Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1. INTRODUCTION
This Handbook aims to provide detailed
guidance to investors in the process of
developing and implementing renewable
energy projects, in particular, photovoltaic
power plants. Yet, this Handbook does not offer
an exhaustive, detailed overview. For more
detailed information refer to the relevant
legislation and regulatory acts listed at the end
of this Handbook.
This Handbook contains three parts. The first
part provides an overview of the applicable
support measures for electricity production
from renewable sources, i.e. premiums for
photovoltaic power plants.
The second part provides a detailed diagram of
the construction procedures and the necessary
documentation.
The third part provides a meticulous overview
of the relevant procedures and requirements
for construction, commissioning and operation
of photovoltaic power plants. We advise the
reader to consult this part often as well as the
detailed diagram given in the second part.
At the end of the brochure there is a list of all
competent authorities with their addresses and
contact details, as well as a list of all relevant
laws and other regulatory acts.
NOTE:
This Handbook provides an overview of the
overall process and procedures for the
development and construction of a photovoltaic
power plant, either as a preferential producer
or as an independent producer selling electricity
on the electricity market. However, please note
that the possibility of signing a contract for the
purchase of produced electricity (4.10) is not
available to producers who do not use premium
as a support measure. Also, this Handbook does
not outline the specific conditions and
procedures for obtaining the status of
preferential producer using a feed-in tariff and
the rights of such a preferential producer, since
no feed-in tariffs are awarded to new investors
in photovoltaic power plants formally as of
February 2019.
This Handbook does not address detailed issues
related to:
- The establishment of a company or the
establishment of foreign subsidiaries;
- Obtaining a construction approval,
- Obtaining licenses for professional staff and
other work and social permits,
- Acquisition of land ownership, expropriation
and other property rights,
- Taxation,
- The rules for granting state aid, etc.
However, keep in mind that these are
important issues that every investor should
carefully consider when preparing a
photovoltaic power plant project.
2. OVERVIEW OF APPLICABLE SUPPORT
MEASURES FOR PHOTOVOLTAIC POWER
PLANTS
With the introduction of premiums as a support
measure, the process of awarding feed-in tariffs
for electricity produced by a photovoltaic power
plant to preferential producers has stopped.
Premiums represent an additional fixed amount
of the price that the preferential producer
achieved by selling the produced energy on the
electricity market. The amount of the premium
is determined at an electronic auction and does
not change for the period for which the
premium is awarded. Premiums are regulated in
the Decree on support measures for electricity
production from renewable energy sources
(“Official Gazette of the Republic of Macedonia”
no. 29/2019).
A producer whose photovoltaic power plant
meets the following requirements shall acquire
the status of a preferential producer using a
premium:
1) The installed capacity does not exceed 30
MW,
2) The equipment and facilities for production
of electricity and connection to the electricity
transmission or electricity distribution system
are a technical-technological functional unit and
the power plant has a connection to the
respective system with an independent
metering point, which is exclusively intended
for that power plant, and
3) It was not built on an existing construction,
except for underground line infrastructure, as
defined in the Law on Construction,
The status of a preferential producer that uses a
premium is acquired through a tender
procedure with an auction for granting the right
to use premiums.
The preferential producer shall have the right to
use the premium for the produced electricity
from the photovoltaic power plant in a period
of 15 years from the day of concluding the
contract for premium use.
The total installed capacity of photovoltaic
power plants for which premiums are awarded
for produced and sold electricity is determined
in the Decision on the total installed capacity of
preferential electricity producers (“Official
Gazette of the Republic of Macedonia” no.
29/2019) and currently amounts to 200 MW.
Every year, the Government of the Republic of
North Macedonia (hereinafter: the
Government) adopts a Program for financial
support for electricity production by
preferential producers that use a premium
which provides for:
The total installed capacity of the power
plants by technology type for which a
premium will be awarded after a
conducted tender procedure in the current
year and
The amount of funds required for payment
of premiums for produced and sold
electricity in the current year.
Tender procedures shall be organized and
implemented by the Ministry of Economy. The
Ministry of Economy shall conclude a contract
for the right to premium use with each selected
bidder. If the selected bidder fulfills the
obligations arising from this contract and above
all constructs the photovoltaic power plant
within the set deadline, the contract for
premium use shall be concluded. The premium
shall be paid on the basis of a submitted
monthly invoice for the produced and sold
quantity of electricity, and the funds for
premium payment shall be provided from the
Budget of the Republic of North Macedonia.
3. DETAILED DIAGRAM FOR THE CONSTRUCTION PROCEDURE AND DOCUMENTS
Key:
Duration of the procedure
Construction works
1 Risk 1: Inability to obtain the right to use state land, delays and uncertainty of outcome and costs
2 Risk 2: Inability to obtain the construction approval or unforeseen delays
3 Risk 3: Increased connection costs if it is not possible to connect to the nearest connection
Start of production and selling electricity
Year 1 Year 2 Duration
4. OVERVIEW OF STEPS, PROCEDURES
AND DOCUMENTS
4.1. BASIC REQUIREMENTS: ESTABLISHING A
COMPANY, AUTHORIZATION FOR
CONSTRUCTION AND LICENSE FOR
PERFORMING AN ACTIVITY
Electricity production can be performed by
domestic and foreign legal entities. The legal
entity should be registered in the Trade Register
and the register of other legal entities
maintained by the Central Register of the
Republic of North Macedonia (hereinafter:
Central Register). If the electricity producer uses
a premium, it should be registered as a capital
trading company (a Joint Stock Company or
Limited Liability Company).
If the photovoltaic power plant has a total
installed capacity of less than or equal to 10
MW, it can be built without an “authorization
for construction of new facilities for electricity
production” issued by the Government at the
proposal of the Ministry of Economy (Law on
Energy, Article 52).
Electricity production cannot start without
having obtained a license for performing an
appropriate energy activity issued by the Energy
and Water Services Regulatory Commission of
the Republic of North Macedonia (hereinafter
the Energy Regulatory Commission). The license
for performing an energy activity is issued for a
period of three to 35 years depending on the
type of energy activity, the type and scope of
the obligation to provide public service in
performing the energy activity, the volume of
funds needed to perform the energy activity,
the duration of the right to use/the concession
of the respective energy resource, as well as the
specific request of the energy activity
performer. The usual license period for
electricity production is 35 years. The same
entity may be issued several licenses for
performing one or more energy activities (Law
on Energy, Article 38). The license is issued in
the procedure described in item 4.8.
4.2. LAND USE
If the land plot on which the investor intends to
build a photovoltaic power plant is classified as
agricultural land (arable or uncultivated land,
forests, pastures, etc.), it must be converted
from agricultural to construction land. To this
end, the competent authority, which upon the
request of the investor prepares the
appropriate urban-planning documentation
(Ministry of Transport and Communications or
the municipality), must ask the Ministry of
Agriculture, Forestry and Water Economy to
make permanent conversion of the respective
agricultural land into construction land. (Law on
Agricultural Land, Article 49). The duration of
this procedure, which is implemented through
the information e-urbanism system, shall
depend on the complexity of the preparation
process and the review of the project
documentation. The Government, on the
proposal of the Ministry of Agriculture, Forestry
and Water Economy, shall adopt a decision to
give consent for permanent conversion of
agricultural into construction land. The costs for
providing project documentation and land
conversion shall be borne by the investor.
The investor shall not undertake a conversion
procedure for agricultural land into
construction land in case when in a tender
procedure he is granted the right to use a
premium for electricity production from a
photovoltaic power plant planned to be built on
state land, because in line with the model
according to which tender procedures are
carried out, the conversion is envisaged to be
performed by the competent state authorities
before the onset, during or immediately after
the completion of the tender procedure.
Unless the land plot(s) on which the investor
intends to build a photovoltaic power plant is
not privately owned, the investor shall establish
the right to a long-term lease of state-owned
construction land. Such procedures shall be
carried out by the municipalities, the
municipalities in the City of Skopje and the City
of Skopje, each for its territory or the Ministry
of Transport and Communications as a
competent state authority for performing the
activities related to the management of
construction land owned by the Republic of
North Macedonia (Law on Construction Land,
Articles 46 - 73). The procedures for long-term
lease of state-owned construction land on
which the construction of a photovoltaic power
plant is envisaged by a preferential producer
who has acquired the right to use a premium
through a conducted tender procedure shall be
performed by way of direct agreement.
In case the land plot is privately owned, the
investor and the landowner can jointly agree on
the alienation, the long-term lease or the right
to land use.
4.3. ELABORATE FOR ENVIRONMENTAL
PROTECTION
It should be taken into consideration that
photovoltaic power plants are subject to the
requirements for preparation and submission of
an Elaborate for environmental protection.
Hence, photovoltaic power plants cannot be
built before the approval of the Elaborate in
accordance with the Law on Environment.
The elaborate for environmental protection for
activities performed on a larger scale shall
contain the following aspects and shall be
structured as follows:
1) General data;
2) Type of elaborate;
3) Authority responsible for approving the
elaborate;
4) Description of the project in which the
activity is performed;
5) Description of the environment around the
project location;
6) Impact of the project on the environment;
7) Environmental protection program;
8) Conclusion;
9) List of attachments;
10) Statement.
Any investor in a photovoltaic power plant shall
submit the prepared Elaborate to the
Directorate of Environment, a body within the
Ministry of Environment and Physical Planning.
4.4. CONSTRUCTION APPROVAL
To build a photovoltaic power plant a
construction approval is required. The
municipality on whose territory the
photovoltaic power plant is planned to be
constructed shall be responsible for issuing a
construction approval if the power plant has an
installed capacity of up to 1 MW, while the
Ministry of Transport and Communications shall
be responsible for issuing a construction
approval for photovoltaic power plants with
installed capacity over 1 MW (Law on
Construction, Articles 57, 58).
The following documents must be submitted
along with the application for a construction
approval:
- architectural-urban project certified by a
competent body, if the urban plan or urban-
planning documentation envisages
preparation of this project, i.e. infrastructure
project, if the application refers to line
infrastructure constructions,
- Basic design (revised and approved),
- Proof of construction right (ownership, right
of use, long-term lease, concession),
- Geodetic elaborate on the numerical data for
the construction land,
- Authorization for construction of facilities for
production of electricity, if the photovoltaic
power plant has an installed capacity above
10 MW.
The municipality, or the Ministry of Transport
and Communications, depending on the case,
shall be obliged to review the documents and
adopt a decision for granting a construction
approval within 15 days from the day of
submitting the complete and accurate
documentation. During the review of the
application, the competent authority shall
submit the application for inspection of the
basic design to the entities responsible for
electricity, water supply and sewage
infrastructure. The entity in charge of electricity
infrastructure shall be obliged within five days
from the day of receiving the request for
inspection to examine the basic design and
submit an opinion on whether the facility can
be connected to the appropriate power system.
Before obtaining the construction approval, the
applicant must pay the construction land
arrangement fee. The construction approval
shall be issued within five working days from
submitting the proof of the paid construction
land arrangement fee.
The application for obtaining a construction
approval shall be submitted and the
construction approval shall be issued in
electronic form, through the information e-
construction approval system.
The construction approval shall cease to be
valid if the applicant does not start construction
within 2 (two) years, or does not complete the
construction within 10 (ten) years, in both cases
counted from the day when the construction
approval became valid (Law on Construction,
Articles 66- 68).
4.5. CONSENT FOR CONNECTION TO THE
DISTRIBUTION SYSTEM
Energy production facilities with an installed
capacity of up to 10 MW are usually connected
to the electricity distribution network.
Therefore, the consent for connection of the
photovoltaic power plants to the electricity
distribution network should be obtained from
the electricity distribution system operator
(EVN Macedonia).
The application for consent for connection shall
be submitted after obtaining the construction
approval, and in practice it is usually submitted
in the initial phase of the construction works.
The application shall be submitted to EVN
Macedonia on form BSP-2, which can be found
in the customer energy centers of EVN
Macedonia or downloaded from the website of
EVN Macedonia (https://evn.mk/Business-
customers/New-connection-fo-distributed-
producers.aspx).
The following documents shall be submitted in
addition to the application:
- Decision for enrollment in the Central
Register with current balance,
- Basic design for the production plant
subject to connection to the distribution
network,
- Excerpt from the cadastral plan with
drawn existing facilities,
- Construction approval,
- Coordinates of the location where the
production plant is to be installed, and
- Technical characteristics of the production
plant in accordance with the Grid Code for
Electricity Distribution.
EVN Macedonia shall be obliged to adopt a
Decision for consent for connection to the
electricity distribution system within 40 days
from the day of receiving the complete
application. The issuance of the Decision for
consent for connection to the electricity
distribution system shall be followed by signing
an Agreement for connection to the distribution
network prepared by EVN Macedonia, which is
an annex to the Grid Code for Electricity
Distribution, both previously approved by the
Energy Regulatory Commission.
The fee for connection of an electricity
producer to the distribution network shall be
defined in accordance with the Methodology
for the manner of determining the fee for
connection to the electricity distribution
network, which is given in addition to the Grid
Code for Electricity Distribution.
The connection costs, as determined by EVN
Macedonia, shall be respectively borne by the
investor, and EVN Macedonia shall be obliged
to install a measuring device at its own expense.
Having in mind the cases in which a
photovoltaic power plant cannot be safely
connected to the nearest connection point, we
advise the investors to check with EVN
Macedonia where their actual connection point
will be and to make an estimate of the costs for
constructing the connection.
The connection point and the amount of the
connection fee for the electricity distribution
network of a preferential producer of electricity
produced by a photovoltaic power plant that
has acquired the right to use a premium after a
conducted tender procedure are determined in
the tender documentation. This benefit can be
used only by those preferential producers that
will build a photovoltaic power plant on state-
owned construction land determined by the
Ministry of Economy.
4.6. DESIGN AND EXECUTION OF THE
CONNECTION
After receiving the Decision for consent for
connection to the distribution network, the user
shall be obliged to conclude an agreement for
design and/or construction of a connection to
the connection point. If the investor has been
issued a Decision for consent for a non-standard
connection, i.e. connection for an isolated user
or if the connection is planned to be used
exclusively for a power plant facility, the
investor may decide that the connection is to be
designed and constructed by:
- EVN Macedonia, or
- An authorized legal entity from the list of
legal entities with which the distribution
system user can conclude an agreement for
designing an external connection previously
selected at a public bid by EVN Macedonia.
If EVN Macedonia determines that the non-
standard connection can be used by several
future users, the connection shall be designed
and constructed by EVN. In that case, the
investor shall pay an amount equal to the
product of the total value of the non-standard
connection and the quotient between the
approved maximum simultaneous capacity
assigned to the investor and the total estimated
installed active capacity of the connection.
The investor shall fully bear the costs for design
and/or construction of the connection,
calculated in accordance with the Methodology
for determining the costs for connection to the
distribution system, which is an integral part of
the Grid Code for Electricity Distribution
4.7. COMMISSIONING
Depending on the installed capacity of the
photovoltaic power plant, commissioning shall
be performed after receiving:
- An approval for use or report for performed
technical inspection by the supervising
engineer, and
- A decision for commissioning of the
technical equipment adopted by the State
Inspectorate for technical inspection.
In case of a photovoltaic power plant with
installed capacity of up to 1 MW, the power
plant shall be commissioned based on the
report of the technical inspection of the
authorized supervising engineer, which has
been previously submitted to the municipality
along with a geodetic elaborate of a completed
survey and proof of paid costs for registration of
the facility in the public books of real estate
(Law on Construction, Article 89).
The approval for use of a photovoltaic power
plant with installed capacity of over 1 MW shall
be issued by the Ministry of Transport and
Communications based on the basic design (or
the design of the constructed condition if during
the construction, there have been major
changes), a report from the technical inspection
and an excerpt from the Real Estate Cadastre as
proof of ownership or other rights of use of the
facility (Law on Construction, Article 87). In case
of incomplete application for approval for use,
the Ministry of Transport and Communications
shall instruct the applicant to submit complete
and appropriate documentation within 7
(seven) days from receiving the application for
approval for use.
A commission composed of three authorized
supervising engineers appointed by the Ministry
of Transport and Communications shall perform
a technical inspection of the facility within 15
days from the date of receiving the complete
application for approval for use.
The commission, or the supervising engineer,
respectively, shall confirm that the facility is:
- built in accordance with the basic design or
in case of changes during the construction,
the design of the completed condition and
the construction approval, and
- safe and can be used.
If the commission or the supervising engineer,
accordingly, determines any shortages that
impair the mechanical resistance, stability and
seismic protection of the facility, it can ask the
investor to correct these aspects within 30 days,
or it can propose not to issue an approval for
use (Law on Construction, Article 90).
In case of a positive report by the commission,
the Ministry of Transport and Communications
shall be obliged to issue an approval for use
within 15 days from the date of technical
inspection of the facility. The costs for
performing the technical inspection and issuing
the approval for use shall be borne by the
investor.
4.8. LICENSE FOR ELECTRICITY PRODUCTION
The requirements for issuing a license for
production of electricity from renewable
sources are stated in the Law on Energy and the
Rulebook on Licenses adopted by the Energy
Regulatory Commission. The investor may
request to be issued a temporary license for
electricity production from renewable sources
by the Energy Regulatory Commission before
receiving the report for a completed technical
inspection by a supervising engineer or the
approval for use if:
The investor has provided authorization
for construction of the energy facility; or
The investor has obtained a construction
approval for the facility in case the
construction of the facility does not
require an authorization for construction,
or
The investor of the energy facility has
acquired the right to build a facility on the
basis of a procedure conducted by means
of a public call for construction of facilities
for electricity production, or
The investor acquired the right to build the
facility on the basis of a granted
concession or a concluded public-private
partnership agreement.
In order to prove that it meets the general
requirements as well as the requirements
regarding the financial situation, the absence of
legal obstacles for performing the activity and
technical qualifications, the investor shall
submit the following documents to the Energy
Regulatory Commission along with the
application for issuing a license:
Statement for reliability of the data and
the attached documentation signed by the
authorized person,
Proof of paid fee for issuing a license in the
amount of EUR 500,
Current balance issued by the Central
Registry,
History with changes issued by the Central
Register,
Property sheet as proof of the right of
ownership or the right of use issued by the
Agency for Real Estate Cadastre,
Concession agreement or public-private
partnership if the activity is performed
using natural resources, that is, proof of
the right to use natural wealth in
accordance with the law,
The organizational structure of the
applicant, including information on the
number of employees, education and
professional training of the persons who
will manage the energy facility and directly
operate the equipment;
Construction approval,
Basic design,
If the facility is built, approval for using the
energy facility or report for performed
technical inspection, or an approval for
commissioning the facility,
Authorization for construction of a facility
for production of electricity, in case the
construction of the facility is subject to
such a requirement,
Document for installation of measuring
equipment,
Decision for consent for connection to the
distribution network;
Information on the economic and financial
status of the applicant issued by the
Central Register,
Certificate for paid taxes, contributions
and other public taxes issued by the Public
Revenue Office,
Confirmation that no bankruptcy or
liquidation procedure has been initiated
against the applicant,
Certificate from the Central Register or a
certificate from the basic court that no
misdemeanor sanction of prohibition to
perform a profession, activity or duty has
been imposed against the applicant,
Certificate from the Central Register or a
certificate from the basic court that the
applicant and the authorized person have
not been pronounced a misdemeanor
sanction - ban on performing a profession,
activity and duty,
Information from the Central Register or a
certificate from a basic court that no
decision has been made against the
applicant for a crime committed on the
territory of the Republic of North
Macedonia.
In case the application and the attached
documentation are incomplete, the Energy
Regulatory Commission shall oblige the
applicant to eliminate the identified shortages
within 20 days.
Following the announcement of the submitted
application, the Energy Regulatory Commission
shall schedule a preparatory session to be held
within 30 days from the date of receiving the
complete application. If the Energy Regulatory
Commission determines from the preparatory
session, as well as from the documentation,
that the conditions for issuing the license are
met, it shall schedule a regular session within 10
days to make a decision on issuing a license.
The Energy Regulatory Commission shall publish
the decision in the “Official Gazette of the
Republic of North Macedonia” and on its
Website.
If a license has been requested for a
photovoltaic power plant that does not yet
have an approval for use or a report for
performed technical inspection, the Energy
Regulatory Commission may decide to issue a
temporary license.
At the request of the investor, the Energy
Regulatory Commission, within seven days from
the day of receiving the application, shall issue a
license for trial operation of the energy facility
through which it should perform the activity.
The holder of the trial work license, for the
duration of the trial work license shall have all
the rights and obligations in relation to the
operation of the facility, as if he were a license
holder. The trial license allows the holder-
producer to produce and sell electricity before
concluding the contract for premium use with
the Ministry of Economy.
4.9. ENROLLMENT OF THE FACILITY IN THE
REGISTER OF POWER PLANTS WHICH PRODUCE
ELECTRICITY FROM RENEWABLE ENERGY
SOURCES
The investor must enroll the photovoltaic plant
in the Register of Power Plants which Produce
Electricity from Renewable Energy Sources
(hereinafter: the Register) maintained by the
Energy Agency. To that end, the investor shall
submit a request to the Energy Agency for
enrollment in the Register along with the
following documents:
1. Approval for using the energy facility or a
report for performed technical inspection,
in case when approval for use is not
required,
2. Agreement for connection with the
operator of the electricity distribution
system with a document - control at the
metering point, i.e. agreement for using the
transmission network concluded with the
electricity transmission system operator,
3. A topographic map with a scale of 1:25,000
showing the location of the photovoltaic
power plant, and
4. Status of the photovoltaic power plant and
a schematic representation of the basic
equipment, including a display of the
measuring equipment (Rulebook on
renewable energy sources, Article 19).
If the Energy Agency, based on the request and
the accompanying documentation, as well as
based on the inspection, determines that there
are no obstacles for enrollment in the Register,
it shall make a decision for enrollment of the
power plant in the Register within 30 days from
the date of submitting the request. The Energy
Agency shall submit to the investor the decision
for enrollment in the Register within three days
from the date of adopting the decision. The
investor shall be assigned a unique registration
serial number that cannot be changed or
transferred (Rulebook on Renewable Energy
Sources, Article 20).
4.10 SHARE IN THE ELECTRICITY MARKET
Any producer not using a preferential tariff shall
be obliged to:
sell the produced energy on the electricity
market,
be registered as a participant in the
wholesale electricity market in accordance
with the Electricity Market Rules and
assume balancing responsibility in
accordance with the Rules for balancing
the power system, unless it uses a
premium and concludes a contract for
purchase and sale of produced electricity
with the buyer in the last resort, in which
case the buyer is ultimately the
responsible party.
Additionally, the preferential producer using
the premium shall be obliged to submit
estimates for electricity production to the
Ministry of Economy in the periods determined
in the Contract for premium use and during the
operation to adhere to the obligations outlined
in the Contract for premium use.
4.10. CONTRACT FOR PURCHASE OF
ELECTRICITY WITH BUYER OF ELECTRICITY IN
THE LAST RESORT
If the premium producer using a premium fails
to conclude a contract for the sale of produced
electricity on the wholesale electricity market, it
may conclude a contract for the sale of
electricity with a trader or an electricity supplier
(buyer of electricity in the last resort) selected
by the Ministry, following a previously
conducted tender procedure by means of a
public announcement (Decree on support
measures to support for electricity production
from renewable energy sources, Article 13). The
buyer of electricity in the last resort shall be
selected for a period of 5 years; a period in
which preferential producers can request
before the beginning of each calendar year to
conclude an agreement with the buyer in the
last resort, thus ensuring a reliable placement
of the produced energy. The manner of
calculating the purchase price shall be
determined in the tender documentation for
selection of a buyer in the last resort, i.e. it shall
be known to the producers even before the
conclusion of the annual bilateral purchase
contracts.
At the same time, the buyer in the last resort is
a balance responsible party that must not
charge the preferential producer fees for
balancing the deviation from the announced
daily physical schedules for delivered electricity
which does not exceed the percentage of the
hourly level specified in the contract (in the
current contract that percentage amounts to
15% on an hourly level).
5. ADDRESSES AND CONTACT DETAILS OF
RELEVANT INSTITUTIONS
5.1 Ministry of Economy, Energy Sector Address: Jurij Gagarin no. 15 (floor 1) 1000 Skopje Telephone: + 389 2 30 93 485, + 389 2 30 93 485 Е-mail: [email protected] Webpage: www.economy.gov.mk 5.2. Energy Agency Address: Orce Nikolov no. 68 1000 Skopje Telephone: + 389 2 32 30 300 Е-mail: [email protected] Webpage: [email protected] 5.3. Energy and Water Services Regulatory Commission Address: Dimitrie Chupovski no. 2, Floor 4 1000 Skopje Telephone: + 389 2 32 33 580, + 389 2 32 54 010 Е-mail: [email protected] Webpage: www.erc.org.mk 5.4. Electricity Transmission System Operator of Macedonia (MEPSO) Address: Maksim Gorki no. 4 1000 Skopje Telephone: + 389 2 31 49 811 Е-mail: [email protected] Webpage: www.mepso.com.mk
5.5. Electricity market operator МЕМО Address: Maksim Gorki no. 4 1000 Skopje Telephone: + 389 2 31 49 805 Е-mail: [email protected] Webpage: www.memo.mk 5.6. Electricity distribution operator/energy supply system (EVN Macedonia) Address: 11 Oktomvri no. 9 1000 Skopje Telephone: + 389 2 3205 000, + 389 89 089 089 Е-mail: [email protected] Webpage: www.evn.mk 5.7. Ministry of Environment and Physical Planning Address: Goce Delchev no. 18 1000 Skopje Telephone: + 389 2 32 51 403, + 389 2 32 51 503, + 389 2 32 51 460 Webpage: www.moepp.gov.mk 5.8. Ministry of Transport and Communications Address: Dame Gruev no. 6 1000 Skopje Telephone: + 389 2 31 45 497, + 389 2 31 23 292 Webpage: www.mtc.gov.mk 5.9. Ministry of Agriculture, Forestry and Water Economy Address: Aminta Treti no. 2 1000 Skopje Telephone: + 389 2 31 34 477 E-mail: [email protected] Webpage: www.mzsv.gov.mk 5.10. Central Register Address: Kuzman Josifovski Pitu no. 1 1000 Skopje Telephone: + 389 2 32 88 100 Webpage: www.crm.com.mk
6. RELEVANT LEGISLATION AND BY-LAWS
1. Law on Energy (Official Gazette no. 96/2018 and 96/2019)
2. Decree on support measures for electricity production from renewable energy sources (Official Gazette no. 29/2019 and 278/2019)
3. Decision on the total installed capacity of preferential electricity producers (Official Gazette no. 29/2019 and 194/2019)
4. Rulebook on renewable energy sources (Official Gazette no. 112/2019 and 240/2019)
5. Rulebook for preferential producers that use a feed-in tariff (Official Gazette no. 116/2019)
6. Rulebook on Licenses (Official Gazette no. 51/2019, 54/2019 and 214/2019)
7. Regulations on the electricity market (Official Gazette no. 173/2018, 222/2018 and 279/2019)
8. Grid Code for Electricity Distribution (Official Gazette no. 191/2019)
9. Law on Physical and Urban Planning (Official Gazette no. 199/2014, 44/2015, 44/15, 193/15, 31/16, 163/16, 64/18 and 168/18)
10. Law on Construction Land (Official Gazette no. 15/15, 98/15, 193/15, 226/15, 31/16, 142/16, 190/16 and 275/2019)
11. Decree on the amount of the price of construction land owned by the Republic of Macedonia and the amount of special costs for conducting the alienation procedures, leasing and the establishment of the right of
real servitude (Official Gazette no. 163/2016, 190/2017 and 201/2018)
12. Law on Agricultural Land (Official Gazette no. 135/07, 18/11, 148/11, 95/12, 79/13, 87/13, 106/13, 164/13, 39/14, 130/14, 166/2014, 72/15, 98/15, 154/15, 215/15, 7/16, 39/16 and 161/2019)
13. Law on Forests (Official Gazette no. 64/2009, 24/2011, 53/2011, 25/2013, 79/2013, 147/2013, 43/2014, 160/2014, 33/2015, 44/2015, 147/15, 7/16 and 39/16)
14. Law on Property and Other Real Rights (Official Gazette no. 18/2001, 92/2008, 139/2009 and 35/2010)
15. Law on Environment (Official Gazette no. 53/2005, 81/2005, 24/2007, 159/2008, 83/2009, 48/2010, 124/2010, 51/2011, 123/2012, 93/2013, 187/2013, 42/2014, 44/15, 129/15, 192/15, 39/16 and 99/18)
16. Decree on the activities for which an Elaborate must be prepared and whose approval depends on the competent authority for performing professional activities in the field of environment (Official Gazette no. 80/2009 and 36/2012)
17. Rulebook on the form and content of the Elaborate for environmental protection in accordance with the types of activities for which the Elaborate is prepared, as well as in accordance with the performers of the activity and the scope of activities performed by legal entities and individuals, the procedure for their approval, as well as the manner of keeping the register of approved elaborates (Official Gazette no. 44/2013 and 111/2014)
18. Law on Construction (Official Gazette no. 130/2009, 124/2010, 18/2011, 36/2011, 54/2011, 13/2012, 144/2012, 25/2013, 79/2013, 137/2013, 163/2013, 27/2014, 28/2014, 42/2014, 115/2014, 149/2014, 187/2014, 44/2015, 129/15, 217/15, 226/15, 30/16, 31/16, 39/16, 71/16, 132/16, 35/18, 64/18, 168/18, 244/19 and 18/20)