    DETERMINATION AND ALLOCATION OF KEY

    RISK EVENTS FOR TOLLWAY

    CONSTRUCTION AND OPERATION ININDONESIA

    Djoen San Santoso

    Tri Basuki Juwono

  • 7/30/2019 10 - Santoso

    2/28

    Introduction

    Infrastructure development is important for

    economic growth.

    Main constraint for infrastructure

    development: government budget.

    Private participation in infrastructure

    development.

    Risk management.

  • 7/30/2019 10 - Santoso

    3/28

    Transportation in Indonesia

    Transportation infrastructure is one of the key

    facilities.

    Tollway construction has been intensified since

    2005, including the release of Presidential

    Regulations concerning the land procurement for

    public interest.

    Transportation = Road

    Indonesia

  • 7/30/2019 10 - Santoso

    4/28

    Tollway in Indonesia

    Risk management is not clear.

    Allocations of risks are not well agreed and some

    are not stipulated in the agreement.

    Attractiveness for investment.

  • 7/30/2019 10 - Santoso

    5/28

    Objectives

    To determine important risk events in Indonesian

    tollway.

    To analyze and propose allocation of important riskevents to serve as guideline in contract agreement.

  • 7/30/2019 10 - Santoso

    6/28

    Limitation

    Only concern about 2 parties:

    1. Government (public)

    2. Highway and tollway companies (private)

  • 7/30/2019 10 - Santoso

    7/28

    Research Method

    Secondary data:

    1. Research papers on this topic.

    2. Previous study.

    3. Documents related to tollway collected from

    government and tollway companies.

    4. Brief discussion.

    Primary data:1. Qualitative risk assessment survey.

    2. Interview.

  • 7/30/2019 10 - Santoso

    8/28

    Questionnaire Survey

    Assessment of risk are based on 2 points of views:

    1. Probability of occurrence

    2. Degree of impact

    5-point Likert scale.

    Allocation of risks

    Total valid respondents = 15

  • 7/30/2019 10 - Santoso

    9/28

    Risk Events

    55 risk events are listed in the questionnaire survey.

    Categorized into:

    1. Politic and Regulation (11 risks)

    2. Tollway company (5 risks)3. Finance and Economic (5 risks)

    4. Design (6 risks)

    5. Land Acquisition (4 risks)

    6. Construction (8 risks)

    7. Traffic (6 risks)

    8. Operation and Maintenance (8 risks)

    9. Force majeure (2 risks)

  • 7/30/2019 10 - Santoso

    10/28

    Risk Index

    Risk Index (RI) indicates the significance of the risk.

    RI = M(P) x M(I)

    where:

    M(P) = Mean of risk probability

    M(I) = Mean of risk impact

  • 7/30/2019 10 - Santoso

    11/28

    Code Risk EventProbability Impact Risk Index

    Mean Rank Mean Rank Score Rank

    R1 Instability and insecurity of the

    region

    1.71 46 3.46 9 5.93 33

    R2 Breach or cancellation of contract 1.60 48 3.73 6 5.97 32

    R3 Expropriation of the project by

    government

    2.00 34 3.07 25 6.13 30

    R4 Change in environmental policy and

    regulation

    2.13 30 2.87 33 6.12 31

    R5 Change in policy and regulation

    related to tollway

    2.07 32 3.20 21 6.61 25

    R6 Change in business policy and

    regulation

    1.80 43 3.00 28 5.40 38

    R7 Delay by government in making

    decision and approval

    3.13 4 3.36 7 10.52 4

    R8 Delay in issuing permits by

    government

    2.53 17 3.13 18 7.94 17

    R9 Coordination problem among

    government agencies related to

    tollway

    2.33 23 2.87 27 6.69 23

    R10 Inability of government to fulfill its

    responsibilities

    2.60 14 3.27 13 8.49 12

    R11 Problem with public acceptance 2.36 21 2.86 31 6.73 21

    R12 Cash flow problems due to investor 2.79 9 3.43 5 9.55 6

  • 7/30/2019 10 - Santoso

    12/28

    Code Risk EventProbability Impact Risk Index

    Mean Rank Mean Rank Score Rank

    R13 Problem in managing income 2.15 29 3.08 19 6.64 24

    R14 Agreement related problems 2.29 26 2.86 30 6.53 26

    R15 Credit related problems 2.57 16 3.36 10 8.63 11

    R16 Regulation related problems 2.29 27 2.71 37 6.20 29

    R17 Limited financial transaction 1.86 42 2.86 34 5.31 39

    R18 Exchange rate fluctuation 2.33 24 2.47 43 5.76 35

    R19 Interest rate fluctuation 2.73 10 3.07 15 8.40 15

    R20 Inflation 2.67 12 3.27 11 8.71 10

    R21 Bankruptcy of consortium's member

    or subcontractor

    2.13 31 2.93 29 6.26 27

    R22 Faults in tender specifications 1.60 49 2.73 36 4.37 48

    R23 Lack of design innovation 1.87 38 2.40 48 4.48 47

    R24 Faults in contractor's design 1.87 39 2.53 45 4.73 46

    R25 Design change requested by

    government

    2.20 28 3.20 16 7.04 20

    R26 Competition in tender 2.36 22 2.50 42 5.89 34

    R27 Project feasibility 2.60 15 3.40 8 8.84 9

  • 7/30/2019 10 - Santoso

    13/28

    Code Risk EventProbability Impact Risk Index

    Mean Rank Mean Rank Score Rank

    R28 Delay in land acquisition 4.13 1 4.00 1 16.53 1

    R29 Delay in payment related to land

    acquisition

    2.73 11 3.27 12 8.93 8

    R30 Over budget in land acquisition 3.80 2 3.80 2 14.44 2

    R31 Claim from community related to

    land right

    2.93 5 2.87 26 8.41 14

    R32 Delay in construction 2.53 18 3.07 24 7.77 18

    R33 Problems with subcontractors 1.87 40 2.67 40 4.98 42

    R34 Over budget due to new safety

    standard and environmental policy

    1.93 36 2.53 47 4.90 43

    R35 Cost over-run 2.87 7 3.20 14 9.17 7

    R36 Lack of skilled or experienced

    workers

    2.07 33 2.71 38 5.61 36

    R37 Problems related to construction

    materials

    1.87 41 2.29 49 4.27 49

    R38 Severe weather causes low

    productivity

    2.67 3 3.17 41 8.46 13

    R39 Change in construction plan due to

    third party interference

    1.93 37 2.53 44 4.90 44

    R40 Low traffic volume 2.93 6 3.80 3 11.15 3

    R41 Faults in toll system application 1.53 51 2.00 53 3.07 53

  • 7/30/2019 10 - Santoso

    14/28

    Code Risk EventProbability Impact Risk Index

    Mean Rank Mean Rank Score Rank

    R42 No increment in toll fee 2.87 8 3.60 4 10.32 5

    R43 Fail in constructing the road feeders 2.67 13 3.07 17 8.18 16

    R44 Change in plan of road network which

    directly affecting the tollway

    2.40 19 3.00 20 7.20 19

    R45 Road users do not pay toll fee 1.40 55 1.67 55 2.33 55

    R46 Unpredicted increment in personel

    cost

    2.33 25 2.67 39 6.22 28

    R47 Unpredicted increment in operationalcost

    2.40 20 2.80 32 6.72 22

    R48 Increment of import fee 1.53 52 2.33 50 3.58 52

    R49 Low traffic volume due to severe

    weather

    1.47 53 1.93 54 2.84 54

    R50 Low achievement of tollway operator 1.73 44 2.80 35 4.85 45

    R51 Technology related problems 1.67 47 2.20 52 3.67 50

    R52 Environmental related problems 2.00 35 2.53 46 5.07 40

    R53 Asset transfer problems 1.73 45 2.07 51 3.58 51

    R54 Natural force majeure (act of God) 1.60 50 3.40 22 5.44 37

    R55 Political force majeure (war, riot) 1.47 54 3.40 23 4.99 41

  • 7/30/2019 10 - Santoso

    15/28

    Top 10 Risk Events

    Based on the value of RI, the top ten risk events are

    as follows:

    Code Risk EventRisk Index

    Score Rank

    R28 Delay in land acquisition 16.53 1

    R30 Over budget in land acquisition 14.44 2

    R40 Low traffic volume 11.15 3

    R7 Delay by government in making decision

    and approval

    10.52 4

    R42 No increment in toll fee 10.32 5R12 Cash flow problems due to investor 9.55 6

    R35 Cost over-run 9.17 7

    R29 Delay in payment related to land

    acquisition

    8.93 8

    R27 Project feasibility 8.84 9

    R20 Inflation 8.71 10

  • 7/30/2019 10 - Santoso

    16/28

    Allocation of Risks

    Top 10 risks were allocated to:

    1. Project stages

    2. Suitable party (public or private or share)

    Allocation based on previous study, result of

    questionnaire survey and discussion with experts in

    tollway.

  • 7/30/2019 10 - Santoso

    17/28

    Risk Allocation to Project Stage

    Rank Code Risk EventDevelop

    ment

    Pre-Construction

    Construc

    tionOperationDetailed

    Design

    Land

    Acquisiti

    on

    1 R28 Delay in land acquisition

    2 R30 Over budget in land acquisition

    3 R40 Low traffic volume

    4 R7 Delay in making decision and

    approval by government

    5 R42 No increment in toll fee

    6 R12 Cash flow problems due to

    investors

    7 R35 Cost over-run in construction

    8 R29 Delay in payment related to

    land acquisition

    9 R27 Project feasibility

    10 R20 Inflation

  • 7/30/2019 10 - Santoso

    18/28

    Risk Allocation to Suitable Party

    Rank Code Risk Event Government

    Highway or

    Tollway

    Company

    1 R28 Delay in land acquisition

    2 R30 Over budget in land acquisition

    3 R40 Low traffic volume

    4 R7 Delay in making decision and

    approval by government

    5 R42 No increment in toll fee

    6 R12 Cash flow problems due to investors 7 R35 Cost over-run in construction

    8 R29 Delay in payment related to land

    acquisition

    9 R27 Project feasibility

    10 R20 Inflation

  • 7/30/2019 10 - Santoso

    19/28

    Land Acquisition Risks

    Risks related to land acquisition:

    1. Delay in land acquisition (R28)

    2. Over budget (R30)

    3. Cash flow problems due to investors (R12)

    4. Delay in payment (R29)

    Possible reasons:

    Availability of cash.

    Land price is not acceptable.

    Land brokers and speculators.

  • 7/30/2019 10 - Santoso

    20/28

    Land Acquisition under Government

    Rank Code Risk Event Government

    Highway or

    Tollway

    Company

    1 R28 Delay in land acquisition

    2 R30 Over budget in land acquisition

    3 R40 Low traffic volume

    4 R7 Delay in making decision and

    approval by government

    5 R42 No increment in toll fee

    6 R12 Cash flow problems due to investors 7 R35 Cost over-run in construction

    8 R29 Delay in payment related to land

    acquisition

    9 R27 Project feasibility

    10 R20 Inflation

  • 7/30/2019 10 - Santoso

    21/28

    Land Capping110%

    Rank Code Risk Event Government

    Highway or

    Tollway

    Company

    1 R28 Delay in land acquisition

    2 R30 Over budget in land acquisition

    3 R40 Low traffic volume

    4 R7 Delay in making decision and

    approval by government

    5 R42 No increment in toll fee

    6 R12 Cash flow problems due to investors 7 R35 Cost over-run in construction

    8 R29 Delay in payment related to land

    acquisition

    9 R27 Project feasibility

    10 R20 Inflation

  • 7/30/2019 10 - Santoso

    22/28

    Approval and Toll Fee Increment

    Delay in making decision and approval (R7) and No

    increment in toll fee (R42) are under government

    control Governments responsibility.

    R7 is at the development stage. While R42 is at the

    operation stage.

  • 7/30/2019 10 - Santoso

    23/28

    Low Traffic Volume

    Directly related to income.

    Allocated to tollway company?

    Investment project so risk is under investor.

    Share with government?

    Attract investor to financially less feasible project.

    Downside risk protection. Downside risk protection with clawback clause.

  • 7/30/2019 10 - Santoso

    24/28

    Cost Overrun and Inflation

    COST

    OVERRUNManagement of

    project

    Change

    order

    INFLATION

    Wrong cost

    estimation

    Tollway companyGovernment

    Delay in

    approval

  • 7/30/2019 10 - Santoso

    25/28

    Project Feasibility

    Exists in the Development and Pre-Construction

    (Detailed Design) stages.

    At Development stage (tender process), cost could

    not be recovered if could not win the project.

    At Detailed Design stage: limited information on

    the Development stage (ground condition, shifting

    the toll route due to problem in land acquisition).

  • 7/30/2019 10 - Santoso

    26/28

    Conclusions

    Proper identification and allocation of risks are

    important to attract investors.

    Regulations on risk allocation should be clearly

    stated in the agreement.

    Government is expected to be more proactive in

    managing land acquisition risks.

  • 7/30/2019 10 - Santoso

    27/28

    Acknowledgement

    Toll Road Regulatory Board (Badan Pengatur Jalan

    Tol)

    PT. Citra Murni Semesta

    Dr. Wimpy Santoso, Dr. Andreas Wibowo and Mr.

    Harlan Pangihutan

  • 7/30/2019 10 - Santoso

    28/28

    THE END

    THANK YOU