Upload
brendan-alexander
View
213
Download
0
Embed Size (px)
Citation preview
1
SMOV Proposal ProcessInitial Submission through Flight
George Chapman
Merle Reinhart
Tony Roman
February 21, 2001
2
Overview
• Proposal Implementation Team (PIT)
• The PIT Process
• PIT Schedule
• The Proposal – Phase 2 Tips
• Beyond the PIT
3
Proposal Implementation Team (PIT)
• A group of experts that meet to develop and implement proposals fast, safely and efficiently
• Compressed timeline for SMOV benefits from a focused group
• Try to accomplish via one or two meetings per proposal (more if necessary)
4
The PIT Process • Proposal Submission
– best attempt at converting Activity Summary into a proposal
– no later than deadline (earlier is better)
• Proposal Processing
• PIT meeting #1– proposal reviewed in detail– modifications identified – special implementation needs identified
5
The PIT Process (cont’d)
• Modifications & Resubmission– no later than deadline (earlier is better)
• Proposal Processing• PIT meeting #2 (if needed)
– verify expected modifications– final review of proposal and ancillary products– approval to process to flight ready state
• If necessary, PIT meeting #3
6
The PIT Schedule
SubmissionDeadline PIT Meeting #1
ResubmissionDeadline PIT Meeting #2
10+working
days5 Working Days
5 Working Days
7
The Proposal – Phase 2 Tips• Use Web version of proposal for any changes
– http://www.stsci.edu/public/propinfo.html
• Good, Detailed Descriptions• Include Related Activity Summary Ids• Include prerequisite Proposal Ids• Default for SMOV is SCHED 100%• Absolute Time constraints should be used only for
visits with alternate targets• SMOV3B is to be tagged as Cycle 10
8
The Proposal – Phase 2 tips (cont’d)Contingency Planning
• Each Phase 2 should allow for a launch shift of at least plus or minus 1 month
• Use the ON HOLD special requirement on conditional visits
9
The Proposal – Phase 2 Tips (cont’d)Expedited Data Flow
• If data is needed in a timeline fashion for analysis, then this needs to be explicitly mentioned in the visit comments.– Data to the PI within 12 hours of visit completion.
– Data to the PI within 20 hours of visit completion.
– Data to the PI within 32 hours of visit completion.
• These numbers assume ~8 hours of processing after the data is downlinked from the spacecraft until the data is available to the PI.
10
The Expedited DataflowSSR
PACOR-IN
PACOR-OUT
OPUS-OUT
PI
PACOR-OUT
OPUS-OUT OPUS-OUT
STARVIEW
PACOR-OUT
RealTime<<1 hr.
Quicklook<2 hrs.
Production<~4 hrs.
<1 hr. <1 hr. <1 hr.
<~1 hr.
<1 hr.
OPUS-IN OPUS-IN OPUS-IN
DADS-IN
<1 hr. ~1 hr. ~3 hrs.
FTP FTP FTP
Spacecraft
PACOR
OPUS
DADS
PACOR-IN
ScienceRealTime
Science Dump <1hr. to <~12 hrs.
CCS-IN
CCS-OUT
Engineering Dump<1 hr. to <~12 hrs.
~2-4 hrs.
SE
OPUS-IN
24 -48 hrs.
Extraction fromWarehouse
CCS
11
Beyond the PIT
• Process proposal through flight ready • Schedule first 4-weeks of SMOV and provide
products for review before launch– First 4-weeks flight ready by launch minus eight weeks
– Representative calendars are built assuming a nominal launch date and without normal science visits (SMOV only)
– Provides feedback into the overall SMOV Timeline
– Provides necessary input for the LRP
12
Beyond the PIT (cont’d)
• After launch, the SMOV and Operational databases are merged and the LRP rebuilt
• Visits are set flight ready during week T-5
• Appropriate flight calendar requirements are defined during week T-4
• Flight calendar building begins at week T-3
• Execution