1
Key Priorities
Root Causes Actions Action By Start
Date
Target Completion Date
Remarks
Carpet stain
Carpet stained (Light color carpet- easily stained) (GM/RDM/QCI performed physical room check end of Mar)
1. Spot cleaning / shampooing of stained carpet (183 rooms identified from the 275 rooms checked)
2. To patch for carpet that cannot remove by cleaning/ shampooing
3. Consult with IHG designer to see if entrance area of room to be change to darker color carpet
4. Conduct next 275 rooms audit
HK Supervisor
Executive Housekeeper
GM
GM/RDM/QCI
24 May
1 Jun
25 May
2 Aug
31 May
9 July
31 May
7 Aug
Based on findings from rooms audit, priority list was created & concern department started to work on it(See attached list -Completed)
Some room not completed due to fully booked situation in Jun
Awaiting reply from Paul Reyburn (See attached email)
HIM: 2010, Q1 GSTS Action PlanningAttractiveness of Guest Room (77.3 ; 1.0)
2
Priority list ( Carpet stain)
3
Email correspondence with Paul Reyburn
4
Key Priorities
Root Causes Actions Action By Start
Date
Target Completio
n Date
Remarks
Wall stained / scratch
I-Interview
Wall stained /scratch (GM/RDM/QCI performed physical room check end of Mar)
Pervious I interview form too general
To fix the wall plaster andre-paint if necessary
Improved Interview form,to get more specificinformation about “Attractiveness of GuestRoom”. Launched on 1 Jun,& brief to auditors
Maintenance Supervisor
QCIM
17 May
1 Jun
9 July
4 Jun(Ongoing)
(See attached list) Some room not completed due to fully booked situation in Jun
Based on Janet comment ( see attachment)
HIM: 2010, Q1 GSTS Action PlanningAttractiveness of Guest Room (77.3 ; 1.0)
5
Priority List ( Wall stain)
6
Revised I –Interview Form
7
Key Priorities
Root Causes Actions Action By Start
Date
Target Completio
n Date
Remarks
External laundry
Outsourced Laundry did not consistently provide clean linen. (I-Interview feedback mostly on linen issue only)
1. Meeting was held with Mr.Azman ( Owner of Azman Laundry ) and GM/RDM/QCIM :
a) Both parties agreed that QCIM will audit laundry flow and HIM flow, and come out with flow chart
b) Base on flow chart analysis, both parties agreed to appoint and train HIM linen staff to be placed at the laundry site for quality control.
c) Daily reporting and review weekly by RDM/ GM on linen rejection rate ( max 5%) and reject reasons
d) EHK to report daily and review weekly by RDM/GM for number of accumulated reject linen (to be sent for special treatment)
QCIM
QCIM/ Executive Housekeeper
Executive Housekeeper /RDM/GM
Executive Housekeeper/RDM/GM
11 May
1 Jun
1 Jun
1 July
17 May
5 Jun
Ongoing
Ongoing
HIM: 2010, Q1 GSTS Action Planning Attractiveness of Guest Room (77.3 ; 1.0)
8
Key Priorities
Root Causes Actions Action By Start
Date
Target Completio
n Date
Remarks
Linen par level
Communication with suppliers
Red zone (Linen handling area)
Par level and laundry quality was not monitored
No regular communication with Azman and Ecolab
Contamination of linen during handling process
1. Linen was checked and beefed up before thebusy period during endof May( borrowed 100king and 250 twin bedsheet from HIGL) , in anticipation of busy schoolholiday period.
2. Monthly reporting ofpar levels ( to be signedoff by RDM /EHK min par levels 3.5)
Weekly review meeting
Improve Red zone area byputting fencingand surface protection(e.g. canvas on floor )
Executive Housekeeper
Executive Housekeeper/RDM
Executive Housekeeper/QCIM/Azman /Ecolab/RDM/GM
Executive Housekeeper
31 May
1 Jun
1 Jul
31 May
4 Jun
30 Jun (Ongoing monthly)
Weekly
4 Jun
Additional linen ordered expected to arrive end of Jun
Monthly Inventory
HIM: 2010, Q1 GSTS Action Planning Attractiveness of Guest Room (77.3 ; 1.0)