10/6 Production Sequencing

• Roll call/collect homework

• issues w/ Excel for CPM

• lecture: production sequencing

• small groups

• assign homework

Page 2: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

CPM & Excel

• Deceptive: “on critical path”.

• Sensitivity report: shadow price of 1 or “LaGrange multiplier” of 1.

Go to spreadsheet example.

Page 3: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Production Sequencing

• Multiple jobs, one work center (machine, person, etc.)

• Schedule to minimize mean flow time.

Page 4: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Production Sequencing: terms

• Work center: machine, person, etc., where some particular task is done.

• Scheduling: assigning jobs to work centers.

• Sequencing: the order in which to process the jobs at a given work center.

• Flow time: amount of time that passes from when an order was received and when it was finished.

Page 5: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Job Sequencing

• Priority Rules for Dispatching Jobs– FCFS - first come, first served– LCFS - last come, first served– SOT - shortest operation time– LOT - longest operation time– Ddate - due date

Page 6: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Job Sequencing: Example

• Copy shop w/ one color copier.

• Orders arrive in the morning in this order:– A. Brochures, 4 hrs. needed in 8 hrs.– B. Presentation, 1 hr. needed in 3 hrs.– C. Flyers, 6 hrs. needed in 7 hrs.– D. Invitations, 8 hrs. needed in 12 hrs.– E. Booklets, 5 hrs. needed in 14 hrs.

Page 7: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Job Sequencing: Example

• How to schedule to minimize the flow time?

• Orders arrive in the morning in this order:– A. Brochures, 4 hrs. needed in 8 hrs.– B. Presentation, 1 hr. needed in 3 hrs.– C. Flyers, 6 hrs. needed in 7 hrs.– D. Invitations, 8 hrs. needed in 12 hrs.– E. Booklets, 5 hrs. needed in 14 hrs.

Page 8: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Copy Shop: FCFS

Arr. Time Due

A 4 8

B 1 3

C 6 7

D 8 12

E 5 14

Arr. Time Due Flow Time

A 4 8 0 + 4 = 4

B 1 3 4 + 1 = 5

C 6 7 5 + 6 = 11

D 8 12 11 + 8 = 19

E 5 14 19 + 5 = 24

tot. flow time = 4 + 5 + 11 + 19 + 24 = 63

mean flow time = 63 / 5 = 12.6 hrs.

Page 9: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Copy Shop: LCFS

Arr. Time Due

A 4 8

B 1 3

C 6 7

D 8 12

E 5 14

Arr. Time Due Flow Time

E 5 14 0 + 5 = 5

D 8 12 5 + 8 = 13

C 6 7 13 + 6 = 19

B 1 3 19 + 1 = 20

A 4 8 20 + 4 = 24

tot. flow time = 5 + 13 + 19 + 20 + 24 = 81

mean flow time = 81 / 5 = 16.2 hrs.

Page 10: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Copy Shop: SOT

Arr. Time Due

A 4 8

B 1 3

C 6 7

D 8 12

E 5 14

Arr. Time Due Flow Time

B 1 3 0 + 1 = 1

A 4 8 1 + 4 = 5

E 5 14 5 + 5 = 10

C 6 7 10 + 6 = 16

D 8 12 16 + 8 = 24

tot. flow time = 1 + 5 + 10 + 16 + 24 = 56

mean flow time = 56 / 5 = 10.2 hrs.

Page 11: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Copy Shop: LOT

Arr. Time Due

A 4 8

B 1 3

C 6 7

D 8 12

E 5 14

Arr. Time Due Flow Time

D 8 12 0 + 8 = 8

C 6 7 8 + 6 = 14

E 5 14 14 + 5 = 19

A 4 8 19 + 4 = 23

B 1 3 23 + 1 = 24

tot. flow time = 8 + 14 + 19 + 23 + 24 = 88

mean flow time = 88 / 5 = 17.6 hrs.

Page 12: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Copy Shop: DDate

Arr. Time Due

A 4 8

B 1 3

C 6 7

D 8 12

E 5 14

Arr. Time Due Flow Time

B 1 3 0 + 1 = 1

C 6 7 1 + 6 = 7

A 4 8 7 + 4 = 11

D 8 12 11 + 8 = 19

E 5 14 19 + 5 = 24

tot. flow time = 1+ 7 + 11 + 19 + 24 = 62

mean flow time = 62 / 5 = 12.4 hrs.

Page 13: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Job Sequencing: notes

• Note that the ending flow time was identical for all methods. (Additivity rule)

• The MEAN flow time varied.

• SOT will ALWAYS produce the lowest mean flow time.

Page 14: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Job Sequencing: 2 work centers

• Multiple jobs to do

• 2 work centers, jobs must be done sequentially (EX: first copy, then staple)

Page 15: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Johnson’s Rule: 2 work centers

• List the time for each job on each machine.

• Select the shortest operation time.

• If the shortest time is on 1st machine, schedule that job first.

• If the shortest time is on 2nd machine, schedule that job LAST.

• Repeat steps until all jobs are scheduled.

Page 16: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

2 work centers - Example

• Copy shop:

• 4 jobs to do, w/ times for each machine– booklets copy: 3 fold: 2– brochures copy: 6 fold: 8– catalogs copy: 5 fold: 6– packets copy: 7 fold: 4

Page 17: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

2 work centers - Example

• Step 1: find shortest time.

• 4 jobs to do, w/ times for each machine

– booklets copy: 3 fold: 2– brochures copy: 6 fold: 8– catalogs copy: 5 fold: 6– packets copy: 7 fold: 4

Page 18: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

2 work centers - Example

• Step 2: on 2nd machine, so schedule it last.

• 4 jobs to do, w/ times for each machine

– brochures copy: 6 fold: 8– catalogs copy: 5 fold: 6– packets copy: 7 fold: 4 – booklets copy: 3 fold: 2

Page 19: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

2 work centers - Example

• Repeat: find lowest (remaining) time.

• 4 jobs to do, w/ times for each machine– brochures copy: 6 fold: 8– catalogs copy: 5 fold: 6

– packets copy: 7 fold: 4

– booklets copy: 3 fold: 2

Page 20: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

2 work centers - Example

• Repeat: 2nd mach., so move (next to) last.

• 4 jobs to do, w/ times for each machine– brochures copy: 6 fold: 8– catalogs copy: 5 fold: 6– packets copy: 7 fold: 4 – booklets copy: 3 fold: 2

Page 21: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

2 work centers - Example

• Repeat: find lowest time.

• 4 jobs to do, w/ times for each machine– brochures copy: 6 fold: 8

– catalogs copy: 5 fold: 6

– packets copy: 7 fold: 4 – booklets copy: 3 fold: 2

Page 22: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

2 work centers - Example

• Repeat: 1st machine, move to front of line.

• 4 jobs to do, w/ times for each machine– catalogs copy: 5 fold: 6– brochures copy: 6 fold: 8– packets copy: 7 fold: 4 – booklets copy: 3 fold: 2

Page 23: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

2 work centers - Example

• Done.

• 4 jobs to do, w/ times for each machine– catalogs copy: 5 fold: 6– brochures copy: 6 fold: 8– packets copy: 7 fold: 4 – booklets copy: 3 fold: 2

catalogs

catalogs

brochures

brochures

packets

packets

booklets

booklets

Copy

fold IDLE

IDLE

Page 24: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Small Group ExerciseYou have an engraving business in a kiosk at

the mall. Today, while you were out buying nachos, your clueless assistant received 4 orders in this sequence: a bracelet, which will take 10 min. to engrave, a locket (6 min.), an award plaque (24 min.), and a pen (12 min.). Your assistant also promised that they would be ready at 12:25, 12:15, 12:40, and 12:50, respectively. It is now 12:00 exactly. Minimize the number of dissatisfied customers by seeing which priority rule you should use. Should you fire your assistant?

Page 25: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

Small Group Exercisetime due

Bracelet 10 25

Locket 6 15

Award 24 40

Pen 12 50

FCFS LCFS SOT LOT Ddate

B 10 P 12 L 6 A 24 L 6

L 16 A 36 B 16 P 36 B 16

A 40 L 42 P 28 B 46 A 40

P 52 B 52 A 52 L 52 P 52

# late 2 2 1 2 1

Choose DDate

Page 26: 10/6 Production Sequencing Roll call/collect homework issues w/ Excel for CPM lecture: production sequencing small groups assign homework

10/6 Homework

• DUE 10/8: Handout

• DUE 10/13: pg. 176, #20, pg. 177, #23