1 Government Contracts Government Contracts

1 Government Contracts. getting started 2 Federal Acquisition Regulation Primary directive for contracting and procurement Applies to acquisition of

Embed Size (px)

Citation preview

1Government ContractsGovernment Contracts

• getting started

2

Federal Acquisition Regulation

• Primary directive for contracting and procurement

• Applies to acquisition of all supplies, services, and research and development

• Impacts on Program Manager• Competition• Acquisition planning

• Many Supplements• DFARS, AFFARS, AFMCFARS, etc.• https://farsite.hill.afb.mil/VFFARA.HTM 3

Federal Acquisition Regulation (FAR)

• principal set of rules in the Federal Acquisition Regulation System.

• System consists of sets of regulations issued by agencies of the federal government to govern what is called the "acquisition process“;

• this is the process the government follows to "acquires" goods and services.

4

FAR Process

• Process consists of three phases:

• 1. need recognition and acquisition planning

• 2. contract formation• 3. contract administration

5

FAR

• The FAR System regulates activities of government personnel in carrying out the process.

• It does not regulate the purchasing activities of private sector firms, except to the extent that parts of it are incorporated into government solicitations and contracts by reference.

6

FAR Structure

• The Federal Acquisition Regulation is contained within Chapter 1 of Title 48, appropriately titled

• "Federal Acquisition Regulation.“ • Chapter 1 is divided into Subchapters A-H

which encompass “FAR Parts 1-53”

• Note: The proper way to cite a regulation within the FAR is by part, section, and subsection, without respect to volume, chapter, or subchapter.

• For instance, the FAR clause on lobbying costs is FAR Part 31, Section 205, Subsection 22 (referenced as FAR 31.205-22). 7

FAR “Table of Contents”

• Subchapter A: General • Part 1. Federal Acquisition Regulations System • Part 2. Definitions of Words and Terms • Part 3. Improper Business Practices and Personal Conflicts of

Interest • Part 4. Administrative Matters

• Subchapter B: Acquisition Planning • Part 5. Publicizing Contract Actions • Part 6. Competition Requirements • Part 7. Acquisition Planning • Part 8. Required Sources of Supplies and Services • Part 9. Contractor Qualifications • Part 10. Market Research • Part 11. Describing Agency Needs • Part 12. Acquisition of Commercial Items

8

FAR “Table of Contents” (continued)

• Subchapter C: Contracting Methods and Contract Types • Part 13. Simplified Acquisition Procedures • Part 14. Sealed Bidding • Part 15. Contracting by Negotiation • Part 16. Types of Contracts • Part 17. Special Contracting Methods • Part 18. Emergency Acquisitions• Subchapter D: Socioeconomic Programs • Part 19. Small business programs • Parts 20-21. Reserved • Part 22. Application of Labor Laws to Government Acquisitions • Part 23. Environment, Energy and Water Efficiency, Renewable

Energy Technologies, Occupational Safety, and Drug-Free Workplace

• Part 24. Protection of Privacy and Freedom of Information • Part 25. Foreign Acquisition • Part 26. Other Socioeconomic Programs

9

• Subchapter E: General Contracting Requirements • Part 27. Patents, Data, and Copyrights • Part 28. Bonds and Insurance • Part 29. Taxes • Part 30. Cost Accounting Standards Administration • Part 31. Contract Cost Principles and Procedures • Part 32. Contract Financing • Part 33. Protests, Disputes, and Appeals• Subchapter F: Special Categories of Contracting • Part 34. Major System Acquisition • Part 35. Research and Development Contracting • Part 36. Construction and Architect-Engineer Contracts • Part 37. Service Contracting • Part 38. Federal Supply Schedule Contracting • Part 39. Acquisition of Information Technology • Part 40. Reserved Part 41. Acquisition of Utility Services

10

FAR “Table of Contents” (continued)

FAR “Table of Contents” (continued)

• Subchapter G: Contract Management • Part 42. Contract Administration and Audit Services • Part 43. Contract Modifications • Part 44. Subcontracting Policies and Procedures • Part 45. Government Property • Part 46. Quality Assurance • Part 47. Transportation • Part 48. Value Engineering • Part 49. Termination of Contracts • Part 50. Extraordinary Contractual Actions and the Safety Act • Part 51. Use of Government Sources by Contractors• In Volume 2:• Subchapter H: Clauses and Forms • Part 52. Solicitation Provisions and Contract Clauses • Part 53. Forms 11

FAR Supplements

• Supplements• original purpose of FAR • consolidate numerous individual agency regulations • create one comprehensive set of standards which would apply government-

wide• officially individual agencies discouraged from issuing supplemental

regulations. • However, nearly every major department /agency has issued such regulations,

which often place further restrictions/requirements on contractors

• One of the best-known examples of an agency supplement is theDefense Federal Acquisition Regulation Supplement (or DFARS) used by the Department of Defense.

The most common format for agency FAR supplements is to follow the basic FAR format. To continue the example above, the companion DFARS section on lobbying costs is DFARS Subpart 231, Section 205, Subsection 22 (referenced as DFARS 231.205-22). 12

Don’t be intimidated by the process!

13

texting/email break

14

15

Overview

• What is a Government Contract? • Authority to Enter into Government Contracts• Four Phases of Government Contracts• Role of the Government Contract Professional

16

“Contracting”

……purchasing, renting, leasing, or purchasing, renting, leasing, or otherwise obtaining supplies otherwise obtaining supplies (products)(products) or services from or services from nonfederal sources. Contracting nonfederal sources. Contracting includes reviewing descriptions of includes reviewing descriptions of supplies and services required, supplies and services required, solicitation and selection of sources, solicitation and selection of sources, preparation and award of contracts, preparation and award of contracts, and all phases of contract and all phases of contract administration/management. administration/management.

17

Sources

• Statutes• Federal Acquisition Regulation (FAR)

•48 C.F.R. Chapter 1 (FAR Council)•http://farsite.hill.af.mil/•Don’t forget FAR Supplements…

• Case Law— administrative cases and Federal

cases

18

What is a Government Contract?

• Offer, Acceptance, Consideration… • Government is a party (of course)• Specialized statutes, regulations,

and case law• Many differences from common law:

e.g., socioeconomic policy, contract changes, contract terminations, etc….

19

• An offer is a response to a solicitation that, if An offer is a response to a solicitation that, if accepted, would bind the offeror to perform the accepted, would bind the offeror to perform the resultant contract. resultant contract.

• The offer indicates The offer indicates an intention to be bound to an intention to be bound to an agreementan agreement. .

• Submitted in the form of “Bids” or “Proposals”Submitted in the form of “Bids” or “Proposals”• Either party can make “offers”Either party can make “offers”• Distinction between Distinction between offeroffer and and advertisementadvertisement..

• Advertisements are generally construed to be Advertisements are generally construed to be invitations for offersinvitations for offers. .

• IFB, RFP, RFQ are IFB, RFP, RFQ are advertisementsadvertisements. The contractor’s bid . The contractor’s bid constitutes an offer that may or may not be accepted by constitutes an offer that may or may not be accepted by the government.the government.

Offer

20

• Acceptance is an Acceptance is an unequivocal communicationunequivocal communication to to the offeror indicating the intention to be bound to the the offeror indicating the intention to be bound to the exact terms of the offer.exact terms of the offer.

• An unequivocal response to an offer is one that is An unequivocal response to an offer is one that is certain, decided, and doubtless.certain, decided, and doubtless.

• A conditional response or one that hedges, A conditional response or one that hedges, procrastinates, or leaves the offeror in doubt does not procrastinates, or leaves the offeror in doubt does not constitute an acceptance.constitute an acceptance.

• For an acceptance to occur there must be no question For an acceptance to occur there must be no question that the offeree intends to be bound to the exact that the offeree intends to be bound to the exact terms of the offer. terms of the offer.

• Therefore, acceptance must be clearly communicated Therefore, acceptance must be clearly communicated to the offeror to become effective.to the offeror to become effective.

Acceptance

21

• Something of value that one party of a Something of value that one party of a contract gives to the other contract party in contract gives to the other contract party in exchange for something else of value.exchange for something else of value.

• Sufficiency vs. adequacySufficiency vs. adequacy• Sufficient consideration - when the consideration has Sufficient consideration - when the consideration has

some value that induces the other party to perform. some value that induces the other party to perform. • Adequacy relates to whether the exchange is a Adequacy relates to whether the exchange is a fairfair

bargain.bargain.• The law will not look to the adequacy of the The law will not look to the adequacy of the

consideration. If a party makes a bad deal, the court consideration. If a party makes a bad deal, the court will lend no assistance.will lend no assistance.

Consideration

22

• Parties to a contract must have the Parties to a contract must have the competency to enter into an agreement. If a competency to enter into an agreement. If a person does not have the mental capacity to person does not have the mental capacity to formulate the requisite intent to be bound, formulate the requisite intent to be bound, there can be no meeting of the minds and there can be no meeting of the minds and there can be no contract.there can be no contract.

• In government contracting the issue of In government contracting the issue of whether a corporation is competent will whether a corporation is competent will generally be whether it is legally entitled to generally be whether it is legally entitled to enter into the agreement.enter into the agreement.• The corporation may be acting outside its charter The corporation may be acting outside its charter

(stockholders may have the power to rescind the (stockholders may have the power to rescind the contract).contract).

• Relatedly, those who act on behalf of a company Relatedly, those who act on behalf of a company must have the must have the authorityauthority to act! to act!

Competency of Parties

23

• Violation of statuteViolation of statute• Certain conduct may be expressly prohibited by Certain conduct may be expressly prohibited by

statutestatute• A contract that imposes a duty to perform such A contract that imposes a duty to perform such

conduct is also illegal and will not be enforced. conduct is also illegal and will not be enforced.

• Violation of public policy Violation of public policy • Public policy applies to matters of public morals, Public policy applies to matters of public morals,

health, safety, and welfare. health, safety, and welfare. • One cannot do that which has a tendency to be One cannot do that which has a tendency to be

injurious to the public or against the public good. injurious to the public or against the public good.

Legality of Purpose

24

• Lack of certainty concerning the terms and conditions of Lack of certainty concerning the terms and conditions of the contract maythe contract may render an agreement unenforceable.render an agreement unenforceable.

• Terms must be clear enough to permit the courts to Terms must be clear enough to permit the courts to interpret the duties and obligation to be performed by interpret the duties and obligation to be performed by either party. either party.

• ““Rules of Construction” as applied by courts:Rules of Construction” as applied by courts:• The ordinary meaning generally given to words applies.The ordinary meaning generally given to words applies.• Technical terms and words are given their technical meaning Technical terms and words are given their technical meaning

unless clearly indicated otherwise.unless clearly indicated otherwise.• The contract must be read and interpreted as a whole.The contract must be read and interpreted as a whole.• Specific terms control over general terms when in conflict. Specific terms control over general terms when in conflict. • Ambiguities are interpreted against the drafter of the Ambiguities are interpreted against the drafter of the

contract.contract.• Best evidence of the parties’ intention is in the written Best evidence of the parties’ intention is in the written

contract. contract. • Purpose is to bar oral evidence that contradicts, adds to, or Purpose is to bar oral evidence that contradicts, adds to, or

otherwise varies the terms of the written contract. otherwise varies the terms of the written contract.

Certainty of Terms

25

FAR Definition of a “Contract”

Definition: “...a mutually binding legal relationship

obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds…” FAR 2.101

FAR--Uniform Contract Format

• Sec A: Solicitation Form• Sec B: Supplies or Services and Prices/Costs• Sec C: Description/Specs/Work Statement• Sec D: Packaging and Marking• Sec E: Inspections and Acceptance• Sec F: Deliveries or Performance• Sec G: Contract Administration Data• Sec H: Special Contract Requirements

26

FAR-- Uniform Contract Format (Continued)

• Sec I: Contracting Clauses• Sec J: List of Attachments• Sec K: Representations, Certifications,

Exhibits, and Other Attachments

• Sec L: Instructions, Conditions, and Notices to Offerors

• Sec M: Evaluation Factors for Award

27

28

General Categories of Government Contracts

• Supplies• Construction• Services • Research and Development (R&D)

29

Every Good Government Procurement System Has…

• Competition

• Transparency

• Integrity

30

• texting/email break

31

32

Government Authority

• Who has the authority to bind the Government with a contract?

33

Government Authority

• General Rule: Only someone with “actual authority”

may bind the Government

34

Government Authority

• Agency Heads (FAR 1.601)•By virtue of their positions (e.g.,

SecAF)•Delegate down to Senior Center

Contracting Official (SCCO)• Government Contracting Personnel

with warrants (FAR 1.602)•Contracting Officers (COs)

Contracting Officers

• Procuring Contracting Officer (PCO)• Enters into contracts

• Administrative Contracting Officer (ACO)• Administers contracts

• Termination Contracting Officer (TCO)• Settles terminated contracts

• ALL HAVE WARRANTS

35

36

Government Authority

•HCAs appoint COs IN WRITING (WARRANT)

•Warrant must be posted

•May include further limitations (e.g. dollar limits)

37

““CONTRACTING OFFICER”CONTRACTING OFFICER”

- Person who has authority to enter Person who has authority to enter into, administer, or terminate contracts into, administer, or terminate contracts and to make related determinations and and to make related determinations and findings. findings. - May bind the government - May bind the government only to the only to the extent of the authority delegatedextent of the authority delegated. . -- CO authority is received from the CO authority is received from the appointing authority with clear appointing authority with clear instructions in writing regarding the instructions in writing regarding the limits of that authority.limits of that authority.

38

Government Authority

•What about other Government personnel?

•Apparent authority—not recognized

•Ratification (of unauthorized act)

39

Contractor Authority

•All types of authority apply:

•Actual

•Apparent

40

4 Phases of Government Contracts

• Acquisition Planning

• Pre-Award (Source

Selection)

• Post-Award (Performance)

• Close-out

41

4 Phases of Government Contracts

• Acquisition Planning

• Pre-Award (Source

Selection)

• Post-Award (Performance)

• Close-out

42

Acquisition Planning

• KEY to successful procurement• Basically, looking at:

• What do we need? (user)• How are we going to get it? (contracting)• How are we going to pay for it? (finance)• Are we following the rules?

(contracting/legal)

43

Acquisition Planning:Basic Contract TYPES

• Two Basic Types:•Fixed Price•Cost

Fixed-Price Cost

Promise

Contractor Risk

Govt. Risk

Cash Flow

Fee / Profit

Govt. Admin

Deliver product Best effort

High Low

Low High

Progress Pmts+ on delivery

Costs paid as incurred / billed

Profit included in price Max 6-15%

Minimal High Surveillance

Characteristics of Contract Types

44

45

Fixed Price Contract (FAR Subpart 16.2)

•Set, predetermined price• Price not subject to any adjustment based on

contractor incurred costs

•Who bears the risk?• Contractor bears risk of increased costs (bound

to perform at specified price)

46

• Firm Fixed Price• Firm Fixed Price with EPA• Fixed Price Prospective Redetermination• Fixed Price Retroactive Redetermination• Firm Fixed Price Level of Effort • Fixed Price Incentive Firm Target• Fixed Price Incentive Successive Target

Fixed Price Types

47

Cost Reimbursement Contract (FAR Subpart 16.3)

• Government pays contractor’s incurred cost•Who bears the risk?

•Government bears risk of increased costs

48

• Cost• Cost Sharing• Cost Plus Fixed Fee

• Completion• Term

• Cost Plus Incentive Fee

NOTE: NOTE: (1) Contractor’s accounting system must be adequate for determining costs(2) Government must have appropriate surveillance during performance(3) Cost-reimbursement contracts are prohibited for acquiring commercial items

Cost Reimbursement Types

49

Acquisition Planning: Contract TYPES—What else?

• Time & Materials• Provides for acquiring supplies or services on the basis of:

• Direct labor hours at specified fixed hourly rates that include wages, overhead, general and administrative expenses, and profit; and

• Materials at cost, including, if appropriate, material handling costs as part of material costs

• Labor-Hour • Variation of the time-and-materials contract, differing only in that

materials are not supplied

NOTE: May be used only when it is May be used only when it is not possiblenot possible at the time of placing the contract to at the time of placing the contract to estimate estimate accuratelyaccurately the extent or duration of the work or to the extent or duration of the work or to anticipate costsanticipate costs with any reasonable degree with any reasonable degree of confidence.of confidence.

50

Acquisition Planning: Contract METHODS

• Negotiated Procurements (FAR Part 15)• Sole Source Acquisitions• Competitive Acquisitions

• Best value• Tradeoff• Lowest Price Technically Acceptable (LPTA)• Performance/Price Tradeoff (PPT)

• Oral Presentations

• Request for Proposals (RFPs) or• Invitation for Bids (IFBs)

51

Acquisition Planning: Contract METHODS

• Sealed Bidding (FAR Part 14)•Price is the only basis

for award•Invitation for Bids

(IFBs)

SEALED BIDS

• Service/Product requirement is

well defined

• Adequate competition and time

• Contract award based solely on price and price related issues

• No discussions

• IFB required

• Service/Product requirement is not well defined

• Competition or Sole Source

• Contract award based on evaluation criteria

• Discussions/negotiation required

• RFP required

COMPETITIVE NEGOTIATED PROPOSAL

FAR 14.101 FAR 15

Solicitation Methods

52

53

Acquisition Planning: Contract METHODS

• Acquisition of Commercial Items (FAR Part 12)•Definition of CI and Services (Section 2.101)

• Simplified Acquisitions (FAR Part 13)•Under $3,000 (Micro-purchase)•$3,000 to $100k (Simplified acquisition

threshold--SAT)•Up to $5.5M (SAT for commercial items)

• Fair Opportunity (FAR Part 16.505)

texting/email break

54

55

4 Phases of Government Contracts

• Acquisition Planning

• Pre-Award (Source

Selection)

• Post-Award (Performance)

• Close-Out

56

Pre-Award (Source Selection):Competition

• Law requires, with certain limited exceptions, that contracting officers promote and provide for full and open competition • Micro-purchases (under $3,000)

- “reasonable price”-FAR 13.202• Between $3,000 and Simplified

Acquisition Threshold (SAT) - “reasonable number of sources” (“Rule of 3”)-FAR 13.104

• Over SAT-Competition in Contracting Act - Full and open competition-FAR 6.101

57

• Full and open competition AFTER EXCLUSION OF SOURCES FAR Subpart 6.2• e.g., contracts set aside for small business, etc.

• OTHER THAN full and open competition FAR Subpart 6.3• requires JUSTIFICATION & APPROVAL

(J&A); • e.g., only one source exists • e.g., “unusual and compelling urgency”

Pre-Award (Source Selection):Competition

58

• Over $25,000 •Government-wide Point of Entry

(GPE) -- www.eps.gov or www.fedbizopps.gov

• $10,000 to $25,000 •Posting in a public place

• Under $10,000 •No requirement

Pre-Award (Source Selection):Advertising

59

Pre-Award (Source Selection):Evaluation of Offers

• Responsibility (FAR 9.103)• A Government contract shall be awarded only to a RESPONSIBLE contractor

• Responsiveness (FAR 14.301)• Offers must meet ALL essential requirements of the solicitation

60

Pre-Award (Source Selection):Bid Protests

• What are they?•Basically, offerors or potential offerors

challenging a solicitation or a contract award

•Various Remedies—includes possible STAY…•Of Award—Pre-Award•Of Performance—Post-Award

61

Pre-Award (Source Selection):Bid Protests

• Where are they filed?•Agency Protests (FAR Subpart 33.1)•Government Accountability Office

(GAO)•Court of Federal Claims (COFC)

62

4 Phases of Government Contracts

• Acquisition Planning

• Pre-Award (Source

Selection)

• Post-Award (Performance)

• Close-out

63

Post-Award (Performance)

• The “Life” of the Contract•Contract Administration•Contract Changes•Claims/Disputes

64

Post-Award (Performance):Contract Administration

• Contract Administration

• Primarily conducted by contracting office personnel (along w/Program Management and functional quality assurance folks with support of DCMA for larger dollar valued, more complex contracts)

• Government should not wait until there is a problem to involve their legal office (JA) or DCMA

• KEY: Foster strong relationships with all resources available

Contract Administration and DCMA

• Defense Contract Management Agency (DCMA)

• Overseeing the Contractor’s Compliance with the Terms and Conditions of the Contract

• Lots of Earned Value Management (EVM)• Contract Modification:

• Supplemental Agreements• Change Orders• Constructive Changes

• http://www.dcma.mil

65

66

Post-Award (Performance):Changes/Modifications

• Contract Changes (FAR Subpart 43.1)• Changes Clause allows “minor” changes• EQUITABLE ADJUSTMENT in price• Change must be:

• WITHIN SCOPE (of work), and• Made by one with PROPER AUTHORITY (CO)

• Unilateral Modifications• Bilateral Modifications

67

• Contract Disputes (FAR Subpart 33.2) - Administrative

or judicial litigation between the contractor and the agency, relating to contract performance• Reasonable efforts should be made to resolve

controversies prior to submission of claim• Use Alternative Dispute Resolution (ADR) to

maximum extent practicable• If contractor initiates claim, CO must issue written

decision• Adverse final decision by CO perfects appeal to the

Armed Services Board of Contract Appeals (ASBCA) or the Court of Federal Claims (COFC)

Post-Award (Performance):Contract Disputes

68

4 Phases of Government Contracts

• Acquisition Planning

• Pre-Award (Source

Selection)

• Post-Award (Performance)

• Close-Out

69

Close-Out

• “Natural” Causes

70

Close-Out

• Early Termination

•Convenience

•Default

71

Close-Out

• Termination for Convenience of the Government (T4C) (FAR Part 49)• May be for any reason• Contractor entitled to submit settlement

proposal

72

Close-Out

• Termination for the Default (T4D) (FAR Part 49)• Contractor’s unexcused,

present or prospective failure to perform

• Contractor may have to pay for Gov’t re-procurement costs• Risk of debarment

73

Role of the Government Contract Professional

• Legal Reviews • Legal Advice• Business Counsel • Litigation Support

74

Role of the Government Contract Professional: Legal Reviews

• Contract File Review• Funding Document• Contract Document• Statement of Work (SOW)/Statement of

Objectives (SOO)/Performance Work Statement (PWS)

• Price Negotiation Memorandum (PNM)• Technical Evaluation• Other Contract Documents

75

Final ThoughtsFinal Thoughts

• Don’t be intimidated by the process • Do assure that the Government person with whom you are dealing

has actual authority to bind the Government--Only the Contracting Only the Contracting Officer may change or agree to changes in the contractOfficer may change or agree to changes in the contract

• The contract is interpreted as a whole--Read the entire contract The contract is interpreted as a whole--Read the entire contract including special contract provisions and the attachments (i.e., including special contract provisions and the attachments (i.e., SOW/SOO, CDRLs, etc.)SOW/SOO, CDRLs, etc.)

• Requirements or material changes must be approved and Requirements or material changes must be approved and documenteddocumented

• ““No funding” means “no requirement”No funding” means “no requirement”• The contract Schedule takes precedence over contract clausesThe contract Schedule takes precedence over contract clauses• Contract clauses take precedence over other documents, exhibits Contract clauses take precedence over other documents, exhibits

and attachmentsand attachments• Other documents, exhibits and attachments take precedence over Other documents, exhibits and attachments take precedence over

the specificationsthe specifications• Use “Plain English” versus technical language.Use “Plain English” versus technical language.• Avoid Ambiguous language--ambiguity is interpreted against the Avoid Ambiguous language--ambiguity is interpreted against the

drafter! drafter! • Don’t be intimidated by the process

HOME WORK• DUE March 2014 (next NCMA March

Workshop):• Reading Assignment:• Read one PART of the FAR each week

• Market Research Assignment: • Find 3 Business Opportunities for your company in

FEDBIZOPS

Class Discussion/Presentation: Bring with you a Federal Government Solicitation and

highlight any special terms/conditions, certification/representations,

and be prepared to discuss interesting FAR provisions, the proposal preparation instructions, the proposal evaluation criteria and basis for selection/award.

76