribed in DMRB, Volume 11, Section 2, Part 5 (HA 205/08)
‘Assessment and Management of Environmental Effects’ (Ref 13-4),
where the ‘significance’ of environmental effects is scored using
‘significance criteria’ in a 25 point matrix containing a five-point
environmental value (sensitivity) score and a five-point magnitude of
impact (degree of change) score, none of the assessments contained
within the ‘vehicle traveller’ chapter of DMRB has assessment ‘significance
criteria’. However, given the simplistic nature of DMRB assessment
methodology, this affords the opportunity to adapt and augment the driver
stress and journey quality scoring framework, without deviating from the
overall approach.
13.2.25 The relative assessment methodology defined within DMRB requires the
comparison of the change in circumstances for the Do Minimum and Do
Something options for the Design Year (2037). These scenarios have
therefore been compared within the analysis, and the ‘net effects’ of
change (attributable to the Scheme) have been presented. This has also
been undertaken for construction effects in 2018 as noted above. The
baseline traffic conditions for driver stress in 2013 are also presented. The
qualitative, comparative outputs are presented as changes which are
classified as neutral, beneficial or adverse. The ‘magnitude of impact’ is
classified as major, moderate, minor, negligible, or no change in
accordance with Table 2.2 of DMRB, Volume 11, Section 2, Part 5, 205/08
(Ref 13-4), which is reproduced in Appendix 13.1.
13.2.26 The augmented methodology on journey quality proposed here, in addition
to using DMRB speed and flow tables for each free running stretch of the
Scheme, and for each of the local roads, introduces the ‘missing factors’
referred to above. These are:
a) journey time reliability;
b) road surfacing;
c) road layout and geometry;
d) junction frequency;
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-10
e) safety;
f) driver information; and
g) reduction of general congestion and likelihood of ‘traffic flow
breakdown’.
13.2.27 These are scored as beneficial, neutral or adverse for the entire Scheme,
rather than for each link, and assigned a ‘magnitude of impact’ of major,
moderate, minor, negligible, or no change, comparing the Do Minimum
and Do Something scenarios.
Non-motorised users
13.2.28 The assessment of the Scheme effects on pedestrians, cyclists and
equestrians - NMUs - is focussed on the impact on the PRoW.
13.2.29 For NMUs the sensitivity, magnitude of impact and significance of effects
have been assessed in accordance DMRB Volume 11, Section 2, Part 5,
HA 205/08 (Ref 13-4), summary tables of which are provided in Appendix
13.1.
Study area
13.2.30 Following DMRB, the study area for the assessment of all travellers is the
M4 junctions 3 to 12. However, for robustness, consideration has also
been given to roads outside of this study area, which may be affected by
traffic re-assignment as a result of the Scheme during construction and
operation. Primarily, these affected roads are M4 distributor roads, and
roads that pass over, beneath or parallel to the M4 (which could be used
as alternative routes). The roads that are included within this assessment
are summarised within Tables 13.4 and 13.5.
Table 13.4 Roads potentially affected by the Scheme (M4 approaches)
M4junction Route
j12 A4W towards Theale A4W towards Calcot j12 A4E from Theale A4E from Calcot j11 A33S towards Three Mile Cross A33S towards Reading j11 A33N from Three Mile Cross A33N from Reading j11 A33S towards Basingstoke B3270E towards Whitley Wood j11 A33N from Basingstoke B3270W from Whitley Wood
j10 A329MS towards Bracknell A329MN towards Winnersh j10 A329MN from Bracknell A329MS from Winnersh j8/9 A308ME towards Maidenhead A404N towards Bisham j8/9 A308MW from Maidenhead A404S from Bisham j7 M4 Spur towards Slough A4W towards Slough
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-11
M4junction Route
j7 M4 Spur from Slough A4E from Slough j6 A355N towards Slough A355S from Slough
j6 A355N from Windsor A4W towards Slough j6 A355S towards Windsor A4E from Slough j5 B470W towards Datchet B470E from Datchet j5 A4E towards Heathrow A4W from Heathrow
j4b M25A north of junction M25C north of junction j4b M25A south of junction M25C south of junction
j4 M4 Spur towards Heathrow A408N towards Uxbridge j4 M4 Spur from Heathrow A408S from Uxbridge j3 A312S towards Heathrow A312N towards Southall j3 A312N from Heathrow A312S from Southall
Table 13.5 Roads potentially affected by the Scheme (A4 and crossing roads)
M4 junction
A4 links
j12 A4E towards Reading A4W from Reading j10 A4W towards Reading A4E from Reading
j10 to j8/9 A4W towards Reading A4E from Reading j8/9 A4W towards Maidenhead A4E from Maidenhead
j7 A4E from Maidenhead A4W towards Maidenhead j5 A4W towards Slough A4E from Slough j3 A312S towards Heathrow A312N from Heathrow j3 A4E towards Heathrow A4W from Heathrow
13.3 Baseline conditions
Vehicle travellers
Driver stress
13.3.1 A summary of average peak hourly flow per lane, average journey speed
and percentage of HGVs, is presented within Table 13.6 (eastbound
traffic) and Table 13.7 (westbound traffic) for the baseline year (2013), for
the mainline M4 carriageway, for the connected road network and for
roads that pass over, under or parallel to the Scheme5. The percentage of
HGVs is weighted by a factor of 3 in comparison to cars when calculating
the average peak hourly flow per lane, to take into account the size of the
vehicles in comparison to a car (this approach is specified within DMRB
and also standard methodology used when analysing vehicle ‘flow units’).
5 Entry and exit slips have not been considered as they would not align with the rigid speed and flow
tables provided in DMRB assessment framework due to the presence and close proximity of junctions, and short link lengths slowing speeds. The tables are designed for free flow sections of the link, not short motorway slips.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-12
Table 13.6 Existing estimated driver stress for drivers on the eastbound M4 carriageway for 2013 (base year)
M4 junctions
Link
2013 Base
Average peak hourly flow per lane (flow units/hr)
Average journey speed
(km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 1998 88 6.7% High
11-10 Mainline 2025 87 6.9% High
10-8/9 Mainline 1930 89 6.2% High
8/9-7 Mainline 2026 87 6.0% High
7-6 Mainline 1947 87 6.8% High
6-5 Mainline 2035 87 6.5% High
5-4b Mainline 1612 93 6.6% High
4b-4 Mainline 1672 83 4.8% High
4-3 Mainline 1907 67 6.1% High
13.3.2 All of the M4 links assessed are categorised as contributing to high levels
of driver stress in the base year in the eastbound direction.
Table 13.7 Existing estimated driver stress for drivers on the westbound M4 carriageway for 2013 (base year)
M4 junctions
Link
2013 Base
Average peak hourly flow per lane (flow units/hr)
Average journey speed
(km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 1746 94 6.5% High
11-10 Mainline 1860 91 6.0% High
10-8/9 Mainline 1776 93 5.8% High
8/9-7 Mainline 1866 91 5.8% High
7-6 Mainline 1835 90 6.2% High
6-5 Mainline 1961 88 6.0% High
5-4b Mainline 1620 92 5.8% High
4b-4 Mainline 1646 111 4.5% High
4-3 Mainline 1945 85 4.5% High
13.3.3 All of the westbound M4 links are categorised as contributing to high levels
of driver stress in the base year in the westbound direction.
13.3.4 A similar analysis has been performed on the local, connected or affected
roads in Table 13.8 using data taken from the strategic traffic model.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-13
Table 13.8 Existing estimated driver stress for drivers on non-motorway local, connected or affected roads – M4 approaches 2013 (base year)
M4 junction
Junction approach link
2013 Base
Average peak hourly flow
per lane (flow units/hr)
Average journey speed (km/hr)
Average HGVs (%)
Driver stress level
12
A4W towards Theale 906 30 6.9% High
A4E from Theale 865 98 11.1% Low
A4W towards Calcot 768 24 2.6% Moderate
A4E from Calcot 852 64 1.1% Moderate
11
A33N from Basingstoke 745 99 4.5% Low
A33S towards Basingstoke 829 87 4.9% Low
A33N from Three Mile Cross 770 64 6.0% Moderate
A33S towards Three Mile Cross 731 52 5.8% Moderate
A33N approach from Reading 336 15 4.8% Moderate
A33S towards Reading 532 39 3.5% Moderate
B3270W from Whitley Wood 836 61 1.4% High
B3270E towards Whitley Wood 915 61 1.3% High
10
A329MN towards Winnersh 1236 96 2.0% Moderate
A329MS from Winnersh 1173 97 2.0% Low
A33N from Bracknell 1869 82 2.6% High
A33S towards Bracknell 1726 86 3.1% High
8/9
A404N towards Bisham 1284 97 4.3% Moderate
A404S approach from Bisham 1481 93 3.5% Moderate
A308MN towards Maidenhead 707 103 3.2% Low
A308MS from Maidenhead 579 13 4.0% High
7 M4 Spur towards Slough 825 51 3.3% High
M4 Spur from Slough 757 103 5.1% Low
6
A355N towards Slough 1015 40 3.5% High
A355S approach from Slough 1047 95 5.1% Low
A355N from Windsor 503 90 1.1% Low
A355S towards Windsor 530 88 4.6% Low
5
A4W towards Slough 549 64 4.7% Moderate
A4E from Slough 478 64 7.4% Moderate
A4W from Heathrow 1087 63 6.3% High
A4E towards Heathrow 1092 63 7.4% High
B470W towards Datchet 539 62 2.4% Moderate
B470E from Datchet 467 62 1.7% Moderate
4b
M25C north of junction 1959 88 8.7% High
M25A north of junction 2171 78 8.3% High
M25C south of junction 1413 98 7.7% Moderate
M25A south of junction 1523 94 7.7% Moderate
4
M4 Spur towards Heathrow 774 78 4.3% Moderate
M4 Spur from Heathrow 652 79 3.6% Moderate
A408N towards Uxbridge 465 19 3.9% High
A408S from Uxbridge 653 42 7.3% High
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-14
M4 junction
Junction approach link
2013 Base
Average peak hourly flow
per lane (flow units/hr)
Average journey speed (km/hr)
Average HGVs (%)
Driver stress level
3
A312N towards Southall 1022 46 5.7% Moderate
A312S from Southall 1070 45 6.9% Moderate
A312N from Heathrow 1048 45 3.5% Moderate
A312S towards Heathrow 989 33 5.0% Moderate
Table 13.9 Existing estimated driver stress for drivers on non-motorway local, connected or affected roads – A4 links 2013 (base year)
M4 section
Parallel A4 link
2013 Base
Average peak hourly flow per
lane
(flow units/hr)
Average journey speed
(Km/hr)
Average HGVs
(%)
Driver stress level
12-11 A4W (M4J12 to Reading) 520 60 4.6% Moderate
A4E (Reading to M4J12) 655 59 5.7% Moderate
11-10
A4W (Reading to A3290 Woodley)
907 45 2.9% Moderate
A4E (A3290 Woodley to Reading)
1147 37 3.9% High
10-8/9
A4W (A3290 Woodley to Maidenhead)
970 74 1.4% High
A4E (Maidenhead to A3290 Woodley)
1245 56 0.9% High
8/9-7
A4W (Maidenhead to Cippenham)
580 49 3.6% Moderate
A4E (Cippenham to Maidenhead)
574 33 1.5% Moderate
7-6 A4W (Cippenham to Slough) 282 36 2.7% Moderate
A4E (Slough to Cippenham) 363 57 3.3% Moderate
6-5 A4W (Slough to M4J5) 825 34 3.4% High
A4E (M4J5 to Slough) 699 38 5.6% High
5-4b A4W (M4J5 to A3044 Longford) 811 73 4.6% High
A4E (A3044 Longford to M4J5) 775 78 6.8% Moderate
4b-4
A4W (A3044 Longford to Heathrow)
322 37 6.4% Moderate
A4E (Heathrow to A3044 Longford)
469 58 5.9% Moderate
4-3 A4W (Heathrow to Cranford) 991 44 14.4% High
A4E (Cranford to Heathrow) 950 44 15.4% High
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-15
Table 13.10 Existing estimated driver stress for drivers on non-motorway local, connected or affected roads – M4 crossing roads 2013 (base year)
M4 section
M4 crossing link
2013 Base
Average peak hourly flow per
lane (flow units/hr)
Average journey speed (km/hr)
Average HGVs (%)
Driver stress level
12-11 Burghfield Ln N from Burghfield 586 82 3.5% Low
Burghfield Ln S towards Burghfield
613 78 1.4% Moderate
11-10
A327N south of B3270 from Shinfield
1134 62 1.0% High
A327S south of B3270 towards Shinfield
1127 62 1.0% High
Mill Ln N towards Earley 323 55 2.3% Moderate
Mill Ln S from Earley 515 58 1.1% Moderate
B3030N towards Winnersh 392 43 0.9% Moderate
B3030S from Winnersh 308 34 0.6% Moderate
A329N towards Reading 714 57 1.5% Moderate
A329S from Reading 841 53 1.3% High
10-8/9
A321N from Wokingham 492 84 1.4% Low
A321S towards Wokingham 476 82 1.3% Low
The Straightmile N from Wokingham
376 69 1.3% Moderate
The Straightmile S towards Wokingham
346 71 1.1% Low
B3018N from Binfield 119 72 2.3% Low
B3018S towards Binfield 210 74 0.6% Low
B3024N from Windsor 352 43 1.6% Moderate
B3024N towards Windsor 395 43 5.0% Moderate
8/9-7
A330N towards Maidenhead 746 35 1.5% High
A308S from Maidenhead 844 33 3.6% High
A308N towards Maidenhead 531 34 2.7% Moderate
A308S from Maidenhead 884 20 4.7% High
Marsh Ln N towards Taplow 10 47 0.0% High
Marsh Ln S from Taplow 119 60 1.8% Moderate
B3026N towards Slough 235 43 3.4% Moderate
B3026S from Slough 164 44 2.8% Moderate
6-5
A332N crossing M4 towards Slough
503 48 2.7% Moderate
A332S crossing M4 from Slough 496 48 3.3% Moderate
B376N crossing M4 towards Slough
441 73 2.1% Low
B376S crossing M4 from Slough 554 73 2.6% Low
Riding Court Rd N from Datchet 123 75 0.9% Low
Riding Court Rd S towards Datchet
496 48 3.3% Moderate
5-4b Sutton Ln N towards Langley 568 51 3.7% Moderate
Sutton Ln S from Langley 592 51 4.2% Moderate
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-16
M4 section
M4 crossing link
2013 Base
Average peak hourly flow per
lane (flow units/hr)
Average journey speed (km/hr)
Average HGVs (%)
Driver stress level
4b-4
Harmondsworth Rd N from Heathrow
388 38 11.7% Moderate
Harmondsworth Rd S towards Heathrow
478 30 13.1% Moderate
A408W towards Heathrow 828 44 5.1% High
A408E from Heathrow 950 82 8.0% High
4-3 A437N from Heathrow 560 40 7.8% Moderate
A437S towards Heathrow 780 35 5.8% High
13.3.5 As the connected or crossing road network is comprised of numerous
different roads types, with varying travel patterns and characteristics, there
is no common pattern of driver stress in the base year.
Non-motorised users
13.3.6 There is a network of PRoWs in the study area, several of which pass
close to and/or cross the M4 (see Drawing 8.2).
13.3.7 There are approximately 113 structures within the scope of the Scheme.
These include all overbridges, underbridges, pedestrian only underpasses,
subways and culverts which carry vehicular and/or NMUs across the M4.
However, not all of these structures will be altered or otherwise affected,
such that their use by NMUs requires assessment. The main effects for
NMUs concern the closure of four bridges for online replacement. These
are at Marsh Lane, Oldway Lane, Recreation Ground and Old Slade Lane.
13.4 Value (sensitivity) of resource
Vehicle travellers
13.4.1 For driver stress, relative levels of sensitivity have not been assigned to
the receptors (vehicle travellers), as DMRB does not provide, or require
the application of, any significance criteria (as noted within paragraph
13.2.24). However, a selection of qualitative assessment criteria is
available in TAG (Ref 13-7) (Unit A4.1, chapter 6) within the section
covering journey quality impacts. For driver stress, the assessment
requires a consideration of the three factors of frustration, fear of potential
accidents and route uncertainty, and a determination as to whether, on
balance, the effect is adverse or beneficial. The following guidance is then
provided to provide an assessment of the scale of effect:
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-17
a) the assessment is likely to be slight when the number of travellers
affected is low (for example, less than 500 a day);
b) the assessment is likely to be large where the number of travellers
affected is high (for example, more than 10,000); and
c) the assessment is likely to be moderate in all other cases.
Non-motorised users
13.4.2 The majority of users (the receptor) of PRoWs (the facility) are assumed to
have low sensitivity (i.e. due to their local scale6). The main exceptions
concern the Thames Path, National Cycle Network Route 4 ("NCN4") and
Route 61 (“NCN61”), each of which has national significance and
accordingly is afforded high sensitivity. The environmental value (or
sensitivity) categories are summarised within Appendix 13.1. The
sensitivity of road crossing points (overbridges and underbridges), which
are not definitive PRoWs, is considered to be low in respect of change
(again, given their local scale and also the fact that the Scheme is not
changing significantly from Do Minimum to Do Something, i.e. the M4
already exists and crossings will be maintained). It is acknowledged there
will be some temporary severance during construction of the Scheme
associated with bridge construction at Marsh Lane, Oldway Lane,
Recreation Ground and Old Slade Lane. However, this severance will be
of a short-term duration, between 9 and 12 months, and there will be no
permanent severance as a result of the Scheme.
13.5 Regulatory/policy framework
13.5.1 A summary of the principal legislation and policy that has been considered
as part of this assessment is provided in Table 13.11.
6 The description and scale of assigning sensitivity within DMRB (Volume 11, Section 2, Part 5, HA
205/08) is relatively vague – so as to be broad enough to be applicable to a range of environmental assessment disciplines (such as air quality and noise). Scores range from very high (high importance, or rarity, or international scale) down to very low (low importance, rarity and local scale).
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-18
Table 13.11 Regulatory and policy framework for all travellers
Policy/Legislation Summary of requirements Scheme response
Countryside and Rights of Way Act 2000 (as
amended) (Ref 13-8)
The Act improves the rights of way legislation by encouraging the creation of new routes and clarifying uncertainties about existing rights.
All PRoWs affected by the Scheme have been assessed.
National Planning Policy Framework 2012
(Ref 13-9)
Planning policies aim to protect and enhance PRoWs and access.
Local authorities should seek opportunities to provide better facilities for users, for example by adding links to existing rights of way networks including National Trails.
All PRoWs affected by the Scheme have been assessed.
National Planning Policy Guidance:
Environmental Impact Assessment (Ref 13-10)
As above. All PRoWs affected by the Scheme have been assessed.
National Networks National Policy
Statement December 2014
(Ref 13-11)
Requirement for Environmental Impact Assessment to assess effects on human beings (including effects on health).
Driver Stress assessment undertaken.
National Networks National Policy
Statement December 2014
(Ref 13-11)
Requirement for applicants to consider effects on the landscape during construction and operation, including effects on local amenity.
Effects on amenity of PRoWs assessed.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-19
Policy/Legislation Summary of requirements Scheme response
Requirement to consider reasonable opportunities to support other transport modes, including reasonable endeavours to address any existing severance issues that act as a barrier to NMUs.
Consideration of needs of pedestrians, cyclists and equestrians during the construction and operation phases.
Government expectation for use of reasonable endeavours to address the needs of cyclists and pedestrians in the design of new schemes.
Consideration of needs of pedestrians, cyclists and equestrians during the construction and operation phases.
13.6 Design, mitigation and enhancement measures, including monitoring requirements
Construction
13.6.1 Proposed mitigation measures during the construction phase will be
managed and monitored as part of the CEMP, which is to be secured by a
requirement attached to the DCO.
13.6.2 As set out in chapter 3 ‘Design Iterations and Alternatives Considered’, the
most appropriate construction methodology for the required improvements
to structures, such as overbridges and underbridges, has been selected
based on the particular circumstances applying in relation to each
structure, such as the availability of diversion routes, and the existence of
sensitive receptors in the vicinity of the structure. The alternatives
considered and the method of construction selected are set out in the
EDR.
13.6.3 Traffic management on the M4 will be in place during the phased
construction period with clear and appropriate signage provided for
alternative routeing. Three narrower lanes will be maintained in each
direction during peak times, with a reduced speed limit of 50 mph in place.
A 24-hour recovery service will be provided over the complete length of
the section of M4 under traffic management. Further details are set out in
the Outline Construction Traffic Management Plan ("CTMP"), which is
appended to the Outline CEMP (Appendix 4.2).
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-20
13.6.4 Temporary road/PRoW closures will be required at overbridges, which are
to be increased in span to accommodate the Scheme. Careful phasing
and on-site management will be controlled through the CEMP to ensure
that disruption and the duration of PRoW closure are kept to a minimum.
13.6.5 During the construction period multiple bridges may be shut at the same
time where the closure of one bridge has no effect on another. Bridge
works at each location will take between 12 and 24 months, but this would
be concurrent with other bridge locations. More detailed information on the
works to be carried out to the structures along the Scheme and the
expected construction period for those works is provided in chapter 4
‘Scheme Description’ and summarised in Tables 13.18 and 13.19.
13.6.6 Where one bridge will be required to act as a diversion route during the
closure of another, these will be replaced sequentially. Overnight closure
of the whole M4 carriageway, eastbound and westbound, will be
necessary at certain times to accommodate demolition and construction
works on the overbridges. All side road crossings of the M4 will be
reinstated such that the long term effects on NMUs will be neutral. The
operational effects of the Scheme are beneficial and mitigation for effects
on travellers during the operational phase of the Scheme is not required.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-21
13.7 Assessment of residual effects
Construction
Vehicle travellers
Driver stress
13.7.1 An indicative assessment of construction effects has been undertaken.
Tables 13.12 and 13.13 show the 2018 construction year stress levels by
link for the eastbound and westbound journeys for the Do Minimum and
Do Something scenarios (i.e. without and with the Scheme). The net
effects of the change are presented in Table 13.14.
Table 13.12 Predicted driver stress experienced by eastbound M4 drivers for the construction assessment year –Do Minimum 2018
M4 junction
Link
2018 Do Minimum
Average peak hourly flow per
lane (flow units/hr)
Average journey speed
(km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 2085 86 6.6% High
11-10 Mainline 2164 84 6.4% High
10-8/9 Mainline 1956 89 5.8% High
8/9-7 Mainline 2032 87 5.6% High
7-6 Mainline 1944 87 6.4% High
6-5 Mainline 2044 87 6.1% High
5-4b Mainline 1620 93 6.2% High
4b-4 Mainline 1723 80 4.3% High
4-3 Mainline 1949 65 5.4% High
Table 13.13 Predicted driver stress experienced by eastbound M4 drivers for the construction assessment year –Do Something 2018
M4 junctions
Link
2018 Do Something
Average peak hourly flow per
lane (flow units/hr)
Average journey speed
(km/hr)
Average HGVs (%)
Driver stress level
12-11 Mainline 1599 97 6.4% Moderate
11-10 Mainline 1726 94 6.0% High
10-8/9 Mainline 1461 100 5.7% Moderate
8/9-7 Mainline 1804 53 5.9% High
7-6 Mainline 1607 58 5.4% High
6-5 Mainline 1680 56 5.0% High
5-4b Mainline 1356 63 4.9% Moderate
4b-4 Mainline 1650 83 4.4% High
4-3 Mainline 1913 67 5.4% High
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-22
Table 13.14 Net effect of driver stress for eastbound M4 traffic associated with construction impact 2018
M4 junctions
Link
Driver stress level
2018 Do Minimum
2018 Do Something
2018 Do Something vs Do
Minimum
12-11 Mainline High Moderate +
11-10 Mainline High High 0
10-8/9 Mainline High Moderate +
8/9-7 Mainline High High 0
7-6 Mainline High High 0
6-5 Mainline High High 0
5-4b Mainline High Moderate +
4b-4 Mainline High High 0
4-3 Mainline High High 0
Net Effect +3
13.7.2 The tables indicate the net effect on driver stress during construction is
predicted to be beneficial, which is counter intuitive and not likely to record
a correct assessment. The result is the outcome of the application of
DMRB, which has not been designed for assessing construction effects.
Nevertheless, a beneficial result will be obtained as traffic flows drop (as
noted in paragraph 13.2.14), which is associated with the reduction of
motorway capacity resulting from a 50 mph speed restriction. Using
DMRB, this yields a positive result. However, in practice, the principle set
out in DMRB, that drivers become more frustrated by not being able to
travel at the normal (as opposed to temporary) motorway speed limit,
would suggest that drivers would become more frustrated by roadworks
and traffic management. As set out at paragraph 13.2.10 (b), fear of
potential accidents associated with road works will be a factor adversely
affecting driver stress. The limitation of the methodology being applied to
construction effects is therefore noted and an adverse effect is predicted
using professional judgement.
13.7.3 A similar analysis is presented for the westbound travelling traffic in Tables
13.15, 13.16 and 13.17.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-23
Table 13.15 Predicted driver stress experienced by westbound M4 drivers for the construction assessment year –Do Minimum 2018
M4 junctions
Link
2018 Do Minimum
Average peak hourly flow per
lane (flow units/hr)
Average journey speed (km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 1825 92 6.4% High
11-10 Mainline 1926 90 5.9% High
10-8/9 Mainline 1865 91 5.5% High
8/9-7 Mainline 1937 89 5.6% High
7-6 Mainline 1911 88 6.0% High
6-5 Mainline 2019 86 5.9% High
5-4b Mainline 1658 91 5.7% High
4b-4 Mainline 1664 111 4.4% High
4-3 Mainline 1953 85 4.3% High
Table 13.16 Predicted driver stress experienced by westbound M4 drivers for the construction assessment year – Do Something 2018
M4 junctions
Link
2018 Do Something
Average peak hourly flow per
lane (flow units/hr)
Average journey speed (km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 1373 102 6.3% Moderate
11-10 Mainline 1484 99 5.7% Moderate
10-8/9 Mainline 1375 101 5.3% Moderate
8/9-7 Mainline 1711 55 5.3% High
7-6 Mainline 1618 58 5.6% High
6-5 Mainline 1694 56 4.9% High
5-4b Mainline 1408 61 5.0% Moderate
4b-4 Mainline 1613 111 4.1% High
4-3 Mainline 1921 86 4.0% High
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-24
Table 13.17 Net effect of driver stress for westbound M4 traffic associated with construction impact 2018
M4 Sections
Link
Driver Stress Level
2018 Do Minimum
2018 Do Something
2018 Do Something vs Do
Minimum
12-11 Mainline High Moderate +
11-10 Mainline High Moderate +
10-8/9 Mainline High Moderate +
8/9-7 Mainline High High 0
7-6 Mainline High High 0
6-5 Mainline High High 0
5-4b Mainline High Moderate +
4b-4 Mainline High High 0
4-3 Mainline High High 0
Net Effect +4
13.7.4 As with the eastbound analysis, a beneficial effect is reported by
application of DMRB, which is counter intuitive. Again, this is because
DMRB has not been designed to assess construction effects and an
adverse effect is predicted, based on professional judgment for the
reasons given above.
13.7.5 In conclusion and notwithstanding the results of the construction impact
assessment presented in this section, there is the potential that the stress
levels for drivers using this part of the M4 during the construction period
will be temporarily elevated, in comparison to the existing levels. This is
due to traffic management measures including the use of narrow lanes
and reduced lane speeds, leading to temporary increases in journey times
and congestion. The lower speeds, greater frustration, possible delay and
queuing could further exacerbate the levels of stress currently experienced
by vehicle travellers. On the basis that only 3 out of 9 links eastbound and
4 out of 9 links westbound have shown changes in assessed levels of
driver stress and each of these changes is only by a single step in
magnitude, the overall magnitude of change is assessed as minor.
13.7.6 Other non-motorway links which could be affected by the introduction of
the Scheme, such as the network of roads feeding the M4, or any other
roads passing under or over or parallel to the M4 (summarised in Tables
13.4 and 13.5), which could be used as alternative routes during
construction, have been considered within the assessment. However, as
full construction and logistics information related to the Scheme is not yet
available, an indicative construction assessment has been undertaken.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-25
13.7.7 During the construction period, four of the overbridges across the M4 will
be closed while a replacement structure is constructed. Table 13.18
provides a list of these bridges together with the nominal duration of
closure from the time demolition of the existing structure commences until
the replacement bridge is open to traffic. In addition to the impact on local
traffic whilst the diversion is in place, disruption to traffic on the M4 will
occur at intermittent periods during demolition of the existing structure and
placement of the replacement bridge deck.
Table 13.18 Construction bridge closures
Overbridge Location Indicative programme Diversion route
Marsh Lane J8/9 – J7 Nov 2018 to Dec 2019 Bath Road (A4) and Lake End Road
Oldway Lane J7 – J6 Nov 2018 to Aug 2019
Using existing public rights of way and Wood Lane overbridge to cross M4
Recreation Ground J6 – J5 Mar 2018 to Nov 2018 Datchet Road and Upton Court Road
Old Slade Lane J5 – J4b Nov 2017 to Dec 2018 Colnbrook Bypass/Sutton Lane and North Park
13.7.8 The other bridges being replaced will in each case remain open until
completion of the replacement structure, at which time traffic will be
diverted to the new bridge and the old bridge demolished. Disruption to
traffic on the M4 will occur at intermittent periods during placement of the
replacement bridge deck and demolition of the existing structure. Table
13.19 provides a list of these bridges. All timescales are based on the
indicative construction programme and are subject to revision by the
appointed contractor.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-26
Table 13.19 Bridges remaining open until replacement bridge is constructed
Overbridge Location Indicative programme Traffic management
Ascot Road J8/9 – J7 Dec. 2017 to June
2019
Signal controlled, alternating, one-way traffic (“shuttle way working”) for tie-in and overlapping works
Monkey Island Lane J8/9 – J7 Oct. 2017 to Nov. 2018
Shuttle way working using signal control for tie-in and overlapping works
Lake End Road J8/9 – J7 Feb. 2018 to Mar. 2019
Shuttle way working using signal control for tie-in and overlapping works
Huntercombe Spur J7 Sept. 2017 to Oct. 2019 Shuttle way working and phased construction
Wood Lane J7 – J6 Oct. 2017 to Aug. 2019
Shuttle way working using signal control for tie-in and overlapping works
Datchet Road J6 – J5 March 2018 to July
2019
Shuttle way working using signal control for tie-in and overlapping works
Riding Court Road J6 – J5 Nov. 2018 to Nov. 2019
Shuttle way working using signal control for tie-in and overlapping works
13.7.9 The underbridges listed in Table 13.20 are to be lengthened during which
three narrower lanes will be generally maintained in each direction during
peak times, with a reduced speed limit of 50mph in place.
Table 13.20 Underbridges to be lengthened
Structure Duration of works
Thames Bray underbridge 27 months
Windsor Branch Railway underbridge 18 months
Langley Interchange underbridges 10 months
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-27
13.7.10 In addition, the following culverts are to be widened (with minimal
disruption to traffic):
a) Ashley Arch culvert;
b) Sipson Subway; and
c) Two service culverts.
13.7.11 This will result in temporary road closure and diversion of vehicular and
NMU traffic. The construction programme will be developed so that when
overbridge crossings are closed, the diversion lengths and adverse
impacts will be kept to a minimum.
13.7.12 During the construction period, the three underbridges (referred to in Table
13.20) and the subway and culverts will be extended, with possible
temporary closure required for underbridge works.
13.7.13 Users of walking and cycling routes in the vicinity of the Scheme may
experience adverse effects as a result of the construction works. However,
appropriate mitigation measures (e.g. diversion routes, signage and
information to be provided to nearby residents prior to rebuilding) will be
implemented by the Contractor as set out in the Outline CEMP and Outline
CTMP (Appendix 4.2).
13.7.14 The effects on NMUs are discussed in the next section. Where journey
times are quoted, they are on the basis of the following speeds prescribed
in DMRB: 5kph on foot, 10kph for horses and 20kph for cyclists. It should
be noted that pedestrians in vulnerable user groups (i.e. elderly, disabled
and children) have an assumed walking speed of 3kph.
Non-motorised users
Journey times and travel patterns
13.7.15 To provide a basis for the assessment of the effect of the proposed bridge
works on NMUs, and in particular those bridges where online construction
with associated diversions of PRoWs is proposed, reference has been
made to DMRB (Ref 13-2, Chapter 6 – New Severance). In the absence
of appropriate survey data, it is not possible at this stage to directly
quantify the number of people whose journey will be affected in each case.
However, it is proposed to undertake surveys at an appropriate time of
year to confirm the assessment. In the meantime, DMRB does provide
guidance on the application of a three-point scale of slight, moderate or
severe in relation to the expected increase in journey distance that people
are likely to incur, as follows:
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-28
a) slight – journeys will be increased by up to 250m;
b) moderate – journeys will be increased by 250 – 500m; or
c) severe – an increase in length of journeys of over 500m.
13.7.16 Marsh Lane overbridge connects Bath Road to the north with the villages
of Dorney, Eton Wick and Eton to the south of the M4. The route also
provides access to Dorney Lake. Marsh Lane overbridge is proposed to be
constructed online. During construction works on Marsh Lane overbridge,
which are anticipated to take 12 months, a diversion route will be available
via Lake End Road.
13.7.17 Lake End Road provides a suitable diversion route for Marsh Lane, as it
connects Bath Road to the north of the M4 with the villages of Dorney,
Eton Wick and Eton to the south of the motorway. Lake End Road
overbridge itself is proposed to be constructed offline to maintain suitable
access to Dorney Lake and Dorney School.
13.7.18 Lake End Road is just over 1km to the east of Marsh Lane and is reached
by diversion routes of 1.7km (20 minutes on foot, 10 minutes on horseback
and 5 minutes by cycle) on the south side and 3.5km (42 minutes on foot,
21 minutes on horseback and 10 minutes by cycle) on the north side. As
such, users of Marsh Lane overbridge may experience lengthened journey
times during the construction period which, based on the above criteria,
would be rated as severe. In response to concerns raised during the
Public Consultation exercise in November 2014, further consideration has
been given to appropriate alternative mitigation measures to address
these concerns. Two options have been identified which are the provision
of a temporary pedestrian access or the provision of a shuttle-bus service
for pupils residing to the north of the motorway, the latter providing the
most flexible and effective option.
13.7.19 Oldway Lane overbridge is used by pedestrians, cyclists and equestrians
to link residential areas on the outskirts of Slough (notably the Cippenham
area) with recreational activities along the Jubilee River. The Jubilee River
Cycle Path and walking routes pass along the towpath of the river and
provide links with Dorney Lake, NCN4 and the Thames Path. Oldway Lane
overbridge will be constructed online, as such the construction works could
have an adverse effect on recreational users in the short-term, as the
crossing would be temporarily severed during reconstruction of the
pedestrian bridge, which is anticipated to take 10 months. Alternative
access could be provided for the residents of Cippenham to the Jubilee
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-29
River via Wood Lane overbridge. This would require a deviation of 1.1km
(13 minutes on foot, 7 minutes on horseback and 3 minutes by cycle)
between the bridges using existing rights of way or a total round trip of just
over 2km (26 minutes on foot, 13 minutes on horseback and 6 minutes by
cycle). Based on the criteria in paragraph 13.7.15, the severance incurred
during the reconstruction period would be adjudged as severe.
13.7.20 Recreation Ground overbridge provides a pedestrian and cycle link from
Datchet Road to the Upton Park area. It also provides properties in the
Upton Court Road area with the opportunity to link in with the wider Jubilee
River walking and cycling network. As the overbridge will be rebuilt online,
the walking/cycling route north to Upton Park Road may be affected by
construction works, which are anticipated to take 8 months to complete. A
diversion route is proposed via Datchet Road bridge. The Recreation
Ground and Datchet Road bridges are only some 350m apart, but the full
diversion route involves a distance of 1.9km (23 minutes on foot, 12
minutes on horseback and 6 minutes by cycle). Based on the criteria in
paragraph 13.7.15, the severance incurred during the reconstruction
period would be adjudged as severe.
13.7.21 Old Slade Lane overbridge is proposed to be rebuilt online, over the
course of approximately 12 months. The overbridge carries an
accommodation track over the M4 to provide access for farm use, local
pedestrians, dog walkers and cyclists as part of the Colne Valley Trail.
During the course of construction, an alternative access could be provided
from the Colnbrook Bypass to the south. However, this would result in
significantly lengthened journey times. The two bridges are just under 2km
apart and the diversion routes between the two are 3.1km (38 minutes on
foot, 19 minutes on horseback and 10 minutes by cycle) on the north side
and 4km (48 minutes on foot, 24 minutes on horseback and 12 minutes by
cycle) on the south side, giving a total round trip of some 7.1km (86
minutes on foot, 43 minutes on horseback and 22 minutes by cycle).
Based on the criteria in paragraph 13.7.15, the severance incurred during
the period of reconstruction would be adjudged as severe.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-30
13.7.22 Reconstruction of Ascot Road overbridge will have an impact on
movements between communities to the north and south of the M4 and
vice versa. It forms a link in conjunction with the A308(M) to connect
junction 8/9 of the M4 with Holyport and residential areas on to Bracknell.
However, the bridge is proposed to be constructed offline, allowing traffic
and pedestrians to continue to use the existing bridge whilst the new
bridge is constructed, such that no severance issues are anticipated.
13.7.23 Monkey Island Lane overbridge provides access from the village of Bray
to the north of the M4 to residential properties and facilities to the south of
the M4, including the Monkey Island Hotel. Monkey Island Lane is a no-
through-road with a section to the south of the M4 comprising a bridleway
and forms part of the route of NCN4. The new bridge will be built offline to
the western side of the existing bridge to enable the latter to remain in use
until the new bridge is completed. As such, no severance issues are
anticipated.
13.7.24 Alterations are proposed to the Huntercombe Spur overbridge at
junction 7 of the M4. The overbridge comprises two structures, one for
each direction of movement, and forms part of a trumpet-shaped junction
at the end of a 1km long dual two-lane road which links the M4 to the A4
Bath Road between Maidenhead and Slough. Reconstruction will be
offline, with traffic using one new span in two directions to allow sequential
demolition and reconstruction of the adjacent spans. Accordingly,
disruption to users will be minimal.
13.7.25 Wood Lane overbridge provides a link across the M4 for 16 properties on
Wood Lane, together with access to Thames Water’s Slough sewage
treatment plant. The route to the south of Wood Lane connects with a
walking/cycling path along the banks of the Jubilee River. The overbridge
is proposed to be reconstructed offline, to the east of the existing bridge, to
enable the latter to remain open during the construction period, such that
no severance issues are anticipated.
13.7.26 Datchet Road overbridge carries the B376 Datchet Road, an all-purpose
urban single carriageway, linking the towns of Slough to the north and
Datchet to the south. The structure is proposed to be rebuilt offline to the
east of its current location enabling it to remain open during the
construction period. Due to the overbridge being constructed offline, there
will be no community severance issues.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-31
13.7.27 Riding Court Road overbridge provides a link between the town of
Datchet and the area of Langley on the outskirts of Slough. It provides
access in particular for employees from the Datchet area and other
residential areas to the south of the M4 travelling to businesses in either
the Riding Court Farm development or the Computer Associates
Technologies business to the north of the M4. The structure is to be
reconstructed offline and therefore there will be no significant disruption to
these movements.
13.7.28 The Thames Bray underbridge will be widened. This may have
implications for walkers, cyclists and boat users along this stretch of the
River Thames during the widening works. There will be a need for a
number of short-term closures of the waterway to river traffic to allow
bridge beam lifts. There are also three footpaths/cycleways which provide
local links to the Thames Valley section of NCN4 to consider:
a) the footpath/cycleway over the river on the south side of the M4 is
not affected by the widening works and will be kept open with a
consequential neutral effect;
b) the footpath/cycleway over the river on the north side of the M4 will
be closed for the duration of the works. Signed diversions will be
provided via Monkey Island Lane to the west (a distance of 1.1km –
i.e. 13 minutes on foot, 7 minutes on horseback and 4 minutes by
cycle) and Marsh Lane to the east (a distance of 1.7km – i.e. 20
minutes on foot, 10 minutes on horseback and 5 minutes by cycle)
which, being over 500m in length, constitutes a severe effect under
DMRB criteria; and
c) the tow-path under the bridge on the east side of the river will be
isolated from the works and kept open during construction.
However, like the river navigation route, short-term closures will be
required during the bridge beam lift and, as such, there will be
minimal effects on users of both the river and this tow path. The
Windsor Branch Railway underbridge is proposed to be widened
asymmetrically to the south. The structure is located at the end of
the slip roads to junction 6 of the M4 and provides the M4 with a
route over the Slough to Windsor and Eton branch railway line.
Cycle and walking routes pass along either side of the railway line
in this location, under the M4. There is likely to be an adverse
impact on users of these routes at certain times as the underbridge
widening work takes place over the course of 27 months.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-32
Depending on which track is closed and the intended direction of
travel, the diversion routes vary between an additional 300m
(moderate impact - 4 minutes on foot, 2 minutes on horseback or 1
minutes by cycle) and an additional 1km (severe impact – 12
minutes on foot, 6 minutes on horseback or 3 minutes by cycle).
However, at most times, these routes will remain open to users, and
consequently the impact will be in place for a short duration.
13.7.29 In summary, a total of 11 overbridges and two underbridges, together with
a number of culverts and subways are proposed to be reconstructed as
part of the construction of the Scheme. Seven of the structures will be
constructed offline (or without significant disruption to users in the case of
the two underbridges). Four of the overbridges are proposed to be
constructed online and, accordingly, will have effects on local communities
that, in DMRB terms, are adjudged to be severe. However, these effects
are for a limited duration of between 9 and 12 months whilst the bridges
are under construction.
Operation
Vehicle travellers
View from the road
13.7.30 As the M4 already exists and the Scheme introduces minor highway
alignment modifications, together with additional driver information,
reallocation of carriageway space and minor carriageway widening, the
view from the M4 is not considered to change materially, nor will the views
of the M4 from other local roads change materially as set out in chapter 8
Landscape.
13.7.31 However, there will be changes to the frequency and number of signs and
gantries. 133 additional gantries and associated signs are proposed as
part of the Scheme, as described in detail in the EDR. The assessment of
the view from the road within DMRB was developed principally to assess
new roads. Four assessment criteria are set out in DMRB for the
assessment of travellers’ ability to see the surrounding landscape – no
view, restricted view, intermittent view and open view. Of these,
“intermittent view” (a road generally at ground level but with shallow
cuttings or barriers at intervals) is considered to best represent the M4.
The effect of the introduction of the additional infrastructure associated
with the Scheme will be to introduce further intermittent, short timescale,
interruptions to the view.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-33
13.7.32 As there are no specific assessment ‘significance criteria’ or ‘magnitude of
impact’ assessment frameworks associated with ‘view from the road’ set
out in DMRB, a qualitative assessment using professional judgment,
based on the above criteria, is considered appropriate. On this basis, it is
considered that the Scheme will have a minor adverse impact on the
basis that the additional gantries that are necessary for the information
system signs will provide intermittent interruptions to the view, albeit ones
that are consistent with typical motorway infrastructure. By reference to the
guidance within DMRB on determining significance of environmental
effects (Ref 13-4, Chapter 2) the effect is adjudged to have a slight level
of significance as it is considered to be a factor local to the M4.
Driver stress
13.7.33 Operational effects are presented in Tables 13.21, 13.22, 13.23 and 13.24
for eastbound and westbound drivers on the M4 for the Do Minimum and
Do Something 2037 scenarios.
Table 13.21 Predicted driver stress experienced by eastbound M4 drivers for the Do Minimum 2037
M4 junctions
Link
2037 Do Minimum
Average peak hourly flow per
lane (flow units/hr)
Average journey speed
(km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 2293 80 6.5% High
11-10 Mainline 2288 80 6.2% High
10-8/9 Mainline 2157 83 5.5% High
8/9-7 Mainline 2184 83 5.4% High
7-6 Mainline 2061 83 6.0% High
6-5 Mainline 2212 82 5.9% High
5-4b Mainline 1746 90 6.0% High
4b-4 Mainline 1782 78 4.3% High
4-3 Mainline 2023 62 5.3% High
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-34
Table 13.22 Predicted driver stress experienced by westbound M4 drivers for the Do Minimum 2037
M4 junctions
Link
2037 Do Minimum
Average peak hourly flow per
lane (flow units/hr)
Average journey speed (km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 2028 87 5.7% High
11-10 Mainline 2133 84 5.4% High
10-8/9 Mainline 2032 86 5.0% High
8/9-7 Mainline 2071 85 5.2% High
7-6 Mainline 2122 79 5.4% High
6-5 Mainline 2191 79 5.5% High
5-4b Mainline 1777 87 5.4% High
4b-4 Mainline 1715 111 4.3% High
4-3 Mainline 1993 83 4.2% High
Table 13.23 Predicted driver stress experienced by eastbound M4 drivers for the Do Something 2037
M4 junctions
Link
2037 Do Something
Average peak hourly flow per
lane (flow units/hr)
Average journey speed
(km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 1951 89 5.9% High
11-10 Mainline 2131 84 5.5% High
10-8/9 Mainline 1951 89 5.0% High
8/9-7 Mainline 2001 87 5.0% High
7-6 Mainline 1891 89 5.5% High
6-5 Mainline 1963 88 5.5% High
5-4b Mainline 1964 82 5.6% High
4b-4 Mainline 1522 89 4.2% Moderate
4-3 Mainline 1616 78 5.1% High
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-35
Table 13.24 Predicted driver stress experienced by westbound M4 drivers for the Do Something 2037
M4 junctions
Link
2037 Do Something
Average peak hourly flow per lane
(flow units/hr)
Average journey speed (km/hr)
Average HGVs
(%)
Driver stress level
12-11 Mainline 1676 95 5.6% High
11-10 Mainline 1829 92 5.1% High
10-8/9 Mainline 1772 93 4.9% High
8/9-7 Mainline 1854 90 4.9% High
7-6 Mainline 1865 90 5.2% High
6-5 Mainline 1883 90 5.3% High
5-4b Mainline 1944 89 5.3% High
4b-4 Mainline 1199 111 4.3% Low
4-3 Mainline 1573 96 4.3% Moderate
13.7.34 The net effects of these changes are described below.
13.8 Net effects of the Scheme on vehicle travellers in the design year (2037)
13.8.1 As noted in paragraph 13.2.24, given the lack of ‘significance criteria’
contained within DMRB, and the relative, indicative nature of the
assessment methodology, an assessment of the net effect of the
introduction of the Scheme based on professional judgement, by
comparing the 2037 Do Minimum and Do Something scenarios, is
required. This is presented below.
13.8.2 Table 13.25 compares driver stress for the Do Something and Do
Minimum scenarios in the eastbound direction for the Design Year (2037).
Table 13.25 Comparison of driver stress for the Do Minimum and the Do Something for the Design Year (2037) for eastbound M4 drivers
M4 junctions
Link
Driver stress level
2037 Do Minimum
2037 Do Something
2037 Do Something vs
Do Minimum
12-11 Mainline High High 0
11-10 Mainline High High 0
10-8/9 Mainline High High 0
8/9-7 Mainline High High 0
7-6 Mainline High High 0
6-5 Mainline High High 0
5-4b Mainline High High 0
4b-4 Mainline High Moderate +
4-3 Mainline High High 0
Net Effect +1
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-36
13.8.3 There is little change between the Do Minimum and Do Something
scenarios, except for a beneficial effect identified between junction 4 and
4b.
13.8.4 Table 13.26 compares driver stress for the Do Something and Do
Minimum scenarios in the westbound direction for the Design Year (2037).
Table 13.26 Comparison of driver stress for the Do Minimum and the Do Something for the Design Year (2037) for westbound M4 drivers
M4 section
Link
Driver stress level
2037 Do Minimum
2037 Do Something
2037 Do Something vs
Do Minimum
12-11 Mainline High High 0
11-10 Mainline High High 0
10-8/9 Mainline High High 0
8/9-7 Mainline High High 0
7-6 Mainline High High 0
6-5 Mainline High High 0
5-4b Mainline High High 0
4b-4 Mainline High Low +
4-3 Mainline High Moderate +
Net Effect +2
13.8.5 In the westbound direction, there is little change between the Do Minimum
and Do Something scenarios, again with beneficial effects identified
between junctions 4 and 4b (on the opposite carriageway) and between
junctions 3 and 4.
13.8.6 Tables 13.27, 13.28 and 13.29 compare driver stress for the Do
Something and Do Minimum scenarios for the local, connected or affected
road network for the Design Year (2037).
Table 13.27 Comparison of driver stress for the Do Minimum and the Do Something for the Design Year (2037) for the M4 approaches
M4 junction
Link
Driver Stress Level
2037 Do Minimum
2037 Do Something
2037 Do Something
vs Do Minimum
12
A4W towards Theale High High 0
A4E from Theale Low Low 0
A4W towards Calcot Moderate Moderate 0
A4E from Calcot Moderate Moderate 0
11
A33N from Three Mile Cross Moderate Moderate 0
A33S towards Three Mile Cross Moderate Moderate 0
A33N approach from Reading Moderate Moderate 0
A33S towards Reading Moderate Moderate 0
B3270W from Whitley Wood High High 0
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-37
M4 junction
Link
Driver Stress Level
2037 Do Minimum
2037 Do Something
2037 Do Something
vs Do Minimum
B3270E towards Whitley Wood High High 0
10
A329MN towards Winnersh Moderate Moderate 0
A329MS from Winnersh Moderate Moderate 0
A33N from Bracknell High High 0
A33S towards Bracknell High High 0
8/9
A404N towards Bisham Moderate Moderate 0
A404S approach from Bisham High High 0
A308MN towards Maidenhead Low Low 0
A308MS from Maidenhead High High 0
7 M4 Spur towards Slough High High 0
M4 Spur from Slough Low Low 0
6
A355N towards Slough High High 0
A355S approach from Slough Low Moderate -
A355N from Windsor Low Low 0
A355S towards Windsor Low Low 0
5
A4W towards Slough Moderate Moderate 0
A4E from Slough Moderate Moderate 0
A4W from Heathrow High High 0
A4E towards Heathrow High High 0
B470W towards Datchet Moderate Moderate 0
4b
M25C north of junction High High 0
M25A north of junction High High 0
M25C south of junction High High 0
M25A south of junction High High 0
4
M4 Spur towards Heathrow Moderate Moderate 0
M4 Spur from Heathrow Moderate Moderate 0
A408N towards Uxbridge High High 0
A408S from Uxbridge High High 0
3
A312N towards Southall Moderate Moderate 0
A312S from Southall Moderate Moderate 0
A312N from Heathrow Moderate Moderate 0
A312S towards Heathrow Moderate Moderate 0
Net Effect -1
13.8.7 Again, there is little net change, with only one link, the A355S approach
from Slough connected to junction 6, where drivers would experience an
increase in driver stress.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-38
Table 13.28 Comparison of Driver Stress for the Do Minimum and the Do Something for the Design Year (2037) for the A4 Link
M4 junctions
A4 Link
Driver stress level
2037 Do Minimum
2037 Do Something
2037 Do Something vs
Do Minimum
11-12 A4W from Reading Moderate Moderate 0
A4E towards Reading High High 0
10-11 A4W towards Reading Moderate Moderate 0
A4E from Reading High High 0
8/9-10 A4W towards Reading High High 0
A4E from Reading High High 0
7-8/9 A4W towards Maidenhead High High 0
A4E from Maidenhead Moderate Moderate 0
6-7 A4W towards Maidenhead Moderate Moderate 0
A4E from Maidenhead Moderate Moderate 0
5-6 A4W towards Slough High High 0
A4E from Slough High High 0
4b-5 A4W from Heathrow High High 0
A4E towards Heathrow High High 0
3-4 A4W towards Heathrow High High 0
A4E from Heathrow High High 0
Net Effect 0
13.8.8 There is no assessed net change in driver stress levels between the Do
Minimum and Do Something scenarios for the A4 link roads. Accordingly,
the effect of the Scheme on driver stress for users of the A4 link roads is
neutral.
Table 13.29 Comparison of Driver Stress for the Do Minimum and the Do Something for the Design Year (2037) for M4 Crossing Roads
M4 junctions
M4 Crossing Link
Driver stress level
2037 Do Minimum
2037 Do Something
2037 Do Something
vs Do Minimum
10-11
A327N north of B3270 towards Reading High High 0
A327S north of B3270 from Reading High High 0
A327N south of B3270 from Shinfield High High 0
A327S south of B3270 towards Shinfield
High High 0
A329N crossing M4 towards Reading High High 0
A329S crossing M4 from Reading High High 0
A327N north of B3270 towards Reading High High 0
8/9/10 A321N crossing M4 from Wokingham Moderate Moderate 0
A321S crossing M4 towards Wokingham
Low Moderate -
7-8/9
A330N crossing M4 towards Maidenhead
High High 0
A330S crossing M4 from Maidenhead High High 0
A330N crossing M4 towards Maidenhead
Moderate Moderate 0
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-39
M4 junctions
M4 Crossing Link
Driver stress level
2037 Do Minimum
2037 Do Something
2037 Do Something
vs Do Minimum
A330S crossing M4 from Maidenhead High High 0
5-6
A332N crossing M4 towards Slough High High 0
A332S crossing M4 from Slough High High 0
B376N crossing M4 towards Slough Low Low 0
B376S crossing M4 from Slough Low Low 0
4-4B A408W towards Heathrow High High 0
A408E from Heathrow High High 0
Net Effect -1
13.8.9 Again, there is little net change on driver stress for travellers crossing the
M4, with only one link, the A321S crossing the M4 towards Wokingham
connected to junction 6, where drivers would experience an increase in
driver stress. Overall this is assessed as a negligible effect and with no
change on the majority of roads, the overall significance is assessed as
neutral.
13.8.10 It should be noted that the assessment reported above uses the rigid
assessment framework put forward in DMRB for the topic of driver stress.
As such, the two improvements in driver stress and the deterioration in
driver stress on two off-site links is not considered to be a definitive
assessment and so it is appropriate to apply professional judgement in this
topic, as described above. This assessment is set out below.
Augmented assessment of driver stress/journey quality
13.8.11 As noted within paragraph 13.2.26, other factors not included within the
pure driver stress speed/flow assessment framework should be
considered.
13.8.12 Journey time reliability will improve as a result of the introduction of the
Scheme. Previously completed smart motorway schemes have
demonstrated improvements in journey time reliability. For example, as
part of a comprehensive study into the post-opening effects of the pilot
smart motorway scheme on the M42, a 22% reduction in journey time
variability was reported (Ref 13-12). As the Scheme will introduce similar
technology to that implemented as part of the M42 scheme, that scheme is
considered an appropriate comparator to the present Scheme and similar
beneficial improvements to journey time variability are expected as a result
of this Scheme to those experienced on the M42.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-40
13.8.13 Road layout and junction frequency are not considered to change
materially as a result of the introduction of the Scheme. As such, the Do
Minimum to Do Something effect of the Scheme is considered to be
neutral. In addition to the benefits associated with the introduction of a
smart motorway, following consultation it has been decided to resurface all
lanes with a Thin Surface Course System, otherwise known as “low noise”
surfacing, along the complete Scheme extent. With this mitigation in place,
in addition to the predicted negligible changes or decreases in noise levels
within the Scheme corridor with the Scheme in operation, the surfacing will
reduce tyre noise7 and consequently in-vehicle noise levels, which will be
beneficial to driver stress.
13.8.14 An important objective of the Scheme is to continue to deliver a high level
of safety performance of the network using smart motorway techniques.
By way of reference, a study of the safety benefits of the M42 pilot smart
motorway reported a 55.7% improvement in (personal injury) accidents as
a result of that scheme (Ref 13-13). Again, as a smart motorway scheme
which implemented similar technology to that proposed as part of this
Scheme, the M42 is considered to be an appropriate comparator for the
Scheme.
13.8.15 Driver information will improve considerably as a result of the introduction
of the Scheme - additional Variable Message Signs ("VMS") being a key
feature of smart motorways. The reduction of general congestion (Ref 13-
14) and the likelihood of ‘traffic flow breakdown’ are other key outcomes
that have been identified from studies following the introduction of a smart
motorway (Ref 13-15).
13.8.16 Each of these factors are considered by DMRB as being able to reduce
driver stress. Whilst these factors fall outside the speed flow assessment
framework contained in DMRB, based on professional judgment and taken
together, the factors referred to above are considered to provide a
beneficial impact on driver stress.
13.9 Cumulative effects
13.9.1 The Design Year (2037) traffic data used to calculate driver stress
included committed developments which could affect the Scheme, as
listed in Appendix 16.2. Therefore, cumulative effects have been taken into
account within this assessment.
7 Further details are provided in chapter 12 ‘Noise and Vibration’.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-41
13.10 Limitations encountered in compiling the ES
13.10.1 The duration of bridge closure and length of route diversions noted above
are subject to revision following the appointment of the contractor.
However, the assessment presented in this report has been based on the
principles for the approach to construction and sequence of activities that
are described in the EDR. Where assumptions have been made in respect
of the extent of diversion involved, distances and times have been based
on a journey from one side of each structure to a point on the immediate
opposite side of the structure to reflect the maximum potential diversion
and consequently a worst case approach has been adopted in the
assessment.
13.11 Summary
13.11.1 The residual effects that could arise from construction and operation of the
Scheme are set out in Table 13.30.
Table 13.30 All travellers impact summary
Impact
description Receptor(s)
affected
Significance of residual
effect
Temporary impacts
Temporary closure of
overbridges and underbridges
during construction
Speed and flow reductions
associated with 50 mph speed
limit
Local road users
Pedestrians
Cyclists
Equestrians
M4 road users
Slight Adverse
Beneficial8
8 By using speed flow tables within DMRB. This is counter intuitive with driver stress likely to increase
associated with a reduction in speed limit during construction.
HIGHWAYS AGENCY – M4 JUNCTIONS 3 TO 12 SMART MOTORWAY
ENVIRONMENTAL STATEMENT CHAPTER 13 EFFECTS ON ALL TRAVELLERS
MARCH 2015
PAGE 13-42
Impact
description Receptor(s)
affected
Significance of residual
effect
Permanent impacts
With the Scheme in place driver stress will be lower due to
improved driver information,
smoother traffic flow and reduced
congestion
M4 road users
Beneficial