1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

Embed Size (px)

DESCRIPTION

3/14 MicroCHeaP WP2 Progress on Deliverables since Copenhagen D8 State of the art and market review PROGRESSdue Sep05 D12 First update to literature and patent search PROGRESSdue Mar06 D12 First update to literature and patent search FUTURE PLANdue Mar06 D19 Second update to literature and patent search... - FUTURE PLANdue Mar07

Citation preview

Page 1: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

1/14

ea technology

MicroCHeaP: Month 18 meeting Petten (NL)Work Package 2 Progress 5 April 2006Presented by Yvonne Dickson

Partners in power asset management

Page 2: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

2/14

MicroCHeaP WP2: Elaboration of theCurrent State of the Art and Market Size

WP2 Objectives• To acquaint members and the European research community with the latest developments in the field of renewable micro-CHP and related subjects

• To assess the market condition and trends in order to find openings for future market penetration

• To analyse renewable micro-CHP and relevant technologies with regards to cost and environmental impact

• To identify market gaps and the barriers to implementation of renewable micro-CHP

Page 3: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

3/14

MicroCHeaP WP2

Progress on Deliverables since Copenhagen

• D8 State of the art and market review . . . . . . . . . . . . . . . - PROGRESS due Sep05

• D12 First update to literature and patent search . . . . . . - PROGRESS due Mar06

• D12 First update to literature and patent search . . . . . - FUTURE PLAN due Mar06

• D19 Second update to literature and patent search . . . - FUTURE PLAN due Mar07

Page 4: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

4/14

D8 State of the Art & Market Review – Final Document

304-page PDF Document- delivered to all partners15 November 2005

Major Headings:

- I State of the Art

- II State of the Art & Market Review

- III Market Review

Plus: IV Excel Spreadsheets

Page 5: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

5/14

D8 - State of the Art & Market Review

I Sections:- FHG-ISE Solar energy- ECN Stirling engines- FEE Organic Rankine cells- CRES Fuel cells- CHALEX Thermoelectrics *- DGS Geothermal power *- NTUA & IUAV Additional references

* added since Copenhagen

Page 6: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

6/14

D8 - State of the Art & Market Review

II Sections:- BTG Biomass technologies- SPUN Slovakia- IUAV Italy- AF Sweden

Page 7: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

7/14

D8 - State of the Art & Market Review

III Sections:

- FORCE Economic potential for biomass

- CODES Legislation and energy pricing in Northern Europe *

- ENEFEL Legislation and pricing withinSouthern Europe

- EATL Feasibility studies

- NTUA & GAIA Market survey model * and Excel s/s

- FEE & partners Barriers and obstacles *and Excel s/s *

* updated since Copenhagen

Page 8: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

8/14

D8 - State of the Art & Market Review

IV Excel Spreadsheets:

- NTUA & GAIA Market trend model

- FEE & partners Barriers and obstacles

Page 9: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

9/14

MicroCHeaP WP2: Connections between work packages 1/2

EXPERT GROUPS

WP4: Co-ordination of European research activities

Leader: FORCE

LITERATURE

WP2: Elaboration of the current state of the art and market size

Leader: EATL

DATABASE

WP3: Mapping of current research activities and centres of excellence

Leader: ECN

Technical Annex page 23 :

WP2, WP3 and WP4 will exchange information

Page 10: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

10/14

MicroCHeaP WP2: Connections between work packages 2/2

LITERATURE WP2: Elaboration of the current state of the art & market sizeLeader: EATL

LINKS WP5: Investigation of links between renewable energy systems & µCHP

Leader: DGS

TECHNOLOGY TRANSFERWP6: Technology transfer and staff secondments

Leader: FEE

Technical Annex page 23 :

WP2 will feed information to WP5

and WP6

Page 11: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

11/14

D12 First Update to Literature & Patent Search

– Draft Document

22-page PDF Document- delivered to all partners27 March 2006

Headings:

- I Literature Search UpdatesECN - Stirling Engines

- II Patent SearchesCHALEX – Patent Search / Update

Page 12: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

12/14

WP2: Updating Literature & Patent Searches

• Deliverables D12 & D19- D12: First update to literature and patent search

(Month 18)- D19: Final update to literature and patent search

(Month 30)

Milestones M2.4 & M2.5- M2.4: Review meeting to discuss updates

to literature/patent search (Month 18)

- M2.5: Second review meeting to discuss updates to literature / patent search (Month 30)

Page 13: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

13/14

MicroCHeaP WP2: Elaboration of theCurrent State of the Art and Market Size

Decisions neededProposal 1: Issue D12 deliverable by 21 April 2006

Proposal 2: Request revisions and updates in January 07 for D19 deliverable due before April 07 meeting

Page 14: 1/14 ea technology MicroCHeaP: Month 18 meeting Petten (NL) Work Package 2 Progress 5 April 2006 Presented by Yvonne Dickson Partners in power asset management

14/14

WP2: Updating Literature & Patent Searches

Milestone M2.4 (Month 18)

Review meeting to discuss updates to literature/patent

search

… DISCUSSION …