1. Items Announced in Budget 10-11
2. Gauge Conversion in NGP Divn.
3. Targeted works 2010-11.
ON GOING PROJECTS
DOUBLING
• Item No. 116 ( XXIX) of Budget Speech• Durg – Rajnandgaon 3rd line ( 30.889 Km)
STATUS• Cost of project - `147.06 Crores. • Budget Grant - `10.00 Crores. for 2010-11 • Detailed estimate sanctioned in Oct. 10.
Items Announced in Budget 10-11
Contd…
New Gauge Conversion works
• Item No 115 (i) Budget speech• Chhindwara -Nainpur – Mandla Fort (182.25 Km)
STATUS• Cost of project - ` 556.54 Crores. • Budget Grant for 10 - 11: ` 1.00 Crores.• Detailed part estimate of NIR - MFR for ` 145.8 Cr.
Prepared.
Contd…
Completed Gauge Conversion Project
• Item No 113 (x) of Budget speech– Gondia - Balaghat including MOIL siding
(42+7 Km) section commissioned in year 2005
– Balaghat - Katangi [46.8] - Section completed & commissioned on 7.05.2010
Contd…
New line Project• Item No 111 of Budget speech• Mandir Hasaud - Naya Raipur (20.00
Km) sanctioned as material modification to Raipur – Titlagarh doubling of East Coast Railway
• Cost of project - ` 77.32 Crores. • Budget Grant for 2010-11 – Nil• Part estimate for ` 28 Lakhs. for preliminary
activities sanctioned by GM/SECR.
Contd…
Updating of Socially Desirable Rail Connectivity Proposals
• Item No 102 of Budget speech (Sr. No.10)
• Barwadih- Chirimiri / Ambikapur [182km]
• RET Survey report submitted on 17.05.03 for ` 406.86 Crs. with ROR (-) 4.85%. Updating done on 16.2.09. with ROR (-) 9.05%. Board again desired for updating. Updated estimate under finance vetting..
Contd…
Updating of proposals
Lohardaga-Korba (326 Km.) (via Dharmjaygarh & Pathalgaon)
• Item No 102 of Budget speech (Sl No. 63)
• Report Submitted to Rly. Board in 2003.• Cost ` 621.67 crores & ROR (+) 07.25
%.• Updated estimate under calculation of
ROR.
Contd…
Updating of proposals Pendra Road –Korba/Gevra Rd. (121.7 Km.)
(via Pasan, Sundargarh & Deepika)
• Item No 102 of Budget speech (Sl. No. 82)
• PET survey sanctioned in 1996-97.
• Report submitted to Board in 2003.
• Cost ` 344.43 Crores & ROR (+)15.23%.
• Updated estimate under finance vetting.
Contd…
Updating of proposals Raigarh - Mand Colliery to Bhupdeopur
(63 Km. with Fly over)
• Item No 102 of Budget speech (Sl. No. 88)
• PET survey sanctioned in 2008-09.
• Report submitted to Railway Board in July -2009 at the cost of ` 310.64 Crores & ROR (+) 29.58%
• Updated report submitted to Board in Aug. -10 at the cost of ` 344.20 crores and ROR (+) 26.33%
Contd…
Updating of proposals
Raipur – Jharsuguda (310 Km.)(via. Kharotapalan, Baloda Bazar, Bhatgaon & Sarangarh.)• Item No 102 of Budget speech (Sl. No. 89)
• RET survey sanctioned in 1999-2000
• Report submitted to Railway Board in Feb-2003.
• Cost ` 971.96 crores & ROR (-) 20%.
• Updating of abstract estimate is being done.
Contd…
Updating of proposals
Ramtek – Gotegaon (275 Km.)(via Khawasa, Sioni & Dhuma)
• Item No 102 of Budget speech (Sl. No. 92) • RET survey sanctioned in 1995. • Report submitted to Railway Board in April
1999. • Cost `. 528.21 crores & ROR (-) 11.50%• Updating in progress.
Contd…
Updating of proposals
• Item No 118 (i) of Budget speech• Wadsa - Desaiganj - Gadchiroli - 49.5 Km
(Cost sharing)• RET survey sanctioned in Aug -1995.• Initial report submitted in July - 1998.• Updated report submitted in Aug - 2010.• Cost ` 232.40 crores & ROR without sharing
(-) 3.88% & with 50% cost sharing by State Govt. ROR (-) 0.40%
Gauge conversion in
NGP division
Section Blocking Opening
(a) JBP - Sukrimangla (43.41km) Oct-2011 June-2012
(b) Sukrimangla-Nainpur (70.1 km)* Oct-2012 June-2013
* Subject to acquisition of forest land in Seoni Distt.
(c) Nainpur – Mandla Fort (42.2 Km.) Oct -2012 June -2013
Planning of N.G. conversion in NGP Divn.
Contd.
Section Blocking Opening
(d) Nainpur - Balaghat (75.4 Km.)* Dec -2012 Dec-2013
* Subject to acquisition of forest land in Balaghat Distt.
(e) NGP - Ramakona (86 Km.) Oct-2012 June-2013
(f) Ramakona - CWA (64 Km.) Jan -2013 Dec – 2013
(g) Nainpur - Seoni (76 Km.) Dec - 2013 Dec-2014
(h) Seoni - Chhindwara (64 Km.) Dec – 2014 Dec - 2015
Progress of Major ItemsJabalpur – Nainpur - Balaghat
Sr. No Items Scope Progress
1.Earth work
(Lakh Cum.)108 40%
2.Major Bridges (Nos.)
49 60%
3.Minor Bridges (Nos.)
313 54%
Progress of Major ItemsJabalpur - Sukarimangla
Sr. No Items Scope Progress
1.Earth work
(Lakh Cum.)14 66%
2.Major Bridges (Nos.)
15 65%
3.Minor Bridges (Nos.)
82 68%
Contd.
Progress of Major ItemsNagpur - Chhindwara
Sr. No
Items Scope Progress
1.Earth work
(Lakh Cum.)99.23
20% work completed. Agency available for 27 Lakh. Cum.
2.
Major Bridges (Nos.)
(a) Sub - Structure 27Completed - 12
In progress – 15
(b) Super - Structure (Nos.)
87 steel girders
W/O placed on MMR/WS and trade. 42 girders received, launching of girders taken up.
Contd.
Sr. No
Items Scope Progress
3.Minor Bridges (Nos.)
254
36 - completed.
169 - Segments casted. Launching in mega block.
44 - In progress.
5 - To be closed.
4. Tunnel 2 Tender under finalization.
Contd.
Targeted works 2010-11Name of work PH Prog. Remarks
Champa – Bye Pass 15 20% Delaying due to non-acquisition of land
Rebuilding of Bridge NO. 99
32 98% Commissioning delaying due to non shifting of HT by CSEB
ROB at Uslapur 30 82% Work in progress
ROB at Raigarh – Kotarlia
30 50% Work in progress
ROB at Raipur – Baloda Bazar
30 90% Work in progress
Name of work PH Prog. Remarks
ROB at KM 867/7-8 at Durg over DRZ line.
Deposit work
90%Work in progress.
USL – Development of Model Goods Shed.
16 100% Completed.
RSD - Raipur development of goods shed.
16 100% Completed.
Jharridih – Additional Dn loop.
16 100%Completed.
Himgir – Additional Up loop. 16 87%Work in progress.
Contd…
Name of work PH Prog Remarks
(a) KDTR – Remodeling for dealing with addl. traffic of JSPL siding.
(b) KDTR – Addl. Loop.
16
85%
95%
Work in progress
Work in progress
Bhilai – Relocation of ART/ARME train
16 96% Work in progress, GJ work being done by Div.
BRJN – Ext.of Dn island platform for 24/26 coaches.
16 98% Completed for 24 coach length.
Contd…
Name of work PH Prog. Remarks
Durg – Development of goods shed by providing common loop.
16 96%
Goods shed work completed. Signaling work to be taken up as per revision.
BSP – Renovation of pit line NO. 1 & 2 of coaching pit line.
42 55% Work in progress
Bhilai Peripheral Yard – Impro. in freight exam. Facility.
42100%
Completed.
Contd…
Name of work PH Prog. Remarks
Bhilai Elect. Loco Shed – Aug. of homing capacity from 150 to 175
42 100% Completed.
BSP – Replacement of W. A. on line No. 1 & Extension of PF No. – 4
42 100% Completed.
BSP – Replacement of W. A. on PF No. 3 & Extension of WA on PF No. - 2
42 50%Work in
progress.
Contd…
Description PB/OB/LB
Prog Remarks
BSP-142 units type-II
PB/242 100% Completed.
Raipur-96 type-II PB/245 36% Work in progress. 48 Qtrs. by Mar-11.
Raipur-11 type-V & 20 type-IV
PB/248 34% Work in progress. All type - V by Mar-11
Raigarh- 10 type-II, 15 type-III
LB/672 100% Completed.
PROGRESS OF QUARTERS
Description PB/OB/LB
Prog Remarks
BSP-Replacement of out house 50 units
LB/270 85%Work is in progress.
BSP-Replacement of type-I 50 units
LB/271 85%Work is in progress.
Contd.
THANK YOU
WORKS COMPLETED IN
2009 -10 & 2010 -11 (PB)
Sr. No.
Name of workSanc. Year
Completed Month
1. Jamga – Addl. Up loop. 07-08 July-09
2. IB – Addl. Dn loop. 07-08 Sep-09
3.Parmalkasa – Conversion of “C” class stn. into “B” class with 4 lines.
05-06 Oct-09
Sr. No.
Name of workSanc. Year
Completed Month
4. Salva - Conversion of “C” class stn. into “B” class with 4 lines.
06-07 Nov-09
5. Belpahar – Addl. Dn loop. 07-08 Dec-09
6. Uslapur – Development of model goods shed.
05-06 Apr-10
7. Raipur – Store depot. Development of goods shed.
08-09 June-10
8. Jharradih – Addl. Loop line. 05-06 Aug-10
9. Bhilai – Jamul cement siding Electrification including yard.
07-08 Feb-10
Contd.
Sr. No.
Name of workSanc. Year
Status
1. BSP : Extn. Of existing shunting neck by 180m at coaching depot.
04-05 Completed
2. BEF : Development of full rake handling point.
07-08 Completed
3. JRMG : Development of full rake handling point.
07-08 Completed
STATUS OF LAW BOOK WORKS
Sr. No
Name of workSanc. Year
Status
4. MXA: Provision of dispatch signal for line No. 5, 6 & 7 towards ore yard and for line No. 2, 3 & 4 towards DUG and DRG.
06-07 Completed
5. Surakachar : Electrification of Siding.
06-07 Completed
6. BRJN : Electrification of Orient Collieries siding.
06-07 Completed
Contd.
Sr. No.
Name of workSanc. Year
Status
7. Shifting of 04 Nos. of Cross – ovar at JRMG Railway Station.
08-09 Completed
8. RSD : Signaling facility for reception and dispatch for line No. 7
07-08 Clubbed with PI work.
TDC- Mar-11
Contd.
Name of Work Sanc. Year
Anti.
Cost
TDC Prg.
Brajrajnagar – Extension of Dn island platform for 24/26 coaches.
07-08 2.40 Jan-11 98%
Remarks
ESP & IP approved. Slewing of main line and major OHE alterations completed. PF extension work completed except stone surfacing.
In. Crs.WORK IN PROGRESS
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Himgir – Addl. Up loop 07-08 4.46 Jan-11 87%
Remarks
Existing relay room will be used. 100 % E/W, bridge work and ballast supply completed. FOB - 100 % & Linking 60%. OHE - 48 foundation out of 53 done & 28 mast erected, steel received. S & T progress - 80%. CRS sanction obtained.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
1.Kirodimalnagar – Addl. Loop.
2.Kirodimalnagar – Remodeling for dealing with additional traffic of JSPL siding.
06-07
08-09
4.20
6.00
Jan-11
Jan-11
85%
60%
Remarks
Work is planned in two stages.
Stage -I – Up loop and one Dn loop work at KDTR.
Stage – II – 2nd Dn loop.
Connection for all 3 loops planned for simultaneous commissioning to avoid redundant works. CRS sanction awaited. E/W – 95%, Building & Bridge work – 100%, S & T – 95%, Track Linking in progress.
Contd. In Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Bhilai – Relocation of ART/ARME train
08-09 5.41 Jan-11 96%
Completed work
Formation, track, extension of culvert.
Shed (40x12) 140 ton for crane.
S & T goomty (3mx3m) & Inspection pit.
Balance work in progress
Service building for C&W staff – Upto plinth level completed.
SIP & SWR to be revised after ESP alteration due to U/M LC in yard to be
manned & relocation of point.
CRS sanction for D cabin submitted on 20.09.10
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Durg – Development of goods shed by providing common loop & better unloading facilities.
08-09 7.00 Jan-11 96%
Goods platform work nearly completed.
Placement/withdrawal of trains being done from BSP end.
Connectivity from NGP end should be done along with 3rd line bet.
Durg – Rajnandgaon to avoid repeated NI and yard modification.
Renovation of existing shed for labour rest room and merchant room
in progress.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Dadhapara – Belha & Urkura – Mandhar (IBS on Up & Dn lines.)
07-08 1.88 Mar-11 65%
Full quantity of cable procured. Electrical work completed. MDH-URK commissioned on 28.7.09.Tender awarded for Dadhapara - Belha section. Work in progress.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Gevra Road – Run through facility.
08-09 6.52 Mar-11 5%
Remarks
Work proposed for dropping.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Mandhar – New goods terminal.
08-09 3.18 NF -
Remarks
ESP Approved. Cost of work is exceeding the abstract estimate substantially. Detailed estimate is under revision.
Contd. In. Crs.
Name of Work Sanc. Year
Anti.Cost
TDC Prog.
Rupond – Addl. Common loop to serve new goods shed.
08-09 3.46 Apr-11 -
Remarks
Scope of work revised. ESP approved. Estimate sanctioned. Civil tender finalised recently. OHE tender finalised. S & T tender opened on 05.02.10 and discharged. Fresh tender opened on 20.08.10 and under finalisation.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
BSP Div. – IBS
(4 location)
08-09 6.00 Jan-11 20%
Detailed estimated sanctioned. Tender awarded & work under progress. SWR’s pending in division.
TDC
Dadhapara - Belha - Oct-10
Jairamnagar - Latia - Nov-10
Gatora - Jairamnagr - Nov-10
BSP - Gatora - Dec-10
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Bhupdeopur – Remodeling for dealing with new pvt. siding.
08-09 10.89 NF -
Remarks
Land acquisition required at JSG end land plan submitted. Revised ESP approved. Land acquisition proceedings stalled. Work to be truncated to avoid land acquisition and revised ESP prepared & under finalisation.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Bhilai – Addl. Freight maintenance depot at coal empty yard with 3 examination lines & one shunting neck of full length.
08-09 19.71 Nov-11 28%
Contd. In. Crs.
S & T and OHE tender finalised. E/W in progress. One high tension tower in the alignment is yet to be dismantled by CSEB.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Bhilai – (Exchange yard) remodeling with 2 addl. loop line by extension of D/End.
09-10 5.95 Feb-12 -
Remarks:-
Scope of work finalised recently by the division. Detailed estimate sanctioned during July- 10. ESP under finalisation.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Himgir – Addl. Dn. Loop. 09-10 5.00 NF -
Remarks:-
ESP approved. Work to be executed with 3rd line.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Jamga – Yard remodeling. 09-10 4.55 NF -
Remarks:-
ESP approved. Work to be executed with 3rd line.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
IB – Addl. Loop. 09-10 4.13 Dec-11 -
Remarks:-
Site details collected. ESP approved. Estimate vetted. Tender to be floated.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Mudaria – Addl. Dn. Loop. 09-10 3.00 NF -
Remarks:-
Heavy cost over runs are noticed in S & T portion of the estimate. Scope of work reviewed and referred to Board.
Contd. In. Crs.
Name of Work Sanc. Year
Anti. Cost
TDC Prog.
Saragbundia – Conversion of goods shed siding into Up loop cum Dn reception line.
09-10 3.13 Oct-11 -
Remarks:-
ESP approved. Estimate under vetting.
In. Crs.
JABALPUR – NAINPUR (113.5 km.) (Non – Electrified section)
This part of the project is falling in Seoni, Mandla & Jabalpur distt. of MP.
Total land acquisition is 344 hec. (Pvt. 261 + Govt. 50 + Forest land 33 hec.)
25 hect of Pvt./Govt. & 30 hect of forest land is balance for acquisition (Seoni district).
One important bridge over Narmada (18 x 30.5 m PSC box) completed.
There are three major detours (Pindarai - Ghansore 20 km, Vinayaki - Shikara 9 km, and Bargi - Kachpura 20.7 km), two minor detours in Shikara – Sukari plus mini diversions at major bridge approaches. Total length of detour alignment is 62 km. Earth Work is progressing in 56 Km length .
Contd.
Item Scope Prog. Remarks
Earth work (Lakh. Cum.)
81 37.53Earth work in 6 km detour portion & in mega block is balance.
Blanketting (Lakh cum.)
7.7 1.54 About 60% qty. to be done in mega-block.
Item Scope Prog. Remarks
Major bridge (Nos.)
33
35%
Tender under finalized for 32bridges.Out of which -
Completed - 3 Br.
In Progress-21Br.
Minor bridge (Nos.)
194 56
Out of 115 bridges located in detour. 53 completed, 65 in progress. Out of 83 in same alignment pre-cast segment completed for 56 bridges & balanced 27 bridges in progress.
Ballast (Cum.)
244000 1413018000 cum taken in Nainpur–Pendarai section. For balance tender to be invited.
Gondia – Jabalpur gauge conversion incl. Balaghat – Katangi (275.20 Km.)
Year of sanction
Anticipated cost.
Exp. Upto Mar-10
2009-10Overall progressExp. Upto
Oct.-10
1996-97 1038.00 453.85 34.48 62%
Gondia – Balaghat section including MOIL siding (42+7 Km) already commissioned.
Balaghat–Katangi section 46.8 km completed. CRS after inspection on 23.02.2010. & section commissioned on 07.05.10
Track Linking – 125 Km. Indent placed for all P. way materials. 12000 Sleepers transported .
JBP-Gwarighat (20km) can be opened in June-2011. Thus abandoning NG alignment from JBP – Gwarighat (9.2 km).
TDC
Contd.
Section Blocking Opening
(a) JBP - Sukrimangla (43.41km) Oct-2011 June-2012
(b) Sukrimangla-Nainpur (70.1 km)* Oct-2012 June-2013
* Subject to acquisition of forest land in Seoni Distt.
(c) Nainpur – Mandla Fort (42.2 Km.) Oct -2012 June -2013
BALAGHAT – NAINPUR (75.41 km. non – electrified section)
I- Section falling in distt. of Balaghat & Mandla in MP state.
II-Acquisition of land
Pvt. & Govt land (50.56 hect.) – nearly 100%.
Mandla distt- 100% (20.60 hect.)
Balaghat distt(75.47 hect) case pending with MOEF since Feb-09 .
Contd.Progress of Major Items as under.
Item Scope Prog. Remarks
Earth work (Lakh. Cum.)
19.0 (Pre.Block) + 9.50 ( in Block)
5.65 Balance Earth work to be done in mega block & in forest area.
Major Bridges (Nos.)
16 70%
3.5 completed.
10 under progress.
1 Bridge falling in forest area.
Item Scope Prog. Remarks
Minor Bridges (Nos.)
119 52%
Pre-cast Segments ready for 19 bridges. For 32 bridges tender finalised & 47 bridges on detour.
Ballast (Cum.) 141100 108000Contract finalised for full quantity. 20% ballast being taken in depot.
Track Linking (In Km.)
80 Km. (Incl. Loop
line)-
65% P. way material arranged.
Contd.
TDC - 30 months after possession of forest land i. e. Oct - 2012. Full 75 Km will be opened in one stretch.
MANDALA FORT- NAINPUR - CHHINDWARA (182.25 Km. Non-Electrified)
The project is being tackled in two phases i. e. (i) Mandla Fort - Nainpur (42.25 Km.) (ii) Nainpur - Chhindwara (140 Km.)
Final location survey of Mandla Fort – Chhindwara completed. Part detailed estimate sent to Rly. Board in May-10.
Tender floated for Major Bridges on 04.10.10. TDC – Dec-2012
Year of sanction
Anticipated cost.
Exp. Upto Mar-10
2009-10Overall progressExp. Upto
Oct-10
2010-11 556.54 - 0 0%
NAINPUR - CHHINDWARA (140 Km. Non-Electrified)
Contd..
Final location completed 50 Km. and balance is under progress.
Detailed estimate will be submitted to Rly. Board by April – 2011.
TDC
Section Blocking Opening
NIR - Seoni (76 Km.) Dec - 13 Dec -14
Seoni – Chhindwara (64 Km.) Dec - 14 Dec - 15
CHHINDWARA – NAGPUR GC (149.52 Km. Non-Electrified)
The project is covering 53 Km. in Nagpur distt. of Maharastra & 96.52 km. in Chhindwara distt. of M.P.
Total land required 328 hec. (128 hec. forest & 200 hect. private/Govt. land. 80% in M. P. & 20% in Maharastra.
2nd stage clearance of MOEF for forest land received on 30.9.09. & trees cutting in progress.
Year of sanction
Anticipated cost.
Exp. Upto Mar-10
2009-10Overall progressExp. Upto
Oct-10
2005-06 585.93 123.23 15.06 23%
Item Scope Prog. Remarks
Earth work (Lakh. Cum.)
95.91 22.08
E/W in progress in six block sections covering 70 km. & including two major bridge approaches.
Major Bridge (Nos.)
27 42%
Sub structure of 12 bridges completed, 12 bridges in progress. Design of 3 bridges in prorgress. 43 fabricated spans received out of 87.
Contd.
Item Scope Prog. Remarks
Minor bridge (Nos.)
254 (40 in detour)
-
18 in situ bridges completed. Segmental casting completed for 139 bridges. Out of 40 bridges in detour portion work is in progress on 3 Br. Tender opened for 16 bridges under finalisation.
Segmental 139
Cast in situ 40
Contd.
Tender for 2 tunnels of 750 m & 150 m long opened on 22.03.2010.
Tender for 3 viaducts are invited.
All indents for span of 12.2 m & 18.3 m placed on CEWS/Manmad. 30.5 m spans are being manufactured by agency. Indents for 45.73 m are being placed with modified 25 tonnes loading on CEWS/Manmad.
Ballast - Total requirement 3.36 lac. cum. Tender finalised for the stretch falling in Maharastra State of 0.84Lac cum and 0.85cum for MP.state and progressed 0.58 lac cum.
TDC
Section Blocking Opening
CWA - ULA (25 Km. Dec - 10 June -11
ULA – Saoner (80 Km.) June - 11 June -12
Saoner - NGP (44 Km.) Dec -12 June -13