56
CHAPTER 12 - PG 1 12. TRANSPORTATION 12.1 INTRODUCTION 12.1.1 This chapter of the Environmental Statement (ES) assesses the likely significant environmental effects created by the changing transport conditions introduced by the Proposed Development. It incorporates the findings of the Transport Assessment (TA), which is provided at Appendix 12.1 of this ES. 12.1.2 The Northampton Gateway Strategic Rail Freight Interchange (SRFI), the ‘Proposed Development’ is described in Chapter 2 of this ES and reference should be made to that chapter for the description of the development that has been assessed. 12.1.3 The Proposed Development would increase the number and alter the pattern of traffic movements on the highway network and would also alter the conditions for other highway users. Hence the effects of the changes on non-motorised users (NMUs) (pedestrians, cyclists, equestrians) as well as drivers are assessed. This chapter of the ES does not present the rail freight strategy, which is considered in separate reports 1 . 12.1.4 The assessment process and methodology are described in the TA and its supporting documents, which include the Framework Travel Plan (FTP) for the development. Where relevant, summaries only are included in this ES chapter and, in general, reference should be made to the TA and its supporting documents for detail. 12.1.5 This chapter describes the assessment methodology, the transport planning policy context, the baseline conditions currently existing at the Proposed Development site and its surroundings, the proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual effects after these measures have been employed. 12.1.6 The appended TA examines the generation, distribution and assignment of trips associated with the Proposed Development and the effects of the external trips (beyond the site boundary) on the surrounding transport network. The TA and FTP examine the accessibility of the site by public transport, cycling and walking, and identify the likely modal split of person trips associated with the development. The impact of the development trips on the surrounding transport infrastructure is addressed and it is demonstrated that the identified ‘highway mitigation strategy’, in combination with the FTP, would appropriately address the increased travel demand and that residual impacts of the Proposed Development are reduced to acceptable levels. However, as referred to later in this Chapter, no assumed reduction in car travel is included in the analysis to ensure a robust and worst-case assessment of likely effects. 12.1.7 The Proposed Development would provide public transport, pedestrian and cycle provision for non-car based modes of transport. 1 For the Rail Operation Report see DCO document 6.7 and for the Rail Capacity Report see DCO document 6.8 – rail policy context in general is set out in the Planning Statement (document 6.6).

12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 1

12. TRANSPORTATION

12.1 INTRODUCTION

12.1.1 ThischapteroftheEnvironmentalStatement(ES)assessesthelikelysignificantenvironmentaleffectscreatedbythechangingtransportconditionsintroducedbytheProposedDevelopment.ItincorporatesthefindingsoftheTransportAssessment(TA),whichisprovidedatAppendix12.1ofthis ES.

12.1.2 TheNorthamptonGatewayStrategicRailFreightInterchange(SRFI),the‘ProposedDevelopment’isdescribedinChapter2ofthisESandreferenceshouldbemadetothatchapterforthedescriptionofthedevelopmentthathasbeenassessed.

12.1.3 TheProposedDevelopmentwouldincreasethenumberandalterthepatternoftrafficmovementsonthehighwaynetworkandwouldalsoaltertheconditionsforotherhighwayusers.Hencetheeffectsofthechangesonnon-motorisedusers(NMUs)(pedestrians,cyclists,equestrians)aswellasdriversareassessed.ThischapteroftheESdoesnotpresenttherailfreightstrategy,whichisconsideredinseparatereports1.

12.1.4 TheassessmentprocessandmethodologyaredescribedintheTAanditssupportingdocuments,whichincludetheFrameworkTravelPlan(FTP)forthedevelopment.Whererelevant,summariesonlyareincludedinthisESchapterand,ingeneral,referenceshouldbemadetotheTAanditssupportingdocumentsfordetail.

12.1.5 Thischapterdescribestheassessmentmethodology,thetransportplanningpolicycontext,thebaselineconditionscurrentlyexistingattheProposedDevelopmentsiteanditssurroundings,theproposeddesignmeasuresrequiredtoprevent,reduceoroffsetanysignificantadverseeffects,andthelikelyresidualeffectsafterthesemeasureshavebeenemployed.

12.1.6 TheappendedTAexaminesthegeneration,distributionandassignmentoftripsassociatedwiththeProposedDevelopmentandtheeffectsoftheexternaltrips(beyondthesiteboundary)onthesurroundingtransportnetwork.TheTAandFTPexaminetheaccessibilityofthesitebypublictransport,cyclingandwalking,andidentifythelikelymodalsplitofpersontripsassociatedwiththedevelopment.Theimpactofthedevelopmenttripsonthesurroundingtransportinfrastructureisaddressedanditisdemonstratedthattheidentified‘highwaymitigationstrategy’,incombinationwiththeFTP,wouldappropriatelyaddresstheincreasedtraveldemandandthatresidualimpactsoftheProposedDevelopmentarereducedtoacceptablelevels.However,asreferredtolaterinthisChapter,noassumedreductionincartravelisincludedintheanalysistoensurearobustandworst-caseassessmentoflikelyeffects.

12.1.7 TheProposedDevelopmentwouldprovidepublictransport,pedestrianandcycleprovisionfornon-carbasedmodesoftransport.

1 For the Rail Operation Report see DCO document 6.7 and for the Rail Capacity Report see DCO document 6.8 – rail policy context in general is set out in the Planning Statement (document 6.6).

Page 2: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 2

12.2 ASSESSMENT METHODOLOGY

General approach12.2.1 ThischapteroftheESdescribesthefindingsoftheTAanditssupportingdocuments,including

theFTP,whichhavebeenundertakentosupporttheapplicationforaDevelopmentConsentOrder(DCO)fortheProposedDevelopment.ItexaminestherelationshipbetweentheProposedDevelopmentandthetransportnetwork,theeffectofthedevelopmentonthatnetwork,andtheneedtoprovideimprovementstoinfrastructuretoaccommodatetheproposedusesinasustainablemanner.

12.2.2 TheassessmenthasbeenundertakenusingaDepartmentforTransport(DfT)WebTAGcomplianttransportmodelandapplyingamethodologythataccordswithbestpracticeguidance.ItincludesanassessmentofboththelocalhighwaynetworkandtheStrategicRoadNetwork(SRN)servingtheProposedDevelopment,thelatterinaccordancewithDfT‘Circular02/2013TheStrategicRoadNetworkandtheDeliveryofSustainableDevelopment’.

12.2.3 Inaddition,thisESChapterexaminestheenvironmentalimpactofthechangingtransportconditionsresultingfromtheproposedtransportinfrastructureandhighwaymitigationworks.ThisisbasedonguidancecontainedwithintheDfT‘DesignManualforRoadsandBridges(DMRB),Volume11,EnvironmentalAssessment,Section3,Parts8and9’.

12.2.4 Forthepurposesofassessment,fourcategoriesofimpactscalehavebeenused,comprising;negligible;minor;moderateandmajor.ThedefinitionofthesignificanceoftheimpactisdescribedinTable12.1.

Table 12.1 Definition of significance of impact

Scale of impact Definition

Negligible Aneffectthatisconsiderednottobesignificantortohavenoinfluence.Thisisapplicablewherethereisaneutralimpactwhichisneitherpositivenornegative.

Minor Aneffectthatmaybealocalissue.Moderate Aneffectthatwillbeimportantatlocallevelandpotentiallyupwards.Major Aneffectthatwillbeimportantatborough,county,orregionallevel.

12.2.5 Whereimpactsarerecordedasbeingminor,moderateormajor,andcauseanincreaseinexistingcongestion,journeytimesorexacerbateexistingsafetyproblems,thentheindividualimpactisdescribedasanadverseone.Wheretheyrelieve,thentheimpactistermedbeneficial.Negligibleimpactscannotbeperceivedandhenceareneitheradversenorbeneficial.

12.2.6 Inadditiontothesignificanceoftheimpact,theassessmentalsoconsiderswhethertheenvironmental impacts are permanent or temporary.

12.2.7 ToassesstheenvironmentalimpactoftheProposedDevelopmentanditstraffic,theinitialstagesaretodeterminethebaselineandfutureyeartrafficvolumesandcharacteristics,determinethetimeperiodsforassessment,andtoidentifythegeographicalboundariesofassessment.Oncethisinformationisestablished,thepredictedimpactsareassessed,alongwithmeasurestomitigateanyadverseimpact.

Scoping Criteria12.2.8 NorthamptonshireCountyCouncil(NCC)isthelocalhighwayauthorityresponsibleforthe

transportationissueswithinNorthamptonshire.HighwaysEnglandhasresponsibilityfortheSRNwhich,adjacenttotheProposedDevelopmentsite,comprisestheM1motorway,M1Junctions15and15A,theA45,A43andA5.

Page 3: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 3

12.2.9 Thescaleofdevelopmentrequiresatransportstrategythatseekstomanagetraveldemandfromtheoutset,whilstprovidingappropriateaccesstoservethedevelopmentandaddressingtheimpactofthedevelopmenttripsontheexistinglocalhighwayandSRN.

12.2.10 InaccordancewiththePINSScopingOpinionreport(refTR050006),theassessmentofthetransportimpactofthedevelopmentisbasedonacomprehensivetransportmodellingexercise,forwhichaTransportWorkingGroupwasestablishedtooverseetheprocess.TheTransportWorkingGroupcomprisesrepresentativesfromthetwohighwayauthoritiesdescribedaboveandHighwaysEngland’stermconsultantAecom,alongwithspecialisttransportconsultantsactingforRoxhill(Junction15)Ltd.IthasmetonanapproximatelymonthlybasissinceJuly2016.

12.2.11 BuckinghamshireCountyCouncilandSouthNorthamptonshireCouncilrequestedintheScopingOpinionthattheyjointheTransportWorkingGroup.TheserequestswerefollowedupwitheachCouncil.ThisincludedmeetingwithBuckinghamshireCountyCouncilonthe13th of March2017todiscusstheProposedDevelopment,itslikelyimpactswithinBuckinghamshire,andtheirinvolvementintheTransportWorkingGroup.Followingthatmeeting,havinggainedafullerunderstandingoftheroleoftheTransportWorkingGroup,BuckinghamshireCountyCouncilconfirmedthattheirrepresentationonthegrouponwasnotnecessary.ItwasagreedseparatelywithSouthNorthamptonshireCouncilthatthetheywereappropriatelyrepresentedontheTransportWorkingGroupviatheattendanceoftheNCChighwayofficerrepresentingSouthNorthamptonshireDevelopmentControl.

12.2.12 Toconfirmthattheproposedhighwaymitigationstrategyisappropriateinscaleandfunction,strategicassessmentoftheProposedDevelopmentandhighwaymitigationhasbeenundertakenusingtheNorthamptonshireStrategicTransportModel(NSTM2).Furtherdetailedanalysisofstudyareajunctionshasthenbeenundertakenusingmicro-simulationandindustrystandardassessmenttools,supportedbyaWalking,Cycling&Horse-RidingAssessmentReviewandStage1RoadSafetyAudit.

12.2.13 SeparatecomprehensivestrategieshavebeendevelopedtoaddressaccesstotheSRFIbypublictransport,walkingandcycling.

12.2.14 NCCandHighwaysEnglandagreedtheTAmethodology,scopeandmodellinginputsviaaseriesoftransportrelateddocumentsandTechnicalNotes.TheTAthereforebringstogetherthefindingsofthesevariousstudiesandpresentstheresultsobtained.ThekeytransportrelateddocumentsandTechnicalNotesareappendedtotheTAatAppendices1to34,aslistedatTable12.2below.TheTAincludesafurther28appendices(Appendices35to62),thatprovidesupplementarybaselinedata,assessmentflowsandmodellingdetail.Ingeneral,therefore,thischapterprovidesonlyanoverviewofthefindingsandreferenceshouldbemadetotheTAandappendicesforfurtherdetail.

Page 4: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 4

Table 12.2: Key transport documents and Technical Notes appended to the TA

Document name Ref TA AppendixFrameworkTravelPlan FTP 1PublicTransportStrategy PTS 2PersonalInjuryAccidentAssessmentTechnicalNote TNA 3TN1:TransportModellingMethodology TN1 4TN2: Trip Generation TN2 5TN2Addendum:OpeningYearTripGeneration TN2A 6TN3:HGVTripDistribution TN3 7LightVehicleTripDistribution WSPTN1 8TN4:ScopeofHighwayDesignWork TN4 9TN5:M1Junction15 TN5 10TN6:M1Junction15A TN6 11

TN7:A45QueenEleanorGyratoryandWoottonInterchange TN7 12

TN8:A508Corridor TN8 13TN9:LaybyCapacity TN9 14TN10:ImpactsnorthoftheM1includingtheA45corridor TN10 15TN10Addendum TN10A 16TN11:ImpactsatjunctionsalongtheA5076corridor TN11 17Walking,Cycling&Horse-RidingAssessmentReview:AssessmentReport WCHAR1 18

Walking,Cycling&Horse-RidingReview:ReviewReport WCHAR2 19RoadeBypassOptionsReport RBOR 20M1Junction15:SummaryofHighwayOptionsReport M1J15OR 21NSTM2:M1J15NorthamptonGatewaySRFILocalModelValidationReport LMVR1 22

NSTM2:ReferenceCaseForecastReport TMR1 23NSTM2:DevelopmentCaseForecastReport TMR2 24M1J15&J15AVISSIMModel-LocalModelValidationReport LMVR2 25VISSIMModellingSummary VISSIM1 26VISSIMModellingSummary–Proposedsiteaccess VISSIM2 27GeometricDesignStrategyRecord–M1J15&A45improvement,M1J15AImprovement GDSR1 28

GeometricDesignStrategyRecord–A508RouteUpgrade GDSR2 29Stage1RoadSafetyAudit RSA1 30Stage1RoadSafetyAuditResponseReport RSA1RR 31NSTM2:EnvironmentalStatementDataProcessing WSPTN2 32Constructiontrafficassumptionsandcalculations ADC 33RoadtoRailFreightmodalshiftcalculations ADC 34

Page 5: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 5

12.3 PLANNING POLICY CONTEXT

General12.3.1 Thissectionconsidersrelevantnationalandlocalpoliciestogetherwithguidanceontransportand

landuse.

Committed development and infrastructure schemes12.3.2 Themainsiteisnotsubjecttoanyextantplanningconsentsofsignificanceintermsoftraffic

generation.Onthisbasis,noaccountofanyexistinglandusesatthemainsitehasbeentaken.

12.3.3 Thereareasignificantnumberofdevelopmentschemeswithplanningconsentinthevicinityofthesite,whosetrafficeffectsneedtobetakenintoaccount.Inaddition,committedorplannedhighwayinfrastructure,andothermajordevelopmentsitesthatarecurrentlythesubjectofplanningapplicationsbutarenotyetcommitted,havebeenincludedwhereagreedwiththeTransportWorkingGroup.Theseschemes,togetherwithrelevantandpotentialLocalPlanallocationshavebeenincorporatedintotheNSTM2modelling,asexplainedintheReferenceCaseForecastReport(TAAppendix23).

12.3.4 ThecommittedschemesincludetheHardingstoneSUEandDaventryInternationalRailFreightTerminal(DIRFT3),asrequestedbyNorthamptonBoroughCouncilintheirScopingOpinionresponse.TheinclusionoftheproposeddevelopmentatMereLane(reference15/01531/OUT),thethirdsitenotedbyNorthamptonBoroughCouncil,wasdiscussedwiththeTransportWorkingGroup.ItwasagreedthatthiswouldbeaccountedforviaTEMRPOtrafficgrowth,asitwastooremotefromtheProposedDevelopmentsitetorequiresitespecificmodelling.

Relevant Transport Policy12.3.5 Thekeytransport-relatedpoliciesandguidanceofrelevancetotheProposedDevelopmentare

containedwithinthefollowingdocuments:

• NationalPolicyStatementforNationalNetwork(December2014);

• NationalPlanningPolicyFramework(March2012);

• NationalPlanningPracticeGuidance:TravelPlans,TransportAssessmentsandStatementsinDecisionMaking(2014);

• DfTCircular02/2013‘TheStrategicRoadNetworkandtheDeliveryofSustainableDevelopment’;

• WestNorthamptonshireJointCoreStrategyLocalPlanPart1(December2014);

• SouthNorthamptonshireLocalPlanSavedPolicies(December2014);

¶ NorthamptonshireTransportationPlan(March2012),including:

¶ NorthamptonshireRoadFreightStrategy(December2013);

¶ NorthamptonshireMajorRoadsStrategy(December2013)

• NorthamptonshireBusStrategyrequirements(January2013).

• A45/M1NorthamptonGrowthManagementsScheme(March2012);

• HighwaysEnglandRoadInvestmentStrategy2015to2020(March2015);

• DesignManualforRoadsandBridges(DMRB);and

• NorthamptonshireParkingStandards(September2016).

12.3.6 Thepolicyframeworkofthetransport-relatedpolicieslistedabovewhicharerelevantarereviewedinthefollowingsections.

Page 6: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 6

The National Policy Statement for National Network (NPSNN)12.3.7 ThepurposeoftheNPSNNistosetouttheimportanceofdeliveringNationallySignificant

InfrastructureProjects(NSIPs)onthenationalroadandrailnetworksinEnglandtosupportnationalandlocaleconomicgrowthandregeneration.Hence,theNPSNNprovidesdirectionforNSIPs,includingSRFIs,fromaplanninganddesignperspective,whichtheSecretaryofStatewillusetodecidewhethertoconsentNSIPapplications.

12.3.8 TheoverallstrategicaimsoftheNPSNNandtheNationalPlanningPolicyFramework(NPPF)areconsistentduetobothdocuments’over-archingthemetosupportsustainabledevelopment.However,theNPPFisnotintendedtocontainspecificpoliciesforNSIPs.TheNPSNNassumesthatfunctionandprovidestheTransportPolicywhichwillguideindividualNSIPsbroughtunderit.TheNPSNNprovidesguidanceandimposesrequirementsonmatterssuchasgoodschemedesign,aswellasthetreatmentofenvironmentalimpact.

12.3.9 TheGovernment’svisionandstrategicobjectivesforthenationalnetworksisdescribedonpage9oftheNPSNNasfollows: “The Government will deliver national networks that meet the country’s long-term needs; supporting a prosperous and competitive economy and improving overall quality of life, as part of a wider transport system. This means:

• Networkswiththecapacityandconnectivityandresiliencetosupportnationalandlocaleconomicactivityandfacilitategrowthandcreatejobs

• Networkswhichsupportandimprovejourneyquality,reliabilityandsafety

• Networkswhichsupportthedeliveryofenvironmentalgoalsandthemovetoalowcarboneconomy

• Networkswhichjoinupourcommunitiesandlinkeffectivelytoeachother.”

12.3.10 Aprimaryconcernrelatingtothenationalnetworkisthecontinueddependencyonthestrategicroadnetworkas“…congestion is forecast to grow fastest on the strategic road network”(paragraph2.19).Paragraph2.43oftheNPSNNidentifiestheimportanceofSRFIsto“…enable freight to be transferred between transport modes, thus allowing rail to be used to best effect to undertake the long-haul primary trunk journey, with other modes (usually road) providing the secondary (final delivery) leg of the journey”.Paragraph2.44states“The aim of a SRFI is to optimise the use of rail in the freight journey by maximising rail trunk haul and minimising some elements of the secondary distribution leg by road, through co-location of other distribution and freight activities. SRFIs are a key element in reducing the cost to users of moving freight by rail and are important in facilitating the transfer of freight from road to rail thereby reducing trip mileage of freight movements on both the national and local road networks.”

12.3.11 Tofacilitatethismodaltransfer,theNPSNNstatesthatanetworkofSRFIsisneededacrosstheregions,toserveregional,sub-regionalandcross-regionalmarkets.Inallcasesitisessentialthatthesehavegoodconnectivitywithboththeroadandrailnetworks.

12.3.12 TheGovernmenthasthereforeconcludedthat“…there is a compelling need for an expanded network of SRFIs” (paragraph 2.56).

12.3.13 TheNPSNNprovidesspecificadviceforSRFIdevelopment,statingthataprojectwithsignificanttransportimpactsshouldincludeaTransportAssessment,usingtheWebTAGmethodologystipulatedinDfTguidance.IfadevelopmentissubjecttoEIAandislikelytohavesignificantenvironmentalimpactsarisingfromimpactsontransportnetworks,theapplicant’sEnvironmentalStatementshoulddescribethoseimpacts.

Page 7: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 7

12.3.14 Paragraph5.208states“Where appropriate, the applicant should prepare a travel plan including management measures to mitigate transport impacts. The applicant should also provide details of proposed measures to improve access by public transport and sustainable modes where relevant, to reduce the need for any parking associated with the proposal and to mitigate transport impacts.”

12.3.15 ForschemesimpactingontheStrategicRoadNetwork,paragraph5.209statesthat“…applicants should have regard to DfT Circular 02/2013 ‘The Strategic Road Network and the delivery of sustainable development’ (or prevailing policy).”

12.3.16 RegardingSRFIs,paragraph5.213states:“Projects may give rise to impacts on the surrounding transport infrastructure including connecting transport networks. The Secretary of State should therefore ensure that the applicant has taken reasonable steps to mitigate these impacts. Where the proposed mitigation measures are insufficient to reduce the impact on the transport infrastructure to acceptable levels, the Secretary of State should expect applicants to accept requirements and/or obligations for funding infrastructure and otherwise mitigating adverse impacts on transport networks…”

12.3.17 Paragraph5.215setsoutthat“mitigation measures for schemes should be proportionate and reasonable, focussed on promoting sustainable development”,andatparagraph5.216that“where development would worsen accessibility such impacts should be mitigated so far as reasonably possible” and that “there is a very strong expectation that impacts on accessibility for non-motorised users should be mitigated”.Paragraph5.218setsoutthat“…travel planning should be undertaken for all major developments which generate significant amounts of transport movement”.

12.3.18 HavingregardtotheNPSNN,theproposedSRFIaccessstrategyincludesmeasurestoconnectthemainsitewiththeadjacentcommunityandsustainabletravelnetworkandincludesaseparatepublictransportstrategytoensure,alongwiththemeasuressetoutintheFTP,thattravelbysustainablemodesaremaximisedasfarasispracticable.Highwaymitigationworksareproposedtoreducetheimpactofthedevelopmenttripsonthenearbytransportinfrastructuretoacceptablelevels,withtheproposedM1Junction15andA45improvementsdirectlyrelatedtothesuitabilityofthesitefordevelopmentofanSRFI.

The National Planning Policy Framework (NPPF)12.3.19 Asreferredtoabove,theNPSNN,ratherthantheNPPF,providesthenationalpolicycontextfor

NSIPapplications.However,forcontextwithregardtotransportissuesparagraph32oftheNPPFguidesdecisionmakerstoapplythefollowingkeyprinciples:

• “theopportunityforsustainabletransportmodeshavebeentakenupdependingonthenatureandlocationofthesite,toreducetheneedformajortransportinfrastructure;

• safeandsuitableaccesstothesitecanbeachievedforallpeople;and

• improvementscanbeundertakenwithinthetransportnetworkthatcosteffectivelylimitsthesignificantimpactsofthedevelopment.Developmentsshouldonlybepreventedorrefusedontransportgroundswheretheresidualcumulativeimpactsofdevelopmentaresevere.”

12.3.20 Thereisarequirementtoensurethatdevelopmentgeneratingsignificantdemandfortravelislocatedwhereitcanbeaccessedbysustainabletravelmodesandwhereefficientdeliveryofgoodsandsuppliescanbeaccommodated.

Page 8: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 8

National Planning Practice Guidance (NPPG): Travel Plans, Transport Assessments and Statements in Decision Making

12.3.21 ThisdocumentsetsoutthemethodologyandrequirementsforTravelPlans,TransportAssessmentsandStatementsfordevelopments.IndeterminingwhetheraTransportAssessmentandTravelPlanwillbeneededforaproposeddevelopment,thisdocumentstatesthatlocalplanningauthoritiesshouldtakeintoaccountthefollowingconsiderations:

• theTransportAssessmentandStatementpolicies,andtheTravelPlanpolicies(ifany)oftheLocalPlan;

• thescaleoftheproposeddevelopmentanditspotentialforadditionaltripgeneration;

• existingintensityoftransportuseandtheavailabilityofpublictransport;

• proximitytonearbyenvironmentaldesignationsorsensitiveareas;

• impactonotherpriorities/strategies(suchaspromotingwalkingandcycling);

• thecumulativeimpactsofmultipledevelopmentswithinaparticulararea;

• whetherthereareparticulartypesofimpactsaroundwhichtofocustheTransportAssessmentandTravelPlan(e.g.minimisingtrafficgeneratedatpeaktimes);and

• relevantnationalpolicies,includingthedecisiontoabolishmaximumparkingstandardsforbothresidentialandnon-residentialdevelopment.

DfT Circular 02/201312.3.22 DfTCircular02/2013‘TheStrategicRoadNetworkandtheDeliveryofSustainableDevelopment’

setsoutHighwaysEngland’s(thenHighwaysAgency)policyonhowitwillengagewithlocalcommunitiesandthedevelopmentindustrytodeliversustainabledevelopmentandmaintainingtheprincipalpurposeoftheSRN.

12.3.23 Thepolicyisintendedforallpartiesinvolvedindevelopmentproposalswhichmayresultintrafficorotherimpactsonthestrategicroadnetwork.Theaimofthepolicyistocutunnecessaryredtapeandmaketheplanningprocesssimplerandmorestraightforward.

12.3.24 Paragraph9setsoutthebroadpolicyaimsoftheCircularasitrelatestodevelopmentproposals,statingthat“Development proposals are likely to be acceptable if they can be accommodated within the existing capacity of a section (link or junction)… or they do not increase demand for use of a section that is already operating at over-capacity levels, taking account of any travel plan, traffic management and/or capacity enhancement measures that may be agreed”.

12.3.25 Withreferencetodecisionmakingregardingdevelopments,paragraph9goesontostate“However, development should only be prevented or refused on transport grounds where the residual cumulative impacts of development are severe”.

12.3.26 Circular02/2013placesanemphasisontheroleofsustainabletravelmodesandtravelplanningasameansofmanagingtheimpactofdevelopmentontheroadnetwork,acknowledgingtherolethatarea-widetravelplaninitiativescanplayto‘free-up’additionalcapacity,sothattraveldemandcreatedbyanewdevelopmentcanbeaccommodated.

12.3.27 Inassessingdevelopmentimpact,theCircularstates,inparagraph33,that“only after travel plan and demand management measure have been fully explored and applied will capacity enhancement measures be considered”.

12.3.28 Intermsofmitigationofdevelopmentimpact,paragraph34statesthat“Where insufficient capacity exists to provide for overall forecast demand at the time of opening, the impact of the development will be mitigated to ensure that at that time, the strategic road network is able to accommodate existing and development generated traffic”.

Page 9: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 9

West Northamptonshire Joint Core Strategy (JCS) Local Plan (Part 1)12.3.29 TheCoreStrategysetsoutthelong-termvisionandobjectivesforthewholeoftheareacovered

byDaventryDistrict,NorthamptonBoroughandSouthNorthamptonshireCouncilsfortheplanperiodupto2029,includingstrategicpoliciesforsteeringandshapingdevelopment.

12.3.30 Paragraph3.6oftheJCSemphasisesprivatesectorinvestmentis“fundamental to the successful achievement of the spatial vision and objectives through the spatial strategy”

12.3.31 TheJCShasprovided16‘SpatialObjectives’atparagraph4.63,whichprovidethedirectionforthepoliciesoftheJCS,withtherelevantlistedbelow:

• Objective1-ClimateChange

¶ Promotingsustainabledesignandconstructioninallnewdevelopments.

• Ensuringnewdevelopmentspromotetheuseofsustainabletravelmodes.

¶ Objective2-InfrastructureandDevelopment.

¶ Ensuresocial,physicalandgreeninfrastructureisadequatelyprovidedtomeettheneedsofpeopleandbusinessinatimelyandsustainablemanner,inresponsetoregenerationandnewdevelopmentinWestNorthamptonshire.

• Objective3-Connections

¶ Encouragetheuseofsustainabletravelandconsequentlypromotedevelopmentswhichwillmaximisetheuseofalternativetravelmodesinordertocombatcongestion,reducecarbonemissionsandaddresssocialexclusionforthoseinbothruralandurbanareaswhodonothaveaccesstoaprivatecar.

• Objective8-EconomicAdvantage

¶ StrengthenanddiversifyWestNorthamptonshire’seconomybytakingadvantageofWestNorthamptonshire’sinternationallywell-placedlocation,strategictransportnetworkandproximitytoLondonandBirmingham.

12.3.32 TheJSCnotesatparagraph8.16that“…in identifying sites for further strategic distribution development regional advice is that priority should be given to sites that can be served by rail freight and operate as intermodal terminals. At the regional level there is strong support for further rail related strategic distribution development and that further provision should be made in the West Northamptonshire area”.

Northamptonshire Transportation Plan (NTP)12.3.33 ThethirdNTPwasadoptedinMarch2012andsetsoutNCC’slong-termvisionsandobjectives

fortransportandthepoliciestoimplementtheobjectives.TheNTPencompassesaselectionof‘DaughterDocuments’andconsistsofTownandThematicStrategies.TheNTP’sultimateaimistoaccompanytheeffortsoftheLocalEnterprisePartnershipsintheareatosecurethedeliveryoftheJCSandprovideacleartransportstrategyforNorthamptonshire.

Page 10: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 10

12.3.34 TheoverallvisionoftheTransportationPlanisprovidedatpage17oftheNTP,itstates:“For Transport and Travel to contribute towards making Northamptonshire a great place to live and work, through creating tangible transport options to satisfy individual needs and to encourage more sustainable travel. The transport system will provide fast and efficient movement of people and goods, and will be accessible for all. Expanding networks and capacity of networks in Northamptonshire will be fully integrated into new developments and regeneration areas to support more sustainable communities. Economic growth and prosperity is a top priority for Northamptonshire and connectivity has a vital role to play in encouraging businesses to locate to the area, and getting people to work and services such as education and health, as well as to leisure activities and for shopping. Improved technology and local accessibility will reduce the need to travel, whilst supporting economic growth, within a low carbon environment and Northamptonshire will become an exemplar for the latest developments in information technology, fuel technology, and new forms of transport. The County Council will work in partnership with all stakeholders and the wider community to deliver this transport vision and strategy”.

12.3.35 Thefollowingpoliciesaregivenatpages58and68oftheNTPrelevanttotheProposedDevelopment. “StrategicPolicy2:WewillsupporttheintroductionofeffectiveandattractivesustainabletransportoptionsthatwillencouragelastingmodalshiftinNorthamptonshire.Wehavesettwotargetsformodalshift,basedon2001Censusjourneytoworkdata,toachieveby2031:

• A reductionof5%insingleoccupancycarjourneystoworkfromtheexistingbuiltupareasofthetowns.

• Areductionof20%insingleoccupancycarjourneystoworkfromnewdevelopments.” “Strategic Policy 3: We will ensure that all new developments are well connected by public transport and walking, cycling and motor vehicles routes, to the existing transport network or one that can be reasonable expected to be created – this will allow ease of movement between the development and existing built up areas and provide access to employment and key services.” “Strategic Policy 19: We will work to improve journey times and reliability on the highway and rail networks in order to increase the efficiency of freight movements and facilitate the local economy to grow.”

Northamptonshire Road Freight Strategy (NRFS)12.3.36 NorthamptonshireRoadFreightStrategy(NRFS)isa‘daughterdocument’oftheNTPand

prioritisestheexistingroadfreightimplicationsandmeasuresrequiredtomitigatesuchimpacts.

12.3.37 Inthestrategiccontext,theNRFSstatesatpage15that:“The continuing choice of Northamptonshire as a location for distribution activity is dependent on continuing good transport links. Congestion causes delay and leads to unreliability in journey times, which has far-reaching negative consequences for distribution operation. The performance of the strategic road network is therefore of critical consequence. If, or when, it becomes severely congested it poses a threat that could lead to companies re-locating elsewhere. It can also cause rat-running on to less suitable routes”.

12.3.38 TheNRFSprovidesrelevantmaterialtotheProposedDevelopmentbecausetheStrategicRoadFreightNetworkidentifiestheA45,A508,andA43locatedtotheimmediatenorth,east,andsouthofthemainsiteas‘strategiclorryroutes’.Consequently,theserespectiveroutes,aswellastheM1Motorway,areprominentcorridorsforheavygoodsvehicles(HGV)movementswithinNorthamptonshire.

Page 11: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 11

12.3.39 TheNRFScontributestoNorthamptonshire’svisiongivenatpage12,to“encourage the sustainable distribution of goods through minimising road based travel and the associated environmental impacts of road haulage, whilst maintaining economic efficiency and helping to improve the quality of life for the residents of Northamptonshire”.

12.3.40 TofulfilNorthamptonshire’svisionofanenhancedroadfreightnetwork,theNRFShassetoutatpage12sixobjectiveswhichwillprovidetheframeworkofthedocument:

• Tomitigatemeasuresrelatedtogrowingdemand;

• ToaddresstheproblemscausedbyHGVtrafficinbothurbanandrurallocationsandtoreducetheimpactofHGVsonlocalcommunities,especiallyconcerningovernightlorryparking;

• Toinfluencemovementpatternsandencouragesustainabledistributionwithinthecounty;

• Toencouragecommercialandeconomicgrowth;

• ToreducetheenvironmentalimpactoffreightmovementandreducetheimpactofHGV’soninappropriateroutese.g.ruralareas,areasinAirQualityManagementAreas(AQMAs),andareaswithweightrestrictions;and

• Tomanagethenetworktoprovideeaseofmovementthroughthecountyandtoreducetheimpactsofcongestionand‘lostproductivetime.

12.3.41 Further,theNRFSdrawsoutatpage19theconstraintsandchallengesposedbysolelyroadfreightmovement,whichinclude:

• TheimpactsontheSRNas“lorries are the primary cause of road deterioration”

• Problemsrelatedto“link speeds, patterns and types of accidents”

• Challengestolocalareasnotably;“pick-up and delivery impacts, parking, noise and vibration emission, bridge strikes and queuing to access delivery sites”.

12.3.42 Therefore,therelevantconstraintsofpurelyroadfreightoperationslistedaboveemphasisesthe “ability to move freight by rail is crucial to the economy”(page21)whichistobecomemoreprominentwiththerequirementsofreducingemissionsandcongestion.

Northamptonshire Major Roads Strategy12.3.43 TheNorthamptonshireMajorRoadsStrategyisa‘daughterdocument’oftheNTPand

concentratesonthemainroadsoutsideourlargertowns,andcomplementstheTownTransportStrategieswhichcovertheroadnetworkwithinthelargertowns.

Page 12: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 12

12.3.44 TheNorthamptonshireMajorRoadsStrategyshowshowtheMajorRoadsStrategytiesinwiththesixover-archingNorthamptonshireTransportationPlanobjectives.Notably,thedocumentoutlinesatpage10:

• Investmentinthehighwayinfrastructurewillbeimportanttomeetthetransportdemandsofthefuture,includingthosearisingfromnewdevelopment;

• Highwayimprovementshelptodiscouragetrafficfromusingunsuitablerouteswhichhaveanadverseeffectonlocalcommunities;

• Highwayimprovementswillbeplannedtomakesuitableprovisionforallroadusers,notjustthecar;

• Highwayimprovementscanhaveasignificantimpactonbusiness,byshorteningjourneytimesandimprovingjourneytimereliabilityforkeymovements;

• Highwayimprovementscanhelptoreducecongestionandtheenvironmentalimpactoftraffic;and

• Highwayimprovementsneedtobedevelopedthatofferthebestvalueformoneyintacklingtheproblemsidentified.

Northamptonshire Bus Strategy12.3.45 TheNorthamptonshireBusStrategyisa‘daughterdocument’oftheNTP.Page7ofthe

NTPoutlinesthat“Expanding networks and capacity of networks in Northamptonshire will be fully integrated into new developments and regeneration areas to support more sustainable communities”.

12.3.46 Therefore,assetoutatpage10,theNorthamptonshireBusStrategyaimsamongstotherobjectivesto“increase the attractiveness of bus travel to encourage modal shift and allow the housing growth proposed in the county to be accommodated”.Indoingso,thebusnetworkwillprovidebenefitssuchasreducedcongestionandcarbonemissions,andthebenefitsfromensuringpeoplecanhavegoodaccesstojobsandservicesandcontributetotheeconomy.

12.3.47 ItoutlinesthatinallproposalswhereTransportAssessmentsarerequired,developersshallclearlysetoutthenumberoftripsexpectedtobegeneratedbyeachmode,includingbybus.Crediblemodeshares,whencomparedwiththeexistingcensus-deriveddataforjourney-to-workmode,shouldbesetout,havingregardtothelevelofaccesstohighqualitybusservices.

A45/M1 Northampton Growth Management Scheme (NGMS) 12.3.48 HighwaysEngland(formerlytheHighwaysAgency)inpartnershipwithNCCandotherlocal

authoritiesinwestNorthamptonshireundertookastudyoftheA45/M1aroundNorthampton.Followingconsiderationoftheforecaststrategicroadnetworkimpacts,itwasconcludedthattheA45/M1NorthamptonGrowthManagementScheme(NGMS)shouldbeimplemented.

12.3.49 CentraltopotentialimpactsofdevelopmentsontheStrategicRoadNetwork(SRN)isastudybythethenHighwaysAgencyoftheSRNaroundNorthampton,notablytheM1andA45.Asreportedatparagraph2.2,thestudyconcludedthat“…there is no feasible and environmentally acceptable solution to accommodating potential peak period traffic demand through large scale capacity improvements to the A45 and its numerous junctions”.

12.3.50 ThestudydeterminedtheNGMSshouldbeputintooperationtosatisfactorilycaterfortheprojecteddevelopmentgrowth(to2026).Paragraph2.3statesthatthe“NGMS has been designed to ensure that vehicular access and egress onto the SRN is managed effectively and that the safety and free flow of traffic on the A45 and M1 is maintained over the plan period”

Page 13: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 13

12.3.51 TheNGMSincludesalistofproposedschemes(Annex1)whichwillformulatetheoverallstrategyforimprovementstotheA45/M1corridor,consequentlyaccommodatingfuturedevelopmentsandmitigatingtheimpactsofthepotentialincreaseoftrafficflowsoftheSRNintheNorthamptonarea.The schemes comprise:

• M1J15:

¶ Rampmeteringonnorthboundon-slip

¶ ExittoA45expandedfromtwotothreelanes

¶ CreationoffourthlanetotheM1southboundoff-slip

¶ Roadmarkingstobeupgradedfortheeasternbridgesection.

• A45WoottonInterchange:

¶ Rampmeteringtobeintroducedforthenorthboundon-slip.

• A45QueenEleanorInterchange:

¶ UpgradedMOVAtrafficsignalssystemtobeproposedforallexistingtrafficsignals.

¶ Introducerampmeteringforthenorthboundandsouthboundon-slips

¶ Forthenorthboundon-slip,theshortmergewillberemovedandtrafficwillaccess the A45mainlineonlythroughthelanegainfacility

¶ LondonRoadapproachtobesignalised(includingcirculatorycarriageway)

¶ WideningNewportPagnellRoad(B526).

• A45BrackmillsInterchange:

¶ UpgradedMOVAtrafficsignalssystemforallexistingtrafficsignals

¶ TrafficsignalsatboththeCaswellRoadapproachandentrytotheA45southboundon-slip(fromPavilionDrive).

• A45BarnesMeadowInterchange:

¶ Rampmeteringonnorthboundon-slip

¶ RemovalofshortmergeandtrafficcanonlyaccessA45mainlinethroughthenorthboundlane gain facility

¶ MOVAcontrolledtrafficsignals.

• A45LumbertubsInterchange:

¶ UpgradedMOVAcontrolledtrafficsignalssystemtobeproposedforallexistingtrafficsignals

¶ Rampmeteringtobeplannedforbothnorthboundandsouthboundon-slips

¶ Removalofshortmergeonsouthboundon-sliproadmeaningtrafficcanaccesstheA45mainlineonlythroughthelanegainfacility.

• A45GreatBillingInterchange:

¶ Rampmeteringatbothnorthboundandsouthboundon-slips

¶ MOVAcontrolledtrafficsignals.

12.3.52 TheA45/M1NGMSMemorandumofUnderstandingprovidesanagreedbasisforsupportingthefundinganddeliveryoftheNGMS,includingthroughnegotiatedcontributionssecuredbySection106planningobligations.ItisanagreementbetweenHighwaysEngland,NCCandtheLocalPlanningAuthorities.

Page 14: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 14

12.3.53 ExceptfortheworksatM1Junction15(whicharenotincludedfollowingadvicefromHighwaysEngland),allotherNGMSworksareincludedforintheNSTM2.

Highways England Road Investment Strategy (2015-2020)12.3.54 ThepurposeofHighwaysEngland’sFirstRoadInvestmentStrategy(RIS1)istofocusonthe

StrategicRoadNetwork(SRN)byoutlining“thefoundationsforabetterfuture–foundationsonwhichfutureRoadInvestmentStrategieswillbuild,aswestrivetoachieveourvisionofarevolutionisedSRNthatwillunderpinprogressandprosperityforgenerationstocome”(page9).

12.3.55 TheRIS1highlightstheimpactofincreasedcongestionontheSRN,includinganannualcostof£3.7billionforthefreightindustryandindicated“traffic density on UK motorways is 113 million vehicles per mile of road compared to 47 million in Germany and 39 million in France”(page19).

12.3.56 Therefore,centraltoRIS1isthe£15billioninvestmentwhich“has been committed to road investment between 2015 and 2021, with annual funding on enhancements tripling to £3 billion per year by 2021”(page19).

12.3.57 BelowliststheschemesinvicinityofthesitethataredescribedinthecurrentRIS2015to2020:

• M1Junctions13to19-TheschemeupgradestheM1toSmartMotorwaybetweenJunction13(MiltonKeynesSouth)andJunction19(M6Catthorpeinterchange).Itinvolvestheconversionofthehardshouldertocreateanewadditionalpermanenttrafficlane,increasingcapacitytoreducecongestion.Junction16to19oftheworksiscomplete,andconstructionofJunctions13to16isduetobeconstructedbetweenJune2018andMarch2022.

• ImprovementtotheAbthorpejunctionontheA43nearTowcester.AlongwiththeA5Towcesterreliefroad,theschemesupportstheTowcestersouthernextensionandhelpsremovetrafficfromthecentreofthetown.Thisschemeiscompleted.

• A5TowcesterReliefRoad(schemecommittedsubjecttoothercontributions)-AnewlinkroadtothesouthofTowcester,agreedaspartoftheTowcestersouthernexpansion,allowingtraffictobypassthetowncentre.

• A45/A6ChownsMilljunctionimprovement(schemenewlyannouncedinthisRIS)-UpgradeoftheChownsMilljunctionbetweentheA45andA6inNorthamptonshire.

• A45ThrapstontoStanwick(schemedevelopedfornextroadperiod)-UpgradingtheexistingsinglecarriagewaysectionoftheA45betweenStanwickandThrapston,sotheA45canprovideacontinuousExpresswaybetweentheA14andtheM1.

12.3.58 Inadditiontotheabove,HighwaysEnglandannounceda£220millionfundinMarch2017forjunctionupgrades,roundaboutimprovementandbettertrafficsignallingfortraffichotspots.Thisinclude£3.3millionforimprovementstotheA5/A508OldStratfordroundabout.DetailsofthisschemewereobtainedfromHighwaysEnglandandareincludedintheNSTM2.

Design Manual for Roads and Bridges (DMRB)12.3.59 ThepurposeoftheDMRBistoproviderequirements,adviceandguidelinesfortheSRNand

isthereforemandatoryforallworksundertakenonmotorwayandallpurposetrunkroads.InpreparingtheproposedhighwaymitigationworksassociatedwiththedevelopmenttheDMRBhasbeenappliedincludingrelevantInterimAdviceNotes(IANs).

12.3.60 ThedesignstandardstobeusedfortheassessmentanddesignfortheDCOsubmissionwereagreedwiththeTransportWorkGroup,assetoutinTN4(TAAppendix9).

Page 15: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 15

Northamptonshire Parking Standards (September 2016)12.3.61 NCCadoptednewparkingstandardsinSeptember2016.Thepreviouscountywideparking

standardsappliedamaximumcarparkingspaceallowance,ascarparkingwasusedasademandmanagement tool.

12.3.62 TheaimsoftheSeptember2016parkingstandardsdocumentareprovidedatpage2,andinclude“to support the provision of sufficient, usable parking within development without compromising highway safety whilst supporting good design and sustainable travel.”Thenewstandardsthereforeprovidedminimumcarparkingrequirements.ThenewstandardsaretherelevantguidancefortheProposedDevelopmentandhavethereforebeenapplied.

Overall Compliance with Policy12.3.63 TheProposedDevelopmentandsupportingtransportdocumentslistedatTable12.2havebeen

developedwithdueregardtotheabovepolicydocuments,withemphasisgiventotheguidancesetoutintheNPSNN.TheproposalsincludeimprovementsandalterationstoboththeSRNandlocalhighwaynetwork,aswellastosustainableinfrastructureandtransportservices.

12.3.64 Thepolicydocumentsstatethatdevelopmentshouldbesitedinsustainablelocationswithaccesstoexistingfacilitiesandservices.InthecaseofanSRFIitisalsonecessarytoidentifyasuitablelocationtoprovidetherequiredconnectiontotherailfreightnetwork,withexcellentconnectionstotheSRN.TheProposedDevelopmentsiteachievestheserequirementsand,assuch,meetswiththeGovernmentObjectivesinNPSNNandthenational,regionalandlocaltransportpoliciesandobjectivessummarisedinthissection.ItcanthereforebeconcludedthattheProposedDevelopmentmeetsrelevantpolicyguidelinesandspecificrequirementsintermsoftransport.

12.4 BASELINE CONDITIONS

Site location and context12.4.1 ThelocationoftheProposedDevelopmentindescribedinChapter2ofthisES.Theexistingand

committedpedestrian,cycle,publictransportandhighwayinfrastructureisdescribedindetailatChapter3oftheTA(Appendix12.1).

12.4.2 AsthemajorityoffreightintheUKismovedbyroad,theNSPNNstatesthatproposedSRFIshouldhavegoodroadaccess,asthiswillallowrailtoeffectivelycompetewith,andworkalongsideroadfreighttoachieveamodalshifttorail.Themainsiteisinastrategicallysignificantlocationforlogisticsanddistributionactivityand,beingadjacenttoJunction15oftheM1,itprovidesexcellentroadconnectionopportunitieswiththerestoftheUK,viatheM1,M6,A45,A14andA43.ThesiteisalsoexcellentlylocatedinrelationtothestrategicfreightroadnetworkinNorthamptonshire,whichinadditiontotheSRN,includesthestrategiclorryroutesoftheA508,A428,A509,A43(northofNorthampton),andtheA6.

Baseline highway network conditions

M1 Motorway12.4.3 TheM1Motorwayisastrategicrouteforlocal,regionalandinternationaltrafficandplays

animportantroleasadirectmotorwaylinkbetweenthenorthandsouthandamajorrouteconnectingsomeofthelargestconurbationsintheUK.NearJunction15itcomprisesastandard3-lanemotorwaywithhardshoulders.ThissectionoftheM1iscongestedduringtheweekdaymorningandeveningpeakhoursandatothertimeswhentrafficflowsareheavy.

Page 16: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 16

12.4.4 TothenorthoftheProposedDevelopment,HighwaysEnglandhasrecentlycompletedworkstoup-gradetheM1betweenjunctions19to16,toalllanerunningaspartoftheHighwaysEnglandSmartMotorwayProject,whichwillreducecongestionofthissectionoftheM1.Tocomplementthatscheme,HighwaysEnglandhaveconfirmedworkstoextendalllanerunningtoincludeM1Junctions16to13,thiswilltaketheformof4lane“alllanerunning”alongwith“throughjunctionrunning”(4laneswithnohardshoulder)ofM1Junctions15and15A.TheSMPisprogrammedtobeconstructedbetweenJune2018andMarch2022.However,whilsttheworksmayincludereconfigurationoftheslip-roads,theydonotincludeimprovementstothejunctionsthemselves.

M1 Junction 1512.4.5 M1Junction15isatear-droparrangementincorporatingaseriesoftightradii.Theconstrained

geometryandhightrafficdemand,particularlyduringpeaktimes,meansthejunctionisoftenveryheavilycongestedwithpeaktimequeuingontheA45andA508approachestothejunctioncommon place.

12.4.6 TheM1off-slipsandA45approachtoJunction15arecontrolledbytrafficsignals,withtheA508andSaxonAvenueapproachesoperatingunderagivewayarrangement.Thejunctioncanbedifficulttonavigateandthelaneallocationaroundthethree-lanecirculatingcarriagewaysattheA508andA45approachesareconfusing;forexample,vehiclesfromtheM1northboundoff-slipcanturnrightinallthreelanesdespitetherebeingtwoexitlanesontoM1northbound,whilstvehiclesfromthebridgecanonlyturnrightintwolanes,makingitdifficultforvehiclesattheA508givewaylinetojudgeentryontotheroundabout.

12.4.7 HighwaysEngland,aspartoftheirM1/A45NGMShaveidentifiedanimprovementschemeforJunction15.Theschemecouldpotentiallyprovideacapacityimprovementofaround9%atthejunction.However,thiswouldstillleavethejunctionovercapacityatcurrenttrafficlevels,andHighwaysEnglandadvisedthatthereisnocertaintywhetheranimprovementatJunction15wouldbedeliveredandthatthisschemeshouldnotbeincludedwithintheNSTM2.

M1 Junction 15A12.4.8 M1Junction15Aisagrade-separateddumb-bellinterchangewithnorthernandsouthern

roundaboutsconnectedbyadualcarriagewaylinkroadwhichpassesunderneaththeM1mainline.M1Junction15AconnectstheA43tothesouthandtheA5123tothenorth,whichprovidesaccesstoNorthampton.M1Junction15AalsoprovidesaccesstotheSwanValleyindustrialestateandtheNorthamptonServiceStationviaaseriesofconnectedroundabouts.

12.4.9 Atpeaktimes,theM1northboundandsouthboundoff-slipsaresusceptibletocongestion,withqueueinganddelayexperiencedontheM1northboundoff-slipespecially.QueuingontheA5123andA43approachesislesssignificantinbothpeakperiods.

A4512.4.10 TheA45LondonRoadformsthemainarterialroutebetweentheM1,NorthamptonandtheA14

andisofdualcarriagewaystandardthroughoutthelocality.ItissubjectgenerallytothenationalspeedlimitbeyondtheimmediateconfinesofM1Junction15,whereitissubjecttoa40mphspeedlimit.Theroadcarrieslargevolumesoftrafficthroughoutthedayandisparticularlybusyduringpeaktimes.

12.4.11 TheNGMSrecognisestheimportanceoftheA45inhelpingtosupportgrowthandsustaintheeconomythroughouttheregion.ItisagreedwiththeneighbouringplanningauthoritiesandNCCforitsfuturemanagementandsafe-guarding.Theproposalscompriseaseriesofdemandmanagementmeasuressuchassignalisationandramp-meteringtolimitcongestionalongtheA45atpeaktimes.TheNGMScontainsonlylimitedproposalsforimprovingM1Junction15,andasdescribedabove,HighwaysEnglandhaveadvisedthatthereisnocertaintywhenthatimprovementwouldbedelivered,asotherNGMSjunctionshavebeenidentifiedaspriorities.

Page 17: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 17

12.4.12 Asaresult,andtheexclusionofanyimprovementsatM1Junction15fromtheSmartMotorwayProject,M1Junction15willinevitablybecomemorecongestedinthefuture

A50812.4.13 TheA508formsthelinkwiththeA5tothesouthandM1Junction15tothenorth.Itbisectsthe

villageofRoadeandpassesadjacenttothesmallervillageofGraftonRegis.

12.4.14 Itisasinglecarriagewayroadandisanimportantpartoftheprincipalroadnetwork,formspartofthestrategicfreightroadnetwork,andithasbeenidentifiedintherecentDfTconsultationaspartoftheproposedMajorRoadNetworkforEngland.TheA508alsoformspartoftheSRNemergencydiversionroutefortheM1andA5.

12.4.15 ThespeedlimitvariesalongtheA508,withthenorthernandsouthernsectionsoftheroadgenerallyderestricted,with30mphspeedlimitspresentthroughRoadeandGraftonRegis,anda50mphspeedlimitonthesectionstothenorthandsouthofRoade,wherethereisahigherconcentrationofbendsandpriority-controlledjunctions.

12.4.16 TothesouthoftheMainSite,BlisworthRoad(becomingCourteenhallRoadtothewest)formsasimplepriority-controlledT-junctionwiththeA508.DriversturningrightfromtheA508intoBlisworthRoadblocksouthboundtrafficontheA508,leadingtoqueuingtrafficanddelays.ThereisaconcernfromresidentsthatdriversuseBlisworthRoadto‘rat-run’betweentheA508andtheA43andviceversa,passingthroughBlisworthvillage.

12.4.17 TothesouthoftheMainSite,theA508passesthroughthevillageofRoade,wherethealignmentisconstrainedattheStratfordRoad/HighStreetmini-roundaboutandoverthenarrowrailwaybridgeovertheWestCoastMainLine(WCML).Stop-starttrafficisfrequentlyseenandatpeaktimesqueuesofstationarytrafficcanquicklydevelop.HGVstravellinginopposingdirectionsontheA508bridgeovertherailwayareoftenobligedtogivewaytoeachotherastheyarenotabletopasssafelyonthebridgestructureitself.

12.4.18 QueuesurveysundertakeninSeptember2016attheA508/HighStreetmini-roundabout,recordedconsistentqueuingofupto100metresduringthemorningpeakhourontheA508southboundapproachtothejunction.Duringtheeveningpeakhour,queueingwasmoretransient,reachingupto155metresontheA508southbound,andupto60metresontheA508northboundovertherailwaybridge

12.4.19 QueuingwasalsoobservedatontheA508ineachdirectionattheA508simplepriority-controlledT-junctionwithHydeRoad,particularlyduringthemorningpeakhouraround3o’clockintheafternoon,whenitislikelythatthenearbysignalcontrolledcrossingwasbeingused.

12.4.20 HydeRoadprovidesaccesstothewestsideofRoade,whichisaccessedbyafurtherbridgeovertheWCML.TothewestHydeRoadbecomesBlisworthRoadtowardstheoutskirtsofthevillage.BlisworthRoadthenbecomesKnockLane,whichtothewestformstheminorarminasimplepriority-controlledT-junctionwithStokeRoad.

12.4.21 TothesouthofRoade,theA508hasastaggeredcrossroadsjunctionwiththeC26RookeryLaneandAshtonRoad.Immediatelytothesouthofthejunction,thereareaseriesofbendsintheA508,whichisaknownaccidenthotspot.

12.4.22 TothesouthofRookeryLane,theA508formsthemajorarminapriority-controlledjunctionwiththeC85PuryRoad,whichprovidesalinkthroughtotheA5.AghostlandrightturnharbouragefacilityisprovidedatthejunctionforrightturnmovementsfromtheA508toPuryRoad.TheentirelengthofthePuryRoad,betweentheA508andA5,issubjecttoa7.5Tenvironmentalweightrestriction,exceptforaccessforloading.

Page 18: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 18

Baseline Conditions for Walking, Cycling and Equestrians 12.4.23 TheexistingconditionsforpedestriansandcyclistaredescribedindetailintheWalking,Cycling

&HorseRidingAssessmentReport(TAAppendix18).TheWCHARAssessmentReportdescribesthepedestrian,cyclistsandequestrianfacilitieswithinthevicinityoftheProposedDevelopment,includingpublicrightsofway(PRoW).

12.4.24 Collingtree,MiltonMalsorandGrangeParkfallwithinthe2kmwalkingdistanceoftheMainSiteandpartsoftheSouthNorthamptonsustainableurbanextension,whichisacommitteddevelopmentofsome1000dwellings,wouldalsobewithinwalkingdistanceofthesite.

12.4.25 AlargepartofsouthernNorthamptonwouldbewithincyclingdistanceoftheMainSite,aswouldseveralofthesurroundingvillages,includeRoadetothesouth.NorthamptonRailwayStationisapproximately6kmcyclefromthemainsite,whichisanacceptablecycledistanceforregularcommuters.

12.4.26 PublicfootpathsKX13andKX17runthroughthemainsite.PublicfootpathKX13andKG5providesaconnectionfromHighStreet,inCollingtree,overtheM1viaanexistingbridgeandacrosstheSRFIsitetowardstheA508.KX17linkswithpublicfootpathKX13whichalsocrossestheSRFIsite,linkingwiththeexistingbridgeovertheWCMLrailway.FootpathKX13linkswithfootpathRD1,providingaccesstoBlisworth.

12.4.27 TheexistingbridlewaysincludingBridlewaysKG1,KG2,LD6andLD7arelocatedtotheimmediatenorthoftheSRFIsite.ThesequenceofbridlewayslinksCollingtreewiththenetworkofcyclewayswithinEastHunsbury,en-routetoNorthamptonandformpartoftheNorthamptoncycleroutenetwork.

12.4.28 ThereareanumberofexistingPRoWsinthevicinityofRoadethatwouldbeeffectedbytheproposedRoadeBypass.ThesearepublicfootpathsKZ30,KZ19,KZ2a,RZ3andpublicbridlewaysKZ10/RZ1andRZ6locatedonthewesternsideofthevillage.

12.4.29 AtM1Junction15asharedusefootway/cyclewayisprovidedalongthewesternsideofthejunction,connectingwiththeshortsectionoffootway/cyclewayonthewesternsideofA45andtheexistingfootwayprovidedalongthewesternsidetheA508.Aseparatefootway/cyclewaylinkisprovidedacrosstheA45onthenorthernpartofJunction15,toconnectwiththefootway/cyclewayonthenorthernsideofSaxonAvenue.AnarrowfootwayisprovidedontheeasternsideoftheA45asfarnorthaspublicfootpathLF2.ExceptfortheM1northboundon-slip,whichisprovidedwithacontrolledsignalisedcrossing,allothercrossingsatthejunctiondonothavetheirowndedicatedsignal,butcanbecrossedona‘walkwithtraffic’basis(i.e.whenthemaintrafficsignalsareonred).

12.4.30 TothenorthoftheA45/WateringLanejunctionasharedusefootway/cyclewayisshownontheNorthamptonCycleMaptothenorthofWateringLane,alongsidethewesternsideoftheA45.ItconnectsWateringLaneintothewiderNorthamptoncyclenetwork.However,tothenorthofM1Junction15thecurrentfacilityterminatesattheA45laybyandthereforethereisnoconnectioncurrentlyprovidedbetweenM1Junction15andfacilitytothenorthofWateringLane.

12.4.31 Thereisnetworkofcyclefacilitiesand‘AdvisoryRoutes’withinEastHunsburythatprovideonwardsconnectiontoNorthamptonandareaccessibleviaCollingtree.ThereisalsoanetworkofcyclefacilitieswithinGrangePark,providingonwardslinkstotheWoottonandHardingstoneresidentialareas.

12.4.32 NCNRoute6islocatedtotheeastoftheMainSite.TherouteencompassesQuinton,Hardingstone(includingtheHardingstoneSUE),andBrackmillsIndustrialEstate,en-routetoNorthamptontowncentre.

Page 19: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 19

12.4.33 Therearenowalking,cyclingorhorse-ridingfacilitiesprovidedatM1Junction15A.However,thereisanexistinguncontrolledatgradecrossingpointontheA43approximately70msouthofthejunction,linkingpublicfootpathKX2withLA13.ThecrossingislocatedweretheA43northboundapproachisproposedtobewidenedtoaccommodateanadditionalflaredlane.

12.4.34 TheGrandUnionCanalislocatedtothewestofthestudyareaandprovidesatowpathrouteconnectingMiltonKeyneswithNorthampton.Therearecurrentlynodedicatedoff-roadcyclefacilitiesprovidedontheA508orwithinRoade.

12.4.35 SignalcontrolledcrossingsareprovidedontheA508atthreeseparatelocationswithinRoadeprovidingpriorityforpedestrianswishingtocross.AnumberofatgradepedestriancrossingswithcentralrefugesarealsoprovidedwithinRoadeallowingpedestrianstocrosstheA508intwostages.

12.4.36 AnarrowfootwayisprovidedonthenorthernsideoftheC26RookeryLanelinkingthefootwayonthewesternsideoftheA508attheA508/RookeryLane/AshtonRoadjunction,withthoseprovidedwithinStokeBruerne.TherearenofootwaysprovidedontheeasternsideoftheA508ortheC26AshtonRoad.

12.4.37 FootwaysareprovidedoneachsideoftheA508inalongitsfrontagewithGraftonRegis,butnopedestriancrossingfacilitiesareprovidedonA508.TothesouthofGraftonRegisthereisnofootwayontheA508untilthejunctionforYardleyGobion

12.4.38 Thereisacontinuous,butnarrow,footwayalongthewesternsideoftheA508fromM1Junction15tothebridgeovertheGrandUnionCanal,nearStokeBruerne,whereitthenswitchestotheeasternsideforapproximately600m.Beyondthis,anduntilthePuryRoadjunction,thereisnofootwayontheA508,althoughacontinuouslinkbetweenthetwopointsisprovidedbyafootwayalongsidetheadjacentaccessroad.AtthePuryRoadjunctionthefootwaycrossesbackovertothewesternside,fromwhereacontinuousfacilityisprovidedlinkingwithGraftonRegis.

12.4.39 Overall,therearesomeopportunitiesforpedestriantravelassociatedwiththeProposedDevelopment,butthesewillberelativelylimitedduetotherestrictednumberofresidentialareaswithinanacceptablewalkingdistance.Pedestrianjourneyswillhowevercontinuetoplayanimportantrole,aspromotingsustainableintegratedtransportinvolvesprovidinggoodpedestrianlinkstopublictransportfacilities.Therearegoodopportunitiesforcycletravelassociatedwiththemainsite,withalargepartofsouthNorthamptonfallingwithinanacceptablecyclingdistance.

12.4.40 TheM1couldhoweverprovideabarriertotraveltoandfromthenortheastofthemainsite.ThedevelopmentshouldthereforeexaminetheopportunitiestoimproveandenhancetheexistinglinksovertheM1bridgeconnectingwithHighStreetinCollingtreeandatM1Junction15.

Baseline Public Transport Conditions12.4.41 TheexistingpublictransportservicesnearthemainsitearedescribedinthePTS(TAAppendix2).

12.4.42 Atpresent,theMainSitehaslimitedaccessibilitybybus,withServices33/33a,X4andX7operatingalongtheA508andpassingbythemainsite.TheX4andX7arebothexpresslimited-stopservices,withtheneareststoptothemainsitebeingnorthofRoade.Theservicesbeginoperationjustafter0630hoursandfinishbefore2100hours.The33/33Aisafrequentstopservicethatrunshourly(combined)between0900hoursand1800hours,servingstopstothesouthofthemainsiteneartheA508/Blisworth(Courteenhall)Roadjunction.

Page 20: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 20

12.4.43 ThismeansthattherearenoservicesoperatingbytheMainSiteat0600hoursand2200hours,whicharekeyshiftchangesfortheProposedDevelopment.Publictransportaccessibilityisbetterduringtheday,withatraveltimeoflessthan30minutestoNorthamptonTownCentre.However,inlinewiththeNorthamptonshireBusStrategyrequirements,anhourlyservicewillnotbeadequatetomeettheneedsofemployeesandmakepublictransportanattractivealternativetotheprivatecar.AcomprehensivestrategytoensurethatthedevelopmentsiteisaccessiblebybusisthereforeproposedinthePTS.

12.4.44 ThenearestrailwaystationtothesiteisNorthampton,ontheWCMLloopfromBirminghamtoLondon.Thereisatrafficfree/lightlytraffickedcycleroutetothestationalthoughitisapproximately6kmfromtheNorthamptonGatewaySRFIsite.TherailwaystationisservedbyagoodservicetoandfromRugby,atleastevery20minutesatpeaktimes,togetherwithdirecttrainstoLondonandBirmingham.TheopportunitywillthereforeexistinthefutureforstafftotravelbytraintoNorthamptonandcompletetheirjourneyeitherbycycleorviatheconnectingbusservices.

Baseline Highway Safety Conditions12.4.45 AnassessmentoftheaccidentdataontheroadnetworkimpactedbytheProposedDevelopment

hasbeenundertaken.ThisisreportedinthePersonalInjuryAccident(PIA)AssessmentreportprovidedatAppendix3oftheTA.

12.4.46 TheassessmentidentifiesthefollowingclustersandtrendsinPIAsthatsuggestexistingproblems:

• M1Junction15-aclusterofsixPIAsattheM1southboundoff-slip/A45northboundexitatthejunction,indicativeofcongestedtrafficconditions.

• M1Junction15-aclusteroffourPIAsontheA508northboundapproachtothejunction,comprisingacombinationofrearendshutandcollisionsonthecirculatorycarriagewayandatthegiveway.

• M1Junction15A-aclusteroffivePIAsontheA43eastboundapproachtothesouthernroundabout,andaclusterofthreePIAsonthecirculatorycarriagewaypassingthisapproachtowardstheA43north.

• QueenEleanorInterchange–smallclustersofPIAsoneachapproachtothejunction,indicativeofthebusyconditionsattheinterchange.

• A45–drivererrorwasaprominentfactor,includingsuddenbreaking,rearendshuts,andtravellingtoofastfortheroadconditions.

• A508/BlisworthRoad(Courteenhall)junction–aclusteroffourPIAsatthejunction,includingonedriverturningrightintotheBlisworthRoadinaninappropriategapinnorthboundtraffic,andtworearendshutsontheA058associatedwithtrafficbeingheldupatthejunction.

• A508bendtosouthofBlisworthRoad(CourteenhallRoad)–aclusteroffourPIAs,threeofwhichrelatetolossofcontrolanddriverstravellingtoofastoftheroadconditions.

• A508bendssouthofRookeryLane/AshtonRoadcrossroads-aclusterofaccidentsonthebendstothesouthofthecrossroads,suggestingatrendofdriverstravellingtoofastinadverseroadconditions,asthemajorityofthePIAsoccurredinwet/damporfrost/icyroadsconditions.

• A43/TowcesterRoad–aclusteroffourPIAs,allinvolvingvehiclesturningrightfromtheA43intoTowcesterRoad.

12.4.47 AttheremainingPIAstudyareas,theassessmentdidnotidentifyanyspecificlocationsortrendswheretheProposedDevelopmentcouldexacerbateexistingtrafficsafetyissues.

12.4.48 RoadsafetyoftheproposedhighwayimprovementshasbeenconsideredviatheStage1RoadSafetyAuditprocessandDesignTeamResponseReportwhichareincludedatAppendices31and32oftheTA.

Page 21: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 21

12.5 ASSESSMENT OF LIKELY SIGNIFICANT ENVIRONMENTAL EFFECTS

Transport Modelling 12.5.1 TheTransportWorkingGrouprequiredthatatastrategiclevelthetransporteffectsofthe

proposeddevelopmentschemebemodelledusingtheNSTM2.WSPLtdmaintainandoperatetheNSTM2onNCC’sbehalfandhaveundertakenallstrategicmodellingwork,withoutputsprovidedtotheTransportWorkingGroup.

12.5.2 TheNSTM2hasundergonearecentmajorupdatebyWSP,includingafullcalibrationandre-validationprocess,includingallappropriatecommittedandallocateddevelopment,therebyensuringconsistencywiththeadoptedCoreStrategyLocalPlans.Inaddition,acomprehensiveprocessofcalibrationandre-validationoftheareasofthemodeltothesouthoftheM1andthesurroundingvillageshasbeenundertakentoensurethattheexistingbaselineconditionsintheseareasareaccuratelyunderstoodandrepresentedintheNSTM2.

12.5.3 ItwasagreedwiththeTransportWorkingGroupthatthemulti-modalfacilityoftheNSTM2wouldnotbeused.InsteadappropriatemodalsplittargetsforpublictransportandothersustainabletravelmodesareidentifiedintheFTP(TAAppendix1)andaseparatePublicTransportStrategy(TAAppendix2)hasbeendevelopedinconsultationwithNCCandthebusoperator.Thisapproach,withnoallowanceformodalshiftinthemodellingensuresarobust,or‘worst-case’approach.

12.5.4 TheTransportWorkingGroupalsorequestedthatassessmentofthevehicleimpactsbeundertakenusingthevehicletripgenerationwithoutconsideringtheeffectoftheFTPorPTSonmodalshare.

12.5.5 ThedevelopmenttripgenerationsincludeintheNSTM2modellingforalldevelopmentcasescenarios(bothwithandwithouthighwaymitigation)reflectthebaselinemodelsplitforsingleoccupancyvehicle(SOV)tripsof92%.Therefore,whilstthisapproachwasundertakeninaccordancewiththerequirementsoftheTransportWorkingGroup,itpresentsaworstcase,asitdoesnotincludefortherequired20%reductioninSOVjourneystoandfromtheSRFIsitethatisthetargetidentifiedintheFTP.WiththePTSandTravelPlanoperational,tripgenerationwouldbereducedincomparisontothatassessedandresidualtrafficimpactswouldalsobereduced.

12.5.6 TheassessmentscenariostobemodelledusingtheNSTM2wereagreedwiththeTransportWorkingGroup,asdescribedinChapter6oftheTAandsummarisedatTable12.3,below.

12.5.7 Aniterativeassessmentanddesignprocesshasbeenfollowed,inwhichtheneedforhighwayinterventionshavebeenidentifiedusingtheNSTM2,bycomparingthemodellingoutputsfromthedifferenceassessmentscenarios.Thishasthenbeenfollowedbydetailedanalysisusingindustrystandardassessmenttoolsand,inthecaseoftheSRN,micro-simulation,todevelopappropriatehighwaymitigationworks.ThisworkisdescribedatChapters7to10oftheTA.

Table 12.3: Transport modelling assessment scenarios

Scenario ID DescriptionReferenceCase B1 2021OpeningYear

C1 2021DfT02/2013CircularCompliantD1 2031FutureYear

DevelopmentCasenohighwaymitigationworks

E1 2021OpeningYearF1 2021DfT02/2013CircularCompliantG1 2031FutureYear

DevelopmentCasewithhighwaymitigationworks

H1 2021OpeningYearI1 2021DfT02/2013CircularCompliantJ1d 2031FutureYear

Page 22: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 22

12.5.8 ThehighwaymitigationworkshavethenbeencodedintotheNSTM2,andthemodelre-runtoconfirmthattheproposedhighwayimprovementsachievetherequiredoutcomesaspartoftheiterativeprocessreferredtoabove.

Traffic flows12.5.9 Theassessmentscenariosincludethe2021OpeningYearand2031FutureYear.The2021

OpeningYearscenariosconsiderthetrafficconditionswith,andwithout,thefirstphaseoftheProposedDevelopmentbeingoperational.The2031FutureYearscenariosconsiderthetrafficconditionswith,andwithout,allthedevelopmentbeingoperational.

12.5.10 Thegreatestenvironmentalchangewillgenerallybewhenthedevelopmenttrafficisatthelargestproportionofthetotalflow,whichhasbeentakentobeoncompletionoftheproposeddevelopment.Hencethe2031FutureYeartrafficflowsfromtheNSTM2scenariosareusedtoundertakeassessmentofthetransportenvironmentaleffectsoftheProposedDevelopment.

12.5.11 Thepeakhours(0800-0900and1700-1800hours),representthetimeperiodswhenbackgroundtrafficflowsareattheirgreatestandthereforetheavailablecapacityofthehighwaynetworkisatitslowest.Hencethesearetheassessmentperiodsusedinthedetailedmodellingwork.Thedevelopment’strafficflowswouldalsobespreadthroughoutthedayandtherefore,whereappropriate,likelyeffectsbasedon24-hourannualaveragedailytrafficflows(AADT)areexamined.ThemethodologyforthecalculationoftheAADTflowsisprovidedatAppendix32oftheTA.

Study area12.5.12 Afulldescriptionofthetransportmodelling,includinguseoftheNSTM2,isprovidedatChapter6

oftheTA

12.5.13 AniterativeassessmentprocesswasfollowedasitwasfoundthatprogressiveelementsoftheproposedhighwaymitigationresultedinbackgroundtrafficreassignmentofsufficientmagnitudetorequirerepresentingintheNSTM2.ThisisbecausetheproposedhighwayimprovementsassociatedwiththetheNorthamptonGatewaySRFIreleaseexistingbottlenecksonthehighwaynetwork.ItwasthereforeimportantthatallreassignmenteffectswereappropriatelyrepresentedintheNSTM2ateachincrementalstageintheevolutionofthehighwaymitigation,andpriortotheresidualhighwayimpactsoftheschemeonthewiderstudyareabeingassessed.

12.5.14 Therefore,areaslocaltothedevelopment,whereimpactswouldbegreatestwerefirstconsidered:

• theSRFIaccess;

• M1Junction15,and

• thevillageofRoade;

12.5.15 Then,astrafficreassignmenteffectswereunderstoodandmodelledintheNSTM2,areasmovingoutwardswereassessed:

• M1Junction15A;

• theA508corridor,includingBlisworthRoadandKnockLane;

• impactsnorthoftheM1includingtheA45;and

• theA5076corridor.

Page 23: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 23

12.5.16 ThetransportmodellingassessmentprocesshasresultedinasignificantbodyofworkthatispresentedatChapters7to10oftheTAandinthefollowingTechnicalNotes:

• TN5-M1Junction15(includingA45improvements)(TAAppendix10)

• RoadeBypassOptionsReport(TAAppendix20)

• TN6-M1Junction15A(TAAppendix11)

• TN7-A45QueenEleanorGyratory&WoottonInterchange(TAAppendix12)

• TN8-A508Corridor(TAAppendix13)

• TN9-LaybySurveys(TAAppendix14)

• TN10-ImpactsnorthoftheM1includingtheA45corridor(TAAppendix15)

• TN10A-ImpactsnorthoftheM1includingtheA45corridor(Addendum)(TAAppendix16)

• TN11-ImpactsatjunctionsalongtheA5076corridor(TAAppendix17).

12.5.17 Collectively,thisbodyofworkidentifiedthestudyareaagreedwiththeTransportWorkingGroupformoredetailedassessment.ThestudyareaisshownatFigure6.1oftheTA,andcomprisesthefollowingjunctions:

1.M1Junction15

2.M1Junction15A

3.A508/SRFIaccess

4.A45/C67WateringLanepriority-controlledT-junction

5.A508/Blisworth(Courteenhall)Roadpriority-controlledT-junction

6.A508NorthamptonRoad/RoadeBypassroundabout

7.BlisworthRoad/KnockLane/RoadeBypassroundabout

8.A508StratfordRoad/RoadeBypassroundabout

9.A508/C26RookeryLane/C26AshtonRoadstaggeredcrossroads

10.A508/C85PuryRoadghostislandpriority-controlledT-junction

11.C27StokeRoad/KnockLanepriority-controlledT-junction

12.A45WoottonInterchange

13.A45QueenEleanorInterchange

14.A45BrackmillsInterchange

15.A45BarnesMeadowInterchange

16.A45/A43LumbertubsInterchange

17.A45GreatBillingInterchange

18.A5076DanesCampWay/A5076MereWay/TowcesterRodgyratory

19.A5076DanesCampWay/HunsburyHillAvenue/HunsbarrowRoad/HunsburyHillRoadroundabout

20.A5076DanesCampway/A5123UptonValleyWay/A5075UptonWaygyratory

21.A4500WeedonRoad/A5076UptonWay/Tollgateroadgyratory

22.A5123StPetersWay/A508BridgeStreet/A5123VictoriaPromenadegyratory

23.A5123StPetersWay/A4500StPetersWay/A508HorseshoeStreet//TowcesterRoadgyratory

Page 24: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 24

24.A508/NorthamptonRoad(inRoade)

25.A508/HydeRoad(inRoade)

26.A508/HighStreetminiroundabout(inRoade)

27.HighStreet/CourteenhallRoad/NorthamptonRoad(inBlisworth)

12.5.18 Inaddition,theforecasttrafficflowschangeonKnockLaneandBlisworthRoad(Roade),andontheA508adjacenttoGraftonRegisarealsoconsidered.

12.5.19 Wherecapacityremains,andajunctionorlinkcontinuestoperformwithincapacity,thenthedegreetowhichsparecapacityiserodedbythedevelopmentisnotrelevant.Wherejunctionsarealreadyovercapacity,orwouldbetakensobythedevelopment,thenthepotentialeffectsoftheschemeareassessed.Thesewouldmanifestthemselvesintheformofincreasedqueuinganddelaystoexistingtraffic,whichwouldallbeadverseimpacts.Wherejourneytimesareshortenedorqueuesreducedbecauseoftheimprovementworks,thentheimpactswouldbebeneficial.

12.5.20 Otherconsiderationssuchasroadsafetymayalsobeimpactedupon,sothisaspectisalsoconsideredasapotentialeffectaswellashighwaycapacity.

12.5.21 Inadditiontotheabove,andinaccordancewiththeDMRBVolume11,thepotentialenvironmentaleffectsassociatedwiththenewtransportinfrastructurefallunderthreegeneralheadings:

a)Disruptionduetoconstruction;

b) Operationalimpactonpedestrians,cyclists,equestriansandthecommunity(termedpedestriansandothers),asfollows:

¶ Journeylengthandlocaltravelpatterns–definedasboththedistancetravelled,andtimetaken,forpedestriansandothers;

¶ Amenity-definedastherelativepleasantnessofajourneyforpedestriansandothers;

¶ Severance-definedastheseparationofresidentsfromfacilitiesandservicestheyusewithintheircommunity,causedbyneworimprovedroadsorbychangesintrafficflows.

c)Operationalimpactonvehicletravellers,asfollows:

¶ Driverstress-definedastheadversementalandphysiologicaleffectsexperiencedbyadriverpassingthrougharoadnetwork;and

¶ Viewfromtheroad-definedastheextenttowhichtravellers,includingdrivers,areexposedtothedifferenttypesofscenerythroughwhicharoutepasses.

Page 25: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 25

12.6 DESIGN OF PROPOSED DEVELOPMENT

12.6.1 TheProposedDevelopmentwillprovideimprovedroadaccess,improvementstopublictransportservices,andimprovedfacilitiesforpedestriansandcyclists.Unlessotherwisestated,alldrawingsreferredtointhissectionareseparateapplicationdocumentsandarereferredtobytheappropriateDCOdocumentnumber.

12.6.2 ThescopeofthedesignworkstobesubmittedwiththeDCOapplicationhasbeenagreedwithTransportWorkingGroup,assetoutinTN4(TAAppendix9).

Highway mitigation strategy 12.6.3 ThebaselineconditionsconcludethattheconstrainedgeometryofM1Junction15andhightraffic

demand,particularlyduringpeaktime,meansthatthejunctionisoftenveryheavilycongestedandanexistingbottleneckfortrafficusingtheA508andA45.TheassessmentworkpresentedinChapters7and8oftheTAconfirmedthatexistingcongestionatM1Junction15wouldworsenwithbackgroundtrafficgrowthand,withoutmitigation,thejunctionperformancewoulddeterioratefurtherwiththeadditionofthedevelopmenttraffic.

12.6.4 TheneedforasignificantandcomprehensiveimprovementschemeatM1Junction15wasthereforeidentifiedasarequirementfortheproject.Inaddition,duetotheexistingconditionsatRoade,withtheA508bisectingthevillageandtheexistingcongestionissuesatthemini-roundaboutandthenarrowrailwaybridge,itwasdeterminedthattheincreasesintrafficpassingthroughthevillagebecauseofthedevelopmentproposalswouldnotbeanacceptableimpact(TAChapter7).Therefore,inconsultationwithNCC,anearlyconceptforthehighwaymitigationstrategywastheinclusionofanewRoadeBypasstotakethrough-traffic,particularlyHGVs,outofthevillage.ItwasconsideredthataRoadeBypasswouldalsobeimportantindrawingdevelopmentandbackgroundtrafficbackontotheA508andawayfromlocalruralroutesthatareusedasanalternativetotheA508duetotheconstrainednatureoftheroadasitpassesthroughRoade.

12.6.5 Theoverallpackageofhighwaymitigationworksevolvedfromthisstartingpoint.TheassessmentprocessisdescribedinfullatChapter6oftheTA.Itfollowedaniterativedesignandassessmentmethodology,usingtraditionalassessmentbasedontheobservedtrafficcountdata,strategicmodellingusingtheNSTM2,anddetailedtransportmodellingincludingVISSIMmicrosimulation.ThelatteridentifiedtheneedforanimprovementschemeatM1Junction15A.

12.6.6 Akeyfinding,reportedinChapter8oftheTA,ofthecombinedimpactoftheproposedimprovementworksatM1Junction15andtheA508RoadeBypass,isthatexistingtrafficisforecasttobedrawnbackontotheSRNandprincipalroadnetwork,particularlytheA508.Thisisabeneficialimpactsincethesearetheroadsmostsuitedforthattrafficandthereisaconsequentialreductionintrafficonthesurroundinglocalroadsandsomeofthesurroundingvillages(seeparagraphs12.7.56and12.7.59).However,toensurethattheA508canaccommodatethetrafficincrease,aseriesofimprovementsareidentifiedalongtheroadaspartoftheproposedA508routeupgrade.

Page 26: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 26

12.6.7 TheresultingoverallhighwaymitigationstrategyisshowndiagrammaticallyatdrawingNWG-BWB-GEN-XX-SK-C-SK28-S1-P10oftheTAandcomprisesthefollowing:

A508 SRFI access• ConstructionofanewroundaboutontheA508NorthamptonRoadtoserveastheaccessto

theDevelopment,configuredtorequirealldepartingHGVstotravelnorthtoM1Junction15;and

• DuallingoftheA508carriagewaybetweenthenewsiteaccessroundaboutandM1Junction15.

Bypass Corridor • ConstructionofanewBypasswestofRoadebetweentheA508NorthamptonRoadtothe

northofRoadeandtheA508StratfordRoadtothesouthofRoade,includingafourarmroundaboutconnectingtheBypasstoBlisworthRoad;

Highway mitigation works/measures• SignificantenlargementandreconfigurationofM1Junction15;

• WideningoftheA45tothenorthofM1Junction15andthesignalisationoftheWateringLanejunction;

• AlterationofM1Junction15AtoprovideanadditionallaneandsignalisationontheA43northboundapproach,signalcontrolandadditionalflaredlaneontheA43eastboundapproach,anadditionallaneontheA5123southboundapproachandcirculatorycarriagewaywidening;

• 7.5Tenvironmentalweightrestriction(withaccesspermittedforloading,thatwouldcomplementexistingrestrictions:

¶ throughoutRoade;

¶ alongKnockLane/BlisworthRoadbetweenRoadeBypassandStokeRoad;

¶ alongBlisworthRoad(CourteenhallRoad)betweentheA508andHighStreet,includingpartsofBlisworth;

¶ alongtheunnamedroadbetweentheA508andQuinton;

¶ throughoutStokeBruerneandShutlanger;and

¶ Wootton&EastHunsbury,tothewestoftheA45,eastofTowcesterRoadandsouthoftheA5076.

• AlterationsatkeylocationsalongtheA508aspartofan‘A508routeupgrade’;comprising:

¶ Blisworth(Courteenhall)Roadjunctionimprovement;

¶ C26RookeryLane/AshtonRoadjunctionimprovement;

¶ C85PuryRoadjunctionimprovement;

¶ C27StokeRoad/KnockLanejunctionimprovementandadditionalwideningtoKnockLane/BlisworthRoad(althoughnotontheA508,thisisrequiredasaresultofchangingtrafficvolumesontheA508);and

¶ ProvisionofapedestriancrossingatabusstopandghostislandinGraftonRegis.

Page 27: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 27

12.6.8 AfinancialcontributionwillalsobeprovidedtoNCCfor:

• capacityimprovementschemesattheA45QueenEleanorInterchangeandatjunctionsalongtheA5076,extendingbetweentheA45andA5123;and

• aKnockLaneandBlisworthRoadmaintenanceandminorworksfund,tobeusedintheeventthattheincreaseduseoftheroadsshouldadvancetheneedformaintenanceorotherremedialworks.

Site access12.6.9 AccesstotheProposedDevelopmentwouldbetakenfromanewroundaboutontheA508that

runsalongsidetheeasternboundarytothemainsite.Theapproximately500msectionoftheA508betweenthesiteaccessroundaboutandM1Junction15wouldbeupgradedtoprovideadualcarriageway.Thiswouldcomprisetwolanesinthesouthbounddirectionandthreelanesinthenorthbounddirection.ThegeneralarrangementoftheproposedsiteaccessjunctionisshownonDCOHighwayPlans2.4B.

12.6.10 AnintegralpartoftheaccesslayoutistheprovisionofasegregatedleftturnlanefortraffictravellingnorthboundtoM1Junction15.Theroundaboutwillincludeaheightbarrier(withintheprivateestateroad)topreventHGVsturningrightattheroundabout,therebyrequiringallHGVsdepartingthesitetotravelnorthontheA508andaccessthewiderhighwaynetworkviaM1Junction15.

12.6.11 ThisphysicalenforcementofthesiteaccesslayoutwillbesupportedbytheinstallationanduseofAutomaticNumberPlateRecognition(ANPR)enforcementcamerasonthesiteaccessarmoftheroundaboutandontheA508tothesouthoftheaccessroundabout.ThecameraswillrecordthenumberplatesofalldepartingHGVsandthesewillbematchedwiththenumberplatesofHGVstravellingsouthboundontheA508.HGVdriversfoundtobedisregardingtheHGVrightturnban,forexamplebyU-turningatM1Junction15,willthusbeidentifiedandtherelevantsiteoccupiersubjecttoanenforcementregime.

M1 Junction 15 and A45 major upgrade12.6.12 ThegeneralarrangementfortheM1Junction15andtheA45majorupgradeareshownonDCO

Highway Plans 2.4A and 2.4B. Theworksconsistofthefollowingelements:

• Enlargementofboththenorthernandsoutherndumbell‘roundabouts’;

• RealignmentandwideningontheA45approachtothejunctiontoprovidefivelanes;

• SignalisingandwideningoftheSaxonAvenueapproachtothejunction;

• LongersectionofthreelanesontheM1northboundoff-slip,wideningtofivelanesatthestopline;

• DuallingoftheA508approachandexit,withfivelanesprovidedatfortheA508northboundatthestopline;

• Acut-throughforM1northboundtraffictotheA45;

• WideningontheM1southboundoff-sliptoprovidesixlanesatthestopline;

• A45northboundwidenedtoprovidethreelanesfromJ15tobeyondC67WateringLanejunction;

• WateringLanejunctionwiththeA45signalised;

• ChangetothespeedlimitonthissectionoftheA45tobecome50mph;

• Removalofthenorthboundparkinglay-by;and

• Removaloftwobusstoplay-bys,withareplacementbusstopprovidedonC67WateringLane.

Page 28: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 28

12.6.13 Thelayoutwouldalsoincludeimprovedroutesforpedestriansandcycliststravellingacrossthejunction,whowouldbeprovidedwithtrafficsignalcontrolledfacilitiesateachcrossinglocation.Furtherdetailsareprovidedatparagraphs12.6.33.

12.6.14 TheschemehasbeendevelopedwithregardtothecommittedM1J13toJ16SmartMotorwayProject(SMP),whichisduetobeconstructedbetweenJune2018andMarch2022.

12.6.15 ItisunderstoodandagreedwiththeTransportWorkingGroupthattheSRFIschemeneedstoincludefortheeventualitythattheSMPisnotconstructedorismateriallydelayed.InthiseventualitythegeneralarrangementforM1Junction15asshownonDCOHighway Plans 2.4T and 2.4UwouldbeprovidedinlieuoftheschemeshownontheDCOHighway Plans 2.4A and 2.4B.Ifthisweretobeimplemented,then,aswiththeproposedschemewhichincludestheSMP,theSRFIschemewouldobtainthenecessarydetaileddesignapprovalsinaccordancewiththeprotectiveprovisionswithintheDCO.

M1 Junction 15A improvement works12.6.16 TheVISSIMmicro-simulationmodellingpresentedatChapter10oftheTAanddemonstratesthat

inthe2031D1ReferenceCasescenarioexistingcongestionatM1Junction15Aisforecasttoleadtosignificantcongestionatthejunction,resultinginqueuesformingontheslipsroadsthatwouldblockbacktotheM1mainline.AsdemonstratedatChapter8oftheTAandTN6(TAAppendix11),theadditionofthedevelopmenttrafficwasshowntocausefurtherreassignmentofexistingtrafficontoalternateroutesbecauseofthiscongestion,potentiallyleadingtoimpactsatotherlocations.Therefore,animprovementschemeisproposed.

12.6.17 ThegeneralarrangementfortheproposedhighwayimprovementschemeatM1Junction15Aisasshownat DCO Highway Plans 2.4F.Theimprovementcomprisesalterationstoboththesouthernandnorthernroundabouts:

• Southernroundabout:

¶ ProvisionofanadditionalflaredlaneandsignalisationoftheA43northboundapproach;

¶ SignalisationandprovisionofashortflareontheA43eastboundapproach;and

¶ Circulatorycarriagewaywidening.

• Northernroundabout:

¶ SignalisationoftheA43northboundentry;

¶ ProvisionofanadditionalflaredlaneontheA5123approachtotheroundabout;and

¶ Circulatorycarriagewaywidening.

A508 Roade Bypass12.6.18 TheA508RoadeBypassproposalisfora100kphdesignspeedsinglecarriagewayroadaround

thewesternsideofthevillage,withfootandcycleprovisionalongthelengthoftheroute,withtreeplanting,environmentalbundingandgenerallandscaping.TheoptionsfortheproposedBypassandthereasonsfortheselectedroutearediscussedinRoadeBypassOptionsReportprovidedatAppendix20oftheTA,alongwiththereasonsfortheselectedroute.ThegeneralarrangementoftheproposedschemeisshownonDCO Highway Plans 2.4C and 2.4D.

Page 29: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 29

12.6.19 The proposals comprise:

• TheconstructionofanewhighwaylinkingtheA508NorthamptonRoadtotheA508StratfordRoad;

• TheprovisionofroundaboutjunctionsbetweentheRoadeBypassandtheA508NorthamptonRoad,A508StratfordRoadandBlisworthRoad(inRoade);

• Drainageswalesandattenuationfeatures;

• Abridgeoverthewestcoastmainlinerailway;

• AnunderpassforbridlewayRZ1/KZ10;

• Thealterationanddiversionofotherexistingpublicrightsofway;

• Theconstructionofasharedusefootwayandcycleway;and

• Environmentalmitigationbunds.

12.6.20 PassiveprovisionhasbeenmadeindesignoftheA508RoadeBypassandroundaboutjunctionstonotprejudicethefutureduallingoftheroute.

A508 corridor - route upgrade 12.6.21 AbeneficialoutcomeoftheM1Junction15andA45majorupgradeandprovidingtheA508

RoadeBypassisthatbackgroundtrafficisdrawnbackontotheA508.Therefore,inadditiontotheRoadeBypass,mitigationworksareproposedatkeylocationsontheA508corridortoensurethattherouteoperatessatisfactorilyandsafely.Therouteupgradecomprises:

• AlterationtotheA508/Blisworth(Courteenhall)RoadT-junctiontobecomealeft-inleft-outonlyjunctionthegeneralarrangementofwhichisasshowninDCOHighway Plans 2.4C. This wouldincludetherelocationoftheexistingbusstopcurrentlylocatedtothesouthofBlisworthRoadapproximately70metresfurthersouth;

• AlterationstoC27StokeRoad/KnockLanepriorityT-junctiontowidenthecarriagewayandimprovethehighwaydrainage,andadditionalwideningtoKnockLane/BlisworthRoade(Roade),thegeneralarrangementbeingasshowninDCOHighway Plans 2.4F;

• AcapacityandroadsafetyimprovementschemeattheA508/C26RookeryLane/C26AshtonRoadcrossroadstoprovideasinglelaneduallingstaggeredcrossroads,thegeneralarrangementbeingasshowninDCO Highway Plans 2.4E;

• AlterationtotheA508/C85PuryRoadghostislandT-junctiontoincreasethestorageareafortrafficturningrightfromtheA508thegeneralarrangementbeingasshowninDCOHighway Plans 2.4F;and

• AnewpedestrianrefugeontheA508atGraftonRegistoassistwithcrossingtothenorthboundbusstop,andprovisionofarightturnharbouragefacilityfornorthboundtrafficfromtheA508turningintoChurchLane,thegeneralarrangementbeingasshowninDCOHighway Plans 2.4F.

Speed limits 12.6.22 Tocomplementthechangesinroadlayouts,somechangestotheexistingspeedlimitsare

proposedontheA45andA508.TheproposedchangesareshownattheDCOSpeed Limit Plans 2.7A, 2.7B, 2.7C, and 2.7D.

12.6.23 Ingeneral,theproposedchangestothespeedlimitswillprovidea50mphspeedlimitontheA45fromthevicinityoftheGrangeParkmerge,throughtoM1Junction15andalongtheA508asfarastheRoade.

Page 30: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 30

HGV routing strategy and environmental weight restrictions12.6.24 TheApplicantrecogniseslocalsensitivitiesregardingthepotentialfortheSRFItoincreaseHGV

movementsonthelocalroadssurroundingthemainsite.Asdescribedatparagraphs12.6.9to12.6.11theproposedsiteaccessontheA508wouldbeconfiguredtorequirealldepartingHGVtraffictotravelnorth,supportedby(ANPR)camerasandanenforcementregimetodeterU-turningmovementsatM1Junction15.

12.6.25 Thissystemwouldbeoperational24hoursadayandwouldminimisedevelopmentHGVimpactstothesouthofthesite.DuringperiodswhentheA508southboundwasrequiredtofunctionasadiversionrouteitwouldbepossibletotemporarilylifttherestrictionsandallowHGVtraffictofollowthediversionroutewithoutpenalty.HGVrightturnmovementswouldbefacilitatedbyraisingtheheightrestrictionatthesiteaccessandnoenforcementoftheANPRcameraswouldbemade.However,thiswouldonlyoccurfollowingnotificationfromthehighwayauthoritiesofanofficialdiversionrouteusingtheA508southbound,asdescribedatChapter3oftheTA.

12.6.26 Thefollowing7.5Tenvironmentalweightrestriction(withaccesspermittedforloading),asshownontheDCOTraffic Regulation Plans 2.6, 2.6A and 2.6B,areproposedonthelocalroadstothesouthandnorthoftheSRFIsite:

• throughoutRoade;

• alongKnockLane/BlisworthRoadbetweenRoadeBypassandStokeRoad;

• alongBlisworthRoadandCourteenhallRoadbetweentheA508andHighStreet,includingpartsofBlisworth;

• alongtheunnamedroadbetweentheA508andQuinton;

• throughoutStokeBruerneandShutlanger;and

• Wootton&EastHunsbury,tothewestoftheA45,eastofTowcesterRoadandsouthoftheA5076.

12.6.27 Thesemeasures,incombinationwiththeconfigurationoftheSRFIaccessandANPRcameraenforcement,andexistingenvironmentalweightrestrictions,willrestrictHGVthroughtrafficfromaccessingunsuitablelocalroads,manyofwhichpassthroughthesurroundingvillages.HGVsarrivingattheSRFIfromthesouthwillberestrictedtousetheA508,includingtheA508RoadeBypass,anddepartingHGVswillberequiredtoexittheSRFIsitetothenorthviatheA508andM1Junction15.TheproposedenvironmentalweightrestrictionsinWoottonandEastHunsburywillrestrictHGVsfrompassingthroughtheseresidentialareas.

Walking and Cycling 12.6.28 ThewalkingandcyclingstrategyfortheProposedDevelopmentareshownonDCOHighway

Plans 2.4, 2.4A to 2.4FandontheDCOAccess and Rights of Way Plans (ARoW), 2.3, 2.3A to 2.3E,andtheIllustrative Masterplan (DCOdocument2.11.TheproposedchangestothePRoWonnon-motorisedusers(pedestrian,cyclistsandequestrians)aredescribedinthefollowingsections.

12.6.29 TheProposedDevelopmentwillprovidenewwalkingandcyclinginfrastructureconnectingthemainsitewiththeexistingnetworksinCollingtree,NorthamptonandRoade.

Page 31: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 31

12.6.30 TheA508SRFIaccessroundaboutisshownonDCOHighwayPlans2.4BandDCOARoWPlans2.3C.TheaccesswouldprovideacontrolledcrossingforpedestriansontheA508northernarmoftheroundabouttofacilitateaccesstothenewsouthboundbusstop.AcontrolledcrossingwouldbeprovidedforpedestriansandcyclistsonthesegregatedleftturnexitlaneoftheSRFIsiteaccessarm,withuncontrolledcrossingsprovidedontherightturnexitandentryarmtotheSRFIsite.Asharedusefootway/cyclewaywouldbeprovidedrunningaroundtheroundaboutandconnectingintothesiteaccess.Thefootway/cyclewaywouldextendtoconnectwiththenewnorthboundbusstopsthatisproposedtothesouthofthesiteaccessroundaboutontheA508.

12.6.31 Itisproposedtoextendthisnewfootway/cyclewayalongsidethewestsideoftheA508linkingthesiteaccessroundaboutandRoadeandtheproposedfootway/cyclewayfacilitytobeprovidedalongsidethewesternsideoftheBypass.Whentakentogether,theproposalswouldprovideanewfootway/cyclewayconnectingRoadewiththesiteandtheexistingNorthamptonfootway/cyclewaynetworktothenorth.

12.6.32 AtthejunctionwiththeunnamedroadtoQuinton,arefugewouldbeprovidedontheA508toassistcyclistswishingtocrosstoandfromtheunnamedroad.ThiswouldprovidealinkwithNationalCycleNetworkRoute6,whichisaccessiblefromQuinton.

12.6.33 AsshownonDCOHighwayPlans2.4Band2.4CandDCOARoWPlans2.3Cand2.3BandtheIllustrativeMasterplan,anewsharedusefootway/cyclewayisproposedtothenortheastofthemainsite.ThiswouldbeprovidedalongthewesternsideofthedualledsectionoftheA508betweenthesiteaccessroundaboutandM1Junction15.AsecondpedestrianandcycleaccesstotheSRFIisproposedmidwayalongthissectionoftheA508,providingdirectaccesstothemaindevelopmentspineroad.Thenewfootway/cyclewaywouldconnectwiththeexistingfootway/cyclewayfacilitiesatM1Junction15,whichwouldbeimprovedtoprovidetrafficsignalcontrolledfacilitiesateachcrossinglocation.AnewsharedusepedestrianandcyclistlinkisproposedfromM1Junction15linkingwithWateringLanetothenorth.

12.6.34 ItisproposedtosignalisetheC67WateringLanejunctionwiththeA45,withpedestriancrossingstoassistpedestriansandcyclistsaccessingthefacilityonthenorthernsideofWateringLane.Inaddition,anuncontrolledcrossingisalsoproposedbetweenthehotelandthefootwayonthenorthernsideofWateringLane.

12.6.35 WithintheNorthamptonGatewaySRFIsite,sharedfootway/cyclewayswouldprovideaccesstoeachofthewarehousedevelopmentplotsandRailTerminal.PublicfootpathsKX17andKX13thatcrossthemainsitewouldbedivertedandextendedtoformaloopwithinthelandscapebunding.Partofthedivertedroutewouldbeupgradedtoprovideacycletrack(forusebypedestriansandcyclists)thatwouldlinkthebridgeovertheM1atCollingtreewiththenewfacilityadjacenttotheA508andtheimprovedfacilitiesatM1Junction15.

12.6.36 ThecyclepathwouldextendwithinthemainsitetothesouthoftheSRFIaccessroundabout,therebyprovidingcycleaccesstoZoneA4ofthemainsite.TothesouthofZoneA4apublicfootpathwouldcompletethenewlooparrangementlinkingwiththeexistingpublicfootpathandbridgeovertheWestCoastMainlinerailway.ThechangestothePRoWareshownontheDCOARoWPlans2.3Ato2.3EinconjunctionwiththeIllustrativeMasterplan.

12.6.37 TothenortheastoftheSRFIsite,acycletrack(forusebypedestriansandcyclists)wouldconnectthedevelopmenttoCollingtree,andthewiderNorthamptonarea,viatheexistingbridgeovertheM1.Aprivatefootway/cyclewaywouldalsoconnectdirectlyfromthebridgetothemainspineroad,providingdirectaccessintothedevelopmentfromCollingtreeandNorthamptonbeyond.TheseproposalsareshownontheIllustrativeMasterplanandontheDCOARoWPlans2.3Aand2.3B.

Page 32: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 32

12.6.38 ThereareseveralPRoW,includingfootpathsandbridleways,inandaroundRoade.PRoWKZ30,KZ19,KZ2a,RZ3andKZ10/RZ1andRZ6locatedonthewesternsideofRoadewouldbeaffectedbytheproposedRoadeBypassasshownontheDCOARoW Plans 2.3D and 2.3E. The scheme wouldmaintainaccessandconnectionsforpedestrians,cyclistsandequestriansusingthesePRoW.

12.6.39 AtgradecrossingsareproposedonallthreearmsoftheRoadeBypass/A508NorthamptonRoadroundabout.AsshownonDCOHighway Plans 2.4DandARoW Plans 2.3D,newfootwayswouldbeprovidedadjacenttotheroundabouttomaintainthefootpathlinkbetweenPRoWKZ30andKZ19.

12.6.40 FurthersouthalongtheBypass,publicfootpathKZ2a,whichrunstothewestoftheWestCoastMainlinerailway,isproposedtobediverted.Anuncontrolledcrossingwithrefugeislandisproposedtocrossthecarriagewayandconnectwiththesharedfootway/cyclewayontheeasternedgeoftheRoadeBypass.

12.6.41 AroundaboutjunctionisproposedtoconnectBlisworthRoad(inRoade)withtheRoadeBypass.Asharedusefootway/cyclewaywouldbeprovidedaroundthenorthernarmoftheBypass,withanatgradecrossingoftheroad.Thiswouldlinkwiththeproposedfootway/cyclewayprovidedalongtheeasternsideoftheBypassandensurepedestriansandcyclistscouldcontinuetoaccessKnockLane.

12.6.42 Thetwo-wayAADTforthenorthern(busier)sectionoftheA508RoadeBypasswouldmeanthatanat-gradecrossingwouldbe‘notnormallyappropriate’.Itisthereforeproposedtoprovideacentralrefugeislandatbothcrossingpointswhichwouldresultinanat-gradecrossingbeingassessedas‘potentiallyappropriate’.Giventhepredictedpedestrianflowsforthecrossingsarelowthisisconsideredacceptable.

12.6.43 FurthersouthalongtheRoadeBypassitisproposedtoprovideanunderpasscrossingforbridlewayRZ1/KZ10beneaththeBypass,thiswouldlinkbridlewayKZ10withRZ1asshownonDCOARoW Plans 2.3D. AnunderpassisconsideredmoreappropriatethanatgradecrossingoftheRoadeBypass,giventheproximityofthebridlewaytostablesatDovecoteFarmanditsknownusebyequestrians(alsoseeWCHAR1,TAAppendix18).

12.6.44 Afootway/cyclewaylinkisalsoproposedbetweentheRoadeBypassandthebridlewaysKZ10/RZ1.TheproposedunderpasslayoutanddesignisshownonDrawingNGW-BWB-SBR-R-DR-CB-0001-S4-P1 includedwithintheTA.Itwouldprovidea4mwidex3.7mhighunderpass(3.8mminus0.1msurfacing).ThisaccordswithguidancepublicisedbytheBritishHorseSocietyandalsotheDMRB.

12.6.45 TheproposedBypasscrossespublicfootpathRZ3.Anatgradeuncontrolledcrossingwithrefugeislandisproposedtomaintainthefootpathinaneast/westdirection.

12.6.46 Anat-graderoundaboutisproposedtothesouthofRoadetoconnectRoadeBypasstotheA508StratfordRoad,asshownonDCOARoW Plans 2.3E.Atgradecrossingsareproposedontheeasternandsouthernarmsoftheroundabout.OnthewesternsideoftheA508,alongthesouthernarmoftheroundaboutafootway/cyclewayisproposedtolinktobridlewayRZ6.

12.6.47 TheproposedschemeinvolvesalterationtotheA508/BlisworthRoad(Courteenhall)T-junctiontobecomealeft-inleft-outonlyjunction.ThiswouldincludetherelocationoftheexistingbusstopcurrentlylocatedtothesouthofCourteenhallRoad,approximately70metresfurthersouth.ThereiscurrentlyafootwaywhichrunsalongthewesternedgeoftheA508fromnorthtosouthpastthejunction,whichwouldbeupgradedtoprovideasharedusefootway/cyclewayaspartofthenewfacilitylinkingRoadewithM1Junction15.

Page 33: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 33

12.6.48 AtGraftonRegisanewpedestrianrefugeisproposedontheA508toassistpedestrianswithcrossingtheroadtothenorthboundbusstop.ThroughGraftonRegisthereisafootwayonbothsidesoftheA508,thesearetobemaintained.

12.6.49 TheproposalshavebeensubjecttoaWalking,Cycling&Horse-RidingAssessmentReviewinaccordancewithHD42/17.TheAssessmentReport(WCHAR1)isprovidedatTAAppendix18andtheReviewReport(WCHAR2)isprovidedatTAAppendix19.Allopportunitieshavebeenreviewedagainsttheschemeproposalsandhavebeenpositivelyaddressed.Wherenecessary,changestotheschemehavebeenincorporatedwithinthedrawingsaccompanyingtheDCO.

Public Transport Strategy12.6.50 Publictransportwillplayanimportantroleinprovidingaccessforstaffcomingtothesiteandthe

strategyforthedevelopmentisdescribedindetailinthePTSreportprovidedatTAAppendix2.

12.6.51 ThePTSincludestheintroductionofanewbusservicespecificallytoservethemainsite,aswellasbuildingontheexistinglocalbusnetworkthroughprovisionofadditionalcapacityandimprovedinfrastructure.ThePTShasemergedfromdiscussionwiththelocalbusoperator(Stagecoach)andthepublictransportofficersatNCC

12.6.52 Thefocusofthestrategyis:

• Thedevelopmentofanewbusserviceto/fromtheNorthamptonGatewaySRFIsitetoNorthamptonTownCentreandassociatedinfrastructure;and

• NewbusstopsontheA508,givingaccesstothesiteforthe33/33a,X4andX7Services.

12.6.53 Inadditiontotheabove,theFTP(TAAppendix1)proposesaSustainableTransportWorkingGroupforthesite,ledbythearea-wideTravelPlanco-ordinator,andformedofkeystakeholders(includingNCC,publictransportoperators,carshareproviders,HighwaysEnglandetc.)andtheUnitTravelPlanCoordinators.TheirrolewillbetooverseethedeliveryoftheTravelPlan,andBusStrategy,andtoreviewchangesinprioritiesandpromotionssuggestedbythearea-wideTravelPlanCo-ordinator,dependingonrequirements.TheGroupwouldmeetbi-annuallyandcoulddevelopad-hocworkinggroupswherespecificneedsariseatcertaintimes.

12.6.54 Figure7.1ofthePTSsummarisestheexistingbusservicesthatoperatenearthesiteandtheproposednewandenhancedbusroutes.

12.6.55 ThebusservicewillbedevelopedinlinewithNCC’sadoptedBusStrategy,withregardtothe10%modalsharetargetforbus.Giventhis,thetriggerforprovidingabusjourneytothesiteisdefined,basedonNCCguidelines,as: A bus journey will be provided between the site and Northampton Town Centre when 100 employees or more start or finish work within a 15minute window (unless an existing journey is available within 30 minutes before the start of shift, or within 30 minutes of the end of shift)

12.6.56 Theendoccupier’sshiftpatterns,employeenumbersandsiterequirementsareunknownattheplanningstage,sothestrategyneedstobeflexibletoactualneed.UsingthetriggerensuresthatthePTScanberesponsiveandcandevelopabusnetworkthatisbuiltaroundactualdemand.

12.6.57 TheSustainableTransportWorkingGroupwouldalsoseektobepragmaticandproactiveasthePTSisimplemented,seekingopportunitiestofurtherdevelopthebusservicewhereverfeasible.Forexample,thegroupcouldinvestigateopportunitiestodevelopservicefrequenciesin-betweenpeaksortriggeredjourneys,toprovideamoreconsistentandregularservicethroughouttheday,whenthiscanbeprovidedatmarginalshort-termcost,orcommercially.

Page 34: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 34

12.6.58 TheproposedbusservicewouldofferdirectaccessfromthesitetoNorthamptonTownCentre.ThemostdirectroutewouldseetheservicefollowingtheA508/A45/A508toTheDrapery(orNorthGateBusStation).Aswellasservingthetowncentre,theservicecouldalsoservestopsonLondonRoad(A508).Onsite,theservicewouldutilisetheSRFIaccessontheA508,penetratethesiteservingthebusstopsonthespineroadandusetheturningcircleatthewesterlyendofthesite.One-waytraveltimewouldlikelybe20minutes,andlessintheoff-peak.GiventhejourneylengthandtherequirementofNCC’sBusStrategytohavea30minutefrequency,atwovehicleoperationcouldservethesite.TimetableswouldbedevelopeddependingonneedandexamplesareprovidedwithinthePTS.

12.6.59 Fourbusstopswillbeincludedwithinthedevelopmentsite,oneneartheentrancetothesiteandanothertwobusstopsalongtheestateroadofthedevelopment.Afinalstopwillbepositionedatthefarendoftheinternalestateroad.Thesebusstopswillensurethatemployeescommutingbybuswillnothavealongwalkfromthebusstoptotheirworkplace.Layoverfacilitieswillbeprovidedtoallowtheservicetodropoffpassengersbeforethestartoftheshiftandthenpickuppassengersfinishingtheirshift.

12.6.60 Threephasestodevelopingthestrategyareproposed,enablingittoadapttodemandthatarisesasnewoccupiersarriveonsite:

• Phase1:Introductionofthenewserviceatkeyshifttimestart/finishesfromoccupationofthefirstwarehouseunitonthesite.Thisismostlikelytobearound0600-1400-2200hours.However,itwillneedtobeflexibletotheenduser’srequirements.Whatevertheshiftpattern,publictransportwouldbeinplacefromfirstoccupationtomakeitanattractiveandrealisticalternative to the private car.

• Phase2a:Developmentoftheservicethroughtheday.Itislikelythatadditionaljourneyswillberequiredbetween0800and0900hoursandfrom1500to1800hoursfromthethirdyearofdevelopment.GiventhattheseservicesfallatpeaktimestherewillbearequirementtoaddanewbustothenetworkinNorthampton.Ratherthanprovidebusesjustatthesetimes,theSustainableTransportWorkingGroupshouldinvestigatetheopportunityofcontinuingthebusserviceinbetweenpeaks,potentiallyatmarginalcosts,thereforebeginningtodeveloparegularserviceforusersthroughouttheday.

• Phase2b:asthesitedevelops,therewillbetheneedtoextendtheoperatingtimesoftheservicefrom0700to0900hoursand1400to1900hours.

• Phase3:Increasetheservicefrequencyfromhourlytohalfhourlyasdemandgrowsduringthepeaktimes,asecondbuswouldbeaddedtothetimetabletoofferhalfhourlyfrequencyatcertain times.

12.6.61 Theinitialbusserviceaimedatkeyshiftchange-overtimeswouldbeinplacefromoccupationofthefirstwarehouseunit.Followingthis,thetriggerpointswouldbeinlinewithNCC’sadoptedPublicTransportStrategyrecognisingthe10%mode-shareforpublictransport.

12.6.62 NewbusstopsandlaybyswouldalsobecreatedontheA508eithersideofthenewsiteaccessroundabout,asshownonHighway Plans 2.4C,andacontrolledcrossingprovidedonthenorthernA508armoftheroundabouttoprovidedirectandsafeaccesstothesouthboundbusstop.ThiswouldprovideaccesstoanhourlyserviceineachdirectionbetweenMiltonKeynesandNorthampton.

12.6.63 Byofferingregularandreliableservices,atappropriatetimes,publictransportbecomesaviablealternativetotheprivatecarfromthepointoffirstoccupation.IncombinationwithpromotionthroughthesiteTravelPlan,thiswillmaximisethepotentialforusebyemployeesasthesitegrows.

Page 35: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 35

Road Safety 12.6.64 AlloftheproposedhighwaymitigationworkshavebeenbethesubjectofaStage1RoadSafety

Audit(RSA)inaccordancewithHD19/15(TAAppendix30).

12.6.65 AllrecommendationsidentifiedwithintheRSA1reporthavebeenconsideredwithintheResponseReport(TAAppendix31).Allrecommendationshavebeenaddressedand,wherenecessary,changestotheschemehavebeenincorporatedwithinthedrawingsaccompanyingtheDCO.

Parking Provision12.6.66 ParkingwillbeprovidedatthemainsiteinaccordancewithNCC’slatestparkingstandards

(September2016).

12.6.67 TheIllustrativeMasterplandemonstratesthatcompliancewiththeseparkingstandardscanbeachievedandissummarisedatTable4.1oftheTA.

12.6.68 AdditionalHGVparkingwillalsobeprovidedintheformofasecure,dedicatedHGVparkingareaofapproximately120spaces.ThiswillincludedriverwelfarefacilitiestomeettheneedsofHGVdriversvisitingthesiteorintermodalterminal.

12.6.69 AspartoftheFTP(TAAppendix1)carsharingwillbeactivelypromotedandtoencouragethis8%(approx.320spaces)ofthetotalcarparkingspaceswouldbemarkedforthosecarsharing.Thesespaceswouldbesplitbetweentheunitsandlocatednexttotheentrancetothebuildings.

12.6.70 Toencouragetheuseofelectricvehicles5%(approx.200spaces)ofthetotalcarparkingspacesprovidedwillincludeelectricchargingpoints,withpassiveprovisionprovidedforafurther5%ofthe total provision.

Page 36: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 36

12.7 RESIDUAL EFFECTS

Disruption Due to Construction 12.7.1 Theoverarchingsystemsandcontrolsthatwouldbeadoptedduringtheconstructionofthe

ProposedDevelopmentandassociatedhighwaymitigationworkstominimiseanyadverseenvironmentalimpactsaresetoutintheprovisionsoftheDCOandaredetailedwithintheConstructionEnvironmentalManagementPlan(CEMP),appendedtoChapter2ofthisES.

12.7.2 TheCEMPprovidestheframeworkwithwhichallPhasespecificConstructionEnvironmentalManagementPlans(P-CEMPs)requiredforeachphaseofdevelopmentbyDCORequirements,mustaccord.

12.7.3 TheexactnumberofP-CEMPswilldependontheprecisesplitofphasesofworkwhichhasyettobeconfirmed.However,itisanticipatedthatP-CEMPswillbeprovidedfor:

• Mainsite;

• Railwayinfrastructure;

• TheRailterminal;

• Eachphaseofthehighwayworks;and

• Eachphaseofwarehousedevelopment.

12.7.4 TheIndicativeMasterProgrammeisprovidedatAppendix2oftheCEMP.Itbreaksdowntheconstructionworksintotwokeycomponents,aslistedbelow:

• Highwayworks;

¶ M1J15&A45majorupgradeandlinktositeaccess;

¶ M1J15Aimprovements;

¶ RoadeBypass/A508improvements;

• MainSiteConstruction;

o Bulk earthworks (Phase 1 and 2);

o Landscaping (Phase 1 and 2);

o Road Construction (Phases 1 to 3);

o Construct Rail Terminal; and

o Buildings.

12.7.5 TheIndicativeMasterProgrammeincludestheindicativeconstructionprogrammeshowingtheaboveworkcomponents.Theworkswouldbephasedovera5.5yearperiod.

12.7.6 Priortooccupationofthefirstbuildingonthesite,thefollowingworkswillhavebeencompleted:

• A508SRFIaccessandduallingbetweenthesiteaccessandM1Junction15;

• M1Junction15andA45majorupgrade;

• Landscapingphase1;

• Onsiteroadconstructionphase1;and

• RailTerminal(‘terminal’asshowninboxa)ofDocument2.8.

Page 37: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 37

12.7.7 TheconstructionoftheA508RoadeBypasswillbegovernedbythemethodologyandavailabilityofpossessionsforthebridgeovertheWCML.TheotherhighwayworksontheA508areassociatedwiththetimingoftheconstructionoftheA508RoadeBypassandwillbecompletedpriortotheopeningoftheA508Bypasstotraffic.

12.7.8 TheA508RoadeBypasswillbedeliveredassoonasispracticable,andnolaterthan2yearsfollowingfirstoccupationofthesite.However,duetotheconstructiontimenecessaryforthebypass,andtimingrestrictionsassociatedwithinstallingthebridgeovertheWCMLrailway,itwouldnotbeinplacepriortotheopeningofthedevelopment.

12.7.9 TheM1Junction15AimprovementswillbecompletepriortotheopeningoftheA508RoadeBypass.However,itcannotbeconstructedatthesametimeastheM1JunctionJ15andA45majorupgradeandSRFIaccesstoavoidworkingontwoadjacentmotorwayjunctionsconcurrently.

12.7.10 AcombinationofappropriatetemporarydiversionsandclosurestoPRoWwillbeimplementedbeforethecommencementofanycomponentofworksanddetailsshallbesetoutinP-CEMPswhereappropriate.Allpermanentrouteswillbeconstructedandimplementedassoonaspractical.

12.7.11 Theaboveconstraintsandotherpracticalrestraintsregardingtheoff-siteworksaresetoutintheCEMP.However,theimportanceofmanagingthephasingofthecomponentstomitigatedelaysanddisruptionontheexistinghighwaynetworkisrecognisedasthemostsignificantpracticalrestraint.

12.7.12 Generally,thisisbestachievedbydivertingtrafficontonewalignmentsawayfromworksunderconstructionandcontrollingthelevelofinterferenceonthenetworksatanytime.TheIndicativeMasterprogrammeplansthehighwayworksatM1Junction15andA45andtheRoadeBypassandA508improvementstobecarriedoutsequentially,butsomeoverlapofthelatterwiththeM1Junction15AshouldbepossiblefollowingthedetaileddesignandwithagreementfromHighwaysEnglandandNorthamptonshireCountyCouncil.

12.7.13 Constructionworkwithinthedevelopmentsitewouldbeconfinedtothefollowing:

• 07:00-19:00hoursMondaytoFriday;

• 07:00-13:00hoursSaturday.

12.7.14 Alldeliveryvehiclesandplantarrivingandleavingthesitewouldalsocomplywiththesametimerestrictions,althoughsitepersonnelwouldbepermittedtoaccessthesiteshortlybeforethesehoursandexitthesiteshortlyafterthem.ConstructionworkoutsidethedevelopmentsitewillrequirenightworkingtocomplywiththerequirementsofHighwaysEngland,orforpracticalandsafety reasons.

12.7.15 NoworkswillbeundertakenonSundaysorpublicholidays,saveinexceptionalcircumstancesonlyandwithpriornotification.

12.7.16 Accessandegresstoeachpartoftheoff-siteconstructionworkswouldbeviaametalledaccessroadjoinedtothepublichighway.Accesstothemainsiteduringtheearlierstagesoftheconstructionprocesswouldbeviaanewtemporaryghostislandpriority-controlledT-junctionconstructionontheA508.ThegeneralarrangementofthisisshownatDrawingNGW-BWB-GEN-XX-SK-C-SK07-S3-P4providedwithintheTA.WhilstthetemporaryjunctionisinplacethespeedlimitonthissectionoftheA508willbereducedfromderestrictedto40mphviaatemporaryTrafficRegulationOrderprovidedforintheDCO.Thetemporaryjunctionwouldbereplacedwiththesiteaccessroundaboutaspartofthesiteaccessconstructionworkspriortofirstoccupationonthemain site.

Page 38: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 38

12.7.17 TheroutingofconstructiontrafficwouldbeagreedwiththePolice,NCC,HighwaysEnglandandtheProjectManagerforeachP-CEMP.Allcontractorsshallthencomplywiththerequirementsofthatstrategy.Deliveryvehicleswouldberoutedviatheprincipalandstrategicroadnetworkstoavoideffectsonlocalresidentialareas.Noheavyconstructiontraffic,otherthanthatassociatedwiththeconstructionoftheA508RoadeBypassandA508improvementswouldbepermittedtousetheA508southofthemainsite.

12.7.18 TheimpactsoftheconstructiontrafficontheoperationofthehighwaynetworkareassessedasChapter12oftheTA.Insummary,fortheconstructionprocess,thefollowingassumptionsweremade:

• A5.5yearsconstructionperiod;and

• A10-hour,fivedayworkingweekfor49weeksperyear.

12.7.19 BasedontheconstructionprogrammeandtotalmassofmaterialrequiredforeachkeyworkscomponentidentifiedwithintheIndicativeMasterProgramme,thetotalnumbersofHGVandlightgoodsvehicle(LGV)movementshavebeenestimated.Estimatesforthenumberofconstructionworkerstravellingtothesitebycarandvanhavealsobeenmade.AdetailedassessmentisincludedintheConstructionTrafficMethodologyReport,whichisincludedatTAAppendix33.

12.7.20 AsummaryoftheestimatedaveragedailyconstructiontrafficmovementsisprovidedaTable12.4.Thisisbasedona5-dayworkingweek,assuming49workingweeksperyear.ItisthereforearobustassessmentastheaverageexcludesSaturdayworking,theinclusionofwhichwouldreducetheoveralldailytrafficmovementfiguresgiveninthetable.

12.4: Average daily construction traffic movements (one-way)

Year HGV LGV Car Vans Total1 147 33 117 157 4552 171 39 175 129 5153 125 28 86 95 3344 72 14 36 48 1705 72 14 36 48 1706 36 7 18 24 85

12.7.21 BasedonTable12.4,Year2wouldbethebusiestintermsofHGVandLGVmovementsassociatedwiththeconstructionprocess.DuringYear2itisestimatedthatanaverageof171dailyone-wayHGVmovementswouldvisitthesite,with39dailyone-wayLGVmovements.

12.7.22 Takenoverthe10-hourworkingday,theaboveone-waymovementswouldequatetosome34HGVtwo-waymovementsperhour,andaround8two-wayLGVmovementsperhour.Evenallowingfordoublingthisaveragefigure,toaccommodateshortperiodsofpeakdemand,theseflowsarelowinthecontextoftheadjacenthighwaynetworkflows,whichatM1Junction15averagearound6,300vehiclesduringeachofthemorningandeveningpeakhours.Hencetheseflowswillnotrequiremitigationworks.

12.7.23 Forconstructionworkers,whentakenintotal,thebusiestperiodforcarandvanmovementswouldalsobeYear2,whenatotalof304dailyone-waymovementsareforecast.Tounderstandthelikelyoriginsofconstructionstaff,theemployeetripdistributionhasbeenextractedfromtheNSTM2.Thishasthenbeenusedtoestablishthetrafficimpactsonthemainroutestoandfromthe site.

Page 39: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 39

12.7.24 Itisassumedthatthemajorityofstaff(80%)wouldarrivejustpriortothestartofworkat0700hoursandleavethesitejustafterat1900hours.TheresultingcumulativeadditionaltripsontheexistinghighwaynetworkaresummarisedatTable12.5.ThedetailedcalculationsareincludedatTAAppendix33.

Table 12.5: Distribution of construction staff arrival and departure trips

Route TripsA45 109M1South 50A508 37M1North 47

12.7.25 Table12.5showsthatthetrafficimpactoftheadditionaljourneysassociatedwithconstructionstaffmovementstothesiteinthemorningandfromthesiteintheeveningwouldbediluted,astheywouldbesplitacrossanumberofmainroutes.Furthermore,theoperationtimesoftheconstructionsitewouldmeanthatstaffmovementsdonotgenerallycoincidewiththehighwaynetworkpeakhours.Itisthereforeconcludedthatconstructionstaffmovementswouldnothaveamaterialimpactontheoperationoftheexistinghighwaynetwork.

12.7.26 Overallitisconcludedthattheconstructiontrafficwouldnotresultinamaterialimpactontheoperationoftheexistinghighwaynetwork.ThemeasuresandproceduresoutlinedintheCEMPwillensurethatanyadverseenvironmentalimpactsareminimised,andheavyconstructiontrafficwouldnotbepermittedtotravelontheA508tothesouthofthesite,therebyavoidingimpactinguponlocalvillages.

12.7.27 Itisconcludedthattheconstructionphaseofthedevelopmentwouldhaveatemporary adverse impact of moderate significanceontheoperationofthesurroundinghighwaynetwork.

Operation 12.7.28 ThissectionoftheESexaminestheresidualtransportimpactoncetheDevelopmentwouldbein

operationandtheassociatedinfrastructureimprovementsandothermitigationmeasuresareinplace.

12.7.29 TheProposedDevelopmentcomprisesSRFconsistingof‘warehousinganddistribution’B8use(ZoneAontheParametersPlan),andthe‘intermodalrailfreightterminal’(ZoneBontheParametersPlan).

12.7.30 ZoneAwouldtaketheformoflargescaleunitsthatwouldsupportacombinationofB8uses,withancillarybuildings.TheIllustrativeMasterplansummarisesthegrossinternalareaofeachunitshown.Asshown,B1officeusewouldcomprisearound5%ofthetotalareaandisthereforeancillarytothepredominantB8use.

12.7.31 TheParametersPlansetsoutamaximumareaforthewarehousinganddistributionuseatthedevelopmentat5,037,510sqft(468,000sqm).However,toprovidesomeflexibilityforfutureoccupiersseekingmezzaninespace,theParametersPlan includesanallowanceforafurther155,000sqmintheformofB8mezzaninefloorspaceuse.Forassessmentpurposesthemaximumfloorarea,includingtheallowanceformezzaninefloorspace,isthereforeusedinthisTA.

Page 40: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 40

12.7.32 TheParametersPlanincludesdirectrailservedwarehouseunitsbymeansofdedicatedrailconnectiontodevelopmentzonesA2a,A2b,A3andA4.

12.7.33 TheintermodalrailfreightterminalandaggregatesterminalwouldtaketheformofanindependentfacilityandassociatedcontainerstorageprovidedinZoneB.Theloadingandunloadingsidingsandtheassociatedpadwouldbeabletoaccommodatetrainsofupto775metresinlength,toallowthelongesttrainstobeaccommodated.

12.7.34 TherewouldalsobecapabilitytoprovideaRapidRailFacility(RRF)aspartoftheintermodalrailfreight terminal.

12.7.35 Containermovementstotheindividualwarehouseunitsonthesitewouldeitherbedirecttotheindividualwarehouseunit(orplot)byrail,bymeansofanadjacentrailloading/unloadingpad,orbydeliveryofthecontainerstothemainloading/unloadingterminalattheintermodalfacility,withthecontainersthenbeingtransferredbyHGVbetweentherailterminalandwarehouseunit.

12.7.36 Inkeepingwithmostinlandrailfreightterminals,therailfreightterminalislikelytooperateona24-hourbasisfromMondaytoFriday,anduntilSaturdaylunchtime.However,volumegrowthatthemainportscouldleadtoanincreaseto6or7-dayoperation.AlltheB8unitsarelikelytooperateona24-hourbasis,sevendaysaweek.Themainshiftsarethereforelikelytobe0600-1400hours,1400-2200hoursand2200-0600hours,althoughtherewillbesomevariationdependingontheindividualoccupierrequirements.Forexample,someoccupiersmayoperatea12-hourshift,from0700-1900hoursand1900-0700hours.

12.7.37 ItisanticipatedthatitwouldtakeseveralyearsbeforetherailfreightterminalatNorthamptonGatewaywouldoperateatfullcapacity.Therailfreightterminalwillbeoperationalupontheopeningofthedevelopmentandwillhavecapacitytoaccommodateatleast4trainsperday.Forthepurposesofassessment,theopeningyearcapacityisthereforeassessedat4trainsperday.However,toensurearobustapproach,maximumcapacityof16trainsperdaytotheIntermodalTerminalSRFIsitehasbeenassumedtooccurwithintheassessmentperiodssetforthefutureyeartransportmodellingassessmentscenarios.

12.7.38 Initiallytheloadingandunloadingofcontainerstoandfromtherailvehiclesattheintermodalterminalwouldbebyreachstacker,whichcouldbereplacedbygantrycranesasvolumesandthroughputattherailterminalincreased.

Modal Shift from Road Freight to Rail Freight12.7.39 TheproposedSRFI,comprisingboththewarehousinganddistributionunitsandtherailterminal,

wouldgeneratethefollowingtypeoftrips:

1.EmployeetripstoandfromworkatboththeB8unitsandtherailterminal;

2.VisitoranddeliverytripstoboththeB8unitsandtherailterminal;

3.HGVtraffictoandfromtheB8units;

4.HGVtraffictoandfromtherailterminal;

5.HGV(ortug)trafficbetweentherailterminalandtheB8units;andRailtrips.

12.7.40 Onlytriptypes1to4wouldusetheoff-sitehighwaynetwork.Triptype5wouldbeontheinternalroadnetwork,betweentherailterminalandwarehousingarea.Triptype6wouldbeontherailnetworkonly,andthecapacityoftherailnetworktoaccommodatethesetripsisdemonstratedintheRailCapacityReport(DCOdocument6.8).

Page 41: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 41

12.7.41 TheTAthereforefocusesontriptypes1to4,astheTAisultimatelyconcernedwiththeimpactofthedevelopmentonthehighwaynetwork.However,itisrecognisedthatthenumberofHGVsgenerated(triptypes3,4and5)willberelatedtothenumberofrailtrips(triptype6)andthesizeofthecontainers/typeofgoods.Furthermore,theamountofexternalHGVtrips(triptypes3and4)willberelatedtothenumberofinternaltrips(type5)andtheoperationandinteractionbetweentherailterminalandtheon-sitewarehousing.

12.7.42 TheabovedependenciesandinteractionsareexaminedindetailedatSections5,6and7ofTN2(TAAppendix5)andareincludedwithinthetripgenerationcalculations.OncetherailfacilitiesatNorthamptonGatewayarefullyoperationaltheycouldaccommodateanaveragemaximumthrough-putofaround1384containersaday.Thisisamodeshiftfromroadfreighttorailfreightequivalentto969HGVloadsor1,938two-wayHGVmovementsperday.Appendix34oftheTAincludesanexampleofhowthiscouldtranslatetoamodalshiftfromroadfreighttorailfreight.Theexampledemonstratesthat,annually,theProposedDevelopmentcouldremoveover92millionHGVmilesperyearfromthehighwaynetwork.Thisequatestoover£50millionperyearinmonetisedenvironmentalbenefitsascalculatedusingthemethodologysetoutintheDfTGuidetoModeShiftRevenueSupportScheme2.

12.7.43 TakentogethertheabovereductioninoverallHGVmileageontheroadnetworkdemonstratehowtheproposedNorthamptonGatewaySRFIwouldcomplywithGovernment’sobjectives,assetoutintheNPSNN,toachieveamodalshiftfromroadfreighttorail.

12.7.44 ItisimportanttounderstandthatmanyoftheremainingHGVtripsforecasttobegeneratedbytheproposedSRFIdevelopmentwouldalreadybepresentonthehighwaynetwork.ThisisbecausemanyoftheHGVtripswouldbeassociatedwiththedeliveryofgoodstomeetexistingbusinessdemandinthelocality.SuchHGVmovementswouldalreadyexistlocallytothosebusinesses,andthedevelopmentoftheSRFIwouldnotaddadditionalHGVtrafficintheseareas.Rather,itwillprovideadistributionhub,meaningthatjourneydistanceswillbereduced,reducingoverallHGVmileageontheroadnetworkasdescribedabove.

12.7.45 TakentogethertheabovemodalshiftandresultantreductioninoverallHGVmileagerepresentsapermanent beneficial impact of major significance

12.7.46 Nevertheless,toensurethatthefullimpactoftheProposedDevelopmentismodelledinthevicinityofthesite,thetransportmodellinghasassumedthatallHGVtripswouldbenewtripstothehighwaynetwork.Forthereasonsgivenabove,thisresultsinarobustassessmentofthetrafficimpactsasitmeansthatthereissomedoublecountingofHGVtraffic,particularlyonthemainlinkstoandfromtheexistingurbanandindustrialareas,suchasBrackmillsIndustrialEstate,locatedofftheA45.

2 DfT Guide to Mode Shift Revenue Support (MSRS) Scheme, April 2015

Page 42: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 42

Development Trip Generation12.7.47 Chapter5oftheTApresentsthepersonandvehiculartrafficgenerationcalculationsforthe

ProposedDevelopment.Thetwo-wayexternalpersontripgeneration(combinedtotalmovementsinandoutofthesite)aresummarisedatTable12andTable12.7summarisesthevehicletripgenerations.

Table 12.6: Off-site person trips (two-way)

Period Person TripsAMPeakHour 1,111PMPeakHour 1,393Daily 17,657

Table 12.7: Off-site vehicle trips (two-way) not accounting for the Travel Plan

Period Light Vehicles HGVs TotalAMPeakHour 775 269 1,044PMPeakHour 1,035 268 1,303Daily 12,286 4,245 16,531

12.7.48 Thevehicletripgenerationsassumeasingleoccupancyvehicle(SOV)rateof92%.Whilstthisprovidesarobustpositionforassessmentofthehighwaycapacity,itisnotrepresentativeofthelikelymodalsharethatwouldbeachievedbytheProposedDevelopmentoncethesustainabletransportinitiativespresentedintheFTP(TAAppendix1)andthePTS(TAAppendix2)areconsidered.

12.7.49 Theemployee(light)vehiclestripspresentedatTable12.7donotthereforerepresenttheexpectedpublictransportmodalshare,orthepotentialforcarsharing.

12.7.50 Table3ofthe FTP(TAAppendix1)setsoutthemodalshifttargetsforemployeesoftheproposeddevelopment.ThemodalsharetargetshavebeenextractedfromtheFTPandaregivenatTable12.8.

Table 12.8: Modal share targets

Mode Baseline Year 3 interim target Year 5 targetSOV 92% 85% 74%Carshare 5% 7% 12%Publictransport 3% 6% 10%Walking&cycling 0% 2% 4%

Page 43: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 43

12.7.51 Table12.9summarisestheresultingoff-sitevehicletripgenerationtakingintoaccounttheaboveSOVmodalsharetargetforemployees.

Table 12.9: Off-site vehicle trips (two-way) accounting for the Travel Plan (5 Year Target)

Period Light Vehicles HGVs TotalAMPeakHour 620 269 889PMPeakHour 828 268 1,096Daily 9,871 4,245 14,116

12.7.52 Theresultedexpectedtwo-waypersontrips(combinedarrivalanddeparture)bytransportmodebasedonthe5yearFTPtargetsaresummarisedatTable12.10.HGVtripsarenotsubjecttomodalsharetargetsasthepurposeofaHGVmovementisthetransportationofitscargo.Therefore,HGVdrivertripsareassumednottoundergomodalshift

Table 12.10: Two-way person trip by mode accounting for the Travel Plan (5 Year Target)

Period AM PM DailySOV 620 828 9,871Carshare 101 135 1,609PublicTransport 84 113 1,341Walking&Cycling 34 45 536

12.7.53 Notwithstandingtheabove,theTransportWorkingGrouprequestedthattheassessmentofthevehicleimpactsbeundertakenusingthevehicletripgenerationwithoutconsideringtheeffectoftheFTPorPTS.TheassessmentofthetrafficimpactoftheProposedDevelopmentisthereforerobustasitdoesnotincludefortherequired20%reductioninemployeejourneystoandfromworkthatisthetargetidentifiedintheFTP.WiththePTSandTravelPlanoperational,tripgenerationwouldbereducedincomparisontotheworst-casescenarioassessed,andtheresidualtrafficimpactswouldalsobereduced.

Impact on Highway Network Operation12.7.54 TheimpactonthetransportnetworkoftheProposedDevelopmenttrafficgivenatTable12.7,

alongwiththeeffectsofexistingtrafficreassignmentassociatedwiththehighwaymitigationworksisexaminedindetailatChapters7to10oftheTA.

12.7.55 TheNSTM2strategicmodellingdemonstratesthattheproposedhighwaymitigationworksremoveexistingcongestion‘bottlenecks’onthehighwaynetwork,particularlyatM1Junction15and15A,andontheA508throughRoade.Therefore,existingtrafficisforecasttoreassigntousetheprincipalandSRN,withincreasesintrafficforecastontheA508betweentheA5andM1Junction15,andatM1Junction15and15A.

Page 44: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 44

12.7.56 ThisisadesirableoutcomeastheA508isanimportantprimaryroute,partofNCC’sroadfreightnetworkandhasbeenidentifiedintheDfTconsultationaspartoftheproposedMajorRoadNetwork.Thestrategictransportmodellingdemonstratesthatwithoutinterventionthe2031D1ReferenceCasebackgroundtrafficgrowthonsectionsoftheA508wouldberestrictedto1%and5%inthemorningandeveningpeakhourperiods.Thisfallsfarshortoftheaverage25%growthinbackgroundtrafficthatisforecastforthe2031D1ReferenceCasefortheNorthamptonshirearea.TheconstraintsontheA508meanthatthesurroundinglocalroadswouldberequiredtoaccommodateagreaterproportionoftrafficgrowthinthe2031D1ReferenceCase.ThehighwaymitigationproposalsreleaseexistingconstraintsthatallowtheA508toaccommodateadditionaltrafficandfunctionasintended.ThisleadstoaconsequentialreductionintrafficonmanyofthelocalroadsandvillagessurroundingtheSRFI,includingtheA508NorthamptonRoadandHighStreetthroughRoade;BlisworthRoad/CourteenhallRoad,TowcesterRoad,HighStreet,NorthamptonRoad,andChapelLaneinBlisworth,RectoryLaneinMiltonMalsor,andWoottonRoadthroughQuintonasshownatFigures8.9and8.10oftheTA.

12.7.57 TheimpactoftheincreasedtrafficontheA508isexaminedatChapters7,8and10oftheTA,whereitisshownthattheA508,withtheproposedhighwaymitigationworks,wouldsatisfactorilyaccommodatethechangesintrafficflows.

12.7.58 TheproposedalterationoftheA508/Blisworth(Courteenhall)Roadsimplepriority-controlledT-junctiontobecomealeft-in,left-outonlyjunction,wouldremoveasignificant(5minute)eveningpeakhourdelayfordriverstravellingsouthboundontheA508.Theproposedjunctionwouldalsodeterthedriversfrom‘ratrunning’betweentheA508andtheA43throughBlisworth,whichisaconcernofresidents.BlisworthresidentsandthosewishingtoaccessBlisworth/CourteenhallRoadfromthenorthviatheA508couldinsteaduseRoadeBypassandthenewroundaboutjunctiononKnockLane,althoughanalternativerouteviaNorthamptonRoadwouldalsobeavailableforthosetravellingfromNorthampton.

12.7.59 TheproposedA508RoadeBypassleadstoforecasttrafficreductionsthroughRoadeofaround74%and52%inthemorningandeveningpeakhoursandaround60%throughouttheday.Thiswouldalleviatecongestionwithinthevillageandatstudyareajunctions24,25and26.TheNSTM2strategicmodellingdemonstratesthatexistingHGVtrafficwouldchoosetousethenewbypassratherthantravelthoughthevillage.However,thiswouldbeenforcedthroughtheproposed7.5TenvironmentalweightrestrictionthroughthevillageandontheotherlocalroadstothesouthoftheSRFIsite,whichalongwiththeexisting7.5TenvironmentalweightrestrictionthatisinplaceonC85PuryRoadwouldrestrictHGVstousingtheA508.

12.7.60 TheproposedalterationofA508/C26RookeryLane/C26AshtonRoadstaggeredcrossroadsjunctiontoprovideasinglelaneduallingarrangement,wouldimprovetheoperationofthejunction,allowingvehiclesturningrighttosafelywaitoutofthepathoftrafficontheA508,whilstenablingdriversturningrightoutoftheminorroads,orgoingstraighton,tosafelymaketheturnintwomoves,i.e.crossingduringagapintrafficfromtherightandthenturningorcrossingduringagapintrafficfromtheleft.Theoperationandcapacityofthejunctionwouldbeimproved.ApedestrianandcyclecrossingpointovertheA508,makinguseofthelargecentralisland,andafootwayontheeastsideoftheA508alongthefrontageofthepropertieswouldalsobeprovided.TheimprovementstothejunctionrealignandsoftenthetightbendontheA508tothesouthofthejunction,therebyimprovingroadsafetyatthisidentifiedaccidenthotspot.

Page 45: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 45

12.7.61 GraftonRegishasanapproximately300metresfrontagealongtheeasternsideoftheA508.ThetrafficimpactonGraftonRegisisexaminedatChapter8oftheTA.TothesouthoftheGraftonRegisthemorningandeveningpeakhours,anddailytrafficflowsontheA508areforecasttoincreaseby23%,15%,and18%respectively.Theseincreasesareallbelowthethresholdthatwouldtriggerfurtherdetailedassessment.TrafficthatisforecasttoavoidtheA508duetocongestioninthe2031D1ReferenceCase,isshowntobeattractedbacktotheA508becausetheproposedA508RoadeBypassandA508corridorrouteupgrademakestheA508amoreattractiveroutechoicefordriverscomparedtotravellingonthesurroundinglocalroadsandvillages.Thisisreflectedbyforecasttrafficreductionsof-70%,-59%and-65%intheAMandPMpeakhourandduringtheday,onChurchLanethroughthevillageinthe2031J1dDevelopmentCasescenario.However,thistrafficreassignstousetheA508tothenorthofChurchLaneandthereforetrafficflowsontheA508tothenorthoftheChurchLanearehigher.Themorningandeveningpeakhours,anddailytrafficflowsontheA508tothenorthofChurchLanearethereforeforecasttoincreasebysome57%,29%,and43%respectively.

12.7.62 TherearenolinkorjunctioncapacityconstraintsidentifiedonthissectionoftheA508adjacenttothevillage.Therefore,whilsttherewouldbelargeincreasesintrafficflowsusingtheshortsectionoftheA508thathasfrontagewiththevillage,trafficwouldbewouldbefreeflowing,subjecttothe30mphspeedlimit,andwouldbeoff-setbytrafficreductionsthroughotherpartsofthevillage.TheresidentsofGraftonRegiswouldalsobenefitfromtheimprovedjourneytimesandjourneyreliabilityassociatedwiththeproposedhighwayworks.

12.7.63 Nevertheless,theadditionaltrafficwouldincreasetheseveranceassociatedwithcrossingtheroadtoaccessthebusstopandfootpathonthewesternsideoftheA508.ThedevelopmentproposalsthereforeincludetheprovisionofanewpedestriancrossingwithacentralrefugeontheA508.

12.7.64 ThewideningontheA508toaccommodatethepedestrianrefugeprovidestheopportunitytoprovidearightturnharbouragefacilityforChurchLane,allowingvehiclesturningrighttosafelywaitoutofthepathoftrafficontheA508.ThenewrefugewillprovideachannellisingeffectforthroughtrafficontheA508,reinforcingthevillagesettingand30mphspeedlimitthroughthevillage.

12.7.65 TheresultsoftheVISSIMmicro-simulationmodellingarepresentedatChapter10oftheTAandattheVISSIM1andVISSIM2TechnicalNotesprovidedatTAAppendices27and28.Themicro-simulationmodellingdemonstratethattheproposedM1Junction15andA45majorupgradeandtheM1Junction15Aimprovementswouldprovideasignificantimprovementtotheoperationofthehighwaynetworkcomparedtothe2031D1ReferenceCase.

12.7.66 Tables12.11and12.12 summarisethechangesinaveragevehiclespeedsandaveragedelaypervehicle,takenfromtheVISSIMmicro-simulationmodellingresultsforthe2031J1dDevelopmentCasecomparedtothe2031D1ReferenceCase.ThisdemonstratesthebeneficialimpactoftheproposedM1Junction15andA45majorupgrade,andM1Junction15Aimprovementworksontheoperationofthehighwaynetwork.Theresultsshowthatwiththedevelopmentoperationalandtheproposedhighwayworksinplace,averagevehiclespeedswouldincreaseby6%inthemorningpeakhourandby47%intheeveningpeakhour.Theaveragedelaypervehiclewouldreduceby40%inthemorningpeakhourand69%intheeveningpeakhour.

Page 46: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 46

Table 12.11: Average vehicle speed

Period 2031 D1 RefCase

2031 J1d Dev Case % Change

AMPeakHour 35 mph 37mph +6%PMPeakHour 27 mph 39mph +47%

Table 12.12: Average delay per vehicle

Period 2031 D1 RefCase

2031 J1d Dev Case % Change

AMPeakHour 141seconds 84seconds -40%PMPeakHour 249seconds 76seconds -69%

12.7.67 ThenumberofunreleasedvehiclesinaVISSIMmodelalsoprovidesagoodindicationofcongestionwithinahighwaynetwork.Inthe2031D1ReferenceCasemodeltherewereapproximately800unreleasedvehiclesinthemorningpeakperiodandapproximately1800unreleasedvehiclesintheeveningpeakperiod.The2031J1dDevelopmentCasemodelresultsshowsthatallvehiclesweresuccessfullyreleasedintothenetworkinboththemorningandeveningpeakperiods,furtherindicatingthatnetworkperformanceissignificantlyimprovedwiththedevelopmentandmitigationproposalsinplace.

12.7.68 Excludingdevelopmenttraffic,inthe2031J1dDevelopmentCaseanadditional1,511vehiclesarepresentintheVISSIMmodelinthemorningpeakhourandadditional2,118vehiclesarepresentintheVISSIMmodelintheeveningpeak,whencomparedtothe2031D1ReferenceCase.ThisadditionaltrafficisbeingdrawnintotheSRNandprincipalroadnetworkbecauseofthehighwayimprovements.Theaboveimprovementsinaveragespeedandaveragedelaypervehicleincludeforboththisadditionalbackgroundtrafficandtheadditionaldevelopmenttraffic.

12.7.69 Overall,journeytimesforcardriversandHGVdriverswouldreduceandthesearesummarisedatTable12.13.AfullassessmentforeachjourneyisprovidedatTables5to8oftheVISSIM1report(TAAppendix26).

Table 12.13: Change in of average journey between 2031 D1 Reference Case and 2031 J1d Development Case

Period Change in average journey time per car

Change in average journey time per HGV

AMPeakHour -27% -37%PMPeakHour -48% -55%

12.7.70 ThepositiveimpactoftheproposedmitigationschemesatM1Junction15andM1Junction15AareparticularlyevidentwhenconsideringthejourneytimecomparisonsonroutesfromtheA508(allroutes),M1South(toA43&A5123),A45(allroutes)andtheM1North(toA43andA5123),wherethejourneytimesarereducedbyaround60%inthemorningpeakperiodandbyup90%intheeveningpeakperiodwhencomparedtothe2031D1ReferenceCasescenario.

Page 47: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 47

12.7.71 Therearethreeroutesinthemorningpeakhourandtworoutesintheeveningpeakhourwherejourneytimesseeanotableincrease.ThesearefromSaxonAvenuetotheA45andfromWateringLanetotheA45inbothpeakhours,andfromSaxonAvenuetoWateringLaneinthemorningpeakhour.Increasesof30%to40%injourneytimesareforecastinthemorningpeakhourandincreasesofupto47%areforecastintheeveningpeakhour.

12.7.72 TheseincreasesarearesultofvehicleshavingtonegotiatethelargerM1Junction15layoutandbecausetheimprovementssignaliseboththeSaxonAvenueandWateringLaneapproaches,whichaddssomedelaytotheseroutes.However,whenconsideringtheoveralltrafficvolumes,thenumberofvehiclesundertakingthesemovementsislowincomparisontothemajorityoftheotherroutesat2.2%inthemorningpeakhourand1.1%intheeveningpeakhour.FurtherqueuelengthsonSaxonAvenuewouldnotbesignificantandwouldbeexpectedtoclearineachtrafficsignal cycle

12.7.73 Section12.4ofthisESChapternotedthatM1Junction15isoftenheavilycongestedwithpeaktimequeueingontheA45andA508approachestothejunctioncommonplace.Chapter10oftheTAandAppendixFofVISSIM1report(TAAppendix26),presentthatforecastqueueingatM1Junction15inthe2031D1ReferenceCaseand2031J1dDevelopmentCase.

12.7.74 DuringthemorningpeakhouraveragequeuelengthsontheA45approachtoM1Junction15areforecasttoreducefromaround2.5kminthe2031D1ReferenceCasetoaround475metresinthe2031J1dDevelopmentCase.QueuesontheA508approachareforecasttoreducefromaround1.5kminthe2031D1ReferenceCasetoaround15metresinthe2031J1dDevelopmentCase.

12.7.75 DuringtheeveningpeakhourqueuelengthsontheA45approachtoM1Junction15areforecasttoreducefromaround2.4kminthe2031D1ReferenceCasetoaround65metresinthe2031J1dDevelopmentCase.QueuesontheA508approachareforecasttoreducefromaround100metresinthe2031D1ReferenceCasetoaround25metresinthe2031J1dDevelopmentCase.

12.7.76 ThesesignificantreductionsinqueuingareadirectresultoftheimprovedcapacityandoperationofM1Junction15andA45thatwouldberealisedaspartofthemajorupgradeworks.TheimprovementswouldleadtotheforecastsavingsinjourneytimewhentravellingnorthboundandsouthboundbetweentheA508andA45thatareshowninTable12.14and12.15.ThesearekeymovementsassociatedwithtraffictravellingtoandfromtheSRFIdevelopment,whichwouldalsoimprovejourneytimesfortheproposedbusserviceandexistingX4andX7busservicesthatwouldalsoservethedevelopment.

Table 12.12: Change in journey times A508 to A45 and A45 to A508 - Cars

Period Journey Journey time (hrs:mins:secs)2031 Ref Case 2031 Dev Case Saving

(% change)AM NB(A508toA45) 00:09:16 00:03:41 -00:05:35

(-60%)SB(A45toA508) 00:05:36 00:04:16 -00:01:20

(-24%)PM NB(A508toA45) 00:04:29 00:03:36 -00:00:54

(-20%)SB(A45toA508) 00:06:04 00:03:22 -00:02:43

(-45%)

Page 48: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 48

Table 12.13: Change in journey times A508 to A45 and A45 to A508 - HGVs

Period Journey Journey time (hrs:mins:secs)2031 Ref Case 2031 Dev Case Saving

(% change)AM NB(A508toA45) 00:09:30 00:03:53 -00:05:37

(-59%)SB(A45toA508) 00:05:47 00:04:33 -00:01:14

(-21%)PM NB(A508toA45) 00:04:46 00:03:50 -00:00:56

(-20%)SB(A45toA508) 00:06:11 00:03:29 -00:02:42

(-44%)

12.7.77 AsdiscussedinChapter10oftheTA,theVISSIMmodellingforecaststhatinthe2031(D1)ReferenceCasequeuingatM1Junction15ontheM1southbounddivergewouldreachbackbeyondtheendofthesliproadinthemorningpeakhour,whereitwouldimpactontheM1mainlineflow.

12.7.78 TheVISSIMmodellingdemonstratesthatinthe2031(J1d)DevelopmentCasescenario,withtheM1Junction15andA45majorupgradeinplace,queuelengthswouldbecomfortablystoredonthesliproadandwouldnotimpactontheM1mainline.ThisrepresentsasignificantoperationalandsafetyimprovementintheperformanceofM1Junction15anditsinteractionwiththeM1mainline.

12.7.79 AtM1Junction15A,queuingonthesliproadsinthe2031(D1)ReferenceCaseisforecasttoexceedthelengthofthesliproadonboththenorthboundandsouthbounddivergesfromthemotorwayinboththemorningandeveningpeakhours.ReferenceCasequeuesonthenorthbounddivergewouldextendtosome3kminthemorningpeakhourand5kmintheeveningpeakhour.Forthesouthbounddiverge,queuesofsome2kmand3.75kmareforecastinthe2031Referenceinthemorningandeveningpeakhour,respectively.ThesearesignificantqueuesandwouldimpactontheM1mainlineflow.

12.7.80 TheVISSIMmodellingdemonstratesthatinthe2031(J1d)DevelopmentCasescenario,withtheM1Junction15Aimprovementsplace,queuelengthswouldbecomfortablystoredonthesliproadandwouldnotimpactontheM1mainline.ThisrepresentsasignificantoperationalandsafetyimprovementintheperformanceofM1Junction15AanditsinteractionwiththeM1mainline.

12.7.81 Chapter8oftheTAandTN10,TN10AandTN11(TAAppendices15,16and17)examinetheresidualhighwayimpactsatthestudyareajunctions.

12.7.82 NorthoftheA45BarnesMeadowInterchangenosignificantincreasesintrafficflowsontheA45intheDevelopmentCasescenariosareforecastascomparedtotheReferenceCasescenarios.However,analysisincludedwithinTN10showsthatdevelopmenttrafficispresentonthissectionoftheA45,andthereforelocalbackgroundtrafficisreassigningawayfromthisroute.ThisreassignmentoccursbecausenorthoftheBarnesMeadowInterchangethelinkcapacityoftheA45isforecasttobeexceededatseverallocationsinboththeDfTCircular02/2013compliantReferenceCaseand2031ReferenceCasescenarios.Thisisduetotheforecastgrowthinbackgroundtraffic,includingthatassociatedwiththecommittedandplanneddevelopmentinNorthamptonshire,andisthereforeanexistingproblemwithorwithouttheadditionofthedevelopmenttraffic.Thedisplacedtrafficreassignsacrossmultipleroutesanddispersesacrosstheroadnetwork.

Page 49: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 49

12.7.83 DetailedmodelswereconstructedandusedtoassesstheimpactofthedevelopmenttrafficandthereassignedtrafficontheeffectedstudyareajunctionswhichincludesallrelevantjunctionontheA45,theA5076MereWay/DanesCampWaycorridor,thekeyjunctionsontheInnerRingRoadandjunctionsnorthofM1Junction15A.

12.7.84 Thejunctionmodellingdemonstratesthattherewouldnotbeasevereimpactatanyofthestudyareajunctionswhenconsideringthepracticalreservecapacityforthejunctionsandtotaldelay.However,whenconsideringthejunctionsinmoredetail,localisedimpactswereidentifiedatthefollowinglocations:

• theA5076MereWayapproachtotheA45QueenEleanorInterchange;

• theMereWayapproachtotheA5076DanesCampWay/MereWay/TowcesterRoadgyratory;and

• theA5123approachtotheA5076DanesCampway/A5123UptonValleyWay/A5075UptonWaygyratory

12.7.85 NCCrequiredthatimprovementschemesbeprovidedattheselocationstomitigatetheimpactofthedevelopmentandtrafficreassignmenteffects.AppropriatehighwayimprovementschemesarethereforeidentifiedandpresentedintheTAforthesejunctions.

12.7.86 NCCaredevelopingacomprehensiveimprovementschemeattheA45QueenEleanorInterchangeanditisrecognisedthatflexibilityregardingthetimingandscopeoftheimprovementworksontheA5076DanesCampWaycorridorwouldbebeneficial.Therefore,itisagreedwithNCCthatthedevelopmentwouldprovideafinancialcontributionequivalenttothecostofimplementingtheproposedimprovementworksatthesejunctions,tobeusedtodelivertheproposedimprovements,oraspartofawiderpackageofimprovementsattheA45QueenEleanorInterchangeandtheA5076corridortobedeliveredbyNCC.

12.7.87 Theresultsofthemicro-simulationmodellingincombinationwiththedetailedjunctionassessmentwork,basedontheoutputsfromthestrategicmodelling,demonstratethesuitabilityoftheproposedhighwaymitigationworkstoaccommodatethetrafficincreasesassociatedwiththeProposedDevelopment.

12.7.88 Overall,itisconcludedthattheproposedhighwaymitigationworksarerequiredtoprovidesatisfactoryaccesstotheProposedDevelopmentandtoaccommodatethetrafficreassignmenteffectsresultingfromboththedevelopmenttrafficandproposedhighwaymitigationworks.ThehighwayworksalsoreleaseconstraintsontheA508,andatM1Junction15andJunction15A,allowingtheexistinghighwaynetworktofunctioninasaferandmoreefficientmanner.ThisinturndrawstrafficbackontotheexistingprincipalandSRN.Indoingsotrafficflowsonmanyofthesurroundinglocalroadsandvillageswouldreduce,ascomparedtotheReferenceCase.Therefore,theresidualeffectsoftheProposedDevelopmentandhighwaymitigationworksingeneraltrafficimpacttermscanbesummarisedasapermanent beneficial impact of major significance.

Impact on Pedestrians, Cyclists, Equestrians (NMUs) and the community12.7.89 TheProposedDevelopmentandassociatedhighwaymitigationworkswouldalterconditionsfor

NMUsusingthepublicrightsofwaythatcrossthemainsiteandthosecrossingtheproposedRoadeBypass.Theproposedhighwaymitigationworkswouldalsoaltertheexistinghighwayinfrastructure.ThechangesaredescribedatChapter4oftheTAandSection12.6ofthisES.

12.7.90 Theproposalswouldalterthejourneylengthandlocaltravelpatternsinthearea.ThesechangesaredescribedindetailintheWCHARAssessmentandReviewReports,whichareAppendices18and19oftheTA.

Page 50: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 50

12.7.91 PRoWsKX17andKX13thatcrossthemainsitewouldbedivertedandextendedtoformalooparoundthemainsitewithinthelandscapebunding.KX17wouldbeincreasedbysome800metres(68%)andKX13bysome180metres(13%).

12.7.92 TheRoadeBypasswouldaffectpublicfootpathsKZ30,KZ19,KZ2aandRZ3,andbridlewayKZ10/RZ1.Ateachlocation,theimpactoftheBypassproposalshasbeenassessed.Suitablecrossingspointsareprovidedforeachofthefootpathsandanunderpasssuitableforequestriansisprovidedforthebridleway.

12.7.93 Therefore,althoughjourneylengthsforsomePRoWwouldbelonger,suitablealternativeroutesthatminimisetheimpactareproposed.

12.7.94 Amenityismainlyinfluencedbythevolumeandtypesoftrafficonanadjacentroadlink.TheeffectoftheProposedDevelopmentandassociatedhighwaymitigationworkswouldbetoincreasetrafficflows,includingHGVs,ontheA508betweentheA5andM1Junction15,includingGraftonRegis,andontheSRNatM1Junction15andM1Junction15A,ontheA45.TherewouldalsobealargepercentageincreaseincarsusingKnockLane,predominantlyduetobackgroundtrafficswitchingfromStokeRoad,althoughactualtrafficvolumeswouldremainlow.

12.7.95 AresultoftrafficbeingdrawnontotheA058andSRNisthattrafficflowswouldreduceonmanyofthesurroundinglocalroads,includingStokeRoad,Blisworth(Courteenhall)Road,TowcesterRoad,NorthamptonRoad,CollingtreeRoad,theunnamedroadbetweentheA508andQuinton,WoottonRoad,ChurchLaneinGraftonRegis,andthroughAshtonandRoade.

12.7.96 TheproposedHGVroutingstrategyfortheSRFIandtheproposed7.5TenvironmentalweightrestrictionswillrestrictHGVaccesstoonlysuitableroutes,andtheA508RoadeBypasswillsignificantlyreducethevolumeoftrafficpassingthroughthevillage.

12.7.97 Overalltherewouldbeimprovedpedestrianandcyclistroutesandconnectivity.ThefacilitiesatM1Junction15wouldbeimprovedandtrafficsignalcontrolledcrossingsprovidedatallcrossingpoints.Anewcycletrack(alsoforusebypedestrians)linkingtheA508withthetrafficfreebridgeovertheM1wouldbeprovide,connectingwithHighStreetinCollingtree.

12.7.98 ThedevelopmentwouldprovideanewcyclepathalongsidetheA508fromRoadetoM1Junction15anditwouldprovideamissingpieceofcyclenetworkadjacenttotheA45betweenM1Junction15andWateringLane.Asharedfootway/cyclewaywouldalsobeprovidedontheeasternsideoftheproposedRoadeBypass,withanewfootwayandatgradecrossingovertheA508providedattheA508/C26RookeryLane/C26AshtonRoadjunction.ThenewpedestrianrefugeprovidedontheA508inGraftonRegiswouldreduceseveranceassociatedwithaccessingthenorthboundbusstopandfootway.

12.7.99 Inadditiontotransportandaccessibilityrelatedeffects,theseelementsoftheProposedDevelopmentcoupledwiththeon-siteroutesforwalking(andrunning)orcyclingwouldsupportpublichealthpromotionandwell-beingagendas,andcouldhavepositivehealthbenefitsforlocalresidentsandemployees.

12.7.100 Overall,withregardstoimpactsonpedestrians,cyclists,equestriansandthecommunityitisconcludedthatthedevelopmentproposalswouldhavepermanent adverse impact of minor significanceonamenity,andanegligibleimpactonseveranceandonjourneylengthandlocaltravel patterns.

Impact on Vehicle Travellers – Driver Stress12.7.101 Driverstresshasthreemaincomponents:frustration,fearofpotentialaccidents,anduncertainty

relatingtotheroutebeingfollowed.

Page 51: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 51

12.7.102 Frustrationiscausedbyadriver’sinabilitytodriveataspeedconsistentwithhisorherownwishesinrelationtothegeneralstandardoftheroad.Itincreasesasspeedfalls.Congestioncanleadtofrustrationcreatingasituationinwhichthedriverdoesnotfeelincontrol,especiallywhenheorshewishestoarriveatadestinationbyacertaintimebutisheldupbytrafficcongestionfromwhichthedurationoftheresultingdelaycannotbedetermined.

12.7.103 TakenincombinationtheproposedhighwaymitigationworksontheA508,includingtheRoadeBypass,wouldreducecongestionandimprovejourneytimesandjourneytimereliabilityfordriversusingthisroute.TheVISSIMmicro-simulationmodellingdemonstratesthattheproposedM1Junction15andA45majorupgradeandM1Junction15AhighwaymitigationworkswillsignificantlyreducecongestionontheSRNandreduceaveragepeakhourjourneytimesforcardrivers.Averagedelaypervehicleisforecasttoreducebya40%inthemorningpeakhourand69%intheeveningpeakhour.TheeffectoftheProposedDevelopmentandassociatedhighwaymitigationworkswouldthereforebeareductionindriverfrustration.

12.7.104 Themainfactorsleadingtodriverfearofpotentialaccidentsisthepresenceofothervehicles,inadequatesightdistancesandthelikelihoodofpedestrians,particularlychildren,steppingintotheroad.Otherfactorsincludeinadequatelighting,narrowroads,roadworksandpoorlymaintainedroadsurfaces.Fearishighestwhenspeeds,flowsandtheproportionofHGVsarehigh.

12.7.105 TheProposedDevelopmentwouldincreasethenumberofHGVsusingtheroadnetworktothenorthofthesite.Theproposedhighwaymitigationworkswouldaltertheroutingoftraffic,drawingtrafficontotheA508andawayfromthesurroundinglocalroadsandvillages.TrafficandHGVflowsontheA508andtheSRNneartothesitearethereforepredictedtoincrease,whichcouldresultinacorrespondingincreaseindriverfearontheseroads.

12.7.106 TheproposedA508RoadeBypassandenvironmentalweightrestrictionthroughRoadewouldsignificantlyreduceA508trafficpassingthoughthevillage.TrafficandHGVflowsthroughRoadewouldthereforereduce,aswouldtrafficandHGVflowsthroughBlisworth,onTowcesterRoadandonBlisworth(Courteenhall)Road.ThiswouldleadtoareductionindriverfearontheseroadsandthroughRoadeandBlisworth.

12.7.107 TheNSMT2forecastsone-waymorningandeveningpeakhourtrafficflowonA508RoadeBypassof1,297and1,179vehicles(highestflows),respectivelyinthe2031J1dDevelopmentCase.InaccordancewithTable3ofDMRB(Volume11,Section3,Part9)theseflowsareconsistentwithahighlevelofdriverstress.

12.7.108 TheproposedhighwaymitigationworksatM1Junction15wouldreplacetheexistinggivewayarrangementswithtrafficlightsfordriversenteringthejunctionfromtheA508andSaxonAvenueapproaches.DriversaccessingtheA45fromWateringLanewillalsobeprovidedwithtrafficlights.Thiswouldremovetheneedfordriverstojudgegapsinbusytrafficflowsasisrequiredunderthecurrentarrangement.Driverswillinsteadbeprovidedwithpriorityduringthegreentrafficsignalphase,therebyleadingtoareductionindriverstress.

12.7.109 TheproposedrealignmentandalterationtothespeedlimitontheA45nearM1Junction15willbringtrafficspeedsinlinewiththeprevailingroadconditions,thereforeleadingtoareductionindriverfear.

12.7.110 Routeuncertaintyiscausedprimarilybysignagethatisinadequatefortheindividual’spurposes.AstrategyfordirectionalsignagehasbeendevelopedforboththeSRNnetworkandtheA508.ThesestrategiesarepresentedSection13oftheM1Junction15&A45ImprovementandM1Junction15AImprovementGDSR1reportfortheSRN(TAAppendix28),andatSection13oftheA508RouteUpgradeGDSR2reportfortheA508andat(TAAppendix29).Therefore,routeuncertaintywouldbelow.

Page 52: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 52

12.7.111 ItisconcludedtheProposedDevelopmentandassociatedhighwaymitigationworkswouldhavea beneficial impact of moderate significanceondriverfrustration,andabeneficial impact of minor significanceondriverfear,withanegligibleimpactonrouteuncertainty.

12.7.112 Overall,whentakentogether,itisconcludedtheProposedDevelopmentandassociatedhighwaymitigationworkswouldhaveapermanent beneficial impact of moderate significanceondriverstress.

Impact on Vehicle Travellers – View from the Road12.7.113 Theexistenceofanewroadmayenablemorepeopletoseethelandscapethanbefore.This

benefitisassessedundertheheadingviewfromtheroad,asisanydisbenefitthatmayarisewherearoadpassesthroughvisuallyunattractiveareas.Itisdefinedastheextenttowhichtravellers,includingdrivers,areexposedtothedifferenttypesofscenerythroughwhicharoutepasses.

12.7.114 TheRoadeBypasswouldprovideamoreruralroutefordriversusingtheA508,whocurrentlyroutethroughRoadevillage.TotheeastofthebypasstherewouldberestrictedviewsofRoade,whichwouldgenerallybescreenedbylandscapingandenvironmentalbunding.Viewstothewestofthebypasswouldbemoreopen,providingsomelimitedviewsofthecountryside.ThenewbridgeovertheWCMLwouldprovidebriefviewsoftherailway.

12.7.115 TheexistingintermittentviewsacrossthesitefromtheM1,theA508,Blisworth(Courteenhall)Road,CollingtreeRoadandNorthamptonRoadwouldbereplacedwithviewsoftheProposedDevelopmentwhichwouldberestrictedviatheuseofnewembankmentsandlandscapingscreening.

12.7.116 Whentakenoverall,itisconcludedthattheproposeddevelopmentandhighwaymitigationworkswouldhaveanegligible impactonviewfromtheroad.

12.8 CUMULATIVE EFFECTS

12.8.1 NCC’sNSTM2includesallcommitteddevelopmentandallocatedsiteswithintheNorthamptonshirearea.Themodelalsoincludesthecommittedinfrastructureschemesandthosehighlylikelytocomeforwardbeforetheforecastassessmentyear.ThisincludesHighwaysEngland’sSmartMotorwayProjects.Thecumulativeimpactsofthedevelopmentincombinationwithotherdefinedlandusesandinfrastructuresschemehasthereforebeenassessedaspartoftheoverallmodellingworkundertaken.FulldetailsofthecommittedandallocateddevelopmentandinfrastructureschemesincludedineachoftheNSTM2assessmentscenariosaredetailedatTAAppendix36.

12.8.2 ThereisaproposedNSIPprojectonanadjacentsite(‘RailCentral’).AlthoughnotacommitmentthepotentialcumulativeeffectsofthatemergingproposalinadditiontotheProposedDevelopmenthasbeenundertakenusingtheNSTM2andVISSIMmicro-simulationbasedontheinformationavailableinrespectofRailCentralatthetimeofthatassessmentwork(December2017).

12.8.3 ThisisreportedondetailatTechnicalNote12,whichformsAppendix12.2ofthisES.TheconclusionsofthatreportandasummaryofthepotentialcumulativeeffectsshouldboththeNorthamptonGatewayandRailCentralschemecomeforwardaresetoutinthefollowingsections.

Page 53: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 53

12.8.4 Itshouldbenotedthataftertheconclusionofthecumulativeassessmentmodellingwork,andjustpriortosubmissionoftheNorthamptonGatewaySRFIDCO,RailCentralreleasedfurtherinformationintothepublicdomainregardingtheirproposedschemeaspartoftheirStage2StatutoryConsultationwhichtookplacebetween15thofMarch2018and23rdApril2018.Theinformationincludedchangestotheiremerginghighwaymitigationproposals.Therefore,whererelevant,thepotentialimplicationsofthechangestotheiremergingproposalsontheconclusionsofthecumulativeassessmentarediscussedinTN12.

12.8.5 Importantly,itshouldbenotedthatRailCentralareyettoundertaketheirownVISSIMmodellingatM1Junction15andJunction15AandhavenotyetmodelledthehighwaymitigationstrategyidentifiedintheirStage2ConsultationintheNSTM2.Intheabsenceofthatessentialmodelling,theobservationsdrawnoncumulativeimpactofNorthamptonGatewayandRailCentralschemesshouldbeconsideredastentative.Inanyevent,RailCentral’songoingassessmentworkmayleadtofurtherchangestotheirhighwaymitigationstrategy,whichinturncouldalterthecumulativeeffects.TheinformationcontainedinTechnicalNote12iscaveatedtothatextent.

Disruption Due to Construction (cumulative assessment with Rail Central)12.8.6 BoththeNorthamptonGatewaySRFIandRailCentralSRFIschemesidentifythesameopening

year,2021.ThehighwayinfrastructurephasingfortheNorthamptonGatewaySRFIisdescribedatChapter4oftheNorthamptonGatewaySRFITA,andthedisruptionduetotheconstructionoftheNorthamptonGatewaySRFIdevelopmentisdescribedatparagraphs12.7.1to12.7.27ofthisESchapter.

12.8.7 RailCentralhavenotatthistimeprovideddetailsoftheirproposedhighwayinfrastructurephasingandthereforethereislimitedinformationonwhichtoassessthecumulativeimpactsofbothschemesduringconstruction.ItispresumedthattheproceduresandcontrolsthataredescribedintheNorthamptonGatewaySRFICEMPwithregardtotheneedtoagreewithHighwaysEnglandandNCCtheroutingofconstructiontrafficandthetrafficmanagementassociatedwiththeconstructionofthehighwaymitigationworkswouldalsoapplytoRailCentral.Thiswouldensurethatpotentialadversecumulativeenvironmentalimpactsthatcouldariseduringconstructionwouldbeminimised.

Impact on Highway Network and Vehicle Drivers (with Rail Central)12.8.8 AnalysisoftheNSTM2cumulativeimpactassessmenthasbeenundertakenforthestudyarea

junctionsidentifiedintheNorthamptonGatewayTA.TheassessmentshowsasignificantincreaseintrafficontheA508corridor,whichislargelyduetotheproposedA508RoadeBypassandtheproposedNorthamptonGatewaySRFIimprovementworksatM1Junction15releasingexistingbottlenecksanddrawingtrafficwhichwouldhavepreviouslyusedalternateroutesbackontotheA508.

12.8.9 TheNSTM2cumulativeimpactassessmentoutputsprovidedinTN12alsoshowsignificanttrafficincreasesontheA43andA5corridors.TheproposedRailCentralSRFIdevelopmentaccessesthehighwaynetworkfromtheA43andsolargetrafficincreaseswouldbeexpectedonthesecorridors.TheNorthamptonGatewaystudyareadoesnotextendtoincludetheA43andA5corridorsandthereforedetailedassessmentoftheimpactoftheadditionalRailCentraltrafficattheselocationshasnotbeenpossible.

12.8.10 TheanalysisprovidedintheNorthamptonGatewaySRFITransportAssessmentshowedthatasaresultoftheNorthamptonGatewayproposedhighwaymitigationtherewouldbereductionsintrafficthroughBlisworth,MiltonMalsorandRoade.TheresultsoftheNSTM2cumulativeimpactassessmentshowsthatingeneraltherewouldbecomparablereductionsthroughthesevillages,althoughthereisahigherwestboundflowforecastalongWateringLanethroughCollingtreeandMiltonMalsor.

Page 54: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 54

12.8.11 Therefore,theNSTM2cumulativeimpactassessmentdemonstratesthatthereisgenerallylittleinteractionbetweentheA508andA43corridorssouthoftheM1.

12.8.12 TothenorthoftheM1,theNSTM2cumulativeimpactassessmentshowsalargeincreaseinthewestboundflowalongtheA5076MereWayfromtheA45QueenEleanorInterchange,withfurtherwestboundtrafficincreasesfromtheA45WoottonInterchangethroughtheresidentialareasofWoottonandEastHunsbury.

12.8.13 TheTransportAssessmentfortheNorthamptonGatewaySRFIshowsthattrafficincreasesontheA5076corridorarerelativelymodestwhencomparedtothe2031(D1)ReferenceCase,asdevelopmenttrafficnorthoftheM1largelystaysontheA45corridor.However,thereissomereassignmentofbackgroundtrafficontotheA5076RingRoadcorridor.TheNSTM2cumulativeimpactassessmentshowsthatwhencomparedtotheNorthamptonGatewaySRFI,theRailCentralSRFIwouldsignificantlyincreasetrafficflowsalongtheA5123,A5076andSwanValleyWaycorridors.

12.8.14 Therefore,duetointeractionsbetweentrafficgeneratedbybothSRFIdevelopmentsandreassigningbackgroundtraffic,theNSTM2cumulativeimpactassessmentshowsthatthetrafficincreasesontheserouteswouldbemoresignificant,especiallyalongtheA5076RingRoadandthroughWoottonandEastHunsbury.

12.8.15 TheTransportAssessmentfortheNorthamptonGatewaySRFIconcludesthatthemodelledimpactattheWoottonInterchangeisaresultofrat-runningtrafficwhichisavoidingtheQueenEleanorInterchange.NCChaveconfirmedthattheyplantoimplementacomprehensiveimprovementschemeattheQueenEleanorInterchangewhichcoulddrawtrafficawayfromtheWoottonInterchange.IthasbeenagreedwiththeTWGthatratherthanpromotinganimprovementattheWoottonInterchange,itwouldbeappropriateforafinancialcontributiontowardsthiscomprehensiveschemetobesecuredaspartoftheNorthamptonGatewaySRFIdevelopment.HighwaysEnglandhavealsoconfirmedthisthisisacceptable.

12.8.16 ThecumulativeimpactassessmentresultsshowthattheperformanceoftheWoottonInterchangewoulddeteriorate.However,itisconsideredthattheabovestrategyremainsvalidandappropriatetoaddressthisimpactinthecumulativeimpactscenario.

12.8.17 IntheirMay2017publiclyavailablyhighwaymitigationproposals,RailCentralpromotedanimprovementschemeattheQueenEleanorInterchange.ThisschemehasbeenremovedfromthemitigationproposalspresentedattheirStage2StatutoryConsultation.Itisnotclearwhatthebasisforthisis.Basedontheabove,itisanticipatedthatRailCentralwillneedtoprovideafinancialcontributiontowardsthecomprehensiveNCCimprovementschemeatthisjunctionalthoughnomentionismadeofitintheRailCentralStage2StatutoryConsultationmaterial.

12.8.18 ThecumulativeimpactassessmentmodelresultsshowthattherewouldbeimpactsattheA45BarnesMeadowInterchange,theA45LumbertubsInterchangeandtheA4500/A5076gyratory.TherearenoimpactsatthesejunctionsintheNorthamptonGatewayonlyscenario.However,thedraftRailCentralTransportAssessmentissuedfortheStage2StatutoryConsultationshowsthatmitigationschemesareproposedatthesejunctionsanditisconsideredthatproposedRailCentralmitigationschemesatthesejunctionscouldpotentiallymitigatethecumulativeimpact.

Page 55: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 55

12.8.19 ThecumulativeimpactassessmentresultsshowthattherewouldbeimpactsattheA5076DanesCampWay/TowcesterRoad/TescogyratoryandattheA5123/A5076gyratory.HighwayimprovementschemesarepromotedatbothofthesejunctionstomitigatetheimpactoftheNorthamptonGatewaySRFI,asdetailedintheNorthamptonGatewayTransportAssessment.IthasbeenagreedwithNCCthatafinancialcontributiontoimprovingthewiderA5076corridorshouldbemade,equivalenttothecostofimplementingtheidentifiedNorthamptonGatewaymitigationschemes.ThescaleoftheidentifiedschemeswouldbeunlikelytomitigatethecumulativeimpactofthetwoSRFIdevelopments.However,thedraftRailCentralTransportAssessmentissuedfortheRailCentralStage2StatutoryConsultationpromoteslargermitigationschemesattheselocations,duetoRailCentralhavingagreatertrafficimpactthanNorthamptonGatewayatthesejunctions.ItisconsideredthattheidentifiedRailCentralschemescouldpotentiallymitigatethecumulativeimpact.

12.8.20 ThedetailedmodellingthereforesupportstheconclusionsofthestrategicNSTM2modellingthatthereisgenerallylittleinteractionbetweentheA508andA43corridorssouthoftheM1,andthattheadditionoftheRailCentralSRFIwouldnotadverselyimpactuponthebenefitstotheA508corridorprovidedbytheNorthamptonGatewaySRFIhighwaymitigationstrategy.

12.8.21 TheresultsoftheVISSIMmicro-simulationmodellingofM1Junction15and15AshowthatnetworkperformanceissignificantlyimprovedinthecumulativeimpactscenarioincomparisontotheReferenceCase,withtheNorthamptonGatewayandRailCentraldevelopmentsandassociatedjunctionimprovementsinplace.

12.8.22 ThecumulativeimpactassessmentVISSIMresultsshowthatjourneytimesforbothcarsandHGVsarereduced,withanaveragejourneytimereductionof18%forcarsand11%forHGVsinthemorningpeakhourwhencomparedtotheReferenceCasescenario.Intheeveningpeakperiod,thejourneytimesarereducedby41%forcarsandby36%forHGVs.

12.8.23 Nonetheless,therewouldbesomeimpactsintermsofqueueinginthecumulativeimpactassessmentscenario,notpresentintheNorthamptonGatewayonlymodelling,detailedasfollows:

• InthemorningpeakhourthemaximumqueuelengthontheM1northbounddivergeatM1Junction15isforecasttoexceedthestoragecapacityonthesliproadandcouldpotentiallyimpactontheM1mainline.ThisisnotpresentintheReferenceCase.

• InthemorningpeakhourtheaveragequeueontheM1southbounddivergeatM1Junction15wouldreachbackbeyondtheendofthesliproadwhereitwouldimpactontheM1mainlineflow.ThisoccurstoagreaterextentintheReferenceCaseandsowouldstillrepresentanimprovement.

• AlthoughstillanimprovementontheReferenceCasescenario,thequeuelengthsontheM1northbounddivergeatM1Junction15AwouldextendbacktotheM1mainlinebeforetheendofthecumulativeimpactassessmenteveningpeakhour.

• OntheA43approachtoM1Junction15AtheaverageandmaximumqueuelengthsintheeveningpeakhourontheA43areshowntoincreasesignificantlyinthecumulativeimpactassessment scenario.

12.8.24 ArevisedM1Junction15AimprovementschemetothatincludedinthecumulativeimpactVISSIMmodellingwaspresentedbyRailCentralaspartoftheirStage2StatutoryConsultation.Thisrevisedmitigationschemereducesthescaleofthemitigationproposals.However,itisnotanticipatedthattherevisedlayoutwouldmateriallychangetheconclusionsdrawnfromthecumulativeassessmentVISSIMmodellingasthealterationstotheschemedonotsubstantiallychangetheproposalsfortheM1sliproads.

12.8.25 ManyoftheconclusionsabovearetentativeintheabsenceofthefinalmitigationstrategyfortheRailCentralscheme,whichisnotyetavailable.

Page 56: 12. TRANSPORTATION€¦ · TRANSPORTATION 12.1 INTRODUCTION ... proposed design measures required to prevent, reduce or offset any significant adverse effects, and the likely residual

CHAPTER 12 - PG 56

Impact on Pedestrians, Cyclists Equestrians and the community (with Rail Central)12.8.26 TherewouldnotbeanyinteractionbetweenthepublictransportstrategiesforthetwoSRFI

developmentsandthereforetherewouldnotbeanadverseimpact.

12.8.27 WithintheNorthamptonGatewaySRFIsite,publicfootpathsKX17andKX13thatcrossthemainsitewouldbedivertedandextendedtoformaloopwithinthelandscapebunding.Tothesouth,apublicfootpathwouldcompletethenewlooparrangementlinkingwiththeexistingpublicfootpathandbridgeovertheWestCoastMainlinerailway.TheemergingRailCentralproposalalsoincludesforafootpathovertherailwaylinewiththepaththentrackingalongsidetherailwaylinebeforecrossingagaintothenorth.However,therespectivestrategiesforPRoWKX17areincompatible.

12.8.28 TheRailCentralStage2StatutoryConsultationmaterialprovidesnodetailsofthelikelyimpactsonexistingPRoWKX2/LA13southofJunction15A,orhowthisroutewillbeaccommodatedwithinthehighwaysmitigationworksthatareproposedbyRailCentralatM1Junction15A.

12.9 STATEMENT OF EFFECTS

12.9.1 Asaresultoftheproposeddesignandhighwaymitigationworks,theeffectsoftheProposedDevelopmentonthesurroundinghighwaynetworkwillnotresultinanypermanentmoderateormajorsignificantadverseresidualeffects.

12.9.2 ThemeasuresandproceduresoutlinedintheConstructionManagementEnvironmentalPlanwillensurethattheanyadverseenvironmentalimpactsduringconstructionareminimised.Overallitisconcludedthattheconstructionphaseofthedevelopmentwouldhaveatemporary adverse impact of moderate significanceontheoperationofthesurroundinghighwaynetwork.

12.9.3 Oncefullyoperational,theProposedDevelopmentwouldremoveover92millionHGVmilesperyearfromthehighwaynetworkequatingtoover£50millioninmonetisedenvironmentalbenefitsperyearascalculatedusingthemethodologysetoutintheDepartmentforTransport’sGuidetoModeShiftRevenueSupportScheme.TheProposedDevelopmentwouldprovideadistributionhub,meaningthatHGVjourneydistanceswouldbereduced,reducingoverallHGVmileageontheroadnetwork.TakentogethertheabovemodalshiftandresultantreductioninoverallHGVmileage represents a permanent beneficial impact of major significance.

12.9.4 TheproposedhighwaymitigationworksarerequiredtoprovidesatisfactoryaccesstotheProposedDevelopmentandtoaccommodatethetrafficreassignmenteffectsresultingfromboththedevelopmenttrafficandproposedhighwaymitigationworks.ThehighwayworksalsoreleaseconstraintsontheA508,andatM1Junction15andJunction15A,allowingtheexistinghighwaynetworktofunctioninasaferandmoreefficientmanner.ThisinturndrawstrafficbackontotheexistingprincipalandSRN.Indoingsotrafficflowsonmanyofthesurroundinglocalroadsandvillageswouldreduce,ascomparedtotheReferenceCase.Therefore,theresidualeffectsoftheProposedDevelopmentandhighwaymitigationworksingeneraltrafficimpacttermscanbesummarisedasapermanent beneficial impact of major significance.

12.9.5 Withregardstoimpactsonpedestrians,cyclists,equestriansandthecommunityitisconcludedthattheProposalDevelopmentwouldhavepermanent adverse impact of minor significance on amenityandanegligibleimpactonseveranceandjourneylengthandonlocaltravelpatterns.

12.9.6 ItisconcludedforimpactsonvehicledriversthattheProposedDevelopmentandassociatedhighwaymitigationworkswouldhaveapermanent beneficial impact of moderate significance ondriverstressandanegligible impactonviewfromtheroad.

12.9.7 ObservationshavebeenmaderegardingthecumulativeimpactofNorthamptonGatewayandRailCentralhowevertheyaretentativeasRailCentral’songoingassessmentworkmayleadtofurtherchangestotheirhighwaymitigationstrategy,whichinturncouldalterthecumulativeeffects.