1-s2.0-S096014811200081X-main

Embed Size (px)

Citation preview

  • 8/10/2019 1-s2.0-S096014811200081X-main

    1/5

    Photovoltaic-grid connection in the UAE: Technical perspective

    Ammar M. Al-Sabounchi*, Esmaeel Al-Hammadi, Saeed Yalyali, Hamda A. Al-Thani

    National Energy and Water Research Center, Abu Dhabi Water & Electricity Authority, Abu Dhabi, United Arab Emirates

    a r t i c l e i n f o

    Article history:

    Available online 10 February 2012

    Keywords:

    Utility-interactive PV System

    Distributed generation

    Distribution feeder

    Dust deposition

    a b s t r a c t

    Connection of utility-interactive PV generators at the distribution level, namely PV distributed generation

    (PVDG), could bring many benets to the distribution network. However, deployment of PVDG systems,

    in any country, requires actual data on the performance of these systems under actual weather condi-tions. Additionally, it needs compliance with the electrical structure and regulations of the power

    distribution network in that country. Hence, applying PVDG technology in the UAE brings forth many

    considerations and this work aims at tackling potential technical ones. Among these is the role of daily

    load curve and PV production curve in determining feasible locations and capacities of PVDG systems.

    The analyses are based on existing case study feeders at the 11 kV level of Abu Dhabi distribution

    network. Accordingly, the work results in suitable recommendations on feasible locations of PVDG

    systems. Also it denes rational objectives and constraints for optimal sizing and location of such

    systems.

    The other consideration tackled in this work is the performance of PVDG systems in actual UAE

    weather conditions. Actual data from two pilot PVDG systems installed in Abu Dhabi are collected and

    analyzed. The production of PV array, consistency of voltage and frequency and the conversion efciency

    of PV modules and inverters along with the impact of ambient temperature are considered. In the same

    connection, the inuence of accumulated dust deposition on the production of PV array in UAE is also

    taken over in this work.

    2012 Elsevier Ltd. All rights reserved.

    1. Introduction

    Knowing that the daily average solar insolation in the UAE is

    topped to around 6 kWh/m2 makes the sense for the country to go

    for solar energy systems over other renewables. Regarding solar

    energy systems, interfacing of photovoltaic (PV) systems with the

    utility grid at the distribution level, so called PV distribution

    generation (PVDG), has been drawing considerable attention in the

    UAE. As in other distribution generation (DG) systems, the PVDG

    can bring many benets to the network. These may include

    reduction of line losses, improvementof voltage prole, postponing

    network upgrade, improvement of system reliability, and reductionof global warming concerns[1].

    However, connection of PVDG systems (and any other DG) may

    bring some concerns to power distribution companies. One of the

    main concerns is that the PVDG systems deviate from the tradi-

    tional concept of hierarchical power ow from the substation to

    consumers. This mayresult in power ow in the upstream direction

    that may disturb the automatic voltage regulators[2]. As for power

    quality concern, the PVDG system shall inject reliable electricity of

    voltage and frequency within the acceptable limits [3].

    This work aims at brieng potential outcomes of research

    activities conducted, by the National Energy and Water Research

    Center (NEWRC), to investigate the performance of PVDG systems

    in the UAE. It is worth mentioning that the UAE power grid is

    mainly supplied by thermal/gas power plants generating three

    phase electricity at 50 Hz frequency. The generated electricity is

    connected to the transmission lines at 132 kV, 220 kV and 400 kV

    voltage levels via step up transformers. The transmission lines, in

    turn, provide the distribution network at 33 kV and 11 kV voltage

    levels via step down transformers. At this stage, the electricity isdistributed through 11 kV underground and overhead feeders

    supplying three phase 11/0.4 kV distribution transformers.

    Based on above, the conguration of distribution feeders along

    with the trends of load and solar irradiance curves are investi-

    gated fundamentally in this work. The performance of PVDG

    systems under actual UAE weather conditions is also tackled. Two

    pilot systems, implemented by NEWRC in Abu Dhabi at the 0.4 kV

    level, are monitored and evaluated for this purpose. The outcomes

    of these systems are believed valuable in generating solid

    recommendations for feasible installation of PVDG systems in

    the UAE.* Corresponding author.

    E-mail address: [email protected](A.M. Al-Sabounchi).

    Contents lists available atSciVerse ScienceDirect

    Renewable Energy

    j o u r n a l h o m e p a g e : w w w . e l s e v i e r . c o m/ l o c a t e / r e n e n e

    0960-1481/$ e see front matter 2012 Elsevier Ltd. All rights reserved.

    doi:10.1016/j.renene.2012.01.070

    Renewable Energy 49 (2013) 39e43

    mailto:[email protected]://www.sciencedirect.com/science/journal/09601481http://www.elsevier.com/locate/renenehttp://dx.doi.org/10.1016/j.renene.2012.01.070http://dx.doi.org/10.1016/j.renene.2012.01.070http://dx.doi.org/10.1016/j.renene.2012.01.070http://dx.doi.org/10.1016/j.renene.2012.01.070http://dx.doi.org/10.1016/j.renene.2012.01.070http://dx.doi.org/10.1016/j.renene.2012.01.070http://www.elsevier.com/locate/renenehttp://www.sciencedirect.com/science/journal/09601481mailto:[email protected]
  • 8/10/2019 1-s2.0-S096014811200081X-main

    2/5

    2. Methodology

    Six 11 kV distribution feeders supplying residential, industrial

    and commercial load demands in Abu Dhabi are taken as casestudies. Those consist ofve underground (UG) and one overhead

    (OH) feeders, inside the city and at suburbs, representing the

    prevalent types of 11 kVfeeders in Abu Dhabi. The data of feederare

    collected and analyzed in terms of physical structure and load

    demand. Additionally, the daily average rates of solar irradiance in

    Abu Dhabi are provided. On performance evaluation aspect, the

    two pilot PVDG systems mentioned above are installed in Abu

    Dhabi at ground and rooftop levels.

    2.1. Physical structure

    The 11 kV feeders and laterals branching from them in Abu

    Dhabi are extended in three phases. They are considered in

    balanced mode operation by the distribution company. Conse-quently, the feeders are usually extended in three wires (Y or D)

    with no return bath for the neutral. Based on the six case studies,

    the capacity of the 11/0.4 kV distribution transformers along 11 kV

    feeders is in the range of 0.2e1.5 MVA. At the same time the

    installed capacity of the feeders is in the range of 10e20 MVA. The

    11 kV feeders are usually extended in XLPE underground cables of

    wire sizes in the range of 185e300 mm2. The available overhead

    feeders are usually found in the suburbs with wire size around

    95 mm2 carried on crossarm poles.

    2.2. Load demand

    The daily demand proles at the input of the feeders were

    collected from the power distribution company for four seasonal

    days reecting the power consumption trends of the four seasons.For each feeder the active power demand (MW) at each time

    interval is represented in per unit of feeder installed capacity

    (MVA). The process is repeated for the four seasonal days with the

    results are depicted inFigs. 1e3.

    The load curves ofFig. 1shows that the highest load demand in

    Abu Dhabi is in summer, which is very normal due to the high

    cooling load. At the same time, the difference between summerand

    winter demands is considerably high. This is due to the absence of

    cooling load in winter, also the moderate ambient temperature in

    winter drops the need for real heating load.

    As for peak load demand (PLD) and peak load time (PLT), Fig. 4

    summarizes the results of the feeders over usual summer day.

    According to thegure the average of the highest PLD -in summer-

    is around25% of feeder installed capacity. This could be an indicatorfordistribution load relief in Abu Dhabi and consequently long time

    before network upgrade is needed.

    Additionally, Fig. 4 shows that PLT most likely occur at late

    daylight hours in Abu Dhabi, or even after nightfall like in feeders

    4-UG & 5-UG. Not to mention that the average PLT of the six feeders

    is found to be at 5:30pm.

    2.3. Solar irradiance

    The daily solar irradiance curves, in per unit of 1000 W/m 2, are

    illustrated in Fig. 5 over four usual seasonal days. The gure is

    plotted based on actual measurements collected from the two pilot

    PVDG systems. Since the PV power production is directly

    Fig. 1. Per-unit daily summer load curves.

    Fig. 2. Per-unit daily winter load curves.

    Fig. 3. Per-unit daily spring & fall load curves.

    Fig. 4. PLD and PLT of feeders in summer day.

    A.M. Al-Sabounchi et al. / Renewable Energy 49 (2013) 39e4340

  • 8/10/2019 1-s2.0-S096014811200081X-main

    3/5

  • 8/10/2019 1-s2.0-S096014811200081X-main

    4/5

    of PV surplus power will be produced in winter resulting in

    unpreferably powerow in the upstream direction. In this course,

    Table 1yields that the average PLD of feeders in winter is around

    47% of that in summer.

    To have an idea about the space area corresponding to PVDG

    system sizing, the multi-crystalline silicon PV modules are taken asexample. According to datasheets, the approximate area required to

    produce 1 kWp at standard conditions is around 7.5e8.0 m2. Asthis

    area is not small, it is deemed rational that prospective PVDG

    systems in Abu Dhabi are most likely t at no higher than the 11 kV

    level.

    3.1.3. Voltage constraint/benet

    Connection of PVDG system on distribution feeder reduces the

    current ow from the substation up to the point of common

    coupling (PCC) resulting in improvement of voltage prole. This

    benet is secured as long as the PVDG system capacity is sized in

    compliance with the sizing constraint avoiding any surplus PVDG

    power generation. Otherwise, the surplus power in the upstream

    direction could be high enough that raises the voltage at some

    downstream nodes to unacceptable values. This may affect the

    performance of automatic voltage regulators that rely on the trend

    of decreasing voltage prole along the feeder[2].

    3.2. Performance evaluation

    For credible performance evaluation of PVDG systems in the

    UAE, two pilot systems rated at 36 kW and 9 kW were installed in

    Abu Dhabi at the 0.4 kV level. Many parameters are being evaluated

    through these systems including production of power, consistency

    of voltage & frequency, efciency of system components, reduction

    of CO2emission, impact of dust deposition, and others. This section

    represents selective synthesized data, taken from the 36 kW

    system, on some potential performance parameters. Out of the 13

    multiple inverters of the system, inverter 9 and the PV strings

    supplying it are taken as example.

    Fig. 6depicts the dc power production and efciency of the PVstrings at different irradiances. Also Fig. 7 shows the impact of

    ambient temperature on PV modules efciency. Mind that the

    measurements were taken in June 6th, 2009 to show the worst

    possible status in summer. Thegure manifests the inverse relation

    between ambient temperature and efciency that raises the

    maximum efciency to around 13% at 7am. Based on the

    same gure, the daily average efciency during daytime hours is

    around 11%.

    Similar evaluation is conducted to inverter 9 at the same day,

    with the results shown in Fig. 8. The gure shows that the daily

    average operation efciency of the inverter is topped to 93%. Also it

    manifests a sort of consistent efciency, even with the variations of

    dc input power.

    As for power quality items, Fig. 9 shows high consistency involtage and frequency of the ac power delivered by inverter 9.

    According to the gure, the average operating voltage and

    frequency are 237.19 V and 49.97 Hz. This means only 1.17% and

    0.04%, respectively, below standard nominal values.

    Respecting daily operating time of the inverters, Fig.10 indicates

    the daily monthly average hours of inverter 9 measured over the

    year of 2009. It shows relatively long operating time extend to 13 h

    daily in June but drop to around 8.5 h in December; means 10.75 h

    daily annual average of around.

    Coming to the inuence of accumulated dust deposition on the

    performance PV modules, Fig. 11 shows serious inuence on the

    production of the PV system. The gure shows the drop in power

    production of PV modules after they had been left without cleaning

    Fig. 8. Conversion efciency of inverter.

    Fig. 9. Operating ac voltage & frequency of inverter.

    Fig. 10. Daily monthly average of invertersoperating hours.

    A.M. Al-Sabounchi et al. / Renewable Energy 49 (2013) 39e4342

  • 8/10/2019 1-s2.0-S096014811200081X-main

    5/5

    for six consecutive months. To be more specic, the powerproduction of inverter 9 was measured on daily basis at irradiance

    800 W/m2 with the PV modules been cleaned once at the beginning

    of the month. The procedure was repeated for three months with

    the results illustrated inFig.12. According to the gure, the average

    monthly drop in PV power production, due to accumulated dust

    deposition, is around 27%. This can provide suitable guidance

    compromising between imposed cleaning frequency, on one side,

    and the extra PV modules to compensate the impact of dust

    deposition, on the other side.

    4. Conclusions

    The PV utility-interactive, especially PVDG systems, is promising

    and highly recommended technology in UAE. In this course, it is

    recommended that prospective PVDG systems are installed at no

    higher than the 11 kV level. This is according to the sizing and

    spacing constraints of PV arrays along with the load demand trends

    of six case study feeders representing the most likely 11 kV feeders

    in Abu Dhabi.

    In the same connection, if the size of the PVDG system is less

    than the PLD delivered by the 11/0.4 kV transformer at the PCC,

    then it is recommended to connect it at the low tension side of

    0.4 kV. Additional loss saving will be gained this way across the

    windings of the transformer. The PVDG system could be even

    connected after the circuit breakers of the low tension side if its size

    is within the ampacity of those breakers. On the contrary, if the

    capacity is higher than the average maximum limit recommended

    in Table 1, then it is suitable to distribute it in separate PVDG

    systems at different 11 kV feeders. Alternatively, it is recommended

    to be installed on next higher voltage level of the grid, considering

    availability of space area.

    In the same connection, it seems rational to rate the size of

    PVDG systems based on winter load demand. This practice is

    deemed suitable for hot summer regions like in UAE and the GCC

    countries. As a matter of fact it may avoid, to great extent, the

    possibility of surplus PV power production and consequent reverse

    power ow during the whole year. To this end, it is recommended

    to rate the PVDG system capacity based on the average maximum

    limit of winter inTable 1.

    As for space area, it seems suitable interfacing the PVDG systems

    with feeders at the suburbs where the space concern is less than

    inside the city. Also suburb feeders are usually extended over

    longer distances facing more voltage drop problems. Connection of

    DG systems, including PVDG, at feasible sizing and location is ideal

    solution for improving the voltage prole of such feeders.

    On different note, the accumulated dust deposition seems to be

    serious concern affecting the production of PVDG systems. The

    impact of dust deposition on the power production of PV moduleswas illustrated inFigs. 11 and 12. This may provide suitable guid-

    ance for PV designers in dealing with the matter. This may impose

    suitable cleaning frequency of PV modules and adding extra

    modules to compensate the reduction in PV production between

    cleaning times.

    Last but not least, the PVDG systems are expected to show good

    performance in terms of operating voltage and frequency along

    with conversion efciency of inverters. Additionally, the high

    ambient temperature in Abu Dhabi seems to be of moderate effect

    on the efciency of PV modules.

    References

    [1] AlHajri M, AlRashidi M, El-Hawary M. Hybrid particle swarm optimizationapproach for optimal distribution generation sizing and allocation in distri-bution systems. Proceedings IEEE Electrical and Computer EngineeringCanadian Conference; 2007:1290e3. April 2007.

    [2] Conti S, Greco A, Messina N, Raiti S. 2006. Local voltage regulation in LVdistribution networks with PV distributed generation, Proceedings IEEESymposium on Power Electronics, Electrical Drives, Automation and Motion,May 2006, pp. 519e524.

    [3] Hacker R, Thornycroft J, Munro D, Rudkin E. 1999. Coordinated experimentalresearch into PV power interaction with the supply network-phase I, reportprepared by Halcrow Gilbert Associates presented in the UK.

    [4] Borges LT, Falcao M. Optimal distributed generation allocation for reliability,losses, and voltage improvement. Electrical Power and Energy Systems Jour-nal 2006;28:413e20.

    [5] Singh R, Goswami S. Optimum sitting and sizing of distributed generations inradial and networked systems. Electric Power Components & Systems Journal2009;37:127e45.

    [6] Prommee W, Ongsakul W. Optimal multi-distributed generation placement byadaptive weight particle swarm optimization. Proceedings IEEE Control,Automation & Systems Conference; 2008:1663e8. Oct. 2008.

    [7] AlHajri M, El-Hawary M. Improving the voltage proles of distributionnetworks using multiple distribution generation sources. Proceedings IEEEPower Engineering Conference; 2007:295e9. Oct. 2007.

    [8] AlHajri M, El-Hawary M. Optimal distribution generation sizing via fastsequential quadratic programming. Proceedings IEEE Power EngineeringConference; 2007:63e6. Oct. 2007.

    [9] Al-Sabounchi A, Gow J, Al-Akaidi M, Al-Thani H. 2010. Optimal sizing andlocation of PVDG units on radial distribution feeders allowing no reversecurrentow, Submitted to IET Electric Power Applications Journal.

    [10] Silva N, Strbac G. Optimal design policy and strategic investment in distri-bution networks with distributed generation. Proceedings CIRED Seminar onSmart-Grids for Distribution; 2008:1e4. June 2008.

    Fig. 12. Monthly power prole with dust deposition.

    Fig. 11. Impact of six months dust deposition.

    A.M. Al-Sabounchi et al. / Renewable Energy 49 (2013) 39e43 43