33
11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

Embed Size (px)

Citation preview

Page 1: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 1

ILC Baseline Schedule, Milestones, and Decision

points

Tom Himel

Page 2: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 2

Preface

• There is a large amount of ongoing R&D.• I will concentrate on those aspects which

have major effects on the ILC design. • Note that ILC R&D, engineering, and

industrialization are all going on in parallel. • I’ll describe each R&D project with its goals,

explain why it is useful, give its schedule, and some results.

• We know many pieces of the schedule, but the fully integrated schedule will be developed during the EDR.

Page 3: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 3

Contents

• Preview of Overall Schedule• Major risk mitigation R&D efforts:

– Cavity gradient– Cryomodule at full gradient– Linac string test– E cloud, DR kicker– BDS system test– Design for High Availability

• Cost reduction R&D– High power RF

• Construction Schedule and overview

Page 4: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 4

Technically Driven Timeline

August

BCD

All regions ~ 5 yrs

Construction Startup

Siting Plan being Developed

2006 2010 2014 2018

RDR EDRBeginConst

EndConst

EngineerDesign

Site Prep

Site Select

R & D -- Industrialization

Gradient

e-CloudCryomoduleFull Production

System Tests

& XFEL

Detector Install

Detector Construct

Pre-Operations

Page 5: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 5

Cavity Gradient – Goal

• Current status: Nine 9 cell cavities have been produced with gradients > 35 MeV/m. Not reproducible and needs several attempts at final processing.

• Goal: After a viable cavity process has been determined through a series of preparations and vertical tests on a significant number of cavities, achieve 35 MV/m at Q0 = 1010 in a sufficiently large final sample (greater than 30) of nine-cell cavities in the low power vertical dewar testing in a production-like operation e.g. all cavities get the same treatment.– The yield for the number of successful cavities of the final

production batch should be larger than 80% in the first test. After re-processing the 20 % underperforming cavities the yield should go up to 95%. This is consistent with the assumption in the RDR costing exercise.

Page 6: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 6

Cavity Gradient – Plan

• There are three main activities which are closely coupled and partially progressing in parallel

– This is needed to separate cavity preparation and production issues• 1. Single-cell R&D

– Establishing more reliable final preparation parameters.– Focus on the final rinse after EP before HPR.– E.g. Ultrasound, Short EP (or HF rinse), H2O2

• 2. Tight-loop (Finish in 2008)– International multi-cell cavity exchange– 1st round

• Comparison of regional differences in preparation and testing– 2nd round

• Use single-cell results and implement on 9-cell cavities.

• 3. Production-like effort (Continues into 2010)– Monitor ongoing productions

• Esp. XFEL preparation• Use qualified and new vendors

– Use improved preparation process for an ultimate batch of cavities• A lot of data will be (is already) available by the time of the EDR writing

Page 7: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 7

Cavity Gradient – Cost/Benefit

• Optimistic scenario with final batch + tight-loop– Costs 36 MILCU for the R&D– Gives highest confidence about the gradient

distribution

• This needs to be compared to:– A reduction of the average gradient for the ILC

from design of 31.5 to 28– ~ 600 MILCU

Page 8: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 8

Cavity Gradient – Results

KEK single cell results:2005 – just learning2006 – standard recipe2007 – add final 3 μm fresh acid EPNote: multi-cells are harder than singles

2005

2007

2006

Page 9: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 9

Module Test – Goal

• Intermediate goal– Achieve 31.5 MV/m average operational accelerating gradient in

a single cryomodule as a proof-of-principle. In case of cavities performing below the average, this could be achieved by tweaking the RF distribution accordingly.

– Auxiliary systems like fast tuners should all work.

• Final goal– Achieve > 31.5 MeV/m operational gradient in 3 cryomodules. – The cavities accepted in the low power test should achieve 35

MV/m at Q0 = 1010 with a yield as described above (80% after first test, 95% after re-preparation).

– It does not need to be the final cryomodule design

Page 10: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 10

Module Test – Plan

• Enough good cavities for the cryomodules are expected from the cavity gradient program. Module assembly plans:

• DESY– 2007: M7: Being tested now. See next slide– 2007: M8: Probably no slow-down to select best cavities– 2008: M10 – could select best cavities from several regions

• US – funding problems have us behind schedule below– 2007 – Assemble a kit of parts from DESY to get first

assembly experience at FNAL– 2008 – assemble 2 cryomodules from US produced

parts. Second may be made by selecting the best available cavities.

– 2009 – build 2 more cryomodules

• Japan– 2009-10: Build, test, 3 cryomodules

Page 11: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 11

Module Test – Results

DESY

Page 12: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 12

String Test – Goal

• Build 1 RF unit (3 cryomodules + 1 Klystron) to fully check:– What gradient spread can be handled by LLRF system.

This test should be done with and without beam loading.– For heating due to high frequency HOMs.– Amplitude and phase stability.– Static and dynamic heat loads.

• To partially check:– Reliability– Dark current– for degradation or other weaknesses

• The ILC cryomodule is enough different than that of the TTF that a new system test is warranted.

Page 13: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 13

String Test – Plan

• Use cryomodules built for module tests and for industrialization.

• Do more tests at TTF/FLASH• XFEL will both be a string test and provide costing,

contracting and construction information.• Build 1 RF unit at KEK and 1 at Fermilab.

– Do this in a phased manner, starting with smaller tests with modules that don’t meet specs.

– Full – to spec – RF unit should work before 1% of the final industrial production of ILC cryomodules is complete. (2014)

• There will be a larger second phase string test to verify quality of the modules going into the ILC.

Page 14: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 14

String test – Cost/Benefit

• The risk if we don’t do the string test is that we will build ~1.5 BILCU of cryomodules and then discover a design flaw.

• Fixing them all could take years and easily cost more than 20% of the original cost.

• If there is a medium risk (25%) of this type of error then the risk*cost ~75 MILCU plus the loss of a few years in schedule.– Note the risk would be high 50-100% if not for

the TTF.

• The planned string tests will cost over 50 MILCU.

Page 15: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 15

Schedule in Graphical Form2009 2012 2015 2018

ConstructionSchedule

CryomoduleProduction

RF System Tests

Page 16: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 16

E cloud – Goal

• Ensure the e- cloud won’t blow up the e+ beam emittance.– Do simulations (cheap)– Test vacuum pipe coatings, grooved

chambers, and clearing electrodes effect on e- cloud buildup

– Do above in ILC style wigglers with low emittance beam to minimize the extrapolation to the ILC.

Page 17: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 17

E cloud – Plan

• Grooved chambers and special coatings are being tested in PEP-II and KEK-B straight sections.

• Lots of simulations have been done and bench-marked against existing accelerators.– Still, the long extrapolation leaves us nervous.

• Plans are being developed to test special chambers in wigglers in CESR and KEK-B. – The funding is not yet assured for these more

definitive tests.– Schedule is for results in 2009

Page 18: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 18

E Cloud – Cost/Benefit

• If we don’t do the R&D, there is a high (50%) risk that we have to build a second e+ DR at a cost of 200 MILCU. Cost*risk = 100 MILCU

• The first 2 types of R&D cost only a few million.

• The costs of the KEK-B and CESR tests are difficult to evaluate as they involve the dedicated use of the whole ring and it is unclear which costs should be accounted to the ILC. The scale is 10 MILCU.

Page 19: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 19

E Cloud – Results

SLAC

Page 20: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 20

BDS System Test – Goal

• Build ATF2, a scaled BDS prototype at KEK to test:– Optics design including never before done

local chromatic correction– Keeping a beam small (35 nm) and stable to a

few nm for days at a time– Laser wires– Intra-train feedback– BPM’s– High availability power supplies– Tuning algorithms

Page 21: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 21

BDS System Test – Plan

• ATF2 is already under construction by a multi-regional collaboration.

• Will be commissioned in 2009 with optics tests done in 2010

Page 22: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 22

BDS System Test – Cost/Benefit

• Cost is ~5 MILCU• Ameliorates a medium (25%) risk of having to

do a major BDS redesign that could lengthen the BDS and cost 200 MILCU extra

• Would be a bargain at twice the price

Page 23: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 23

High Power RF – Goals

• The baseline HPRF design is mature and has very little risk.

• The R&D concentrates on cost reduction– A Marx modulator to replace the bouncer

modulator– Modified RF distribution system– Sheet-beam klystron to replace multi-beam

klystron

• If all are used, the HPRF cost is cut in half.

Page 24: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 24

Marx Modulator – Results

SLAC

Page 25: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 25

Marx Modulator – Results

100kV Output –1400 μsec, Leveled

Long term test planned in coming year.

SLAC

Page 26: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 26

Modified RF Distribution System – Plans

SLAC

Page 27: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 27

Sheet Beam Klystron – Plan

• Build beam tester and klystron by Summer 2008

• The beam tester will validate 3-D beam transport simulations and allow a more rapid turnaround for electron gun changes

• The klystron will be developed in parallel with little feedback from the beam tester. A rebuild of the klystron can incorporate design changes motivated by the beam tester

Page 28: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 28

Sheet Beam Klystron – Plan

Page 29: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 29

Americas Site Plan

Page 30: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 30

~ 5.5 km

~ 5.5 km

Central Area fits inside the Fermilab boundary

Site Characterization of the Central Area can be done

~ Boundary of Fermilab

Preconstruction Plan for Fermilab

Page 31: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 31

Preparing for 2012 Construction Start2007 2010 2012

Phase 1

Phase 2

Phase 3

Page 32: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 32

Civil Construction Timeline

Page 33: 11 June 07 Fermilab Steering Group 1 ILC Baseline Schedule, Milestones, and Decision points Tom Himel

11 June 07 Fermilab Steering Group 33

Technically Driven Timeline (reprise)

August

BCD

All regions ~ 5 yrs

Construction Startup

Siting Plan being Developed

2006 2010 2014 2018

RDR EDRBeginConst

EndConst

EngineerDesign

Site Prep

Site Select

R & D -- Industrialization

Gradient

e-CloudCryomoduleFull Production

System Tests

& XFEL

Detector Install

Detector Construct

Pre-Operations