Upload
christian-todd
View
215
Download
2
Embed Size (px)
Citation preview
1
SPDC
Outline
– Concept Definition – Models of PPP– Risk Classification– Hazards and Effect Management process (HEMP)– Risk Assessment– Management of Hazards to ALARP– Development Poles Approach Towards PPP– Leveraging PPP for Environmental Hazards Management– Conclusion
2
SPDC
PRIVATE-PUBLIC-PARTNERSHIP AS A VERITABLE MODEL FOR ENVIRONMENTAL HAZARDS
& RISK REDUCTIONPaper Delivered At The 1st Annual Conference of Emergency,
Crisis & Risk Management Institute.
at CMD Shangisha, Lagos
On December 2, 2011By
Paul Akporowho mnes, mnitp, rtp
3
SPDCConcept Definition-I
1.0 Introduction
Typically, public-private partnership (PPP) is a concessionary accord between the public and the organized private sectors. The public sector could be government at any level (Local/ Municipal, State/ Region or Centre/ Federal). The public sector role is usually that of providing land, enabling environment and some times market while the private investors provide the funds, technicality/ technology and assume the role of facility operator/ manager with a view of providing affordable and competitive public services/ goods.
The merits of PPP includes but not limited to the following:
• Reduce operational and overhead cost for public products/ services
• Enhance risk allocation;
• Timely delivery of public infrastructures/ services;
• Improve quality of public products and services;
• Improve revenue generation.
4
SPDCConcept Definition-II
. PPP is essentially aimed at circumvent the inherent bureaucracy
that makes the public sector less efficient while taking advantage of the efficiency and management qualificationsof the organized private sector without compromising quality and standards of outputs,The private sector is profit oriented unlike the public sector that is essentially driven by social and political forces. The PPP arrangement tends to identify the party that is better suited to bear the risk and allocate such risk accordingly. Consequently, loss is minimize while return on investment is better assured.
5
SPDC
Examples of Public-Private Partnership includes but not limited to the following:Build-Operate Transfer (BOT), Build-Own-Operate Transfer (BOOT), Rehabilitate-Operate Transfer (ROT) and Joint Venture Development (JVD)The preceding tabular presentation is an overview of the basic features of the various models.
Models Features Examples Risk Allocation
Contractual Schemes Marginal involvement of the private sector
Printing and sales of bus tickets by private firm.
Minimal risk borne by private sector
Build –Operate Transfer Leasehold & facility mangers scheme
Recreational facilities Minimal risk to Public sector
Build-Own-Operate Transfer
Leasehold Shipping/ Air line Minimal risk to public sector
Rehabilitate-Operate Transfer
Highly technical/ financially demanding infrastructural schemes
Upgrading of market/ shopping centres
Risk distributed between Beneficiaries and investors with the public sector guaranteeing the loan.
Joint-Venture Development Jointly held Corporative Oil field exploration and exploitation.
Risk shared & Responsibilities are spread across board.
Models of PPP
6
SPDCWhy PPP?
Public-private partnerships are becoming highly valuable in the provision of a wide range of public services and infrastructures. The transportation and communication sector has received much attention due to the failure of the public sector to meet the growing demand in this sector. Another sector that is clamoring for the attention/ adoption of the PPP is the energy and environmental management sectors. The energy and environmental management sectors are often perceived as social responsibilities because they are characterized by externalities which makes it very difficult/ costly to exclude others from benefiting from such services and products. For instants, it is very difficult or almost impossible to exclude others from benefiting from a cleaning and healthy environment. Pricing/ willingness to pay makes the environment unattractive to investment because investors often find it difficult to recoup their investment in a project where the willingness to pay is minimal or non-existence. It is only with special intervention such as provision of a concession agreement that will protect and empower private investors to recoup their funds that will attract such investors to contemplate venturing into such sectors. Special strategies such as erection of toll gates and other barriers can ensure that only those who pay for such services benefit directly from such services/ products.
7
SPDC
The guiding principle of PPP is to reduce and manage risk with a view of ensuring value for money.The primary responsibility of the private party is to evolve and adopt strategies that will improve service delivery within project delivery schedule without overrunning the cost. The public sector on the other hand is to create appropriate incentives and motivation that will attract the appropriate demand and patronage that will sustain the scheme.
Objective of PPP
8
SPDC
• Construction risk This risk is directly associated with design and construction phase of the scheme/ project, i.e. the risk of poor project conceptualization, definition, costs overruns, late delivery of the asset• Financial risk This risk is related to the charges of interest or exchange and offshore financiers are usually more exposed to changes and factors that can influence the cost of financing a project;• Performance/availability risk This risk is associated with the delivery/availability of the asset against contractual specification, i.e. the failure to meet quality standards or to ensure the continuity of service provision;• Demand riskThis risk is linked to the actual need for the service, i.e. the risk that the overall demandfor the service/asset concerned turns out being lower than initially expected;• Residual value This risk has to do with the future market price of the asset; it is particularly relevant if property/ asset must be transferred back to the public entity at the end of the contract.
Risk Classification in PPP
9
SPDC
Activities Environmental Hazards
Impacts Consequences RiskClassification
Oil Exploration & Exploitation
Oil Spill Soil & Water Contamination/ pollution
Destruction of aquatic/ marine life
Lumbering & Urbanization Deforestation global warming Climate change & epidemiological related issues
Dredging & land reclamation Salinization & flooding Coastal erosion, Settlement displacement
Lose of habitation, fatality & Siltation
Mining Erosion & landslide Landscape degradation
Settlement/ community displacement
Transportation, waste incineration & power generation
Emission of greenhouse gases
Ozone layer depletion & acid rain
Loss of biodiversity & epidemiological related issues
Commercial & mechanized farming
Deforestation & land contamination
Erosion and soil quality alteration
Desertification & Biodiversity loss
Hazards and Effective Management Process (HEMP) in Perspective
10
SPDCEnvironmental Hazards
Environmental Hazard are mainly man induce circumstances, phenomenon,
situation which result in undesirable occurrence and substances with potential
to cause harm either directly or indirectly. This is not say that Environmental
Hazards do not occur naturally but their impact and effect are usually
aggravated by human activities.
The scale and consequences of such occurrence may range from minor to
catastrophic in nature depending on several factors.
HEMP is highly valuable in identification and evaluation of environmental
hazards. The severity of impact and likelihood of occurrence are employ in
combination with other parameters in the determination and classification of
risk level.
Potentially impacted target (persons/ objects) are also very critical in this
analysis.
11
SPDC
• “Environmental Hazards” is any condition, situation or source of physical or other nature, that causes or may cause undue negative consequences; in terms of human injury, damage to property, or a combination of these.
• “Hazard Identification" is the process of recognizing that a hazard exists and defining its characteristics.
• "Hazard Assessment" is the overall process of determining significant level of Hazards.
• "Significant hazard" means a hazard that is an actual or potential cause or source of
Serious harm (that is more than trivial) the severity of the effects on any target depend on the extent or frequency of the target's exposure to the hazard
"Harm" means “ illness, injury or both". The term is only used in the context of harm that is more than trivial.
• “Environmental Impact” -Any change to the environment, whether adverse or beneficial, wholly/ partially resulting from human activities.
Key Component of HEMP
12
SPDCRisk Assessment Rating
(a) A potential Severity RatingWhat degree of injury or illness could occur? 1 Negligible2 Minor3 Major (includes possible long term disabling effects)4 Fatality (Resulting to loss of life)
(b) A probable Frequency RatingWith this hazard how likely is it that an injury/ illness/ damage will occur? 1 Remotely possible2 Known to have happened in the past3 Strong possibility of it happening4 Has happened before within the company5 Happens all the time
13
SPDC
A risk assessment number for each hazard is compiled by using the table below. Hazards with the highest rating are given priority.
Severity 4 3 2 1
Frequency
5 20 15 10 5
4 16 12 8 4
3 12 9 6 3
2 8 6 4 2
1 4 3 2 1
Risk Assessment Table
Each hazard is weighted/ scored and entered in their respectful column on the hazards register/ table where further can be taken on how to control and manage such risk to an ALARP level.
14
SPDC
"Significant Hazards" are identified according to the definition above. Where a significant hazard is to be controlled, this must, if practicable, be by elimination. Where elimination is not practicable then the hazard must be isolated. Only where both elimination and isolation are not practicable are methods of minimization to be applied. Environmental Management Programme (EMP) are developed and implemented towards controlling of significant hazards that have been identified, but have not been permanently controlled. Information on this control programme must be made available to responsible parties and affected stakeholders, and should include:
•the nature and location of the significant hazard; •the preferred method of control and steps to be taken; •the date by which work is to be completed; •the person(s) responsible for the work; and•the date the action was completed.
Management of Hazards to ALARP
15
SPDCKey Stages to the Environmental Risk Analysis
• “FISH BONE” Option/ Methodology
• Identify the key Environmental Impacts
• For each Impact, map out each of the processes using a Ishikawa-diagram
• Identify the key environmental Impact within the process
• Complete a risk assessment for each Impact
16
SPDCStructure causes: Ishikawa-diagram
environmental problem
people equipment
material external conditions
methods
17
SPDCStructure causes: Ishikawa-diagram
high Energy consumption
people equipment
material external conditions
methods
Uninformed &
Non-sustainable attitude
poor vehicle & equipment maintenance
Obsolete vehicles
& equipments
Obsolete spares
Substandard materials
Poor road network
High population pressure on facilities
Inefficient transport policy & transport mgt. procedures
18
SPDC The Criteria for Assessing Risk
Legal (A) Impact (B)
The nature of the pollution
agent/waste/ natural resource (D)
Quantity of pollution
agent / waste /
natural resource (C)
A x B x C x D = ENVIROMENTAL RISK
19
SPDCThe Criteria for Assessing Risk
LEGAL (A)
1.The impact is not limited/ controlled by legal or other environmental requirements
2.The impact is limited/controlled by mutual parties requirements only
3.The impact is limited/controlled by environmental authorization and/or by environmental legislation
IMPACT (B)
1. The impacts occurs during emergency situation
2. The impact occurs during abnormal functioning only
3. The impact occurs during normal functioning only
20
SPDCThe Criteria for Assessing Risk
Quantity of pollution agent / waste / naturel ressource (C)
1. Concentration of pollution agent generated is below alert level indicated by legislation in use. Monthly waste quantity generated is lower than 1000 kg*. Natural resource consumption is below planned consumption
2. The pollution agent concentration occasionaly equals the alert level. Waste quantity is between 1,000 and 10,000 kg/month*. Natural resource consumption is frequently at the planned level
3. Concentration of pollution agent is between alert and action level or overshoots the action level. The waste quantity is higher than 10,000 kg/month* Natural resource consumption is higher than planned specific consumption
•NB. * Waste quantity is determined in accordance to the level of waste generated.
21
SPDCThe Criteria for Assessing Risk
The nature of the pollution agent/waste/natural resource (D)
1. The major pollution agent is harmless to human beings and to the environment. Waste is recycled waste. Naturel ressource is not regulated
2. The major pollution agent is hazardous (flamable, corrosive, carcinogenic, oxidizing). Waste is assimilated to garbage although it does not belong to this category. The affected natural resource is monitored through oranization’s regulations only
3. The major pollution agent is toxic/banned/global environment impacts generator. The waste is toxic and hazardous. The affected natural resource belongs to the organization’s priorities
22
SPDCEnvironmental Improvement Measures
PRODUCT CHANGE
• Substitution of the product
• Extension of life cycle
• Change of materials
• Change of product design
• Improved recovery possibilities
SUBSTITION OF RAW AUXILIARY MATERIALS
• Substitution of organic solvents
• Substitution of petrochemical (non-renewable) materials by biochemical (renewable) materials
• Use waste as raw material
• Use biodegradable materials
• Reduce number of components
• Use alternative energy sources
23
SPDC
Incineration
Global Warming Ozone layer depletion
GreenhouseGases
NOX
?C02
CFC’s
Acid Rain
CH4, CO2
Landfill
ProductsWastes Land
Contamination
Discharge/Drains Sewers
River / Marine pollution
Energy
Raw Materials Transport
StationsMining etc..
Power
Impact of Development
24
SPDC
Pollution
Cause - Dissolution of SO2 and NOX in moist air- Gases originate from fossil fuel combustion & transport.
Effect - Sterile lakes and rivers, damage to buildings & trees.
Pesticides
Fertilizers Sewage Toxic Substances
Oils
Wastes
25
SPDCDevelopment Poles Approach Towards PPP
The establishment of development centres using settlement profiling evaluation approach can aid optimising scarce resources. Such investment in public goods will transform into promotion of regional development centres which will serve as focal point and incentive for private investors to enter into partnership arrangement for further development. Concentration of facilities will also enhance interdependence such that provision of stable electricity supply can enhance water supply and waste management plants, thereby reducing environmental hazards to ALARP.Technologically, external economies can induce and attract further growth for entrepreneurs.This theory is a sort of 'regional unbalanced growth theory' which uses temporary regional imbalances to initiate desirable development without compromising the ability of future generation to meet their own need. The demerit is that it gives little or no attention to equity; the process which is necessary to ensure a spread or linkage from the centres to the hinterland without which the poles may transform the economy of the region into a dual economy.
26
SPDC
“Meeting the needs of the present without compromising the needs of the future”
Public Private Partnership
BOT, Bonds, Grants, etc,
Budgetary Allocation
Infrastructural Related Taxes and Charges
Utility Bills
Land and Property Processing Charges
Promoter Funds/ Self Raised Funds
Angels Investors
Sources of Fund For
Infrastructural Development
Leveraging PPP for Hazard Management
There are various models available for fund Environmental Hazard Management
27
SPDCImpacts of Industrialization
Emissions into the atmosphere
Odor
HeatRadiation
Solid, liquid,dangerous waste
Soil
water,sewer system
Eco systems
Noise
Dust
• Normal
• Abnormal
• Accidents, emergencies
yesterday today tomorrow
28
SPDC
• Efficient use of input materials and energy (Renewable energy/ Materials)
• Minimization of Environmental impact • (Reduction of emission & Discharge)• Sustainable utilization of Resources (Adopt Recycling & Reuse
Strategy)• Action plan towards Legal Compliance (Compliance
enforcement)• Facilitating the attainment of permits and authorizations • (Stick/Carrot policy)• Increasing liability through prevention of incidents • (and Emergency Preparedness)• New perspective on cost control (Waste Reduction Strategy)• Enhancing image and market share • (Promote Best Practices Through Public Awareness/
Networking)• Maintaining good public / community relations • (Popular Participation/ Communication/ Stakeholder
Consultation)• Reduction of insurance premium (Risk Evaluation & Mitigation Plan)
Green Economy Development Approach Towards PPP
29
SPDCEnvironmental Improvement Measures
PRODUCT CHANGE
• Substitution of the product
• Extension of life cycle
• Change of materials
• Change of product design
• Improved recovery possibilities
SUBSTITION OF RAW AUXILIARY MATERIALS
• Substitution of organic solvents
• Substitution of petrochemical (non-renewable) materials by biochemical (renewable) materials
• Use waste as raw material
• Use biodegradable materials
• Reduce number of components
• Use alternative energy sources
30
SPDC
CassavaRoots
Storage
Dry Cleaning
WetCleaning Peeling Rasping
TuberProcessing
InitialLiquefaction
Final Liquefaction
Distillation Decantation
Storage
Evaporation
Water Water
Dry /LooseSoil & Mud Soil & Mud
Peel with Sandand some Starch ~ 4-5%w/w
Slurry toLiquefaction
Cassava
Saccharification&
Fermentation
Bio Methanation
DWGS
Product Al cohol
Syrup
Slurry Mash CO2
ThinSlops
Example of Green Project/ Processes of Cassava Ethanol
31
SPDC
The high technological and financial requirement needed for the development of
Environmental Management Project makes the role of PPP almost inevitable. For
instance a sugar cane/ cassava-based Ethanol scheme with high level potential
towards reducing the generation and effect of greenhouse gases with the potential of
qualifying the nation for carbon credit is beyond the threshold of the public sector.
Aside from the production of fuel ethanol, biogas -a basic by-products from the
process could be used to generating electricity.
An integrated ethanol plant with a feed stock capacity of 20 metric tones per annum
could generate as much as 2,000 kilowatts/day of electricity, 20,000 metric liquefied
food/ beverage and 30,000 metric tons/year of bio fertilizer. Such integrated scheme
can attract as much as N4 billion Naira as initial capita requirement. A PPP
arrangement can secure the huge fund and provide the high level technology while
helping to reduce poverty via improve crop yield, provision of employment and
reduction of environmental hazards to ALARP.
Conclusion
32
SPDC
THANK YOU