Microturbine CHP Applicationin the Hotel Business

DOE MicroturbineApplication Workshop

Embassy Suites Brea January 20, 2004

Page 2: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

2

Who is PowerHouse Energy

A Southern California based Distributor and Authorized Service Provider of both traditional and state-of-the-art energy products

It’s sole mission is to create a win-win solution for it’s customers by reducing energy costs and increasing profits through the use of on-site generation equipment while never reducing the customer’s security of supply

PHE offers a variety of options for equipment ownership. It will install and service the equipment to insure seamless energy generation

Page 3: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

3

Who is Embassy Suites

Embassy Suites, Brea is a full service hotel in the central retail district

They have 228 guest rooms with a 400 seat restaurant with conference/meeting rooms

The hotel operates 24 hours X 7 days a week They have room heat pumps, central water

heating, laundry, swimming pool and spa PHE partnered with the hotel in an energy

service The hotel was interested in cost savings

Page 4: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

4

Pre-CHP Electrical Load

One Quarter Power Consumption - Chart 1

Test 4Start: 7/28/2002 2:46:07 PM End: 8/1/2002 5:02:07 PM

Real Power - 3Ø (W)

8/ 1/ 2002 12: 00: 00 PM8/ 1/ 2002 12: 00: 00 AM7/ 31/ 2002 12: 00: 00 PM7/ 31/ 2002 12: 00: 00 AM7/ 30/ 2002 12: 00: 00 PM7/ 30/ 2002 12: 00: 00 AM7/ 29/ 2002 12: 00: 00 PM7/ 29/ 2002 12: 00: 00 AM

126, 000

125, 000

124, 000

123, 000

122, 000

121, 000

120, 000

119, 000

118, 000

117, 000

116, 000

115, 000

114, 000

113, 000

112, 000

111, 000

110, 000

109, 000

108, 000

107, 000

106, 000

105, 000

104, 000

103, 000

102, 000

101, 000

100, 000

99, 000

98, 000

97, 000

96, 000

95, 000

94, 000

93, 000

92, 000

91, 000

90, 000

89, 000

88, 000

87, 000

86, 000

85, 000

84, 000

83, 000

82, 000

81, 000

80, 000

79, 000

78, 000

77, 000

76, 000

W

Page 5: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

5

Post CHP Installation

Page 6: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

6

Progress Checklist

Process 1. PHE shares energy options and programs available today 2. CUSTOMER provides PHE with energy bills 3. PHE and CUSTOMER establish energy requirements for customer’s business 4. PHE performs a site survey 5. PHE and CUSTOMER discuss project’s technical and financial aspects 6. PHE develops project evaluation checklist 7. PHE prepares a preliminary report and meets with CUSTOMER to review

project recommendations, costs, timing and evaluation checklist 8. CUSTOMER reviews preliminary report and makes decision to proceed 9. PHE monitors CUSTOMER’S energy use 10. PHE documents use and files utility rebate forms on CUSTOMER’S behalf 11. Financial, engineering and construction bids are obtained 12. CUSTOMER internally reviews ownership and leasing options 13. PHE produces final report and proposal and meets with CUSTOMER to review all project implementation details 14. PHE and CUSTOMER sign contract 15. PHE handles site engineering, construction procedures, and permitting 16. Construction and installation

Page 7: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

7

Project Schedule

Page 8: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

8

Organization

Project Management- Thom McMahon/ Installation, Ken Nilsson/Service

Funded, Owned and Operated by PowerHouse Energy

Project Plan (Actual Date)

- Equipment Delivery 12/2002(Same)

- System Commissioned 3/2003(5/2003)

- Monitoring Underway 5/2003(5/2003)

Page 9: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

9

Pictures of Site

Page 10: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

10

Pictures of Site

Page 11: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

11

P&ID As Built

Page 12: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

12

Installation Improvements

Improvements this Site

- Ventilation improvements

- Metering equipment and pool heat interfaces as original installation

- Selection of installation contractors

- Poor fit of supplied package exhaust ducting Target Improvements-Volume Installations

- Standard drawing packages

- Experienced installation contractors

- Volume material purchases

Page 13: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

13

Project Cost Table

Item Actual HindSight 50th InstallTurbine $100,000 $100,000 $92,000CHP Unit Inc. N/C N/CMechanical $30,000 $25,000 $22,000Electrical $25,000 $23,000 $21,000Civil $2,000 $2,000 $2,000Consulting $10,000 $0 $0Engineering $4,000 $4,000 $2,500Proj. Mgnt. $15,000 $3,000 $2,000Total $186,000 $157,000 $141,500

Page 14: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

14

Electrical Performance

Hours of operation to Date 4000 & 4100 Average Electrical Performance 26% 65,000kW/9,200 Therms (LHV) (Dec. 2003) Estimated Parasitic Loses in KW- 5kW/hr Power Quality Tests Done as required by

Southern California Edison for Interconnection acceptance.

Page 15: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

15

Thermal Performance

Thermal Output used 420,000,Btu/hr Average water Delta T across HTX 12oF Average flow rate through HTX 70gpm CHP Efficiency 55%, (26%e+29%t) Expected Peak Total System Efficiency 70% Electrical 28%+ Thermal 40% Cooling system N/A

Page 16: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

16

Emission Performance

No emission testing has been done to date. Emissions appear to be in line with Capstone

estimates.

Page 17: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

17

O&M Performance

Availability The equipment was unavailable for 612 hours due to

equipment failure, (2 units including site issues). Availability cumulative since start 94.4%. 15 site visits due to equipment, 15 due to data acquisition and site issues.

Cost of O&M (less fuel) The current estimate of annual O&M costs excluding

hot end replacement in total costs is $7,000 and 0.8cents/kWh, (2 units).

Page 18: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

18

Institutional Experience

Building department and electric utility interconnection approvals were required.

Project management overhead costs associated with approvals were approximately $2,500.

No issues were encountered with either approval process.

Page 19: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

19

Supplier Support

PHE was the supplier that “turn keyed” the installation. Better understanding of radiant heat generation for ventilation of product would be helpful, ~70,000Btu/hr each w/gas compressor.

Technical support was very good from Capstone with clear documentation.

PHE is a Capstone Business Partner with a clear understanding of O&M costs.

PHE took advantage of Capstone’s promotional two unit package with a 3-year back stop warranty of $0.008/kWh costs.

Page 20: 1 Microturbine CHP Application in the Hotel Business DOE Microturbine Application Workshop Embassy Suites Brea January 20, 2004

20

General Experience

Indoor installations need to account for radiant heat with ventilation. Tight space installations may not be able to accommodate product improvements.

PHE has gone on to do several other hotel installations, honing design and contractor work. Current installation costs by PHE are now within 1-2% of planned or budget costs.

Suggested development areas, monitoring capability of kW, thermal and gas use in unit. Reliability of electrical components.