1

Systems Analysis & Design

System Development Process

IS 431: Lecture 2

CSUN Information Systems

http://www.csun.edu/~dn58412/IS431/IS431_F15.htm

Page 2: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 2

System Development Process

Value Chain and Innovation CyclePrinciples of systems development.PIECES framework for categorizing problems,

opportunities, and directives.Systems development phases: purpose, inputs, and

outputs.Alternative “routes” through the basic phases of

system development. Computer-aided systems engineering (CASE) and

application development environments (ADEs)

Page 3: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

Value Chain & Five Forces Model

3IS 431 : Lecture 2

Page 4: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 4

The Value Chain

FIRM INFRASTRUCTURE

INBOUNDLOGISTICS

OPERATIONS OUTBOUNDLOGISTIC

MARKETING& SALESLOGISTIC

SERVICE

HUMAN RESOURCE MANAGEMENT

TECHNOLOGY DEVELOPMENT

PROCUREMENT

VALUE

COST MARGIN

                       

   

Page 5: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 5

The Value Chain

INBOUNDLOGISTICS

OPERATIONSOUTBOUNDLOGISTICS

MARKETING& SALES

SERVICE

SUPPORT ACTIVITIES

Receiving, Storing,

Distributing Raw Materials

ManufacturingDistribution

Order ProcessingAdvertising

SellingRepair

Maintenance

FIRM INFRASTRUCTUREHUMAN RESOURCESTECHNOLOGYPURCHASING

PRIMARY ACTIVITIES

Page 6: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 6

Value-Added Activities

Customer-Value-Added Activity (maximize)– a business process generating a value (utility) that a

customer is willing to pay for Business-Value-Added Activity (minimize)

– a business process that is essential to managing an organization (cost)

Non-Value-Added Activity (eliminate)– customer will not pay; business value will not be

increased (waste)Goals of a business system: effective (do right

thing), efficient (do thing right), competitive (do thing differently).

Page 7: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 7

STRATEGIC

OPERATIONAL

EXECUTIVE INFORMATION SYSTEMS

MANAGEMENT INFORMATION SYSTEMS

TRANSACTION PROCESSING SYSTEMS

ACCOUNT I NG

F I NANCE

HUMAN  RES

PRODUCTION

SALES

OTHERS

TACTICAL

VALUE CHAIN

    

 

Information Systems in Organization

Page 8: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 8

Emerging Technology in Business Innovation Cycle

Page 9: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 9

Page 10: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 10

System Development Process

System development process – a set of activities, methods, best practices, deliverables, and automated tools that stakeholders use to develop and continuously improve information systems and software

CMM RequirementA consistent process for system development assures

– Efficiencies to allow management to shift resources between projects (best practices/ thorough procedures)

– Consistent documentation to reduce lifetime costs to maintain the systems (by other developers/teams)

– Consistent quality across projects

Page 11: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 11

CMM Process Management Model

Capability Maturity Model (CMM) – a standardized framework for assessing the maturity level of an organization’s information system development and management processes and products. It consists of five levels of maturity:

– Level 1—Initial: System development projects follow no prescribed process.

– Level 2—Repeatable: Project management processes and practices are established to track project costs, schedules, and functionality.

– Level 3—Defined: A standard system development process (a “methodology”) is purchased or developed. All projects use a version of this process to develop and maintain information systems and software.

– Level 4—Managed: Measurable goals for quality and productivity are established.

– Level 5—Optimizing: The standardized system development process is continuously monitored and improved based on measures and data analysis established in Level 4.

Page 12: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 12

System Development Process and Quality

CMM Project Statistics for a Project Resulting

in 200,000 Lines of CodeOrganization’s CMM Level

Project Duration (months)

Project Person-Months

Number of Defects Shipped

Median Cost ($ millions)

Lowest Cost ($ millions)

Highest Cost

($ millions)

1 30 600 61 5.5 1.8 100+

2 18.5 143 12 1.3 .96 1.7

3 15 80 7 .728 .518 .933

Page 13: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 13

Life Cycle vs.Methodology

System life cycle – the factoring of the lifetime of an information system into two stages, (1) systems development and (2) systems operation and maintenance.

System development methodology – a standardized development process that defines a set of activities, methods, best practices, deliverables, and automated tools that system developers and project managers are to use to develop and continuously improve information systems and software.

Page 14: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 14

A System Life Cycle

Page 15: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 15

System Development Methodologies

Architected Rapid Application Development (Architected RAD)

Dynamic Systems Development Methodology (DSDM)

Joint Application Development (JAD)Information Engineering (IE)Rapid Application Development (RAD)Rational Unified Process (RUP)Structured Analysis and DesigneXtreme Programming (XP)

Page 16: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 16

Principles of System Development

Get the system users involved.

Use a problem-solving approach.

Establish phases and activities.

Document throughout the development.

Establish standards.

Manage the process and projects

Justify systems as capital investments.

Don’t be afraid to cancel or revise scope.

Divide and conquer.

Design systems for growth and change.

Page 17: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 17

A Meeting TranscriptSystem Developer:

– “I am going to build a P2P system [???] with killer apps in PHP and CCC [???] running on cutting-edge technologies DSL and XYZ [???].”

System Owner/User:

– “Would YOUR system solve MY problem [in singular] or it just introduce YOUR %&$# [unprintable term / bleep] technology and leave ME to figure out the solutions for new problems [in plural] created by YOU &%$# &c&c… [again, longer and stronger unprintable terms / louder bleep-bleep-bleep] ? ”

Page 18: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 18

Principles of System Development …

Principle 1: Get the owners and users involved in all system development phases.

User Participation/Involvement creates “System Ownership” and leads to User Acceptance and User Satisfaction .

Bottom line: owners and users will live with the system !!!

“OUR system [owners + users + developers] will be effective, efficient, competitive, user friendly etc, etc [fiddles playing softly in the background…]”

Page 19: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 19

Principles of System Development …

Principle 2: Use a problem solving approach

– Study and understand the problem in its context

– Define the requirements of a suitable solution

– Identify candidate solutions and select the best available

– Design and /or implement the solution

– Observe and evaluate the solution impact, and refine the solution accordingly

Solve a WRONG problem with a WRONG solution !!!

Page 20: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 20

Principles of System Development …

Principle 3: Establish phases and activities (define a process to follow)

– Scope definition

– Problem Analysis

– Requirement Analysis

– Logical Design

– Decision Analysis

– Physical Design and Integration

– Construction and Testing

– Implementation and Delivery

These phases identify problems, evaluate, design, and implement solution (Systems Development Process)

Page 21: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 21

Principles of System Development …

Principle 4: Document throughout the system development process

– Ongoing activity to reveal strength and weakness of the system during the development process

– Enhance communication and acceptance among stakeholders

– Agreements and Contracts between Owner/User and Analyst/Designer on the Scope, Requirements, Resources of the project.

Page 22: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 22

Principles of System Development …

Principle 5: Establish standards for consistency

– System development standards: documentation, methodology

– Business standards: business rules and practices

– IT standards : common architecture and configuration for a consistent system development

Page 23: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 23

Principles of System Development …

Principle 6: Manage the process and projects– Process management : ongoing activity that documents,

manages, oversees the use of, and improves an organization’s chosen methodology (the “process”) for system development. Process management is concerned with phases, activities, deliverables, and quality standards should be consistently applied to all projects.

– Project management : the process of scoping, planning, staffing, organizing, directing, and controlling a project to develop an information system at a minimum cost, within a specified time frame, and with acceptable quality.

Page 24: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 24

Principles of System Development …

Principle 7: Justify Systems as Capital Investments

– Strategic Information System Plan fits in and supports Strategic Enterprise Plan

– There are several possible solutions, the first one is not necessary the best *

– Feasibility of each solution in terms of

Cost Effectiveness: Cost/benefit analysis

Risk management: Identification, evaluation, and control of potential threat to the completion of a system

* In fact, there is a saying “ If you have two alternatives to solve a problem, the third one is the best ” (See Murphy’s Laws)

Page 25: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 25

Principles of System Development …

Principle 8: Don’t be Afraid to Cancel and Revise Scope: Creeping Commitment

– Expectation and scope of a project may be growing up

– Development process has checkpoints for its phases: all costs committed so far are sunk costs.

Cancel the project if it is no longer feasible (ORGANIZATION)

Reevaluate/adjust cost/schedule if the scope expanding (ANALYST)

Reduce the scope if budget/schedule shrinking (ANALYST)

Page 26: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 26

Principles of System Development …

Principle 9: Divide and Conquer

– Divide a complex system into simpler subsystems /components

– Problem solving process could be simplified for smaller problems

– Different subsystems for different stakeholders

Page 27: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 27

Principles of System Development …

Principle 10: Design Systems for Growth and Change

– The entropy of a system

– Changes of technology, user requirements

– Flexibility and adaptability should be built into the system

Page 28: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 28

Where Do Systems Development Projects Come From?

Problem – an actual undesirable situation that prevents the organization from fully achieving its purpose, goals, and/or objectives.

Opportunity – a chance to improve the organization even in the absence of an identified problem (using PIECES framework).

Directive - a new requirement that is imposed by management, government, or some external influence/parties.

Page 29: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 29

Where Do Systems Development Projects Come From?

Planned Projects

– An information systems strategy plan has examined the business as a whole to identify those system development projects that will return the greatest strategic (long-term) value to the business

– A business process redesign has thoroughly analyzed a series of business processes to eliminate redundancy and bureaucracy and to improve efficiency and value added. Now it is time to design/redesign the supporting information system for those redesigned business processes.

Page 30: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 30

Where Do Systems Development Projects Come From?

Unplanned projects

– Triggered by a specific problem, opportunity, or directive that occurs in the course of doing business.

– Steering committee – an administrative body of system owners and information technology executives that prioritizes and approves candidate system development projects.

– Backlog – a repository of project proposals that cannot be funded or staffed because they are a lower priority than those that have been approved for system development.

Page 31: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 31

PIECES Framework for Systems Improvement

P the need to improve performance

I the need to improve information (and data)

E the need to improve economics, control costs, or

increase profits

C the need to improve control or security

E the need to improve efficiency of people and processes

S the need to improve service to customers, suppliers, partners, employees, etc.

(They are Opportunities for New System Development Projects)

Page 32: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 32

Classic Project Phases

Page 33: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 33

System Building Blocks

Page 34: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 34

1. Scope Definition

• Purpose: define perceived problems, opportunities, and directives (POD); assess the risk of project; establish scope, preliminary requirements and constraints, participants, budget and schedule (preliminary study)

• Issues: Is the project worthwhile? (using PIECES framework) Define the scope of project

• Deliverable: Project charter/plan

•Feasibility check: Cancel project / Approve to continue / Reduce or expanse the scope with budget and schedule modification

Page 35: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 35

2. Problem Analysis

• Purpose: to study and analyze the existing system from the users’ perspectives as they see Data, Processes, and Interfaces

• Issue: Cost/benefits of building new system to solve these problems

• Deliverable: system improvement objectives (business criteria to evaluate the new system)

• Feasibility check: Cancel project / Approve to continue / Reduce or expanse the scope with budget and schedule modification

Page 36: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 36

3. Requirement Analysis

• Purpose: discover users’ needs or expectations out of the new system in terms of Data, Processes, and Interfaces

• Issue: Specify requirements for the new system (WHAT TO BE DONE) without prematurely expressing technical details (HOW)

• Errors and omissions in requirement analysis result in user dissatisfaction of final system and costly modifications

• Deliverable: business requirements statement

Page 37: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 37

4. Logical Design• Purpose: translating business user requirements into a system model that depicts only WHAT TO DO without specifying any possible technical design or implementation of those requirements (conceptual design). • Issue: using graphical model of a system to represent user requirements in terms of Data, Processes and Interfaces, and to facilitate improved communication between system stakeholders.•Caution: Analysis paralysis – excessive system modeling dramatically slows progress toward implementation of the intended system solution.•Deliverable: Logical Systems Models (DFD, ERD etc)

Page 38: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 38

5. Decision Analysis

• Purpose: identify all candidate solutions, analyze the feasibility of each candidate, recommend a candidate system as the target solution

• Issue: Feasibility analysis in terms of technical, operational, economic, schedule (TOES), and risk

•Deliverable: approved system proposal

•Feasibility check: Cancel project / Approve system proposal with budget and schedule modification / Reduce the scope of proposed solution with budget and schedule modification

Page 39: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 39

Decision Analysis Preview

Candidate solutions evaluated in terms of TOES and Risks:– Technical feasibility – Is the solution technically practical? Does

our staff have the technical expertise to design and build this solution?

– Operational feasibility – Will the solution fulfill the users’ requirements? To what degree? How will the solution change the users’ work environment? How do users feel about such a solution?

– Economic feasibility – Is the solution cost-effective?

– Schedule feasibility – Can the solution be designed and implemented within an acceptable time?

– Risk feasibility – What is the probability of a successful implementation using the technology and approach? (Risk Management)

Page 40: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 40

6. Physical Design• Purpose: to transform business requirements into technical design specifications for construction

• Issue: HOW technology will be used to build the system in terms of Data, Processes, and Interfaces

• Design by Specifications vs. Design by Prototyping

• Deliverable: System design specifications (blueprints)

•Feasibility check: Continue/ Reduce or expanse the scope with budget and schedule modification

Page 41: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 41

7. Construction Phase

• Purpose: to build and test a system that fulfill business requirements and design specs; implement interfaces between new and existing systems

• Issue: Construct database, application programs, user/system interfaces, implement purchased or leased software

• Deliverable: proposed system within budget and schedule

Page 42: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 42

8. Implementation Phase

• Purpose: deliver the production system into operation

• Issue: Train users, write manuals, load files, populate database, final test

• Conversion plan: parallel systems, switch point

• Deliverable: system up and running

Page 43: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 43

Operation and Support

• Ongoing system support would be provided until the system becomes obsolete and is replaced by a new one

• Issues: technical support for user, fixing bugs, recovering plan, adapt to emerging requirements

• When a system has reached entropy, new project for new system should be initiated

Page 44: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 44

Summary: Systems Development Process

Scope Definition Phase: What Business ProblemProblem Analysis Phase: What System Issues

(Info/Data, Processes, Communications/Interfaces)Requirement Analysis Phase: What User NeedsLogical Design: Conceptual Model – What to DoDecision Analysis Phase: What SolutionDesign Phase: Physical Model: How to DoConstruction Phase: Do ItImplementation Phase: Use It

Page 45: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 45

Systems Development Process in Practice

Page 46: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 46

System Development Documentations

Page 47: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 47

Cross Life-Cycle Activities

Cross life-cycle activity – any activity that overlaps many or all phases of the systems development process.

– Fact-finding Fact-finding - the formal process of using research, interviews,

meetings, questionnaires, sampling, and other techniques to collect information about system problems, requirements,and preferences.

– Documentation and presentation Documentation – the ongoing activity of recording facts and

specifications for a systems for current and future reference. Presentation – the ongoing activity of communicating findings,

recommendations, and documentation for review by interested users and mangers.

Repository – a database and/or file directory where system developers store all documentation, knowledge, and artifacts for one or more information systems or projects.

– Feasibility analysis– Process and project management

Page 48: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 48

System Analysis & Design Approaches

DEVELOPMENT

• Modeling

• Prototyping (RAD)

IMPLEMENTATION

• Build (In-house)

• Buy (COTS)

Page 49: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 49

Model-Driven Development

Page 50: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 50

Model-Driven Development

Model-driven development – a system development strategy that emphasizes the drawing of system models to help visualize and analyze problems, define business requirements, and design information systems.

– Process Modeling – a process-centered technique popularized by the structured analysis and design methodology used models of business process requirements to derive effective software designs for a system.

– Data Modeling – a data-centered technique to model business data requirements and design appropriate database systems.

– Object Modeling – a technique to merge the data and process concerns into singular constructs called objects. Object models are diagrams that document a system in terms of its objects and their interactions.

Page 51: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 51

Model-Driven Development …

Advantages:

– Planning ahead

– Extensive modeling current system and requirement analysis

– Analyze many alternative technical solutions

– Suitable for well understood systems

Page 52: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 52

Model-Driven Development …

Disadvantages:

– Long duration

– Passive participation of user as they don’t see the product

– Requirements in each phase should be fully addressed: impractical and/or inflexible

Page 53: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 53

Rapid Application Development

Page 54: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 54

Rapid Application Development

Rapid application development (RAD) techniques emphasize extensive user involvement in the rapid and evolutionary construction of working prototypes of a system to accelerate the system development process.

RAD is based on building prototypes that evolve into finished systems (often using time boxing)

– A prototype is a smaller-scale, representative or working model of the users’ requirements or a proposed design for an information system.

– A time box is a non-extendable period of time, usually 60-120 days, by which a candidate system must be placed into operation. Improvements will be released in later versions

Page 55: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 55

Rapid Application Development …

Advantages:

– Handle uncertain or imprecise user requirements

– Active user participation in building physical product: increase enthusiasm, support

– Early detection of errors and omissions: with testing and modifying prototype

– Reduce risk with iterative prototyping

Page 56: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 56

Rapid Application Development …

Disadvantages:

– Increase lifetime costs to operate, support, and maintain the system (constantly doing and fixing)

– Short problem analysis may result in solving wrong problems

– Discourage an analyst from considering other technical alternatives than the one being used in prototyping

Page 57: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 57

Commerce Application Package

Page 58: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 58

Commerce Application Package

Commercial application package – a software application that can be purchased and customized to meet the business requirements of a large number of organizations or a specific industry. A synonym is commercial off-the-shelf (COTS) system.

– Request for proposal (RFP) for all potential vendors

– Request for quotation (RFQ) for some selected vendors

– Gap analysis – a comparison of business and technical requirements against the capabilities and features of a specific commercial application package for the purpose of defining the requirements that cannot be met.

Page 59: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 59

Commercial Off-the-Shelf Software …

Advantages

– Fast implementation of new system (many functions are similar across businesses, no need to build them from scratch.)

– No need for expertise and staff for in-house development

– Low development costs (but expensive to customize and implement !!!)

– Vendors are responsible for software improvements and error corrections

Page 60: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 60

Commercial Off-the-Shelf Software …

Disadvantages

– Dependent on the vendors

– Future upgrade/customization is expensive

– A COTS rarely reflects ideal solution developed in-house

– Changing current business processes to fit the COTS

Page 61: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 61

Hybrid Strategies

Page 62: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 62

Hybrid: Multiple Implementation

Page 63: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 63

Hybrid: Staged Implementation

Page 64: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 64

System Maintenance

Page 65: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 65

Automated Tools and Technology

Computer-aided systems engineering (CASE)

Application development environments (ADEs)

Process and project managers

Page 66: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 66

Computer-Assisted Software Engineering

Computer-aided systems engineering (CASE) – the use of automated software tools that support the drawing and analysis of system models and associated specifications. Some CASE tools also provide prototyping and code generation capabilities.

– CASE repository – a system developers’ database where developers can store system models, detailed descriptions and specifications, and other products of system development. Synonyms include dictionary and encyclopedia.

– Forward engineering – a CASE tool capability that can generate initial software or database code directly from system.

– Reverse engineering – a CASE tool capability that can generate initial system models from software or database code.

Page 67: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 67

CASE Tool Architecture

Page 68: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 68

Application Development Environments

Application development environments (ADEs) – an integrated software development tool that provides all the facilities necessary to develop new application software with maximum speed and quality. A common synonym is integrated development environment (IDE)

– ADE facilities may include: Programming languages or interpreters Interface construction tools Middleware Testing tools Version control tools Help authoring tools Repository links

Page 69: 1 Systems Analysis & Design System Development Process IS 431: Lecture 2 CSUN Information Systems dn58412/IS431/IS431_F15.htm

IS 431 : Lecture 2 69

Process and Project Managers

Process manager application – an automated tool that helps document and manage a methodology and routes, its deliverables, and quality management standards. An emerging synonym is methodware (e.g., Visio, Visible Analyst, Rational Rose etc.).

Project manager application – an automated tool to help plan system development activities (preferably using the approved methodology), estimate and assign resources (including people and costs), schedule activities and resources, monitor progress against schedule and budget, control and modify schedule and resources, and report project progress (e.g., MS Project etc.).