1 | P a g e
2 | P a g e
MAINTENANCE EXPERIENCE
LOCO TYPE YEAR OF HOLDING
FROM TO
WAM-1 1994 1998
WAM-2 1994 2000
WAM-3 1994 2000
WAG-3 1994 1997 WAG-4 1994 2001
WAP-6 1998 2007
WAG-5 1998 2020
WAG-7 2000 2020
WAM-4 2005 2020
WAP-4 2019 2020
3 | P a g e
Brief History of Electric Loco Shed;
Asansol
Dt. of Commencement – May – 1969
Established in May-1959 and it is the first AC Loco Shed in
Indian Railways. The shed was originally created for
homing 80 Locomotives; subsequently some infrastructural
facilities have been added to increase 100 Locomotives.
This Shed has got the rich experience of maintaining
various types of Locomotives since its inception, ranging
from WAM-1, WAM-2, WAM-3, WAM-4, WAG-3, WAG-4,
WAP-6 to WAG-5, WAG-7 & WAM-4 Locomotives. In the
financial year 2019-20, 18 nos. WAP-4 Locomotives have
been commissioned on transfer from HWH and very soon
WAG-9 (3 Ø) Locomotives will be in holding. These
Locomotives are dedicated to freight traffic except 18 nos.
WAP-4 Locos which are for coaching services. These
Locomotives are equipped with modern devices as a result
of technological advancement like Static Inverter Unit
(SIV), Microprocessor based fault diagnostic & control
system (MPFDCS), Vigilance Control Device (VCD),
Microprocessor based Energy cum speed monitoring
system (ESMON), aerodynamic Crew Friendly Cab and
Real Time Information System (RTIS) etc.
4 | P a g e
Inception of Electric Loco Shed;
Asansol
Electric loco Shed; Asansol is the first A.C.Electric Loco
Shed over Indian Railways. Electric Loco Shed; Asansol
was started in May – 1959 by converting a small portion of
Steam Loco Shed with a holding of 45 Locos. Initially
WAM-1 Locos imported from Japan were based in this
shed. Subsequently the holding of the shed was
increased, as a few more imported Locos like WAG-2,
WAG-3 and WAM-2 were based in this shed. With the
addition of locos imported from Japan, the need for the
expansion of this shed was felt and it was expanded to
home 80 Locos in the year 1969 by taking a few more
portion of Steam Shed. By the end of 1969 the shed was
holding imported locos from continent i.e. (WAM-1 – 45 &
WAG-3 – 10), 12 imported mixed Locos from Japan
(WAM-2 – 10 & WAM-3 – 02) and 45 WAG-2 Locos which
were also imported from Japan.
During 1970 CLW manufactured WAG-4 Locos were also
homed at the shed. With the introduction of EMU rakes
from BHEL & ICF, in Calcutta suburbarn section 25 WAM-
2 Locos which were working in push-pull operation were
converted to main line operation. These Locos were also
transferred & homed at the shed. CLW started production
5 | P a g e
and the first batch of 10 WAG-4 IR5 series Locos were
commissioned and based at this shed in 1970. Gradually
the holding of WAG-4 Locos have gone up to 45.
As the holding was increasing further, the shed was further
expanded to home 110 Locos in the Year 1974 by taking
some more portion of Steam shed. More & more locos
have been added & finally shed was expanded to home
115 Locos in the year 1980. With the introduction of Air
Brake Stock, a few WAG-4 Locos were converted for dual
brake operation. Further facilities were created for
maintaining 20 dual brake locos by taking some portion of
Steam Shed. Initially 15 nos. WAP-6 Locos were based at
Baroda Loco Shed & MGS Loco shed. These Locos had a
number of maintenance problems due to defect in
mechanical & pneumatic side. After about one year of
unsuccessful trial these 15 Locos were transferred to this
shed within May’98 to Sep’98 and after a service of 09
years maintained by ELS/ASN these locos have been
transferred to ELS/HWH for conversion to WAP-4 as per
the competent authority.
6 | P a g e
PRESENT LOCO HOLDING
166 LOCOS
LOCO TYPE WISE BREAK UP
Type WAG-5
(HITACHI) WAG-5
(TAOCHI) WAG-7
WAM-4 (TAOCHI)
WAP-4 TOTAL
Population 65 45 35 03 18 166
Maximum Speed
80 KMPH
105 KMPH
100 KMPH
110 KMPH
140 KMPH
-
MULTI 22 +
05(Consist) 18 Nil
Nil
Nil 45
INCREASE OF LOCO HOLDING
132.00
166.00
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
160.00
180.00
2018-19 2019-20
HOLDING
HOLDING
7 | P a g e
SERVICE WISE CLASSIFICATION OF
LOCOMOTIVES
Type of Loco Holding Codal Life
Over-aged
Utilisation
WAG-5/HITACHI
65 35 NIL. FREIGHT
WAG-5/TAOCHI
45 35 NIL. FREIGHT
WAG-7 35 35 NIL. FREIGHT
WAP-4 18 35 NIL. COACHING
WAM-4 03 35 03 INFERIOUR SERVICE
Total 166 35 03 -
Goods Service – 145 Locos
WAG-5/T - 45, WAG-5/H – 65
& WAG-7 - 35
Passenger Service – 18
Locos WAP-4 – 18
Inferiour Service – 03
Locos. WAM-4 - 03
Link Requirement – 16 (WAP-4)
8 | P a g e
LOCO AGE PROFILE
Type of Loco
Holding
Age Profile
Up to 10 Yrs
11 – 15 Yrs
16 – 20
Yrs.
21 – 25
Yrs.
26 – 30
Yrs.
31 – 35
Yrs.
Above 35 Yrs.
WAG-5/HITACHI
65 0 0 0 03 41 21 0
WAG-5/TAOCHI
45 0 0 0 05 21 19 0
WAG-7 35 17 15 0 03 0 0 0
WAP-4 18 07 02 05 04 0 0 0
WAM-4 03 0 0 0 0 0 0 03 Total 166 24 17 05 15 62 40 03
9 | P a g e
MINOR & MAJOR SCHEDULES
PRESENTLY BEING CARRIED OUT AT
ELS/ASN
Minor Inspection Major Inspection
IA Insp.
IB Insp. IC /IC0Insp.
TOH AOH IOH
All locos.
All locos except WAP-4.
All Locos.
WAG-5/Hitachi,
WAG-5/Taochi
being used in Goods
service & WAG-7.
WAP-4. All
Locos.
10 | P a g e
PERIODICITY OF & MINOR & MAJOR SCHEDULE
Loco Type IA IB IC AOH TOH IOH Trip Insp.
WAM-4
40
DAYS
+ 03
DAYS
80
DAYS
+ 03
DAYS
120
DAYS
+ 03
DAYS
12MONTHS
+ 15 DAYS
-
36MONTHS
+ 01
MONTH
After 3000KMS or One Trip
whichever is later.
WAG-
5/TAOCHI
(PASSANGER)
&
WAP-4
60
DAYS
-
120
DAYS
18MONTHS
+ 15 DAYS
-
36MONTHS
+ 01
MONTH
After 3000KMS or One Trip
whichever is later.
WAG-
5/HITACHI
60
DAYS
120
DAYS
180
DAYS
-
24
MONTHS
72 MONTHS
+ 01
20 DAYS
11 | P a g e
&
WAG-
5/TAOCHI
(GOODS)
+ 03
DAYS
+ 03
DAYS
+ 03
DAYS
+ 15 DAYS
MONTH
WAG-
7/HITACHI
60
DAYS
+ 03
DAYS
120
DAYS
+ 03
DAYS
180
DAYS
+ 03
DAYS
-
24
MONTHS
+ 15 DAY
72 MONTHS
+ 01
MONTH
20 DAYS
12 | P a g e
AREA OF ELECTRIC LOCO SHED;
ASANSOL :
The present area of this shed is 13375 mt sq. which
includes pit area of 837 sq. mt. of total 09 nos. pits.
However after augmentation work, the shed will become
13953 mt sq as total proposed area under shed extension
work was 1958 sq. mt.
INFRASTRUCTURE :
At present ELS/ASN is holding 166 nos. of Locomotives against the existing capacity of 100 Locos. However current augmentation work is in progress for homing up to 120 Locos. 1st phase work under augmentation program has been completed 100% i.e. construction of Capital Store Building & Trip shed along with building has been completed.
13 | P a g e
Extension of Electric Loco Shed under 2nd phase of augmentation work is under progress. The overall physical progress of the shed augmentation work is 66%.
At present ELS/ASN is facing infrastructural
constraint towards discharging the responsibilities of
smooth preventive maintenance of locomotives due to
increased holding, moreover in the present scenario it
is expected that more locomotives including 3-phase
locomotives will be homed at this shed in near future
as 34 Locomotives have already been homed at
ELS/ASN within last 18 months resulting in increase
of holding from 132 to 166 Locos,
However a work of Rs.2.92 crore for further up
gradation of Electric Loco Shed, Asansol has already
been sanctioned under umbrella work to overcome
the aforesaid day to day difficulties being faced at this
end towards maintenance activities. The detailed
estimate has already been sanctioned & Tender has
been called by Civl. Engg Department.
Another works of Rs. 119998th has been proposed
through IRMPSM which has been sent to HQ after
short listing from division.
14 | P a g e
DETAILS OF PITS / BAYS
Item Inspection
Bay Light lifting Bay
Medium
lifting bay Heavy lifting bay
No. of Lines 06 4 0 3
Area (in Sq. Mtrs.)
1960.56 (147.3x13.31)
1863.4 (140X13.31)
1029.6 (52X19.8)
3381 (161X21)
No. of Pits per line
2 pits/line -04nos.
1 pit/line- 02 nos.
1 pit/line-02 nos.
0 1 pit/line-01 no 2 pit/line-01 no 3 pit/line-01 no
No. of Pits 10 nos. 2 0 6
No. of locos berthing capacity
10 Locos 02 Locos 0 03 Locos.
Under construction
in augmentation works- Area
&
-
870.4 (65.395X13.31) Extension of 5 ton crane bay
-
997.5 (47.5X21)
Extension of heavy lifting bay.
15 | P a g e
COMPARATIVE FIGURES OF LOP
(LAST 04 YEARS)
2016-17 2017-18 2018-19 2019-20
26 17 27 14
26.00
17.00
27.00
14.00
0.00
5.00
10.00
15.00
20.00
25.00
30.00
16-17 17-18 18-19 19-20
LOP
LOP
16 | P a g e
COMPARATIVE FIGURES OF TOTAL LOCO AVAILABILITY (In %)
(LAST 04 YEARS)
2016-17 2017-18 2018-19 2019-20
90.18% 89.76% 90.65% 92.27%
88.50
89.00
89.50
90.00
90.50
91.00
91.50
92.00
92.50
16-17 17-18 18-19 19-20
90.18
89.76
90.65
92.27
Loco Avl.%
Loco Avl.%
17 | P a g e
COMPARATIVE FIGURES OF
UNSCHEDULED VISIT /100 LOCOS / MONTH
(LAST 04 YEARS)
2016-17 2017-18 2018-19 2019-20
13.96 11.27 9.20 6.31
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16-17 17-18 18-19 19-20
13.96
11.27
9.20
6.31
Unsc.Visit/100 Locos/Month
Unsc.Visit/100 Locos/Month
18 | P a g e
COMPARATIVE FIGURES OF
UNSCHEDULED LIFTING /100 LOCOS / MONTH
(LAST 04 YEARS)
2016-17 2017-18 2018-19 2019-20
6.54 5.27 7.05 3.54
6.54
5.27
7.05
3.54
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
16-17 17-18 18-19 19-20
Unsc.Lifting/100 Locos/Month
Unsc.Lifting/100 Locos/Month
19 | P a g e
SALIENT FEATURES OF
ELECTRIC LOCO SHED; ASANSOL
QUALITY CERTIFICATION IMS certification
o ELS/ASN is certified with Integrated Management
System (IMS) which includes ( ISO 9001-2015 – Quality
Management System, ISO 14001:2015 – Environment
management system & ISO 45001:2018 – Occupational
Health & Safety management system).
IMS certification of ELS/ASN
20 | P a g e
Six-Sigma Certification o Certified with Lean & Six Sigma implementation by M/s.
Anexas, Europe, certifying body.
Presentation of Six Sigma certification in presence of respected General
5-S Certification o As a part of workplace Management process / quality
certification process, ELS/ASN is certified with the
prestigious 5S Certificate. ELS/ASN has successfully
achieved and implemented the standard of 5S in its
workplace.
Presentation of 5S certificate
21 | P a g e
MAJOR PROJECT
Day Light Harvesting Project:
o Commissioned solar pipe lights as a part of day light
harvesting. This is the 1st time in Eastern Railway that
day light harvesting has been started. Huge
improvement in illumination level during day time has
been observed in the areas where the said light has
been commissioned. The same has not only increased
illumination level in working place but also reduced
energy consumption.
Solar Pipe Light installation on the roof of ELS/ASN
22 | P a g e
INNOVATION
Scrap To Art : ELS/ASN has fabricated a few models from scrap as a part
of “Scrap to Art”. An Art gallery has been formed at ASN
Rly. Station with the said models.
Sofa from scrap drum
23 | P a g e
Fighter Plane Mother with child
Robot from pipes, springs & nut bolts. Table from Sky-light glass
Peacock Lion
24 | P a g e
Prithvi Make in India emblem.
Respected PCEE/ER, DRM/ASN & CEE/OP/ER are seeing scrap to art models /
sitting on sopha made from scrap.
25 | P a g e
Automated Sand dryer & sand filling machine. :
A sand dryer along with the facility of automated sand filling
machine has been fabricated at ELS/ASN with internal
resources (mostly of scrap material).
Automated sand drying & filling machine.
26 | P a g e
Inauguration of Automated sand filling machine by PCEE/ER & DRM/ASN on 06.09.19.
Consist Formation 1st time in Eastern Railway at ELS/ASN : o 05 nos. of WAG-5 consist of 03 locos each formed at
ELS/ASN which is 1st time in Eastern Railway.
Consist formation by ELS/ASN.
27 | P a g e
Timer Test Bench : A highly sensitive timer test bench with micro-second accuracy for monitoring the simultaneous operation of three phase contacts of EMC fabricated internally at ELS/ASN. This has saved more than 03 lakh rupees.
Ideal Conditioon Testing Condition.
Test Bench of EMC with micro sec. accuracy.
PCEE/ER inaugurating Timer Test Bench of EMC
28 | P a g e
Tri Plate Test Bench:
A Tri-plate test bench fabricated at ELS/ASN with internal resources for testing of valves provided in Tri-plate panel before fitment in Locomotive to reduce down time & also improve reliability has been inaugurated by respected General Manager / ER.
Inauguration of Tri-plate test bench by respected GM/ER.
29 | P a g e
HOM TEST BENCH :
HOM test bench has been fabricated in-house for leakage testing of HOM valve during major schedule / unscheduled changing before fitment in Loco to reduce down time & also improve reliability as previously the valve was being tested only after fitment in Loco & if there would be any problem the same would be rectified, this lead to unnecessary wastage of valuable man hour.
In-house fabricated HOM Leakage Test Bench
30 | P a g e
DC-DC CONVERTER TEST BENCH :
Fabrication of DC-DC converter test bench has been done with internal resources at shed level.
DC-DC Converter test bench.
31 | P a g e
Auxiliary Park:
o A rack for storing of Auxiliary motors named as
“Auxiliary Park” has been fabricated at ELS/ASN for
systematic storing of auxiliary machines.
Newly fabricated Auxiliary Park
Racks for systematic storing of Helical Springs :
o 02 nos. racks have been fabricated at heavy lifting bay
with internal resources for stacking of inner & outer
helical springs in a systematic manner.
Stacking of Helical springs after commissioning of rack
32 | P a g e
Fabrication of Wheel Park : o A wheel rack named as “Wheel Park” has been
fabricated for proper stacking of wheels to save valuable
working space as well as to fetch aesthetic look.
Wheel Rack.
33 | P a g e
STAFF WELFARE ACTIVITIES
COVID-19 :
o This shed has prepared sanitizer at its lab as per
WHO's recommendation indigenously. The shed
manufactured sanitizers along masks are being
distributed not only to all the personnel (approximately
805 nos. of the shed staff) but also distributed to
approximately 2000 Rly. Quarters of ASN which
includes Durand Loco Colony, Domhani, Chelidanga,
Traffic Colony to fight with the present grave situation.
o The shed has taken care the demand of sanitizers of
other divisional personnel also. Procurement of 8000
nos. of 3-layer masks has been done and the same
have been distributed among shed personnel and
different railway colonies.
Stacking of Helical springs after commissioning of rack
34 | P a g e
o Non-stock procurement of raw material for in-house
preparation of hand sanitizer has been done as per
WHO’s reccomendation.
In-house preparation of sanitizer at Lab.
o 750 ml pouched Dettol liquid soap and 125 gm soap
bars have been procured and are being distributed
among the shed personnel.
Distribution of Liquid soap to shed personnel.
o As a preventive measure, thermal screening of the
personnel at shed has been undergoing on daily basis
through thermal temperature Gun.
35 | P a g e
Thermal screening.
o Foot operated water tap along with soap dispenser has
been manufactured through In house effort for the use
of shed personnel to avoid infection.
Foot operated water tap.
o Social distancing norms are being maintained strictly at
work premises of ELS/ASN.
36 | P a g e
Social Distancing.
o Complete Electric Loco Shed including all sections is
being disinfected twice on daily basis.
Sanitization of shed.
o Sanitization of Loco cab is being done on regular basis.
Sanitization of Loco Cab.
o Coloured posters containing Do’s / Don’ts have been
pasted all over the shed for creating awareness.
37 | P a g e
Covid related awareness posters
o Sanitizer/Liquid soap has been kept at PPO & all
sections of ELS/ASN and it has been instructed to use
these frequently to maintain hygiene.
Hand Sanitization at PPO
o Maintaining of social distancing with each other to
prevent any type of infection.
Social Distancing
o Contact free hand sanitizer dispenser unit (censor
based) capacity 08 ltr. cum Automatic temperature
scanner has been procured & commissioned at
38 | P a g e
ELS/ASN for temp. scanning as well as hand
sanitization.
Thermal checking with sanitizer dispenser.
Bilingual Flex posters containing COVID-19 protocol i.e.
guidelines to be maintained to cope up with the present
situation have been provided at the main entry point of
Electric Loco Shed Asansol.
39 | P a g e
Bi-lingual Posters.
o Four nos. automatic sanitizer dispenser machines have
been commissioned at 04 different locations of
ELS/ASN to cope up with the present situation.
Automatic sanitizer dispenser machines.
40 | P a g e
o One no. contact free hand sanitizer dispenser has been
fabricated at ELS/ASN in-house & commissioned at E-1
section. The same has been inaugurated by respected
DRM/ASN on 10.06.2020.
In-house fabricated Hand Sanitizer Dispenser
o A portable Ultra Violet Sanitization Chamber has been
developed in-house at Electric Loco Shed; Asansol to sanitize
hand tools regularly being used by shed personnel to prevent
41 | P a g e
contamination of droplet of Corona virus & cope up with the
present situation by preventing COVID-19.
In-house fabricated UV-Hand Tools Sanitization Chamber
Other Staff Welfare Activities at ELS/ASN :
Water Booth & Staff Corner :
o Respected General Manager has inaugurated a few
staff amenities like a “Water Booth” consists of “Water
Purifier cum cooler”, wash basin including mirror & also
a Staff corner.
Inauguration of “Water Booth” by respected GM/ER.
42 | P a g e
Staff Corner & Water Booth.
Electrical Maintenance Hand Book :
o Maintenance Hand Book prepared by Electrical section
(E-2) as a ready reference to working personnel has
been unveiled by respected GM/ER. The initiative will
definitely upgrade the quality of day to day preventive
maintenance at shed.
Unveiling of handbook of E-2 section by Hon’ble GM/ER
43 | P a g e
Pocket Trouble Shooting Directory :
o Pocket Trouble Shooting Directory prepared by E-1
section has been unveiled by GM/ER. This will be very
much useful for pin point trouble shooting of
Locomotives at line as well as shed.
Inauguration of handbook of E-1 section by Hon’ble GM/ER
Introduction of ORS in Summer :
o A drive has been carried out at ELS/ASN during
Summer to avoid de-hydration of working personnel.
Oral Re-hydration Salt water (O.R.S.) is being
introduced to cope up with the scorching heat of
summer. Daily approximately 150 to 200 working
personnel are drinking the said ORS-water This drive
has welcome by all staff & supervisors and also
appreciated at all level.
44 | P a g e
Introduction of ORS to avoid de-hydration
Inauguration of room with attached toilet facility for lady personnel :
o Respected PCEE/ER has inaugurated newly
constructed room with attached toilet for exclusive use
of lady personnel of ELS/ASN during his visit.
Inauguration of room for lady personnel
45 | P a g e
Renovation of Ladies’ Toilet :
o Ladies’ toilet renovated with modern amenities like
facilities of Wash basin, Mirror, Dustbin, Towel Hanger,
Hand wash, Floor & wall tiles etc.
Inauguration of Ladies toilet,
Women’s Day Celebration :
o Women’s Day has been celebrated at ELS/ASN.
Women’s Day Celebration at ELS/ASN
46 | P a g e
Provision of Sanitary Napkin Disposal Machine:
o Sanitary Napkin Disposal Mchine has been provided at
ELS/ASN.
Sanitary Napkin Disposal machine at ELS/ASN.
Water Purifiers / Coolers :
o As an input to staff amenity item, 04 nos. Water purifiers
cum coolers have been installed at different locations of
ELS/ASN in G-1 / E-4 / M-5 sections as well as at
Sr.DEE/TRS Office.
Water cooler in Sr.DEE/TRS/Office Water cooler beside E-4 section
47 | P a g e
Water cooler in front of G-1 section Water cooler beside M-5 section
Annual Sports Meet :
Annual Sports meet 2020 was organised by TRS/ASN at
Divisional Railway Stadium, Asansol. The Meet was
inaugurated by respected DRM/ASN/ER.
Annual Sports Meet 2020
48 | P a g e
Renovation of Supervisors’ refreshment room:
Supervisors’ refreshment room along with attached toilet
has been renovated.
Newly renovated Supervisors’ refreshment room :
49 | P a g e
Health Camp :
As per Rly.Bd’s Annual Wellness Assurance Checkup
(AWAC) project, Health camp is being organized at
ELS/ASN at regular interval.
Health Camp at ELS/ASN
50 | P a g e
UMID Registration :
As a part of digital Medical card project, UMID registration of
all the TRS personnel has been completed by in-house
effort.
UMID Registration Camp.
Project Saksham :
Training of all the TRS Personnel under Project Saksham, skill development programme launched by Rly. Board, completed 100% at ELS/ASN.
Ongoing Reliability, Safety measures taken :
Review of RAP and RDSO/TC-142 has been completed
during lockdown period. Daily video conference through app has been conducting
by CELE/ER with Shed Officers and Supervisors regarding gap analysis of maintenance practices to improve of overall Loco performance.
51 | P a g e
Daily video conference has been carried out by Officers
and section in charges of ELS/ASN regarding planning of day to day work. Day wise monitoring of Locomotives for any arising / line
report at Supervisors’ & Officers’ level to take necessary onward action. RAP against each & every LOP case.
Strict monitoring of Un-schedule visit to identify the root
cause of failure to prevent recurrence. Proper analysis of shed arising. Super checking of fit Locomotives at Supervisors’ /
Officers’ level. Rectification of the points noted during super checking
before turning out of Locos. Footplate Inspection by Supervisors in ASN based Locos
to identify the deficiencies. Discussion regarding the report generated through
footplate in next day meeting & their rectification in next visit / calling the Loco if required.
52 | P a g e
Night shed inspection by supervisors from 00:00 Hrs. to 04:00 Hrs. Vigorous Safety checking of Locomotives at Supervisors’ /
Officers’ level. Carrying out various modifications related to improvement
of reliability & safety measures advised by RDSO/Rly.BD./Zonal Rly. Safety action plan related to Human safety as well as
Loco safety has been prepared. A safety Whatsapp group has been formed for monitoring
safety related issues. 100% OHE assurance / Counseling done.
Mock fire drill is conducted at the workplace in frequent
basis to train the personnel regarding fire fighting. Mock Fire Drill:
53 | P a g e
Mock Fire Drill at ELS/ASN OHE Assurance:
Counseling on OHE power isolation
54 | P a g e
Detailed status of sanctioned works of ELS/ASN under Demand-16
Sr Details of work Physical Status
1 Augmentation work of ELS/ASN 66% completed
2 Renovation work of insp. Pit no 7,8,9 & 11.
75% completed
Proposed M&P-2021-22 at RB’s level / GM’s level
(2020-21) / DRM level (2020-21) level :
Rly. Bd level – 2021-22 - One no. Universal
multipurpose Arm. Machine amounting Rs.01 crore & 02 nos. EOT cranes (30 Ton – 01 no. & 50 Ton – 01 no.) amounting 18093th (30 Ton – 7448 th & 50 Ton – 10645th) have been proposed in M&P-2021-22 under Rly.Bd. level under plan head 4100/DRF.
GM level – 2020-21 - 01 set synchronized lifting
jack amounting 4400th (CAP) & 01 no. 5 Ton EOT crane amounting 3748th (4100/DRF) have been proposed in M&P – 2020-21 under GM’s level.
DRM level – 2020-21
Battery operated four wheeler platform Truck – 920th . (DRF)
55 | P a g e
Leakage current analyser surge arrester – 1418th (CAP)
Diesel battery operated fork lifter – Capacity 2 Ton
– 1470th (DRF) Baking oven – 150 KVA – 1500 th (DRF)
56 | P a g e
Photographs of Electric Loco Shed; Asansol ENTRANCE
ENTRANCE
LADIES ROOM
LADIES ROOM
AUXILIARY SECTION AREA
AUXILIARY SECTION AREA
57 | P a g e
AUXILIARY PARK
AUXILIARY PARK
WHEEL PARK
STAFF CORNER
M-4 & MILLWRIGHT SECTION AREA
M-4 & MILLWRIGHT SECTION AREA
58 | P a g e
SHED EXTENSION WORK
SHED EXTENSION WORK
CAPITAL STORE BUILDING
CAPITAL STORE BUILDING