1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007

1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

Embed Size (px)

Citation preview

Page 1: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

1

"On PD-->SNuMI-->PP2-->NoVA transition" {VS}

Bob Zwaska

Accelerator Physics Department Meeting

Jan. 10, 2007

≠≠

Page 2: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

2

Yes: More changes• Proton Plan 2 is being absorbed into the NOvA project

May retain the name “Proton Plan 2”

• PP2 work is being carved up (next slide)

• Hopefully, schedule will not be significantly affected by the

merger

• Budget looks comparable to existing plans

• “SNuMI” still refers to inclusion of the Accumulator in the chain

Not part of NOvA – a little off the radar screen

Page 3: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

3

Pieces of PP2• Booster work goes to Proton Plan (1)

Not very much

• Civil work goes to GPPAlways need more service buildings and

penetrations

• Everything else goes into NOvASplit between construction (MIE) and R&D or

operating costsMIE is the price tag of interest: $240-245M (TEC?)

Page 4: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

4

Organization• Nancy becomes Associate Project Manager

There is already a deputy

• PP2 becomes two Level 2s in the NOvA WBSLevel 1s split along the R&D/Ops vs. constructionNancy and Elaine in charge of the PP2 L2sDon’t think there are any level 1 managers

• All documentation needs to be merged with NOvA and brought to Project standards

• Hopefully, it is all the same at lower levels\No technical changes

Page 5: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

5

NOvA

1.0 NON-MIE Accelerator & NuMI Beamline Upgrades

Nancy & ElaineBob & Rob

1.1 Far Site & Building R&D

1.2 Scintillator 1.3 Fiber

1.0.1 Recycler Upgrades

Paul Derwent

1.0.2 Main Injector Upgrades

Ioanis Kourbanis

1.4… 1.10 Project Management

1.0.3 NuMI UpgradesMichael Martens

Kamran Vaziri (RSC)

1.04 Beam PhysicsRobert Zwaska

Page 6: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

6

NOvA

2.0 MIE Accelerator & NuMI Beamline Upgrades

Nancy & ElaineBob & Rob

2.1 Far Site & Building R&D

2.2 Scintillator 2.3 Fiber

2.0.1 Recycler Upgrades

Paul Derwent

2.0.2 Main Injector Upgrades

Ioanis Kourbanis

2.4… 2.10 Project Management

2.0.3 NuMI UpgradesMichael Martens

Kamran Vaziri (RSC)

Page 7: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

7

Staying on Schedule• PP2 (then SNuMI) DR in Nov. will substitute

for CD-1 reviewRequires some cleanup of documentation (mostly

done)

• Then, many more reviews

• Still plan to do first round of installs in Oct., 2009 (or whenever available)

Page 8: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

8

NOvA/PP2 Merger

Page 9: 1 "On PD-->SNuMI-->PP2-->NoVA transition" {VS} Bob Zwaska Accelerator Physics Department Meeting Jan. 10, 2007 ≠

9

Plan Ahead• After a lot of initial worry, PP2 looks to be fine

Extra headaches, as usual

Few serious changes to project

• Still need to do a lot of workWill use division resources

Physicists are (again) asked to get involved• No cost to project – by some accounting

• “SNuMI” will have to be something completely separate