Upload
brett-pierce
View
213
Download
0
Embed Size (px)
Citation preview
11.12.2003 AB-CO TC / J. Wenninger 1
MCB orbit correctorsMCB orbit correctors
There are 752 MCBH(V) SSS orbit corrector circuits.
Individually powered by a ± 60 A, ± 8 V converter.
PCs installed in the tunnel (radiation).
PCs are in production today.
The design MTBF is 100’000 hours
1 failure in operation every 100 hours.
Assuming ½ MCBs have significant kicks, we may get 1 MCB-induced beam loss per week due to our orbit tight tolerances !
11.12.2003 AB-CO TC / J. Wenninger 2
CrowbarCrowbar
In case of PC failure the magnet is shorted and discharged through a crowbar.
Time constants :
without crowbar 85-130 seconds
with crowbar 30-35 seconds - mostly due to 100 mresistors
11.12.2003 AB-CO TC / J. Wenninger 3
RemediesRemedies
The orbit FB could save the beam :
The FB must switch in a compensating scheme based on nearby correctors (or equivalent) reduce effect to a local bump.
The FB must be informed rapidly – time scale of 1 second or less.
The circuit time constants should be as long as possible.
With the 2 crowbar resistors the situation is very tight…
From MP point of view, the MCBs are slow enough even with crowbar resistors not to present a major problem.
But the slow is beautiful for MP slower is better !
11.12.2003 AB-CO TC / J. Wenninger 4
Can we remove 1 or both crowbar resistors ?Can we remove 1 or both crowbar resistors ?
Meeting with all concerned parties (AB & AT) :
The crowbar resistors have no role in protecting the magnets. The magnets are self-protected.
Motivation behind resistors seems to be a shorter circuit discharge time.
PC tests performed without crowbar resistors by AB/PO indicate that the resistors can be removed.
Implications for electrical safety, since it takes then ~ 10 minutes for the current to go from 60 to below 1 A for the slowest elements.
need a rapid decision since the PCs are in production.
ECR will be prepared this week.