12 Tools to Make Waste Visible

Embed Size (px)

Citation preview

  • 7/27/2019 12 Tools to Make Waste Visible

    1/37

    2001 ConceptFlow 1

    Tools to Make Waste Visible

  • 7/27/2019 12 Tools to Make Waste Visible

    2/37

    2001 ConceptFlow 2

    Module Objectives

    By the end of this module participants should be able to: Develop a Spaghetti Chart to identify waste

    Develop a Process Flow Diagram to identify waste

    Create a Pareto Chart to identify waste

    Develop a Cause and Effect Diagram to identify waste

    Utilize Process Reports and Assessments to identify waste

  • 7/27/2019 12 Tools to Make Waste Visible

    3/37

    2001 ConceptFlow 3

    * Womack, J. P. and D. T. Jones, 1996, Lean Thinking, Simon & Schuster

    Recall The Five Principles Of Lean Thinking

    Lean Thinking can be summarized in five principles*: Principle 1 - Precisely specify the value of a specific process

    Principle 2 - Identify the value stream for each process

    Principle 3 - Allow value to flow without interruptions

    Principle 4 - Let the client pull value from the process

    Principle 5 - Continuously pursue perfection

  • 7/27/2019 12 Tools to Make Waste Visible

    4/37

    2001 ConceptFlow 4

    What Tools Exist To Make Waste Visible?

    Workplace Organization 5S

    Visual Workplace

    Spaghetti Chart

    Pareto Chart

    Cause and Effect Diagram

    Five Whys

    Process Reports and Assessments

  • 7/27/2019 12 Tools to Make Waste Visible

    5/37

    2001 ConceptFlow 5

    Manufacturing Waste

    Types ofWaste Overproduction

    Inventory

    Waiting

    Transportation

    Motion

    Making Defects

    Overprocessing

    Contributors to Waste Unevenness

    Overburden

    Current Methods and Processes

  • 7/27/2019 12 Tools to Make Waste Visible

    6/37

    2001 ConceptFlow 6

    Additional Tools: Spaghetti Chart

  • 7/27/2019 12 Tools to Make Waste Visible

    7/37 2001 ConceptFlow 7

    Spaghetti Chart

    Obtain a layout List the steps in the process

    Draw the path of the process from start to finish on the layout

  • 7/27/2019 12 Tools to Make Waste Visible

    8/37 2001 ConceptFlow 8

    Example Spaghetti Chart - Round #1 Of DotGame

    Red Glow

    Dept.

    Yellow Glow

    Dept.

    Inspection

    Red

    Dept. Orange

    Glow

    Dept.

    Yellow

    Dept.

    Client

    1

    2

    3

    4

    5

    6

    8

    O

    B

    ST

    R

    U

    C

    TI

    ONRec/Ship/

    Stock

    7

    O

    B

    ST

    R

    U

    C

    TI

    O

    N

  • 7/27/2019 12 Tools to Make Waste Visible

    9/37 2001 ConceptFlow 9

    Constructing a Spaghetti Chart

  • 7/27/2019 12 Tools to Make Waste Visible

    10/37 2001 ConceptFlow 10

    Waste Map

    Remarks

    1

    DescriptionStep

    2345

    6789

    101112131415

    Team

    DateComments

    Component

    Operation

    Activity Analysis

    Action Study

    Waste Map.ppt

  • 7/27/2019 12 Tools to Make Waste Visible

    11/37 2001 ConceptFlow 11

    Additional Tools: Pareto Charts

  • 7/27/2019 12 Tools to Make Waste Visible

    12/37 2001 ConceptFlow 12

    Pareto Chart

    A descending bar graph that helps to focus on the problems that offerthe greatest potential for improvement by showing their relative

    frequency or size

    Compare the relative frequency or cost of each problem category

    List the categories in descending order from left to right on the

    horizontal axis The height of the bars corresponds to the frequency or cost

  • 7/27/2019 12 Tools to Make Waste Visible

    13/37 2001 ConceptFlow 13

    Pareto Chart Example

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    B

    E

    G

    A

    C

    D

    F

    A = 19

    B = 45

    C = 12 D = 7

    E = 32

    F = 5

    G = 25

  • 7/27/2019 12 Tools to Make Waste Visible

    14/37

    2001 ConceptFlow 14

    Team Pareto Exercise

    For the Electrical Connector Exercise Flipchart a Pareto of the frequency of steps versus each element of

    production (SHIP)

    Where is the greatest opportunity for improvement?

  • 7/27/2019 12 Tools to Make Waste Visible

    15/37

    2001 ConceptFlow 15

    Pareto Chart Solution

    Where is the greatest improvement opportunity?

  • 7/27/2019 12 Tools to Make Waste Visible

    16/37

    2001 ConceptFlow 16

    Exercise - Pareto Chart

    Given the following data, construct a Pareto chart Item A, Frequency = 22

    Item B, Frequency = 11

    Item C, Frequency = 17

    Item D, Frequency = 5

    Item E, Frequency = 8

  • 7/27/2019 12 Tools to Make Waste Visible

    17/37

    2001 ConceptFlow 17

    Pareto Chart Solution

    The Pareto can be created in Excel or MINITAB

    0

    10

    20

    30

    A C B E D

    Pareto Chart Solution

    Series1

  • 7/27/2019 12 Tools to Make Waste Visible

    18/37

    2001 ConceptFlow 18

    Additional Tools: Cause and Effect Diagram

  • 7/27/2019 12 Tools to Make Waste Visible

    19/37

    2001 ConceptFlow 19

    Cause And Effect Diagram (FishboneDiagram)

    Used to allow team to identify and graphically display, in increasingdetail, all potential root causes

    Place problem (effect) in box on right-hand side of chart

    Draw major cause categories as bones on chart

    Repeatedly ask why each cause happens

    Look for root cause that appears repeatedly within or across majorcauses

  • 7/27/2019 12 Tools to Make Waste Visible

    20/37

    2001 ConceptFlow 20

    Source Categories For Potential Causes

    People

    Do they follow standards?

    Efficiency acceptable?

    Are they problem conscious?

    Are they responsible?

    Are they qualified?Are they experienced?

    Are they assigned to the right job?

    Are they willing to improve?

    Do they maintain good human

    relations?Are they healthy?

    Machines (facilities)

    Do they meet production

    requirements?

    Process capability?

    Oiling, greasing adequacy?

    Is inspection adequate?

    Frequency of down-time and why?

    Does it meet precision

    requirements?

    Unusual noises?

    Layout adequacies?

    Are there enough machines/

    facilities?

    Are they in good working order?

    Preventative maintenance schedule?

  • 7/27/2019 12 Tools to Make Waste Visible

    21/37

    2001 ConceptFlow 21

    Source Categories For Potential Causes

    Material

    Mistakes in volume?

    Mistakes in grade?

    Mistakes in brand name?

    Are there impurities mixed up?

    Is the inventory level adequate? How much WIP is there? Where?

    Is the layout adequate to

    accommodate materials?

    Is the quality standard adequate?

    Method (operation)

    Are the work standards adequate?

    Is the work standard upgraded?

    Is is a safe procedure or method?

    Does it ensure a good product?

    Is the method efficient? Is the sequence of work adequate?

    How is it setup?

    Is the setup adequate?

    Is there adequate contact/

    communication with the upstreamand downstream steps?

    What method is used to

    communicate?

  • 7/27/2019 12 Tools to Make Waste Visible

    22/37

    2001 ConceptFlow 22

    Team Exercise - Your Turn!

    Measurements

    Environment

  • 7/27/2019 12 Tools to Make Waste Visible

    23/37

    2001 ConceptFlow 23

    Basic Structure Of The C&E Diagram

    Problem/

    Desired

    Improvement

    Causes Effect

    Main Category

    Measurements Materials People

    Environment Methods Machines

  • 7/27/2019 12 Tools to Make Waste Visible

    24/37

    2001 ConceptFlow 24

    Level 1 Cause

    Basic Structure - Level 1 Causes

    Problem/

    Desired

    Improvement

    Causes Effect

    Main Category

    Measurements Materials People

    Environment Methods Machines

  • 7/27/2019 12 Tools to Make Waste Visible

    25/37

    2001 ConceptFlow 25

    Five Whys?

    1. Ask why?2. When presented with an answer, ask why?

    3. Add additional levels to the C&E diagram

    4. Repeat step two until you get the real problem or issue identified

  • 7/27/2019 12 Tools to Make Waste Visible

    26/37

    2001 ConceptFlow 26

    Business Process Example - The Five Whys

    The Five Whys Method -Supervisor: Why is the sales order being released so late?

    Employee: Because the client requirements are not entirely known

    Supervisor: Why are the client requirements not known?

    Employee: Because the proposal was vague and incomplete

    Supervisor: Why was the proposal vague and incomplete?Employee: Because the performing organization didnt participate

    in creating it

    Supervisor: Why didnt the proposal team consult with the properexperts?

    Employee: Because we hardly ever talk with those guysSupervisor: Why is communication so poor between departments?

    Engineer: Because that is how we always do proposals, and wedont have a process that encourages us to worktogether

  • 7/27/2019 12 Tools to Make Waste Visible

    27/37

    2001 ConceptFlow 27

    Problem/

    Desired

    Improvement

    Causes Effect

    Level 1 Cause

    Level 2 Cause

    Main Category

    Measurements Materials People

    Environment Methods Machines

    Basic Structure - Level 2 Causes

  • 7/27/2019 12 Tools to Make Waste Visible

    28/37

    2001 ConceptFlow 28

    Construction Of The Diagram

    MethodsMaterials

    Machinery Personnel

    Problem/

    DesiredImprovement

    C/N/Sc c

    s

    cc

    n n

    nnn

    Shows various influences on a process to identify

    probable root causes of problem or defect

    C = Control Factor

    N = Noise factor

    S = Standard Operating Procedure

  • 7/27/2019 12 Tools to Make Waste Visible

    29/37

    2001 ConceptFlow 29

    Schedule Changes

    Estimated

    Ship Date

    Changes

    PEOPLE

    ENVIRONMENT

    SUPPLIES

    POLICIES & PROCEDURES

    MEASUREMENTS

    PLACES

    Algorithm Anomalies

    MDC

    NCSC

    MDC Ship Confirm Late

    Back Order Consolidation

    NCSC Practices

    Inventory Accuracy

    Order Entry

    Order Cancellations

    Off Shift Support

    In Transit Times

    MDC Practices

    PC Delays

    Business Process Example - Estimated ShipDate Change

  • 7/27/2019 12 Tools to Make Waste Visible

    30/37

    2001 ConceptFlow 30

    Estimated Ship Date Changes

    Order Cancellations

    Inventory Accuracy

    Schedule Changes

    PC Delays

    In Transit Time

    NCSC

    MDC

    MDC Practices

    NCSC Practices

    Algorithm Anomalies

    MDC Ship Late

    Off Shift Support

    Backorder Consolidat

    Order Entry

    People

    Policies & Procedures

    Supplies

    Places

    Measurements

    Environment

    C&E for Estimated Ship Date Changes

    MINITAB Generated C&E Diagram

  • 7/27/2019 12 Tools to Make Waste Visible

    31/37

    2001 ConceptFlow 31

    Process Reports And Assessments

    Various Types: Present Value Stream Map and Future Value Stream Map Existing Quality Reports; Control Charts Product Cost COPQ: recorded defect and scrap cost/rates Manufacturing Operation or Process Documents

    Current Control Plans Standard Operating Procedures Manufacturing Lead TimeAttendance Safety Downtime Preventative Maintenance Schedules Expedited Transportation Material Shortages Throughput Yield Current Visual Controls

  • 7/27/2019 12 Tools to Make Waste Visible

    32/37

    2001 ConceptFlow 32

    Case Example - Prioritize Waste/DefectOpportunities

    Dark Gray - Greatest Potential Benefit

    Gray - Worthwhile Opportunity

    Revise

    Continue

    C/T = 14 days

    W/T = 2 days

    VA/T = 1 day

    Customer

    Meetings

    C/T = 14 daysW/T = 2 days

    VA/T = 1 day

    Verify

    Customer

    Requirements

    C/T = 5 daysW/T = 2 days

    VA/T = 4 hours

    Consult With

    Manufacturing

    Engineer

    C/T = 5 daysW/T = 2 days

    VA/T = 1 day

    Create

    Preliminary

    RFQ

    C/T = 14 daysW/T = 2 days

    VA/T = 1 day

    Gather Strawman

    Requirements

    C/T = 3 daysW/T = 4 hours

    VA/T = ~ 0

    Assign Buyer

    C/T = 5 days

    W/T = 1 day

    VA/T = ~ 0

    Review and

    Approval Cycle

    C/T = 5 days

    W/T = 2 days

    VA/T = 1 day

    Create Final

    RFQ

    C/T = 5 days

    W/T = 1 day

    VA/T = ~0

    Review and

    Approval Cycle

    C/T = 2 days

    W/T = 1 day

    VA/T = 2 hours

    Release RFQ

    Continue

    Iterate

    Revise

  • 7/27/2019 12 Tools to Make Waste Visible

    33/37

    2001 ConceptFlow 33

    Case Example - Identify Lean Methods AndAssign Action Items

    Waste Opportunity Impact Ease Priority Six Sigma/Lean Method1. Eliminate first iteration loop to

    determine client needs

    2. Reduce time to gather strawman

    requirements

    3. Reduce time required to consult

    with manufacturing engineer

    4. Eliminate first approval cycle

    5. Reduce final approval cycle

    6. Reduce time to assign buyer

    5 3 15

    5 2 10

    3 3 9

    4 3 12

    4 4 16

    3 3 9

    Hold focused client needs

    negotiation meeting

    Use template or checklist to

    accelerate info. gathering

    Involve ME in client meetings or

    use a feed forward of info.

    Use client-defined template and

    feed forward of prelim. info.

    Use a reservation system to

    enable immediate review

    Implement real-time priority

    system to eliminate queue

    Now assign responsibilities and due dates... and get started!

  • 7/27/2019 12 Tools to Make Waste Visible

    34/37

    2001 ConceptFlow 34

    Case Example - Map Future State, PerformDemo, And Deploy

    Targets for First Round

    Improvement:

    C/T = 16 days

    W/T = ~8 days

    VA/T = 5 days

    As-Is Process

    Cycle Time:

    C/T = 58 days

    W/T = ~14 days

    VA/T = 5 days

    Revise

    Continue

    C/T = 14 days

    W/T = 2 days

    VA/T = 1 day

    Customer

    Meetings

    C/T = 2 days

    W/T = 2 days

    VA/T = 1 day

    Hold Focused

    Customer Needs

    Negotiation

    C/T = 5 days

    W/T = 2 days

    VA/T = 4 hours

    Consult With

    Manufacturing

    Engineer

    C/T = 5 days

    W/T = 2 days

    VA/T = 1 day

    Create

    Preliminary

    RFQ

    C/T = 5 days

    W/T = 2 days

    VA/T = 1 day

    Gather Strawman

    Requirements

    C/T = 1 day

    W/T = 4 hours

    VA/T = ~ 0

    Assign Buyer

    C/T = 5 days

    W/T = 1 day

    VA/T = ~ 0

    Review and

    Approval Cycle

    C/T = 5 days

    W/T = 2 days

    VA/T = 1 day

    Create Final

    RFQ

    C/T = 1 day

    W/T = 1 day

    VA/T = ~0

    Review and

    Approval Cycle

    C/T = 2 days

    W/T = 1 day

    VA/T = 2 hours

    Release RFQ

    Continue

  • 7/27/2019 12 Tools to Make Waste Visible

    35/37

    2001 ConceptFlow 35

    Key Learning Points

  • 7/27/2019 12 Tools to Make Waste Visible

    36/37

    2001 ConceptFlow 36

    Module Review

    By the end of this module participants should be able to:

    Develop a Spaghetti Chart to identify waste

    Develop a Process Flow Diagram to identify waste

    Create a Pareto Chart to identify waste

    Develop a Cause and Effect Diagram to identify waste

    Utilize Process Reports and Assessments to identify waste

  • 7/27/2019 12 Tools to Make Waste Visible

    37/37

    Trademarks and Service Marks

    Six Sigma is a federally registered trademark of Motorola, Inc.

    Breakthrough Strategy is a federally registered trademark of Six Sigma Academy.

    VISION. FOR A MORE PERFECT WORLD is a federally registered trademark of Six Sigma Academy.

    ESSENTEQ is a trademark of Six Sigma Academy.

    FASTART is a trademark of Six Sigma Academy.

    Breakthrough Design is a trademark of Six Sigma Academy.

    Breakthrough Lean is a trademark of Six Sigma Academy.

    Design with the Power of Six Sigma is a trademark of Six Sigma Academy.

    Legal Lean is a trademark of Six Sigma Academy.

    SSA Navigator is a trademark of Six Sigma Academy.

    SigmaCALC is a trademark of Six Sigma Academy.

    iGrafxis a trademark of Micrografx, Inc.

    SigmaTRAC is a trademark of DuPont.

    MINITAB is a trademark of Minitab, Inc.