Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
The University of Southampton School of Engineering Sciences
10. STEELWORK PRODUCTIVITY
10.1 Background
In general terms, productivity is a measurement to indicate how well an operation
has been run by a unit or a system. It can be defined as the relationship between the
volume of goods and services (output) and the quantity of goods and services
required to produce that output.
Productivity =Output
Input
where: output could be the number of units produced, weight of units, length of
joint, area of manufactured units, etc. and
input represents all the effort both by the use of labour and the use of
equipment which is required to produce the output. Manhours, equipment,
design, facilities, etc. are all inputs to the system. These input are affected
by some influences over which no immediate control could be made. Work
rules, environmental conditions, economic conditions and government
regulations illustrate a few of these factors.
Productivity is then the output related to one or more of the inputs. The following
diagram shows this relationship.
Man hours Equipment Design Facilities Supervision
Work rules
The number of input
measurement.
(i) Total Productivity = La
Professor R A Shenoi
TOTAL
Economic conditions Statutes/regulations INPUTvariables used in the ratio provides two cla
Output
bour + Equipment + Facilities + . . .
Part II - S10-1
OUTPUT
sses of productivity
hip Production Technology
The University of Southampton School of Engineering Sciences
Such an index on the one hand evaluates the appropriate results obtained for the
whole firm but, on the other hand, it often omits the exact value of individual
activities.
(ii) Partial Productivity = Output
One Factor of Input
Labour and machine productivities are the more commonly used partial
measurements. In this sense, labour productivity is the amount produced divided
by the time worked and it expressed as output per manhours or vice-versa. This is
the meaning of productivity used in measuring shipyard efficiency.
Labour productivity can be further subdivided to cover major cost centres:
- Steelwork
- Outfitting
- Engineering
Steelwork productivity can be measured in terms of:
- Weight
- Wield length
- Measured day work.
Outfitting and engineering can be measured in terms of:
- Total manhours/contract/trade
- Total manhours/activity/trade
- Measured day work.
The rest of this chapter is devoted to an examination of steelwork productivity
indices.
Professor R A Shenoi Part II - Ship Production Technology 10-2
The University of Southampton School of Engineering Sciences
10.2 Weight Based Criteria
(A) Manhours/Gross Tonne
Many shipbuilders throughout the world use their own system of productivity index
in terms of manhours required to fabricate one tonne of steel. This requirement can
relate to performance of workers in different shops – eg. preparation, assembly or
fabrication. The indices for the different shops can and do vary. Some aspects of
labour are excluded. These include steelwork manhours spent after launch, all
steelwork servicing to sub-contractors, percentage claims on fabricated units, etc.
In terms of steel weight, no correction is applied for higher tensile steels and
aluminium.
(B) BSRA Manhours/Gross Tonne
In an attempt to provide a basis for inter-firm comparison and also to show the
general trend of industry, British Ship Research Association (BSRA – the force
runner of BMT – defined manhours and steel weight content to be used in the
performance calculation as follows:
Manhours - to include all shipyard boilermakers, platers, drillers, shipwrights,
loftsmen, welders, chargehands, apprentices, to exclude foremen,
supervisors, storemen. (Everything excluded here is transferred in
the fitting out on overhead returns).
Steel - to include invoiced steel (plates and sections) and all steelwork
items made in the yard such as lawsepipes, deck and machinery
seats, sternframes, etc.
to exclude bought-in items such as rudder castings, propellers, etc.
When high tensile steel and/or aluminium are used, the following
equivalents are recommended:
1 tonne of Aluminium = 2½ tonnes of mild steel.
1 tonne of HTS = 1⅛ tonnes of mild steel.
Professor R A Shenoi Part II - Ship Production Technology 10-3
The University of Southampton School of Engineering Sciences
(C) BSRA Manhours/Equivalent Gross Tonne
Up to now no difference in complexity of different ship types has not been allowed
for. For example, it is obviously easier to construct a box shaped tanker than a fine
shaped refrigerated ship. To allow for this, BSRA suggested the concept of using
the bulk carrier and cargo ship as the basis ship and applying corrections to the
gross tonnes for:
(i) Block coefficient – increase tonnes by 1% - for every 0.0% decrease in Cb
from 0.70 and vice versa if above 0.70.
(ii) Ships of complex specification (such as reefer ships) – add 5% to the
equivalent tonnes. For cargo ships, the correction is not to exceed this value.
(iii) Corrections for steel – as mentioned in the previous section above.
Example of application: consider a refrigerated ship of 10,000 tonnes deadweight
with a Cb of 0.60.
Invoiced steel: Mild Steel 4000
H.T Steel 200
Aluminium 50
The equivalent gross tonnes (EGT’s) are as follows:
Mild Steel = 4000 x 1 + = 4000
H.T Steel = 200 x 1⅛ = 225
Aluminium = 50 x 2½ = 125
4350 tonnes
BSRA factor at given deadweight 1.173
Correction for Cb (0.70 – 0.60) = 0.01 1.010
Correction for specification @ 5% 1.050
Total complexity factor = 1.173 x 1.010 x 1.050 = 1.244
Equivalent gross tonnes = 1.244 x 4350 = 5411 tonnes
Professor R A Shenoi Part II - Ship Production Technology 10-4
The University of Southampton School of Engineering Sciences
A further refinement in the use of indices can be made by allocating proportions of
the total EGTs to the various steelwork departments such as:
Preparation 10%
Fabrication 40%
Erect, fair and weld 30%
Jobbing, service, etc 20%
By applying BSRA manhours as defined in (B) for each department, the
manhours/equivalent gross tonne target figures can be deduced.
10.3 Weld/Joint Length Based Criteria
This method, though not extensively used in UK yards, is adopted in some Japanese
shipyards; it measures performance in terms of cumulative manhours against
welded length. The control centres usually cover sub-assembly, fabrication and
berth with a further subdivision in terms of the weld position. The results can be
plotted in the form shown below.
Cumulative Manhours
For quality control purpose
the target line, will initiate
Refinements in the approac
Professor R A Shenoi
Cumulative Weld Length
s any negative deviance, say, greater than 15-20% from
an investigation to determine and rectify the fault.
h include:
Part II - Ship Production Technology 10-5
The University of Southampton School of Engineering Sciences
(a) thickness correction which takes into account the fact that thicker plates
may require more time to align and would need more weld passes – see
Figure 10.1.
(b) weld position correction which accounts for the fact that downhand
(manual) welding is easier and quicker than vertical or overhead work.
(c) unit complexity which allows for differences between various stages of
work (eg. preparation, fabrication, erection) and for relative structural
complexities of different units – see Table 10.1.
As an example, consider a double-bottom unit at the fabrication stage. Assume that
all welds are performed in the downhand position.
From the material list, it was noticed that the average plate thickness of the unit was
11mm. From the drawings, the joint length was found to be 5200 mm. (An
alternative approach is for a shipyard to record hull steel weight versus weld length
data as shown in Figure 10.2. Such data can be recorded as pertaining to assembly,
sub-assembly or erection stages). From job cards, the labour content was found to
be 3061 manhours.
Thickness factor = 1.22 (From figure 10.1)
Weld position factor = 1.00 (Down hand)
Unit complexity = 1.51 (From Table 10.1)
Performance Index = 5200
30611 22 1 00 151 313 m / manhour× × × =. . . .
Professor R A Shenoi Part II - Ship Production Technology 10-6
The University of Southampton School of Engineering Sciences
Figure 10.1: Thickness Correction Factor
Table 10.1: Unit Complexity Factors
Professor R A Shenoi Part II - Ship Production Technology 10-7
The University of Southampton School of Engineering Sciences
Figure 10.2: Hull steel weight versus welded length
Figure 10.3: Basic structure of work study
Professor R A Shenoi Part II - Ship Production Technology 10-8
The University of Southampton School of Engineering Sciences
10.4 Work Study Approach
One definition, attributed to the International Labour Organisation, states that
“work study is a term used to embrace the techniques of method study and work
measurement which are employed to ensure the best possible use of human and
material resources in carrying out a specified activity.
Figure 10.3 illustrates the general structure of work stud techniques. It will be
noticed that method study is concerned with establishing optimum work methods
and work measurement deals with establishing time standards for these methods.
Method study is normally conducted before work measurement.
Figures 10.4 and 10.5 illustrate the manner in which the data is recorded. The
problem concerns specifying a time rate for fairing and tacking flat bars and angles
up to 6”. Figure 10.4 shows the problem and summarises the results. Figure 10.5
lists the method, ie. the steps required to do the job. The times would have been
recorded through the use of work measurement techniques.
The end result from work measurement is the allocation of a standard time for a
job. This can be in standard minutes or, in shipbuilding, standard hours. These
standard time values can be established from one of several methods which are
outlined in standard text books on this topic.
Standard times correspond to “the average rate at which qualified workers will
naturally work at a job, provided. They know and adhere to the specified method,
and provided they are motivated to apply themselves to their work” (quoted from
BS3138). A comparison of the actual rate of working against the standard work
rate is achieved through a performance rating index.
Professor R A Shenoi Part II - Ship Production Technology 10-9
The University of Southampton School of Engineering Sciences
Figure 10.4: Example of application – work study
Professor R A Shenoi Part II - Ship Production Technology 10-10
The University of Southampton School of Engineering Sciences
Figure 10.5: Example of method specification – work study
Professor R A Shenoi Part II - Ship Production Technology 10-11
The University of Southampton School of Engineering Sciences
Various methods of rating have been evolved and the four most popular scales are
shown in Figure 10.6. The standard performance using a British standard 100 is
considered to be equivalent to a walking speed of 4 miles/hour, are to dealing a
pack of cards into 4 hands in 22½ seconds; but unfortunately neither of these jobs
occurs frequently in industry! Hence a company needs to train the time study
analyst to recognise what the company (poor industry in general) regards as
“standard performance”.
The standard time foran element or a job is calculate as follows:
Standard time Observed timeRating
100 percent total allowance= × ×
In a shipbuilding context, the interest is centered around what information can be
obtained from the system and the corrective action that can be initiated. In terms of
management, reporting, industrial engineers can provide the following:
(A) Breakdown of hours
This comprises:
- Total attendance hours
- Total standard hours
- Unmeasured hours (eg. for marshalling of material)
- Rectification hours
- Waiting time
- Productive time (= Total attendance time – waiting time)
(B) Performance Indices:
These can be subdivided into two major groups as shown in Figure 10.7.
Based on the information recorded, the indices can be calculated and
performance criteria for both labour and machines known. The management
reports, say, produced on a weekly basis will then provide departmental
managers with sufficient information on performance and the degree to which
it is influenced by waiting time, rectification and machine utilisation, thus
prompting remedial action – see Table 10.2.
Professor R A Shenoi Part II - Ship Production Technology 10-12
The University of Southampton School of Engineering Sciences
100 Standard Performance
80 100 133
60
75
100
B.S SCALE 60/80 75/100 100/133 Scale Scale Scale
Figure 10.6: Work study rating scales
Performance Indices
Labour Machines Effective Operator Effective Operator Machine Performance Performance Performance Performance Utilisation
Effective Performance =
Unmeasured Attendance Hours at the
Standard Hours + Previous Weeks Effective Performance
Total Attendance Hours× 100
Operator PerformanceStandard Hours
Productive Hours= × 100
Machine Utilisation =
Unmeasured Attendance Hours
Standard Hours + at Previous Weeks Eff. Perf.
Manning Machine Available hours
×× 100
Figure 10.7: Performance Indices
Professor R A Shenoi Part II - Ship Production Technology 10-13
The University of Southampton School of Engineering Sciences
10.5 The Learning Curve Concept
The concept of the learning curve is that a worker learns as he works; the more
often he repeats an operation, the more efficient he becomes with the result that
direct labour per unit output declines with a corresponding increase in productivity.
Moreover, and importantly, the rate of movement is regular enough to be predicted.
Research in a number of industries has shown that there is a regular pattern of
improvement and that this is likely to be a constant percentage when cumulative
production doubles. On a double logarithmic scale the experience curve is
represented as a straight line. Figure 10.8 and 10.9 show decreases both in terms of
manhours/tonne and of weld length/manhours for bulk carriers at different
production stages and for varying modules/units respectively. The reduction in
labour time per unit can be considered as raising productivity.
In a steelwork particularly, a large percentage of work is represented by direct
labour. The learning curve could be used for four purposes.
(a) It could be used to measure the “learning productivity performance” of each
work station. After the learning curves are drawn, the learning productivity
performance will be given by their slope.
(b) It could be used to predict the manhours per tonne (Figure 10.8) or the
manhours per joint length (figure 10.9) for each of a series of ships. Having
established such graphs for the first two or three repeat ships, the prediction
of manhours per tonne required for each production stage and the total
manhours content can easily be predicted by projecting the curve.
(c) It is useful in predicting the manhours per unit length of joint for specific
units/modules for each ship, such as a stern unit, bow unit, double-bottom
unit, a deck unit, etc. (See Figure 10.9). Knowing the length of joint of each
unit and having recorded the manhours required to construct such units for
the first two or three repeat ships, the slope of the curve can be established.
It is then a simple matter to extrapolate the curve to cover requirements for
the next ships in the same series.
Professor R A Shenoi Part II - Ship Production Technology 10-14
The University of Southampton School of Engineering Sciences
Figure 10.9: Learning curve – production units Figure 10.8: Learning curve – production areas
Professor R A Shenoi Part II - Ship Production Technology 10-15
The University of Southampton School of Engineering Sciences
(d) It is necessary for purposes of comparing the learning productivity
performances of different shipyards.
The learning curve concept offers four-fold benefits.
(1) It offers a practical solution for fairly accurate forecasts of direct labour
and productivity. It’s most obvious use is forecasting output.
(2) When the rate of learning falls below the standard productivity
improvement, management and supervision would be alerted to look
for the correct causes.
(3) Realistic production goals can be set (with the learning curve effect in
mind). This would enable management to compare actual performance
with goals.
(4) If a new innovation in the production process is introduced, it will
change the slope of the learning curve. This will indicate whether the
innovation is productive or not.
Today, if a shipyard wishes to complete successfully in an increasingly
complex technological and market-orientated environment, it needs to use
every available production/productivity control tool. Productivity indices and
the learning curve concept are two simple but powerful such aids.
Professor R A Shenoi Part II - Ship Production Technology 10-16