7/27/2019 11 Multiple Openings in Bridges
1/21
Multiple Bridge and CulvertOpenings
With HEC-RAS
Objective: To become familiar with
the multiple opening flow options.
7/27/2019 11 Multiple Openings in Bridges
2/21
Multiple Openings
Divided Flow Approach
Multiple Opening Approach
Entering Multiple Opening Data
Multiple Opening Output
7/27/2019 11 Multiple Openings in Bridges
3/21
Divided Flow Approach
High Ground
1
2
3
4
5
6
7
8
Q
Q
T
T
Stagnation Point
Stagnation Point
Q Q12
7/27/2019 11 Multiple Openings in Bridges
4/21
A Multiple Opening
Multiple Opening Test Plan: Multiple Opening planLegend
Ground
Bank Sta
Inef f
7/27/2019 11 Multiple Openings in Bridges
5/21
Example of Multiple Opening (see previous slide)
There is a bridge opening over the main stream and aculvert group in the overbank area.
Types of openings: bridges, culvert groups (a group ofculverts is considered to be a single opening), andconveyance areas.
In the above example, the low area on the side wouldnot act hydraulically as a weir. Therefore, instead ofincluding it as part of the bridge, it should be modeledas a separate, conveyance opening.
Up to seven openings can be modeled at a givenlocation, and any combination of bridges and culvertgroups can be used.
A maximum of two conveyance type openings can beused and the conveyance area must be on theextreme left or extreme right side.
7/27/2019 11 Multiple Openings in Bridges
6/21
Multiple Opening
0 200 400 600 800 1000510
515
520
525
530
535
540
RS=3.5 Upstream (Multiple Opening)
Station (f t)
Elevation
(ft)
Legend
Ground
Inef f
Bank Sta
Stag Limit
#1
#2
#3
7/27/2019 11 Multiple Openings in Bridges
7/21
Plan View of Multiple Opening
7/27/2019 11 Multiple Openings in Bridges
8/21
Locating Stagnation Points
Stagnation Pointfloats inside
overlapping arrows.
For low flow,Stagnation Points
should always be
inside of ineffective
area block!400 500 600 700 800
510
515
520
525
530
RS=3.5 Upstream (Multiple Opening)
Station (ft )
Elevation
(ft)
Legend
Ground
Inef f
Bank Sta
Stag Limit
#2#3
7/27/2019 11 Multiple Openings in Bridges
9/21
Computational Procedure for Multiple
Opening
1. Program assumes a flow distribution
2. Energy computed for each opening
3. Energies compared for each opening
4. Flows are adjusted and procedure is
repeated
5. Program iterates until convergence or
maximum number of trials
7/27/2019 11 Multiple Openings in Bridges
10/21
Multiple Opening Limitations
This is a one-dimensionalmodel!
Energy grade line is assumed constant
upstream and downstream of opening
Stagnation points are not allowed tomigrate past the edge of adjacent
opening.
7/27/2019 11 Multiple Openings in Bridges
11/21
Divided Flow Tradeoffs
Energies for each reach/opening canbe different
Energies for each reach/opening
may be too different User must decide how to split the
cross sections.
7/27/2019 11 Multiple Openings in Bridges
12/21
Entering Multiple Opening Data
Multiple opening data are entered in thesame manner as any other bridge or
culvert
From the Geometric Data window, pressthe Bridge/Culvert button and select the
appropriate reach
Enter the river station
7/27/2019 11 Multiple Openings in Bridges
13/21
Enter Deck and Road Data
200 400 600 800 1000 1200510
515
520
525
530
535
RS=3.5 Upst ream (Multiple Opening)
Station (f t)
Elevation
(ft)
Legend
Ground
Ineff
Bank Sta
Stag Limit
#1#2
7/27/2019 11 Multiple Openings in Bridges
14/21
Pier and Abutment Data
200 400 600 800 1000 1200510
515
520
525
530
535
RS=3.5 Upst ream (Multiple Opening)
Station (ft )
Elevation
(ft)
Legend
Ground
Inef f
Bank Sta
Stag Limit
#1#2
7/27/2019 11 Multiple Openings in Bridges
15/21
Bridge Modeling Approach
7/27/2019 11 Multiple Openings in Bridges
16/21
Enter Culvert Data
700 750 800 850 900 950
520
522
524
526
528
530
RS=3.5 Upst ream (Multiple Opening)
Station (ft )
Elevation
(ft)
Legend
Ground
Ineff
Bank Sta
Stag Limit
#2#3
7/27/2019 11 Multiple Openings in Bridges
17/21
Defining the Openings
7/27/2019 11 Multiple Openings in Bridges
18/21
Multiple Opening Output
0 200 400 600 800 1000510
515
520
525
530
535
540
Multiple Opening Test Plan: Multiple Opening plan
Station (f t)
Elevation
(ft)
Legend
EG PF 4
WS PF 4
EG PF 3
WS PF 3
EG PF 2
WS PF 2
EG PF 1
WS PF 1
Ground
Inef f
Bank Sta
.08 .04 .08
7/27/2019 11 Multiple Openings in Bridges
19/21
Bridge and Culvert Output
7/27/2019 11 Multiple Openings in Bridges
20/21
Conveyance Output
7/27/2019 11 Multiple Openings in Bridges
21/21
Multiple Opening Profile Table