12 SEPTEMBER 2012

SELECT COMMITTEE ON EDUCATION AND RECREATION

(Progress on Accelerated Schools Infrastructure Delivery Initiative (ASIDI))

1

Page 2: 12 SEPTEMBER 2012

ASIDI BACKGROUND

2

Page 3: 12 SEPTEMBER 2012

SCHEDULE 7: SCHOOL INFRASTRUCTURE BACKLOGS GRANT

• The purpose of the grant is – for the eradication of entire inappropriate schools;– provision of basic level of water, sanitation and

electricity to schools.

• The grant is also referred to as the ASIDI (Accelerated School Infrastructure Delivery Initiative)

3

Page 4: 12 SEPTEMBER 2012

ASIDI Targets

The targets are as follows:

Infrastructure Category Baseline 2011/2012 2012/2013 2013/2014 Inappropriate Structures 496 50 100 346 Water 1257 188 1069 Electrification 878 164 714 Sanitation 868 354 514 Specialist Classrooms 50

MTEF ALLOCATIONS2011/12 R 7002012/13 R2 3152013/14 R5 189TOTAL R8 204

The budget allocation for the ASIDI programme over the MTEF period is R8.2 billion and allocated as indicated in the table below:

4

Page 5: 12 SEPTEMBER 2012

ASIDI 2011/12 FINANCIAL BUDGET SPLIT

• In 2011/12 financial year the budget split was as follows– R420mil was allocated towards the eradication of 50

entire mud schools;– R280mil was allocated towards provision of water,

sanitation and electricity to schools

5

Page 6: 12 SEPTEMBER 2012

ASIDI IMPLEMENTATION STRUCTURE

6

Page 7: 12 SEPTEMBER 2012

ASIDI : PROGRAMME IMPLEMENTATION STRUCTURE

7

• The programme is driven by Department of Basic Education (DBE) has established a Project Support Unit to support the Programme Manager.

• The DBE works closely with its provincial counterparts at Provincial Education Departments (PEDs) to prioritise and assess the needs for specific projects.

• PED’s interacts with the Provincial Public Works Departments as custodians to coordinate the improvement of the facilities.

• DBE will appoint Implementing Agents to manage batches of projects.

• The Implementing Agents will appoint professional service providers and contractors to execute the work.

Page 8: 12 SEPTEMBER 2012

ASIDI : PROGRAMME IMPLEMENTATION STRUCTURE

8

Page 9: 12 SEPTEMBER 2012

ASIDI 2011/12 IMPLEMENTATION

9

Page 10: 12 SEPTEMBER 2012

ASIDI 2011/12 TARGETS

10

Inappropriate Electricity Sanitation Water Province Eastern Cape 50 104 58 84Free State 0 26 13 32Gauteng 0 2 7 0KwaZulu Natal 0 0 82 10Limpopo 0 4 40 38Mpumalanga 0 47 0 0North West 0 0 0 0Northern Cape 0 0 16 6Western Cape 0 7 21 3Total 50 190 237 173

The following work was implemented during the 2011/12 financial year:

Page 11: 12 SEPTEMBER 2012

ASIDI IMPLEMENTING AGENTS 2011/12

• DBSA is the appointed Implementing Agent for the 50 inappropriate schools in the Eastern Cape

• However only 49 schools are being implemented, 1 school is being implemented by EC DoE and has therefore been removed from the ASIDI programme,

• Mvula Trust is appointed to implement water and sanitation projects in Limpopo and Eastern Cape

• Eskom is the appointed Implementing Agent for electrification of schools in Eastern Cape, Mpumalanga and Limpopo Provinces.

• Free State, Gauteng, KZN and Western Cape were the Implementing Agents in 2011/12 financial year.

11

Page 12: 12 SEPTEMBER 2012

ASIDI ACTUAL FINANCIAL COMMITTMENTS 2011/12

• The actual commitments made in 2011/12 financial year– R841mil was committed towards the eradication of

school infrastructure (including professional fees, etc.);– R217.3mil was committed towards provision of water,

sanitation and electricity to schools

• Therefore approximately R1.058bil was committed in contracts for the ASIDI implementation during the 2011/12 financial year.

12

Page 13: 12 SEPTEMBER 2012

Progress ReportInappropriate Schools

13

Page 14: 12 SEPTEMBER 2012

Overall Contractors’ Physical Progress As At (ASSESSMENTS 13-17 August)

Page 15: 12 SEPTEMBER 2012

ASIDI 2011/12 INAPPROPRIATE SCHOOLS PROGRESS (ASSESSMENTS 13-17 August)

Contractor Contract No No. Sch Sch ID School Name Building Progress Building Progress (Mean)

Armstrong RFP 29/2011-E 12 Schools

1 Qaka JPS 54.10%

43.30%

2 Ntsonyini JSS 43.20%4 Ngidini SPS 50.30%

10 Ndluzula JPS 36.40%11 Nomandla SPS 52.70%15 Gcinizizwe SPS 70.10%20 Maqolo SPS 43.40%24 Jonguxolo JSS 52.00%27 Vuyani SPS 36.40%30 Sidanda SPS 33.10%36 Tembeni SPS 23.70%38 Sizwe JPS 19.70%

15

Page 16: 12 SEPTEMBER 2012

ASIDI 2011/12 INAPPROPRIATE SCHOOLS PROGRESS:DBSA

Contractor Contract No No. Sch Sch ID School Name Building Progress

Building Progress (Mean)

Keren Kula Construction RFP 31/2011-I 10 Schools

5 Mpatiswa SPS 69.80%

49.70%

7 Zingisile SPS 41.20%14 Goso JPS 27.30%18 Eludikidi SPS 32.70%

25 Upper Mbange SPS 53.30%

32 Welese JSS 53.50%33 Sizane JSS 51.30%46 Nginza SPS 37.40%

50 Lower Mpako SPS 34.50%

16

Page 17: 12 SEPTEMBER 2012

ASIDI 2011/12 INAPPROPRIATE SCHOOLS PROGRESS:DBSA

Contractor Contract No No. Sch Sch ID School Name Building Progress

Building Progress (Mean)

SSI Mafuri JV RFP 29/2011-F1 6 Schools

12 Manzabila SPS 55.50%

49.70%

13 Gqweza SPS 56.80%

28 Tshantshala SPS 48.30%

29 Mseleni SPS 37.80%31 Mceteni SPS 40.70%

37 Maphindela SPS 59.40%

TBP RFP 29/2011-F2 6 Schools

16 Gungubele SPS 34.60%

28.20%

21 Mahahane SPS 21.70%22 Madwaleni SPS 35.60%23 Ludeke SPS 21.20%34 Sompa SPS 19.20%35 Nkonkoni SPS 36.80% 17

Page 18: 12 SEPTEMBER 2012

ASIDI 2011/12 INAPPROPRIATE SCHOOLS PROGRESS:DBSA

Contractor Contract No No. Sch Sch ID School Name Building Progress

Building Progress (Mean)

Trencon Construction RFP 31/2011-G 5 Schools

3 Notsolo SPS 55.80%

59.40%

6 Mqokolweni SPS 57.10%

9 Ndlovayiphathwa SPS 52.90%

19 Mdavuza SPS 65.80%26 Dumile SPS 65.30%

     Alfdav Construction RFP 31/2011-F x1 45 Vulindlela JPS 65.20%Base Major Construction RFP 31/2011-H x1 40 Mazama SPS 51.00%Cecils RFP 29/2011-C x1 48 Kwezilethu JPS 68.90%Keren Kula (Inyameko/ Vukukhanye) RFP 31/2011-B

x1 17 Dikiso JSS 22.30%

Inyameko Deck Steel JV RFP 31/2011-C x1 41 Thabatha SPS 65.50%

18

Page 19: 12 SEPTEMBER 2012

ASIDI 2011/12 INAPPROPRIATE SCHOOLS PROGRESS:DBSA

Contractor Contract No No. Sch Sch ID School Name Building Progress

Building Progress (Mean)

Ishvuyo Building Construction RFP 31/2011-E x1 44 Dakhile JSS 88.70%

Leungo Construction RFP 31/2011-D x1 43 Dumakude JPS 35.30%

Marnolda RFP 29/2011-B x1 47 Kwenxura SPS 64.30%Mauga Projects cc RFP 31/2011-A x1 8 Nogaya SPS 41.90%Setheo RFP 29/2011-A x1 39 Mandlobe SPS 36.60%Sizisa Ukhanyo RFP 29/2011-D x1 49 Nobantu JPS 67.60%

46.80%

19

Page 20: 12 SEPTEMBER 2012

ASIDI 2011/12 PROGRESS ANALYSIS: INAPPROPRIATE SCHOOLS

• The planned completion date of 20 August has lapsed.– Various on-site conditions have been cited as the cause and

they include,• Poor accessibility of site due to lack of proper roads• Difficult terrain• Physical features• Inclement weather• Difficulty in obtaining material supply

20

Page 21: 12 SEPTEMBER 2012

ASIDI 2011/12 PROGRESS ANALYSIS: INAPPROPRIATE SCHOOLS

• In summary progress is as follows– Progress at 2 of the schools is between 10.1% and 20%– Progress at 5 of the schools is between 20.1% and 30%– Progress at 12 of the schools is between 30.1% and 40%– Progress at 6 of the schools is between 40.1% and 50%– Progress at 14 of the schools is between 50.1% and 60%– Progress at 8 of the schools is between 60.1% and70%– Progress at 1 of the schools is over 70.1%– Progress at 1 of the schools is over 80.1%

21

Page 22: 12 SEPTEMBER 2012

Progress ReportServices

22

Page 23: 12 SEPTEMBER 2012

ASIDI 2011/12 WATER AND SANITATION SCHOOLS PROGRESS : MVULA TRUST

PROGRESS IN LIMPOPO

• Forty (40) of the 40 sanitation projects have achieved practical completion.

• Thirty-eight (38) of the 38 water projects have been completed.

23

Page 24: 12 SEPTEMBER 2012

PROGRESS IN EASTERN CAPE

ASIDI 2011/12 WATER AND SANITATION SCHOOLS PROGRESS : MVULA TRUST

• Fifty-Eight (58) of the 58 sanitation projects have achieved practical completion.

• Eighty-four of the 84 schools have been provided with Rain Water Harvesting tanks and related infrastructure.

• Thirty-one (31) of the 32 projects have been connected to municipal bulk supply.

• None on the 49 projects identified for borehole connections are completed yet.

24

Page 25: 12 SEPTEMBER 2012

ASIDI 2011/12 WATER AND SANITATION SCHOOLS PROGRESS : WC

• Western Cape is the Appointed Implementing Agent.• Project scope entailed upgrading of water, ablution

facilities & electrical and sanitation facilities. The targets were 7 schools for electrification, 21 schools for Sanitation and upgrading of water in 3 schools.

• All projects have achieved final completion.

25

Page 26: 12 SEPTEMBER 2012

ASIDI 2011/12 WATER AND SANITATION SCHOOLS PROGRESS : GAUTENG

• Gauteng DoE is the appointed Implementing Agent.• Seven (7) sanitation projects were implemented and two

(2) electrification projects. All nine projects have achieved practical completion.

26

Page 27: 12 SEPTEMBER 2012

ASIDI 2011/12 WATER AND SANITATION SCHOOLS PROGRESS : KZN

• KZN is the Implementing Agent. There were 88 schools identified in this Programme, after assessments 5 schools were taken out after it was found that they were already addressed.

• 33 schools have been completed, 13 projects are in progress and are between 90% and 99%

• Completion date is projected for 30 September 2012 for remaining projects.

• The balance of the 40 schools are on site but were delayed due to Inclement weather and procurement challenges.

• Projects are between 25% and 90% complete • Projected completion date is 30 October 2012

27

Page 28: 12 SEPTEMBER 2012

ASIDI 2011/12 WATER AND SANITATION SCHOOLS PROGRESS : FREE STATE

• Free State DoE is the Implementing Agent.• Water - 30; Sanitation - 12; Electricity – 24• Progress on projects:

– Water – Finalising final completion defects lists. – Sanitation – All VIP’s reached final completion. Both mobile ablution

practical completion reached.– Electricity – All final completion, except Huntersvlei are done by ESKOM

– final completion scheduled for Sept 2012.

28

Page 29: 12 SEPTEMBER 2012

PROGRESS IN EASTERN CAPE

ASIDI 2011/12 WATER AND SANITATION SCHOOLS PROGRESS : MVULA TRUST

• Fifty-Eight (58) of the 58 sanitation projects have achieved practical completion.

• Eighty-four of the 84 schools have been provided with Rain Water Harvesting tanks and related infrastructure.

• Thirty-one (31) of the 32 projects have been connected to municipal bulk supply.

29

Page 30: 12 SEPTEMBER 2012

ASIDI 2011/12 ELECTRIFICATION OF SCHOOLS PROGRESS : ESKOM

ProvinceTotal Planned Connections

July Planned Connections

July Actual Connections

YTD Planned Connections

YTD Actual Connections

Eastern Cape 100 11 14 61 48Mpumalanga 31 0 0 10 0Limpopo 5 0 2 3 3Grand Total 136 11 16 74 51

30

Page 31: 12 SEPTEMBER 2012

EXPENDITURE

31

Page 32: 12 SEPTEMBER 2012

ASIDI: TOTAL EXPENDITURE

32

• 2011/12 commitments were approximately R1bil• R59.7mil was paid in 2011/12 and R944.9mil was carried over into the 2012/13 financial

year.• R2.3bil is the allocated budget for 2012/13 and commitments carried over are funded

through the allocated budget.

Description 2011/12 Commitments

Expenditure as at 31 March

2012

2012/13 Budget

Allocation

Commitments Carried Forward from 11/12

Expenditure as at June 30, 2012

Expenditure as at August 29, 2012

R’000 R’000 R’000 R’000 R’000 R’000

Inappropriate Structures 48 353 114 257

212 080

 Sanitation 7 918  42 337  42 337

 Water 1 116  14 299  14 434

 Electricity 42    7 399    7 399

 Other 2 254 2 622 8 405

 TOTAL 1 040 849

59 683 2 315 000 987 467 180 914

284

520

Page 33: 12 SEPTEMBER 2012

CHALLENGES IN THE 1ST YEAR OF ASIDI IMPLEMENTATION

33

Page 34: 12 SEPTEMBER 2012

ASIDI CHALLENGES IN 2011/12

• Progress has been delayed on the construction of the 49 schools due to the following challenges:– Procurement of Implementing Agents took longer than anticipated.

Negotiations with the Independent Development Trust (IDT) commenced in February 2011 as the implementing agent for the programme.

– However, in April 2011, when negotiations with IDT were to be concluded, it was indicated that the Development Bank of South Africa, (DBSA) should be used as the implementing agent.

– Negotiations with DBSA started in April 2011. – There were delays in the finalisation of the MOA with the DBSA as the bank

had to receive approval from the Minister of Finance before the MOA could be concluded.

Page 35: 12 SEPTEMBER 2012

ASIDI CHALLENGES IN 2011/12

– Subsequently, DBE signed the MOA on the 13th June and DBSA only signed on the 06th July 2011. The DBSA submitted the implementation Plan on 03 August 2011

– DBSA planned to use PSPs to undertake scoping work which was crucial for determining the extent of scope of work.

– This process for procurement of PSP to undertake the work had to be rescinded end of August after issues of conflict of interest were discovered between the companies bidding for the PSU and Project scoping.

Page 36: 12 SEPTEMBER 2012

ASIDI CHALLENGES IN 2011/12

– DBSA then started another process to appoint PSP’s for scoping, planning and detailed designs which was concluded on 15 September 2100 and resulted in a delay in the finalisation of scope before going out on tender in October 2011.

– DBSA started another process to appoint PSPs for scoping, planning and detailed designs which was concluded on the 15 September 2011 and resulted in delay in finalisation of scope before going out to tender in October 2011.

– A strategy adopted for procurement of contractors was to pre-Qualify contractors initially and appoint from a pool of pre-qualified contractors.

Page 37: 12 SEPTEMBER 2012

ASIDI CHALLENGES IN 2011/12

– The process started on the 22nd August 2011 but the process halted due to a dispute by contractors from the Eastern Cape who requested consideration of Grade 6GB instead of Grade 7GB.

– Procurement of contractors resumed on the 25th October 2011 and was concluded on the 04th and 29th November for 28 of 50 schools and 22 of 50 schools respectively.

– Tenders received were based on the generic scope of work due to the delay in the development of project scoping per school.

– As a result the tendered amounts for the first 28 of 50 and 22 of 50 schools were R711 044 966.48 and R595 167 614.37 respectively. This resulted in a prolonged adjudication process and appointment of successful tenderers.

– Sites were handed over to the contractors on the 12th and 13th January 2012 for a contraction amount of approximately R675mil.

Page 38: 12 SEPTEMBER 2012

LESSONS LEARNED

38

Page 39: 12 SEPTEMBER 2012

LESSONS FROM 2011/12 FINANCIAL YEAR

• The programme has been approached through a number of relationships entered into with implementing agents specific to delivery requirements viz.

• DBSA for the Inappropriate structures; Mvula Trust and IDT (through a sanitation programme of the department of Human Settlements) for Water and Sanitation and Eskom for Electrification.

• In the 2011/12 financial year 50 schools were allocated to DBSA as implementing agent. The number was constrained by the budget available in the first year of the programme.

Page 40: 12 SEPTEMBER 2012

LESSONS FROM 2011/12 FINANCIAL YEAR

• It is difficult to understand levels for accountability, ineffective in communication and poor information flow

• The outcomes and outputs of the various implementing agents have not been logically related to an overall ASIDI programme plan.

• In those instances where Programme Implementation Plans have been submitted by implementing agents they have been limited to the projects allocated and have not been adequate to determine if and how they will complete the targeted number of projects within the time and budget parameters.

Page 41: 12 SEPTEMBER 2012

LESSONS FROM 2011/12 FINANCIAL YEAR

• The logical relationships between these agreements programme milestones and targets have not been established or documented.

• Analysis of the performance and health check on these IA has not been conducted.

• The PEDs and previous initiatives have adopted a practice of handing over project lists to implementing agents and consultants without adequate control and decision gates.

• The consequence has been a loss of control and inadequate control on the programme.

• The PSU has noted that all implementing agents have been surprised by the level of monitoring and accountability and in most instance have had difficulty in meeting requirements.

Page 42: 12 SEPTEMBER 2012

RISKS AND MITIGATIONS

42

Page 43: 12 SEPTEMBER 2012

RISKS AND MITIGATIONS FOR IMPLEMENTATION

Risk Probability MitigationCurrent programme management and delivery experience is limited. Capacity of the all the Implementing Agents contracted with is limited and their systems do not meet requirements.

High Diversify delivery modality. Reduce reliance and dependence on implementing agents.

DBSA has low project maturity and capacity. Experiencing a learning curve on the first 50 Schools allocated.

High Additional contract allocation will be dependent on competence, capacity and will be subject to performance.

Mvula Trust are receptive and co operative but, need support and assistance in developing their systems, reporting, accountability and national programme management. They are equipped to deliver at local level and work through provincial directorated that work independent of each other.

High Use their allocation in 2011/12 to develop their systems. On assessment of their compliance and performance increase allocations.

Identify additional delivery modelities.

Have not established a relationship with or finalise an agreement with IDT at a national level. Performance between different provinces has been observed to be variable. They demonstrated an ability to deliver for PEDs in selected provines (Gauteng, North West, Limpopo).

High Limit risk exposure to contracting with IDT at a provincial level. It will contain risk on allocations to one province and also slow release of work package in relation to performance.

Page 44: 12 SEPTEMBER 2012

RISKS AND MITIGATIONS FOR IMPLEMENTATION

Risk Probability MitigationEskom as with other implementing agents have not been used to being held accountable and reporting to a “client”. No alternative available for electrification especially with regard to securing network point of connection.

Medium Develop their reporting capacity and closer monitoring.

PEDs have not demonstrated an ability to implement water and sanitation allocations . They are often stretched by EIG and Equitable share projects with a few acceptions

Medium Shift allocations away from PEDs in subsequent periods.

Institutional capacity for traditional procurement timeframesand inadequate planning for procurement result in delays and also will require more capacity to cope with the programme.

Medium Adopting a range of procurement options in addition to traditional approach.

Capacity of smaller or lower CIDB grade contractors to complete projects.

Medium Workpackages will allow for subcontracting and alternative delivery modelities will allow them to be accommodated in different sub programmes.

The range of Schedule 2 (Major Public Entities e.g DBSA, IDT, ESKOM, ect.), implementing agents limited and they cannot be relied upon.

High Expanding the range of delivery agents to reduce reliance on implementing agents.

Page 45: 12 SEPTEMBER 2012

ASIDI IMPLEMENTATION APPROACH FOR THE REMAINING YEARS

45

Page 46: 12 SEPTEMBER 2012

ASIDI:IMPLEMENTATION APPROACH

• The programme approach has been revised.• It is not limited to the existing relationships with DBE’s

implementing agents as the only mode of delivery. This has already demonstrated the risk and constraints.

• DBE is increasing its capacity to ensure that it is able to maintain a greater degree of control at project level.

• DBE is also beginning to encourage efficiency by allowing the slack capacity to be used to accelerate delivery where practical.

Page 47: 12 SEPTEMBER 2012

ASIDI: IMPLEMENTATION APPROACH

• The following implementation measures and principles have been adopted and adhered to in the programmes:– Work Packages as a mechanism to manage the work breakdown structure

but, retain the economy and scale required to accelerate delivery.– The Project Cycle turnaround time can be reduced to accelerate the

programme and minimise bottlenecks. – Procurement bottlenecks be minimised by using a range of procurement

strategies and expanding the resource pool beyond DBE.– Adopt a mix of delivery modalities increasing the number and diversity of

implementing agents. – In addition to traditional procurement and procurement through

implementing agents, DBE has entered into strategic relationships with those PED’s who have already established their own resources panels. These rosters be made available to the programme in the procurement of professional service providers and contractors.

Page 48: 12 SEPTEMBER 2012

ASIDI: IMPLEMENTATION APPROACH

• The following implementation measures and principles will be adopted and adhered to in the programmes:– DBE will negotiate with other National Department of Public Works in

relevant provinces, their rosters are constituted of the relevant built environment skills sets and may already have a geographic focus.

– The DBE has initiated a process to implement a framework agreement procurement model.

– Implementing Agents, Professional Service Providers and Contractors are pre qualified. The services can be secured through their inclusion in a pre approved panel. DBE and the implementing agents have access to the panel appointed through the framework agreement. Thus reducing procurement through traditional open tender routes. It has the possibility of attracting larger contractors and professional teams. Project Teams will be assembled from the framework agreement.

Page 49: 12 SEPTEMBER 2012

PROGRESS ON 2012/13 PLANS

49

Page 50: 12 SEPTEMBER 2012

50

INFRASTRUCTURE DELIVERY MANAGEMENT SYSTEM (IDMS):

The Programme will be delivered according to the Integrated Infrastructure Management System (IDMS) from the CIDB and National Treasury as depicted below.

Page 51: 12 SEPTEMBER 2012

ASIDI 2012/13 PLANS: MASTER LIST

  Inappropriate Electricity Sanitation Water

Province No of

2012/13 No of

2012/13 No of

2012/13 No of

2012/13 Schools Schools Schools Schools

Eastern Cape 424 50 317 213 345 290 619 535

Free State 30 20 129 103 26 12 99 61Gauteng 2 2 2 0 21 14 0 0

KwaZulu Natal 3 3 116 116 139 56 229 219

Limpopo 3 3 141 137 77 37 121 83

Mpumalanga 5 5 129 82 8 8 17 17

North West 2 2 41 41 33 33 13 13

Northern Cape 1 1 0 0 19 3 6 0

Western Cape 22 14 7 0 21 0 3 0

Total 492 100 882 692 689 453 1 107 928

51

Page 52: 12 SEPTEMBER 2012

ASIDI 2012/13 PLANS: PROCUREMENT

• COEGA, IDT AND DPWEC have been appointed for the implementation of the 50 schools in the EC and the MOA’s have been signed.

• An appointment letter has been issued to IDT FS for implementation of 10 schools in FS and MOA has been signed

• WCED is an appointment Implementing Agent for the implementation of 14 schools in WC.

52

Page 53: 12 SEPTEMBER 2012

ASIDI 2012/13 PLANS: PROCUREMENT

• Mvula Trust’s appointment includes implementation of Water and Sanitation in Limpopo and Eastern Cape for 2012/13 as well as Mpumalanga .

• ESKOM is appointed for the duration of ASIDI for Electrification.• Implementation of Water, Sanitation and Electrification in FS and Gauteng will

continue to be implemented by the provincial PED’s• NW PED is the implementing agent of water and sanitation projects in NW. • Outstanding and in progress:

– Appointment of IA (s) for KZN water and sanitation– Appointment of IA for water and Sanitation in Northern Cape– Appointment of IA (s) for Inappropriate schools in other provinces

53

Page 54: 12 SEPTEMBER 2012

ASIDI 2013/14 PLANS: Rationalisation

• Approximately 424 Inappropriate Schools in ASIDI are from EC Province

• Approximately 324 Inappropriate Schools remain to be constructed

• 203 of 324 Inappropriate schools have enrolment figures of below 135 learners– In line with the guidelines these schools cannot be provided with a full

compliment of infrastructure to schools with higher enrolment (over 135 learners)

– The province needs to provide way forward on status of Rationalisation to avoid delays in implementation in the next financial year.

54

Page 55: 12 SEPTEMBER 2012

THANK YOU