1 MWth Oxyfuel Combustion Test FacilityBen Goh, Power Technology
“Recent Developments in CCS”Coal Research Forum – Combustion Division meeting17th April 2007, Imperial College London
© 2004 E.ON 23 November 2007, E.ON UK, Page 2
E.ON UK’s 1 MWth Combustion Test Facility (CTF)
Commissioned 1993Located at Power TechnologyTime-temperature scaledFuel flexible
Coal, biomass, oil, Orimulsion, gas, others
Full combustion stagingOverfire airReburnFlue gas recycle
Highly instrumented and controllableOther capabilities added
© 2004 E.ON 23 November 2007, E.ON UK, Page 4
RFSC Project RFS-PR-02003 : “ASSOCOGS”
“Assessment of Options for CO2 Capture and Geological Sequestration”
Start date January 2004
Project co-ordinator E.ON UK
Partners Aristotle University of ThessalonikiCentre For Research and Technology HellasCERECOIMCG InternationalUniversity of NottinghamIVD Stuttgart
© 2004 E.ON 23 November 2007, E.ON UK, Page 5
RFSC Project RFS-PR-02003 : “ASSOCOGS”
“Assessment of Options for CO2 Capture and Geological Sequestration”
WP1 Co-ordinationWP2 Oxyfuel combustionWP3 Development of ceramic membrane supportWP4 Catalyst development for H2S and NH3 decompositionWP5 Catalytic decomposition membrane reactorWP6 Gas-liquid contact membranesWP7 Modelling and scale-upWP8 Adsorption of CO2 from flue gasWP9 Feasibility of CO2 sequestration with in-situ coalsWP10Comparative assessment of technologies and review of
implications for full-scale plant
© 2004 E.ON 23 November 2007, E.ON UK, Page 6
RFSC Project RFS-PR-02003 : “ASSOCOGS”
“Assessment of Options for CO2 Capture and Geological Sequestration”
WP2 Oxyfuel combustion
Review design of CTF for oxyfuel combustionDevelop revised operational proceduresPrepare detailed redesignConstruct and commission CTFRefine operational proceduresPerform parametric testingReview findings and implications
© 2004 E.ON 23 November 2007, E.ON UK, Page 11
“Carrier stream”
Moisture removalMinimise air ingressMinimise gas egress
© 2004 E.ON 23 November 2007, E.ON UK, Page 12
“Ballast flow”
Maintain flows through cyclone, fan and stack
© 2004 E.ON 23 November 2007, E.ON UK, Page 13
Issues
SafetyGas compositionsMaterials flammability, explosion riskFlame detectionInterlocks
ProcessCoal feedingHeat extractionParticulate removalMaterials – high temperature, O2 purityAir ingressMoisture removal
Control and InstrumentationMass flow – via densityO2 concentration
OperationSwitchoverFeedbackTrips
Others….
© 2004 E.ON 23 November 2007, E.ON UK, Page 15
Bulk stream tower
Bulk stream cyclone Bulk
stream cooler
Bulk stream fan
O2 injection point
Carrier stream chiller
Bulk stream measurement stream
© 2004 E.ON 23 November 2007, E.ON UK, Page 16
Carrier stream – first floor
Carrier stream cooler
Carrier stream chiller
Carrier stream ‘knockout’ pot
Bulk stream tap in
© 2004 E.ON 23 November 2007, E.ON UK, Page 17
Carrier stream – ground floor
Carrier stream condensate
Carrier stream final cooler
Carrier stream fan
© 2004 E.ON 23 November 2007, E.ON UK, Page 18
Test programme
ConditionsO2 enrichment (14 to 28% vol, wet)Excess oxygen (1 to 4% vol, dry)‘Air’ staging (0 to 25% OFA)Fuel type (VM, S, Cl)Trip tests, changeover tests, operation/procedure
RFSC ASSOCOGSKleinkopje coal – combustion
DTI OxyCoal-UKEl Cerrejon and Thoresby – combustion, deposition, corrosion
© 2004 E.ON 23 November 2007, E.ON UK, Page 19
Test programme
MeasurementsGaseous emissions – O2, NO, SO2, CO, CO2, othersExtractive sampling – LOI, CO, othersAsh size distributionExtracted water compositionHeat fluxFlue gas temperature – optical pyrometerDepositionSlagging and foulingCorrosion – 50 hour tests
© 2004 E.ON 23 November 2007, E.ON UK, Page 21
Summary
HistoryRFSC ASSOCOGS project – started
FlowsFuel – 1 MW pulverised coalCarrier stream – cooled, cleaned, dried recirculated flue gasBulk stream – cooled, cleaned, wet recirculated flue gasOxygen – LOXOutput – 5X CO2 (>80%), 3X SO2, 2X CO, 0.5X NO, 0.3X exhaust
MeasurementMass and volume flow => density – bulk and carrier streamsTemperaturesO2 concentration – bulk stream pre- and post-O2 injection
OperationRetains original air stagingO2 enrichment 14 to 28% volExcess oxygen 0 to 4%
ResultsStill coming in…