Click here to load reader
Upload
jithujohn
View
326
Download
28
Embed Size (px)
DESCRIPTION
HN
Citation preview
2.3Verification, Visual inspection and storage/Preservation of Electrical and instrumentation components
See Remarks
W1H1
Refer to the respective SATIPs for Electrical & Instrumentation (SATIP-P-113-01/02/03 P-116-06 , P-515-01, J-100-01, J-200-01, J-300-01, J-400-01, J-902-03)
SW1
Concrete Foundation Installation See Remarks
Verification of Equipment Support Structure or Foundation (Pre-Installation) SAIC-M-2006 SAIC-M-2006
SAIC-G-2003
3.2
3.4
Refer to SATIP-J-600-01
See SATIP-Q-010-01 or Q-011-01whichever is applicableGrouting of Machinery Support
H1 W1
H1
SAIC-G-2003
Inspection of Auxiliary Piping Installation SAIC-G-2004 SAIC-G-2004
See Remarks
Equipment Handling, Storage and Preservation
See Remarks
Per Schedule Q, attach III, Para.
CNTRCTR
RH1 RH1SAIC-G-2001
SAUDI ARAMCO ID/PID - REV 1 - 05/18/05 (Standards Cutoff - August 2004)DISCIPLINE:
REMARKS
INSPECTION RESPONSIBILITYASSIGNMENTS
DOCUMENT REVIEW
MECHANICAL-Rotating EquipmentPROJECT TITLE:
ITEM NO.
PROJECT PHASE& ACTIVITY CODE TASK / ACTIVITY QUALITY
RECORD
CONTRACTOR/SUBCONTRACTOR
2.0
QUALITY PROCEDURE
1.0
Review of Material & Equipt Storage, Handling and Preservation Procedure-
MATERIAL RECEIVING
1.1
2.1 Equipment Verification and Visual Inspection of Centrifugal Pumps SAIC-G-2002
2.2
HI W1
See SATIP-Q-001-02
25-May-05
W1
SAIC-G-2002
CENTRIFUGAL PUMPSAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No.
SATIP-G-005-01
SAUDI ARAMCO
SAIC-G-2001
APPROVED DATE
3.0 INSTALLATION
3.5
3.3
3.1
Mounting Plate ( Base plate and Soleplate) Installation and Leveling
Relief Valve Installation See Remarks3.6
See Remarks
SAIC-G-2021 SAIC-G-2021SATR-G-2005
See Remarks
See Remarks
Page 1 of 3
CNTRCTR
SAUDI ARAMCO ID/PID - REV 1 - 05/18/05 (Standards Cutoff - August 2004)DISCIPLINE:
REMARKS
INSPECTION RESPONSIBILITYASSIGNMENTS
MECHANICAL-Rotating EquipmentPROJECT TITLE:
ITEM NO.
PROJECT PHASE& ACTIVITY CODE TASK / ACTIVITY QUALITY
RECORD
CONTRACTOR/SUBCONTRACTOR
QUALITY PROCEDURE
25-May-05CENTRIFUGAL PUMPSAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No.
SATIP-G-005-01
SAUDI ARAMCO
APPROVED DATE
Form SA-6133 H1
SAIC-L-2014
Skid Mounted Aux. Electrical System installation See Remarks
SAIC-G-2005
See Remarks
W1
Skid Mounted Aux. Instrumentation Systems installation See Remarks
H1
Refer to SATIP-J-902-03
See Note 3 of the General Notes for S.Aramco's Responsibility and minimum of 10% thereafter.
Refer to SATIP-P-515-01
W2
Refer to the applicable SATIP: SATIP-P-113-06, P-113-01, P-113-02, P-113-03, P-116-06
S
3.12
3.11
3.9
H1Pump Suction and Discharge Piping Connection
Welding
4
5
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
Refer to the respective SATIPs for Electrical & Instrumentation noted above.
Final Inspection for mechanical completion acceptance
H1
See Remarks
SAIC-L-2014SATR-L-2001
See Remarks
SAIC-G-2005
4.2
4.0 PRE-COMMISSIONING
Final Pump/Driver Alignment W1
3
SAIC-G-2007 SAIC-G-2007SATR-A-2011
SAIC-G-2022 SAIC-G-2022SATR-G-2004
Instrumentation and Electrical Pre- Commissioning prior MCC
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.
See Remarks
H14.3
4.3
GENERAL NOTES
4.1
Final Inspection/walkthrough (by Contractor)
See Remarks
See Remarks
If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
See SATIP-W-011-01
1
2
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
3.7
3.10
3.8
Electric Motor (Driver) Installation
Flange Joint, gasket verification and bolt tightening
See RemarksSee Remarks
Page 2 of 3
CNTRCTR
SAUDI ARAMCO ID/PID - REV 1 - 05/18/05 (Standards Cutoff - August 2004)DISCIPLINE:
REMARKS
INSPECTION RESPONSIBILITYASSIGNMENTS
MECHANICAL-Rotating EquipmentPROJECT TITLE:
ITEM NO.
PROJECT PHASE& ACTIVITY CODE TASK / ACTIVITY QUALITY
RECORD
CONTRACTOR/SUBCONTRACTOR
QUALITY PROCEDURE
25-May-05CENTRIFUGAL PUMPSAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No.
SATIP-G-005-01
SAUDI ARAMCO
APPROVED DATE
W1
LEGEND
SurveillanceW2
RH2RH1
100% Review and Approval of DocumentsSample Review and Approval of Documents
H1
100% Witness Inspection/TestSample Witness Inspection/Test100% Hold Point for QC Inspection or Test sample Review of Documents S
H2
R2
Sample Hold Point for QC Inspection or Test100% Review of DocumentsR1
Page 3 of 3