16
1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

Embed Size (px)

Citation preview

Page 1: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

1

Moving Forward with

the USEPR

Greg GibsonVice President

Regulatory Affairs

Page 2: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

2

Discussion Topics

• UniStar

• Current Status of the EPR

• USEPR Owners Group

• EPR Fleet Experience Feedback

• ITAAC (Inspections, Tests, Analyses Acceptance Criteria)

Page 3: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

Like-minded owners Shared resources Shared generic development costs Standardized fleet AREVA’s U.S. EPR technology

UniStar:

Generic DDE Licensing (DCD, COLAs)Equipment procurementConstruction best practicesOperating proceduresSimulator and training developmentCommunications programs

Cost Optimization:

Page 4: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

4

UniStar Business Model Principles• Standardization

– Use FL-3 design criteria for control room, MMI and TG/BOP design– Use EDF planning, construction, startup and operating experience

and procedures– Maximize the use of real time OL-3 and FL-3 lessons learned– Create processes to maintain fleet standardization in all project

phases

• Risk Mitigation– Levelize the most controllable portions of overnight capital costs

(paper and procurement)– Risk management improves as fleet size grows

• Flexibility– Provide the tools and procedures needed by owners in licensing,

EPC and operations of the Fleet – Operate U.S. EPRs as a standardized fleet, through the entire

plant lifecycle

Page 5: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

5

UniStar Project Timelines

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

COL Issued

CODConstruction begins

Calvert Cliffs3 - MD

Nine Mile Point - NY

Callaway - MO

Bell Bend - PA

New Project

Page 6: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

Current Status of the EPR

Page 7: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

7

EPR in Finland: Olkiluoto 3

Page 8: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

MAY 2006

MAY 2007

MAY 2008

Page 9: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

EPRTM in China

Artist rendering of Taishan site with four EPRs

January 2009 – Taishan construction site

Page 10: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

10

New EPRs

• Penly 3 Status– Electricite de France and GDF Suez

welcomed the announcement of a second French EPR, to be built in partnership at the Penly nuclear power plant site on the Channel.

• Potential additional EPR in France (3 total by 2020)

Page 11: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

11

EPR Owners Group

Each EPR project belongs to a worldwide community

What affects one of us

will impact all of us

We need an organization and a means to communicate

Page 12: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

12

EDF to UniStar FA3/OL3 Lessons Learned Transfer Process

Page 13: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

13

How ITAAC Fits Into Commissioning Tests

Integrated Test Program

•Pre-operational Tests (includes ITAAC)•Initial Fuel Load and Pre-critical Tests•Initial Criticality and Low Power Physics Tests•Power Ascension Tests

Other Tests

•Performance Tests•Demonstration Tests•Initial Surveillance Tests•Component/Equipment Tests•Systems Tests

ITAAC*

•SSC Inspections, Tests and Analysis•Non-SSC Inspections, Tests and Analysis

Required prior to Fuel Load

* Inspection, Test, Analysis, Acceptance Criteria

Page 14: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

14

Current ITAAC Challenges

• There are currently 1000+ ITAAC which will require detailed plans for execution, scheduling, documentation, and NRC notification = collaborative effort

• NRC review and approval of ITAAC in the DCD is not yet complete and will likely result in comments.

• Configuration Management of completed/inspected ITAAC is yet to be developed.

• ITAAC delays during construction and/or testing could impact the fuel load schedule, and Commercial Operation Date.

Page 15: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

15

Objectives of an ITAAC Program:

• The ITAAC process should take advantage of current processes/programs (i.e., QA Program, Pre-Op Test Program)

• “Book of ITAAC”– Detailed description and definitions for each ITAAC– Execution Plan including methodology & closure

criteria– Sequence and Schedule– Ensure the Schedule is shared with the NRC so

independent verification and validation is ensured

Page 16: 1 Moving Forward with the USEPR Greg Gibson Vice President Regulatory Affairs

16

Objectives of an ITAAC Program:

• ITAAC results should not result in unexpected NRC findings.

• ITAAC inspections hopefully will not impact the construction schedule.

• ITAAC information and Project Schedule should be provided to the NRC in a proactive manner to avoid impacts on schedule.

• Owners should have a close working relationship with the NRC in order to establish and implement the ITAAC process.

• Experience from the industry will be shared – NRUG concept