10 Most Common Mistakes Schedulers Make

Embed Size (px)

Citation preview

  • 8/18/2019 10 Most Common Mistakes Schedulers Make

    1/2

    10 Most Common Mistakes

    Schedulers Make

    Good schedulers are hard to come by. Most of them have either IT or field experience,

    but few have both skill sets. Practical, or field experience, is invaluable to a scheduler,

    because it enables him to see the project from a builder’s standpoint. Experience with

    scheduling programs is a prerequisite of a solid schedule: if you don’t’ know how to

    substantially use the program, it won’t matter what field experience you possess.

    That being said, a scheduler optimally has both field and schedule programming

    experience. With these tools a scheduler can do his best work, as his expertise

    encompasses both the practical and theoretical. Nevertheless; regardless of

    background, there are some basic pitfalls that any scheduler must be wary of. Technical

    errors are plainly evident in the schedule, and can be readily identified in the oversight

    process, whereas practical, or non-technical mistakes are more generic. Here are 10 of

    the most common type of non-technical mistakes that schedulers make:

    1. Failure to solicit or incorporate the builder’s input: the builder is the

    best resource for determining the sequence of installations. Quite often,

    he is the only one who really knows this sequence, as it pertains directly

    to his means and methods. It is therefore eigent not only to solicit this

    data from the builder, but also to ensure that his data set is complete.

    !any builders assume that the scheduler will determine the pro"ect

    logic independently. It is incumbent on the scheduler to educate the

    builder as to what is required of him.

    #. Failure to study the pro"ect drawings, or incorporate knowledge from a

    proper plan re$iew into the schedule.

    %. Failure to be cogni&ant and obser$ant of pro"ect speci'cation

    requirements that are stated in the pro"ect manual. ($ery public agency

    seems to ha$e its own scheduling standards, thus it is e$er important to

    consider each pro"ect independently.

  • 8/18/2019 10 Most Common Mistakes Schedulers Make

    2/2

    ). Inability to correctly eecute mitigation measures * or to conduct

    mitigation without the builder’s input. !itigation and reco$ery e+orts

    require interface with the contractor. nilateral measures only ensure

    that the schedule will ha$e to be reworked once the contractor has his

    say.

    -. (rrors and omissions: a theoretician is more likely to not reali&e many

    of the subtasks that compose the more comple acti$ities, and to

    generate a broad stroke schedule that will require ma"or etrapolation.

    /. Inability to generate and obtain owner appro$al of the schedule before

    the pro"ect starts. In this way, it is not possible for updates to keep pace

    with actual progress.

    0. missions of interrelated sequences: many acti$ities ha$e se$eral

    relationships with other acti$ities. 2oo often, these are not represented.

     2he mistake becomes e$ident in the update process, when acti$ities

    that cannot be performed show positi$e 3oat 4they appear to be ready

    to perform5.

    6. nderrepresentation of the submittalappro$al process. ften, a

    scheduler does not allow enough time for the detailing, preparation,

    issuance of submittals * especially resubmittals, and a su7cient window

    for the appro$al process, e$en though the term for re$iew is typically

    found in the pro"ect speci'cations.

    8. 9ack of contingency and o$ercompression: more aggressi$e schedules

    ha$e less 3oat. ontractors often allow themsel$es to get roped in to

    such pro"ects well knowing that there is a good chance they may not

    meet the substantial completion date.

    1;. Inability to track change orders and their e+ect on the critical path.