Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
1
1. INTRODUCTION
Cathral Investments Ninety One (Pty) Ltd (i.e. Cathral
Investments) holds EPL 6545, which is located in the
Lüderitz district, Karas Region approximately 50 km
northwest of Helmeringhausen (refer to Figure 1). EPL
6545 is approximately 34 600 hectares (ha) in size,
encompassing eight privately owned farms. The C27
Road crosses through the center of the EPL.
Tulela Processing Solutions (Pty) Ltd (i.e. Tulela), a
wholly-owned Namibian Metallurgical and Mining
company, holds majority shares in Cathral Investments.
Tulela intends to recover economical minerals from the
Sinclair ore body.
Cathral Investments / Tulela proposes to conduct further
exploration on the EPL, within the “area of interest”,
indicated in red in Figure 1. Furthermore, Cathral
Investments proposes to apply for a Mining Licence
(ML) from the Ministry of Mines and Energy (MME) for
mining; processing of the ore and associated activities.
The proposed ML area would cover a similar area to the
red block (in Figure 1), which is approximately 863 ha in
size.
This area of interest encompasses the “Sinclair Mine”,
where various companies have conducted exploration
and mining activities in the past. The Sinclair Mine is
situated on the Sinclair Farm.
2. ENVIRONMENTAL CLEARANCE
Prior to the commencement of the proposed Sinclair
Project activities, an application for an environmental
clearance will be submitted in terms of the
Environmental Management Act, 7 of 2007 and the
associated environmental impact assessment (EIA)
Regulations (January 2012) to the MME, as the
competent authority.
MME will review the application and relevant reports and
submit their comments to the Ministry of Environment
and Tourism (MET). An EIA process will be conducted
in terms of the above-mentioned Act and Regulations.
Namisun Environmental Projects & Development
(Namisun) has been appointed by Tulela as the
independent Environmental Assessment Practitioner to
undertake the EIA process for the proposed project.
3. PURPOSE OF THIS DOCUMENT
This document has been prepared by Namisun to inform
you about:
Previous activities at the Sinclair Mine (Section 5);
Proposed project activities (Section 6);
The EIA process (section 7);
the key environmental and social issues (i.e.
aspects and potential impacts) (Section 8); and
How you can register as an interested and /or
affected party (IAP) (sections 4 and 9).
4. PARTICIPATION IN THE EIA PROCESS
Public participation is an essential part of the EIA
process.
You have been identified as a possible IAP who may
want to be informed about the proposed project and
have input into the EIA process. All comments will be
recorded and addressed in the EIA process.
CATHRAL INVESTMENTS NINETY ONE (Pty) Ltd
EIA FOR SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT
THE SINCLAIR MINE ON EXCLUSIVE PROSPECTIVE LICENCE (EPL) 6545, KARAS REGION
BACKGROUND INFORMATION DOCUMENT
HOW TO REGISTER AS AN IAP Please register as an IAP and submit any questions or
comments by means of the enclosed registration / comment sheet or through communication with
Namisun.
Attention: Werner Petrick E-mail address: [email protected]
Cell number: +264 (0)81 739 4591
If you would like your comments to be addressed in the Scoping Report please submit them by
27 September 2019.
2
Sinclair Project
NAMISUN Environmental
Projects and Development
P.O. Box 8127, Swakopmund,
Namibia
E-mail:
Client: Tulela
LOCALITY MAP
Helmeringhausen
20 km
Legend:
Area of interest
EPL 6545
C27
C14
Sinclair Farm house
Sinclair Mine
Proposed Access Road
Figure 1: Regional Location of the Sinclair Project (Ref: Google Earth)
3
Figure 2: Sinclair Project layout and infrastructure (Ref: Google Earth)
Sinclair Project
NAMISUN Environmental
Projects and Development
P.O. Box 8127, Swakopmund,
Namibia
E-mail:
Client: Tulela
Proposed
Infrastructure Layout
Plant Feed stockpile
200m
Legend:
Indicative Open Pit
DMS & Gravity Plant
VAT Leach Vessels area
Site office & workshopsSX, EW & Stripping
Water StorageProposed Access
Road
Box cut
VAT leach vessel areaPower station & Fuel storage
WRD
Sewerage System
4
5. DESCRIPTION OF PREVIOUS AND PROPOSED
ACTIVITIES
5.1. PREVIOUS MINING AND EXPLORATION
ACTIVITIES AT SINCLAIR
Extensive exploration and mining programmes have
previously been carried out in this area.
The copper deposit was discovered and mined since
the mid-nineteenth century, when several ox wagon
loads of ore was hauled to the Prinzenbucht, a small
bay south of Lüderitz. (Ref: mindat.org):
Mining entrances around the hill, tracks, ore stockpiles
and old building foundations and rubble, amongst
others, are still visible, as rehabilitation work was only
carried out rudimentary.
Some of the historic work in the area is briefly listed
below (Ref: mindat.org):
1900s: First description of the deposit.
1912/13: Exploration and mining of the ore body
by the German Colonial Bergbaugesellschaft.
World War 1 put a halt to the mining.
1920s/30s: Exploration and mining resumed
under the South West Copper Company
(abandoned during the depression in 1932).
Since then, the deposit has been re-evaluated by
several companies including the African Metals
Corporation of South Africa (ISCOR) and Rio
Tinto.
Welwitschia Minerals and Hydrocarbons cc conducted
an EIA in 2017 and received an environmental
clearance from the MET in 2018 for small scale mining
and material handling at Sinclair. However, they’ve
conducted very little activities.
6.1 PHASE 1: PROCESS EXISTING SURFACE
STOCKPILES
Existing ore stockpiles (from historic mining activities)
are located at various locations around cuts into south-
west face of the hill, at Sinclair. Tulela proposes to
move all these ore stockpiles to a centralised location
(i.e. the ‘Plant feed stockpile’ on Figure 2). Excavators
and front end loaders will be used to relocate the small
stockpiles.
By moving these ore stockpiles away from their current
locations will allow Tulela to:
1. Process the ore to sell the copper product; and
2. Clear the areas for further exploration.
6. PROPOSED ACTIVITIES
No immediate blasting is required. However, in the
longer term, depending on the exploration results,
blasting might be required (refer to section 6.2).
6.1.1 Ore Processing
From the plant feed stockpile, the ore will first be
crushed via a mobile crushing plant; and thereafter
screened and treated via Dense Medium Separation
(DMS) and a spiral gravity circuit.
Two streams will be generated: 1.) A high grade
concentrate, which will be sold as product (i.e.
exported through the port of Lüderitz); and 2.) “Low
grade material” to be further processed.
Low grade material processing – Copper
extraction
Multiple VAT Leach Vessels (dams) will be constructed
in the area highlighted in light green in Figure 2. These
vessels will be constructed as required, i.e. as one
becomes redundant, it will be neutralised and the next
vessel constructed. Each vessel will be constructed on
ground surface and will have a footprint in the order of
2 500 m2 and would be ± 4 m in height.
The bottom and sides of the vessels will be lined with
a plastic lining and once it has been filled with the low
grade ore, it will also be covered (on top) with a plastic
lining. Therefore, the ore will be encapsulated inside
the plastic lining, ready to be treated.
An alkaline solution will be added to the encapsulated
ore. The leached copper-bearing solution (“PLS”) will
be pumped to the proposed solvent extraction (SX)
section and electro winning (EW) processing plant
where copper plates will be produced. The alkaline
solution will be recycled and pumped back as a
“raffinate stream” into the VAT leach vessel.
Low grade material processing – Gold / silver
extraction
The process will make provision to possibly recover
small quantities of gold and silver post the extraction
of the copper. Cyanide solution will be added to the
encapsulated material. The gold / silver-bearing
solution will be extracted; filtered and precipitated. The
VAT will be neutralised post the extraction process.
6.2 PHASE 2: FURTHER EXPLORATION, MINING
AND PROCESSING OF MINED ORE
6.2.1 Exploration
The further exploration for copper (and gold / silver)
mineral will be done on the Sinclair mine area (only),
within the red area indicated in Figure 1. The
5
exploration activities will be conducted in parallel with
phase 1 of the project, as the existing ore stockpiles
are removed from their current locations.
An exploration crew will be set up to commence with
extended resource drilling in the above mentioned
target area. As the resource is partially exposed on the
surface, a box cut sample will also be taken
(highlighted in light blue in Figure 2) by further
excavation of the existing cut in the hill. The size of the
box cut will be determined as the exploration
progresses.
The following machinery/vehicles will be utilized in the
drilling program:
One Light Duty Vehicle (LDV) (i.e. 4x4 Vehicle)
Two Drill Rigs (one Reverse circulation (RC) Drill
and one Diamond Drill)
One excavator and one loader for the box cut.
It is anticipated that five people will be permanently
employed, of which three will be skilled, to carry out the
above-mentioned activities.
5.2.2 Mining
Tulela proposes to conduct relatively “small scale”
mining activities at the existing Sinclair Mine, which is
dependent on the future exploration results.
The possible mine pit footprint is indicatively illustrated
in yellow in Figure 2 and could be ±7.8 ha in size. The
open cast mining would be undertaken to depths
ranging between ± 5 and 30 m depending the
exploration results.
As per conventional open pit mining, this would include
drill and blast followed by load and haul activities.
The following machinery/vehicles will be utilized in the
mining activities:
One Dozer
One Excavator
Two Loaders
Four articulated Dump Trucks (30 ton each).
Waste rock would be disposed of at an area
(indicatively) illustrated as the WRD (i.e. waste rock
dump) in Figure 2.
5.2.3 Processing of the mined ore
The future mined ore (from the open pits and
potentially from the box cut) will be hauled to the ‘Plant
feed stockpile’ and similarly processed in the proposed
(multiple) VAT leach vessels and SX, EW & Stripping
Plant, as described in Section 6.1.
The estimated feed rate of ore to the DMS would be ±
50 t/hr and 38 t/hr to the VAT leach vessels.
6.3 WATER SUPPLY
Approximately 50 m3 per annum of water will be used
for exploration and 40 000 m3 per annum (excluding
for human consumption) for the mining and processing
activities.
Water will be sourced from nearby borehole(s) on the
farm within the area of interest.
5.2.4 Power Supply
Because of the remote site, the entire site will be
powered by diesel generators.
5.2.5 Site Access
A new road is to be graded. The proposed new site
access route is indicatively illustrated in Figure 1 in
black.
5.2.6 Employment and accommodation
Construction Phase
Approximately 50 people will be required over the ± 4
month construction period to construct the processing
plant.
For the construction phase of the project about 70% of
the crew is expected to be skilled. It is estimated that
80 % will be contractors.
Operational phase
Approximately 30 people will be required for the
operational phase of the project, of which 80% to be
skilled. It is estimated that about 70% will be fix term
contractors and 30% permanent.
A 4 shift cycle team of 5 people per shift will be
required, including the supervisor.
Three options are currently being evaluated to
accommodate the work crew:
Utilising a site base camp on the mining lease;
Accommodation on the adjacent farm; or
Accommodation in Helmeninghausen.
Both operational cost and safety risks of extended
travel distances to town will be considered.
5.2.7 Transportation
Chemicals will be trucked to site from Lüderitz or RSA.
The final metal product will be trucked to Lüderitz for
shipment to the end client.
5.2.8 Life of mine
The life of mine is expected to be between 14 and 24
months. This might however increase, depending on
future exploration results.
6
6. EIA PROCESS
The main objectives of the EIA process are to:
Provide information on the proposed project
activities and facilities / infrastructure;
Describe the current environment in which it will
be situated;
Identifies, in consultation with IAPs, the potential
negative and positive environmental (and social)
aspects;
Assesses the associated potential impacts of the
proposed project; and
Report on measures required to avoid impacts or
mitigate such impacts to acceptable levels.
The likely process steps and timeframes of the EIA
process are provided in Table 1.
Table 1: EIA Process for the proposed Sinclair
Project.
STEPS IN THE EIA PROCESS
PHASE I: Project initiation & Internal Screening (August - September 2019)
EIA project initiation.
Notify MME and MET through the submission of the EIA Application Form and online (MET) Registration.
Site visit and identify environmental issues.
Identify key stakeholders.
PHASE II – Combined Scoping & Assessment Phase and Environmental Management Plan
(EMP) (September – November 2019)
Notify other regulatory authorities and IAPs of the proposed project (via newspaper advertisements, this document, emails, site notices).
Conduct public meeting (see details provided) and key stakeholder (focus group) meetings.
Carry out specialist investigations.
Assess the potential impacts of the proposed Sinclair project activities and compile a Scoping (including assessment) Report and EMP.
Distribute the EIA reports for review and comment by regulatory authorities and IAPs.
Consider comments received and compile the final reports (including an Issues and Response Report).
Submit the final reports to MME and MET for their review and decision-making.
A draft Scoping Report (including an assessment of
impacts) and an Environmental Management Plan
(EMP) for the proposed project will be made available
for public review / comment. Registered IAPs will be
notified via e-mail of the review period and the
availability of the draft Scoping Report (including impact
assessment) and EMP.
The final Report, along with all IAP comments, will be
submitted to the Ministry of Mines and Energy (MME)
for their review and recommendation, after which it will
be forwarded to MET (Environmental Commissioner)
for their review and a final decision.
7. KEY ISSUES RELATED TO THE PROPOSED
EXPLORATION, SMALL SCALE MINING AND
PROCESSING ACTIVITIES
Potential environmental issues (i.e. aspects / potential
impacts), that need to be assessed as part of the EIA,
associated with the proposed Sinclair Project, include:
Groundwater and Surface water impacts:
Groundwater contamination; lowering of
groundwater level due to pumping from on-site
borehole(s); alteration of drainage patterns and
pollution of surface water.
Air Quality:
Potential air pollution as a result of dust from
exploration and mining activities, i.e. trucks,
machinery, blasting, etc., impacting on third
parties’ health and causing nuisance.
Noise:
Increase in ambient noise causing
disturbance/nuisance.
Biodiversity:
Physical destruction and general disturbance of
biodiversity.
Archaeology:
Destruction and damage to archaeological sites
and landscapes.
Socio-economic:
Potential negative impacts on current
(surrounding) land use activities; health and
safety concerns to nearby land owners;
nuisance-related disturbance; impacts relating to
mining staff on site.
Positive economic impacts associated with
income and employment.
7
8. INVITATION TO REGISTER AND COMMENT
Please complete the enclosed registration/comment
form or contact Namisun to register as an IAP.
For comments to be included in the Scoping (including
Impact Assessment) Report they must reach Namisun
by no later than 27 September 2019.
9. INFORMATION SHARING MEETING
6. K
You are invited to attend the following information-sharing meeting:
Date: 2 October 2019
Location & venue: Sinclair Farm Homestead
Time: 9:00 am
DMS and Spiral Supply
Leach Feed
VAT Leaching
Ammonium Makeup
WaterAmmonium
Reagent
Cyanide Dilution
Water Cyanide
Reagent
SXExtraction
SX PLS Feed
SXStripping
Electrowinning
Cu
Plates
Gold Extraction
Precipitation
PLS
Zn Dust
Ore Concentrate
Mined Ore
Water
Metal
Concentrate
Neutralising Reagent
Sulphuric
Acid
Water
Organic
Supply
Impurity
Bleed
Figure 3: Conceptual Process Flow Diagram
CATHRAL INVESTMENTS NINETY ONE (Pty) Ltd
EIA FOR SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT
THE SINCLAIR MINE ON EXCLUSIVE PROSPECTIVE LICENCE (EPL) 6545, KARAS REGION
IAP REGISTRATION AND COMMENTS FORM
DATE:
IAP PARTICULARS:
NAME AND SURNAME:
ORGANISATION:
E-MAIL:
TEL & CELL PHONE NUMBERS:
PLEASE IDENTIFY YOUR INTERS IN THE PROPOSED PROJECT:
PLEASE PROVIDE YOUR COMMENTS / QUESTIONS:
From: Werner Petrick [mailto:[email protected]] Sent: Monday, 16 September 2019 12:05 Subject: NOTICE OF EIA PROCESS: PROPOSED SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT THE SINCLAIR MINE Dear Sir/Madam This email and attached background information document (BID) provides formal notification
that Cathral Investments Ninety One (Pty) Ltd is in the process of applying for a Mining
Licence (ML) from the Ministry of Mines and Energy (MME) for mining and associated
activities at the Sinclair Mine.
Tulela Processing Solutions (Pty) Ltd (i.e. Tulela), a wholly-owned Namibian Metallurgical
and Mining company, holds majority shares in Cathral Investments. Cathral Investments /
Tulela proposes to process existing surface ore stockpiles from historic mining activities; and
to conduct further exploration, mining and processing (of future mined ore) activities, to
extract copper and to possibly recover small quantities of gold and silver, at the Sinclair
Mine.
Prior to conducting the proposed activities, an Environmental Impact Assessment (EIA) process will be conducted and an application for an environmental clearance certificate will be submitted to the MME as the competent authority who will review and forward the application to the Ministry of Environment and Tourism (Environmental Commissioner) in terms of the Environmental Management Act, 7 of 2007 and Regulations 19 and 21 of the EIA Regulations (January 2012). The Sinclair Mine is located in the Lüderitz district, Karas Region, approximately 50 km
northwest of Helmeringhausen, on the Sinclair Farm. Extensive exploration and mining
programmes have previously been carried out at the Sinclair Mine by various companies.
Namisun Environmental Projects & Development (Namisun) has been appointed by Tulela as
the independent Environmental Assessment Practitioner to undertake the EIA process for the
proposed project.
Registration to receive notifications and information:
If you would like to register as an Interested and/or Affected Party (IAP) with Namisun,
please submit your comments, full name and contact details by email, or by contacting the
undersigned. The attached BID is available for a review and comment period until 27
September 2019.
An information-sharing meeting will be held at the Sinclair Farm:
Date: 2 October 2019
Location & venue:
Sinclair Farm Homestead
Time: 9:00 am
For questions, issues and/or comments to be included in the EIA Scoping (including Impact
Assessment) Report, please forward them to Namisun by no later than 27 September
2019.
Yours sincerely
Werner Petrick +264 (0)81 739 4591
From: Werner Petrick [mailto:[email protected]] Sent: Thursday, 31 October 2019 14:12 Subject: EIA FOR THE PROPOSED SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT THE SINCLAIR MINE Dear Sir / Madam
EIA FOR THE PROPOSED SMALL SCALE MINING & PROCESSING ACTIVITIES AND
ONGOING EXPLORATION AT THE SINCLAIR MINE, KARAS REGION - 50 KM
NORTHWEST OF HELMERINGHAUSEN
With reference to earlier correspondence regarding the above mentioned project and EIA
process, please be advised that the Environmental Impact Assessment (EIA) Scoping &
Assessment Report and Environmental Management Plan are now available for review and
comment.
A hard copy and an electronic copy of the full report (including all Appendices) are available
at the Sinclair Farm Homestead from the 6th of November 2019.
Attached, please find the Main Report (excluding Appendices). An electronic copy of the full
report is also available on request to Namisun.
Please send any comments you might have on the report to the undersigned by 15
November 2019.
Yours sincerely,
Werner Petrick +264(0)81 140 5968
1
EIA FOR SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT
THE SINCLAIR MINE ON EXCLUSIVE PROSPECTIVE LICENCE (EPL) 6545, KARAS REGION
MINUTES OF FOCUS GROUP MEETING 1:
Sinclair Farm Owner
MEETING DETAILS
DATE 10 September 2019
TIME: 14:00
VENUE: Telecom
PROJECT: Sinclair Project
PURPOSE: The purpose of the meeting was to:
Inform the Sinclair Farm Owner about:
The proposed project activities;
The Environmental Impact Assessment (EIA) process being followed;
To agree on the date, time and venue for the public meeting; and
How interested and/or affected parties (IAPs) could participate in the
EIA process.
Discuss potential environmental impacts.
Obtain initial input from the Sinclair Farm Owner on issues and concerns,
and input on environmental sensitivities and potential impacts.
ATTENDANCE: Mr. Marc Pampe (Sinclair Farm owner)
Mr. Philip Badenhorst (Tulela Processing Solutions (Pty) Ltd)
Mr. Werner Petrick (Namisun Environmental Projects & Development)
1. OPENING OF THE MEETING AND GENERAL INTRODUCTION
Werner Petrick (WP) welcomed all to the meeting and WP and Philip Badenhorst (PB) introduced
themselves to Marc Pampe (MP). This was followed by a short introduction, which included:
The objectives of the meeting
Brief explanation of the EIA process being followed, the EIA Team, etc.
2. PRESENTATION
Due to the fact that it was a telecom meeting, a formal presentation was not made. However, the
Background Information Document (BID), which WP send to MP before the meeting, was used as the
basis for the discussion. WP and PB provided an overview of the proposed project activities, EIA
process and key environmental issues, by referring to the BID.
2
3. DISCUSSION (QUESTIONS AND ANSWERS)
MP raised a number of questions / comments / issues during the meeting. These have been recorded
in the attached table (refer to Appendix 1). The responses provided by either WP or PB are also
recorded in the table.
4. THE WAY FORWARD
WP outlined the way forward as follows:
MP will send a list of neighbouring farmers with contact details to WP.
WP will update his IAP database with the above information and distribute the BID to all IAPs on
the database (via e-mail).
MP will send further comments in writing (if any) soonest (but before 27 September 2019).
A public meeting will be held at the Sinclair Farm Homestead on the 2nd of October 2019
(9:00am). WP will invite IAPs to the meeting through the newspaper advert and e-mails that will
be sent to IAPs.
3
APPENDIX 1: Questions / Comments / Concerns raised by MP and responses provided by WP and PB
No. Questions / Comment / Issue raised Response
1 Will the copper be in the solution coming from the
VAT System?
Yes. An alkaline solution will be added to the encapsulated ore. The leached
copper-bearing solution will be pumped to the processing plant where copper
plates will be produced.
2 Is it a Closed Cycle? With the solution therefore be
pumped back into the VAT?
Yes. The alkaline solution will be recycled and pumped back into the VAT leach
vessel.
3 After neutralising the material inside the VAT, what
will happen with the solution? Will there be any
discharge of the “Neutralised solution” into the
environment”?
Multiple VAT Leach Vessels (dams) will be constructed. As one becomes
redundant, it will be neutralised and the next vessel constructed. The neutralised
solution will also be pumped from the “redundant VAT” to the new one.
4 What happened at the last / final VAT. Will the
“neutralised solution” from this VAT have to be
discharged?
The decision regarding the final VAT and the discharge from this VAT still need to
be confirmed. A possibility would be that a small evaporation pond will have to be
constructed next to the last VAT and the “neutralised solution pumped to this
evaporation pond.
5 Can one VAT be used than once?? Each VAT will only be used once for the copper extractions and thereafter
(possibly) for the gold / silver extraction.
The soil will therefore remain, encapsulated, indie the plastic liners (i.e. plastic
lining on all sides). Once neutralised, it will therefore remain as is.
If this soil were to be removed, there would be a danger in damaging the liner and
the soil/slurry will have to be disposed of at a new “tailings storage facility.
6 Will the plastic line stay behind after the VAT become
redundant?
My concern is that the plastic will demolish from the
sun and be blown around.
The “Neutralised soil / slurry will remain inside the VAT. Therefore, the only plastic
lining that will be exposed will the top part that covers the soil/slurry.
Once redundant, the plastic liner will have to be covered with soil / topsoil and
vegetation growth allowed. This would form part of the rehabilitation strategy.
7 Is it therefore part of th planning to add soil on top of
the VAT?
Yes. The exact timing in terms of covering the VAT with soil still needs to be
confirmed though (i.e. during or after the operations of the VAT).
8 Will there be any harmful chemicals staying behind?
Howe affective will the neutralization be?
The soil/slurry inside the VAT will be flooded and this should be 100% affective.
4
No. Questions / Comment / Issue raised Response
9 I see diesel generators will be used for power supply.
I am concerned about the noise from the generators.
Will make noise also at night?
The electro winning and SX will run 24/7. None of the other activities(i.e. earth
moving activities, crushing, etc.) will be undertaken during the night time.
The generators will however have to run 24/7. The diesel generators will be
enclosed in a container to minimize the noise.
A noise specialist was appointed as part of the EIA team to assess the potential
noise impacts from the proposed activities and provide management and
mitigation measures regarding these issues.
10 Will the activities be 24/7? Concerned about noise at
night.
11 Will the further explanation only entail drilling, or will
there also be further trenching.
Only drilling and a box cut sample will be taken by further excavation of the
existing cut in the hill.
12 Will holes be covered up attention drilling The boreholes drilled need to be covered, however, it must still be acceptable for
possible future monitoring.
13 How high will the waste rock dump (WRD) be? Will
this be a new mountain?
The only material that will be disposed of at such a WRD facility will be overburden
from the mining activities. The volumes of WRD still needs to be estimated.
Another options would be to backfill the mine pit with the waste rock.
14 My biggest concern is water. What is the maximum
volume of water that will be required?
Max 40 000 m3 per annum would be required (for phase 1 and 2). The same plant
will be used for processing the mined ore during phase 2 and it is designed to
handle a specific throughput.
15 How will the housing for the workers be handled. The housing for the workers still need to be confirmed. Either way, Tulela is
considering temporary infrastructure. This could possibly be a business opportunity
for someone to provide the housing to the workers.
1
EIA FOR SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT
THE SINCLAIR MINE ON EXCLUSIVE PROSPECTIVE LICENCE (EPL) 6545, KARAS REGION
MINUTES OF MEETING:
Public Meeting
MEETING DETAILS
DATE 02 October 2019
TIME: 14:00
VENUE: Sinclair Farm Homestead
PROJECT: Tulela Processing Solution: Sinclair Project – EIA Process
PURPOSE: The purpose of the meeting was to:
Provide a description of the proposed “Sinclair Project” activities
Provide a description of the EIA process
Provide IAPs with further opportunity to be involved in the EIA
Identify any potential environmental issues and impacts
Describe the way forward, highlighting further opportunities to be involved
in the EIA process.
ATTENDANCE: Refer to Appendix 2.
1. OPENING OF THE MEETING AND GENERAL INTRODUCTION
Werner Petrick (WP) from Namisun Environmental Projects and Development introduced himself as the
independent environmental practitioner, conducting the EIA process, and welcomed all to the meeting.
Philip Badenhorst (PB) (Tulela Processing Solutions (Pty) Ltd) and Arnold Bittner (AB) (SLR
Environmental Consulting (Pty) Ltd) - Water Specialist and part of the EIA Team) introduced
themselves.
This was followed by a short introduction by WP, which included:
The meeting procedure and objectives of the meeting.
General introduction to the project and brief explanation of the EIA process being followed, the
EIA Team, etc.
2. PRESENTATION
A formal PowerPoint presentation was made, as follows:
• A description of proposed project activities by PB.
• The EIA process and key potential environmental issues identified to the date of the meeting by
WP
• Background and initial study findings of the ground water supply and related issues by AB.
2
3. DISCUSSION (QUESTIONS, COMMENTS AND ISSUES RAISED)
The meeting attendees (i.e. interested and affected parties) raised a number of questions / comments /
issues during the meeting. These have been recorded in the attached table (refer to Appendix 1).
Responses provided in the meeting are not captured as part of this minutes of the meeting. A separate
Comments and Response Report (CRR), incorporating all questions / comments / issues raised
throughout the EIA process (including those raised in the meeting) is attached as Appendix B to the EIA
Scoping & Assessment Report.
4. THE WAY FORWARD
WP outlined the way forward as follows:
Comments received to date and during this meeting will be considered and included in the Draft
EIA Scoping & Assessment Report, where relevant.
The Draft Report will be distributed for comment towards mid-October 2019.
It was agreed in the meeting that the review will be conducted as follows:
o A two week review period will suffice.
o The Main EIA Scoping & Assessment Report (excluding Appendices) will be sent per e-
mail to all attendees (and other registered IAPs).
o One hard copy and one electronic copy of the full report (including all Appendices) will
be made available at the Sinclair Homestead for review by all IAPs.
3
APPENDIX 1: QUESTIONS / COMMENTS / ISSUES RAISED BY IAPS (REFER TO THE CRR, ATTACHED TO THE EIA SCOPING & ASSESSMENT REPORT,
FOR REPONSES TO ALL QUESTIONS / COMMENTS / ISSUES RAISED THROUGHOUT THE EIA PROCESS)
No. Questions / Comment / Issue raised
1 Is there a feasibility study? Is the project Economically feasible?
2 What method did you use to assess, explore & determine the feasibility?
3 Where is the Sinclair homestead located in relation to the mine?
4 Explain the difference between VAT leach and Heap leach.
5 What is meant with agglomeration??
6 Will water to the mine come from the ground?
7 Where will you add an acid solution?
8 How high is the VAT/Leach facility? What will be the overall dimensions of the VAT/Leach facility be?
9 What volumes of crushed material will go onto each VAT?
10 The Background Information Document (BID) mentioned DMS and Spirals. Where are those (not mentioned in the presentation)?
11 Why were these taken out?
12 What is the difference in permeability between the current stock piles future mined ore?
What will the difference be in particle size?
13 Will you screen the material before it goes onto the VAT/leach facility?
14 Without agglomeration you will not get permeability.
15 How was the sampling done? How many samples were taken?
16 Once leaching is done how will the VATs be closed and rehabilitated?
17 A Mine Closure Plan (including closure costing) needs to be developed. A key issues is, should the project not be feasible, there needs to be budget for
properly closing the mine and conducting effective rehabilitation.
4
No. Questions / Comment / Issue raised
18 Topsoil needs to be removed prior to the construction activities / clearing of areas; separately stockpiled and used during the rehabilitation at closure. Also, to
get the rehabilitation “going” the topsoil (once placed back) might require some water.
19 Will the material in the VATs be neutralised? How will the neutralising differ between the Acid and Alkaline leaching processes?
20 Is Tulela happy with one bakkie load as a representative sample?
It is not a representative sample of the area – it is a risk.
21 Will all material be crushed & Screened. How long does the crushing & screening take? Will it be done 24/7?
22 Why conduct exploration after processing starts? This seems to be the wrong way around.
23 Will it be entirely an open pit?
Why one big open pit? It should rather be various smaller pits / box cuts along the areas where the ore is found due to the fact that there will likely be various
areas between the ore veins without any ore.
24 Does the processing remain the same for phase 2?
25 Concerned about the noise from the electricity generators.
26 How much power is required?
27 There are various endemic biodiversity species in the area and they are seasonal. It is currently a bad time of the year for plants as there are were no rains
yet. Locals need to look at the species list.
28 Tourism is important for the area.
29 Will you use existing boreholes or drill new ones for the water supply to the mine?
30 The proposed new borehole location is a good location for groundwater monitoring.
31 We are concerned about the water abstraction as the mine will be pumping for many days/ weeks/months. How will this impact the other groundwater users
in the area?
32 The water table is a concern. The water requirements for the mine is an order of magnitude difference of water used by farmers. Also, the average rainfall in
the area is very low and we are concerned about the recharge of the groundwater.
Neighbouring could be affected. Should the groundwater monitoring not also be extended to neighbouring farms as well?
5
No. Questions / Comment / Issue raised
33 The groundwater abstraction could be a long term impact, extending beyond the operations of the mine.
34 Ideally long term monitoring data is required.
35 An independent person should do the monitoring.
36 The EPL holder is Cathral Investments. Do they do other project as well?
37 Does Tulela have 3rd party insurance in terms of liabilities?
I.e. field fires, water losses, etc.
38 After mining, what will happen? There must be a funds for mine closure / rehabilitation from the beginning of the project.
39 Where will water be stored?
40 What chemicals will be used and where will chemicals be stored?
41 Is there no low grade stockpile / dump?
42 Will there be Crushing plant?
43 There is lots of quarts that could damage the crusher.
44 What will be the width and depth of the box cut? There might be lots of waste?
45 What will be the tonnage of ore from box cut?
46 What grade is expected?
47 The BID referred to “ore stockpiles”. That is wrong terminology. Is should be regarded as “waste dumps” with some copper.
48 It is on record that the ore reserve estimate is 3%. Valuable ore have been “hand-picked already by historical mining activities.
There is a risk that too little samples were taken by Tulela to determine whether it will be a feasible project.
The risk lies in the fact that, if there is no income from the project, there will also be no money for rehabilitation - as part of closure.
There needs to be a fund for the closure / rehabilitation.
49 What are the copper minerals?
6
No. Questions / Comment / Issue raised
50 Gold would be negligible.
51 How long will the liners in the VAT/ Leach facility last?
52 Will there be dust suppression on the crushers?
53 Will the material stay in the VATs?
54 What is the expected copper recovery?
55 What will be used to neutralise the material in the VATs?
56 From where will the neutralising material come?
57 Will calcrete from the area be used the neutralise the VAT? If this is mined, what will be the impacts?
58 What will happen with final effluent from the VATs?
59 How long will the alkaline leaching take in one VAT?
60 Will permeability play a role in leaching process?
61 How long will the acid leaching take in one VAT?
62 What will the average grades left behind in VATs?
63 What neutralising agent will be used for the VATs?
64 What if the grade of gold and silver is not good?
65 If recovery of copper is much lower than expected but precious metals is good, will you then process this only?
66 Will there be no slimes dam (i.e. Tailings storage facility)?
67 What will happen with the final effluent coming out of the process – any discharge to the environment?
68 The MAWF will have to be part of the EIA.
69 Land use needs to be considered in the EIA?
70 Will the geology be described?
7
No. Questions / Comment / Issue raised
71 Will there be dust suppression?
72 Workers might be an issue regarding community safety. Also, drug use and dealing with drugs s are issues in the area.
73 All potential impacts must be considered as part of the EIA and management and mitigation measure developed in included in an EMP.
8
APPENDIX 2: ATTENDANCE REGISTER
2019/12/02
1
EIA FOR SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT
SINCLAIR MINE ON EPL 6545
2 October 2019
1
Public Information Sharing Meeting
Sinclair Farm Homestead
Agenda
2
• IntroductionMeeting ProcedureObjectives of the meeting General introduction
• Description of proposed project activities• EIA process• Key potential environmental issues• Question and answer session • Way forward and closure
Meeting Procedures
3
• Opportunity to ask questions / give comments• Minutes are being taken• Please sign the Attendance Register
Objectives of the meeting
4
• Provide a description of the proposed “Sinclair Project” activities
• Provide a description of the EIA process
• Provide IAPs with further opportunity to be involved in the EIA
• Identify any potential environmental issues and impacts
• Describe the way forward, highlighting further opportunities to be involved in the EIA process
General Introduction
5
• Cathral Investments Ninety One (Pty) Ltd holds EPL 6545 34 600 ha in size.
• Tulela Processing Solutions (Pty) Ltd (i.e. Tulela), a wholly-owned Namibian Metallurgical and Mining company, holds majority shares in Cathral Investments.
• Tulela intends to recover economical minerals from the Sinclair ore body.
General Introduction
6
• Cathral Investments proposes to:Conduct further exploration on the EPL, within the “area of interest”Apply for a Mining Licence MME for:
• Mining; • Processing of the ore and associated activities
ML area would be ± 863 ha Encompasses the “Sinclair Mine”, where various companies have
conducted exploration and mining activities in the past. The life of mine: ± 14 and 24 months (might however increase,
depending on future exploration results).
2019/12/02
2
7 8
Project Description
9
• Phase 1:Process existing surface stockpiles
• Phase 2:Further exploration, mining and processing of mined ore
Project Description: Phase 1
10
• Move existing “ore stockpiles” to a centralised location with excavators and front end loaders
Process the ore to sell the copper product
…This will Clear the areas for further exploration.
Project Description: Ore Processing
11
Sinclair Project
Crushing & Screening
Leach Feed
VAT Leaching
Leach ReagentMakeup
Water Leach Reagent
Cyanide Dilution
Water Cyanide Reagent
SXExtraction
SX PLS FeedRaffinate return to VAT
SXStripping
Loaded OrganicStripped Organic
Electrowinning
Loaded ElectrolyteStripped Electrolyte
Cu Plates
Gold Extraction
Pregnant Solution
Barren Solution
Zn Dust
Mined Ore
Metal Concentrate
Neutralising Reagent
Sulphuric Acid
Water
Organic Supply
Impurity Bleed
12
Crushing and Screening
Plant feed stockpile
Site offices & workshops Water Storage
SX, EW & Stripping
2019/12/02
3
Project Description: Ore Processing – Leaching Alternatives
13
Dump Leach Heap Leach In-Situ Leach VAT Leach Tank LeachCrushing Yes Yes No Yes YesAgglomeration No Yes No No NoMilling No No No No YesTailings Dam No No No No YesWater Required High High High Low HighWater Recycling Med Low Med High LowEnergy Required Low Med Low Low High
Tulela AdditionCover
RequiredSpecial Conditions Required? No No
Impermeable Layer No No
Residence Time High High High High LowPerformance Medium Med - High Med - High Med - High High
Project Description: Ore Processing – Leaching Alternatives
14
• Tank Leach: • High capital cost and water required.
• Heap leach:
• Surface area of the heaps require a considerable amount of water addition due to evaporation.
• VAT leach: • VAT is typically flooded with leached solution.
Project Description: Ore Processing – Leaching Alternatives
15
• Hybrid VAT / Heap leach: • VAT is drip irrigated with leached solution.
• To reduce water consumption and foot print - combined the VAT and heap leach concept
• Added plastic cover - reducing water locked up in the ore; reduce water evaporation significantly.
• Acid leach being considered.
Project Description: VAT Leach System design
16
Side and bottom
Plastic lining
Top Plastic lining
Drip Irrigation
(Drawing not to scale)
Project Description: Phase 2
17
Exploration• Further exploration for copper (and gold / silver) mineral will
be done on the Sinclair mine area (only): Extended resource drilling.A box cut sample - further excavation of the existing cut in the hill.
Project Description: Phase 2
18
Mining• Relatively “small scale” mining activitiesDependent on the future exploration resultsConventional open pit mining (i.e. drill and blast followed by
load and haul activities)One DozerOne Excavator Two Loaders Four articulated Dump Trucks (30 ton each)
• The possible mine pit footprint: ±7.8 ha in size• Open cast mining to depths ranging between ± 5 and 30 m
depending the exploration results• Waste rock would be disposed of at the WRD (i.e. waste
rock dump)
2019/12/02
4
19
Project Description: Phase 2
20
Processing of the mined ore• Future mined ore will be hauled to the ‘Plant feed stockpile’
and similarly processed in the proposed (multiple) VAT leach vessels and SX, EW & Stripping Plant, as previously described.
• Estimated feed rate of ore: ± 50 t/hr to the crusher and thereafter to the VAT leach area
Project Description: Water supply
21
• Exploration: ±50 m3 / annum • Mining and processing: (estimate) 40 000 m3 / annum
(90 - 120m3/day)• Water will be sourced from nearby borehole(s) on the farm.
Project Description: Power supply
22
• The entire site will be powered by diesel generators.
Project Description: Site Access
23
• A new road is to be graded.
Project Description: Employment & Accommodation
24
Construction Phase• ± 20 people (estimated)• ± 4 month construction period.
Operational phase• ± 20 people (80% skilled. It is estimated that about 70% will be
fix term contractors and 30% permanent). • A 4 shift cycle team of 5 people per shift will be required,
including the supervisor.
Accommodation • Three options:
Site base camp on the mining lease; Accommodation on adjacent farm; orAccommodation in Helmeninghausen.
2019/12/02
5
EIA Process
25
Aug - Sept ’19
Screening & initiation
Sept – Oct ‘19
• Registration period, advertise,distribute BID, etc. receive initial comments
• IAP meetings
Oct ’19
Finalise specialist investigations
EIA Scoping & Assessment
Report and EMP
Oct ’19
IAPS review of reports
Nov ’19
Finalise reports with
IAP comments & submit to MME & MET
Authority review and decision-making
Key Potential Issues
26
Groundwater and Surface water impacts: • Groundwater contamination; • lowering of groundwater level due to pumping from on-site
borehole(s);
Surface Water:• Alteration of drainage patterns and pollution of surface
water.
Key Potential Issues
27
Air Quality: • Potential air pollution as a result of dust from exploration and
mining activities, i.e. trucks, machinery, etc., impacting on third parties’ health and causing nuisance.
Noise: Increase in ambient noise causing disturbance/nuisance.
Key Potential Issues
28
Biodiversity: • Physical destruction and general disturbance of biodiversity.
Archaeology: • Destruction and damage to archaeological sites and
landscapes.
Socio-economic:• Potential negative impacts on current (surrounding) land use
activities; health and safety concerns to nearby land owners; nuisance-related disturbance; impacts relating to mining staff on site.
• Positive economic impacts associated with income and employment.
Key Potential Issues: Groundwater - supply
29
Water supply from borehole WW70293• Test
pumping of WW70293
BH
Id
Test type
RWL
[m bgl]
PID
[m bgl]
Discharge rate
[m3/h]
Test Duration Max. WL drawdown
[m]
Residual drawdown
[m]Pumping Recovery
WW70293STD 24.89 35 2,3,5 3 0.32 0CDT 24.89 35 5 24 24 0.35 0
Borehole Id Maximum abstraction rate Expected pump water level
Pump inlet depth Use
m3/h hours/day1) m3/day [m bgl] [m]
Sinclair Windmill 10 12 120 28 35 Sinclair Mine
31
2019/12/02
6
Sinclair Mine Groundwater Monitoring• Planned drilling of 2 production/monitoring boreholes
30
Way Forward
32
• Comments received to date and during this meeting will be included in the Draft EIA Scoping & Assessment Report.
• Draft Report will be distributed for comment: Towards mid-October 2019.
Attention: Werner Petrick
E-mail address: [email protected]
Cell number: +264 (0)81 739 4591
Questions / Comments ?
33
NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS
PROPOSED SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT THE SINCLAIR MINE, ±50 KM NORTHWEST OF HELMERINGHAUSEN, KARAS REGION.
Cathral Investments Ninety One (Pty) Ltd herewith gives notice in terms of the Environmental Management Act, 7 of 2007 and Regulations 19 and 21 of the Environmental Impact Assessment (EIA) Regulations (January 2012), of the proposed mining, processing, exploration and associated activities at the Sinclair Mine.
Prior to conducting the proposed activities, an EIA process will be conducted and an application for an environmental clearance certificate will be submitted to the Ministry of Mines and Energy (MME) as the competent authority who will review and forward the application to the Ministry of Environment and Tourism (Environmental Commissioner) in terms of the above mentioned regulations. This advertisement forms part of the EIA public participation process.
Applicant: Cathral Investments Ninety One (Pty) Ltd (i.e. Cathral Investments).
Nature and location of the proposed activity: The Sinclair Mine is located in the Lüderitz district, Karas Region, approximately 50 km northwest of Helmeringhausen, on the Sinclair Farm. Extensive exploration and mining programmes have previously been carried out at the Sinclair Mine by various companies.
Tulela Processing Solutions (Pty) Ltd (i.e. Tulela), a wholly-owned Namibian Metallurgical and Mining company, holds majority shares in Cathral Investments. Cathral Investments / Tulela proposes to process existing surface ore stockpiles from historic mining activities; and to conduct further exploration, mining and processing (of future mined ore) activities, to extract copper and to possibly recover small quantities of gold and silver, at the Sinclair Mine.
Independent Environmental Assessment Practitioner: Namisun Environmental Projects & Development (Namisun) has been appointed by Tulela as the independent Environmental Assessment Practitioner to undertake the EIA process for the proposed project.
Contact Person: Werner PetrickTel: +264 (0)81 739 4591E-mail: [email protected]
Registration to receive notifications and information: Register as an Interested and/or Affected Party (IAP) with Namisun by submitting your comments, full name and contact details by email, or by contacting Werner Petrick. A Background Information Document (BID) is available for a review and comment period from 13 to 27 September 2019. Electronic copies of the BID are available on request from Namisun as per above details.
An information-sharing meeting will be held at the Sinclair Farm:
Date: 2 October 2019
Location & venue: Sinclair Farm Homestead
Time: 9:00 am
For issues and/or comments to be included in the Scoping Report forward them to Namisun by no later than 27 September 2019.
DM0201900345853_IK
EIA FOR SMALL SCALE MINING & PROCESSING ACTIVITIES AND ONGOING EXPLORATION AT THE SINCLAIR MINE ON
EXCLUSIVE PROSPECTIVE LICENCE (EPL) 6545, KARAS REGION
ISSUES AND RESPONSE REPORT
TABLE 1: COMMENTS / QUESTIONS / ISSUES RAISED DURING THE BID REVIEW AND REGISTRATION PERIOD AND DURING PUBLIC AND KEY STAKEHOLDER
MEETINGS
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
General / EIA process
G1 Welwitschia Minerals and Hydrocarbons received an environmental clearance from MET in 2018. How and why was this possible without public participation? Will the MET official responsible in 2018 just rubber stamp the current EIA again?
JDS Miller Email Cannot comment on the previous EIA process that was conducted. Refer to section 10 (Environmental Impact Statement and Conclusions) of the EIA report relating to the current EIA.
G2 If agreements are reached between the mine and the local community regarding any potential disruptions to the community’s daily activities and also long-term livelihood, how are these agreements monitored and enforced?
Contractual agreements will be signed, where relevant.
G3 Where is the Sinclair house located in relation to the mine?
Farm owners Public meeting (2nd of October)
Refer to sections 1.1 and 5.8.2.7 of the EIA Scoping & Assessment Report.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
G4 How much power is required? ±1 MW (EW use the most power). Refer to section 4.2.6 of the EIA Scoping & Assessment Report.
G5 The EPL holder is Cathral Investments. Do they do other project as well?
Cathral Invests is a consortium of investors for this project alone, although Tulela, as a majority shareholder, is involved in various other operational sites in the Africa Continent.
G6 Does Tulela have 3rd party insurance in
terms of liabilities?
I.e. field fires, water losses, etc.
Yes, this will be in place prior to the implementation of the project.
Noise
N1 I see diesel generators will be used for power supply. I am concerned about the noise from the generators.
Will it make noise also at night?
Marc Pampe (Sinclair farm owner)
Telephonic meeting (10th of September)
The electro winning and SX will run 24/7. None of the other activities (i.e. earth moving activities, crushing, etc.) will be undertaken during the night time. The generators will however have to run 24/7.
The diesel generators will be enclosed in a container to minimize the noise. A noise specialist was appointed as part of the EIA team to assess the potential noise impacts from the proposed activities and provide management and mitigation measures regarding these issues.
Refer to section 8.6 of the EIA Scoping & Assessment Report.
N2 Will the activities be 24/7? Concerned about noise at night.
N3 Concerned about the noise from the electricity generators.
Farm owner Public meeting (2 October 2019)
Technical issues (Processing, mining, exploration, etc.)
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
T1 Will the further exploration only entail drilling, or will there also be further trenching.
Marc Pampe (Sinclair farm owner)
Telephonic meeting (10th of September)
Only drilling and a box cut sample will be taken by further excavation of the existing cut in the hill. Size of excavation will depend on the exploration outcome.
T2 Will holes be covered up after drilling With reference to the EMP, the Exploration boreholes should be capped.
The boreholes will be marked as it must still be accessible for possible future use.
T3 How high will the waste rock dump (WRD) be? Will this be a new mountain?
The only material that will be disposed of at such a WRD facility will be overburden from the mining and associated activities. The volumes of WRD is unknown at this stage.
However, an estimated ±100,000 ton waste rock might be produced. The height will be approximately 10 m.
T4 Where is the Sinclair homestead located in relation to the mine?
Farm owners Public meeting (2 October 2019)
Refer to sections 1.1 and 5.8.2.7 of the EIA Scoping & Assessment Report.
T5 Explain the difference between VAT leach and Heap leach.
A Combination of the two will be used in order to reduce fresh water consumption.
T6 What is meant with agglomeration? No agglomeration will be done as part of the process.
T7 Where will you add an acid solution? At the SX section of the process.
T8 How high is the VAT/Leach facility? What will be the overall dimensions of the VAT/Leach facility be?
±6 m (refer to section 3.1.2 of the EIA report).
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
T9 What volumes of crushed material will go onto each VAT?
± 200,000tons.
T10 The Background Information Document (BID) mentioned DMS and Spirals. Where are those (not mentioned in the presentation)?
The process design has changed since the time the BID was developed. However, with reference to section 4.2.1.1, Tulela might in future change the design again to re-introduce the installation of the Dense Medium Separation (DMS) and a spiral gravity circuit for treatment of the screened material before leaching.
T11 Why were these taken out?
T12 Will you screen the material before it goes onto the VAT/leach facility?
Yes.
T13 Will the material in the VATs be neutralised? How will the neutralising differ between the Acid and Alkaline leaching processes?
Yes. Refer to section 4 of the EIA report.
T14 Will all material be crushed & Screened. How long does the crushing & screening take? Will it be done 24/7?
Yes. This will only be conducted during daytime hours.
T15 Why conduct exploration after processing starts? This seems to be the wrong way around.
These two processes would run in parallel (to a certain extent). Refer to section 4 of the EIA report.
T16 Does the processing remain the same for phase 2?
Yes.
T17 Will you use existing boreholes or drill new ones for the water supply to the mine?
New holes will be drilled, which will also be used for monitoring purposes.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
T18 What chemicals will be used and where will chemicals be stored?
Organic compounds and sulphuric acid / ammonia. Refer to the EMP requirements relating to storage of hazardous substances.
T19 Is there no low grade stockpile / dump? No.
T20 Will there be Crushing plant? Yes.
T21 There is lots of quarts that could damage the crusher.
Noted.
T22 What will be the width and depth of the box cut? There might be lots of waste?
This depends on the exploration results.
T23 What will be the tonnage of ore from box cut?
T24 What grade is expected?
T25 What are the copper minerals? Primary mineral is Malachite.
T26 Gold would be negligible. Noted.
T27 How long will the liners in the VAT/ Leach facility last?
The liners will not be exposed to the sun and is expected to last for decades.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
T28 Will the material stay in the VATs? Yes.
T29 What will be used to neutralise the material in the VATs?
Refer to section 4 of the EIA report.
T30 From where will the neutralising material come?
It will be purchased.
T31 Will calcrete from the area be used the neutralise the VAT? If this is mined, what will be the impacts?
No.
T32 What will happen with final effluent from the VATs?
It will evaporate in the ILS pond. The crystalized residue will be removed and disposed of at a licensed hazardous waste site. Refer to section 4.2.1.4 of the EIA Scoping & Assessment Report.
T33 How long will the alkaline leaching take in one VAT?
Unknown at this stage.
T34 Will permeability play a role in leaching process?
Yes.
T35 What will the average grades be left behind in VATs?
Unknown at this stage, however the target less than 0.5 %.
T36 What if the grade of gold and silver is not good?
Then it will not be processed.
T37 If recovery of copper is much lower than expected but precious metals is good, will you then process this only?
Yes.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
T38 Will there be no slimes dam (i.e. Tailings storage facility)?
No.
T39 During the operational phase, a 4 shift working cycle will be required. Does this mean that mining operations will be carried out throughout the night? What hours of operation are envisaged?
JDS Miller Email Refer to section 4.4 of the EIA report.
T40 Roy Miller Email Refer to section 4.3 of the EIA Scoping & Assessment Report and various related management plans in the EMP.
T41 How often do you sprinkle your leach dams before pumping to the SX plant?
Continuously.
T42 How and what with do you finally cover the leach dams once all leaching and neutralization is complete?
Refer to section 4.2 of the EIA report.
T43 You indicate that the leach dams will be covered during leaching. How then do you get the leach solutions into the crushed ore?
Drip irrigation will be used.
T44 How long before all cyanide is neutralized?
Unknown at this stage.
T45 What are the alkaline chemicals you use in the leaching dams?
Ammonia solution.
T46 How do you get effective penetration of the cyanide neutralizing solutions into the finely crushed waste in the leach dams?
Drip irrigation.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
T47 What are the daughter products of that neutralization process?
Nitrogen and water for Ammonia breakdown and also Nitrogen for Cyanide.
T48 With what do you neutralize the cyanide remaining in the leach dams?
SMBS.
T49 What do you precipitate Au and Ag with? Zinc dust.
T50 Will the alkali leach process release Au and Ag from the minerals that they occur in.
No. Alkaline is only used for copper leaching
T51 How often do you sprinkle your leach dams with cyanide before pumping out the leachate?
Continuously.
T52 Cyanide extraction – what cyanide compound do you use?
Thiocyanate solution.
T53 “Multiple VAT Leach Vessels will be constructed….” . How many?
JDS Miller Email Refer to section 4 of the EIA report.
T54 After DMS, the high grade concentrate will be sold as product, and the low grade material will go to the VAT leach dams. What is the tonnage of high grade concentrate expected to be, and what transport logistics will be required?
This process has changed since the BID was developed. Refer to section 4 of the EIA report.
T55 Will the copper be in the solution coming from the VAT System?
Marc Pampe (Sinclair farm owner)
Telephonic meeting (10th of September)
Yes.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
T56 Is it a Closed Cycle? With the solution therefore be pumped back into the VAT?
Yes.
T56 After neutralising the material inside the VAT, what will happen with the solution? Will there be any discharge of the “Neutralised solution” into the environment”?
The remaining solution will evaporated in the ILS pond.
T57 What happened at the last / final VAT. Will the “neutralised solution” from this VAT have to be discharged?
T58 Can one VAT be used more than once Each VAT will only be used once.
T59 Will the plastic line stay behind after the VAT become redundant?
My concern is that the plastic will demolish from the sun and be blown around.
The plastic liner will have to be covered with soil / topsoil and vegetation growth allowed. This would form part of the rehabilitation strategy.
T60 Is it therefore part of the planning to add soil on top of the VAT?
Yes.
T61 Will there be any harmful chemicals staying behind? Howe affective will the neutralization be?
Unlikely. The compounds will be in steady state.
T62 Will it be entirely an open pit? Why one big open pit? It should rather be various smaller pits / box cuts along the areas where the ore is found due to the fact that there will likely be various areas between the ore veins without any ore.
Farm owner Public meeting This is depended on exploration results. The EIA however assessed a “worst case scenario”.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
T63 What happens to this solution after EW extraction of the copper?
Roy Miller Email Recycled to SX.
T64 What happens to the cyanide solution after precipitation of the Au and Ag?
Recycled back to the VATs.
T65 What are your plans for avoiding slimes dam failures during operations and for decades into the future
There will be no slimes dams.
T66 What chemical is used to release the copper back into solution from the SX compound?
Sulphuric Acid.
T67 What happens to leachate solution after SX extraction of the copper?
Recycled back to the VATs.
T68 What compound is used for SX? Organic compounds.
T70 During the operational phase, a 4 shift working cycle will be required. Does this mean that mining operations will be carried out throughout the night? What hours of operation are envisaged?
JDS Miller Email Refer to section 4.4 of the scoping report.
Water
W1 There is not regional aquifer in the area. Roy Miller Email The potential impacts on groundwater (i.e. potential groundwater quality impacts and impacts due to groundwater abstraction) was assessed by the Water Specialist Team, i.e. SLR Environmental Consulting. Refer to Appendix G of the EIA Scoping 5.5 and 8.3 of the EIA report.
W2 Should this submitted proof be inaccurate, how will you compensate surrounding farmers for falling water
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
tables in their boreholes and for drying up of boreholes?
The EMP also provide relevant management and mitigation measures and morning requirements.
W3 With the need for this amount of water, the Ministry of Agriculture, Water and Forestry (MAWF) must also be informed of your activities and plans and you will need their approval for the abstraction of that amount of water. This approval will depend on whether you can prove that water boreholes/wells in the area will not be affected by your abstraction. This proof that you give to MAWF must be part of you EIA report and must be circulated to all IAPs.
W4 Apparently, some pump tests have been done. We need to have the details of these tests sent to all IAPs before the meeting on the 2nd October. This MUST include all the graphics produced during the pump tests.
W5 There is no borehole in the area that comes anywhere near this daily requirement.
W6 With plant, human usage and exploration drilling you will need 125 m3 of water per day according to the numbers you present in your Background Information Document.
W7 With an estimated ore feed rate of 50t/hour, how much water will be required in the DMS stage of ore processing?
JDS Miller Email
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
W8 Have any groundwater samples from the area been analysed yet to establish baseline values for the monitoring of the water quality? Is a monitoring program in place yet?
W9 The estimated water requirements of the project will have a devastating effect on the surrounding groundwater aquifer, exceeding the expected lifespan of the mine by far.
Thorsten Theile Email
W10 How is the wastewater treated and what measures are in place to avoid environmental contamination?
W11 Will water to the mine come from the ground?
Farm owners
Public meeting (2nd of October)
W12 The proposed new borehole location is a good location for groundwater monitoring.
W13 We are concerned about the water abstraction as the mine will be pumping for many days/ weeks/months. How will this impact the other groundwater users in the area?
W14 The water table is a concern. The water
requirements for the mine is an order of
magnitude difference of water used by
farmers. Also, the average rainfall in the
area is very low and we are concerned
about the recharge of the groundwater.
Neighbouring could be affected. Should the groundwater monitoring not also be extended to neighbouring farms as well?
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
W15 The groundwater abstraction could be a
long term impact, extending beyond the
operations of the mine.
W16 Ideally long term monitoring data is
required.
W17 An independent person should do the
monitoring.
W18 Where will water be stored?
W19 Will the geology be described?
Feasibility
F1 No mention is made in the scoping report about a recent detailed exploration programme report
Roy Miller Email The questions / comments in this section relate (mostly) to the “Feasibility of the proposed project”. The feasibility the project (i.e. to establish whether the project would be feasible or not) is not part of the scope of the EIA. However, an associated issue relating to this relate to the risk of closure or even ’early closure’ of the mine and whether there will be funds available for closure and rehabilitation requirements.
F2 Is there a feasibility study? Is the project Economically feasible?
Farm owners Public meeting (2nd of October)
F3 What method did you use to assess, explore & determine the feasibility?
F4 How was the sampling done? How many samples were taken?
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
F5 It is not a representative sample of the area – it is a risk.
Refer to the Mine Closure Strategy (Appendix A to the EMP) as well as further specific Mine Closure Questions below.
F6 The BID referred to “ore stockpiles”. That is wrong terminology. Is should be regarded as “waste dumps” with some copper.
F7 It is on record that the ore reserve
estimate is 3%. Valuable ore have been
“hand-picked already by historical mining
activities.
There is a risk that too little samples
were taken by Tulela to determine
whether it will be a feasible project.
The risk lies in the fact that, if there is no
income from the project, there will also
be no money for rehabilitation - as part of
closure.
There needs to be a fund for the closure / rehabilitation.
F8 What is the difference in permeability
between the current stock piles and
future mined ore?
What will the difference be in particle
size?
F9 Without agglomeration you will not get
permeability.
F10 What is the expected copper recovery?
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
F11 What is the concentration of copper in
the low grade stream expected to be and
how much of this will be recovered by
the leaching process?
F12 Have the silver and gold concentrations
in the surface ore stockpiles been
determined yet.
F13 What fraction of any gold or silver is
expected to be recovered by the VAT
cyanide leaching process?
F14 No mention is made in the scoping report about a recent detailed geological report.
Le Roux van Schalwyk
F14 No mention is made in the scoping report about a recent detailed feasibility report.
Environmental Impacts
E1 All IAPs need to see and understand your detailed Environmental Management Plan.
Roy Miller Email Noted. Refer to Appendix J of the EIA Scoping & Assessment Report for the EMP.
E2 What specialized investigations are being carried out?
Refer to sections 1.3 and 8 of the EIA Scoping Report and Appendices E to I.
E3 What are your plans to avoid and mitigate impacts?
Refer to section 8 of the EIA Scoping Report and Appendix J for the EMP.
E4 What plans do you have to ensure that construction and operational employees
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
have no contact whatsoever with farmers and farm workers in the area.
E5 What are your plans for dust suppression during operations and for decades into the future?
E6 There are various endemic biodiversity species in the area and they are seasonal. It is currently a bad time of the year for plants as there are were no rains yet. Locals need to look at the species list.
Farm owners Public meeting (2nd of October)
Noted. The Biodiversity Specialist is aware of this. Specialist lists were shared by locals and considered by the Biodiversity Specialist.
E7 Will there be dust suppression on the crushers?
Refer to section 8 of the EIA Scoping Report and Appendix J for the EMP.
E8 Will there be dust suppression?
E9 The MAWF will have to be part of the EIA. The MAWF is part of the IAP database and the relevant reports (i.e. BID and EIA Scoping and Assessment Report) shared with them.
E10 All potential impacts must be considered as part of the EIA and management and mitigation measure developed in included in an EMP.
Refer to sections 7 and 8 of the EIA Scoping Report and Appendix J for the EMP.
Socio – economic – including Community Health and Safety, tourism, traffic, economy, etc.
S1 Introducing 30 – 50 mine employees, which in all likelihood will be 90% male will have a disturbing effect on the farming community in the surrounding area, i.e.
Thorsten Theile Email Potential impacts from the workers were assessed. Refer to Appendix H and section 7 of the EIA Scoping & Assessment Report. Refer to the EMP for relevant management and mitigation measures.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
labour force related, threat to game & livestock, etc.
S2 What is the impact of this project on tourism in the area?
Potential Tourism impacts were considered. Refer to Appendix H and section 7 of the EIA Scoping & Assessment Report.
S3 Increased heavy traffic on the gravel roads. Already not coping with the current traffic load will lead to even faster deterioration of this infrastructure
Potential traffic related impacts were considered. Refer to sections 4.2.8 and 7 of the EIA Scoping & Assessment Report.
S4 Tourism is important for the area. Farm owners Public meeting (2nd of October)
Potential Tourism impacts were considered. Refer to Appendix H and section 7 of the EIA Scoping & Assessment Report.
S5 Land use needs to be considered in the EIA?
A detailed description of the current / receiving environment is provided in section 5 of the EIA Scoping & Assessment Report.
S6 Workers might be an issue regarding community safety. Also, drug use and dealing with drugs s are issues in the area.
Potential impacts from the workers were assessed. Refer to Appendix H and section 7 of the EIA Scoping & Assessment Report. Refer to the EMP for relevant management and mitigation measures.
S7 How will the housing for the workers be handled.
Marc Pampe (Sinclair farm owner)
Telephonic meeting (10th of September)
Refer to section 4.2.9 and 6.4 of the EIA Scoping and Assessment Report.
Mine Closure and Rehabilitation
MC1 Plan for mine closure. Specifically, for early mine closure.
Roy Miller (Farm owner)
Email Refer to section 4.4 of the EIA Scoping and Assessment Report and the Mine Closure Strategy in Appendix A of the EMP.
MC2 A Mine Closure Plan (including closure costing) needs to be developed. A key issues is, should the project not be
Farm owners Public meeting (2nd of October
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
feasible, there needs to be budget for properly closing the mine and conducting effective rehabilitation
MC3 Once leaching is done how will the VATs be closed and rehabilitated?
MC4 Topsoil needs to be removed prior to the construction activities / clearing of areas; separately stockpiled and used during the rehabilitation at closure. Also, to get the rehabilitation “going” the topsoil (once placed back) might require some water.
Refer to Section 8.4 of the EIA report and the EMP for topsoil Management.
MC5 After mining, what will happen? There must be a funds for mine closure / rehabilitation from the beginning of the project.
Refer to section 4.4 of the EIA Scoping and Assessment Report and the Mine Closure Strategy in Appendix A of the EMP.
TABLE 2: COMMENTS RECEIVED ON THE DRAFT EIA SCOPING / ASSESSMENT REPORT AND EMP DURING THE REVIEW PERIOD BY IAPS
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
General
G1 On page 19, 4.1.2 – Cathral Investments Shareholders:
Morne Du Plessis – 20%
Morne Du Plessis was the person who received an Environmental Clearance Certificate on the 08.10.2018, as attached.
No Public Participation Process ever happened. No stakeholder was consulted. On the 07.12.2018, Morne Du Plessis signed the Surface Rights Agreement, where it was stipulated, that certain compensations must be paid to Marc Pampe on a monthly basis.
The effective date of the agreement was the 07.12.2018.
Invoices were send to Morne Du Plessis on a monthly basis.
To date no payment was effected by Morne Du Plessis.
It is of great concern, that Morne Du Plessis, with all his short comings, ignoring the signed document between him and myself, is a 20% stakeholder/shareholder in Cathral Investments.
My faith, trust and confidence levels in Cathral Investments are negatively impacted by this.
Marc Pampe (Sinclair farm owner)
e-mail Please note that the previous EIA was conducted by a different company / Applicant and Cathral Investments / Tulela did not form part of this company. Also at that time, Morne Du Plessis was not a shareholder of Cathral Investments. Cannot comment on the previous EIA process that was conducted. Refer to section 10) of the EIA Scoping & Assessment Report relating to the Environmental Impact Statement and Conclusions of the current EIA. Cannot comment on previous agreements. Cathral Investments / Tulela was not part of those agreements. New contractual agreements will be signed, between the landowner and Cathral Investments / Tulela.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
This makes for a unhealthy relationship between Cathral Investments and me the owner of the farm.
G2 “Attached please find The EIA and EMP with my editing comments. Without a Closure and Restoration Plan, the EMP is incomplete”.
Roy Miller
(Neighboring
farm owner)
e-mail Various comments were made directly in the EIA Scoping and Assessment Report, EMP and IAP database by Mr. Miller – as “comments”.
These are not all be included in this table. However, the key comments (or questions) made in the Scoping/Assessment Report and EMP are included in the relevant sections below.
Other comments made to the EMP were considered and the EMP amended, where relevant.
The IAP database was updated.
G3 Original statement in EMP (section 4.2.2): “Some of the waste rock will be used for construction of the VAT/Heap Leach facility”.
Question:
What waste rock are you talking about? According to your plans, you intend starting immediately with VAT/heap leach. All the present dumps you call ore stockpile. Thus, without any mining at the start of the processing you do not have any waste rock to construct VAT/heap
Roy Miller
(Neighboring
farm owner)
e-mail (comment in EMP)
The sentence in the EMP was changed to elaborate more on the specific material tpo be used:
“Some of the waste rock produced while doing surface treatment / levelling for the VAT/Heap leach will be used for construction of the VAT/Heap Leach facility”.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
leach facilities. This does not make sense.
Topsoil
S1 Section 3.1.2 of the Scoping/Assessment Report (Leaching – top of VAT/Heap leach vessels):
“Top cannot be covered with top soil as the chemicals will destroy the micro-organisms that are critical to keeping the top soil viable for the healthy rooting of plants which will be part of the rehabilitation process. Furthermore, there is very little top soil in the area and this has to be retained for final rehabilitation and not used in the processing of ore”.
Roy Miller
(Neighboring
farm owner)
e-mail (comments made in the report)
This section was amended in the report. The intension is to cover (on top) the facility with a plastic lining.
At closure, the entire VAT/Heap leach vessel (with the bottom, side and top plastic liner remaining) will be covered with waste rock material and then topsoil. The final Mine Closure Plan, however still needs to be developed – as described in the EMP and the Mine Closure Framework provided as Appendix A to the EMP.
Water
W1 The rainfall data for Farm Sinclair, for the last four rainy seasons is the following:
2015/2016 – 78mm
2016/2017 – 67mm
2017/2018 – 46mm
2018/2019 – 12mm
It is not accurate to use the average rainfall data of Farm Aruab – Farm Aruab
Marc Pampe (Sinclair farm owner)
e-mail The rainfall baseline data was updated in the Water Specialist Report under section 2.2.1 taking into consideration most up-to-date rainfall information as well as rainfall stations that are closest to the Sinclair mine. To that effect a composite rainfall record was thus developed and re-assed to give a more realistic rainfall picture in the local area. These amendments were included in the EIA Scoping & Assessment Report (section
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
has a much higher average rainfall than Farm Sinclair.
Farm Aruab lies in the mountains and it is well known that the average rainfall is higher in that area than at Sinclair.
5.1.2.2), taking this information provided into account. Furthermore, this information was considered in the assessment of impacts relating to the groundwater abstraction activities. The Water Specialist Report and the EIA Scoping & Assessment Report (section 8.3) was amended accordingly. However, the overall significance rating, in the mitigated scenario, has not changed.
W2 I have gone through the EIA and EMP for Sinclair, and have attached my comments. I have also attached Sinclair rainfall data that was given to me by the previous owner, Mrs. Hannelore Hoffmann. Although there is a gap in the data, it is more relevant to the project than the rainfall data from Aruab.
Jörn Miller
(Neighboring
farm owner)
W3 Section 5.1.2.2 of Scoping/Assessment Report (Rainfall):
Why does the Aruab data not extend to 2018. Data from 2004 to 2018 is available. This data is relevant to the present drought and to the fact that the project intends to pump up to 120 m3 per day of water from underground sources.
Roy Miller
(Neighboring
farm owner)
e-mail (comments made in the report)
W4 The rainfall situation is not correct. On Campbells Valley (Mount Valley), neighbor farm to Sinclair, the average farm rainfall was:
2012/2013: 32,2 mm,
2013/2014: 86,5 mm,
2014/2015: 47,3 mm,
2015/2016: 39,3 mm,
2016/2017: 35,6 mm,
2017/2018: 100,1 mm,
2018/2019: 0 mm.
Christa and
Ruediger
Hennings
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
W5 Surface Water (Report Par. 8.2)
Although the storm water management plan foresees the mitigation/avoidance of
contamination of surface water during normal operations, it does not make any mention of what measures are to be undertaken if there is any breach of the VAT leach dams or any other reservoirs filled with dangerous liquids and a subsequent accidental contamination of the surface water. Furthermore I did not see any mention of how a possible contamination is then reversed should it occur irrespective of preventative measures being in place. The client must have processes in place to recover/reverse any contamination of surface water in case of an accident as part of the EMP.
Thorsten Theile
(NAMTIB
Biosphere
Reserve)
e-mail In Section 5.2 of the water specialist report safeguards against surface water contamination have been addressed. In that regard, process material in the VAT/Heap Leach Vessels is in pulp or slurry form (not liquid), therefore it will not flow when the vessels breach. However, the requirement for emergency measures to contain and remove the slurry has been recommended to be in place to address the breach of VAT vessels, was added the Water Specialist Report, the EIA Scoping & Assessment Report and the EMP (Surface Water MP).
W6 Reduction in Groundwater Levels (Report Par. 8.3.1).
Even though the groundwater report has shown that the impact of the mining activities may be moderate to low at the proposed maximum abstraction rate, these assumptions are based on short term tests only and with very little knowledge of the local aquifer formations. It should be kept in mind that once a significant drop in water levels can be noted within the area, the damage has already been done and based on the historic local rainfall figures, recharge of the water table will definitely take much longer than the duration of the project.
Thorsten Theile
(NAMTIB
Biosphere
Reserve)
e-mail Section 5.3 in the water specialist report where it is highlighted that “in the absence of pertinent data required to quantify resources and define limits for abstraction measures to collect such data should be in place in the form of a groundwater management plan forming part of this assessment. The monitoring plan includes the groundwater levels and groundwater quality in production and monitoring boreholes on farms Sinclair and Aubures, as well as metered abstraction volumes from production boreholes” This in addition to recommendations to drill additional abstraction boreholes will reduce stress on the current envisioned production borehole.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
Additionally the report should also include the consequences for the client, should the abstraction exceed the recommended limit and/or cause the groundwater level to drop, i.e. there must be a financial implication for the client if either is the case in the form of a penalty to be paid to the landowner / neighboring farms affected.
With the above measures in place to collect necessary information that will be used to update the monitoring plan as well as firm up additional measures that will be required to mitigate impact on other users. A measure is in place for contingent water supply to users in the event that water level drop proven to be caused by mining operations. Another action included in the EMP, to address the specific comment, is to reduce pumping rates in case water levels in production boreholes drop to levels deeper than expected - to stabilise the water level. Specific actions have been included in the EMP for the event that groundwater abstraction for mining activities has been proven to affect other users.
W7 Contamination of Groundwater (Report Par 8.3.2)
Contamination of the groundwater is probably the worst that could happen during and after the mining process. The client should also be obliged to supply a written guarantee on the lifetime of the lining used for the VAT leach dams. Furthermore, the same comments apply as mentioned in Paragraph 1 above with the addition of financial penalties to be implemented for the client should a contamination of the groundwater take place.
Thorsten Theile
(NAMTIB
Biosphere
Reserve)
e-mail With reference to section 3.1.4 of the EIA Scoping & Assessment Report, the material in the VAT/Leach Vessels will be neutralized post the extraction process. Therefore, the potential for groundwater contamination impacts would reduce. Furthermore, an action in the EMP requires that Tulela need to line the facility with long-term durable lining to prevent seepage of contaminants into the groundwater. With reference to Appendix A of the EMP, a Mine Closure Framework was developed. The requirement for Tulela to develop a Mine Closure Plan is specified and the relevant closure objectives, key
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
environmental values and closure needs are provided. The requirement for monitoring after closure is also one of the items to be further developed as part of the Closure Plan.
W8 The water which ‘Cathral’ will need daily is only estimation. Maybe ‘Cathral’ take 200.000 Litre or more daily. It is not said, what the maximum is ‘Cathral’ can take without the boreholes and the environment in the neighbourhood will collapse.
Christa and
Ruediger
Hennings
e-mail The maximum (allowed) abstraction rate is included in the EMP. Refer to Action 2 in the Groundwater Management Plan.
W9 I have gone through the EIA for the Sinclair Project and I remain extremely concerned about the water requirements for the project. I feel very strongly that the potential impact on groundwater reserves should be classed as “high” especially considering the aridity of the area, and the fact that depletion of this resource will have an impact well beyond the envisaged life of the mine.
Furthermore, steps to mitigate the impact should not only include a program of monitoring the groundwater, but also a well defined set of depletion limits and the clear stipulation to cease abstraction should these depletion limits be reached. (Drilling a borehole deeper to get more water is not a mitigating step because it only facilitates further depletion of the resource.)
My arguments to have the ground water impact classed as “high” are as follows:
1. The water requirement of 90 to 120m3 per day, is between ten
Jörn Miller
(Neighboring
farm owner)
e-mail Section 5.3 in the water specialist report where it is highlighted that “in the absence of pertinent data required to quantify resources and define limits for abstraction measures to collect such data should be in place in the form of a groundwater management plan forming part of this assessment. The monitoring plan includes the groundwater levels and groundwater quality in production and monitoring boreholes on farms Sinclair and Aubures, as well as metered abstraction volumes from production boreholes”
This in addition to recommendations to drill additional abstraction boreholes will reduce stress on the current envisioned production borehole.
With the above measures in place to collect necessary information that will be used to update the monitoring plan as well as firm up additional measures that will be required to mitigate impact on other users.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
and twenty times higher than the extraction rate that groundwater resources in the area are normally subjected to.
2. The pumping rate of 5m3/hour that the mine requires is more than double the average yield (1.95m3/hour) of boreholes in this area.
3. The size and extent of the groundwater resources to be pumped are completely unknown factors.
4. Sinclair is a very arid farm where groundwater recharging events are even less predictable than the rainfall. In this respect, it must be pointed out that the use of the Aruab rainfall data in the climatic baseline description is inappropriate and highly misleading. The Aruab rain gauge is situated at 1600m (above sea level) on the eastern slopes of the “Rooi Rand” Escarpment, some 3 km from the north-south trending watershed. Sinclair on the other hand lies 17 km to the west and approximately 700m below the peaks of the escarpment (i.e. in a rainshadow). Rain that falls at the Aruab gauge drains towards the east into the Konkiep River basin, and does not recharge any of the groundwater structures on Sinclair.
A measure is in place for contingent water supply to users in the event that water level drop proven to be caused by mining operations Key in this regard is that the actions (i.e. management and mitigation measures) provided by the Water Specialist Team, which are included in the EMP must be implemented by Tulela.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
5. Sinclair rainfall data (from 1933 – 1976 and 1990 – 2016) was provided to me by the previous owners of the farm (see Excel attachment to my email)). This data, particularly from the last three decades, should underline our concerns. From 1990 to 2016 the average annual rainfall for Sinclair was 82.8 mm, which is less than half, and close to 100 mm below the 180mm average that Aruab recorded for the same period.
6. Of even greater concern from the 1990 – 2016 data is the sixteen year interval (1990 to 2005) during which the annual total rainfall only exceeded 100 mm on one occasion, and then only by a very small margin (115 mm in 1994). It is highly unlikely that groundwater was replenished at all during this period. Without any guarantee of when the next replenishment will occur, the mine’s annual water consumption, ten to twenty times above the historical abstraction rates, represents a very high risk to the resource. The problem is compounded if extraction at this rate is to continue over two years.
W10 On the subject of groundwater in the proposed EMP, I also have a number of concerns:
Jörn Miller
(Neighboring
farm owner)
e-mail Section 4.4 in the Water specialist report a revised monitoring plan was recommended taking into consideration all boreholes on Farm Sinclair as well as the frequency of monitoring.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
1. The water levels in all the boreholes at the Sinclair house, and the “Garden Borehole” in the Aubures River should be monitored at least once a month. These boreholes are closest to the mine, they serve the activity hub of the farm, and potentially negative effects due to excessive pumping should be flagged at the earliest sign. (Even the characteristic stands of Camelthorn Trees in the Aubures River may deteriorate if groundwater levels drop significantly.)
2. Since the Sinclair borehole WW70293 (which is to be used as a production borehole) is close to the Aubures boundary, I will monitor the water levels of boreholes WW70289 (at the Aubures house) and WW70285 (Aubures, Cattle Post) on a monthly basis. (Aubures borehole WW70286 at the Sinclair / Aubures boundary fence has been dry for several years already).
3. Marc , the owner of Sinclair, his foreman or any other person appointed by him, should be able to attend any groundwater monitoring events, and all weekly/monthly test results should be forwarded to him on an ongoing basis. Any chemical analysis results of groundwater
This practical and effective Groundwater Monitoring Programme, is also included in the revised EMP. Noted. Reporting requirements are include in section 7 of the EMP. However, more detailed reporting requirements between Tulela and the Farm Owner needs to be confirmed in the agreement between these two parties.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
samples should also be forwarded to him directly.
4. If a cyanide leaching step is to be included as a processing step, groundwater samples should be analysed for cyanide residues as well.
5. Before processing and water abstraction commences, a clearly defined set of groundwater depletion limits should be agreed upon (i.e. fall in water table, lower pumping yields, slower water level recoveries). Furthermore, it must be agreed that pumping must cease if any of these limits are reached or exceeded. In such an event, drilling the borehole deeper is not an acceptable solution – it may temporarily provide the mine with more water, but it compounds the long-term risk of water resource depletion.
Included in the EMP Section 5.3 in the water specialist report where it is highlighted that “in the absence of pertinent data required to quantify resources and define limits for abstraction measures to collect such data should be in place in the form of a groundwater management plan forming part of this assessment. The monitoring plan includes the groundwater levels and groundwater quality in production and monitoring boreholes on farms Sinclair and Aubures As well as metered abstraction volumes from production boreholes” This in addition to recommendations to drill additional abstraction boreholes will reduce stress on the current envisioned production borehole. With the above measures in place to collect necessary information that will be used to update the monitoring plan as well as firm up additional measures that will be required to mitigate impact on other users. A measure is in place for contingent water supply to users in the event that water level drop proven. The following action was included in the EMP - In case water levels in production
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
boreholes drop to levels deeper than expected, pumping rates should be reduced to stabilise the water level.
W11 Section 5.5.2.1 of Scoping/Assessment Report (The farm house is located on the Barby Formation / Aubures Formation contact):
“near the contact, not on it”
Roy Miller
(Neighboring
farm owner)
e-mail (comments made in the report)
Wording was changed in the report.
W12 Section 5.5.2.1 of Scoping/Assessment Report:
“The alluvium is definitely not saturated”
Roy Miller
(Neighboring farm
owner)
e-mail (comments made in the report)
Wording was changed in the report.
W13 Section 5.6.2.1 of Scoping/Assessment Report (All rivers in the catchment are ephemeral rivers with episodic flows (less than 75% of the year)):
“much less than 75%”
Roy Miller
(Neighboring farm
owner)
e-mail (comments made in the report)
Noted.
W14 Section 5.6.2.1 of Scoping/Assessment Report (the Aubures River flows in a northeastern direction, before turning southwest and disappearing under the Namib Sand sea):
“southeast then northwest, then southwest, not northeast at all”
Roy Miller
(Neighboring farm
owner)
e-mail (comments made in the report)
Wording was changed in the report.
W15 Section 8.3.1.2 of Scoping/Assessment Report (nature of impact) will reduce to low with mitigation):
“only if additional boreholes are drilled over a wider area to reduce the impact on the only borehole that came anywhere near providing the required amount of water. Pumping of that borehole alone will
Roy Miller
(Neighboring
farm owner)
e-mail (comments made in the report)
Key requirements (amongst others) included in the EMP drilling of 2 production boreholes at the mine site in order to supplement the water supply from borehole WW70293 and reduce the impact on the groundwater level around that borehole on farms Sinclair and Aubures. Furthermore, these two new production boreholes will be used as monitoring boreholes.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
have a massive impact on its water table. A 24-hour pump test is not measure of the impact that pumping at the required rate day after day for a year and more. SLR said they did not know why that borehole was so strong, i.e they did not understand it - dangerous for long-term intense utilisation. We also do not know how water from this borehole/geological feature feeds into that groundwater system that feeds other boreholes, e.g. those at the Sinclair house which is downslope from the strong borehole”.
W16 Section 8.3.1.2 of Scoping/Assessment Report (Extent - impact will be localised to the farm Sinclair:
“You do not know this. The strong borehole is located close to the boundary of the farm Aubures. The impact will not be low in this environment where most boreholes have yields of about 2m3 per hour. Its impact would be moderate, or even high. Mitigation is to drill other boreholes and use these as well instead of over-exploiting a single borehole. This would then reduce impact to moderate or low.”
Roy Miller
(Neighboring farm
owner)
e-mail (comments made in the report)
The assessment of the potential impacts were conducted for the unmitigated and mitigated scenario. The significance rating in the “Mitigated Scenario” is assessed as Low. One of the key requirements (amongst others) included in the EMP are is the drilling of 2 production boreholes at the mine site in order to supplement the water supply from borehole WW70293 and reduce the impact on the groundwater level around that borehole on farms Sinclair and Aubures. The Water Specialist Team took the additional information (i.e. historic rainfall data) provided by the relevant farmers into consideration and amended their report accordingly. The severity of the potential impact relating the water abstraction was
W17 Section 8.3.1.2 of Scoping/Assessment Report (probability): “With most other boreholes in the region having yields of about 2m3 per hour, the potential is high for abstraction volumes being too high”.
Roy Miller
(Neighboring
farm owner)
e-mail (comments made in the report)
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
W18 Section 8.3.1.2 of Scoping/Assessment
Report (With mitigation, probability reduces to low):
“Only if other boreholes are drilled and used.”
Roy Miller
(Neighboring
farm owner)
e-mail (comments made in the report)
changed to “high” in the unmitigated scenario. The overall significance rating, in the mitigated scenario, has not changed.
W19 Section 8.3.1.2 of Scoping/Assessment Report (The significance of this potential impact is moderate in the unmitigated scenario and low in the mitigated scenario):
“Nonsense - see above comments”.
Roy Miller
(Neighboring farm
owner)
e-mail (comments made in the report)
W20 Section 8.3.1.2 of Scoping/Assessment Report (significance rating with mitigation):
“All should be M”.
Roy Miller
(Neighboring
farm owner)
e-mail (comments made in the report)
W21 Section 8.3.2.2 of Scoping/Assessment Report (Seepage from the waste rock dumpsite is not considered hazardous due to the oxide nature of the rocks and ore minerals that are contained as these do not contain sulphides):
“The main ore mineral, chalcocite, is a sulphide. There is also some chalcopyrite and bornite which are also sulphides. Rephrase.”.
Roy Miller
(Neighboring farm
owner)
e-mail (comments made in the report)
The Section in the report was rephrased accordingly.
W22 Statement in EMP (section 4.2.5): “Once the final infrastructure drawings and plans have been completed, the conceptual storm water plan can be updated to take into account the final layouts”.
Comment / question:
This sentence means that the EMP is not complete. A final, complete EMP needs to be prepared for final comment and
Roy Miller
(Neighboring
farm owner)
e-mail (comment in EMP)
The EMP, submitted to MME & MET is the Final version, for their review and decision. All comments and questions raised by IAPs during the review of the (draft) report were considered and incorporated into the various documents, where relevant. In general, EIAs are never conducted on “detail design” information. Rather, the EIA process is generally aligned with the
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
evaluation by IAPs before being submitted to MET for a clearance certificate.
Feasibility / Basic design stages in the project execution model”. Sometimes EIAs could even commence as early as the “Concept stage”. Prior to the implementation of the proposed Sinclair Project, the design Team might still propose minor changes to the site layout (amongst others). This could therefore also entail that the final Storm Water Management Plan needs minor modifications - as long as the relevant requirements are implemented to ensure potential impacts are avoided / minimized – i.e. the relevant management and mitigation measures (as stipulated in the EMP) are incorporated. Therefore, should the final layout not change, the “Conceptual” Storm Water Plan presented in the EIA could very well be the final one. Significant changes to a project (i.e. in terms of additional / new activities or increase in the proposed project capacity/throughput, or footprint, etc.) could require an EIA amendment, if an ECC has already been issued by MET.
Feasibility of the Project and Mine Closure
F1 During the public meeting it became apparent that the feasibility of the whole project was based on rather basic, if not insufficient, sampling being done on the waste dumps (referred to as stockpiles in the EIA report) of the old Sinclair Mine,
Thorsten Theile
(NAMTIB
Biosphere
Reserve)
e-mail The questions / comments in this section relate (mostly) to the “Feasibility of the proposed project”. The feasibility the project (i.e. to establish whether the project would be feasible or not
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
which has been abandoned a couple of times in the past. It was generally agreed amongst all IAP’s that more sampling should be undertaken in order to truly establish the feasibility of reviving the mining activities at Sinclair Mine. Based on the general doubt of the feasibility of this project it is even more important that sufficient funding must be available to cover all costs that might be incurred during the mining process (any penalties that might become applicable) and especially to cover the costs involved when shutting down the mine in accordance with the EMP. These funds should be placed in a trust especially earmarked for this purpose, before any mining/exploration activities commence. The exact amount to be deposited in the trust and subsequent management of the trust should be agreed upon between the client and the affected stakeholders.
and the need for further sampling, etc.) is not part of the scope of the EIA. However, an associated issue relating to this relate to the risk of closure or even ’early closure’ of the mine and whether there will be funds available for closure and rehabilitation requirements. Refer to section 4.4 of the EIA Scoping and Assessment Report and the (revised) Mine Closure Strategy in Appendix A of the EMP. A Mine Closure Plan (including closure costing) needs to be developed, in line with the relevant legislation and Namibia Mine Closure Framework, long before the closure of the mine. This is essential, given the very short lifespan of the mine. Tulela will make funds (Financial Assurance) available for closure of the mine, from the outset of the implementation of the project. A (Conceptual) Mine Closure Plan will be submitted as part of the Mining Licence Application to MME. The Conceptual Financial Assurance amount will be included as part of the Conceptual Mine Closure Plan, to be submitted to MME as part of the ML Application (see section 1).
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
F2 Mr. Badenhorst told on the 2.10.19 at Sinclair, that ‘Cathral’ will fall bankrupt if the mine is not profitable. The same will happen, when the project is finished. Who will then remove the environment damages in the region?
Christa and Ruediger Hennings
e-mail This statement it not correct and was misinterpreted. Please see F1 regarding the Mine Closure Plan and Financial Assurance.
F3 Table 6 in EMP (section 6)
Comment / question:
Rehabilitation missing in this list.
Roy Miller
(Neighboring
farm owner)
e-mail (comment in EMP)
The list provides the various “Management Plans (MP)” as part of the EMP. There is not a specific MP for “Rehabilitation”. Rather, various rehabilitation requirements are included under the relevant MPs. Furthermore, Appendix A of the EMP provides the Mine Closure Framework and includes the requirement for Tulela to develop a Mine Closure Plan. The “rehabilitation requirements” need to be further developed as part of the Mine Closure Plan (MCP) – taking the commitments that form part of the EMP into consideration. A MCP does not have to form part of the EIA / EMP before an ECC is issued by MET. However, the decommissioning and closure phase were considered as part of the EIA, and relevant management and mitigation measures relating to this phase included in the EMP. However, the requirements for the (Conceptual) Mine Closure Plan that needs to be submitted as part of the Mining Licence Application to MME, is included in the Mine Closure Framework (Appendix A of the EMP).
F4 Socio-Economic MP (section 6.10.2.4) – closure:
“Ensure there is a detailed Mine Closure Plan in place long before the closure of the mine. This is essential, given the very short lifespan of the mine”.
Comment / question:
This indicates there is no Mine Decommissioning and Closure Plan. Must be part of the EMP before an EC is issued. The MCP is a living document so is modified continuously as mining and rehabilitation progress.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
Biodiversity and topsoil
B1 Biodiversity (Report Par 8.4)
The mining area should be completely fenced off, so as to prevent any animals from entering it. Signposts alone should not be an option as mitigating measure.
Thorsten Theile
(NAMTIB
Biosphere
Reserve)
e-mail There is an existing fence around the working are of the mine. Section 6.2.2.1 of the EMP stipulates that the fence around the working area of the mine will be maintained. The requirement for the fence is to provide a barrier to keep third parties from potentially dangerous excavations, infrastructure and associated activities. Also, to prevent workers to move freely outside the project area. Unless it is game fencing, a fence has limited efficacy in keeping out (all) animals - it works for ostrich and some antelopes, but not for all mammals nor reptiles. On this site, the main value to biodiversity would be to restrict human activity and disturbance to the mine site.
B2 Dust prevention measures should be implemented to the full extend technically possible.
The report mentions Acacia Erioloba trees in particular in the close vicinity of the project.
Excessive dust pollution will eventually suffocate these trees and other plants, due to the lack of regular rainfall to wash off the dust from the trees’ leaves. Once again the client should be held accountable in case these plants are killed off by insufficient dust control measures on his behalf.
Thorsten Theile
(NAMTIB
Biosphere
Reserve)
e-mail With reference to section 5.7.2.2, there are only limited protected trees in the proposed mining and processing area, including:
One mature Acacia erioloba.
Three mature Aloe dichotoma
One mature Parkinsonia Africana The Biodiversity assessment (Appendix E of the EIA Scoping/Assessment Report) took cognisance of this fact in assessing the potential impacts on vegetation. Potential impacts on protected tree species, relating to dust, are not regarded significant.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
With reference to section 6.5 of the EMP, relevant management and mitigation measures (including monitoring) for air pollution (i.e. dust) is provided.
B3 Section 8.4.1.2 of Scoping/Assessment Report (Larger mammals and birds are the taxa most likely to be affected):
“and small reptiles”.
Roy Miller (Neighboring farm owner)
e-mail (comments made in the report)
Section 8.4.1.2 of the report was amended accordingly. It is unlikely that the directional movements, daily activities and behavior of reptiles would be significantly affected by the mining activities, certainly not to the same extent as those of mammals and birds. It is likely that some individual reptiles will die, but destruction of organisms is dealt with in another impact.
B4 Section 8.4.1.2 of Scoping/Assessment Report (Mining and processing areas are already disturbed to a certain extend):
“but existing dumps provide refuges for small mammals, small reptiles and invertebrates”.
Roy Miller
(Neighboring farm
owner)
e-mail (comments made in the report)
Correct, the old dumps have been recolonised over time and now provide habitat for certain organisms. However, on balance, the mining area still is disturbed rather than pristine in terms of biodiversity. Section 8.4.1.2 of the report was amended accordingly.
B5 Section 8.4.2.2 of Scoping/Assessment Report (The Aubures River is however alluvial and its ecology thus depends more on surface water than groundwater): “Wrong. It is rare for the Aubures River to flow. Surface water therefore lasts only a few days. The water in the alluvium is also underground water”.
Roy Miller (Neighboring farm owner)
(comments
made in the
report)
Section 8.4.2.2 was amended accordingly.
The amended section in the report is as
follows:
“The Aubures River in the project area
comprises alluvial sediments of unknown
saturated thickness (an open well located
in the Aubures River on farm Sinclair
showed an alluvium thickness of more than
5 m at that location). Its ecology thus
depends on shallow alluvial groundwater,
which is recharged after irregular seasonal
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
flood events, rather than on deeper
groundwater (i.e. deep hardrock aquifer).
Although the alluvial aquifer is also
recharged to a small percentage by the
hardrock aquifer, the proposed volumes of
abstraction are not expected to negatively
affect the groundwater levels in the
Aubures River alluvium”.
B6 Biodiversity MP in the EMP (Issue 4):
Comment / question:
..."should be drawn up".... This means there is no comprehensive restoration plan which also means that this EMP is incomplete and as such cannot be issued a clearance certificate.
Roy Miller
(Neighboring
farm owner)
e-mail (comment
in EMP)
Not correct. This EMP is complete. Appendix A of the EMP provides the Mine Closure Framework and includes the requirement for Tulela to develop a Mine Closure Plan. The “detailed rehabilitation requirements” need to be further developed as part of the Mine Closure Plan – taking the commitments that form part of the EMP into consideration. The relevant section in the EMP was however modified as follows: “A comprehensive restoration plan must be drawn up by an expert as part of the Mine Closure Plan. Some rehabilitation actions must be implemented during construction / operations in order to be effective, e.g. removal and storage of topsoil (refer to “Issue 5”)”.
Socio – economic – including Community Health and Safety, etc.
S1 Section 5.8.2.3 of Scoping/Assessment Report (Bethanie Village Council office about 100 km south-east of the mine in Bethanie village):
Roy Miller (Neighboring farm owner)
e-mail (comments made in the report)
Section 5.8.2.3 was amended accordingly.
NO. COMMENT / QUESTIONS / ISSUE RAISED
NAME & ORGANISATION
METHOD RESPONSE
“more than 100 km”
S2 Section 8.1.1.2 of Scoping/Assessment Report (duration of impact):
You cannot avoid the long-term impacts. You will always have long-term impacts, even after rehabilitation.
Roy Miller (Neighboring farm owner)
e-mail (comments made in the report)
This comment relates to the “duration” of the following potential impact – in the mitigated scenario: Hazardous excavations, infrastructure and activities; and movement of mining vehicles that could pose a safety risk, specifically to 3rd parties, but also animals. Comment noted and the assessment amended. However, the overall significance rating before and after remains as is, because with mitigation, the possibility of the safety risks are reduced, meaning the nature and intensity are also reduced. The same argument applies for potential hazardous infrastructure that will remain beyond closure of the mine. Even though the potential hazardous infrastructure will remain (after closure), with the effective implementation of relevant management and mitigation measure (i.e. facilities to be “closed in a manner that they present land forms that have similar safety attributes to the natural land forms in the area”, etc.), potential impacts can be avoided / minimized.