Upload
crystal-sutton
View
216
Download
0
Embed Size (px)
Citation preview
1
LRO Mission Overview
Craig Tooley - GSFC/431September 7, 2005
2
2008 Lunar Reconnaissance Orbiter (LRO)First Step in the Robotic Lunar Exploration
Program
Robotic Lunar Exploration ProgramRobotic Lunar Exploration Program
LRO Objectives
• Characterization of the lunar radiation environment, biological impacts, and potential mitigation. Key aspects of this objective include determining the global radiation environment, investigating the capabilities of potential shielding materials, and validating deep space radiation prototype hardware and software.
• Develop a high resolution global, three dimensional geodetic grid of the Moon and provide the topography necessary for selecting future landing sites.
• Assess in detail the resources and environments of the Moon’s polar regions.
• High spatial resolution assessment of the Moon’s surface addressing elemental composition, mineralogy, and Regolith characteristics
3
• LRO provides major scientific and exploration benefit by 2009– Apollo provided only a small glimpse of Moon; much to be explored– LRO address both science and exploration objectives– LRO brings many benefits (e.g., future landing sites, polar resources, safety, science)
• LRO selected instruments complement other foreign efforts– Six instruments competitively selected (“next-generation payload”)– Comparison to foreign systems demonstrate uniqueness and value– LRO will also accommodate a HQ directed Technology Demonstration payload, the
Mini-RF (SAR) instrument.
• LRO will enhance our knowledge of the Moon and increase the safety of future human missions.
– 3D maps of terrain and hazards, as well as of localized resources (ice) will tell us where to land (and at what precision).
– Exploration of new sites where resources may be available requires new and timely knowledge of those sites at scales never before possible.
• Current state of knowledge does not allow us to reduce the risk and cost of humans landing and working on the Moon.
– Equatorial environment (terrain, thermal, lighting) is different from polar region.– Apollo Program flight system capability limited to equatorial region (capability)
Investigation Background
4
Benefit Example: Identifying Landing Sites & Resources
Polar Topography/shadow mapping
Resource imaging
Temperature mapping (find cold traps)
5
• Launch in late 2008 on a Delta II rocket into a direct insertion trajectory to the moon.
• On-board propulsion system used to capture at the moon, insert into and maintain 50 km altitude circular polar reconnaissance orbit.
• 1 year mission• Orbiter is a 3-axis stabilized,
nadir pointed spacecraft designed to operate continuously during the primary mission.
LRO Mission OverviewFlight Plan – Direct using 3-Stage ELV
Solar Rotating Coordinates
Earth
Moon at encounter
Cis-lunar transfer5.1978 day transferLaunch C3 –2.07 km2/s2
1-dayLunar Orbit
Sun direction
Nominal Cis-lunar Trajectory
Cis-Lunar Transfer
12-hour orbit
6-hour orbit
100 and 50kmmission orbits
Insertion and CircularizationImpulsive Vs (m/s)
1 – 344.242 – 113.063 – 383.914 – 11.455 – 12.18
6
LRO Mission OverviewOrbiter
LRO Instruments
• Lunar Orbiter Laser Altimeter (LOLA) Measurement Investigation – LOLA will determine the global topography of the lunar surface at high resolution, measure landing site slopes and search for polar ices in shadowed regions.
• Lunar Reconnaissance Orbiter Camera (LROC) – LROC will acquire targeted images of the lunar surface capable of resolving small-scale features that could be landing site hazards, as well as wide-angle images at multiple wavelengths of the lunar poles to document changing illumination conditions and potential resources.
• Lunar Exploration Neutron Detector (LEND) – LEND will map the flux of neutrons from the lunar surface to search for evidence of water ice and provide measurements of the space radiation environment which can be useful for future human exploration.
• Diviner Lunar Radiometer Experiment – Diviner will map the temperature of the entire lunar surface at 300 meter horizontal scales to identify cold-traps and potential ice deposits.
• Lyman-Alpha Mapping Project (LAMP) – LAMP will observe the entire lunar surface in the far ultraviolet. LAMP will search for surface ices and frosts in the polar regions and provide images of permanently shadowed regions illuminated only by starlight.
• Cosmic Ray Telescope for the Effects of Radiation (CRaTER) – CRaTER will investigate the effect of galactic cosmic rays on tissue-equivalent plastics as a constraint on models of biological response to background space radiation.
SOLAR ARRAY
PROPULSION MODULE
AVIONICS MODULE
INSTRUMENT MODULE
Mini-RF
LOLA
LAMP
LROC
CRaTER
SOLAR ARRAY
HGA
PROPULSION MODULE
AVIONICS MODULE
INSTRUMENT MODULE
Diviner
LEND
LAMP
LRO Preliminary Design
Preliminary LRO Characteristics
Mass 1317 kgDry: 603 kg
Fuel: 714 kg
Power 745 W
Measurement Data Volume
575 Gb/day
7
Competitively Selected LRO Instruments Provide Broad Benefits
1000’s of 50cm/pixel images (125km2), and entire Moon at 100m in UV, Visible
~50m scale polar topography at < 1m vertical, roughness
Hydrogen content in and neutron radiation maps
from upper 1m of Moon at 5km scales, Rad > 10 MeV
Maps of frosts in permanently shadowed
areas, etc.
300m scale maps of Temperature, surface
ice, rocks
Tissue equivalent response to radiation
Measurement
Resource evaluation, impact flux and
crustal evolution
Safe landing sitesthrough hazard
identification; some resource identification
LROC
Geological evolution of the solar system by geodetic topography
Safe landing site selection, and
enhanced surface navigation (3D)
LOLA
Improved understanding of
volatiles in the solar system - source,
history, migration and depositionLocate potential water-
ice in lunar soil and enhanced crew safety
LEND
Locate potential water-ice (as frosts) on the
surface
LAMP
Determines conditionsfor systems operability and water-ice location
Diviner
Radiation conditions that influence life
beyond Earth
Safe, lighter weight space vehicles that
protect humans
CRaTER
ScienceBenefit
ExplorationBenefit
INSTRUMENT
1000’s of 50cm/pixel images (125km2), and entire Moon at 100m in UV, Visible
~50m scale polar topography at < 1m vertical, roughness
Hydrogen content in and neutron radiation maps
from upper 1m of Moon at 5km scales, Rad > 10 MeV
Maps of frosts in permanently shadowed
areas, etc.
300m scale maps of Temperature, surface
ice, rocks
Tissue equivalent response to radiation
Measurement
Resource evaluation, impact flux and
crustal evolution
Safe landing sitesthrough hazard
identification; some resource identification
LROC
Geological evolution of the solar system by geodetic topography
Safe landing site selection, and
enhanced surface navigation (3D)
LOLA
Improved understanding of
volatiles in the solar system - source,
history, migration and depositionLocate potential water-
ice in lunar soil and enhanced crew safety
LEND
Locate potential water-ice (as frosts) on the
surface
LAMP
Determines conditionsfor systems operability and water-ice location
Diviner
Radiation conditions that influence life
beyond Earth
Safe, lighter weight space vehicles that
protect humans
CRaTER
ScienceBenefit
ExplorationBenefit
INSTRUMENT
(BU+MIT)Cosmic Ray Telescopefor the Effects of Radiation
(UCLA)
(SWRI)Lyman-Alpha Mapping Project
(Russia)Lunar Exploration Neutron Detector
(GSFC)Lunar Orbiter Laser Altimeter
(NWU+MSSS)Lunar Recon Orbiter Camera
8
LRO Spacecraft Systems Block Diagram
9
LRO C&DH Architecture Block Diagram (New-8/29/05)
RAD750SBC
GD-DIB# HK/IO
Ka-Comm
S-Comm
LROC
LAMP
LOLA
NAC1 WACNAC2
32 Mbps
1Mbps 38.4Kbps(UART)
ThermalCard
1553BSerial IF
LEND
Diviner
CRATER
SpaceWire (HSB)
1553B (LSB)
125 Mbps (Science Downlink)
Mini-RF
8 to 32Mbps(Max.)
BAE SpaceWire
ASIC
1553 Summit
3U-cPCI
SpaceWire FPGA
SpaceWire FPGA
SpaceWire FPGA
SpaceWire FPGA
SpaceWire FPGA
C&DH
Instruments
LVPC
SUBSYSTEMS (ACS, PSE, PRO/DEP)
Unsw. +28V
Backplane
HGA
Hi-RateTlm125Mbps (Max.)
S-Xpndr
Ka-Xmtr
HGAGimbalsLow-Rate
Tlm 2Mbps Max & Command 4Kbps
UnSw. +28V (SBC)
1553 Summit
5 Heater out Unsw.+28V
Sw. +28V (Ka-Comm)
UnSw. +28V (S-Comm)
+3.3V (B), +5V (B)
+/-15V, +5V, +3.3V (A)
I/O
( A) (B)
Sw. +28V (Heater)2 Mbps Max. (HK Downlink)
2 Mbps Max. (LAMP Tlm)
+28V Power
1PPS
6U-cPCI
GD-DDAGD-DDA
ATA IF
#Changed
cPCI Backplane
10
LRO Spacecraft Systems Capabilities
LRO Capability Highlights
Mass: 1480 kg
Power: 823 W orbit average @ 35V
Battery: Lithium Ion Chemistry
80 Amp-Hour Capacity
Data Storage Capacity: 400 Gb
Data Rate: 100 Mbps Down – Ka Band
2.186 Mbps Up/Down – S Band
Timing relative to UTC: 3ms
Delta V Capability: 1326 m/sec
Pointing Accuracy: 60 Asec relative to GCI
Pointing Knowledge: 30 Asec relative to GCI
LRO Capability Highlights
Mass: 1480 kg
Power: 823 W orbit average @ 35V
Battery: Lithium Ion Chemistry
80 Amp-Hour Capacity
Data Storage Capacity: 400 Gb
Data Rate: 100 Mbps Down – Ka Band
2.186 Mbps Up/Down – S Band
Timing relative to UTC: 3ms
Delta V Capability: 1326 m/sec
Pointing Accuracy: 60 Asec relative to GCI
Pointing Knowledge: 30 Asec relative to GCI
LRO Overview
6 Instruments and 1 Technical Demonstration
3 Spacecraft Modules – Instrument, Propulsion, Avionics
2 Deployable Systems – High Gain Antenna, Solar Array
2 Data Buses – Low Rate 1553, High Rate Spacewire
2 Comm Links – S Band, Ka Band
Monopropellant System – Hydrazine, Single Tank design
LRO Overview
6 Instruments and 1 Technical Demonstration
3 Spacecraft Modules – Instrument, Propulsion, Avionics
2 Deployable Systems – High Gain Antenna, Solar Array
2 Data Buses – Low Rate 1553, High Rate Spacewire
2 Comm Links – S Band, Ka Band
Monopropellant System – Hydrazine, Single Tank design
11
Ground System Architecture Overview
12
LRO Mission Phases Overview
No Phase Sub-Phases Description
1Pre-Launch/ Launch
Readiness
Space Segment Readiness Ground Segment Readiness
Includes instrument I&T, spacecraft/orbiter I&T, space/ground segment testing as well as operations preparation and ground readiness testing leading up to launch.
2
Launch & Lunar Transfer
Launch and Ascent Separation and De-spin Deployment and Sun Acq. Lunar Cruise Lunar Orbit Insertion
Includes all activities & operations from launch countdown sequence to Lunar Orbit Insertion (LOI). LOI includes all maneuvers necessary to obtain the temporary parking orbit for Orbiter activation and commissioning. During the cruise phase, initial spacecraft checkout will be performed to support activities for mid course correction (MCC) and LOI.
3
Orbiter Commissioning
Spacecraft Commissioning Integrated Instrument
Commissioning
Configure and checkout the spacecraft subsystems and ground systems prior to instrument turn-on. Instrument integrated activation will be developed to complete instruments turn-on and commissioning. Instrument commissioning includes any calibration activities needed in the temporary orbit.
4
Routine Operations
Measurements (Routine Ops) Station-keeping Momentum Management Instrument Calibrations Lunar Eclipse Yaw Maneuver Safe Mode
One year of nominal science collection in the 50 (+/- 20) km orbit.
5Extended Mission
Operations
After 1-year of science observations, orbiter will be boosted into a higher orbit to reduce maintenance requirements. Potential purpose for extended mission operationsmay be to perform relay comm. operations. Alternatively additional measurementoperations may be performed for a shorter period in a continued low orbit.
6End-of-Mission Disposal
Includes planning and execution of end-of-life operations. LRO will impact lunar surface.
13
LRO Project OrganizationLRO Project Manager
C. Tooley
400
System AssuranceManagerR. Kolecki
08/31/2005
Deputy Project ManagerTBD
Deputy Project Manager/Resources
P. Campanella
Materials EngineerP. Joy
Manufacturing EngineerN. Virmani
Safety ManagerD. Bogart
RM CoordinatorA. Rad
Project ScientistG. Chin
FinancialManagerB. Sluder
Project SupportManager
K. Opperhauser
CM/DMD. Yoder
SchedulingA. Eaker
General BusinessD. Yoder/ P. Gregory
MISA. Hess/ J. Brill
Mission Business Mgr.J. Smith
ContractingOfficerJ. Janus
OrbiterI & T Lead
J. Baker
ACS HardwareJ. Simpson
CommunicationsJ. Soloff
C&DHQ. Nguyen
Flight DynamicsM. Beckman/ D. Folta
SoftwareM. Blau
ThermalC. Baker
PowerT. Spitzer
ACS AnalystJ. Garrett
PropulsionC. Zakrzwski
ElectricalR. Kinder
MechanicalG. Rosanova
Mission SystemEngineer
M. Houghton
GN&C Systems EngineerE. Holmes
Avionics Systems EngineerP. Luers
Orbiter Systems EngineerM. Pryzby
Operations System EngineerM. Beckman/ D. Folta
SW/HW SystemsEngineerC. Wilderman
Contamination ControlC. Lorenston
Mission Success EngineerK. Deily
Payload SystemsManagerA. Bartels
Ground Network& Operations
R. Saylor
Payload SystemsEngineers
CRaTERD. Spence
Boston University
DivinerD. Paige
UCLA
LENDI. Mitrofanov
ISR, Moscow
LAMPS. Stern
SWRI
LROCM. Robinson
Northwestern Univ.
Mini -RF
NAWC
LOLAD. Smith
GSFC
L. Hartz
J. Baker
M. Reden
Launch VehicleManagerT. Jones
200
600
300
400
400
500
500 400 400 400
500
14
LRO Mission Schedule
2004 2005 2006 2007 2008 2009Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
7/31/05
LRO Mission Schedule
LRO Mission Milestones
Mission Feasibility Definition
Payload Proposal Development
Payload Preliminary Design
System Definition
S/C &GDS/OPS Preliminary Design
Payload Design (Final)
Spacecraft Design (Final)
GDS/OPS Definition/ Design
Payload Fab/Assy/Test(7 Instruments)
S/C Fab/Assy/Bus Test
GDS/OPS DevelopmentImplemention & Test
Integration and Test
Launch Site Operations
Mission Operations
AO Release
AO Sel. MRD
SRR
IPDR PDR
IBRConf. Review
ICDR CDR MOR
IPSR
PER
FOR/ORR
MRR
PSR
LRR
Launch
Instr. PDR's9/6-9/29
Network Decision
Payload complete (Final Delivery to I&T)(LAMP/LOLA/LROC/Diviner/CraTer/LEND/Mini-RF)
S/C complete (Final delivery to I&T)
GND Net Test Ready
S/C BUS Payload
Ship to KSC
Launch
(1M Float)
(1M Float)
(1M Float)
Ver. 0.9
(1M Float)
CY
Envir. Testing
Mission PDR target: November 14
15
LRO Project Overall Status• Project almost fully staffed
– 45 civil servants & 23 support contractor at present (FTEs & WYEs)– Project level augmentations in-work as Program/Project resources are phased out.
• Project infrastructure in-place– Project organization and staffing being adjusted in reaction to RLEP transfer to ARC
• Project Plan drafted for November 2004 Program review– Currently being revised to reflect RLEP move to ARC & to comply with NPR 7120.5 rev.
C
• Mission SRR successfully conducted August 16-17
• Major system trades nearly complete– C&DH Architecture– Propulsion System – Ground Network – Data Recorder Technology – High Accuracy Tracking Methodology
• Level 2 & Level 3 Requirements established and moving thru review/approval cycles – SRR successfully completed
• Overall integrated mission development schedule developed and in review– Baselined after PDR in preparation for Confirmation
16
LRO Element Development Status
• Instruments – high heritage proposed designs converging to preliminary designs– Design efforts primarily focused in two areas
• Design modifications to adapt to LRO command/data interfaces• Design modifications driven by lunar thermal environment
– Low lunar polar orbit is significantly different than Mars missions where most instrument heritage is from.
– Interfaces with spacecraft well defined – ICDs in review/release cycle• Allocations released and agreed upon
– LRO Payload Science Working Group formed and functioning• Consists of PI’s lead by LRO Project Scientist
– Integral part of LRO mission operations planning
• Spacecraft bus – AO design concept evolving to preliminary design– All subsystems on track for mission PDR this Fall
• Propulsion subsystem moved in-house at GSFC – leverages HST-DM surplus hardware• Spacecraft Computer specified and under development on ESES contract• SQ-RAID (hard disk) technology selected for data recorder. Acquisition now in-work.• Subsystem technical Peer Review being conducted Sept. - November• Approximately $15M in direct procurements planned during Sept.-Dec.
• Ground Systems – architecture and acquisition approach defined– Mission Operations Center
• Preliminary design established based on GSFC heritage systems• Location established, initial facility agreements in-place
– Ground Network• Requirements and architecture established• Primary 18m antenna procurement contract in place• GSFC Ground Networks providing end-to-end system
– Development tasks on NENS contract established
• SRR Planned for November
17
LRO Requirements
• Mission SRR held 9/16-17/2005 – judged very successful– Review covered development and flow down of level 2 and 3
requirements from the NASA ESMD Level 1 requirements• Instruments presented flow down of Level 1 measurement and data
product requirements to their level 2 and 3 performance and functional requirements
• Project presented flow down of level 2 and 3 mission, spacecraft, and ground system requirements
• ~ 50 RFAs/Comments, none specific to instruments.
• Level 1 requirements being refined by ESMD with Project and assistance.
– Ongoing work includes establishment of Mission Success Criteria
– SRR demonstrated that instrument requirements are established, understood, and realizable.
18
LRO Requirements Development Roadmap
LRO Level 1 RequirementsESMD-RQMT-0010
Mini-RFAllocationsElectrical Spec
Mechanical SpecThermal Spec
LRO Mission RequirementsDocument
431-RQMT-000004
Level 2 Performance & SOC
Requirements
Level 2 Requirement Synthesis
Instrument Proposals & LRO AO/PIP+
Instrument Questionnaires+
Instrument-Project TIMs+
Instrument Accommodation Review+
Mission Trade Studies+
Collaborative Drafting of ICDs
Instrument interface requirements & constraints on spacecraft
Spacecraft and Ground Requirements
Operations
Contamination
RadiationMission Assurance
LOLALROC
LAMPLEND
CRaTERDiviner
Project Requirements
Measurement Requirements & Instrument Specific Expected Data Products
Spacecraft, Instrument & Ground Level 3 Requirements Documents & ICDs
Preliminary Engineering
Launch Vehicle
19
LRO Mission Requirements Hierarchy
ESMD
Launch Vehicle
LRO OrbiterInstrumentsSpacecraft Bus
Tech Demo
FSW Power
Flight Dynamics
Propulsion
Communication
Electrical
C&DHMechanical
LAMP LROC LEND DRLE LOLACRaTER
LRO Mission
Ground System
LRO Level 1Requirements
ESMD-RLEP-0010
LEVEL 2
LEVEL 3
LEVEL 1
Mission Assurance
MISSIONASSURANCE
Mission Requirements Documents
Mission Requirements Document (MRD)
431-RQMT-000004
ACS
LOLA to Spacecraft Electrical ICD
431-ICD-000098
DLRE Electrical ICD
431-ICD-000095
LEND Electrical ICD
431-ICD-000097
LROC Electrical ICD
431-ICD-000099
LAMP Electrical ICD
431-ICD-000096
CRaTER Electrical ICD
431-ICD-000094
Tech Demo Requirements
Mini RF Requirements and Goals Document
431-RQMT-000157
GROUND/OPERATION
GENERAL SPECSSYSTEMS
Thermal
CM Key
Released
Document
In CCB for Release
Document
DRAFT
Document
To Be Written
Document
LV Questionnaire
431-REF-000172
Delta II Payload Planners Guide
MDC 00H0016
Range Safety User Requirements
AFSPCMAN 91-710
Thermal Modeling Reqt Document
431-RQMT-000092
Component MICD Guidelines HDBK
431-HDBK-000093
LRO SpaceWire Spec
431-SPEC-000103
Thermal Systems Spec
431-SPEC-000091
LRO Electrical Systems Spec
431-SPEC-000008
Mechanical Systems Spec
431-SPEC-000012
LRO Mission Assurance Reqt
431-RQMT-000174
LRO Mission Concept of Operations
431-OPS-000042
LRO Data Management Plan
431-PLAN-000182
LRO Observatory Verification Plan
431-PLAN-000101
LRO Contamination Control Plan
431-PLAN-000110
LRO Integration and Test Plan
431-PLAN-000100
LRO Radiation Reqt
431-RQMT-000045
DRLE Instrument Requirements
DRLE Instrument Performance RD
JPL-D-32399
DRLE Functional Requirements Doc
JPL-D-32375
DRLE Data Management Plan
JPL-D-32477
DRLE Data Product Specification
JPL-D-32400
LRO Spacecraft Payload Assurance
Implementation Plan
431-PLAN-000131
LRO Mechanical Systems Req’ts
431-RQMT-000183
Thermal Level III Requirements
431-RQMT-000205
Electrical Systems Reqt Doc
431-RQMT-000140
C&DH System Requirements
431-RQMT-000168
C&DH EICD
431-ICD-000141
C & DH MICD/TICD
431-ICD-TBD
LRO Flight Software Rqmt
431-RQMT-000139
LRO Communication
Systems Requirements
431-RQMT-000137
Comm System EICD
431-ICD-000146
RF ICD Between LRO and the Lunar
Network
451-RFICD-LRO/LN
Flight Dynamics Specification
431-SPEC-000184
LRO GNC ACS Spec
431-SPEC-000162
LRO PROP Subsystem SOW &
SPEC
431-PROP-000017
Propulsion to Spacecraft EICD
431-ICD-000147
Propulsion to Spacecraft MICD
431-ICD-TBD
LRO Electrical Power Subsystem
Spec
431-SPEC-000013
Power Subsystem Electronics EICD
431-ICD-000142
Solay Array EICD
431-ICD-000150
Battery EICD
431-ICD-000151
Mini RF Electrical ICD
431-ICD-000152
Mini RF Data ICD
431-ICD-000160
Mini RF TICD
431-ICD-000159
Mini RF Mechanical ICD
431-ICD-000158
Mini RF PAIP
431-PLAN-000181
Detailed Mission Reqt (DMR) for
LRO Ground System
431-RQMT-000048
LRO Ground System ICD
431-ICD-000049 CRaTER Data ICD
431-ICD-000104
LAMP Data ICD
431-ICD-000106
LROC Data ICD
431-ICD-000109
LEND Data ICD
431-ICD-000107
DLRE Data ICD
431-ICD-000105
LOLA Data ICD
431-ICD-000108
CRaTER TICD
431-ICD-000118
LAMP TICD
431-ICD-000115
LROC TICD
431-ICD-000114
LEND TICD
431-ICD-000119
DLRE TICD
431-ICD-000116
LOLA TICD
431-ICD-000117
CRaTER Mechanical ICD
431-ICD-000085
LAMP Mechanical ICD
431-ICD-000087
LROC Mechanical ICD
431-ICD-000090
LEND Mechanical ICD
431-ICD-000088
DLRE Mechanical ICD
431-ICD-000086
LOLA Mechanical ICD
431-ICD-000089
CRaTER PAIP
32-01204
LAMP PAIP
PAIP-05-15-11239
LROC PAIP
MSSS-LROC-7001
LEND PAIP
LEND PAIP 01
DLRE PAIP
JPL-D-31796
LOLA PAIP
LOLA-PLAN-0003
8/12/2005
LAMP Instrument Requirements
LAMP IRD
11239-IRD-01
LAMP Data Management Plan
11239-DMP-01
CRaTER Instrument Requirements
CRaTER IRD
32-01205 01
CRaTER Data Management Plan
LOLA Instrument Requirements
LOLA Science & Functional RD
LOLA-RQMT-00002
LOLA Data Management Plan
LOLA-PLAN-00005
LEND Instrument Requirements
LEND IRD
LEND IRD 01
LEND Data Management Plan
LEND DMP 01
Instrument Requirements
LROC IRD
MSSS-LROC-001
LROC Data Management Plan
MSSS-LROC-010
RESOURCE ALLOCATIONS
LRO Pointing & Alignment Alloc
431-SPEC-000113
LRO Tech Resoures Alloc
431-SPEC-000112
20
LRO Overview
Back-Ups
21
LRO Timeline to Confirmation
Instrument
Selection
Project Funded
InstrumentK.O. Mtg.
1/05 2/05 3/05 4/05 5/05 7/056/05 8/05 9/05
InstrumentAccommodation
Rvw.
Instrument ContractAwards
Mission SRR
Requirements Definition & Preliminary Design
Level 1Requirements
Baselined
LEND US-Russian Implementing Agree draft into HQ-State Dept. review.
10/05 11/05 12/05
IPDRs
Mission PDR
IBR
NAR
Baseline Establishment Phase C/D/E
Ground SRR
22
LRO Lifecycle Cost Estimate
• LRO LCC estimate is in process.
Initial Cost Estimate ($M)
Management & Sys. Engr. 25
Spacecraft 120
Instruments
CRaTER 6.8
Diviner 11.9
LAMP 5.5
LEND 5.1
LOLA 19.7
LROC 17.3
Launch Vehicle 90
Ground Network/MOC & Mission Ops. 39
I&T 11
Reserve 56
Total 407
Initial Guiding Boundary Conditions• 2008 launch•Delta II class LV•Accommodate Investigations sought
by ORDT/AO• $400M cost target put forth in FAD
Conceptual Cost Estimates• Parametric estimate based on historical
data for recent mission with similarities• Application of simple CERsby Project
Initial Grassroots Estimates• Done at subsystem level
-Subsystem estimates experience based- Instruments per AO
LCC estimate for Confirmation Process• Results from reconciliation of Grassroots
& RAO estimates. Reviewed by GSFC PMC
Refined Grassroots Estimates• Done at subsystem level
-Subsystem estimates prelim. design based- Instruments per proposals, C/D/E contracts
In Progress
GSFC RAO Cost Modeling• Mission input data defined/delivered
by Project
In Progress
POP 05
POP 06
“Discovery Class”Initial Guiding Boundary Conditions• 2008 launch•Delta II class LV•Accommodate Investigations sought
by ORDT/AO• $400M cost target put forth in FAD
Conceptual Cost Estimates• Parametric estimate based on historical
data for recent mission with similarities• Application of simple CERsby Project
Initial Grassroots Estimates• Done at subsystem level
-Subsystem estimates experience based- Instruments per AO
LCC estimate for Confirmation Process• Results from reconciliation of Grassroots
& RAO estimates. Reviewed by GSFC PMC
Refined Grassroots Estimates• Done at subsystem level
-Subsystem estimates prelim. design based- Instruments per proposals, C/D/E contracts
In Progress
GSFC RAO Cost Modeling• Mission input data defined/delivered
by Project
In Progress
POP 05
POP 06
“Discovery Class”