13 - 1 Copyright © 2002 Harcourt, Inc. All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

  • View
    218

  • Download
    3

Embed Size (px)

Citation preview

Page 1: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 1

Copyright © 2002 Harcourt, Inc. All rights reserved.

Should we build thisplant?

CHAPTER 13The Basics of Capital Budgeting:

Evaluating Cash Flows

Page 2: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 2

Copyright © 2002 Harcourt, Inc. All rights reserved.

What is capital budgeting?

Analysis of potential additions to fixed assets.

Long-term decisions; involve large expenditures.

Very important to firm’s future.

Page 3: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 3

Copyright © 2002 Harcourt, Inc. All rights reserved.

Steps

1. Estimate CFs (inflows & outflows).

2. Assess riskiness of CFs.

3. Determine k = WACC for project.

4. Find NPV and/or IRR.

5. Accept if NPV > 0 and/or IRR > WACC.

Page 4: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 4

Copyright © 2002 Harcourt, Inc. All rights reserved.

What is the difference between independent and mutually exclusive

projects?

Projects are:

independent, if the cash flows of one are unaffected by the acceptance of the other.

mutually exclusive, if the cash flows of one can be adversely impacted by the acceptance of the other.

Page 5: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 5

Copyright © 2002 Harcourt, Inc. All rights reserved.

An Example of Mutually Exclusive Projects

BRIDGE vs. BOAT to get products across a river.

Page 6: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 6

Copyright © 2002 Harcourt, Inc. All rights reserved.

Normal Cash Flow Project:

Cost (negative CF) followed by aseries of positive cash inflows. One change of signs.

Nonnormal Cash Flow Project:

Two or more changes of signs.Most common: Cost (negativeCF), then string of positive CFs,then cost to close project.Nuclear power plant, strip mine.

Page 7: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 7

Copyright © 2002 Harcourt, Inc. All rights reserved.

Inflow (+) or Outflow (-) in Year

0 1 2 3 4 5 N NN

- + + + + + N

- + + + + - NN

- - - + + + N

+ + + - - - N

- + + - + - NN

Page 8: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 8

Copyright © 2002 Harcourt, Inc. All rights reserved.

What is the payback period?

The number of years required to recover a project’s cost,

or how long does it take to get the business’s money back?

Page 9: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 9

Copyright © 2002 Harcourt, Inc. All rights reserved.

Payback for Project L(Long: Most CFs in out years)

10 8060

0 1 2 3

-100

=

CFt

Cumulative -100 -90 -30 50

PaybackL 2 + 30/80 = 2.375 years

0100

2.4

Page 10: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 10

Copyright © 2002 Harcourt, Inc. All rights reserved.

Project S (Short: CFs come quickly)

70 2050

0 1 2 3

-100CFt

Cumulative -100 -30 20 40

PaybackS 1 + 30/50 = 1.6 years

100

0

1.6

=

Page 11: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 11

Copyright © 2002 Harcourt, Inc. All rights reserved.

Strengths of Payback:

1. Provides an indication of a project’s risk and liquidity.

2. Easy to calculate and understand.

Weaknesses of Payback:

1. Ignores the TVM.

2. Ignores CFs occurring after the payback period.

Page 12: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 12

Copyright © 2002 Harcourt, Inc. All rights reserved.

10 8060

0 1 2 3

CFt

Cumulative -100 -90.91 -41.32 18.79

Discountedpayback 2 + 41.32/60.11 = 2.7 yrs

Discounted Payback: Uses discountedrather than raw CFs.

PVCFt -100

-100

10%

9.09 49.59 60.11

=

Recover invest. + cap. costs in 2.7 yrs.

Page 13: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 13

Copyright © 2002 Harcourt, Inc. All rights reserved.

NPV

CF

kt

nt

t 0 1

.

NPV: Sum of the PVs of inflows and outflows.

Cost often is CF0 and is negative.

.CF

k1

CFNPV 0t

tn

1t

Page 14: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 14

Copyright © 2002 Harcourt, Inc. All rights reserved.

What’s Project L’s NPV?

10 8060

0 1 2 310%

Project L:

-100.00

9.09

49.59

60.1118.79 = NPVL NPVS = $19.98.

Page 15: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 15

Copyright © 2002 Harcourt, Inc. All rights reserved.

Calculator Solution

Enter in CFLO for L:

-100

10

60

80

10

CF0

CF1

NPV

CF2

CF3

I = 18.78 = NPVL

Page 16: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 16

Copyright © 2002 Harcourt, Inc. All rights reserved.

Rationale for the NPV Method

NPV = PV inflows - Cost= Net gain in wealth.

Accept project if NPV > 0.

Choose between mutually exclusive projects on basis ofhigher NPV. Adds most value.

Page 17: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 17

Copyright © 2002 Harcourt, Inc. All rights reserved.

Using NPV method, which project(s) should be accepted?

If Projects S and L are mutually exclusive, accept S because NPVs > NPVL .

If S & L are independent, accept both; NPV > 0.

Page 18: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 18

Copyright © 2002 Harcourt, Inc. All rights reserved.

Internal Rate of Return: IRR

0 1 2 3

CF0 CF1 CF2 CF3

Cost Inflows

IRR is the discount rate that forcesPV inflows = cost. This is the sameas forcing NPV = 0.

Page 19: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 19

Copyright © 2002 Harcourt, Inc. All rights reserved.

t

nt

t

CF

kNPV

0 1.

t

nt

t

CF

IRR

0 10.

NPV: Enter k, solve for NPV.

IRR: Enter NPV = 0, solve for IRR.

Page 20: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 20

Copyright © 2002 Harcourt, Inc. All rights reserved.

What’s Project L’s IRR?

10 8060

0 1 2 3IRR = ?

-100.00

PV3

PV2

PV1

0 = NPV

Enter CFs in CFLO, then press IRR:IRRL = 18.13%. IRRS = 23.56%.

Page 21: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 21

Copyright © 2002 Harcourt, Inc. All rights reserved.

40 40 40

0 1 2 3IRR = ?

Find IRR if CFs are constant:

-100

Or, with CFLO, enter CFs and press IRR = 9.70%.

3 -100 40 0

9.70%N I/YR PV PMT FV

INPUTS

OUTPUT

Page 22: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 22

Copyright © 2002 Harcourt, Inc. All rights reserved.

90 1,09090

0 1 2 10IRR = ?

Q. How is a project’s IRRrelated to a bond’s YTM?

A. They are the same thing.A bond’s YTM is the IRRif you invest in the bond.

-1,134.2

IRR = 7.08% (use TVM or CFLO).

...

Page 23: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 23

Copyright © 2002 Harcourt, Inc. All rights reserved.

Rationale for the IRR Method

If IRR > WACC, then the project’s rate of return is greater than its cost-- some return is left over to boost stockholders’ returns.

Example: WACC = 10%, IRR = 15%.Profitable.

Page 24: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 24

Copyright © 2002 Harcourt, Inc. All rights reserved.

IRR Acceptance Criteria

If IRR > k, accept project.

If IRR < k, reject project.

Page 25: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 25

Copyright © 2002 Harcourt, Inc. All rights reserved.

Decisions on Projects S and L per IRR

If S and L are independent, accept both. IRRs > k = 10%.

If S and L are mutually exclusive, accept S because IRRS > IRRL .

Page 26: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 26

Copyright © 2002 Harcourt, Inc. All rights reserved.

Construct NPV Profiles

Enter CFs in CFLO and find NPVL andNPVS at different discount rates:

k

0

5

10

15

20

NPVL

50

33

19

7

NPVS

40

29

20

12

5 (4)

Page 27: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 27

Copyright © 2002 Harcourt, Inc. All rights reserved.

-10

0

10

20

30

40

50

60

0 5 10 15 20 23.6

NPV ($)

Discount Rate (%)

IRRL = 18.1%

IRRS = 23.6%

Crossover Point = 8.7%

k

0

5

10

15

20

NPVL

50

33

19

7

(4)

NPVS

40

29

20

12

5

S

L

Page 28: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 28

Copyright © 2002 Harcourt, Inc. All rights reserved.

NPV and IRR always lead to the same accept/reject decision for independent projects:

k > IRRand NPV < 0.

Reject.

NPV ($)

k (%)IRR

IRR > kand NPV > 0

Accept.

Page 29: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 29

Copyright © 2002 Harcourt, Inc. All rights reserved.

Mutually Exclusive Projects

k 8.7 k

NPV

%

IRRS

IRRL

L

S

k < 8.7: NPVL> NPVS , IRRS > IRRL

CONFLICT k > 8.7: NPVS> NPVL , IRRS > IRRL

NO CONFLICT

Page 30: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 30

Copyright © 2002 Harcourt, Inc. All rights reserved.

To Find the Crossover Rate

1. Find cash flow differences between the projects. See data at beginning of the case.

2. Enter these differences in CFLO register, then press IRR. Crossover rate = 8.68%, rounded to 8.7%.

3. Can subtract S from L or vice versa, but better to have first CF negative.

4. If profiles don’t cross, one project dominates the other.

Page 31: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 31

Copyright © 2002 Harcourt, Inc. All rights reserved.

Two Reasons NPV Profiles Cross

1. Size (scale) differences. Smaller project frees up funds at t = 0 for investment. The higher the opportunity cost, the more valuable these funds, so high k favors small projects.

2. Timing differences. Project with faster payback provides more CF in early years for reinvestment. If k is high, early CF especially good, NPVS > NPVL.

Page 32: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 32

Copyright © 2002 Harcourt, Inc. All rights reserved.

Reinvestment Rate Assumptions

NPV assumes reinvest at k (opportunity cost of capital).

IRR assumes reinvest at IRR.

Reinvest at opportunity cost, k, is more realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects.

Page 33: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 33

Copyright © 2002 Harcourt, Inc. All rights reserved.

Managers like rates--prefer IRR to NPV comparisons. Can we give them a

better IRR?

Yes, MIRR is the discount rate whichcauses the PV of a project’s terminalvalue (TV) to equal the PV of costs.TV is found by compounding inflowsat WACC.

Thus, MIRR assumes cash inflows are reinvested at WACC.

Page 34: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 34

Copyright © 2002 Harcourt, Inc. All rights reserved.

MIRR = 16.5%

10.0 80.060.0

0 1 2 310%

66.0 12.1

158.1

MIRR for Project L (k = 10%)

-100.010%

10%

TV inflows-100.0

PV outflowsMIRRL = 16.5%

$100 = $158.1

(1+MIRRL)3

Page 35: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 35

Copyright © 2002 Harcourt, Inc. All rights reserved.

To find TV with 10B, enter in CFLO:

I = 10

NPV = 118.78 = PV of inflows.

Enter PV = -118.78, N = 3, I = 10, PMT = 0.Press FV = 158.10 = FV of inflows.

Enter FV = 158.10, PV = -100, PMT = 0, N = 3.Press I = 16.50% = MIRR.

CF0 = 0, CF1 = 10, CF2 = 60, CF3 = 80

Page 36: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 36

Copyright © 2002 Harcourt, Inc. All rights reserved.

Why use MIRR versus IRR?

MIRR correctly assumes reinvestment at opportunity cost = WACC. MIRR also avoids the problem of multiple IRRs.

Managers like rate of return comparisons, and MIRR is better for this than IRR.

Page 37: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 37

Copyright © 2002 Harcourt, Inc. All rights reserved.

Pavilion Project: NPV and IRR?

5,000 -5,000

0 1 2k = 10%

-800

Enter CFs in CFLO, enter I = 10.

NPV = -386.78

IRR = ERROR. Why?

Page 38: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 38

Copyright © 2002 Harcourt, Inc. All rights reserved.

We got IRR = ERROR because there are 2 IRRs. Nonnormal CFs--two signchanges. Here’s a picture:

NPV Profile

450

-800

0400100

IRR2 = 400%

IRR1 = 25%

k

NPV

Page 39: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 39

Copyright © 2002 Harcourt, Inc. All rights reserved.

Logic of Multiple IRRs

1. At very low discount rates, the PV of CF2 is large & negative, so NPV < 0.

2. At very high discount rates, the PV of both CF1 and CF2 are low, so CF0 dominates and again NPV < 0.

3. In between, the discount rate hits CF2 harder than CF1, so NPV > 0.

4. Result: 2 IRRs.

Page 40: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 40

Copyright © 2002 Harcourt, Inc. All rights reserved.

Could find IRR with calculator:

1. Enter CFs as before.

2. Enter a “guess” as to IRR by storing the guess. Try 10%:

10 STO

IRR = 25% = lower IRR

Now guess large IRR, say, 200:

200 STO

IRR = 400% = upper IRR

Page 41: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 41

Copyright © 2002 Harcourt, Inc. All rights reserved.

When there are nonnormal CFs and more than one IRR, use MIRR:

0 1 2

-800,000 5,000,000 -5,000,000

PV outflows @ 10% = -4,932,231.40.

TV inflows @ 10% = 5,500,000.00.

MIRR = 5.6%

Page 42: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 42

Copyright © 2002 Harcourt, Inc. All rights reserved.

Accept Project P?

NO. Reject because MIRR = 5.6% < k = 10%.

Also, if MIRR < k, NPV will be negative: NPV = -$386,777.

Page 43: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 43

Copyright © 2002 Harcourt, Inc. All rights reserved.

S and L are mutually exclusive and will be repeated. k = 10%. Which is

better? (000s)

0 1 2 3 4

Project S:(100)

Project L:(100)

60

33.5

60

33.5 33.5 33.5

Page 44: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 44

Copyright © 2002 Harcourt, Inc. All rights reserved.

S LCF0 -100,000 -100,000CF1 60,000 33,500Nj 2 4I 10 10

NPV 4,132 6,190

NPVL > NPVS. But is L better?Can’t say yet. Need to perform common life analysis.

Page 45: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 45

Copyright © 2002 Harcourt, Inc. All rights reserved.

Note that Project S could be repeated after 2 years to generate additional profits.

Can use either replacement chain or equivalent annual annuity analysis to make decision.

Page 46: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 46

Copyright © 2002 Harcourt, Inc. All rights reserved.

Project S with Replication:

NPV = $7,547.

Replacement Chain Approach (000s)

0 1 2 3 4

Project S:(100) (100)

60 60

60(100) (40)

6060

6060

Page 47: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 47

Copyright © 2002 Harcourt, Inc. All rights reserved.

Compare to Project L NPV = $6,190.Compare to Project L NPV = $6,190.

Or, use NPVs:

0 1 2 3 4

4,1323,4157,547

4,13210%

Page 48: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 48

Copyright © 2002 Harcourt, Inc. All rights reserved.

If the cost to repeat S in two years rises to $105,000, which is best? (000s)

NPVS = $3,415 < NPVL = $6,190.Now choose L.NPVS = $3,415 < NPVL = $6,190.Now choose L.

0 1 2 3 4

Project S:(100)

60 60(105) (45)

60 60

Page 49: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 49

Copyright © 2002 Harcourt, Inc. All rights reserved.

Year0123

CF ($5,000) 2,100 2,000 1,750

Salvage Value $5,000 3,100 2,000 0

Consider another project with a 3-year life. If terminated prior to Year 3, the machinery will have positive salvage

value.

Page 50: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 50

Copyright © 2002 Harcourt, Inc. All rights reserved.

1.751. No termination

2. Terminate 2 years

3. Terminate 1 year

(5)

(5)

(5)

2.1

2.1

5.2

2

4

0 1 2 3

CFs Under Each Alternative (000s)

Page 51: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 51

Copyright © 2002 Harcourt, Inc. All rights reserved.

NPV(no) = -$123.

NPV(2) = $215.

NPV(1) = -$273.

Assuming a 10% cost of capital, what is the project’s optimal, or economic life?

Page 52: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 52

Copyright © 2002 Harcourt, Inc. All rights reserved.

The project is acceptable only if operated for 2 years.

A project’s engineering life does not always equal its economic life.

Conclusions

Page 53: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 53

Copyright © 2002 Harcourt, Inc. All rights reserved.

Choosing the Optimal Capital Budget

Finance theory says to accept all positive NPV projects.

Two problems can occur when there is not enough internally generated cash to fund all positive NPV projects:

An increasing marginal cost of capital.

Capital rationing

Page 54: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 54

Copyright © 2002 Harcourt, Inc. All rights reserved.

Increasing Marginal Cost of Capital

Externally raised capital can have large flotation costs, which increase the cost of capital.

Investors often perceive large capital budgets as being risky, which drives up the cost of capital.

(More...)

Page 55: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 55

Copyright © 2002 Harcourt, Inc. All rights reserved.

If external funds will be raised, then the NPV of all projects should be estimated using this higher marginal cost of capital.

Page 56: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 56

Copyright © 2002 Harcourt, Inc. All rights reserved.

Capital Rationing

Capital rationing occurs when a company chooses not to fund all positive NPV projects.

The company typically sets an upper limit on the total amount of capital expenditures that it will make in the upcoming year.

(More...)

Page 57: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 57

Copyright © 2002 Harcourt, Inc. All rights reserved.

Reason: Companies want to avoid the direct costs (i.e., flotation costs) and the indirect costs of issuing new capital.

Solution: Increase the cost of capital by enough to reflect all of these costs, and then accept all projects that still have a positive NPV with the higher cost of capital.

(More...)

Page 58: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 58

Copyright © 2002 Harcourt, Inc. All rights reserved.

Reason: Companies don’t have enough managerial, marketing, or engineering staff to implement all positive NPV projects.

Solution: Use linear programming to maximize NPV subject to not exceeding the constraints on staffing.

(More...)

Page 59: 13 - 1 Copyright © 2002 Harcourt, Inc.All rights reserved. Should we build this plant? CHAPTER 13 The Basics of Capital Budgeting: Evaluating Cash Flows

13 - 59

Copyright © 2002 Harcourt, Inc. All rights reserved.

Reason: Companies believe that the project’s managers forecast unreasonably high cash flow estimates, so companies “filter” out the worst projects by limiting the total amount of projects that can be accepted.

Solution: Implement a post-audit process and tie the managers’ compensation to the subsequent performance of the project.