Upload
sheila-bradley
View
219
Download
2
Embed Size (px)
Citation preview
2
Ensuring sponsors’ and lenders’ involvement
A double objective: Satisfy sponsors’ requirements in order to secure equity
financing under a limited recourse scheme Meet lenders’ requirements to attract in excess of USD
1 billion of debt financing
The response primarily rests with the alignment of interests of parties as a risk mitigant under a well developed contractual framework
Strong project rationale Adequate risk allocation and sharing
3
A classical project finance structure, but …
The Nam Theun 2 project has a standard emerging market power project finance
structure … A SPC (NTPC) to implement the Project on a BOOT
basis under a limited recourse finance scheme A turnkey construction contract A Concession Agreement with the Govt of Laos A main PPA with EGAT as offtaker and a PPA with EdL
…but some challenges to overcome
… but combines a few specific and innovative features in response to various
challenges
4
Nam Theun 2 Power Company Limited (“NTPC”) is a Lao company established in Aug. 2002 by :
35% EDF International (EDFI)
25% Electricity Generating Public Company Limited (EGCO)
25% Government of the Lao PDR (GOL)
15% Italian-Thai Development Public Company Limited (ITD)
EDF is acting as Head Contractor, managing three Civil Work subcontracts and two Electromechanical Works subcontracts.
EDF & EGCO are also providing personnel & technical assistance
A classical project finance structure …
experienced sponsors have brought their development expertise
experienced sponsors have brought their development expertise
5
Meeting lenders’ requirements under an acceptable project framework, risk allocation & timeframe
2004-05 prevailing financial market conditions were attractive
high liquidity in bank market, relatively low interest rate environment & few good power projects in the region to attract investments
but Lao risk assessment led to full political risk cover requirement from Lenders & standard emerging market contractual risk allocation
Sponsors require effective financing phase management and timely completion of financing plan
the project financing plan was clear and adequately structured from the outset, project agreements were detailed and based on international standards
these conditions, under proper management, contributed to a smooth and relatively brief financing phase (15 months)
Timely project development is possible with appropriate expertiseTimely project development is possible with appropriate expertise
7
The response: documentation & risk allocation consistent with international
practice All standard risk allocation requirements are
addressed in the Concession Agreement and the PPA
Obligations of host government conformed to standard practice Force Majeure and compensation protection Termination and associated compensation Allocation of land and associated rights Tax incentives and dividend repatriation
The Concession Agreement also addresses specific issues to enhance the existing regulatory framework
List and agreed forms of Governmental approvals Granting of security rights and direct agreement Applicable laws and exemptions to laws
International practice to be followed to meet sponsors’ and lenders’ expectations
International practice to be followed to meet sponsors’ and lenders’ expectations
8
The response: detailed E&S plans allocating responsibilities
The E&S dimension of the project had to be properly addressed to enable project financing: costs, contingencies, liabilities to be clearly expressed to avoid uncertainties or direct recourse to shareholders
A satisfactory E&S structure underpinned by: Founder E&S documents
Concession Agreement (CA) SESIA, EAMP, SDP (incl. RAP), SEMFOP, CIA
Wrap up of E&S obligations, breaches, remedies & defaults in the finance documents
On-going monitoring and progressive and adaptive joint implementation carried out by the Govt of Laos and NTPC through coordination with the IFIs.
E&S obligations back-stopped by bonds in favour of the Govt of Laos USD 16.5 m. of letters of credit financed under the Project finance
plan
9
Emphasis on specific issues of lenders’ due diligence in an hydro project
During construction Specific civil works, e.g. tunnelling Specific construction critical path
To assess appropriate level of contractor’s liabilities
During operation Reliability of hydrology regime Relationship between hydrology,
operating regime and revenues
To assess certainty of take or pay structure
Lenders’ due diligence has departed from usual issues scrutinised in conventional thermal IPP projects.
Access tunnel
Power house
Water intake
Proper risk allocation and contractual documentation allows financeability
Proper risk allocation and contractual documentation allows financeability
11
A suitable response to allow a smooth financing phase
The finance plan is built on a limited recourse project finance scheme
Substantial financing amount required: raising USD 1,581 million eq. in a country without access to commercial funding
The Project finance plan revolves primarily around MLAs, BLAs and ECAs to allow the Project bankability given
the quantum of financing required the perceived sovereign risks Laos unproven track record re. private investments
Strong involvement of Thai commercial banks to allow local currency funding and mitigate forex risk
detailed finance plan and documentation proposed to the Lenders enabled a smooth due diligence phase
detailed finance plan and documentation proposed to the Lenders enabled a smooth due diligence phase
12
A financing structure to match the Project economics
Equi
ty
USD
Deb
t
THB
Deb
t
Con
tinge
nt D
ebt
USD
Con
tinge
nt D
ebt
THB
Bond
ing
Deb
tFa
ciliti
es
Con
tinge
nt E
quity
350
450 450
50 50
131.5100
Total Base Financing
= USD equiv. 1,250
million
Contingent Financing and
Bonding Facilities
=
USD equiv. 331.5 million
Equity Equity CommitmentCommitment
US$ 450 million
USD DebtUSD Debt
US$ 500 m.
THB DebtTHB Debt
THB 20,000 m.
(USD 500 m. equiv)
Bonding Debt Bonding Debt FacilitiesFacilities
USD 131.5 m.
The funding structure matches the cost and revenue profiles (½ THB - ½ USD)
Contin-gent debt & equity funding can cope with a 12-month delay scenario
a natural hedge is provided against foreign exchange risk a natural hedge is provided against foreign exchange risk
13
A requirement for MLA support
Early market sounding has shown expectations from ECAs and commercial banks for a strong IFI / World Bank involvement in the Project
to ensure compliance with highest E&S standards
to share or cover political risk Involvement of the World Group from 1995 substitution of MIGA for IFC due to lack of
attractiveness of “B” loans post Asian crisis
Involvement of the ADB from 2002ADB and MIGA provide pioneering dual-country PRI to accommodate the cross-border nature of the deal
14
Diverse ECA, MLA and BLA & Thai commercial banks participation
World Bank Group and ADB were joined by ECAs upon selection of the electro-mechanical equipment suppliers
Coface (France) EKN (Sweden) GIEK (Norway)
and a MLA, Nordic Investment Bank and by other institutions to complete the finance
plan AFD (French Agency for Development) Proparco (subsidiary of AFD) Thai Exim
All these institutions act as either PRI providers (PRI and commercial risk cover from ECAs) or direct lenders.
Commercial facilities were allocated to 7 Thai banks and 9 international banks on a club-deal basis.
7 Thai commercial banks provide in THB half of the long term loan facilities, and together with Thai Exim, all of the US$131 m. long term L/Cs
Coface is fronting the insurance for EKN &
GIEK under a reinsurance scheme
15
A resulting complex financing structure …
The finance plan comprises 27 financial institutions: 5 MLAs; 4 ECAs; 2 BLAs; 16 Thai & international commercial banks.
d. to d. tenor: USD 16.5 yrs THB 15 yrs
i.e. up to 12 year repayment
… but detailed preparation enabled timely financial close … but detailed preparation enabled timely financial close
16
The Project….
US$ 1.45 billion,1070 MW project in Lao PDR, the largest ever foreign investment in the country.
The project is being implemented by Nam Theun 2 Power Company limited (NTPC), which was established as a limited liability company.
As part of the Concession Agreement (CA), NTPC will develop, finance, construct and operate the plant system.
After a period of 25 years, the plant will revert back to the Government of Laos (GOL).
NT2 will primarily export electricity to EGAT of Thailand. About 5% would be for domestic use.
17
Background….
Project identified in the 1980s. Concession awarded in 1993. Project subject to a long anti-dam campaign. Project preparation discontinued following Asian
financial crisis (1997). Preparation resumed successfully in 2001 when the
parties agreed on a mutually binding set of actions to reach financial close.
Since 2001, extensive due diligence has been undertaken by project participants.
Took about 4 years of preparation (2001-2005) Financial Close - June 15, 2005.
18
Challenges faced in Financing NT2….
Largest private financing in the region at the time. Non-availability of US$ debt (about 500m) w/out cover.
– Export Credits– Political Risk Guarantees– Direct US$ loans– EGAT credit risk– Tenors and pricing
Availability of THB debt (about US$ 500m equivalent).– Non availability of long-term fixed-rate debt– Project location outside Thailand
Cross Border Risk. Funding for GOL Equity (about US$ 90m); HIPC.
19
Bank Group Support….
IDA Grant– To finance E&S expenditures (as GOL Equity in
NTPC) IDA Guarantee
– To mobilize private capital by mitigating Lao PDR political risks
– Covered GOL obligations under project documents IDA Credit to GOL for associated impacts – LeNs MIGA guarantee
– Covered key Thai & Lao political risks
20
World Bank key Due Diligence comprised…
Safeguards – Environment Management, Social Development & Resettlement Plans
Economic/Financial – Financing and Economic viability, Power Sector Analysis – Laos and Thailand, Regional Economic Least-Cost Analysis
Procurement Review Study of Alternatives Economic Impact Study Technical – DSRP Reports, Feasibility Studies Commercial Due Diligence – PPA, CA, SHA, other
Financing Docs
21
Key Lessons Learnt...for large Hydros
Long arduous negotiations on the Concession. Concession deemed “fair” by all partiesConcession deemed “fair” by all parties.– Inclusion of detailed E&S obligations in concessions could
be replicated in future large infrastructure projects. Due Diligence should be of high qualityDue Diligence should be of high quality.
– Fine balance between requirements and cost implications.
Common E&S regimeCommon E&S regime acceptance by all lenders and guarantors facilitates project implementation.
– Harmonization of IFI safeguards requirements is a replicable innovation.
22
Thank YouThank You
Suman BabbarSuman Babbar
Finance & GuaranteesThe World Bank Group
www.worldbank.org/guarantees
23
Contractual Structure
LHSE EGCO EDFI
Nam Theun 2 Power Company
Shareholders Agreement & Equity
Head Construction Contract
EM1 & EM2 CW1, CW2, &
CW3
Construction Sub-Contracts
GOL EGAT EDL
EGAT PPA
EDL PPA
Concession Agreement
Technical Services and Management Services
Agreements
GOL Undertaking
ITD
ECAs
MIGA
Loans
PRG / PRI
ESCO Multilateral & Bilateral Agencies
US$ Banks
World Bank
THB Banks
EIB
ADB
GOL Equity Funding
AFD
EDF
Shareholders’ Agreement
Coverage
24
Global Financial Stake in NT2
WB (US$ 62 million); MIGA (US$ 42 million); ADB (US$ 110 million)
EIB and NIB (about US$ 85 million) European ECA’s (US$ 200 million) French Development Agencies (US$ 60 million) Nine International Dollar Banks (US$ 500 million) Seven Thai Commercial Banks (US$ 500 million
equivalent) Thai Exim (US$ 30 million)
Excluding Private EquityExcluding Private Equity
25
Nam Theun 2: Financing PlanUses of Funds THB Millions USD Millions Total USD Million EquivalentDevelopment Costs 80 72 74Environmental/Social Costs 0 49 49Head Construction Contract 12,847 401 722Financing Costs 4,271 144 250NTPC General and Administrative, incl. Working Capital 414 36 46Pre-operating and Other Costs 568 94 109Total Base Costs 18,180 795 1,250Contingencies 0 200 200Total Project Cost 18,180 995 1,450
Sources of Funds THB Millions USD Millions Total USD Million Equivalent
Equity EDFI 67 121 122 ITD 29 52 52 EGCO 48 86 87 GOL 48 86 87Contingent Equity 0 100 100Total Base Equity 192 345 350Total Project Equity 192 445 450DebtThai Commercial Lenders 20,000 500Commercial Loans covered by ECA's - Coface, GIEK and EKN 200 200Commercial Loans covered by ADB PRG 42 42Commercial Loans covered by IDA PRG 42 42Commercial Loans covered by MIGA Guarantees 42 42Thai Exim Bank 30 30Nordic Investment Bank 34 34ADB OCR Loan 50 50AFD 30 30Proparco 30 30Total Debt 20,000 500 1,000
Total Project Financing 20,192 945 1,450
26
Using IDA PRG to mobilize private debt financing……..
NTPC (SPV)
GOLEquity
PrivateEquity
EGAT(primary offtaker)
Government of Laos(as concessionaire)
THB & non-WBGuaranteed
US$ Commercial Debt
WB GuaranteedUS$ Debt
Limited GOL PerformanceObligations• Permits, Consents• Change in Law• Political FM• Termination of the CA
PPAPPA CACA
CTACTA
IDAIDAGuaranteeGuaranteeAgreementAgreement
SHASHA
IDAIDAIndemnityIndemnityAgreementAgreement
IDAIDAProjectProjectAgreementAgreement
27
Using IDA Grant to finance E&S expenditures (as GOL Equity)……..
LHSE
Lenders
NTPC
IDA
MOF
Loan andShareholdersAgreement
DevelopmentGrant
Agreement
NTSEPProject
Agreement
ShareholdersAgreement
GOL SpecialAccount
Drawdown Request / Withdrawal Application
Finance Documents/Agreements
Flow of Funds
EquityContributionAgreement
TripartiteAgreement
(disbursementarrangements)
Key
28
Key Lessons Learnt...for large Hydros
PRG Lenders were made accountable for Prohibited Lenders were made accountable for Prohibited Activities undertaken by Company and/or Head Activities undertaken by Company and/or Head ContractorContractor.
PRGs provide appropriate risk mitigationPRGs provide appropriate risk mitigation for large private hydropower schemes.
– Political risks– Cross border risks
Optimization of the Financing PackageOptimization of the Financing Package is essential.– Over-commitment by lenders/guarantors– Over 25 project participants– Number of overlapping institutional requirements– Inter-guarantor and lender coordination
29
Rationale for Bank involvement
The project generates revenues (US$ 80 million on average), through socially and environmentally sustainable development of NT2’s hydropower potential.
NT2 revenues finance Lao PDR's poverty reduction and development strategy, key elements of Lao PDR's NGPES and the GOL’s MDG targets in 2015 (about 3% to 5% of gross revenues).
The use of NT2 revenues for these purposes was envisioned in the Decision Framework agreed between the GOL and the Bank in 2001 and reiterated in the Government's Letter of Implementation Policy (GLIP) in 2005.