52
Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report 10-47 10.5.3 Questionnaire Survey (1) Necessity of Questionnaire Survey As described above, available hazard maps lack sufficient accuracy to estimate the actual inundation area. Furthermore, existing marks that indicate the height of the flood waters have disappeared as time passes by. As such, a questionnaire survey was conducted to: (i) collect responses from a sufficient pool of respondents in the affected areas and make record height measurements left behind by the waters from the 2004 tsunami and 2003 flood; and (ii) investigate the actual results of inundation, damage, and evacuation during the noted tsunami and flood. This survey was subcontracted to the ENGINEERING & LABORATORY SERVICES (PVT) LTD from the middle of October 2005 to the middle of December 2005. (2) Methodology 1) Survey Area The survey area covered the Matara Division, which was affected by the 2004 tsunami and 2003 flood as shown in Figure 10.23. The number of samples for the questionnaire was to be at least 500 samples from each disaster. 2) Questionnaire Sheet Questionnaire sheets were prepared for the 2004 tsunami and for 2003 flood, respectively. The items in the questionnaire survey are shown in Table 10.8 and the survey sheet is attached in Annex 10-2. Table 10.8 Items of Questionnaire Survey Item Questionnaire a) General information Name Sex Disaster experience, etc. b) Result of Inundation Location of high water marks Distance form coastline/river Inundation depth and inundation period Current direction c) Result of Tsunami/Flood Damage Number of affected people, casualties, and fatalities Damage to houses, movable assets, crops, livestock, and infrastructure d) Warning and Evacuation system Tsunami/flood forecasting and warning system Publication of hazard areas and evacuation areas Results of evacuation (place, route, period, method, etc.) e) Hazard Map Awareness of hazard maps Utilization of hazard maps Source: Project Team

10.5.3 Questionnaire Survey2) Questionnaire Sheet Questionnaire sheets were prepared for the 2004 tsunami and for 2003 flood, respectively. The items in the questionnaire survey are

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-47

    10.5.3 Questionnaire Survey

    (1) Necessity of Questionnaire Survey

    As described above, available hazard maps lack sufficient accuracy to estimate the actual inundation area. Furthermore, existing marks that indicate the height of the flood waters have disappeared as time passes by. As such, a questionnaire survey was conducted to: (i) collect responses from a sufficient pool of respondents in the affected areas and make record height measurements left behind by the waters from the 2004 tsunami and 2003 flood; and (ii) investigate the actual results of inundation, damage, and evacuation during the noted tsunami and flood. This survey was subcontracted to the ENGINEERING & LABORATORY SERVICES (PVT) LTD from the middle of October 2005 to the middle of December 2005.

    (2) Methodology

    1) Survey Area The survey area covered the Matara Division, which was affected by the 2004 tsunami and 2003 flood as shown in Figure 10.23. The number of samples for the questionnaire was to be at least 500 samples from each disaster. 2) Questionnaire Sheet

    Questionnaire sheets were prepared for the 2004 tsunami and for 2003 flood, respectively. The items in the questionnaire survey are shown in Table 10.8 and the survey sheet is attached in Annex 10-2.

    Table 10.8 Items of Questionnaire Survey Item Questionnaire

    a) General information

    ・ Name ・ Sex ・ Disaster experience, etc.

    b) Result of Inundation

    ・ Location of high water marks ・ Distance form coastline/river ・ Inundation depth and inundation period ・ Current direction

    c) Result of Tsunami/Flood Damage

    ・ Number of affected people, casualties, and fatalities ・ Damage to houses, movable assets, crops, livestock, and

    infrastructure d) Warning and Evacuation system

    ・ Tsunami/flood forecasting and warning system ・ Publication of hazard areas and evacuation areas ・ Results of evacuation (place, route, period, method, etc.)

    e) Hazard Map ・ Awareness of hazard maps ・ Utilization of hazard maps

    Source: Project Team

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-48

    3) Methodology To improve the reliability of the survey, the questionnaire survey was conducted by adopting the following procedures:

    i) Survey respondents were selected from residents actually affected by the disasters;

    ii) The sheet was completed via face-to-face interviews;

    iii) Inundation depth was measured from the ground and floor levels;

    iv) High water mark location was confirmed with portable GPS;

    v) Survey responses were compared with responses from neighbors to determine if

    considerable disparities were present in the responses;

    vi) The survey sheet, which showed an outline of the survey results, was pasted on the

    mark indicating the highest water level;

    vii) Photographs were taken of all height measurements (corresponding to their survey

    sheet) and compiled in photo books; and

    viii) Some height measurements of floodwaters were surveyed by leveling, so as to convert

    the inundation depth to the elevation data.

    (3) Results of Questionnaire Survey for 2004 Tsunami

    1) Characteristics of Respondents

    • The total number of respondents for the tsunami disaster was 586, with 44% being male and 56% being female. Approximately 14% of 4,330 houses damaged by tsunami in Matara Division were queried.

    • Out of all respondents, 79% experienced the tsunami disaster in 2004. • 22% of respondents lived within 100 m of the coast, 67.3% lived between 100 m to 500

    m away, and 10.7% lived between 500 m to 1,000 m away, respectively.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-49

    Source: Project Team

    Figure 10.23 Accumulated Number of Houses vs. Distance from the Coast 2) Results of Inundation by the 2004 Tsunami

    • Inundation conditions reported by respondents are summarized in Figure 10.24. The maximum inundation depth was 410 cm from the ground at 40 m from the coastline.

    • In regards to the inundation depth from the ground, 54% of houses were more than 2.0 m, 31% were between 1.0 m and 2.0 m, and 32% were between 0.5 m and 1.0 m, respectively.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-50

    • Regarding the inundation period, the average time experienced by the respondents was estimated at 5.9 hours. Some 43.2% of houses were inundated from longer than four hours.

    • Regarding the inundation speed, 75% of respondents felt it was very fast (within a few seconds), while 17% felt it was fast (within a minute).

    • Regarding the direction of the tsunami wave, it was basically from south to north, and came through the coastal line. It was very rare that the direction changed due to the effect of drain canals and small ponds. Also, respondents who lived close to the Nilwala River experienced the tsunami from the river.

    3) Results of Damage from 2004 Tsunami

    Since the respondents for the survey were selected from those actually affected by disasters and living in their original locations, the following data may be less accurate:

    • 4% of houses were damaged completely and 19% were partially damaged; • 80% of respondents lost their movable property, 39% completely lost their crops, while

    6% completely lost their livestock;

    • From the survey, 60 people from the homes of respondents died due to tsunami; and • 4% of respondents noted road damage. 4) Evacuation and Warning System

    • 89% of respondents were unaware of tsunami-prone areas and evacuation locations. • Before the 2004 tsunami, people had never experienced a tsunami, so there was no

    tsunami forecasting and warning system.

    • Regarding conditions for dwelling, 150 respondents thought they did not live in a dangerous place, 286 respondents thought they lived in a dangerous place, but the danger was not imminent, and 150 respondents thought they lived in a very dangerous place, respectively.

    • Regarding the first evacuation, the average distance from the house was 3,132 m; 47.1% of respondents did not evacuate from their house during the 2004 tsunami. Evacuation locations were schools, temples, two-story buildings, and elevated areas.

    • Regarding the final evacuation, 19% of respondents moved to a safer location and 81% returned to their houses after the tsunami water subsided. Evacuation locations included relatives’ homes, schools, and temples.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-51

    0

    5000

    10000

    15000

    20000

    25000

    0 200 400 600 800 1000 1200

    Distance from Coastline (m)

    Eva

    cuat

    ion D

    ista

    nce (m

    )

    Source: Project Team

    Figure 10.25 Results of First Evacuation during the 2004 Tsunami 5) Tsunami Hazard Map

    • No one knew about the hazard map. • Expected information to be displayed on a hazard map included evacuation centers,

    evacuation routes, hazard areas on evacuation routes, medical care facilities, and special signs along evacuation routes, etc.

    • Many respondents expected a hazard map to be distributed to each house. Some expected publishing to be done by public servants, with maps displayed at public places. Also, there was an idea that media publicity would facilitate understanding of the findings of the survey.

    (4) Results of Questionnaire Survey for the Flood in 2003

    1) Characteristics of Respondents

    • The total number of respondents for the flood disaster survey was 503, with 44% being male and 56% being female.

    • Out of the respondents, 94% experienced the flood disaster in 2003. • Those who experienced the flood and responded to the questionnaire had lived within

    6,500 m of the Nilwala River. Those who experienced floods from the branch rivers (Tributaries) had lived within 2,500 m of the tributary.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-52

    Source: Project Team

    Figure 10.26 Number of Houses vs. Distance from the Nilwala River

    2) Result of Inundation by the Flood in 2003

    • Inundation conditions related to the number of houses and distance from the Nilwala River are summarized in Figure 10.27. The maximum inundation depth was 386 cm from the ground, at a distance of 200 m from the Nilwala River.

    • Regarding the inundation depth from the ground, 18% of houses were inundated less than 0.5 m, 24% were between 0.5 m and 1.0 m, 51% were between 1.0 m and 2.0 m, and 7% were more than 2.0 m, respectively.

    • 457 houses were inundated above the floor level.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-53

    >2.0m, 6.96, 7%

    0-0.5 m, 17.69, 18%

    0.5m-1.0m, 24.06, 24%1.0m-2.0m,

    51.29, 51%

    0-0.5 m0.5m-1.0m1.0m-2.0m>2.0m

    Source: Project Team

    Figure 10.27 Results of Inundation Depth by 2003 Flood

    • Regarding the inundation period, 60% of houses were inundated for more than six days, while 22% were inundated at least 10 days.

    • Regarding the inundation speed, 26% of respondents felt it was very fast (within a few minutes), 28% felt it was fast (within a hour), and 36% felt it was slow (within a few hours), respectively.

    • Regarding the direction of the flood, it was basically from the Nilwala River or tributary. At certain locations, some respondents had experienced the flood from both the Nilwala River and tributary.

    3) Result of Damage by the Flood in 2003

    • 9% of houses were completely damaged, 48% were partially damaged, and 43% were not damaged, respectively.

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    0 1000 2000 3000 4000 5000 6000 7000

    Distance from Nilwara River (m)

    Inunda

    tion D

    ept

    h (

    cm

    )

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-54

    • Inundation levels varied from 40 cm below the floor level to 380 m above it. • 72% of respondents lost their movable items and 54% lost their crops. Only 4%,

    however, lost their livestock.

    • According to the survey, only one person died and 503 were injured from the homes of respondents, respectively.

    • 2% of respondents mentioned damage to the roads. 4) Evacuation and Warning System

    • Only 71 respondents out of 503 (14%) were aware of flood disaster warning. Flood warnings were generally disseminated by the police.

    • 12% of respondents were aware of flood-prone areas and official evacuation locations. Most evacuation locations during the flood were schools and temples.

    • Regarding dwelling conditions, 42% of respondents thought they lived in a dangerous place, 51% thought they lived in a dangerous place, but the danger was not imminent, and 7% thought they lived in a very dangerous place, respectively.

    • Regarding the first evacuation, 390 of the respondents (78%) evacuated to schools and temples, while 113 (22%) did not evacuate and stayed in their homes. Respondents stayed an average of 10 days at their first evacuation locations.

    • Regarding the final evacuation, only 5% of respondents moved to a safer location, while 95% returned to their house after floodwaters subsided. Evacuation locations were mainly the homes of relatives.

    0

    2000

    4000

    6000

    8000

    10000

    0 100 200 300 400 500 600

    Distance from Nilwara River (m)

    Eva

    cuat

    ion D

    ista

    nce (

    m)

    Source: Project Team

    Figure 10.28 Results of First Evacuation during the 2003 Flood 5) Flood Hazard Map

    • Only three out of 503 respondents knew of the hazard map. • Many respondents expected that hazard map would be distributed to each house.

    Some expected publishing by civil servants, with maps being displayed at public places.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-55

    10.5.4 Tsunami/Flood Disaster Map

    (1) Basic Specifications for the Disaster Map

    Considering the improvements to the hazard map and ease of utilization, basic specifications for the disaster map were defined as below:

    • Type: Colored Map; • Size: A2 size; • Area: Matara Division; • Scale: 1:20,000; • Topographic Information: Referring to the map data of the UDA GIS Division Survey

    Department; and

    • Disaster Information: Results of the questionnaire survey for the 2004 tsunami and 2003 flood.

    (2) Basic Information

    Basic information was plotted on the disaster maps to utilize: (i) topographic information that was collected from the Survey Department and UDA GIS Division; and (ii) disaster information based on the results of questionnaire surveys as listed below. 1) Topographic Information

    i) Topographic data (based on 1:10,000 scale map) ii) Contour line (from 0 m to 5 m MSL, with intervals of 1 m) iii) Niliwara River, tributaries, and drainage canals iv) Main roads v) Divisional boundaries vi) Location of houses vii) High elevation areas (higher than 5 m MSL) 2) Disaster Information

    i) Boundaries of inundation area ii) Locations of inundation area (grid of 50 m x 50 m) or contour data iii) Inundation depth (0.0 m to 0.5 m - green, 0.5 m to 1.0 m - yellow, 1.0 m to 2.0 m - cyan,

    more than 2.0 m - blue) iv) Numerical data of inundation depth v) Flow direction vi) Evacuation direction vii) Location of present evacuation shelters

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-56

    (3) Main Findings

    Based on the above works, the 2004 tsunami disaster map and 2003 flood disaster map were prepared as shown in Figures 10.29 and 30. Main findings are noted below. 1) Tsunami Disaster Map

    • Detailed and reliable flood-affected areas were defined. • Precise tsunami movement was indicated with a scale of 50 m as noted below: i) The 2004 tsunami penetrated up to 4 km upstream from the river mouth, along the

    Nilwala River; ii) Around the U-shape bay in the Pholhena area, the inundation height was relatively

    high; and iii) Tsunami movement was affected by small canals.

    • The area that was not indicated in the available hazard map was newly identified as a disaster area.

    • The tsunami inundation area was spread approximately 800 m from the coastline. • Actual flow direction indicated on the map shows a high correlation between the flow

    direction and the direction of inundation.

    • Actual evacuation direction indicated on the map shows that people evacuated to high elevation or inland areas.

    2) Flood Disaster Map

    • Detailed and reliable flood-affected area were defined. • Precise flood movement was indicated with a scale of 50 m as noted below: i) The 2003 flood spread from the northwestern area along the main body of the Nilwala

    River; ii) The inundation depth on the right side of the river was especially high; iii) The area along some tributaries was seriously affected by inland water; and iv) The lower river basin was not flooded.

    • Actual flow direction indicated on the map shows a highly correlation between the flow direction and the direction of inundation.

    • Actual evacuation direction indicated on the map shows that people evacuated to high elevation or low inundated areas.

  • Recovery, R

    ehabilitation and Developm

    ent Project for Tsunam

    i Affected Area of Southern Region in the D

    emocratic Socialist R

    epublic of Sri Lanka Final R

    eport

    10-57

    Source: Project Team

    Figure 10.29 2004 Tsunami Disaster Map (Grid Data)

    Inundation Depth 0 – 0.5m 0.5 – 1.0m 1.0 – 2.0m > 2.0m

  • Recovery, R

    ehabilitation and Developm

    ent Project for Tsunam

    i Affected Area of Southern Region in the D

    emocratic Socialist R

    epublic of Sri Lanka Final R

    eport

    10-58

    Source: Project Team

    Figure 10.30 2004 Tsunami Disaster Map (Contour Data)

    Inundation Depth 0 – 0.5m 0.5 – 1.0m 1.0 – 2.0m > 2.0m

    Evacuation Direction

    Tsunami Direction

    Existing Refugee Shelter

    Elevated Area

  • Recovery, R

    ehabilitation and Developm

    ent Project for Tsunam

    i Affected Area of Southern Region in the D

    emocratic Socialist R

    epublic of Sri Lanka Final R

    eport

    10-59

    Source: Project Team

    Figure 10.31 2003 Flood Disaster Map (Grid Data)

    Inundation Depth 0 – 0.5m 0.5 – 1.0m1.0 – 2.0m> 2.0m

  • Recovery, R

    ehabilitation and Developm

    ent Project for Tsunam

    i Affected Area of Southern Region in the D

    emocratic Socialist R

    epublic of Sri Lanka Final R

    eport

    10-60

    Source: Project Team

    Figure 10.32 2003 Flood Disaster Map (Contour Data)

    Inundation Depth 0 – 0.5m 0.5 – 1.0m1.0 – 2.0m> 2.0m

    Evacuation Direction

    Flood Direction

    Evacuation Location

    Elevated Area

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-61

    10.5.5 Tsunami Simulation

    (1) Outline

    Tsunami simulation was carried out to estimate accurate data with respect to the area of inundation, the inundation depth, and the arrival time to Matara City -this in order to make a preliminary tsunami hazard map, in case of a tsunami on a similar scale to the 2004 one. The tsunami simulation process is detailed as shown in Figure 10.33. As shown in Figure 10.34, the simulation area includes the seismic center, the wave-propagating sea, and Matara city. The grid size for computation varies and lessens toward Matara city (with a 50 m grid in Matara city).

    Source: Project Team

    Figure 10.33 Process of Tsunami Simulation

    Development of Geographical Configuration 1) Grid data in sea area 2) Grid data in land area

    Setup of Tsunami Wave Source Model

    1) Collection of tsunami wave source model 2) Tsunami simulation trial by each model 3) Calibration by actual tsunami height 4) Determination of the model

    Calculation of Tsunami Approach 1) Tsunami simulation in sea areas 2) Tsunami run-up distance in land areas

    Setup of Analysis Conditions

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-62

    Source: Project Team

    Figure 10.34 Area for Tsunami Simulation

    (2) Calculation Condition

    1) Calculation Method The behavior of tsunamis is known to be dominated by the law of conservation of mass and the law of conservation of momentum, and is described by the equation of continuity and equation of motion, respectively. In this model, the displacement of sea levels caused by the movement of a tectonic plate is given as the initial condition. Solving the equations with a time parameter, tsunami behavior can be expressed numerically. The numerical analysis method to estimate the inundation situation in Mantra City is summarized in Table 10.9.

    Table 10.9 Numerical Analysis Method for Tsunami Simulation Area Applied Method

    From seismic center to offshore Liner long wave equations

    From offshore to coastal line Non-liner long wave equations (shallow water theory) On-shore Iwasaki and Shinno Theory (1979)

    Source: Project Team

    Area for Tsunami Simulation

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-63

    2) Data of Sea and Land Geographic Configurations The grid data for the geographical configuration are based on the data collected and surveyed by the JICA Project Team. As stated before, the minimum size of the grid is chosen to be 50 m. In order to carry out numerical analysis, continuous geographical configuration data is translated to an individual elevation value in each grid. When determining the size of the grid, guidelines advise that it should be at least 20 m within a wave length. As a tsunami wave approaches shore, the wave length becomes shorter, the wave height becomes higher, and the flow speed becomes faster. Thus, the size of a grid in the open sea including the seismic center is taken to be larger, while that nearer the shore to be smaller, making computation speed faster without sacrificing reliability of the analysis. At the smallest grid area (50 m spacing), the grid data includes not only elevation values, but also land utilization information (roughness coefficient, and with/without building), so that the simulation of the tsunami run-up on the land area can be more accurate. Table10.10 shows the data used for numerical analysis, while Figure 10.35 shows a 50 m grid and its elevation values on the land area.

    Table 10.10 Data Used for Numerical Analysis Item Name Issue

    ETOPO2 2’ Mesh NOAA/NGDC Water Depth CHART WELIGAMA-MATARA S=1/25,000

    National Aquatic Resources and Development

    Elevation on Land Topographic Information (DWG) Survey Department Source: Project Team

  • Recovery, R

    ehabilitation and Developm

    ent Project for Tsunam

    i Affected Area of Southern Region in the D

    emocratic Socialist R

    epublic of Sri Lanka Final R

    eport

    10-64

    Source: Project Team

    Figure 10.35 50 m Grid and Elevation on Land Area

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-65

    3) Consideration of Obstacles Such As Structures It is well known that the existence of seawalls along the coastline, relatively large reinforcement concrete (RC) structures, greatly impacts the extent of a tsunami’s reach inland. Thus, these obstacles are treated as boundary conditions in the numerical analysis. The locations, figures, and heights of such obstacles are surveyed by the JICA Project Team, and the information is simplified and assigned to each grid (as shown in Figure 10.36).

    4) Initial Conditions The displacement of the sea level caused by the movement of tectonic plates is calculated by the earthquake fault model, and its value is used as the initial condition of the tsunami inundation analysis. The earthquake fault model explains that a sudden slip of the adjacent strata is caused by accumulated energies due to deformation at the crusts. If such a slip occurs at the seabed strata, the seabed will rise up or subduct, resulting in a tsunami (refer to Figure 10.37).

  • 10-66

    Recovery, R

    ehabilitation and Developm

    ent Project for Tsunam

    i Affected Area of Southern Region in the D

    emocratic Socialist R

    epublic of Sri Lanka Final R

    eport

    10-66

    Source: Project Team

    Figure 10.36 Location of Boundary Conditions of On-shore Structures for Numerical Analysis

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-67

    Source: Nature Vol433 p352

    Figure 10.37 Basic Concept of Seismic Occurrences and Seismic Foul Model 5) Tsunami Source Model

    a) Selection Method of Fault Model Fault Model for the Tsunami simulation was chosen from issued models for Sumatran Earthquake Tsunami. Flowchart of Fault Modeling Approach is shown in Figure 10.38, and characteristic of the issued models is shown in Table 10.11.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-68

    Figure 10.38 Choice Flowchart of Fault Model

    Table 10.11 Characteristic of issued Models Organization Characteristics of fault Modeling approach

    1.Tohoku Univ. Site investigation result at Kirinda in Sri Lanka 2.Kyoto Univ. Seismographic date by Tokyo Univ. Seismic research laboratory 3.Koshimura(Tohoku Univ.) Wave height of sea leveling by artificial satellite over the Indian Ocean 4.JAMSTEC ditto 5.AIST ditto 6.Akita Univ. Compression with site investigation result at the South West area in

    Thailand

    According to the Coastal Development Institute of Technology (April 2004) the fault models are categorized in Table 10.12. Because there were no issued models for checking with the site investigation result in the Matara City, the model for this project was basically chosen by the data of site investigation result in Sri Lanka and water levels recorded by satellite remote sensing.

    Table 10.12 Category of Fault Mode Category of Fault Model Approach accuracy

    1 Modeling by Seismographic and Geodesic data 2 Optimum fault model by re-create tsunami simulation:

    3 Modified model by site investigation based on optimum fault model by re-create tsunami simulation

    Low

    High

    b) Selection of Fault Model Re-create simulations by six issued fault models were carried out and were checked with tidal level records at 4 places (Colombo in Sri Lanka and Male, Hanimaadhoo and Gan in Maldives). The parameters of the models and the location maps of fault are shown in Annex10.3. From the result of comparison of re-create simulation with tidal level record as shown in Annex10.3, the fault model by Tohoku University was most similar to the first and the second waves. The validity of the model was identified with site investigation result in Sri Lanka. So the fault model by Tohoku University was selected for this project.

    Issued Fault Models

    Checking with 4 tidal level records and

    choice the model

    Adjustment of Parameter

    Fault Model Selection

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-69

    The selected fault model will be used for not only the Matara City but also the other cities in Sri Lanka and Maldives.

    c) Parameter Modification of Fault Model The parameters of Fault Model by Tohoku University were modified to be consistent with inundation conditions at Matara city. Since the wave height of the Tsunami simulation result by Tohoku University tended to be a little smaller than the tidal level record at Colombo, the parameter of slipping volumes was modified. Figure 10.39 show inundation area at Matara city through 5 cases (11m to 18m) of slipping volume. The simulation result of 14 m as a slipping volume matched with site investigation result. Table 10.13 shows the modification result of parameter fault model.

    (a) 11m (b) 13m

    (b) 14m (c) 15m

    (d) 18m Figure 10.39 Tsunami inundation area by fault slipping volumes

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-70

    Table 10.13 Modification Result of Parameter Fault Model Fault plate

    Upper edge depth

    slipping volume

    direction angle of inclination

    slipping inclination

    Length width Base point Crashing time

    HH(km) D(m) TH(°) DL(°) RD(°) L(km) W(km) Y0 X0 Fault-1 7 14 329 15 110 330 150 2.5

    0 95.75

    0

    Fault-2 7 14 340 15 110 570 150 5.00

    94.00

    0

    Fault-3 7 14 5 15 110 300 150 10.00

    92.00

    0

    d) Comparison with Tidemark The maximum tsunami water levels at various points within two hours from the time of the earthquake were calculated by an applied numerical model, and summarized as a univariate data distribution. Such calculated values are then compared with the tidemarks (highest inundation levels) caused by tsunami inundation. To evaluate the fit of

    the model, the calibration indices, Κ and κ , defined by Aida’s series of study are used.

    Geometrical Average ∑=

    =ΚΚ

    n

    i i

    i

    HR

    n 1log1log   

    Logarithm Standard Deviation 2

    1

    1

    22

    )(loglog1log

    Κ−

    = ∑

    =

    n

    i i

    i

    HR

    nκκ   

    iR Observation Inundation Level

    iH Estimated Inundation Level n Number of Observations Κ Index Indicating Actual Tsunami Inundation Height Is Κ -fold of

    Estimation κ Logarithm Standard Deviation of ii HR /

    Κ is the index meaning that K times the calculated height is, on average, equal to the observed height. Thus, if K is closer to 1.0, the numerical model can be considered to fit better to the actual data. κ is the index indicating the variance of the ratio ( ii HR / ), which is comparable to the standard deviation in the normal distribution. Also, it is construed that the majority of the values of ii HR / at the observed points are less than Κ x κ . According to Souda (1986), apart from the value of Κ , the fit of the numerical model can be evaluated to be

    fairly accurate if 2.1≤κ , and very accurate if 4.1≤κ .

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-71

    Table 10.14 Comparison Simulation Result with Site Investigation Result No (i) Investigation

    Result (R) Simulation Result (H)

    log(R/H) (log(R/H))2

    1 0.27 0.29 -0.03103 0.00096 2 0.84 0.86 -0.01022 0.00010 3 0.92 0.81 0.05530 0.00306 4 0.58 0.71 -0.08783 0.00771 5 1.02 1.05 -0.01259 0.00016 6 2.04 2.75 -0.12970 0.01682 7 0.55 0.64 -0.06582 0.00433 8 1.50 1.36 0.04255 0.00181 9 1.90 1.40 0.13263 0.01759

    10 1.22 1.14 0.02945 0.00087 11 1.63 1.41 0.06297 0.00397 12 0.89 0.79 0.05176 0.00268 13 1.00 1.03 -0.01284 0.00016 14 3.60 3.26 0.04308 0.00186 15 2.40 2.87 -0.07767 0.00603 16 1.13 1.01 0.04876 0.00238 17 2.08 2.16 -0.01639 0.00027 18 2.55 2.54 0.00171 0.00000 19 1.80 1.96 -0.03698 0.00137 20 1.60 1.63 -0.00807 0.00007 21 2.40 2.28 0.02228 0.00050 22 1.71 1.05 0.21181 0.04486 23 4.10 3.46 0.07371 0.00543 24 2.76 2.17 0.10445 0.01091 24 1.04 0.93 0.04855 0.00236 25 0.93 1.62 -0.24103 0.05810

    Σ 0.19883 0.19436 logK K logκ κ 0.007953 1.018 0.087812 1.224

  • Recovery, R

    ehabilitation and Developm

    ent Project for Tsunam

    i Affected Area of Southern Region in the D

    emocratic Socialist R

    epublic of Sri Lanka Final R

    epor t

    10-72

    Source: JICA Project Team, Red: Investigation Result, Blue: Simulation Result

    Figure 10.40 Comparison investigation result with simulation result

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-73

    e) Comparison with Recorded Tide Levels Since there is not any available recorded tide data of the Tsunami wave in Matara City is available, the calculated water levels within 2 hours from the time of earthquake occurrence are compared with the actual water levels based on the questionnaire survey data. Under this section, the calculated water levels varied with time are analyzed and evaluated by the abovementioned method. Figure 10.41 shows that Arrival time at Matara city is approximately 2 hours from the time of earthquake occurrence, the first wave of the tsunami was highest and the following waves came at intervals of 20 or 30 minutes. After 20 minutes, the first wave came from the coastal line and arrived at the farthest inundation area. Table 10.14 shows the tsunami arrival time at Matara city and additional cities in the Southern area of Sri Lanka. Since the arrival time was estimated by questionnaire and/or site survey, it seems that it was inundation time. Since the simulation results are the same as the results from the above data, the simulation was determined to be valid.

    -5

    -4

    -3

    -2

    -1

    0

    1

    2

    3

    4

    5

    0 1 2 3 4 5 6

    Arrival time

    Wav

    e h

    eight (m

    )

    Figure 10.41 Tsunami Time Series

    Table 10.15 Tsunami Approach Time to the South Area in Sri Lanka

    Earthquake time (Local Time) Tsunami Arrival time

    (Local Time) Arrival hour

    Yala 6: 58 9:10 1) 2h 12m

    Hambantota 9:22 2) 2h 24m

    Matara 9:20 1) 2h 22m

    Galle 9:20 1) 2h 22m

    Source 1) Kiobuchi, JSCE Coastal Engineering Paper (No. 52) 2005 2) NIshihata, JSCE Coastal Engineering Paper (No. 52) 2005

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-74

    (3) Result of Tsunami Simulation

    The results were summarized by inundation area and depth at each area.

    Table 10.16 Inundation Area and Depth

    GN Inundation Area (%) (Rate for Total Area) Inundation Depth (m)

    Madiha West 40 0.1~5.0 Madiha East 90 0.1~4.0

    Walgama Central 15 0.1~1.0 Walgama South 50 0.1~2.5 Welegoda West 20 0.1~1.0 Welegoda East 15 0.1~0.5

    Polhena 100 1.0~3.5 Pamburana 100 0.5~3.5

    Noope 70 0.1~1.0 Thotamuna 100 0.5~4.0

    Kadaweediya West 15 0.1~0.5 Kadaweediya South 60 0.1~2.0

    Fort 100 0.2~3.5 Uyanwatta North 5 0.1

    Uyanwatta 40 0.1~1.0 Kotuwegoda North 100 0.1~2.0 Kotuwegoda South 100 1.0~4.5

    Weragampita 10 0.1~0.5 Navimana South 20 0.1~1.2

    Weraduwa 20 0.1~0.5 Eliyakanda North 5 0.1~0.5 Eliyakanda South 15 0.3~2.5 Meddawatta South 5 0.2~4.3

    (4) Conclusion

    Simulated and surveyed results of inundation depth generally matched (refer to P.10.70 Comparison with Tidemark). The arrival time and inundation area of Tsunami wave generally matched, too. Accordingly, it was confirmed that the simulation results were suitable. Therefore, these results are satisfactory for planning the disaster prevention and mitigation of Matara city.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-75

    Figure 10.42 Results of Tsunami Simulation

    10.5.6 Preliminary Tsunami Hazard Map

    (1) Overview

    A preliminary tsunami hazard map for the tsunami of 2004 was prepared for basic information on planning of disaster prevention and mitigation, as well as enhancement of disaster awareness for both residents and local authorities. This preliminary tsunami hazard map does not include some information that needs to be authorized by local agencies as shown in Table10.16. As described in Section 10.3, local authorities are expected to use the map for various measures as soon as possible.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-76

    Table 10.17 Comparison of Tsunami Hazard Map and Preliminary Tsunami Hazard Map Item

    HM Classification Item Resi-dents

    Author-ities

    PHMRemarks

    Information about External Force ○ ○ ○

    External Force Unused Information about External Force

    ○ ○

    In case of a tsunami equivalent to the 2004 tsunami

    Expected Inundation Area ○ ○ ○

    Have to be careful to fix disaster image for inhabitants

    Area for Refuge ○ ○ △ To indicate a draft buffer zone that is decided by elevation

    Maximum Inundation Depth ○ ○ ○

    Forecasted Arrival Time ○ ○ ○

    Starting Point of Inundation ○ ○ ○

    Information of Inundation

    Current Speed ○ ○ ○

    Shelter ○ ○

    Evacuation Route ○ ○

    Disaster Prevention Shelter Base ○ ○

    Information of Disaster Prevention

    Inundation Record ○ ○ ○ On Disaster Map

    Area Condition ○ ○

    Shelter Condition ○ ○

    Ground Elevation ○ ○

    Necessary Rescue Institutions ○ ○

    Others

    Evacuation Guidelines, etc. ○

    * HM :Tsunami Hazard Map * PHM :Preliminary Tsunami Hazard Map Source: Project Team.

    (2) Methodology

    1) Necessity of Input for Preparation of Preliminary Tsunami Hazard Map The necessities of input for the preparation of a preliminary tsunami hazard map are extracted from the results of the tsunami simulation, and are indicated on a base map made from satellite photographs of Matara city.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-77

    Source: GIS Division, UDA

    Figure 10.43 Satellite Photograph of Matara City 2) Presumption of Damage

    Displaying the number of victims and damage to the houses are effective for gathering basic information on planning disaster prevention and mitigation, as well as enhancement of disaster awareness for both residents and local authorities. The number of victims and damage to the houses are commonly presumed from structure (Brick, Wooden or RC Structure) and people in houses based on the disaster caused by the past Tsunami in the area. Therefore, the number of victims calculated from the damaged houses was presumed from the disaster record of the 2004-Tsunami. The Presumption methodology is shown in Figure 10.44.

    Source: Project Team

    Figure 10.44 Procedure of Presumption of Damage by Tsunami

    Relation with Tsunami current and damage1) Damaged area is presumed from site survey 2) Tsunami current are calculated by Tsunami simulation by equivalent 2004-Tsunami

    Current by equivalent 2004-Tsunami1) Current are presumed from Tsunami simulation

    Presumption of Damage1) Damage of houses are presumed roughly

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-78

    (3) Preliminary Tsunami Hazard Map

    Preliminary Tsunami Hazard Map is shown in Figure 10.44. Basic information was mentioned for planning of disaster prevention and mitigation in Matara city (refer to Table 10.15). The information is the following:

    - Information about External Force; - Expect Inundation Area; - Maximum Inundation Depth; - Forecast Arrival Time; and - Current Speed.

    Animation of simulated Wave Spreading from the seismic center and Inundation Condition are made in order to increase the understanding of disaster awareness as shown in Figure10.45 and Figure10.46.

    Figure 10.45 Animation of simulated Wave Spread from the seismic center

    Figure 10.46 Animation of simulated Inundation Condition

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-79

    Source: Project Team

    Figure 10.47 Preliminary Tsunami Hazard Map

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-80

    10.6 Implementation of Awareness Activities

    10.6.1 JICA-Net Seminar

    (1) Background

    Tsunami-affected people and officers in the local public administration in Matara District are well aware that Japan is a very experienced nation in terms of disasters such as earthquakes, typhoons, tsunamis, and flooding. Local people are extremely interested in mitigating damage from the next possible disaster. The JICA Project Team has continually been asked questions such as, “How are Japanese people preparing for disaster?” In order to satisfy this interest in Japanese disaster management, the JICA Project Team conducted seminars and transferred lessons learned from Japanese disasters to residents and officers of the Matara District.

    (2) JICA Net Seminars

    JICA-Net is an interactive Internet-television-computer system that connects studios in Colombo with JICA Headquarters in Tokyo, Japan. Seminar participants in the studios, who are thousands of kilometers apart, can attend a seminar together in real-time. In the seminars, resource persons in Japan come to the Tokyo studio and make presentations on various topics. Participants in Sri Lanka assemble in a studio in the JICA Colombo Office and are free to ask questions and discuss topics from their own viewpoints so that they can obtain a good understanding of the topic in the context of Sri Lanka. The JICA Project Team carefully prepared and held two seminars on disaster management and rehabilitation in order to facilitate the transfer of knowledge. This included:

    • Community Initiatives in Disaster Management and Rehabilitation, and • Role of the Local Authorities in Disaster Management.

    Detailed program information is discussed below.

    (3) Seminar 1 - Community Initiative in Disaster Management and Rehabilitation

    This seminar was held on the 13th December at the JICA Sri Lanka Office as one of the activities of the JICA Project. There were 30 participants from the pilot project organizations, such as refugee camp societies, fishery corporative societies, and small

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-81

    industry associations. For seminar participants, it required a full-day round trip from Matara to Colombo and back, spending eight hours in the bus. Despite this, the seminar was greatly appreciated. The program was as follows.

    Table 10.18 JICA-Net Program for Community Initiative on Disaster Management Module Facilitator or lecturer

    1 Introduction to JICA-Net Seminar Katsura MIZUNO, PADECO, Tokyo 2 1st lecture

    Okushiri Tsunami and disaster management of the town council

    Mr. Kakemi NAGASAKI, Officer in charge of tourism and planning, Okushiri Town Council

    3 2nd lecture What we learned from the Hanshin-Awaji Earthquake and the importance of community initiative in disaster management

    Mr. Masakiyo MURAI, Director, CODE

    4 Question & Answer Mr. Dahanayake 5 Group discussion on what we can do in Matara,

    and presentation from three groups Coordinators of the JICA Project Team

    6 Mechanisms of a tsunami Mr. Ryo MATSUMARU, JICA expert for disaster management

    Source: Project Team.

    Based on the evaluation sheets collected after the session, it appeared that the participants recognized the importance of this kind of disaster management seminar for communities, and were satisfied with information and lessons offered by the seminar.

    (4) Seminar 2 - Disaster Management for Local Public Administrations

    This seminar was held on the 14th December at JICA Sri Lanka Office as one of the activities of the JICA Project. In total, 24 participants came (mainly from the Matara area, but also some from Colombo). Participating organizations included the police, army, divisional secretariat, Urban Development Authority, Fishery Department, Corporative Department, and Matara Municipal Council, etc. Since co-assistance among community people produces significant impacts in terms of disaster management and rehabilitation works, it is very important for officers of local public administrations to be aware of this and to know how to draw such effects out of communities. This seminar explained Japanese disaster experiences and systems for disaster management (particularly how to enhance community participation). The program was as follows.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-82

    Table 10.19 JICA-Net Program for Public Administration Module Facilitator or lecturer

    1 Introduction to JICA-Net Seminar Katsura MIZUNO, PADECO, Tokyo 2 1st lecture

    Okushiri Tsunami and disaster management of the town council

    Mr. Kakemi NAGASAKI, Officer in charge of tourism and planning, Okushiri Town Council

    3 2nd lecture Hanshin-Awaji Earthquake and community involvement in disaster management

    Mr. Isamu OKADA, Director, Suma Fire Station, Kobe Municipal Council

    4 Question & Answer Mr. Dahanayake 5 Group discussion on what we can do in

    Matara, and presentation from three groups Coordinators of the JICA Project Team

    6 Mechanisms of a tsunami Mr. Ryo MATSUMARU, JICA expert for disaster management

    Source: Project Team.

    The public administration participants understood the necessity to involve local communities in counter-disaster administration.

    (5) Feedback from Seminar Participants

    Since the participants are all interested in disaster management, the vast majority of the participants appreciated the seminars. Requests and suggestions mentioned in the evaluation sheets included:

    - A half day was insufficient for this kind of seminar; - Many more people should attend the seminar; - This seminar should be held in every region of the country; - This seminar should be aired as a television program; and - Besides disaster preparedness, subjects such as rehabilitation should also be

    discussed. Participants mentioned in the evaluation sheets that they have:

    - Shared Japanese disaster experience; - Learned how to protect themselves from tsunamis; - Received useful knowledge and information; and - Realized the importance of co-assistance.

    As a part of the seminar program, participants held group discussions on what they can do for disaster management in Matara. Three groups were formulated for discussion, with each group proposing dozens of ideas for effective preparation against disaster. They are motivated to have the same kind of discussions in their communities and offices. Some ideas derived from the group discussions are the following:

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-83

    - Community and government should conduct annual evacuation drills like Japan; - Every family should check evacuation routes in the case of an emergency; - We (participants) will organize disaster committee in every community under

    Grama Niladari (community chief); - School children should learn disaster management to protect themselves; - We will discuss the warning system of our village; - Our community should prepare a storehouses to keep tools, equipment, and food

    to survive disaster; - We should edit a manual of lessons learned from our disaster experience and

    keep it for generations; - Police officers need practical training for disaster management; - Community should cooperate on protecting children, the elders, and disabled in a

    disaster; and - Every public agency should prepare for next tsunami in order not to be

    affectedand still maintain its ability to save citizens.

    10.6.2 Seminars on Disaster Management

    The JICA Project Team conducted seminars on disaster management to raise awareness of disaster management for both government staff and community members. The details of the seminars are found below.

    • Date and Place 6th of March 2006 in Matara and 8th of March 2006 in Colombo

    • Agenda Opening Speech Presentation of the Project and Outcomes Presentation of Disaster Management Coffee Break Presentation by a Sri Lankan Expert Open Discussion Handover Ceremony of the Hazard Map Best Practice Award Giving Ceremony (only in Matara) Closing Speech

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    10-84

    • Attendees Matara

    - Government officials: GA office, Police, DMCC - Pilot Project related agencies. - PP representatives - Donors and NGOs - Academics

    Colombo - Government officials: Central ministries, DMC, - McRAP Committee - Donors and NGOs - Academics

    Presentation materials used for the seminars are found in Annex 10.4.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-1

    Chapter 11 Conclusions

    11.1 Conclusions

    11.1.1 Summary of Conclusion

    The JICA Project Team has done various work for in rehabilitation process in the southern region of Sri Lanka. To examine the achievements, the results of the Project were summarized below against the objectives of the Project, as stated in Chapter 2.

    − To formulate a plan for the recovery, rehabilitation, and development of tsunami- affected areas in the southern region of Sri Lanka.

    The JICA Project Team introduced two approaches for developing the rehabilitation program, which were based on the Japanese experience in the Great Hanshin-Awaji Earthquake, that is the bottleneck identification approach and co-assistance approach. The bottleneck identification approach is based on lessons learned in the aftermath of the Great Hanshin-Awaji Earthquake and was used for identifying rehabilitation bottlenecks and identifying necessary activities quickly. Co-assistance, defined as mutual assistance among victims, is employed for expediting livelihood rehabilitation. Utilizing the bottleneck identification approach, strategies for rehabilitation of the southern region were developed. The strategies included assessment and identification of necessary rehabilitation activities. For verification of the co-assistance approach, three Pilot Projects for community assistance were formulated and implemented. A fisheries sector rehabilitation strategy was also developed. The JICA Project Team implemented three Pilot Projects in the following aspects: refugee camp support, fishery cooperative support, and small industry association support. These Pilot Projects consisted of various community activities with full consideration of the co-assistance approach, such as the establishment of associations and steering committees, publishing of newsletters, and lending of equipment. Through implementation of the Pilot Projects, the JICA Project Team assessed these two approaches. It was found that the two approaches generally worked well for the rehabilitation process in Sri Lanka. Based on these results, lessons learned and follow-up work of the Pilot Projects were prepared.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-2

    The JICA Project Team also developed suggestions for the disaster management plan in the Matara area. These suggestions included disaster prevention measures and emergency preparedness and response measures. The community activities for disaster preparedness were also included, based on the co-assistance approach. As a part of disaster management, the JICA Project Team prepared a preliminary tsunami hazard map and tsunami/flood disaster maps. Disaster awareness workshops were also held.

    − To assist and monitor technically the implementation of recovery and rehabilitation projects to be funded under Japanese Non-project Grant Aid and ODA Loans.

    The JICA Project Team technically assisted and monitored two rehabilitation projects funded under Japanese Non-project Grant Aid and ODA Loans: (i) the reconstruction of the Matara Aqueduct Bridge; and (ii) the rehabilitation of fishery harbors at Galle and Tangalle. The JICA Program Team has been in charge of technical assistance of design, tender, and monitoring of construction. Construction work is being implemented by the Non-Project Grant Aid scheme.

    − To share Japanese experiences in disaster management through implementation of the Project.

    The two approaches: the identification of bottleneck and the co-assistance were adapted from Japanese experience. These approaches formed the backbone of the Project. In particular, Pilot Projects applying the co-assistance approach were well-accepted and appreciated by the subject persons. This success, however, was derived partly from the traditional propensity for group work in Sri Lankan rural societies. Nevertheless, differences between Sri Lanka and Japan in coping with tsunamis on the one hand and earthquake on the other, each with different social settings, were made apparent in details. It is very much desirable to formulate approaches fully reflecting Sri Lankan realities. Also, some concrete measures concerning disaster management suggested for the Matara area were adapted from measures developed in Japan, including tsunami hazard maps and tsunami signboards, etc.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-3

    11.1.2 Lesson Learned from the Project

    (1) Identification of Bottlenecks

    The list of possible bottlenecks adapted from ones prepared in Japan proved to be quite useful. However, it is strongly recommended that the list be modified to reflect the actual circumstances in Sri Lanka by planners of the regional rehabilitation plan especially in the following aspects:

    - The dual structure of local administration in Sri Lanka; - Involvement of a large number of donors and NGOs; - The co-assistance approach; - Availability of land for evacuees; - Roles of the Urban Development Authority, Provincial Government, and

    Municipality; - Adequately reflecting the needs and opinions of victims themselves; - Reviving small-scale industries; and - Expanding to include public health and education anticipated in earlier stages.

    (2) Co-Assistance

    The co-assistance approach proved to be quite effective in post-disaster management. There are a number of points that have emerged in the course of implementing the Pilot Projects, which, if properly done, would make the approach even more effective. These points are as follows:

    - Members of a newly formed society should be of a similar background (as much as possible);

    - Societies should be given an opportunity to negotiate with external organizations to the extent possible;

    - Meetings should be held as frequently as possible; - Micro-finance can serve as a glue to keep society cohesive, while its interest

    payments can be used for the society’s own activities; - Training can enhance the standing of society to individuals, a mutually reinforcing

    cycle; and - Formation of internally-cohesive and outwardly-oriented societies enables them

    to link up with existing organizations to enlarge their scope.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-4

    (3) Priority Projects for Infrastructure

    • Smooth Project Identification

    The Steering Committee, which included both Sri Lankan and Japanese representatives concerned with Non-Project Grant Aid, has selected projects quickly. In the course of selecting candidate project components, the Steering Committee has widely gathered information on components with urgent restoration needs from local and central government agencies. This action was performed in a short time period, resulting in the selection of project components that obviously required urgent restoration as claimed by the local residents affected by the tsunami.

    • Quick Preparation of Facility Design Draft tender documents were prepared within two months after the commencement of the Project due to the urgency of facility rehabilitation and to resume their functions as early as possible. The other reason why the JICA Project Team prepared the design and tender documents in such a short time was that damaged facilities simply required restoration to their original forms, without time-consuming studies.

    11.2 Recommendations

    This section summarizes recommendations on rehabilitation activities in Sri Lanka, based on achievements and evaluations of the Project.

    11.2.1 Preparation of a List of Lessons and Checkpoints on the Disaster Rehabilitation

    In the Project, the JICA Project Team made the hypothesis that the methodology of using a list of lessons and checkpoints for disaster rehabilitation would be useful to identify bottlenecks and necessary administrative activities quickly. The bottlenecks and necessary activities were clarified according to the list developed after the Great Hanshin-Awaji Earthquake in Japan. Through the evaluation, it became clear that the methodology was quite useful for tsunami rehabilitation in Sri Lanka, although it was necessary to adapt contents to the situation in the Sri Lanka case. It is recommended that one government agency collect issues on tsunami rehabilitation from various government agencies, donors, and NGOs, and summarize them into one list. This list should be open to the public and disseminated to local authorities for rehabilitation of additional disasters.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-5

    Since the situation varies considerably according to the phase of rehabilitation, lists for each phase need to be prepared. In the Project, the JICA Project Team used only the list for initial recovery phase. At least, it is necessary to prepare lists for the emergency phase, evacuation phase, initial rehabilitation phase, and full-scale rehabilitation phase. Besides the list for tsunamis, it is also considered beneficial to have ones for floods and landslides, as these will be quite useful for effective rehabilitation in Sri Lanka.

    11.2.2 Enhancement of Co-assistance Activities for Community Rehabilitation

    Based on Japanese experience, the JICA Project Team introduced the concept of co-assistance to develop the strategy of community rehabilitation. Three Pilot Projects for community assistance were formulated and implemented from the point of view of enhancement of co-assistance activities such as the establishment of committees, recovery of micro-finance schemes, and provision of training opportunities. Through the evaluation of these activities, it became clear that co-assistance activities improved internal relationships, mutual trust, and external networks. It was also observed that these improvements improved synergies in terms of assistance for physical, financial and human assets, and promoted rehabilitation of community. Considering the above findings, it is recommended that assistance of co-assistance activities be expanded to other tsunami-affected communities nationwide. As the first step, it is very important to disseminate a concept of co-assistance among government authorities, communities, and NGOs. Local authorities need to take the initiative of enhancing co-assistance activities in all affected communities, closely cooperated with NGOs and donors. The details are shown in Section 11.1 in the report.

    11.2.3 Promotion of Regional Disaster Management

    As well as rehabilitation, preparation for future disasters is quite an important issue in this stage. The JICA Project Team focused on disaster management in the Matara urban area. Through a review of existing measures, it was clear that disaster management in Matara was insufficient. It is recommended that comprehensive disaster management measures be implemented in Matara area as soon as possible. Disaster prevention measures are expected to prevent or reduce physical damage from disasters directly, such as the construction of seawalls and strong buildings in dangerous

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-6

    area. Emergency preparedness and response are measures for planning and preparing for emergency activities, including early-warning systems and emergency evacuation areas/routes, as well as disaster awareness measures. In addition, establishment of the Disaster Management Committee in Matara is recommended for promotion of the implementation these measures. The details of each measure are shown in Section 10.3 in the report. As a priority measure for disaster management, the JICA Project Team prepared a preliminary tsunami hazard map and tsunami/flood disaster maps. It is recommended that local authorities effectively use these maps in the following ways: (i) to authorize dangerous zones in reference to them; and (ii) to distribute them to government staff and community members for disaster awareness.

    1) Phasing of Disaster Rehabilitation As is explained in Chapter 2 of this report, there are several phases in disaster rehabilitation, including the: (i) emergency rescue phase; (ii) evacuation phase; (iii) initial full-scale rehabilitation phase; and (iv) full-scale rehabilitation phase. Co-assistance can be applied in any of these phases.

    2) Motivation to Prepare for Another Disaster Many communities and governmental agencies are still very much motivated for disaster prevention. It is best to disseminate the lessons learned while people are motivated. 3) Integration of Disaster Preparation and Rehabilitation If the co-assistance approach is to be disseminated, the three steps mentioned in the previous section (i.e., survey, policy, and training) should include aspects of disaster preparedness.

    11.2.4 Dissemination of the Project Results

    As described above, the Project produced valuable recommendations on regional rehabilitation processes. It is very important to widely disseminate these results. There are two targets for dissemination, communities and government officers. All three recommendations (including a list of lessons and checkpoints), as well as co-assistance, and disaster management aspects, needs to be disseminated to central government agencies and local authorities through workshops and seminars. For communities, it is useful to raise the awareness of co-assistance and disaster management through

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-7

    workshops, seminars, and public relations. The details of the awareness activities are shown in Sections 10.4 and 11.1.

    (1) Dissemination of Co-assistance Approach

    Through implementation of the Pilot Projects, the JICA Project Team realized that the co-assistance approach works. The question is how this approach can be spread to other parts of Sri Lanka. Since the Pilot Projects targeted a very limited part of the tsunami-affected population (even in Matara) and only a few government officers were actually involved in their implementation, the immediate influence of the co-assistance approach has been quite limited. People in Sri Lanka are relatively well-educated and have a tradition of mutual help. Community development projects of the National Housing Development Authority, as well as of Sarvodaya, are widely-practiced in Sri Lanka in line with the co-assistance approach. Communities in this country have substantial foundations to build co-assistance structures upon.

    (2) Target Community Groups

    One year after the disaster, all the tsunami-affected population has received external assistance to some extent, recovering their livelihoods that existed prior to the disaster. As such, it may not be the best time to organize new societies and associations in order to start co-assistance work for rehabilitation. However, strengthening existing grassroots organizations has enough justification to accelerate the well-being of the people. Co-assistance work can be applied to many kinds of organizations such as:

    • Various cooperatives (agriculture, fishery, consumers, etc.); • Community-Based Organizations like committees under Grama Niradari; • Age-based groups like community youth associations; • Parent and teacher associations at each school or student groups; and • Religious groups at each Buddhist temple, Hindu kovil, mosque, and church.

    These parties or Community-Based Organizations (CBOs) can be the targets for dissemination work, however, there should also be facilitators of co-assistance extension work.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-8

    (3) Three Steps of Co-assistance Dissemination

    The JICA Project Team has experienced various constraints concerning how to buildup co-assistance during the course of Pilot Projects. This experience should be shared with a broad set of disaster rehabilitation stakeholders in Sri Lanka. Three steps to disseminate co-assistance are proposed as follows.

    1) Survey Of Existing Community-based Organizations and Their Achievements This survey is to identify effective CBOs for rehabilitation. Good practices were collected from all the potential target areas. These results may be used to develop CBO database and used to repeat good practices. Survey results can be used for subsequent steps.

    2) Policy Development at the Government Level A central government agency, together with the District Secretaries of each area, should take initiatives to establish policies and rules of co-assistance. An example of this policy is the organization of residents associations in each refugee camp during the next disaster. Typical dissemination tools include seminars and training sessions for government officials at the central or local level as following.

    • Training on public administration for co-assistance facilitation This training is for high-ranking government officials and includes investigation of disaster- prone communities and discussions about disaster rehabilitation, disaster awareness, and disaster preparedness.

    • Training on enhancement of co-assistance activities for tsunami-affected communities This training is designated for government officials on the rural or grassroots level. Venues include best practices of community rehabilitation in Tsunami-related countries and training of facilitators for enhancement of community activities. Participants have received the training in a practical manner, so that officers can obtain distinct ideas on how co-assistance works on the community level.

    • Policy coordination with NGOs NGOs’ activities contribute a great deal to community rehabilitation. Government agencies, especially at the local level, need to coordinate with NGOs for the dissemination of co-assistance. Local agencies should have seminars or meetings with NGOs on how to introduce and implement co-assistance activities for sustainable rehabilitation.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-9

    3) Dissemination on the Community Level The following measures are proposed for dissemination of co-assistance on the community level.

    • Group training for community leader Until each community understands the importance of co-assistance, co-assistance activities will not be disseminated widely. Government agencies closely cooperating with NGOs should provide group trainings for community leaders and committee members in order to introduce the co-assistance activities into the community as a first step to disseminate co-assistance to each community.

    • Assistance of establishment of community organization The establishment of community organization is essential. During the Pilot Projects preceding the actual Project, the JICA Project Team promoted target communities to establish steering committees and the committees took an important role for various community activities. Local agencies, or NGOs, should assist to establish such committees in target communities, and encourage them to take leadership in their communities.

    • Monitoring of co-assistance activities Even though co-assistance activities can promote sustainable rehabilitation with the initiative of communities, it is expected that there are many implementation issues on various co-assistance activities, especially in the introduction period. Local agencies and NGOs should frequently monitor community activities and advise them or provide assistance if it is necessary. Financial or physical assistance through committees is highly recommended because such assistance can enhance internal coordination and bonding of communities. On the other hands, assistance directly to each community member can easily discourage the initiative of coordination and cooperation among community members.

    11.2.5 Subsequent Follow-up for the Project

    1) Necessary Activities for Project Follow-up In regards to the implementation of recommendations, the following activities are recommended for short-term implementation by the Sri Lankan side and JICA.

    • Sri Lankan side: - Dissemination by distributing copies of the report to concerned agencies; - Handover of the Pilot Project from the JICA Project Team to government agencies;

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-10

    - Continuation of the Pilot Projects by government agencies, with close cooperation from Berendina;

    - Promotion of co-assistance dissemination through the following three steps: (i) survey of existing community-based organizations and their achievements; (ii) policy development at the government level; and (iii) trainings and seminars;

    - Preparation of lists of lessons and checkpoints according to the phase of rehabilitation and type of disaster (by a committee specifically formed for the purpose); and

    - Promotion of short-term measures on disaster management, such as the implementation of awareness programs with hazard maps and the establishment of a disaster management committee.

    • JICA: - Support of the continuation of Pilot Projects, which are to be implemented by GA

    and Berendina (NGOs). In regards to the follow-up of the Pilot Project, the following institutional settings should be implemented.

    2) Proposed Institutional Settings for Pilot Projects The JICA Project Team has built the following structures to execute the Pilot Projects:

    • Each project has one or two government agencies as the counterparts; • For each Pilot Project, beneficiaries formed a society or an association for the purpose

    of achieving project goals;

    • Berendina, a Sri Lankan NGO, has managed the operation of the Pilot Projects; and • The steering committee of each Pilot Project includes representatives from

    beneficiaries, government agencies, local NGOs, and the JICA Project Team. Co-assistance is a mechanism that tsunami-affected people use to organize their own society or association to effectively control and facilitate rehabilitation. This does not mean that co-assistance mechanism should be free of external assistance, however. On the contrary, obtaining assistance from government, donors, and NGOs is a very important part of the co-assistance mechanism. The diagram below illustrates the operational structure of the Pilot Projects.

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-11

    Source: Project Team

    Figure 11.1 Organizational Structure for Pilot Project Implementation

    Figure 11.2 shows a suggested structure for Pilot Project implementation after the JICA Team departs in March 2006.

    Source: Project Team

    Figure 11.2 Pilot Project Structure after March 2006

    Finally, it was concluded that governmental agency involvement is essential. The JICA Project Team exchanged Memorandum of Understanding (MOU) with the governmental agencies mentioned in Table 11.1 below. MOUs for the three Pilot Projects are attached in

    Association of Affected People

    Local NGO Government Agencies

    Beneficiary

    Association of Affected People

    Beneficiary

    Beneficiary

    Beneficiary

    Beneficiary

    Beneficiary

    Additional Support from Donors

    (Including Japan)

    Association of Affected People

    JICA Project Team

    Government Agencies

    Steering Committee (JICA Team as Secretariat)

    Local NGO (Contract with JICA)

    Beneficiary

    Association of Affected People

    Beneficiary

    Beneficiary

    Beneficiary

    Beneficiary

    Beneficiary

  • Recovery, Rehabilitation and Development Project for Tsunami Affected Area of Southern Region in the Democratic Socialist Republic of Sri Lanka Final Report

    11-12

    Annexes 4-8, 5-8, and 6-7. These government agencies are also in a position to extend co-assistance approaches to other parts of the nation.

    Table 11.1 Government Agencies that Supported Pilot Projects Pilot Project Government Agencies

    1 Refugee Camps District Secretary, Divisional Secretary 2 Fishery Cooperative

    Societies Fishery Department (Matara branch office of Central Government Department) Cooperative Office (Matara branch office of Southern Provincial Council)

    3 Small Industries Industrial Development Board Source: Project Team

    A local NGO, the Berendina Foundation, has been undertaking the manager of Pilot Project implementation, while the JICA Team has acted as the supervisor. Considerable know-how in managing co-assistance projects has been accumulated in this NGO. The JICA Team also expects Berendina to stay in Matara and continue its support of beneficiary societies and associations. The associations have reached a point where they do not require daily support for their activities, thus only monitoring and occasional consultation activities would be sufficient for sustainable co-assistance activities.

  • PART IV SUPPORT OF MID-TERM REHABILITATION PLANChapter 10 Suggestions for Regional Rehabilitation Plan10.5 Preparation of Hazard Maps10.5.3 Questionnarie Survey10.5.4 Tsuanami /Flood Disaster Map10.5.5 Tsuanami Simulation10.5.6 Preliminary TSunami Hazard Map

    10.6 Implemetation of Awareness Activities10.6.1 JICA-Net Seminar10.6.2 Seminar on Disaster Management

    Chapter 11 Conclusions11.1 Conclusions11.1.1 Summary of Conclusion11.1.2 Lesson Leamed from the Project

    11.2 Recommendations11.2.1 Preparation of a List of Lesson and Checkpoints on the Disaster Rehabilitation11.2.2 Enahancement of Co-assistance Activities for Community Rehabilitation11.2.3 Promotion of Regional Disaster Management11.2.4 Dissemination of the Project Results11.2.5 Subsequent Follow-up for Project