1000MW Wind Power Project

Embed Size (px)

Citation preview

  • 7/23/2019 1000MW Wind Power Project

    1/27

    1000 MW Wind Power Project

    Key Challenges

    Z A

    Tin Min Latt

    Project Manager

    1000 MW Wind Power ProjectZeya & Associates 1

  • 7/23/2019 1000MW Wind Power Project

    2/27

    Content

    Introduction

    Wind Mapping

    Site Survey & Weather Mast Installation

    Challenges

    Conclusion

    2

  • 7/23/2019 1000MW Wind Power Project

    3/27

    Introduction

    3

  • 7/23/2019 1000MW Wind Power Project

    4/27

    Kayin & Mon

    4

  • 7/23/2019 1000MW Wind Power Project

    5/27

    Tanintharyi

    5

  • 7/23/2019 1000MW Wind Power Project

    6/27

    Tanintharyi

    6

  • 7/23/2019 1000MW Wind Power Project

    7/27

    Developer

    Gunkul Engineering Public, Thailand.

    Impact Energy Asia, Hong Kong.

    Zeya & Associates, Myanmar.

    Consultant

    GL Garrad Hassan, Australia

    7

  • 7/23/2019 1000MW Wind Power Project

    8/27

    Wind Mapping

    8

  • 7/23/2019 1000MW Wind Power Project

    9/27

    Wind Mapping Process

    International wind expert hascompleted an extensive wind

    mapping process for Myanmar.

    Micro-scale wind modeling carried

    out at a grid spacing of 1 km

    resolution.

    Wind Speed determined at hub height

    80m.

    Overall estimated wind speed mean to

    be 5.5 m/s and up to 7 m/s in some

    areas close to the border of Thailand.

    Uncertainty is inherent in this modeling

    process.

    Modeling has allowed us to choose the

    best positioning for approximately three wind

    speed recording towers, 9

  • 7/23/2019 1000MW Wind Power Project

    10/27

    CONSTRAINT SCORES

    Distance Scoring

    Transmission lines

    Population Centres

    Roads & Rails

    Grip Points Scoring

    Wind Resources

    Topographic Complexity

    10

  • 7/23/2019 1000MW Wind Power Project

    11/27

    Potential Site Information

    11

  • 7/23/2019 1000MW Wind Power Project

    12/27

    Site Survey & Weather Mast

    Installation

    12

  • 7/23/2019 1000MW Wind Power Project

    13/27

    Survey PointsM2-Tanintharyi Division

    M5-Kayin State

    M4-Mon StateM3-Mon State

    M8-Mon State

    13

  • 7/23/2019 1000MW Wind Power Project

    14/27

    M2-Kadwe Site Tanintaryi Division

    Latitude:

    1414'25.01"N

    Longitude:

    9823'47.14"E

    14

  • 7/23/2019 1000MW Wind Power Project

    15/27

    M3-Zingyalk Site Mon State

    Latitude:

    1642'16.38"N

    Longitude:

    9727'25.07"E

    15

  • 7/23/2019 1000MW Wind Power Project

    16/27

    M5-Kawkareik Site Kayin State

    Latitude:

    1632'18.20"N

    Longitude:

    9815'27.35"E

    16

  • 7/23/2019 1000MW Wind Power Project

    17/27

    M-8 Chaungsauk Site Mon State

    Latitude:

    1716'21.35"N

    Longitude:

    97 2'46.92"E

    17

  • 7/23/2019 1000MW Wind Power Project

    18/27

    Weather Mast Installation

    Soil Test

    Tower Foundation

    Tower Erection

    18

  • 7/23/2019 1000MW Wind Power Project

    19/27

    Key Challenges

    19

  • 7/23/2019 1000MW Wind Power Project

    20/27

    Key Challenges

    Technology & Experience

    Finance

    Infrastructure

    Land Leasing

    Political & Public Relation

    20

  • 7/23/2019 1000MW Wind Power Project

    21/27

    Technology & Experience

    First Project in Myanmar

    Experience Personnel

    Wind Turbine Selection

    High Tower Construction

    Meteorological Data Collection

    21

  • 7/23/2019 1000MW Wind Power Project

    22/27

    Finance

    Significant Project

    Financing and Insurance

    Power Purchase Structure

    Long Term PPA

    22

  • 7/23/2019 1000MW Wind Power Project

    23/27

    Infrastructure

    23

    RoadsAccess & Limitation

    RailsAccess & Limitation

    BridgesAccess & Limitation

    Communication

    Transmission Line Intelligent Control System for Generation

    Mix

  • 7/23/2019 1000MW Wind Power Project

    24/27

    Agriculture Area

    Reserve Forest

    Religious Building

    Land Leasing

    24

  • 7/23/2019 1000MW Wind Power Project

    25/27

    Political & Public Relation

    Local Authorities & Civilians

    Investment Law

    Rule & Regulation

    Transparency

    Environmental Impact Assessment

    Social Impact Assessment

    25

  • 7/23/2019 1000MW Wind Power Project

    26/27

    Conclusion

    There are many challenges but we are able to

    overcome them with strong support from

    ADB.

    We would like to invite companies and

    financial institutions to support technologies

    and financial to involve wind power project in

    Myanmar.

    26

  • 7/23/2019 1000MW Wind Power Project

    27/27

    Thank You