Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Environmental Evaluation Report on
Implementation of the Project of
Comprehensive Treatment of Water Environment
in Bayannaoer City by Loan from the World Bank
Project file:Implementation of the Project of Comprehensive Treatment of
Water Environment in Bayannaoer City by Loan from the World
Bank
Client: Bayannaoer Hetao Water Group Co., Ltd.
Appraising unit: China Research Academy of Environmental Sciences
President: Meng Wei
Project leader: Xi Beidou
Technical chief: Li Xiang Jiang Jinyuan Huo Shouliang
1
E2498v2
Chinese Research Academy Environmental Sciences
June 2010
2
Table of Contents
Environmental Evaluation Report on.............................................................................1
Implementation of the Project of....................................................................................1
Comprehensive Treatment of Water Environment.........................................................1
in Bayannaoer City by Loan from the World Bank........................................................1
Client: Bayannur Hetao Water Group Co., Ltd..............................................................1
Appraising unit: China Research Academy of Environmental Sciences.......................1
President: Meng Wei......................................................................................................1
Project leader: Xi Beidou...............................................................................................1
Technical chief: Li Xiang Jiang Jinyuan Huo Shouliang...............................................1
Table of Contents...........................................................................................................2
1 General Introduction...................................................................................................1
1.1 Project Background...........................................................................................1
1.1.1 Project Origin..........................................................................................1
1.1.2 Present Situation and Existing Problems of Water Resources................2
1.1.3 Construction Significance of Project......................................................3
1.1.4 Project Objectives...................................................................................7
1.1.5 Relevant Policies and Regulations..........................................................9
1.1.6 Relevant Planning of Environmental Protection Strategies..................10
1.2 Assessment Purposes......................................................................................16
1.3 Assessment Grade and Key Points..................................................................18
1.3.1 Assessment Grade.................................................................................18
1.3.2 Assessment Key Points.........................................................................19
1.4 Scope of Evaluation, Time Interval of Evaluation and Environmental Protection Objectives
20
1.4.1 Scope of Evaluation.....................................................................................20
1.4.2 Time Interval of Environmental Evaluation................................................23
1.4.3 Environmental Protection Objectives..........................................................23
1.5 Evaluative standards........................................................................................27
1.5.1 Environmental quality standards...........................................................27
1.5.2 Standards for the discharge of pollutants..............................................29
1.6 Environmental impact factors and evaluation factors.....................................33
3
1.6.1 Identification of environmental impact factors.....................................33
1.6.2 Selection of environmental impact and evaluation factors...................35
1.7 Evaluation principles and methods.................................................................46
1.8 Technical route for environmental impact assessment...................................46
2. Framework for Policy, Law and Administration......................................................48
2.1 Documents on Environment Policy and Law..................................................48
2.1.1 Outline...................................................................................................48
2.1.2 Laws and rules on environmental protection........................................48
2.1.3 Technology policy for pollution prevention.........................................50
2.1.4 Plans and layout of social and economic development and environmental protection
51
2.1.5 The urban master planning and related plans........................................51
2.1.6 The technology guideline and standards for environmental impact assessment 52
2.1.7 Environmental quality standard............................................................52
2.1.8 Control standards for pollution discharge.............................................53
2.1.9 World Bank safeguard policies.............................................................53
2.1.10 Documents related to the Project........................................................54
2.2 Environmental Management Institutions and Their Responsibilities.............54
3. Description and Analysis of the Project...................................................................61
3.1 Outline of the Project......................................................................................61
3.1.1 Name, Construction Nature and Legal Person of the Project...............61
3.1.2 Investment of the Project......................................................................61
3.1.3 Composition, construction content and size of the project...................61
3.1.4 Proposed Locale of the Project.............................................................61
3.1.5 Floor Area of the Project and Plane Layout of Factory Area...............69
3.1.6 Construction Progress Schedule and Staffing of the Project................80
3.1.7 Main Technical and Economic Indicators.............................................82
3.2 Construction Proposal of the Project...............................................................83
3.2.1 Water Supply Subproject of Reclaimed Water.....................................83
3.2.2 Processing park sewage treatment and reclamation sub-projects......116
3.2.3 Wuliangsuhai Lake Area Treatment Sub-project...........................121
3.3 Pollution source analysis...............................................................................145
3.3.1 Sub-project of reclaimed water supply...............................................146
4
3.3.2 Waste water treatment and reclamation projects in the manufacture park 156
3.3.3 Project of Wuliangsu Lake area comprehensive treatment.................161
3.4 Relative projects............................................................................................163
4. Environmental Baseline.........................................................................................169
4.1 Profile of Regional Environment..................................................................169
4.1.1 Environmental Profile of Bayannur City............................................169
4.1.2 Environmental Profile of Subitem Location.......................................184
4.2 Evaluation on the situation of regional environment quality........................223
4.2.1 Evaluation on the situation of air environment quality.......................223
4.2.2 Current surface water environmental quality assessment...................237
4.2.3 Assessment of current groundwater environmental quality................247
4.2.4 Evaluation of current acoustic environmental quality........................253
4.2.5 Sediment Monitoring..........................................................................256
4.2.6 Current status of ecological environment...........................................260
4.3 Balance analysis on the project water resource.............................................292
4.3.1 Balance analysis on the regional water resources...............................292
4.3.2 Water capacity balance in Ulansuhai..................................................295
4.4 The pollution source in the project area and its treatment overview............299
4.4.1The water supply and consumption in the project area and the sewage pollution source
299
4.4.2 Industrial solid waste...........................................................................300
5 Comprehensive Environment Impact Assessment..................................................301
5.1 Analysis on Environment Impact during Construction.................................301
5.1.1 Ambient Air Impact Analysis.............................................................301
5.1.2 Water Environment Impact Analysis and Assessment.......................306
5.1.3 Analysis of Acoustic Environmental Impact......................................311
5.1.4 Analysis of Solid Waste Environmental Impact.................................314
5.1.5 Analysis of Ecological Impact............................................................317
5.1.6 Social Environmental Impact Analysis...............................................322
5.2 Environmental Impact Analysis of Operation Period...................................325
5.2.1 Reclaimed Water Supply Works.........................................................325
5.2.2 Sewage treatment and recycling engineering in Processing Park.......331
5.2.3 Wuliangsu Lake Lake Administration Project....................................340
5
5.2.4 Analysis of the sewage treatment plant and recycling plant after completion356
5.2.5 Water environmental impact prediction and assessment of the project’s implementation
359
5.3 Mitigation Measures......................................................................................372
5.3.1 Mitigation Measures in Construction Period.............................................372
5.3.2 Mitigation Measures in Operation Stage....................................................382
6. Environmental Risk Analysis and Relief Measures...............................................398
6.1 Environmental Risk Analysis and Relief Measures of Reclaimed Water Supply Works 398
6.1.1 Environmental Risk Analysis of Reclaimed Water Supply Works...........398
6.1.2 Environmental Risk Relief Measures of Reclaimed Water Supply Works399
6.2 Environmental Risk Analysis and Relief Measures of Sewage Treatment and Recycling
Works..................................................................................................................401
6.2.1 Potential Environmental Risk and Accident..............................................401
6.2.2 Prevention Countermeasure and Measures of Risk and Accident.............403
6.3 Sea Area Treatment Works of Wuliangsu Lake...........................................410
6.3.1 Winter Wetland Operation Analysis..........................................................410
6.3.2 Inlet Water Quantity of Wetland in Winter and Water Quality Analysis. .414
6.3.3 Accident analysis on Abnormal Operation................................................416
7 Comparison, selection and analysis of substitute plans..........................................420
7.1 Content and principle of comparison, selection and analysis.......................420
7.2 Comparison, selection and analysis on zero plan..........................................420
7.3 Comparison, selection and analysis on substitute plan of reclaimed water supply project 422
7.3.1 Comparison, selection and analysis on zero plan of reclaimed water supply project 422
7.3.2 Comparison, selection and analysis on restoration process of reclaimed water supply
project..................................................................................................................424
7.3.3 Comparison, selection and analysis on process plans of reclaimed water supply project
427
7.3.4 Selection of sterilization mode...................................................................430
7.3.5 Comparison and selection on sludge treatment plans of reclaimed water supply works 431
7.3.6 Comparison and selection of pipe material................................................436
7.3.7 Comparison, selection and analysis on plant site plan of reclaimed water supply plant 440
7.4 Comparison, selection and analysis on substitute plan of sewage treatment and reuse item
445
6
7.4.1 Comparison and selection on zero plan.....................................................445
7.4.2 Comparison and selection on sewage treatment process plan...................446
7.4.4 Comparison and selection on sludge treatment processes.........................455
7.5 Comparison, selection and analysis on substitute plan of treatment works of Wuliansu Lake
456
7.5.1 Comparison, selection and analysis on constructed wetland.....................456
7.5.2 Comparison and selection on execution plans of grid water channel........474
8. Analysis on Environmental and Economic Loss and Profit...................................485
8.1 Project Development Target and Impact Analysis........................................485
8.2 Economic Benefits........................................................................................485
8.3 Social Benefits..............................................................................................488
8.4 Environmental Benefits.................................................................................489
8.4.1 Improving Hydraulic Conditions of Sea Area...........................................489
8.4.2 Cutting off Pollutants.................................................................................490
8.4.3 Improving Water Quality of Sea Area of Wuliangsu Lake........................491
9. Public Participation and Information Disclosure...................................................492
9.1 Goal of Public Participation..........................................................................492
9.2 Mode of Public Participation........................................................................492
9.3 Media Announcement-Direct Information Feedback...................................493
9.3.1 Time and Details of the First Media Annoucement...................................493
9.3.2 Time and Details of the Second Media Annoucement...............................494
9.3.3 Summany....................................................................................................495
9.4 Results and Conclusion of Questionaires......................................................495
9.4.1 Results and Conclusion of Individual Questionaires.................................496
9.4.2 Statistical analysis of Group Questionnaire...............................................524
9.5 Public Participation Forum...........................................................................528
9.6 Public Participation Summary and Public Opinion Adoption......................530
9.6.1 Public Participation Summary....................................................................530
9.6.2 Public Opinion Adoption...........................................................................531
10. Social Impact and Migrant Resettlement.............................................................534
10.1 Social Impact Analysis................................................................................534
10.1.1 Project Impact and Service Scope............................................................534
10.1.2 Project Impact Analysis...........................................................................534
7
10.1.3Determination of project affected area.....................................................541
10.1.4 Impact indicator of Project.......................................................................545
10.1.5Analysis on impact by land expropriation................................................551
10.2 Migration and resettlement plans................................................................554
10.2.1Policy basis...............................................................................................554
10.2.2Resettlement policies applicable to this Project.......................................555
10.2.3Compensation standard.............................................................................557
10.2.4Resettlement and compensation plans......................................................560
10.2.5Estimate of compensations for land expropriation and house removal....567
10.2.6 Implementation plans of resettlement works............................................567
10.2.7Organization and structure........................................................................571
11 Abstracts of Environmental Management Plan.....................................................576
11.1 Environmental Management System..........................................................576
11.1.1 Organization of Environmental Protection in Construction Period.........580
11.1.2 Environmental Management Organ in Operation Period.........................584
11.1.3 List of Environmental Management Organs of Sub-project....................584
11.2 Implementation of Environmental Management Plan................................585
11.2.1 Detailed Tasks of Environmental Management Plan...............................585
11.2.2 Contractual Requirement on Environmental Management......................587
11.2.3 Information Exchange and Solution to Non-conformity Case.................588
11.2.4 Training—Necessary Capability Development and Means Development589
11.3 Environment Monitoring Plan.....................................................................593
11.3.1 Monitoring Purpose..................................................................................593
11.3.2 Environment Monitoring Organ...............................................................593
11.3.3 Environment Monitoring Plan..................................................................595
14.4 Estimates on Environmental Management Expenses and Source of Capital600
14.4.1 Budget Distribution..................................................................................600
14.4.2 Capital Source and EMP Budget..............................................................600
11.5 Information Management of Environmental Management Plan.................604
11.5.1 Information Exchange..............................................................................604
11.5.2 Recording Mechanism.............................................................................604
11.5.3 Report Mechanism...................................................................................605
12 Conclusion of Environmental Appraisal...............................................................607
8
12.1 Relevant Policies and Conformity with the Planning.................................607
12.2 Analysis on Water Resources Balance........................................................608
12.3 Appraisal Result of Present Environment Quality......................................609
12.4 Appraisal Result of Environmental Impact.................................................609
12.4.1 Environmental Impact in Construction Period.........................................609
12.4.2 Environmental Impact in Operation Period.............................................612
12.5 Relief Measures of Environmental Impact.................................................615
12.6 Conclusion of Analysis on Environmental Benefits...................................615
12.7 Conclusion of Public Participation..............................................................616
12.8 General Conclusion.....................................................................................616
9
1 General Introduction
1.1 Project Background
1.1.1 Project Origin Bayannur City is located in the west of North China's frontier province, Inner Mongolia
Autonomous Region between 105°12′~109°53′E and 40°13′~42°28′N. It connects Baotou City and
Ulanqab City to the east, borders on Alashan League to the west and faces Ikchor across Yellow
River and borders on People's Republic of Mongolia with a boundary of 368.89km. The city, 378km
long from east to west and 238km wide from north to south, covers an area of about 65,788km 2.
The administrative divisions contain 4 banners, 2 counties and 1 district such as Urad Front Banner,
Urad Middle Banner, Urad Back Banner, Hangjin Back Banner, Wuyuan County and Dengkou
County. Its core area is Hetao Irrigation District. Approved by State Council at the end of 2000, the
city was updated to be a prefecture-level city in the west of the autonomous region.
According to the strategy for economic development of both the autonomous region and
Bayannur City, to make the best of the abundant mineral resources in the city and Mongolia, such
projects have been planned to build, including Qingshan Industrial Park, Jinquan Industrial Park,
Shahai Industrial Park, Linhe Chemical Industry Park and Urad Industrial Base. Thus Bayannur will
be a key heavy chemical industry base in Inner Mongolia Autonomous Region. Water demand for
its perspective long-term plan will reach about 520,000,000m3. The water demand for long-term
plan of such industrial parks in the area along the mountains where water shortage is very acute is
about 410,000,000 m3. According to the estimates of Water Resource Comprehensive Planning
Report of Bayannur of Inner Mongolia Autonomous Region, the gross amount of water resources at
the southern foot of Yishan Moutain in Yellow River valley in Bayannur is 587,000,000m3, where
ground water resource, totaling 380,000,000m3, mainly serve as domestic water for urban and rural
residents. In line with the state’s relevant industrial policies, industrial water is mainly subject to
reclaimedwater.
With 293km2 water surface and about 330,000,000m3 total reservoir capacities, Ulansuhai Nur
is the largest riverside freshwater lake along the middle and upper reaches of the Yellow River. With
the development of industrial production and increase in town populations in the irrigation district,
industrial sewage and municipal domestic sewage are increasing year by year, the pollution of main
1
drain getting worse. Eutrophication Ulansuhai Nur in particular is getting worse. Accordingly, total
phosphorus and nitrogen contents and chemical oxygen consumption in the lake water exceed 3~5
times the national category-3 standard. The water quality is worse than Grade V. The biological
filling speed of the lake is picked up, the ecological functions subsiding. Moreover, before the flood
period, to reserve enough flood storage capacity, it is necessary to take off the check gate at the exit
section of main drain to sluice water to the Yellow River. Large amounts of sewage accumulated in
the lake pose serious pollution threat to Yellow River.
To further promote comprehensive improvement of water environment in Bayannur city, exert
more efforts to strengthen infrastructure construction of urban environment, lower pollution load of
Ulansuhai Nur, slow down environmental degradation, better the quality of urban water
environment and further advance urbanization process and economic growth, Bayannur municipal
Party committee and municipal government decided to cooperate with the Word Bank so as to make
use of World Bank loans to implement comprehensive treatment project of water environment of
Bayannur city. With extensive preliminary investigation and elaborate preparations, Bayannur
submitted a formal application to the State Development and Reform Commission in August 2006
for World Bank load of 150,000,000 dollars (totaling about 2.125 billion RMB with domestic
supporting funds) to implement “Bayannur Water Environmental Treatment Project” (hereinafter
called The Project). This application was approved in July, 2009 and was listed in the China
Alternative Project Planning in 2010-2012 Fiscal Year by Use of World Bank Loan.
1.1.2 Present Situation and Existing Problems of Water Resources The average annual amount of water resources in Bayannur is 5,574,200,000m3, where surface
water resources amount is 4,779,100,000 m3 (most are diverted from Yellow River, amounting to
4,674,800,000 m3, and surface water runoff comes next, amounting to 104,300,000m3 from arid
mountainous pastoral areas), ground water resources amount is 2,419,600,000 m3 and the
exploitable amount is 850,000,000m3.
According to GB3838-2002 Environmental Quality Standard for Surface Water, the water
quality of rivers in the whole city is evaluated in 2008. The water quality of main drain is subject to
Grade Ⅴ, Ulansuhai Nur Grade Ⅴ and showing organic pollution. In terms of nourishment, the
water body of Ulansuhai Nur is subject to heavy eutrophication. The total nitrogen reaches to heavy
eutrophic level, and the total phosphorus to eutrophic level. The average annual salinity of ground
water is 3.920g/l, 0.200g/l less than 2007.
2
According to the Allocation Plan of Yellow River Water Resources approved by No.(1987)67
document issued by General Office of the State Council and governor office meeting of
autonomous region, the target of water amount diverted from Yellow River to Bayannur Hetao
Irrigation District is determined to be 4,000,000,000m3 based on water-saving irrigation plant of
Hetao Irrigation Area. Now Hetao Irrigation Area diverts more water from Yellow River than the
planned quota per year, overusing 674,800,000m3. In addition, among the seven banners, counties
and cities, Urad Front Banner, Wuyuan County and Urad Back Banner face problems of water
quality and water amount. The domestic water demands of urban and rural inhabitants have been
badly affected. The water head site of Urad Front Banner, Alaben region suffers sharp lowering of
water level, having formed large cone of groundwater depression. Water for industrial production
and urban and rural inhabitants is encountering crisis. Quality water that is suitable for human and
animal drinking use within Wuyuan County is less. With much brackish water, water demands of
urban and rural inhabitants faces difficulties. Saiwusu Town, the original locality of Urad Back
Banner Government suffers serious shortage of ground water resource. Therefore, shortage of water
resource has become an important factor restricting socio-economic development of Bayannur city.
1.1.3 Construction Significance of Project 1.1.3.1 Needs for Comprehensive Treatment of Ulansuhai Nur
Located in Urad Front Banner, Bayannur, Inner Mongolia, Ulansuhai Nur is are large
multifunctional lake which is rare in semi-desert regions worldwide and has tremendous ecological
benefit. It is the largest freshwater lake in China and the largest inland lake in northwestern China.
Ulansuhai Nur is an important component of water conservancy project in Hetao Area. It is the
only receiving water and drainage channel of Hetao irrigation return flow, receiving more than 90%
of drained water of the irrigation area. It plays an important role in developing industrial and
agricultural production of Bayannur city.
Owing to the discharge of urban sewage, industrial waste water and agricultural return flow,
Ulansuhai Nur has been one who boasts the fastest swamping speed in the world. If not treated
promptly, it will vanish from the earth in 20~30 years. Then its hydrophyte resources, fishery
resources, bird resources and tourist resources will no longer exist. Moreover, the drainage works of
the 3,935m2 Hetao Irrigation District will not work normally either. Therefore, to improve the
quality of water environment of Ulansuhai Nur, it is of imperative and great strategic significance
to implement the comprehensive treatment project of Bayannur water environment.
3
1.1.3.2 Needs for Comprehensive Allocation of Water Resources
Located in arid and semi-arid areas, Bayannur is typical of temperate and monsoonal climate.
The water resources in this area are relatively poor. The average annual precipitation in the city is
150mm and the evaporation capacity is 2,200mm, the latter is 14 times as much as the former.
Local surface water and ground water are relatively poor, too. Yellow River is the largest surface
runoff across the city. Ground water resources here are mainly formed by recharge from irrigation
by diverting water from Yellow River. Ground water resources, little available, is subject to
complex and extremely heterogeneous distribution. The water quality is commonly bad, and
resource shortage coexists with structural shortage.
According to the Allocation Plan of Yellow River Water Resources approved by No.(1987) 67
document issued by General Office of the State Council, water consumption allocated from Yellow
River to Inner Mongolia Autonomous Region in its normal water income year is 5,860,000,000m3.
However, according to Hetao Irrigation District Water-saving Project Planning, the governor office
meeting of autonomous region in October 1999 preliminarily determined that the target of water
amount diverted from Yellow River to Hetao Irrigation District is 4,000,000,000m3. This raises
much higher requirements for comprehensive allocation of water resources.
With the socio-economic development, expanding urban size and increasing population,
demand for water resources and water environment quality constantly rises. However, historically-
formed allocation model of water resources is far from suitable to Bayannur planning objectives to
realize the transformation of social and economic developmental pattern. Development of
hydroelectric and hydropower resources is still of great potential. Besides, water use efficiency in
both agriculture and industry is low and waste of water is extremely severe. Water consumption
norm in service sector is high, having great potential for water saving. Thus, we must center on
efficient use of water resources and reasonable allocation to promote construction of living system
and protect comprehensive exploitation and utilization of water resources, and advance the socio-
economic development of Bayannur.
1. Promote and Drive Regional Economic Cooperation and Development
Comprehensive allocation of water resources provides a favorable supporting guarantee of
water resources for utilization of mineral recourses of coal and copper in Mongolia and promotion
of regional economic cooperation in international community. Water is the major factor that
restricts the development of industrial parks. To strengthen management and promote optimum
4
allocation, strict policies to limit the use of groundwater, control the use of Yellow River water and
encourage the use of treated industrial waste water and reclaimed water are made for enterprises in
industrial parks. Therefore, building Bayannur reclaimed water supply works by World Bank loan
is very essential, for it solves water use problems in industrial parks on one hand, and reduces
pollutant discharge on the other.
2. Water for Ecological Needs in Ulansuhai Nur
Owing to the discharge of agricultural drainage, city living sewage and industrial waste water
into Ulansuhai Nur, the water is deteriorated and produces serious eutrophication. The lake receives
drainage with organic substances such as nitrogen and phosphorus from the irrigation area is
close to 600,000,000 m3. As a result, fertilizer and other nutrient salt were flowed into the lake,
providing a great force for its swamping progress and making it one of the lakes which has the
fastest swamping speed. According to measurement, the gross productivity of aquatic macrophytes
in Ulansuhai Nur has reached more than 2,300,000t/a (fresh weight). It is a world typical weedy
lake of heavy eutrophication. Reed spread rapidly over the lake and weeds grow wild. The water
surface is almost totally covered by sunken plants. The underwater parts of reeds and weeds root
and sink down to the bottom, which produces intensive sedimentation promotion. The lake bottom
is rising at a rate of 1-9mm/year. The sludge and sand are filling it, and worsen year by year. At that
rate, Ulansuhai Nur will become reed marsh within 20~30 years, losing all ecological functions. To
improve the water environment of Ulansuhai Nur, some effective measures must be taken to control
exogenous pollution and reduce endogenous pollution.
3. Resolve Contradiction between Industrial and Agricultural Water
Over these years, as the water resources in Yellow River basin is in increasing short supply,
the state place Yellow River water resources under unified control, allocating water to areas
diverting from Yellow River based on the principle of “increase in high flow period and decrease in
low flow period” in different time periods. Water supply for Hetao Irrigation District tends to
become tenser day by day. Especially in the period of summer irrigation when water supply is most
tense, the water quantity falls into bad shortage. In 2003, the water shortage gap in Hetao Irrigation
District in irrigation period reached 55%. With the development of national economy in Bayannur
and readjustment of industrial structure, as well as accelerating pace of urbanization and
industrialization, a number of new industrial parks have risen up. Thus the demand of industrial
development for water resources becomes much more urgent. To guarantee local industrial water,
5
promote sustainable development of local industry, alleviate imbalance between supply and
demand, water resources shall be allocated in a optimum way so as to realize reasonable
exploitation and utilization in accordance with the distribution features of water resources in the
city, current situation of development and use and the requirement of economic development and
production pattern. Besides, more efforts shall be paid to developing and using non-traditional
water resources.
1.1.3.3 Needs to Protect Water Entironment of Yellow River
There are many high-pollution industrial enterprises of energy, heavy chemical, non-ferrous
metal and paper-making on the banks of Yellow River in Ningxia and Inner Mongolia. As the
pollution treatment lags far behind and the wastewater treatment rate is somewhat low, many
enterprises failed to meet the discharge limits, wastewater and sewage quantity continuing
increasing year by year. With the accelerated progress of Western Development, new high-pollution
projects are launched while the ole ones are not thoroughly treated. This aggravates the pollution of
Yellow River, making easy the water pollution emergency in years when water of Yellow River is
not much and in periods when flood peak is caused by heavy rainfall.
The primary runoff source of Ulansuhai Nur is field irrigation return flow from Hetao
Irrigation Area, and industrial and domestic sewage comes after. Irrigation return flow to Ulanushai
Nur is dominant in the irrigation period while domestic sewage dominant in non-irrigation period.
According to the law of return flow in Hetao Irrigation Area and the requirement of torrential flood
storage and regulation in flood period, Ulanushai Nur need discharge water to Yellow River in June
every year so as to lower the water level and reserve storage capacity for storage and regulation of
torrential flood.
Based on the analysis of the operation mode of Ulanushai Nur, it satisfies the requirements to
cause sudden water pollution incidents in trunk stream of Yellow River. First, it has practical
requirements to discharge storage and regulation water into Yellow River; second, the water quality
of it now is worse than Grade Ⅴ, giving it a pollution source which may cause sudden water
pollution incidents; third, when torrential flood, once breaking out in northern mountain areas,
exceeds the storage and regulation capacity, and Ulanushai Nur has to discharge flood, sudden
water pollution incidents in trunk stream of Yellow River may be caused as well. Huajinagying,
about 90km down from the estuary of Yellow River into which Ulanushai Nur returned flow
debouches, is the water head site for Baotou city and Baotou Iron and Steel Company. Thus, sudden
6
pollution incident of Yellow River trunk streak caused by pollution source of Ulanushai Nur will
have a direct impact on the safe water supply for the largest city in Inner Mongolia Autonomous
Region and China’s important industrial base. The hazard and influence will be significant.
Implementing comprehensive treatment project of Bayannur water environment by World
Bank loan to improve Ulanushai Nur water environmental quality and establish better water quality
early warning system is able to protect the safety of Yellow River water entironment.
1.1.4 Project ObjectivesThe comprehensive treatment works of Bayannur water environment is to mainly improve the
quality of water environment in Bayannur city, make reasonable regulation and storage of water
resources and promote the overall sustainable development of ecological environment and
economic society through the construction of works to clean the water body of Yellow River Hetao
Irrigation Area and Ulansuhai Nur.
This project mainly include the Processing Park Sewage Treatment and Reuse Works (Urad
Back Banner Processing Park (Hohhot) Sewage Treat Works, Ganqimaodu Port Processing Park
(Deling Mountain Town) Sewage Treatment and Reuse Works, Urad Front Banner Processing Park
(Xianfeng Town) Sewage Treatment and Reuse Works), Processing Park Reclaimed Water Supply
Works (Urad Back Banner Processing Park, Ganqimaodu Port Processing Park, No. 3 and 7
Drainage Line Reclaimed Water Supply Works) and Ulansuhai Nur Treatment Works (Ulansuhai
Nur Grid Waterway Works, Ulansuhai Nur Ecotone Artificial Wetland Works and Area Source
Pollution Control Demonstration and Promotion Program).
1) Sewage Treatment and Reuse and Reclaimed Water Supply Works
Efforts will be made in the construction of sewage treatment plants and reclaimed water supply
Works to both ensure the industrial water of processing park and reduce the total pollutants of main
drainage line so as to lower the pollution load from main drainage line to Ulansuhai Nur and
improve the water quality of Ulansuhai Nur.
2) Comprehensive Treatment Works of Ulansuhai Nur
In order to improve the water environment quality and fully play the water regulation and
storage functions of Ulansuhai Nur, a lot of works construction is required:
① Ulansuhai Nur Garden Grid Waterway Works
The excavation of sea zone grid waterway will be made to reinforce the water body circulation,
control the internal pollution of Ulansuhai Nur, keep the spreading of sea area plants under
7
limitation, harvest water plants and transfer nitrogen and phosphorus as well as effectively lower
the nutrient salt content of sea area and release the eutrophication trend.
② Ulansuhai Nur Ecotone Artificial Wetland Works and Area Source Pollution Control
Demonstration and Promotion Program
For This project, the ecotone artificial wetland works will be established in west Ulansuhai
Nur and northwest small sea area to make the back water of main drainage line, No. 8 and 9
drainage lines and control the area source pollution from end of pipe.
The area source pollution control demonstration and promotion is made along with middle and
later period promotion works based on the national water works. The area source pollution control
in irrigation area is a drainage area source pollution control system works to be completed in phases
and promoted to all irrigation area from pilot areas.
In order to improve the water environment quality of Bayannur, a lot of favorable engineering
are under construction:
For urban domestic sewage and industrial waste water, banners and counties of Bayannur are
organizing the construction of sewage treatment plants and reclaimed water works. The
construction and running off sewage treatment facilities will greatly reduce the gross pollution of
water environment and significantly improve the water quality of Ulansuhai Nur.
For rural domestic sewage and farming and breeding feces, the rural promotion of “Biogas
Works” is being made under New Rural Construction to realize the resource, decrement and
innocent treatment of sewage and rubbish and clean rural environment.
For water break pollution in irrigation area farms, the key technical works of state water
pollution control, the water break pollution trench reconditioning and water infusion technologies
and the treatment and key pollutant reduction and wetland reconditioning key technologies are
undergone. Comprehensive test demonstration base is being established in irrigation area to
demonstrate the key technologies of agricultural water break pollution treatment.
In order to ensure the ecological water utilization of Ulansuhai Nur, the conveyance canal
expansion and dredging works will be made to ensure the water compensation for Ulansuhai Nur
from Yellow River Ice Flood and the seawater rehabilitation work, bed mud dredging and ice flood
compensation will be also implemented in Ulansuhai Nur to improve its water quality and prevent it
from eutrophication and degeneration of wetland.
The above water pollution treatment works along with the implementation of The project will
8
reduce the pollution load entering Ulansuhai Nur and significantly improve the water pollution
condition of irrigation area and Ulansuhai Nur.
1.1.4.1 Improving the Water Environment Condition of Bayannur City
The comprehensive treatment works of Ulansuhai Nur will be implemented to dredge water
courses of lakes, construct artificial wetland, reduce the total amount of pollutants, reduce internal
source pollution, make real-time monitoring on water quality and divert Yellow River ice flood
water to improve the water quality of Ulansuhai Nur.
The processing park sewage treatment and reuse and reclaimed water supply works will be
constructed to reduce the pollution load entering Ulansuhai Nur, prevent Ulansuhai Nur from
becoming eutrophication and paludification and improve the water environment conditions of
Ulansuhai Nur and protect Yellow River ecological environment.
1.1.4.2 Comprehensive Allocation of Water Resources
The construction of processing park sewage treatment and reuse works and reclaimed water
supply works and the industrial use of treatment water after irrigation area water break will be made
to efficiently use water sources, save underground water resources and effectively release the water
shortage caused by industrial and agricultural production in Hetao Irrigation Area.
Ulansuhai Nur will be built into an agricultural irrigation and regulation water source in Hetao
Irrigation Area through the Comprehensive Treatment Works. When much water coming from the
Yellow River or water resource is sufficient, the Yellow River water will be diverted into Ulansuhai
Nur. And when water is shortage for agriculture, water will be diverted into Yellow River to meet
the irrigation demand.
1.1.5 Relevant Policies and Regulations1.1.5.1 Chinese Relevant Policies and Regulations
The reclaimed water supply and sewage treatment and reuse works are the “brackish water,
poor quality water and sea water exploitation and utilization works” and “three wastes”
comprehensive utilization and treatment works under the environmental protection and resources-
saving and comprehensive utilization categories encouraged by the catalogue for guidance of
national industrial structure restructuring (2005 edition). Ulansuhai Nur is the natural reserve of
Inner Mongolia Autonomous Region. According to the Regulations on the Nature Protection
Regions of the People’s Republic of China, nobody is allowed to enter the core area and run tourism
and production acuities in the buffer zone of the natural reserve. However, This project is of water
environment treatment works aiming at improving the water environment quality and ecological
9
conditions of Ulansuhai Nur, protecting and restoring its wetland functions. The project will avoid
constructing in core area but in buffer zone and experimental area. According to the Circular of the
of the General Office of the State Council on Intensifying Wetland Protection and Management
(GBF [2004] No.50), importance shall be attached to the strengthening of wetland protection and
restoring of function. Therefore, the Ulansuhai Nur treatment Works is in accordance with the
national relevant laws and regulations. To sum up, This project meets the requirements of national
relevant industrial policies, laws and regulations.
1.1.5.2 World Bank Environmental Assessment Policy
The implementation of sewage treatment and reuse and reclaimed water supply works,
especially the Ulansuhai Nur sea area treatment works may reduce the pollutant-intaking amount of
Ulansuhai Nur, improve its water environment quality, improve and protect its aquatic environment
and restore its nature reserve function. According to the World Bank environmental assessment
policy (OP 4.01, 4.04), the project of world bank such as economic research, Project loan and policy
dialogue are all favorable to protect, maintain and restore the natural habitat and its functions. The
World Bank has been supporting and expecting the borrower to adopt defensive measures on natural
resource management to ensure the sustainable development of environment. It has also initiated
and supported the protection and land-improvement activities for natural habitat and provided funds
for the natural habitat and ecological function protection programs which are favorable to the
national and local development. The World Bank has also further initiated the restoring and
reconstruction works on the deteriorative natural habitat. Therefore, this project meets the
environmental assessment policies of World Bank for loaning program.
1.1.6 Relevant Planning of Environmental Protection Strategies
1) National Economic Development Program
During the “11th Five-Year” period, the overall requirements of Bayannur for economic and
social development are to take Deng Xiaoping Theory and the important thought of “Three
Represents" as guidance, lead economic and social development by scientific concept of
development. make further reform and deepen opening-up policies, make further implementation of
rejuvenating and prospering the market by science, technology and talents, accelerate economical
transition, adjust economic structure, change economic growth methods, speed up industrialization
and urbanization process, promote the construction of socialism new rural and pastoral areas,
increase infrastructure and ecological environment construction, establish Chinese western green
agricultural and animal products and non-ferrous metals industry production and opening-up to the
North bases, establish important hinges linking North China and North west, insist on people-
oriented, make overall development of social undertakings, improve community services, better 10
social security and assistance mechanism, make all efforts to maintain social stability, accelerate the
overall construction of affluent society and try hard to build a prosperous, civilized, ecological and
harmonious Bayannur.
The macroeconomic development strategy of Bayannur is to aim at the ecological environment
protection and sustainable development, take green agriculture and animal husbandry as basis, take
the agricultural and animal products deep processing as guidance and selectively develop the new
type industrialization of mining and smelting industries.
During the “11th Five-Year” period, one of the main objective of economic and social
development of Bayannur is to make achievements in environmental protection and construction,
including the further improved ecological environment, above 15% forest coverage rate, Class Ⅰ
country level of atmospheric environment, qualified water environment, 90% qualified discharge
standard of “Three Waste” and 40% comprehensive utilization rate.
The Plan has put forward an objective to build a resource-saving and environmental-friendly
society by integrating water resources, making unified planning of Yellow River, surface water,
underground water and rain water and trying hard to realize the cyclic utilization of water resources.
It has also request the whole city to center on water resources optimal allocation, insist on
broadening sources of incoming and reducing expenditure on reasonable utilization of water
resources, deepen water right displacement, positively explore the water consumption modes of
along-mountain industrial enterprise from Ulansuhai Nur and main drainage line, promote water
saving in cities, make full use of the treated water and Yellow River ice flood and flood diversion
water, make reasonable use of lake, sea, reservoir and running off water under the premise of un-
destroying wetland ecological environment and attach importance to protect industrial water. On the
other hand, the city is request to intensity water environment protection and treatment, plan drinking
water protection area, strictly implement the water quality control standard for drinking-water
source Carry out industrial discharge license system, achieve more than 90% pass rate of industrial
waste water, attach importance to treat papermaking, brewing and smelting pollution, consolidating
achievements, improve urban sewage treatment ratio, intensity comprehensive treatment of
agricultural area source pollution, reduce application of fertilizer and pesticide, strengthen the
construction of urban sewage treatment facilities and supporting pipelines, gradually reach the
industrial and domestic sewage discharge standard, cut off pollution source of Yellow River and
underground water, plan Ulansuhai Nur treatment Works, implement urban roads, pipelines, water
11
supply and discharge, refuse treatment and sewage treatment programs taking all these as the
important programs during the “11th Five-Year Plan” period.
To sum up, the construction of this project is an important part of Bayannur Municipal
National Economic and Social Development Program, which is of great importance to the
realization of planned environmental protection objectives and in accordance with the requirements
for development.
2) Urban Master Planning
The general objective and strategy of the Bayannur master planning are: to speed up the
process of urbanization, to enhance the core competitiveness of the city, to actively support by
coordinated action the development strategy fit to the regional situation of Inner Mongolia
Autonomous Region, and to build Bayannur City into a medium-sized city with increasingly
integrated services, making it a Hetao garden city with continually developing economy, evolving
society, and excellent maintaining environment.
The Bayannur master planning puts the protection of ecological environment at the first place,
basically realizing ecologization and garden style. The green coverage of the city shall get up to
more than 35%, and the urban per capita public green space 19m 2. These are the objectives and
strategy of the environmental development of Bayannur City.
Development and construction activities aiming to non-agricultural nature under city regional
planning of the outside of city proper in the Bayannur master plan divide the Bayannur space into
three land use types, namely rigid control developing area, limited control developing area, and
developing construction area. Rigid control developing area can be proximately regarded as non-
allowable construction area, including: ①First-grade basic farmland protection areas and first-grade
basic pasture designated in Overall Plan of Land Utilization; ② existing and planning natural
reserves designated in Conservation Development Plan; Water protection area specified in ③ Over
City Plan; cultural heritages and historical and cultural sites under government protection, etc.④
designated by Cultural Relics Protection Department; Other non-allowable construction control⑤
areas and important green areas for environmental protection, etc. along both sides of the nation
highway or provincial highway; Developing construction area is mainly city(town) planning
construction land scope confirmed by the general planning of various levels of city(or town), and
the scope of use of land in construction like independent industrial and mining sites and major
regional infrastructure, public social service facilities approved of the development and construction
12
by the planning, land and other related administrative departments, non-agricultural development
and construction activities approved by the law are allowed and encouraged in development
construction areas; strictly control areas outside the development areas and the development
construction areas as limited control development area, can do moderate village and town
constructions and non-agricultural constructions under the control of strict policy and planning. Any
non-agricultural development construction activities in limited control development areas are
subject to careful legal procedures. The site selections of both resurgent water supply project and
wastewater treatment and recycling project of this project are not in strict control development area,
and The Ulansuhai Nur area treatment project is an environment treatment project aiming at
improving the sea area water environment, not belongs to production construction development
activity.
The water resources planning of Bayannur master planning regard adjusting water structure,
developing water-saving agriculture, reducing agricultural water use to replenish industrial water
use, actively developing wastewater treatment and reclaimed water recycling, relieving and
avoiding the vicious cycle of scarcity of clean water as the planning principles. It also levies
charge for water resources on agricultural exploitation of groundwater in irrigation areas, and
maintains the balance of groundwater resources by the use of price leverage. The layout of
industry should consider the actual situation of water resources. Meanwhile, large high-water-
consumption industries are not encouraged to develop. Efforts shall be made to increase the
recycling rate of industrial water use, so as to realize the harmony and sustainable development of
industry and water resource. It puts forward active wastewater treatment and recycles wastewater,
aiming to establish wastewater treatment factories in each county and each town and realizing
wastewater reuse to replenish industrial water use and landscape water use, so as to release the
increasingly tense water use conflict.
The environmental protection objectives of Bayannur master planning is to bring the
environment pollution and ecological deterioration fully under control, completely realize the
discharge standards of pollutants, and enter a virtuous cycles of ecological systems. Thereinto, the
atmosphere quality should stay at the national secondary standard. Among the quality of surface
water environment, the water quality of the Yellow River and its irrigation channels should reach
the National Surface Water Standard Class III, Ulansuhai Nur, the main drain and arterial drainage
should reach National Standard Grade IV, realizing the sustainable development of social economy 13
and ecological environment. Such areas as Yellow River, Ulansuhai Nur, Ural Mountains National
Forest Park, Nudengsuosuolin Natural Reserve, water and soil erosion area, prairie desertification
and degradation area, Ulan Buh desertification area and Hetao secondary salinization area, the
urban area and all counties shall be regarded as key areas of environment protection. Efforts shall
be focused on the pollution prevention and ecological environment protection of the Yellow River
and Ulansuhai Nur. Efforts shall be also made to speed up the construction of waste water treatment
factories in each county, controlling industrial pollution sources along the banks and achieving
standard discharge of domestic and industrial wastewater. Pollution shall be controlled in terms of
sources. Comprehensive renovation shall be imposed on Ulansuhai Nur. Great efforts shall be made
to plant trees and grass, make a good job in water and soil conservation and restore natural ecology.
The regional pollution emission shall be subject to strict control. Long-term effective management
measures among industrial enterprises shall be carried out. Water quality of irrigation channels from
Yellow River and sewage discharged into Ulansuhai Nur shall be under strict control so as to make
wastewater treatment rate to reach 100%, ensuring the water quality of Yellow River to reach
National Surface Water Standard Class III.
In sum, the sites selection of all works of the comprehensive control project of the Bayannur
water environment by World Bank loans is in accordance with the requirements of the urban master
planning and city regional planning, and it is also an important measure to accomplish city goals,
water resource allocation and environment protection goals of Bayannur master planning and city
regional planning. Therefore, the project accords with the Bayannur master planning and the city
regional plan.
3) Land Use Planning
The land use type of this project’s reclaimed water supply works and sewage treatment plant
site is waste land, unused land and processing park construction land respectively, none of which is
in the strictly controlled development area. Therefore, the works construction of this project meets
the land use planning of Bayannur.
4) Environmental Protection Planning
Water environment protection objectives of Bayannur include: urban drinking water quality
shall meet the sanitary standard for drinking water; water quality of the Yellow River Bayannur
League section: water at the boundary section shall meet the class standard of the nationalⅢ
Environmental Quality Standard for Surface Water; water quality of Ulansuhai Nur shall meet the
14
class standard of the national Ⅲ Environmental Quality Standard for Surface Water; water quality
of the main drain and other drainage lines shall meet the class Ⅳ standard of the national
Environmental Quality Standard for Surface Water;
The “11th Five-Year” planning objectives of environmental protection are determined as
follows: by 2010, the development trend of environmental pollution and ecological damage shall
reduce, urban lake water pollution and atmospheric environment pollution shall be reduced, urban
environmental infrastructural construction shall be greatly improved; realize the total amount
control objective of pollutants. The total amount control objective of water pollutants shall be as
follows: COD shall be controlled within 40,000 t/a and the ammonia nitrogen within 2,000 t/a.
Water pollution control measures to be adopted during the period of “11th Five-Year Plan” are
mainly as follows:
1) Establish and implement the water pollution control planning on each drainage line, main
drain and Ulansuhai Nur with the focus on improving the water environmental quality of river
reaches in key cities and towns. Slow down lake sedimentation and effectively control pollution and
eutrophication trend. Build sewage treatment plant in 4 cities and towns to improve sewerage
treatment rate and attainment rate, gradually realize the reclamation of sewage and reduce the
discharge amount of pollutants and the pollution load of each drainage line and lake.
2) Perfect pollution monitoring network, pay attention to preventing the pollution damage of
accidental toxic and hazardous chemicals. Implement pollutant discharging license and total amount
control system, increase the monitoring efforts and accelerate the pollution source control. The
control attainment rate of enterprises in the city with the daily discharge of wastewater more than
100t shall reach 90%; the city's two major paper mills shall build alkali recovery system and
achieve discharge up to standard.
3) Establish the groundwater pollution control measures of Linhe District, unified planning,
unified management and rational exploitation. Strictly control the pollution of industrial wastewater,
toxic and hazardous substances and solid waste on groundwater.
4) Combining with industrial enterprise management and technological transformation,
develop clean production technology in paper making, brewing, energy, metallurgy, chemical
industry and other key industries and gradually realize circular economy. Meanwhile, in the
introduction of new projects and new technologies, the energy saving, comprehensive utilization
and pollutant discharge reduction shall be brought into business management and technological
15
transformation. Actively carry out the certification of ISO14000 environmental management series
standards and environmental labeling products, and improve the environmental management level
of enterprises.
In addition, aiming at the water environmental pollution status of Ulansuhai Nur, based on the
overall control and planning, it is planned to strengthen the control work form the following two
aspects:
1) Control on farmland area source. According to the characteristics of agricultural area
pollution in Hetao irrigated areas, propose agricultural area pollution prevention project planning;
through the adjusting of agricultural structure, popularize the long-acting and sustained-release
compound fertilizers and high-efficiency, low-toxic and less persistent pesticides, promote
agricultural water-saving irrigation technology, introduce advanced and scientific technique of
fertilization, control agricultural area pollution, effectively control and reduce the eutrophication of
Ulansuhai Nur.
2) Works treatment measures: adopt various measures such as the setup of pre-setting reservoir
in the front of lake, partial deepening at lake bottom, aquatic plant harvesting, diversion of water
from the Yellow River to lake and resources development and utilization, etc. Promote the control
of Ulansuhai Nur, restore its own beneficial cycle and maintain the sustainable development.
This project is an organic part of the environmental protection planning of Bayannur, which can effectively promote the comprehensive control of Bayannur water environment, especially the quality improvement of Ulansuhai Nur water environment.
1.2 Assessment Purposes
According to the regulations of China Environmental Influence Assessment Law, Regulations on the Administration of Construction Project Environmental Protection and Notice on the Strengthening of Administration on the Environmental Impact Assessment of Construction Projects Using Loans from International Financial Organizations and the requirements of World Bank’s Safeguard Policies, as well as domestic and World Bank’s environmental impact assessment procedure, the environmental impact assessment on this project shall reach the following main purposes:
(1) Through data analysis, field survey and monitoring, and necessary simulation experiment and analogy analysis, make a comprehensive assessment on the background situation of environment in the assessment areas, diagnose the main environmental problems existing in current situation, provide background information for the prediction and assessment of the environmental impact degree and range of the projects to be built as well as the future final acceptance of projects.
(2) Through field survey and analogy analysis, judge the environmental impact factors during the construction process and after the operation of projects, determine the parameters of primary pollution sources.
16
(3) Through the adopting of model simulation, analogy survey and other technical means, predict and assess the impact degree and range of the projects on the atmospheric environment, water environment, soil, ecological environment, noise and social environment in the assessment areas.
(4) In accordance with the requirements of relevant laws, regulations and technical specifications, combining with the characteristics of local natural and social environment, propose and stipulate the protective measures which shall be adopted to reduce environmental impact.
(5) Through the assessment of this project, propose targeted and effective mitigation measures and environmental management plan, provide basis for the independent assessment of the World Bank on this project, also provide scientific basis for the construction, operation, environmental management and environmental pollution prevention of water environment comprehensive control project, minimize the adverse impacts of project construction on surrounding environment, maximize the social environmental benefit, achieve the coordination and unification of economic, social and environmental benefits.
(6) This environmental impact assessment not only focuses on the analysis of water environment improvement of Ulansuhai Nur, but also considers the feasibility analysis on water resources allotment of the project; not only considers the impact of this project, but will consider the combined influence of the projects having been built, under construction and planned to be implemented in the next few years.
1.3 Assessment Grade and Key Points
1.3.1 Assessment GradeAccording to the regulations of the Notice on the Strengthening of Administration on the
Environmental Impact Assessment of Construction Projects Using Loans from International
Financial Organizations (HJ[1993] No. 324) of State Environmental Protection Administration of
China and other ministries and commissions as well as the World Bank’s Safeguard Policies OP4.01
Environmental Assessment, combining with the identification and screening results of this project
environmental assessment factors, the environmental assessment category of this project is
determined as category A.
Carry out the assessment grade classification according to the Technical Guidelines for
Environmental Impact Assessment (HJ/T2.1-93, HJ2.2-2008, HJ/T 2.3-93, HJ/T2.4-1995 and
HJ/T19-1997). (Expressed in the form of table)
(1) Surface Water Environment
According to the surface water environmental impact assessment classification of HJ/T2.3-93
Technical Guidelines for Environmental Impact Assessment—Surface Water Environment, the
assessment grade is determined by the following four factors: sewage discharge of the construction
project, complexity of sewage quality, scale of surface water area and surface water quality
17
requirements. The surface water environment assessment grades of this project are as follows:
because there is no wastewater discharged in the processing park sewage treatment and reuse works
of this project, only a brief analysis will be made on the water environmental impact of such works;
the tail water discharge amount of reclaimed water supply works is small, the water quality is
simple and the tail water is discharged into the class Ⅳwater body of surface water, the assessment
grade is determined as Grade Ⅲ and qualitative assessment will be made on the water
environmental impact of such works; the assessment grade of Ulansuhai Nur sea area control works
is difficult to be directly judged according to the four factors alone. The pollutant source is mainly
the pollutants discharge during the construction period. In view of the special properties of
Ulansuhai Nur, the project scale is large and the involvement aspect is broad. Therefore, the
assessment grade is determined as Grade Ⅱ of surface water environmental impact assessment.
(2) Ecology
The reclaimed water supply works and the processing park sewage treatment and reuse works
of this project have very small range of influence, also very small impact on the ecological
environment, therefore, only a brief analysis will be made on the ecological environment impact of
these two types of works; the sea area control works of Ulansuhai Nur is environmental treatment
works itself and its environmental impact is mainly the environmental impact during the
construction period, which is temporary, short-term and will gradually disappear as the construction
is completed. Therefore, the ecological environment assessment grade of this project is determined
as Grade .Ⅱ
(3) Atmospheric Environment
The impacts of this project on atmospheric environment mainly include the dust emission
during the construction period and the offensive odor during the operation period of the processing
park sewage treatment and reuse works as well as the reclaimed water supply works. This project
will adopt biological deodorization after the collection of the offensive odor caused during the
operation period, which has small discharge amount; in addition, there are very few environmental
objects around each works. Therefore, the atmospheric environment assessment grade of all works
of this project is determined as Grade Ⅲ and only qualitative assessment will be made.
(4) Acoustic Environment
The impacts of this project on acoustic environment mainly include the construction machinery
and traffic noises during the construction period of each works and the power equipment operating
18
noise during the operation period of the processing park sewage treatment and reuse works as well
as the reclaimed water supply works. Consider that the noise impact during the construction period
is short-term behavior, and during the operation period, the site selection of the sewage treatment
and reuse works as well as the reclaimed water supply works avoids the densely populated
residential areas, hospitals, schools and other sensitive points. Therefore, the acoustic environment
assessment grade of all works of this project is determined as Grade Ⅲ and only qualitative
assessment will be made.
1.3.2 Assessment Key PointsThe implementation of this project includes the construction period and operation period. The
assessment key points of the construction period are as follows:
(1) Ulansuhai Nur bed mud and ecological environment impact;
(2) Environmental impact and mitigation measures of pollution during the construction period.
The assessment key points of the operation period are as follows:
(1) The quality improvement of Ulansuhai Nur water environment after the project is put into
operation and the combined influence of tail water discharge on Ulansuhai Nur water quality. This
part includes 3 main aspects:
① Combined influence on Ulansuhai Nur water quality after completion of the project;
② Impacts on the growing and reproduction condition changes of terrestrial life and aquatic
life and the impacts on aquatic resources, breeding and fishery production before and after
completion of the project;
③ Impacts of single subproject on Ulansuhai Nur water quality during the operation.
(2) Environmental impact mitigation measures and environmental management plan during the
operation period of the project.
(3) The treatment impacts and mitigation measures of sludge in the processing park sewage
treatment and reuse works, reclaimed water supply works and the excavated bed mud in grid
waterway.
1.4 Scope of Evaluation, Time Interval of Evaluation and Environmental
Protection Objectives
19
1.4.1 Scope of EvaluationThe scope of overall environmental evaluation of this project is:
(1)Under the requirements of Technical Guidelines for Environmental Impact Assessment, and
on the basis of formulated evaluation grades, the scope of evaluation of each subproject shall be
regarded as the basic scope of evaluation of the overall environmental evaluation of this project;
(2)If there are environmental protection objectives or objectives concerned by the universal
Security Policy proximate to the basic scope of evaluation, they should be included in the scope of
evaluation;
(3)Elements and issues having direct relevance with or potential influence on this project
should be included in the scope of evaluation as well;
(4) Other correlative similar projects (relating works) over the same period or regions
possibly having an impact should be considered in the scope of evaluation.
The scope of environmental evaluation of all classes of subprojects can be seen in Table 1.4-1
and Figure1-1-Figure1-6.
Table 1.4-1 Scope of Environmental Evaluation of Subprojects
Number
Project Category
Works Name
Scope of Evaluation
AtmosphereWater
Environment
Acoustic Environmen
t
Ecological Environment
1 Reclaimed water supply
Urad Back Banner
processing zone water-supply
works
100m around the
construction site;
200m on both sides of
the construction
pipelines; 2.5km
around the operation
site
3km off the upstream and downstream of the main drain water intake
200m around the
site;200m on
both sides of the
construction pipelines
100m around the construction site; 20m on both sides of the construction
pipelines
Ganqimaodu Port processing
zone water-supply works
100m around the
construction site;
300m on both sides of
3km off the upstream and downstream of the main drain water
intake and the
200m around the
site;300m on
both sides of the
200m around the construction site;20m on both sides of the construction
pipelines
20
the construction
pipelines; 2.5km
around the operation
site
tail water discharge
outlet
construction pipelines
Tri-drainagereclaimed water
supply works
100m around the
construction site;
300m on both sides of
the construction
pipelines; 2.5km
around the operation
site
3km off the upstream and downstream
of the tri-drainage
water intake and the
tail water discharge
outlet
200m around the
site;300m on
both sides of the
construction pipelines
200m around the construction site;20m on both sides of the construction
pipelines
Hept-drainageReclaimed
water supply works
100m around the
construction site;
300m on both sides of
the construction
pipelines; 2.5km
around the operation
site
3km off the upstream and downstream of the hept-
drainage water intake
and thetail water discharge
outlet
200m around the
site;300m on
both sides of the
construction pipelines
200m around the construction site;20m on both sides of the construction
pipelines
2 Processing zone
wastewater treatment and reuse
works
Urad Back Banner
processing zone (Huhe Town) wastewater
treatment and reuse works
100m around the
construction site;
2.5km around the operation
site.
-
200m200m
around the site
100m around the site
Ganqimaodu Port
processing zone (Deling Mount
100m around the
construction site;
- 200m around the
site
100m around the site
21
Town) wastewater
treatment and reuse works
2.5km around the operation
site.Urad Front
Banner processing zone
(Xianfeng Town)
wastewater treatment and reuse works
100m around the
construction site;
2.5km around the operation
site
-200m
around the site
100m around the site
3
Ulansuhai Nur
sea areatreatment
works
Ulansuhai Nurgridding field
waterwayworks
200m around the
construction site;
Sediment pile site 500m
Ulansuhai Nur
Sea area
200m around the
construction site
Ulansuhai Nurarea and 1km around the sea area
Ulansuhai Nur biological
transition zone artificial
wetlands works
200m around the
construction site
Ulansuhai Nur
area; ground water
evaluation scope is 500m
around the artificial wetlands
200m around the
construction site
Ulansuhai Nurarea and 1km
around the sea area
1.4.2 Time Interval of Environmental EvaluationThe overall report of this project environmental evaluation mainly analyses and evaluates two
periods of construction and operation.
1.4.3 Environmental Protection ObjectivesAccording to the regulations of domestic laws and regulations on environmental influence
evaluation and universal security policy, the environmental protection objectives concerned by this
project environmental evaluation can be seen in Table 1.4-2 and Figure 1-1-Figure 1-6
Figure 1.4-2 Environmental Protection Objectives of Subprojects
Works Name Environmental Elements
Environmental protection
Location Resident Populatio
Protection Requirements
22
Objective n
Urad Back Banner
processing zone (Huhe
Town) wastewater treatment
project and Urad Back
Banner processing
zone Reclaimed
water supply works
Ambient air, acoustical
environment
Menglain Society 1
SE,1.92km
260
Secondary standard in Ambient Air Quality Standard(GB3095-
1996);Maximum allowable concentration standards of harmful substances in residential area atmosphere in Design of Industrial Enterprises hygiene standards(TJ 36-79)
Menglian Society 2 S,1.82km 450
Menglian Society 3 S,1.83km 270
Menglian Society 4 S,2.48km 200
Livestock Society SE,1.77km
140
Menglian Village S,2.81km 300
Zhangdagebo NE,1.60km
400
Xinhong Village 1
NE,3.75km
210
Surface water Main drain S,2.9km ——
IV Class standard in Surface water quality
standards(GB/T3838-2002)
Ecology200m Expansion
off the factoryExtent 5.47ha
——Bring water and soil loss
under control, not influence the ecology significantly
Tri-drainageReclaimed
water supply works
Ambient air, acoustical
environment
DashunchengGroup 4 E,0.71km 210
Secondary standard in Ambient Air Quality Standard(GB3095-
1996);Maximum allowable
concentration standards of harmful substances in
residential area atmosphere in Design of Industrial
Enterprises hygiene standards(TJ 36-79)
Shawan Village Cultivation
Society
SW,0.5km
50
Zhangtiancaigedan
NW,0.69km
260
Surface waterTri-drainage
channel E,0.1km ——
IV Class standard in Surface water quality
standards(GB/T3838-2002)
Ecology200m expansion off the factory
Extent 3.52ha
——Bring water and soil loss
under control, not influence the ecology significantly
Hept-drainageReclaimed
water supply works
Ambient air, acoustical
environment
Five Star Team 1 N,2.33km
1400Secondary standard in Ambient Air Quality Standard(GB3095-
1996);Old City Society
1E,1.66km 500
23
Maximum allowable concentration standards of
harmful substances in residential area atmosphere
in Design of Industrial Enterprises hygiene standards(TJ 36-79)
Querhong Gedan WN,1.68km
520
Weijia Gedan W,1.79km
490
Liuwen Gedan SE,1.24km
500
Wuyuan County brick yard
W,0.15km
60
Hept-drainageWastewater
Treatment FactoryS,0.1km 50
Hongzhu Environmental
Protection Thermoelectricity
CO., Ltd.
SW,0.5km
1000
Surface waterHept-drainage
channel E,0.1km ——
IV Class standard in Surface water quality
standards(GB/T3838-2002)
Ecology200m expansion off the factory
Extent 3.52ha
——Bring water and soil loss
under control, not influence the ecology significantly
Ganqimaodu Port
Processing zone
Reclaimed water supply
works
Ambient air, acoustical
environment
Muyanghai Farm Company 6
SE,0.79km
270Secondary standard in Ambient Air Quality Standard(GB3095-
1996);Maximum allowable
concentration standards of harmful substances in
residential area atmosphere in Design of Industrial
Enterprises hygiene standards(TJ 36-79)
Fodder Team NE,0.81 km
315
Tractor Plowing Team
NE,1.39 km
280
Eryang Gedan SW,2.35 km
340
Surface water
Wangbahaizi N,2.44km
——
III Class standard in Surface water quality
standards(GB/T3838-2002)
Main drain S,1.68km ——
IV Class standard in Surface water quality
standards(GB/T3838-2002)
Ecology200m expansion off the factory
范围3.05haExtent 3.05ha
——Bring water and soil loss
under control, not influence the ecology significantly
24
Ganqimaodu Port
Processing zone (Deling
Mount Village)
wastewater treatment and reuse works
Ambient air, acoustical
environment
East Siyitang SW,1.90km
310Secondary standard in Ambient Air Quality Standard(GB3095-
1996);Maximum allowable
concentration standards of harmful substances in
residential area atmosphere in Design of Industrial
Enterprises hygiene standards(TJ 36-79)
West Siyitang SW,3.11km
350
Ganqimaodu Port Processing zone
NE,1.58km
200
Ecology200m expansion off the factory
Extent 2.55ha
——Bring water and soil loss
under control, not influence the ecology significantly
Urad Front Banner
processing zone
(Xianfeng Town)
wastewater treatment and reuse works
Ambient air, acoustical
environment
Shagedan Village S,0.33km 53Secondary standard in Ambient Air Quality Standard(GB3095-
1996);Maximum allowable
concentration standards of harmful substances in
residential area atmosphere in Design of Industrial
Enterprises hygiene standards(TJ 36-79)
Zhaoxiaoer Gedan SW,0.79km
350
Shijia Gedu S,1.23km 150
Fujia Gedu SE,1.38km
510
Anweigedu SW,1.44km
153
Gejia Gedan N,1.26km
130
Wangyinwei Gedan
NW,1.35km
130
Surface waterQuadri-drainage
Channel S,0.33km ——
IV Class standard in Surface water quality
standards(GB/T3838-2002)
Ecology200m expansion off the factory
Extent 11.16ha
——Bring water and soil loss
under control, not influence the ecology significantly
Wuliangsu Sea Comprehensiv
e Treatment works
Ambient air, acoustical
environment
XinminSW,1.66
km300
Secondary standard in Ambient Air Quality Standard(GB3095-
1996);Maximum allowable
concentration standards of harmful substances in
residential area atmosphere in Design of Industrial
Enterprises hygiene standards(TJ 36-79)
XinhaiSW,1.96
km450
Bailiukou W,0.70 km
260
Wuhai Village W,1.95 km
490
Lihonghao W,0.98 km
330
Wangmanku W,0.74 350
25
kmBabei Water
CourseW,2.29
km240
Banjie Channel W,0.20 km
260
Xiaoquanzi W,0.40 km
220
Honggebo W,0.50 km
500
Huanchao Gedan W,1.56 km
420
GuangyizhanSW,1.35
km280
Shilanli VillageNW,2.89
km480
Zhaogetai Village SW,2.38 km
270
Erfen Channel W,1.28 km
200
Xinjian VillageNW,1.92
km290
Wayaotan N,1.45 km
1050
Diangedan E,1.88 km
300
Mabozi SE,2.35 km
220
Bawan SE,1.48 km
400
Batou SE,0.70 km
300
Xin’an Farm Banch 9 W,0.2 km 210
Cachu Gedan W,1.96 km
260
Xin’an Farm Branch 8 W,0.7 km 200
Xin’an Farm Branch 7 W,0.5 km 320
Yongfeng Village NW,0.5 km
400
Ulansuhai Nur core area E,0.2km ——
Surface water Ulansuhai Nur Extent 293.2km2
—— III Class standard in Surface water quality standards
26
(GB/T3838-2002)
Ground waterUlansuhai Nur
artificial wetland
500m outside project
——
III Class standard in Groundwater Quality
Standard(GB/T 14848-93)
Ecology
200m off Ulansuhai Nur
areaExtent
293.2 km2 ——
Project construction does not affect animals and plants in conservation
districts
1.5 Evaluative standards
1.5.1 Environmental quality standards
(1)Ambient air
On the basis of the approval letter on environmental assessment implement standard of
Bayannaoer Environmental Protection Bureau, the zones where the sewage treatment and reuse
engineerings as well as reclaimed water supply engineering are carried out in the Processing
Industrial Park, shall all be the Class II environmental air quality functional zones, in which the
Ambient Air Quality Standard ( GB3095-1996) and the secondary standard in modification notice
shall be implemented for the environmental air assessment; the Wuliangsuhai Zone shall be the
Class I environmental air quality functional zone, in which the Ambient Air Quality Standard
( GB3095-1996) and the primary standard in modification notice shall be implemented for the
environmental air assessment; the maximum allowable concentration standard of harmful
substances in the atmosphere of residential zone of Sanitary Standard for Design of Industrial
Enterprises (GB3095-1996) shall be carried out for H2S and NH3; for standard values, see Table
1.5-1.
Table 1.5-1 Ambient air quality standards (mg/m3)
Name of pollutants Value timeConcentration limit Remarks
Primary standard
Secondary standard
SO2
Average value for one hour
0.15 0.50 GB3095-1996
Daily average value 0.05 0.15
Annual average value 0.02 0.06TSP Daily average value 0.12 0.30
Annual average value 0.08 0.20
27
PM10Daily average value 0.05 0.15
Annual average value 0.04 0.10
NO2
Average value for one hour
0.12 0.24
Daily average value 0.08 0.12
Annual average value 0.04 0.08
H2S Once 0.01 TJ 36-79the maximum allowable concentration standard of harmful substances in the atmosphere of residential
zones
NH3 once 0.20
(2)Environment of groundwater
The class III standards of Groundwater Quality Standards (GB/T14848-93) shall be
implemented for the groundwater quality, see Table 1.5-2.
Table 1.5-2 Environmental Quality Standards for Groundwater
No. Name of projects Unit Standard values Remarks1 pH —— 6.5~8.5
GB/T 14848-93Class III standards
2 Total hardness mg/l ≤450
3 Nitrates mg/l ≤20
4 Nitrites mg/l ≤0.02
5 Ammonia nitrogen mg/l ≤0.2
6 Potassium permanganate index
mg/l ≤3.0
7 Prussiates mg/l ≤0.05
8 Fluoride mg/l ≤1.0
9 Cr6+ mg/l ≤0.05
10 Volatile phenols mg/l ≤0.002
11 Cu mg/l ≤1.0
12 Zn mg/l ≤1.0
13 Fe mg/l ≤0.3
14 Chlorides mg/l ≤250
17 Hg mg/l ≤0.01
18 Mineralization mg/l ≤1000
19 Total number of bacteria
个/L ≤100
20 Total coliforms 个/L ≤3.0
(3)Environmental quality standards for surface water
For the environmental quality of total and other draining water related to this project, the Class
IV standards of Environmental Quality Standards for Surface Water ( GB3838-2002 ) shall be
28
implemented, while the Environmental Quality Standards for Surface Water shall be implemented
for the water environmental quality of lakes "haiti" (meaning "little sea") and Wuliangsuhai Sea
Area. For the specific limits, see Table 1.5-3.
Table 1.5-3 Environmental quality standards for surface water (mg/l)No. Name of projects
Class III standard values
Class IV standard values
Source of standards
1 PH 6-9 6-9
GB3838-2002
2 CODcr ≤ 20 30
3 DO ≥ 5 3
4 BOD5 ≤ 4 6
5 NH3-N ≤ 1.0 1.5
6 Oils ≤ 0.05 0. 5
7 Chlorides (in term of CL) ≤ 250 250
8 Volatile phenols ≤ 0.005 0.01
9 Sulfides ≤ 0.2 0.5
10 Mercury ≤ 0.0001 0.001
11 Total phosphorus ≤ 0.2 0.3
12 Total nitrogen ≤ 1.0 1.5
(4)Environmental quality standards for noise
The sewage treatment and reuse engineerings are carried out in the Processing Industrial Park,
in which the Class III standards of Environmental Quality Standards for Noise (GB3096-2008) shall
be implemented for the environmental quality for noise; the zones where the reclaimed water supply
engineering is carried out shall be the functional zones for Class II sound environment, in which the
Class II standards of Environmental Quality Standards for Noise (GB3096-2008) shall be
implemented for the environmental quality for noise; the zones where the comprehensive treatment
engineering of Wuliangsuhai Sea Area is carried out shall be the functional zones for Class I sound
environment, in which the Class I standards of Environmental Quality Standards for Noise
(GB3096-2008) shall be implemented for the environmental quality for noise. For the
environmental quality standard values for noise, see Table 1.5-4.
Table 1.5-4 Environmental quality standards for noise
Category During the daytime [dB(A)] At night [dB(A)]
29
1 55 45
2 60 50
3 65 55
1.5.2 Standards for the discharge of pollutants
(1)Standards for the discharge of water pollutants
For the wastewater discharge standards of reclaimed water supply engineering, the secondary
standards of national Integrated Wastewater Discharge Standards (GB8978-1996) shall be
implemented; for the wetland drainage engineering of artificial biological filter areas, the primary
standards of national Integrated Wastewater Discharge Standards (GB8978-1996) shall be
implemented. For the specific standard values of some pollutants, see Table 1.5-5.
Table 1.5-5 Integrated wastewater discharge standards (Unit: mg/l)Pollutant factors COD BOD5 SS
Animal or vegetable oils
Oils
Primary standard ≤100 ≤30 ≤70 ≤20 ≤10Secondary standard ≤150 ≤60 ≤200 ≤20 ≤10
Pollutant factorsAmmoni
a nitrogen
Phosphorus
Chromaticity
pH Anion active agent
Primary standard ≤15 ≤0.1 ≤50 6~9 ≤5.0Secondary standard 25 0.3 ≤80 6~9 ≤10
(2)Emission standards for environmental air pollutants
For the emission of atmospheric pollutants during construction, the Integrated Emission
Standards of Atmospheric Pollutants (GB16297-1996) shall be implemented; for the inorganization
emission monitoring concentration limits of particulate matters in the atmospheric pollutants from
new pollutant sources, the standard value shall be 1.0mg/m3 hereof; for the emission of odor
pollutants of sewage treatment and reuse engineerings in each Processing Industrial Park, the
secondary (new) standards of the national Pollutant Emission Standards for Municipal Wastewater
Treatment Plants (GB18918-2002) shall be implemented; for the standard values, see Table 1.5-6;
as the secondary (new) standards of Emission Standards of Odor Pollutants (GB14554-93) are
implemented, for the standard values, see Table 1.5-7.
Table 1.5-6 The maximum allowable concentration of exhaust emission at the factory boundary (at edge of
protection zone)
No. Control projects Secondary standard(mg/m3)30
1 Ammonia 1.5
2 Sulfureted hydrogen 0.06
3 Odor concentration 20
Table 1.5-7 Factory boundary standard values of odor pollutants
No. Control projects Primary standard(mg/m3)1 Ammonia 1.0
2 Sulfureted hydrogen 0.03
3 Odor concentration 10
(3)Noise
For the factory boundary noise of sewage treatment and reuse engineerings in the Processing
Industrial Park, the Class III standards of Standards of Noise at Boundary of Industrial Enterprises
(GB12348-2008)shall be implemented; for the factory boundary noise of reclaimed water supply
engineering, the Class II standards of Standards of Noise at Boundary of Industrial Enterprises
(GB12348-2008)shall be implemented; for the comprehensive treatment engineering noise of
Wuliangsuhai Sea Area, the Class I standards of Standards of Noise at Boundary of Industrial
Enterprises (GB12348-2008) shall be implemented; as the Noise Limits for Construction Site
(GB12523-90) are implemented on construction site, for the standard limits, see Table 1.5-8 and
1.5-9.
Table 1.5-8 Standard limits of noise at boundary of industrial enterprises
Period of timeCategory of noise functional areas
In the daytime[dB(A)] At night[dB(A)]
1 55 45
2 60 50
3 65 55Table 1.5-9 Noise limits for construction site
Construction stage
Chief noise source In the daytime At night Unit
Cubic metre of earth and
stone机 Bulldozers, excavators and loaders 75 55 dB(A)
Piling All kinds of piling machines 85 It is forbidden dB(A)31
for construction
StructureConcrete mixers, vibrators and electric
saws70 55 dB(A)
Decoration Cranes and elevators 65 55 dB(A)(4)Solid wastes
For the pollutant emission of Wuliangsuhai grid channel excavation sediments, sewage
treatment and reuse engineering sludge and reclaimed water supply engineering sludge in the
Processing Industrial Park, the relevant standards of national Pollutant Emission Standards for
Municipal Wastewater Treatment Plants (GB18918-2002) shall be implemented, and the sludge
should meet the provisions of Table 1.5-10 after the stabilization treatment; When the sludge after
the treatment is used for agriculture, its pollutant concentration shall meet the requirements of Table
1.5-11, while the Control Standards for Pollutants in Sludges from Agricultural Use (GB4284-84)
shall be implemented; when the sludge after the treatment is treated by a landfill method, the
control standards for safety landfill shall be implemented; as the Identification Standards for
Hazardous Wastes - Leaching Toxicity Identification (GB5085.3-1996) are implemented for the
leaching toxicity identification of sludge, see Table 1.5-12.
Table 1.5-10 Control indexes for stabilization of sludge
Method of stabilization Control projects Control indexes
Anaerobic digestion Degradation ratio of organic substance(%) >40
Aerobic digestion Degradation ratio of organic substance(%) >40
Aerobic compost
Rate of water content(%) <65
Degradation ratio of organic substance(%) >50
Death rate of worm eggs(%) >95
Bacteria value of fecal coliforms >0.01
Table 1.5-11 Control standard limits for pollutants in sludges from agricultural use
No. Control projectsMaximum permissible content(mg/kg dried sludge)On acid soils(pH<6.5) On neutral and alkaline
soils (pH>=6.5)1 Total cadmium 5 202 Total mercury 5 153 Total lead 300 10004 Total chromium 600 10005 Total arsenic 75 756 Total nickel 100 2007 Total zinc 2000 3000
32
8 Total copper 800 1500
9 Boron 150 150
10 Oils 3000 300011 Benzo (a) pyrene 3 3
12
Polychlorinated dibenzo dioxins / polychlorinated dibenzofurans (PCDD / PCDF unit: ng toxicity units / kg dried
sludge)
100 100
13Adsorbable organic halogen compound
(AOX) (in terms of Cl)500 500
14 Polychlorinated biphenyls (PCB) 0.2 0.2Table 1.5-12 Identification standards for leaching toxicity
No. ProjectsMaximum allowable concentration of
leaching liquor,mg/l
1Mercury and its compounds (in term of total
mercury)0.05
2 Lead (in term of total lead) 33 Cadmium (in term of total cadmium) 0.3
4 Total chromium 10
5 Hexavalent chromium 1.5
6Copper and its compounds (in term of total
copper)50
7 Zinc and its compounds (in term of total zinc) 50
8Beryllium and its compounds (in term of total
beryllium)0.1
9Barium and its compounds (in term of total
barium)100
10 Nickel and its compounds (in term of total nickel) 10
11Arsenic and its compounds (in term of total
arsenic)1.5
12 Inorganic fluoride (excluding calcium fluoride) 5013 Cyanide (in term of CN) 1.0
(5)Sanitation protection distance
According to the requirements of Construction Standards for Municipal Sewage Treatment
Engineering Projects of the Ministry of Construction, the treatment & production facilities of
sewage & sludge resulting in odor shall be located in the downwind direction in summer in the
auxiliary production areas of sewage treatment plant, far from residential zones outside the plant as
much as possible, and in accordance with relevant national regulations. If not meet the
requirements, the distance of odor arising from production facilities between the sewage treatment
33
plant and residential zones outside the plant should not be less than 50 ~ 100 meters.
1.6 Environmental impact factors and evaluation factors
1.6.1 Identification of environmental impact factorsThe implementation of this project will help to reduce the pollution load of Wuliangsuhai as
well as improve its water environment, which is important not only for the promotion of
comprehensive and sustainable development of Bayannaoer's environment and social economy, but
also for the protection of water ecological environment security of the Yellow River. At the same
time, during the construction and operation, the implementation of this project may also have some
adverse environmental impacts on the social environment, ecological environment and
environmental quality. On the design stage, the site selection, selection and comparison of technical
schemes, feasibility studies and other works shall be carried out mainly, which won't directly have
some adverse impacts on the environment in general.
The impacts during the construction and operation mainly include:
(1)Social and environmental impacts: The implementation of this project will inevitably
bring the certain socio-economic impacts on the proposed areas, mainly including the impacts of
land acquisition and demolition. This project will involve four administrative villages of four towns
(streets) of five banners (counties) of Bayannaoer, a state-owned farm as well as a state-owned
pasture, in which 22 rural residents of 5 families will be affected by land acquisition, who are the
affected population not dismantled arising from land acquisition. This project does not involve the
houses to be dismantled, with the collection and temporary acquisition of various land of 3597.25
mu, including 758.00 mu of collecting land, 2839.25 mu of temporary land and150 scattered fruit
trees, in which the land with an area of about 50.5ha will be occupied for the project construction,
and then about 22 people will be affected by the project construction.
The problems of land acquisition, demolition and resettlement caused by this would affect the
daily lives of local residents, resulting in changing their possession quantity of means of production
and subsistence; the construction for roads and sewage pipe networks would also affect the travel
and security of residents along the line, as well as traffic conditions, etc..
(2)Impacts on ecological environment
As for the occupation of land for project construction, the local total arable land and vegetation
34
quantity will be reduced, changing the nature of land use, causing the impact on the local
agricultural ecology; destroying the vegetation on the project proposed site during the construction;
easily resulting in the soil erosion due to inadequate protection on the high filled and deep
excavated sections, earthwork filled and excavated sections as well as temporary piling sections,
etc.; impacting on the Wuliangsuhai aquatic life due to the release of pollutants from bottom sludge
during the construction for grid channel excavation engineering in Wuliangsuhai Sea Area.
(3)Impacts on environmental quality
During construction: The nearby water bodies may be polluted by the running, spilling,
dripping and leaking grease/oil stains from construction machinery as well as domestic sewage
caused by construction workers, and the release of pollutants from bottom sludge during the
construction for grid channel excavation engineering in Wuliangsuhai Sea Area will impact on the
water quality of Wuliangsuhai; the ambient air will be polluted by a great amount of dust generated
in the material transport and mixing processes; the mechanical noise will also impact on the normal
work and living of residents nearby construction site; the running frequently construction vehicles
will impact on the existing traffic order.
During operation: To some extent, the surrounding environment will be polluted as well due to
the odor waste gas giving out during the sewage treatment and reuse engineerings as well as the tail
water discharged during the reclaimed water supply engineering in the Processing Industrial Park;
for the drainage during the wetland engineering in artificial filter areas,due to the reduction of
quantity of pollutants discharged into Wuliangsuhai, the water environmental quality of
Wuliangsuhai will be significantly improved. Since the local engineering needs to be consolidated
and maintained and the vegetation still needs some time to be recovered, the phenomenon of soil
erosion will still exist for a period of time after the construction period.
To sum up, the main existing impact factors of this project during construction and operation
include:
( 1 ) Social environment: Land occupation, demolition, relocation and resettlement, road
traffic as well as urban appearance and landscape, etc.;
(2)Ecological environment: Changing the impacts on the water ecological environment due
to the land use condition, vegetation destruction, soil erosion and grid channel excavation, etc.;
35
( 3 ) Water environment: The the release of pollutants from bottom sludge for grid
excavation, domestic sewage and road runoff during construction; the production sewage and living
sewage during operation, etc.;
(4);Noise environment: The traffic noise and machinery noise, etc.;
(5)Ambient air: Dust and exhaust pollutants arising from transport vehicles as well as odor
produced by piling up and transporting the bottom sludge for grid excavation during construction;
the foul gas generated from the sewage treatment and reuse engineerings in the Processing
Industrial Park during operation, etc..
1.6.2 Selection of environmental impact and evaluation factorsBased on the above analysis, combining the engineering category and characteristics of this
project, the environmental impact recognition matrix has been established, see Table 1.6-1.
36
Table 1.6-1 Environmental impact recognition matrix
Constructio
n phase
Building
activities
Impact factors
Natural environment Ecological environment Social environment
Atmospheric
environment
Water
environment
Noise
environment
Land
utilization
Water and
soil
conservation
Plants Animals Landscape Employmen
Income
of
residents
Local
economy
Quality
of lifeTourism
Constructio
n period
Selection of
construction site-○ -○ -○ -★ -☆ -★ -○ -★ +○ +○ +○ -○ -○
Material
handling-○ -○ -○ -○ -★ -★ -○ -★ +○ +○ +○ -○ -○
Site cleaning -○ -○ -☆ -○ -☆ -★ -☆ -★ +○ +○ +○ -○ -○
Engineering
construction-★ -○ -★ -☆ -★ -★ -○ -★ +○ +○ +○ -○ -○
Excavation of
grid channel-☆ -★ -☆ -○ -○ -★ -★ -☆ +○ +○ +○ -○ -☆
Operation
period
Sewage
treatment and
reuse
engineerings
-☆ +★ -☆ -○ -○ -○ -○ +★ +☆ +☆ +☆ +☆ +★
Reclaimed
water supply
engineering
-○ +☆ -☆ -○ -○ -○ -○ +★ +☆ +☆ +☆ +☆ +★
Artificial
wetland+○ +★ +○ +☆ +☆ +★ +★ +★ +☆ +☆ +☆ +☆ +★
Note: The symbol★indicates the significant impact; the symbol ☆indicates the general impact; the symbol ○indicates the slight impact; the symbol -indicates the negative impact; the symbol
+indicates the positive impact.
37
For the identification results of environmental impact factors of various sub-projects, see Table
1.6-2.
The selecting principles of environmental assessment factors shall be:
A、Normal pollutant factors;
B、Pollutant factors greatly impacting on the environment and belonging to the characteristics
of sub projects;
C、Factors specified by clear limits in accordance with national environmental standards.
Based on the identification of environmental impact, in accordance with the major pollutants
determined by the engineering analysis, for the selected environmental evaluation factors of various
subprojects, see Table 1.6-3.
(1)Evaluation factors of current surface water: Potassium permanganate index, BOD5, DO,
NH3-N, TN, TP, pH, lead and total mercury;
Predictive analytical factors: TN, TP and eutrophication.
(2)Evaluation factors of groundwater: NH3-N, NO2-N, As, Pb, Cd, Hg, Cr6 + and total
coliforms;( 3 ) Aquatic ecological evaluation factors: Status, algae content, chlorophyll a, dominant
species, zooplankton, benthic animals and large aquatic plants;
Predictive analytical factors: Chlorophyll a, zooplankton and large aquatic animals.
(4)Environmental evaluation factors of bottom sludge: Content of organic matter, CEC, pH,
Pb, Cr, Cd, Hg, As and pH;
(5)Environment evaluation factors of noise: Equivalent continuous dB (A) sound level;
(6)Atmospheric Environment Assessment factors: Odor.
38
Table 1.6-2 Identification results of environmental impact factors of various sub-projects
Actions possibly
impacting on the
environmental
resources and value
Damages or benefits of natural or
social environmentBasis for impact analysis Typical mitigation measures
Categories of sunprojects and possible identification of
impact factors
Reclaimed
water supply
engineerings
Sewage treatment
and reuse
engineerings in
the Processing
Industrial Park
Comprehensive
treatment in
Wuliangsuhai Sea
Area
1 、 Environmental issues related to project location (site selection)
Impacts on production
systems (such as
agriculture)
Loss of production capacity
Occupied area
type of production/income
of unit ha
Changing the location of
project
(relocation)
compensation measures
√
Impacts on trafficChanging the roads in fields or
residential zones
Description of roads
(width and length)
area and service
population
Changing the location of
project
rehabilitation or
replacement of traffic
√ √
Destruction of the
existing buildings
Loss of private buildingsType, quantity, value,
removal population
Changing the location of
project
properly arranging the
removal
immigrants
Loss of infrastructure Type, characteristics and
estimating the value
Changing the location of
project
compensation or
√ √
39
substitution
Destruction of areas
with ecological value
Destruction of vegetation
Vegetation area/plant
species
value (financial and
ecological)
Changing the location of
project
restoring the vegetation
√ √
Destruction of biological diversityList of species
special areas
Changing the location of
project
reducing the land area
√
Impacts on protected areas:
National parks and natural reserves
Type and purpose of
protection
total area, area to be
affected
Changing the location of
project
reducing the land area
√
Impacts on the surface water
environment and flood risk
Hydrological parameters,
monitoring values of
water quality
Changing the location of
project
changing the location of
outfall
√ √ √
Destruction of
drainage channels and
ditches
Floods, soil acidification
Main drainage patterns or
line of channels and
ditches (pipeline)
Changing the location of
project
paying attention to the
protection of drainage
channels and ditches during
construction
√
Artificial
infrastructure to be
built in outdoor scenic
Destruction of landscape and
tourism value
Destructiveness and area
of landscape value
Changing the location of
project
carrying out the appropriate
√
40
areasdesign to protect the scenic
areas
2 、 Environmental issues possibly existing during construction of project
Temporary occupied
land for work sheds
and storage areas, etc.
Impacts on land use and productionOccupied area, use,
location
Reducing the area of
occupied land, requiring the
contractor's obligation
monitoring and supervising
the construction activities
√ √ √
Clearing of vegetationDestruction of woodland, orchard
and farmland
Type / area and economic
value of vegetation to be
damaged
Clearing ways, monitoring
the clearing activities
division of area
√ √ √
More accessible to
arrive in natural areas
There are risks, such as the risk of
poaching, etc.
Location of sensitive
areas
threatened areas or
species
Contractor's obligations
monitoring and managing
the construction personnel
√
Wastes generated
from the civil
engineering Loss of soil erosion and sediment
Location of earth and
stone works for
excavation, landfill and
disposal, natural drainage
patterns
Contractor's obligations
(drainage and sedimentation
pool)
monitoring
√ √ √
Temporary occupation or
destruction
Location, scope, purpose
of occupied land
The contractor is obliged to
submit a Management Plan
for Damaged and Temporily
Occupied Land.
√ √ √
Emission of dust and other particles Location, distance and Schedule of engineering √ √ √
41
wind direction in
residential zones
construction
contractor's obligations
(sprinkling)
monitoring the activities of
the civil engineering
Excavation of grid
channel in Sea Area
During the excavation and disposal
of grid channel in Sea Area, the
sediments of bottom sludge can
release some pollutants. If disposed
inappropriately, they will pollute
the environment.
Measurement of sampling
analysis of sediments
quantities of grid channel
excavation
Methods of excavation
disposal conditions
(stacking or processing),
monitoring
√
Pollution caused by bottom sludge
disposed inappropriately
Yield, composition, trace
and disposal method of
bottom sludge
Detailed management and
disposal plans for bottom
sludge
monitoring
√
Impacts on aquatic lifeList of species
special areas
Changin the construction
methods
developing the detailed and
effective mitigation
measures
√
Transportation of
construction materials
and engineering
equipment
Particulate matter and noise
transportation security
Material volume, traffic
volume
means of transportation
through environmentally
sensitive areas
Contractor's obligations:
maintaining the vehicles and
road signs, monitoring the
means of transportation
√ √ √
42
Engagement of
construction
personnel
If hiring the local labor, the direct
benefits can brought to the local
residents and ethnic minorities.
Predicting the number of
employees
estimating the number
and proportion of local
staff to be employed
Contractor's obligations
(implementing in EMP)
monitoring
√ √ √
Health and safety impacts on the
construction personnel and
surrounding residents
Number of personnel to
be possibly affected
health statistics
(incidence rate)
conditions on local
infectious and epidemic
diseases
Contractor's obligations:
Health and safety
management
monitoring
√ √ √
Nearby surface water polluted by
domestic sewage
Quality of surface water,
environmental quality
standards, emission
standards
facilities for downstream
water conservancy works
Contractor's obligations:
Managing and monitoring
the wastes as well as health
and safety
√ √ √
Use of large
construction
equipment
Noise and waste (exhaust) gas
impacting on the surrounding
residents
Construction equipment
required for use,
construction schedule
distance from the nearest
residential zones, its
population density
direction and velocity of
Construction operations of
large-scale equipment
prohibitted at night
notifying the time of
construction operations to
the surrounding residents
contractor's obligations
√ √ √
43
wind
noise and waste gas
emission standards
monitoring
Production of solid
wastes
Pollution of soil, rivers and
groundwater aquifers
Number and type of
wastes: Domestic
garbage, construction
waste, spoil, chemical
waste
Waste management and
disposal program
contractor's obligations
monitoring
√ √ √
Completion of
construction
Not repairing or improperly
repairing on siteLocation and area of
temporary land
equipment to be possibly
used and wastes to be
generated
The contractor is obligated
to prepare a Site Restoration
Programme after
Completion for each project,
in which the repair
expenditure shall be added.
√ √
3 、 Environmental issues possibly existing during operation of project
1) Subprojects of
reclaimed water
supply engineering
Operation of water
reclamation plantNoise
Noise standards
distance to the nearest
residential zones
Procuring the low-noise
equipment, strengthening
the routine maintenance
monitoring
√
Impacts on water sources Average monthly output
of supplying water from
water sources
Ensuring the minimum
storage capacity from water
sources
√
44
intake ratio of total
storage capacity
meeting the minimum
water requirements of
other water
monitoring the water quality
and quantity of underground
water sources
Impacts on emission of tail water
Water quality of surface
water, water quality of tail
water, quantity of water
Environmental quality
standards, emission
standards, monitoring the
water quality of tail water
water environmental
protection plans and
emergency measures
√
Production of sludge
in water reclamation
plant
Impacts caused by the improper
management of sludge
Estimated output and
composition of sludge
Disposal measures of sludge
detailed management plans
of sludge
monitoring
√
Pullution of raw water Pollution status of water sources
Water quality of water
sources
Type and quantity of
surrounding main
pollution sources
Monitoring the water
quality of raw water
Protection plans for water
sources and emergency
measures
√
2) Subprojects of
sewage treatment and
reuse engineerings
Production of sludge Pollution caused by the Output and composition 监 测 Detailed management √
45
in the sewage
treatment plant
management and improper
treatment of sludge
of sludge
trace and disposal
methods of sludge
and disposal plans for
sludge
monitoring
Impacts of agricultural sludge
Sludge purification /
concentration of heavy
metals
Sludge reuse standards
detailed disposal and
utilization plan for sludge
monitoring
√
Toxicity and corrosivity of sludge
and waste residue
Category of toxic or
corrosive substances
distance to the nearest
residential zones
Storage and treatment of
sludge and waste residue
control of toxic substances
√
Operation of sewage
treatment plants,
sewage networks and
sewage pumping
stations
Odor and noise
Location of pumping
station/odor distribution
sources,
distance to residential
zones
Noise standards, foul gas
emission standards
procuring the low-noise
equipment, strengthening
the duties of maintenance
monitoring
√
3) Subprojects of
management in
Wuliangsuhai Sea
Area
Operation of artificial
wetland
Impacts on the water environmental
quality of Wuliangsuhai
Hydrological parameters,
monitoring values of
water quality
Water quality standards for
surface water
emission standards
monitoring
√
46
Impacts on natural reserves
Type and purpose of
protection
total area
Biological diversity
monitoring the water quality√
47
Table 1.6-3 Selection of environmental evaluation factors of various subprojects
No.Category of subprojects and
content of major projects
Environmental evaluation factorsDegree of possible
impact
Ecological
environmentAmbient air Surface water Groundwater
Noise
environm
ent
Solid
wastes
Constructio
n period
Operat
ion
period
1
Reclaimed
water supply
engineering
Water supply
networks
Land
utilization, soil
erosion
vegetation
TSP 、 P
M10 SS
NH3-N, NO2-N,
As, Pb, Cd, Hg, Cr6
+ and total
coliforms
Traffic
noise
constructi
on noise
Constructi
on spoil - ★ -
Water
reclamation
plant
Land
utilization,
vegetation
TSP 、 P
M10
pH, COD,
BOD, NH3-N,
TP, TN, oils,
SS, volatile
phenols and
fecal coliforms
-Factory
boundary
noise
constructi
on noise
Constructi
on spoil
sludge
- ★ + ☆
2 Sewage
treatment
and reuse
engineerings
Pipe network
engineering
Land
utilization, soil
erosion
vegetation
TSP 、 P
M10 SS
NH3-N, NO2-N,
As, Pb, Cd, Hg, Cr6
+ and total
coliforms
Traffic
noise
constructi
on noise
Constructi
on spoil- ★ -
Sewage
treatment plant
Land
utilization,
vegetation
TSP,
PM10,
ozone, NH3
and H2S
- - Factory
boundary
noise
constructi
Constructi
on spoil
surplus
sludge
- ★ + ★
48
on noise
3
Management
engineering
in
Wuliangsuha
i Sea Area
Excavation of
grid channel
Algal volume,
chlorophyll a,
dominant
species,
zooplankton,
benthic
animals and
large aquatic
plants
TSP,
PM10,
ozone, NH3
and H2S
pH, COD,
BOD, NH3-N,
TP, TN, lead
and total
mercury
- Construct
ion noise
Excavatio
n of
sludge
- ★ + ★
Artificial
wetland
Algal volume,
chlorophyll a,
dominant
species,
zooplankton,
benthic
animals and
large aquatic
plants
TSP 、 P
M10
pH, COD,
BOD, NH3-N,
TP, TN, lead
and total
mercury
- Construct
ion noise- ○ + ★
Note: The symbol★indicates the significant impact; the symbol ☆indicates the general impact; the symbol ○indicates the slight impact; the symbol -indicates the negative impact; the
symbol +indicates the positive impact.
49
1.7 Evaluation principles and methods
(1)Meet the requirements of construction project environmental management
of national and local environmental protection departments and industry competent
authorities as well as the requirements of environmental impact evaluation of World
Bank and Notice on Strengthening the Environmental Management of Loan
Construction Project of International Financial Organization;
( 2 ) In accordance with the characteristics of construction environmental
impact assessment, take the key environmental factors and pollution factors as the
evaluation objects, highlight the evaluation of key protection objectives, and pay
attention to the rational analysis of discharge after reaching standards, cleaning
production, gross control and site selection;
(3);Use the methods of combining with the analogy investigation, model
simulations, data collection and analysis, etc., fully use the existing data, predict the
environmental benefits and possible environmental impacts of project construction,
and use the method of providing the Public Opinion Questionnaire and other methods
for public participation;
( 4 ) For the management services, prepare the environmental management
plans (EMP), provide the administration sections and construction units with the
opinions and suggestions for decision and reference, through the development of a
series of measures for mitigation, monitoring and institution building during the
implementation and operation of projects, so as to eliminate or compensate the
adverse effects on society and envirenment during project construction;
(5)From the point of environmental protection, demonstrate the feasibility of
project construction, strive to make the scientific and feasible conclusion of
environmental impact assessment, and provide the scientific basis for the
50
environmental protection management during the approval, design and construction of
projects.
1.8 Technical route for environmental impact assessment
This technical route for environmental impact assessment shall be shown in
Fig.1.8-1.
Fig.1.8-1 Technical route for environmental impact assessment
Data collection, field investigation and engineering analysis
Determination of Content of evaluation, emphasis, level, scope and standards
Identification of key issues and selection of evaluation factors
Development of work program
Engineering analysis
Atm
ospheric
environment
Water
environmen
Noise
environment
Ecological
environment
Public participation
Environmental monitoring and existing condition analysis
Analysis and evaluation of environmental impacts
Analysis of
questionnaire
survey
Environmental protection
measures
Measures for
improvement of
program
Consultation of expert opinions
Giving advice and conclusion of environmental impact assessment
Environmental management and monitoring program
Preparing and submitting the environmental impact assessment report
51
2. Framework for Policy, Law and Administration
2.1 Documents on Environment Policy and Law
2.1.1 OutlineOn the basis of the comprehensive analysis on the type, scale, location and
environmental sensibility of the project and the character and size of the potential
environmental impact, the main policy, law and standards governing or involved with
the environmental assessment of this Project include:
(1) Laws and rules on environmental protection;
(2) Technology policy for pollution prevention;
(3) Plans and layout of social and economic development and environmental
protection;
(4) Urban master planning;
(5)Technology guideline for environmental impact assessment;
(6) Environmental quality standard;
(7) Control standards for pollution discharge; and
(8) World Bank safeguard policies.
The aforesaid policies, laws and standards constitute the document framework of
policy, law and standards guiding and standardizing the environmental assessment of
this Project. Each sub-project is governed by different policy, law and standards
because of the different type and character.
Other than aforesaid documents, one of the basis for the environmental
assessment of this Project includes the outline of environmental impact assessment
(TOR), the feasibility study report, the administrative examination and approval
52
documents of the government authorities and other related documents in which the
said policy, law and standards are embodied and applied concretely.
2.1.2 Laws and rules on environmental protection(1) The Environmental Protection Law of the People's Republic of China,
1989.12.26;
(2) The Environmental Impact Assessment Law of the People's Republic of
China, 2002.10.28;
(3) The Water Pollution Prevention and Control Law of the People's Republic of
China, 2008.06.01;
(4) The Air Pollution Prevention and Control Law of the People's Republic of
China, 2000.04.29;
(5) The Environmental Noise Pollution Prevention and Control Law of the
People's Republic of China, 1996.10.29;
(6) The Law of the People's Republic of China on the Prevention and Control of
Environmental Pollution by Solid Waste, 2004.12.29;
(7) The Water Law of the People's Republic of China, 1988.01.21;
(8) The Law of the People's Republic of China on Water and Soil Conservation,
1991.06.29;
(9) The Law of the People's Republic of China on the Protection of Cultural
Relics, 2002.10.28;
(10) The Regulations on the Administration of Construction Project
Environmental Protection, 1992.08.17;
(11) The Regulations on the Protection of Basic Farmland, 1998.12.27;
(12) The Rules for the Implementation of the Water Pollution Prevention and
Control Law of the People's Republic of China, 2000.3.20;
(13) The Regulations of the People's Republic of China on Nature Reserves,
1994.12.01;
(14) The Circular of the General Office of the State Council on Strengthening the
Administration of the Wetland Protection, 2004.06.05;
(15) The Circular of the State Council on Strengthening Urban Water Supply and
53
Saving and Water Pollution Prevention, 2000.11.7;
(16) The Opinions on Strengthening Industrial Water Saving, 2000.10.25;
(17) The Circular on Strengthening the Administration of Environmental Impact
Assessment of the Construction Projects with Loans from International Financial
Organizations, 1993.6.21;
(18) The Provisions on Hierarchical Examination and Approval of the
Environmental Impact Assessment of Construction Projects, 2008.12.11;
(19) The Guiding Catalog of Industrial Structure Adjustment, 2007;
(20) The Categorized List of the Environmental Impact Assessment of
Construction Projects, 2008.10.01;
(21) The Interim Measures on Public Participation in Environmental Impact
Assessment, 2006.02.22;
(22) The Measures for the Disclosure of Environmental Information (Trial
Implementation), 2007.04.21;
(23) The Regulations on Water Resources Justification for Construction Projects,
2002.05;
(24) The Interim Provisions on the Punishment of Activities Violating the Law
and Discipline on Environmental Protection, 2006.02.20;
(25) The Opinions on Strengthening the Environmental Protection of
Construction Projects in the Development of the West Regions, 2001.01.08;
(26) The Regulations on Water Pollution Prevention of Yellow River Basin
within the Territory of Inner Mongolia Autonomous Region, 1996.09.28;
(27) The Implementation Opinions of the People's Government of Inner
Mongolia Autonomous Region on Strengthening Energy Saving and Emission
Reduction in the 11th Five Years, 2007.04.29;
(28) The Regulations of Inner Mongolia Autonomous Region on the
Environmental Protection (revised in 2002), 2002.03.21;
(29) The Implementation Measures of Inner Mongolia Autonomous Region on
the Law of the People's Republic of China on Water and Soil Conservation,
1997.09.24; and
54
(30) The Announcement of the People's Government of Inner Mongolia
Autonomous Region on the Division of the Main Prevention Areas of Water and Soil
Loss, 1999.05.20.
2.1.3 Technology policy for pollution prevention(1) The disposal and the technology policy for pollution prevention of urban
domestic wastes
(2) The disposal and the technology policy for pollution prevention of urban
domestic sewage
(3) The prevention and control technology policy for lake and reservoir
eutrophication.
(4) The technology policy for the sludge treatment and disposal and the pollution
prevention and control in municipal wastewater treatment plant (trial implementation)
(5) The prevention and control technology policy for hazardous wastes pollution
(6) Opinions on strengthening the water environmental protection of important
lakes.
2.1.4 Plans and layout of social and economic development and
environmental protection(1) Outline of the Eleventh Five-Year Plan for National Economic and Social
Development in Inner Mongolia Autonomous Region
(2) Outline of the Eleventh Five-Year Plan for National Economic and Social
Development in Bayannaoer City
(3) The Eleventh Five-year Plan of Water Pollution Prevention and Control in
Key River Basins
(4) The Comprehensive Planning for the Water Resources in Yellow River Basin
(5) The Function Division of the Inland Rivers in Northwestern and Yellow
River Basin
(6) The Environmental Protection Planning of Bayannaoer City (2005-2010)
2.1.5 The urban master planning and related plans(1) The Compilation of the Urban Master Planning of Bayannaoer City (2004-
2020)
55
(2) The Industrial Water Supply Planning in Bayannaoer City, Inner Mongolia
Autonomous Region (2007)
(3) The Water Resources Comprehensive Planning in Bayannaoer City
(4) The Urban Water System Planning in Bayannaoer City, Inner Mongolia
Autonomous Region (F208G-A1)
2.1.6 The technology guideline and standards for environmental
impact assessment(1) HJ/T2.1-93 Technology Guideline for Environmental Impact Assessment
General Provisions
(2) HJ2.2-2008 Technology Guideline for Environmental Impact Assessment
Atmospheric Environment
(3) HJ/T2.3-93 Technology Guideline for Environmental Impact Assessment
Surface Water Environment
(4) HJ/T2.4-1995 Technology Guideline for Environmental Impact Assessment
Sound Environment
(5) HJ/T19-1997 Technology Guideline for Environmental Impact Assessment
Non-Pollution Ecological Impact
(6) HJ/T169-2004 Technical Guidelines for Environmental Risk Assessment
on Projects
(7) HJ/T192-2006 Technical Criterion for Eco-environmental Status
Evaluation (Trial Implementation)
(8) GB/T16453.1~6-1996 Technical specification for comprehensive control
of soil and water conservation
(9) SL204-98 Technical Regulation on Water and Soil Conservation Plan of
Development and Construction Projects
2.1.7 Environmental quality standard(1) GB3095-1996 Ambient Air Quality Standard
(2) GB3838-2002 Environmental quality Standards for Surface Water
(3) GB/T14848-93 Quality Standard for ground Water
56
(4) CJ/T206-2005 Quality Standard for Urban Water Supply
(5) GB5749-2006 Sanitary Standard for Drinking Water
(6) CJ 3020-93 Water Quality Standard for Drinking Water Sources
(7) GB5084-92 Standards for Irrigation Water Quality
(8) GB15618-1995 Environmental Quality Standard for Soils
(9) GB3096-2008 Environmental Quality Standards for Noise
(10) TJ36-79 Sanitary Standard for the Design of Industrial Enterprise
(the Maximum Allowable Concentration of Hazardous Substances in Atmosphere of
Residential Area)
(11) GB/T18883-2002 Indoor Air Quality Standard
2.1.8 Control standards for pollution discharge(1) GB16297-1996 Integrated Emission Standard of Air Pollutants
(2) GB14554-93 Emission Standard for Odor Pollutants
(3) GB8978-1996 Integrated Wastewater Discharge Standard
(4) GB18918-2002 Discharge Standard of Pollutants for Municipal
Wastewater Treatment Plant
(5) GB12523-90 Noise Limits for Construction Site
(6) GB12348-2008 Standard of Noise at Boundary of Industrial Enterprises
(7) GB18599-2001 Standards for Pollution Control on the Storage and
Disposal Site for General Industrial Solid Wastes
(8) GB5085-1996 Identification Standard for Hazardous Wastes
(9) GB8172-87 Control Standards for Urban Wastes for Agricultural Use
(10) GB4284-84 Control Standards for Pollutants in Sludges from
Agricultural Use
2.1.9 World Bank safeguard policies
(1)OP/BP 4.01 Environmental Assessment
(2)OP/BP 4.04 Natural Habitats
(3)OP 4.09 Pest Management
57
(4)OP 4.37 Safety of Dams
(5)OP 4.11 Physical Cultural Resources
(6)OP/BP 4.12 Involuntary Resettlement
(7)OD 4.20 Indigenous Peoples
(8)OP 7.50 Projects on International Waterways
(9)BP17.50 Information Disclosure
2.1.10 Documents related to the Project(1) The proposals for the project of the comprehensive treatment of the water
environment in Bayannaoer City, Inner Mongolia Autonomous Region (SC2006-101-
(H)-49);
(2) The proposals for the project of the comprehensive treatment of
Wuliangsuhai Lake, the project of environmental treatment in Yellow River basin in
Inner Mongolia;
(3) The feasibility study report for the ecological treatment project of
Wuliangsuhai Lake in Bayannaoer,Inner Mongolia;
(4) The implementation plan of the ice jam flood detention project from
Sanshenggong to Sanhehukou of Yellow River in Inner Mongolia (BSSDY·SJ-039-
2005);
(5) The outline of the water ecosystem recovery plan of Wuliangsuhai Lake
(2008-2033);
(6) The report of water resources in Bayannaoer (2002-2006);
(7) The report on the investigation of the reasonable disposition of the water
resources in Bayannaoer City; and
(8) The reply on the standard of environmental assessment of the water
58
environment comprehensive treatment in Bayannaoer City with the loan from World
Bank (Ba Huan Han Fa [2009] No.79).
2.2 Environmental Management Institutions and Their
Responsibilities
PRC Central People's Government and the People's Governments in all
provinces(municipalities directly under the central government and autonomous
regions ), cities(municipalities) and counties(prefectures) all have their own
environmental management institutions which perform their environmental
management duties according to law. The environmental management institutions in
relation with this Project mainly include: State Environment Protection
Administration (SEPA), the Department of Environmental Protection of Inner
Mongolia Autonomous Region and the environmental protection bureaus in all cities,
municipalities and banners(counties and districts).
(1) State Environment Protection Administration (SEPA)
In March 1998, the former State Environment Protection Administration became
the organization directly under the State Council. It is in charge of the administrative
management and enforcement of the environmental protection all over the country
and its main tasks and responsibilities include: to draw up the environmental
protection guideline, policy, laws and rules, planning and administrative regulations;
to supervise the exploitation and utilization of natural resources, the main ecological
environment construction and the ecological damage restoration that have an
influence on the ecological environment; to check and supervise the biodiversity
protection, the wildlife protection, wetland environment protection and the desert
prevention; to supervise and manage the national nature reserves; to direct and
harmonize the significant environmental matters among all localities and departments
and the multi-locations and multi-basins; to establish and organize to implement all
environmental management systems; to examine and approve the environmental
impact reports of development and construction activities according to laws and rules;
59
to direct the comprehensive environmental regulation in cities and towns; in charge of
rural eco-environmental protection; to manage the international cooperation and
communication on environmental protection; to involve the harmonization of the
important international activities on environmental protection; to mange, organize and
harmonize the domestic implementation of the international treaties in relation with
the environmental protection; to unify contacts with other countries and territories; to
manage the foreign economic cooperations of the environmental protection system; to
harmonize and implement the related foreign-funded projects; to deal with foreign-
related environmental protection matters authorized by the State Council; and in
charge of contacting with the environmental protection international organizations.
State Environment Protection Administration establishes an Environmental
Impact Assessment Department in special charge of the administrative management of
environmental impact assessment and its main tasks and responsibilities include: to
draw up and organize to implement environmental impact assessment, "three
simultaneousness" and other environment management policy, laws and rules; to
undertake the environmental impact assessment of significant economic and
technology policy, development plans and important economic development plans; to
draw up the categorized list of environmental impact assessment; and to examine and
approve the environmental impact reports of the significant development and
construction activities.
(2) Department of Environmental Protection of Inner Mongolia Autonomous
Region
The Department of Environmental Protection of Inner Mongolia Autonomous
Region is in charge of the administrative management and enforcement of the
environmental protection in all the region and its main tasks and responsibilities
include: to implement the State environmental protection guideline, policy, laws and
rules, administrative regulations and standards; to draw up and supervise the
implementation of the environmental protection rules and administrative regulations
in all the region; to undertake, upon the authorization by the People's Government of
60
Inner Mongolia Autonomous Region, the environmental impact assessment of
significant economic and technology policy, development plans and important
economic development plans in all the region; to draw up the environmental
protection plans, to organize the compilation of the environmental function division,
the regional and basinal pollution prevention plans and the ecological protection
plans, and to supervise the implementation thereof; to involve the establishment of the
environmental protection industrial policy and development plans; to manage and
supervise the environmental protection of the natural ecology and construction
projects; to organize to draw up and supervise the implementation of the prescribed-
time treatment plan of pollution resources; to make the control plan of the total
amount of pollution discharge in all the region, in charge of the registration of the
pollution discharge and the management of the pollution discharge license, and to
organize and supervise the collection of pollution discharge fees; in charge of the
environmental supervision and the environmental protection administrative check; to
organize the implementation of the international treaties in relation with the
environmental protection in all the region; in charge of the international economic and
technology cooperation and communication related to the environmental protection;
and to deal with foreign-related environmental protection matters authorized by the
People's Government of Inner Mongolia Autonomous Region.
The Department of Environmental Protection of Inner Mongolia Autonomous
Region establishes an environmental impact assessment administrative office in
special charge of the administrative management of environmental impact assessment
and its main tasks and responsibilities include: to supervise and manage the
implementation of the environmental impact assessment and the "three
simultaneousness" system in all the region; to implement the State laws, rules,
regulations and policy in relation with environmental impact assessment and the
"three simultaneousness" system; to draw up, implement and supervise the local
regulations, rules and policy in relation with the environmental impact assessment and
the "three simultaneousness" system; in charge of the examination of environmental
61
impact assessment documents of the plans examined and approved by the People's
Government and its departments in the region; to guide and supervise the examination
and approval of environmental impact assessment of construction projects in all the
region; in charge of the administrative license of environmental impact assessment
documents of construction projects within the authorization of the Department of
Environmental Protection of the region; in charge of the administrative license of the
trial production (operation) and the environmental protection check and acceptance of
construction projects within the authorization of the Department of Environmental
Protection of the region; and to guide the business of the environment examination
centers of construction project in the region.
The Department of Environmental Protection of Inner Mongolia Autonomous
Region establishes an foreign cooperation and communication office in charge of the
international cooperation and communication related to environmental protection in
all the region and its main tasks and responsibilities include: to organize, in
cooperation with related offices and branches, the filtration, recommendation and
application of foreign cooperation and investment projects on environmental
protection in all the region; in charge of the negotiation on environmental protection
between Inner Mongolia Autonomous Region and international organizations, foreign
governments and organizations and on-governmental organizations and the
management of the organization and implementation of the cooperation projects; and
to undertake the business of foreign-funded projects in relation with environmental
protection.
(3) Environmental Protection Bureau in Bayannaoer City
The Environmental Protection Bureau in Bayannaoer City is in charge of the
administrative management and enforcement of the environmental protection in the
city and its main tasks and responsibilities include: to implement the State
environmental protection guideline, policy, laws and rules, administrative regulations
and standards; to draw up and supervise the implementation of the environmental
protection rules and administrative regulations in the city; to undertake, upon the
62
authorization by the People's Government of the city, the environmental impact
assessment of significant economic and technology policy, development plans and
important economic development plans in the city; to draw up the environmental
protection plans, to organize the compilation of basinal pollution prevention plans and
ecological protection plans, and to supervise the implementation thereof; to manage
and supervise the environmental protection of the natural ecology and construction
projects; to organize to draw up and supervise the implementation of the prescribed-
time treatment plan of pollution resources; to make the control plan of the total
amount of pollution discharge in the city, in charge of the registration of the pollution
discharge and the management of the pollution discharge license, and to organize and
supervise the collection of pollution discharge fees; in charge of the environmental
supervision and the environmental protection administrative check; in charge of the
international economic and technology cooperation and communication related to the
environmental protection; and to deal with foreign-related environmental protection
matters authorized by the People's Government of Bayannaoer City.
The Environmental Protection Bureau in Bayannaoer City establishes an
environmental impact assessment administrative office (or pollution control office,
supervision and management office) in special charge of the administrative
management of environmental impact assessment and its main tasks and
responsibilities include: to supervise and manage the implementation of the
environmental impact assessment and the "three simultaneousness" system in the city;
to implement the laws, rules, regulations and policy, stipulated by the State or Inner
Mongolia Autonomous Region, in relation with environmental impact assessment and
the "three simultaneousness" system; to draw up, implement and supervise the local
regulations, rules and policy in relation with the environmental impact assessment and
the "three simultaneousness" system; to guide and supervise the examination and
approval of environmental impact assessment of construction projects in the city; in
charge of the administrative license guideline of environmental impact assessment
documents of construction projects within the authorization of the Environmental
63
Protection Bureau in the city; and in charge of the administrative license of the trial
production (operation) and the environmental protection check and acceptance of
construction projects within the authorization of Environmental Protection Bureau in
the city.
(4) Environmental Protection Bureaus in all counties (districts)
The Environmental Protection Bureaus in all banners (counties, districts) where
the sub-projects of this Project located are in charge of the administrative
management and enforcement of the environmental protection in the banner (county,
district) and their main tasks and responsibilities include: to implement the State
environmental protection guideline, policy, laws and rules, administrative regulations
and standards; to draw up and supervise the implementation of the environmental
protection plan in the banner (county, district); to manage and supervise the
environmental protection of the natural ecology and construction projects; to organize
to draw up and supervise the implementation of the prescribed-time treatment plan of
pollution resources; to make the control plan of the total amount of pollution
discharge in the banner (county, district), in charge of the registration of the pollution
discharge and the management of the pollution discharge license within the
authorization thereof, and to organize and supervise the collection of pollution
discharge fees; and in charge of the environmental supervision and the environmental
protection administrative check.
In order to generally organize, harmonize and manage the filtration,
recommendation, application, business negotiation and check and acceptance of the
environment projects with the loan from World Bank in Bayannaoer City, the
government of Bayannaoer City establishes the project cooperation and lead group
(PCLG) the leader of which is the deputy mayor in main charge of environmental
protection. PCLG have a project management office (YNPMO), administratively
established in Hetao Water Affairs Group Limited, which is the representative of the
municipal project cooperation and lead group to undertake the related business.
64
3. Description and Analysis of the Project
3.1 Outline of the Project
3.1.1 Name, Construction Nature and Legal Person of the Project (1) Name of the Project
Comprehensive Harness Project of Bayan Nur Water Environment upon the
Loan of the World’s Bank
(2) Construction Nature
To be newly built
(3) Legal Person of the Project
Inner Mongolia Bayan Nur Hetao Water Affairs Group Co., Ltd
3.1.2 Investment of the Project The total investment of the project is RMB 996.4533 million, and it is proposed
to borrow RMB 546.126 million from the world’s bank, which accounts for 54.81%
of the total investment.
3.1.3 Composition, construction content and size of the project
65
Composition, construction content and size of various subprojects of Bayan Nur
Water Environment Comprehensive Harness Project upon the Loan of the World’s
Bank are shown in Table 3.1-1.
3.1.4 Proposed Locale of the Project 3.1.4.1 Geographic Location
The project consists of nine subprojects, distributed in five banners or counties in
Bayan Nur and the proposed locales are as follows:
(1) Urat Middle Banner (two subprojects): located in Delingshan Town and near
Wangba Reservoir in Urat Middle Banner, respectively;
(2) Wuyuan County (one subproject): located in Longxingchang Town, Wuyuan
County;
(3) Hanggin Rear Banner (one subproject): Located in Shaanba Town, Hanggin
Rear Banner;
(4) Urat Rear Banner (two subprojects): Located in Hohwedor Town, Urat Rear
Banner;
(5) Urat Front Banner (three subprojects): Located in Xianfeng Town,
Wuliangsu Lake Area of Urat Front Banner.
The geographic location of the proposed project in Bayan Nur is shown in Fig.
3.1-1.
66
Fig. 3.1-1 Geographic Location of Proposed Project in Bayan Nur City
3.1.4.2 Proposed Construction Site of the Project
In the feasibility study report of the project, the comparison and selection of the
construction site is made according to the following principles:
(1) Comply with the local urban overall planning and relevant special planning;
(2) Comply with the provisions of location selection in the relevant standards and
codes, such as Stipulation for the Environment Protection Design of Construction
Projects, Code for Design of Outdoor Wastewater Engineering (GB50014-2006),
Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant
(GB18918-2002), Discharge Standard of Wastewater or Sewage for Municipal
Wastewater Treatment Plant (CJ3025-93), Construction Standard for Urban
Wastewater Treatment Project, and so on;
(3) Comply with the principle of less investment and lower operation cost;
The recommended construction site is shown in Table 3.1-2 upon the site
investigation and the comprehensive comparison and analysis of technical economy
and environment condition. The rational analysis of the site selection is detailed in
Chapter 10 Comparison and Analysis of Alternatives.
67
Table 3.1-1 Composition, Construction Content and Size of Various Subprojects
No. Type Name Content Construction Size Location1 Supply of
Reclaimed Water
Water Supply Project of Urat Rear
Banner Processing
Park
1) Water intake works: consist of the intake pump station, water pipeline and ancillary facilities, and the water intake works shall utilize the existing intake pump station and water pipeline, and increase a standby water pump (Q=580m3,H=35m) and a ductile cast iron pressure pipe of DN500, with a design flow of 255L/s for water piping network. 2) One water reclamation plant shall be built at southeast of the processing park, including the buildings and structures such as, contact tank, chlorination-feeding chamber, clean water tank, pumping station, etc.; 3) Water distribution network is laid out along the planned route toward the northwest, southwest and southeast of the processing park and PE pipes and ductile cast iron pipes of DN 200 are used.
35,000 t/dHohwedor Town, Urat
Rear Banner
Water Supply Project of
Ganqimaodu Port
Processing Park
1) Water intake works: consist of the intake pump station, water pipeline and ancillary facilities, with an intake capacity of 6.25m3/d. Intake pump station belongs to the combined structure at bank and adopts 6 horizontal centrifugal pumps. The water pipeline is connected from the intake pump station to the water reclamation plant along the pathway; 2) One water reclamation plant shall be built near Wangba Reservoir, including the buildings and structures such as lift pump station, pre-aeration basin, flocculation tank, filter station, contact tank, sludge discharge tank and backwash tank, chlorination-feeding chamber, anti-
40,000t/d Near Wangba Reservoir of Urat Middle
Banner
68
seepage chamber and clean water tank and pumping station; 3) Water distribution network: Double ductile cast iron pressure pipes of DN500 are laid out along the planned route to the clean water tank of sewage treatment & reuse of the park, totaling 28km, with a design flow of 509l/s.
Reclaimed Water Supply
Project of Drainage Canal 3
1) Water intake works: its intake capacity is 33,000m³/d and it adopts the gravity pipe intake structure and the pumping station is built together with the suction well. Four horizontal centrifugal pumps are used (Q=340m3). Double pipes are used for the water delivery pipeline and subject to the supporting construction with the water reclamation plant; 2) One water reclamation plant shall be built in the north of sewage treatment plant of drainage canal 3, including the buildings and structures such as distributing well, pipeline mixer, one mesh reactor, one sloping plate sedimentation tank, one V-type filter tank, chlorination chamber, reflux tank, sludge equalization basin, anti-seepage chamber and pumping station, etc.; 3) Water distribution network: two water pipelines are drawn out from pumping station of water reclamation plant to water supply piping network of Hanggin Rear Banner Industrial Park.
20,000t/dShanba Town, Hanggin Rear
Banner
Reclaimed Water Supply
Project of Drainage Canal 7
1) Water intake works: its intake capacity is 33,000m³/d and it adopts the gravity pipe intake structure and the pumping station is built together with the suction well (20m×16m). Four horizontal centrifugal pumps are used (Q=340m3). Double pipes are used for the water delivery pipeline and two ductile cast iron pipes of DN400 are laid out,
20,000t/d Longxingchang Town, Wuyuan County
69
totaling 0.2km; 2) One water reclamation plant shall be built, including the buildings and structures such as, one distributing well, one static mixer, one mesh reactor, one sloping plate sedimentation tank, one common filter tank, one reflux tank, one sludge equalization basin, one clean water tank, one chlorination-feeding or dosing chamber, one ultrafiltration & anti-seepage chamber, etc.; 3) Water distribution network: two pipelines of DN400 are laid out, with a design flow of 20,000m3/d×1.1 =255l/s, and a length of 19km.
2 Sewage Treatment & Reuse Project of Processin
g Park
Sewage Treatment Project of Urat Rear
Banner Processing Park (Hoh Town)
1) Sewage collection system: the sewer network shall be laid out as per the planning of the processing park, and the sewage main pipes of DN400-DN700 are laid out from the north to the south along Jingyi Road, Jingsan Road, Jingwu Road and Jingqi Road, and the main trunk pipes are laid out at Jingwu Road, which are undertaken by the government. The construction commitment letter of sewage collection network of the processing park is shown in the attachment; 2) The buildings and structures for the sewage treatment engineering include bar screen, intake pump station, aeration tank, equalization basin, primary sedimentation tank, biological tank, secondary sedimentation tank, flocculation tank, filter station, sludge thickening & dewatering house, blower room, chlorination chamber, odor-removing chamber, etc.
20,000t/dHohwedor Town, Urat
Rear Banner
Sewage Treatment & Reuse Project
1) Sewage collection network: the sewage main pipes are built by the government and excluded in the Project, and the construction commitment letter of sewage collection network of the processing park
Sewage treatment capacity::30,000t/d; Reclaimed water
Delingshan Town, Urat
Middle Banner
70
of Ganqimaodu
Port Processing
Park
is shown in the attachment; 2) Process flow includes pre-treatment work stage, secondary bio-treatment work stage, reclaimed water deep-treatment stage, and sludge treatment stage. Main buildings and structures include equalization basin, bar screen, sewage pump room, grit chamber, biological tank, contact tank, distributing well, small-hole mesh reactor, sloping plate sedimentation tank, V-type filter tank, sludge pump room, sludge thickening & dewatering house, blower room, chlorination chamber, odor-removing chamber, etc.;
3 ) Total length of water distribution network is 45.08km and the
ductile cast iron pipes and PE pipes of DN 100-DN600 are used, with a maximum design flow of 902.7L/s.
capacity:20,000t/d
Sewage Treatment & Reuse Project of Urat Front
Banner (Xianfeng
Town) Processing
Park
1) Sewage collection network: the sewage main pipes are built by the government and excluded in the Project, and the construction commitment letter of sewage collection network of the processing park is shown in the attachment;2) Sewage treatment & reuse project: it covers a land area of 370m×300m, 11.0ha, and the main buildings and structures include equalization basin, bar screen, sewage pump room, grit chamber, biological tank, secondary sedimentation tank, flocculation tank, filter station, sludge pump room, sludge dewatering house, lift pump room, blower room, chlorination-feeding & dosing chamber, odor-removing chamber, etc. 3) it is necessary to build the sewage main pipes of DN800-DN1400
Sewage treatment capacity::30,000t/d; Reclaimed water capacity:20,000t/d
Xianfeng Town, Urat
Front Banner
71
from drainage main trunk to sewage treatment plant, totaling 9.00km, reclaimed water pipelines of 23.4km (DN500-DN300) and necessary supporting facilities.
3
Harness Project of Wuliangsu Lake
Pastoral Grid Channel
Project of Wuliangsu
Lake
The main drainage canal of grid channel system is 45m wide, 1.4m deep and 40.00km long, and the branch canal is 10m wide, 2m deep and 100.00km long. Excavation works of main channels and branch channels.
Construction area 2.451×106m2,
excavated sediment
2.295×105m3
Wuliangsu Lake, Urat
Front Banner
Artificial wetland
project and Area-Source Demonstration Project in
Biologic Transition
Belt of Wuliangsu
Lake
1) Biologic transition belt artificial wetland project in the west and northwest of Wuliangsu Lake, including general drainage canal wetland area of 90514mu, with pumping station flow of 15 m3/s, the eighth drainage canal wetland area of 8569mu, with pumping station flow of 3 m3/s, and the ninth drainage canal wetland area of 11100mu, with pumping station flow of 3 m3/s. 2) Area-source demonstration project is located in the Beichang Branch Ditch experimental area of drainage canal 9 at Qinghua Village Beichang Community and Dengcundian Village Tabu Community of Beiqidu Township, Urat Front Banner of Inner Mongolia Autonomous Region, with a total area of 3 km2.
7345.5haWuliangsu Lake, Urat
Front Banner
72
Table 3.1-2 Recommended Construction Sites for Various Subprojects
No
.Type Name of Project Recommended Construction Site
1Supply of
Reclaimed
Water
Water Supply Project of
Urat Rear Banner
Processing Park
Southeast of Urat Rear Banner Processing Park
Water Supply Project of
Ganqimaodu Port
Processing Park
Near Wangba Reservoir of Delingshan Town of Urat Middle
Banner
Water Supply Project
of Reclaimed Water for
Drainage Canal 3
North of Drainage Canal 3 Sewage Treatment Plant of
Shaanba Town, Hanggin Rear Banner
Water Supply Project
of Reclaimed Water for
Drainage Canal 7
North of Drainage Canal 7 Sewage Treatment Plant of
Longxingchang Town, Wuyuan County
2
Sewage
Treatment &
Reuse Project
of Processing
Park
Sewage Treatment
Project of Urat Rear
Banner Processing Park
(Hoh Town)
Southeast of Urat Rear Banner Processing Park
Sewage Treatment &
Reuse Project of
Ganqimaodu Port
Processing Park
South of Ganqimaodu Port Processing Park (Delingshan
Town), Urat Middle Banner
Sewage Treatment &
Reuse Project of Urat
Front Banner (Xianfeng
Town) Processing Park
Southeast of Urat Front Banner (Xianfeng Town) Processing
Park
3
Harness
Project of
Wuliangsu
Lake
Pastoral Grid Channel
Project of Wuliangsu
Lake
Wuliangsu Lake
Artificial wetland
project and Area-Source
Demonstration Project
in Biologic Transition
Belt of Wuliangsu Lake
Biologic transition belt artificial wetland is built on the
existing reed marsh of lake area in the west and north of
Wuliangsu Lake, and area-source pollution control
demonstration zone is built in Beichang Branch Ditch of
Drainage Canal 9 near Wuliangsu Lake
3.1.5 Floor Area of the Project and Plane Layout of Factory Area Floor area and plane layout of the Project are shown in Table 3.1-3 and the plane
layout of various subprojects is shown in Fig. 3.1-2 – Fig. 3.1-12.
73
Fig. 3.1-2 Plane Layout of Reclaimed Water Supply Project for Urat Rear Banner
Processing Park
74
Table 3.1-3 Floor Area of the Project and Plane Layout of Factory Area
No. TypeName of
SubprojectFloor Area Overall Layout
1 Supply of
Reclaimed
Water Water Supply
Project of Urat Rear
Banner Processing
Park
Permanent floor area of the project
is 5.58ha, including the floor area of
5.51ha for water reclamation plant,
floor area of 0.06ha for roads out of
the factory, and floor area of 0.01ha
for piping valve well. Temporary
floor area is 18.5ha.
Structures are laid out as per the process flow and the vertical arrangement of structures is made rationally
in combination with the vertical condition of the factory area to ensure the raw water can automatically
flow into the next structure; road width is identical to the structure. In the west of water reclamation plant
from the south to the north are laid out warehouse repair workshop, comprehensive building, contact tank,
clean water tank, intake pump room, chlorination-feeding chamber and switchgear room, and the east of
the reclamation plant is for future expansion. The roads in the factory area are divided by functions and
shall be circulated around the buildings and structures, of which the width of main trunk roads is 7m and
width of secondary trunk roads is 4m, and the width of walkway is 1.5m. The width of workshop approach
roads is identical to the door width and the road pavement shall be concreted.
Water Supply
Project of
Ganqimaodu Port
Processing Park
Permanent floor area of the project
is 10.59ha, including the floor area
of 0.02ha for intake pump station,
floor area of 10.5ha for water
reclamation plant, floor area of
0.06ha for roads out of the factory,
and floor area of 0.01ha for piping
valve well. Temporary floor area is
18.5ha.
Structures are laid out as per the process flow and the vertical arrangement of structures is made
rationally in combination with the vertical condition of the factory area to ensure the raw water can
automatically flow into the next structure; road width is identical to the structure. In the water reclamation
plant from the south to the north are laid out warehouse repair workshop, comprehensive building, sludge
treatment tank, backwash tank, contact tank, collecting well, intake pump room, distributing well, pre-
aeration tank, sedimentation tank, filter station, clean water tank, pumping station, chlorination-feeding
chamber, contact tank, RO workshop and switchgear room.
The roads in the factory area are divided by functions and shall be circulated around the buildings and
structures, of which the width of main trunk roads is 7m and width of secondary trunk roads is 4m, and the
width of walkway is 1.5m. The width of workshop approach roads is identical to the door width and the
road pavement shall be concreted.
Reclaimed Water
Supply Project of
The floor area of the project is
2.50ha, 125m in length and 200m in
According to the recommended process flow, selection of buildings & structures and land use condition
and in full consideration of various factors, the factory area of water reclamation plant for drainage canal 3
75
Drainage Canal 3 width.
is divided into two function areas: one is production and management area, which is located in the west of
the factory area, arranged with reception room, comprehensive building, repair workshop, warehouse,
switchgear room & auxiliary structures; the other is the production structure area of water reclamation
plant, located in the east of the factory area, and arranged with from the south to the north small-hole mesh
reactor, V-type filter tank, clean water tank, and pumping station. The width of main trunk roads is 7m and
the width of secondary trunk roads is 4m. The roads are built into the screen traffic network in the factory
area. Rain/sewage diversion system is applied to the drainage system of the factory area. And the sewer
will collect the domestic sewage and discharge them into the supporting sewer network of sewage
treatment plant in the south. There are rain pipelines in the factory area and the rain water will
automatically flow into the Drainage Canal 3. Water supply of the factory is from the underground water
supply system and the water distribution network shall be designed into the ring-like structure, and the fire
hydrants shall be equipped as per the fire-prevention requirement, with a protection radius of less than
60m.
Reclaimed Water
Supply Project of
Drainage Canal 7
The floor area of water reclamation
plant of Drainage Canal 7 is 2.50ha,
100m in length and 250m in width.
According to the recommended process flow, selection of buildings & structures and land use condition
and in full consideration of various factors, the factory area of water reclamation plant for drainage canal 7
is divided into two function areas: one is production and management area, which is located in the west of
the factory area, arranged with reception room, comprehensive building, repair workshop, warehouse,
switchgear room & auxiliary structures; the other is the production structure area of water reclamation
plant, located in the east of the factory area, and arranged with from the south to the north small-hole mesh
reactor, common filter tank, ultrafiltration anti-seepage chamber, ultrafiltration tank, backwash tank,
wastewater neutralization pool, clean water tank, and pumping station. The width of main trunk roads is
7m and the width of secondary trunk roads is 4m. The roads are built into the screen traffic network in the
factory area. Rain/sewage diversion system is applied to the drainage system of the factory area. And the
sewer will collect the domestic sewage and discharge them into the supporting sewer network of sewage
treatment plant in the south. There are rain pipelines in the factory area and the rain water will
76
automatically flow into the Drainage Canal 7. Water supply of the factory is from the underground water
supply system and the water distribution network shall be designed into the ring-like structure, and the fire
hydrants shall be equipped as per the fire-prevention requirement, with a protection radius of less than
60m.
2 Sewage
Treatment
& Reuse
Project of
Processing
Park
Sewage Treatment
Project of Urat Rear
Banner Processing
Park (Hoh Town)
The project covers a land area of
7.0ha, and a building area of 1.13ha.
Roads and square cover a land area
of 3.9ha, and the greening area is
0.65453ha.
According to the characteristics of sewage treatment process and function partitioning principle, the
project can be divided into the production area and front plant area. The production area is laid out as per
the process flow; coarse bar screen and intake pump house are arranged in the south of the factory area
and the pipelines to the plant shall be unblocked and the selection tank and oxidation ditch and secondary
sedimentation tank shall be laid out in order, and the sewage shall be discharged into the water reclamation
plant; the sludge system shall be convenient to the sludge discharge and outward transportation, which
shall be arranged in the middle of the factory area. Switchgear room is located in the central load center of
the factory area. The front plant area is located in the north of the factory area and the leeward side with
the minimum wind direction frequency in summer, complying with the direction of pedestrian flow into
the plant. Under the precondition of meeting the fire prevention and transportation requirements, the roads
in the plant shall adopt the feeder roads, with a width of 5m, and the turning radius of road curb stones is
6m and the roads shall be the urban concreted pavement.
Sewage Treatment
& Reuse Project of
Ganqimaodu Port
(Delingshan Town)
Processing Park
The project covers a land area of
11.1ha, and a building area of 1.
20ha. Roads and square cover a land
area of 0.81ha, and the greening area
is 5.3ha.
According to the characteristics of sewage treatment process and function partitioning principle, the
project can be divided into the production area and front plant area. The production area is laid out as per
the process flow; coarse bar screen and intake pump house are arranged in the south of the factory area
and the pipelines to the plant shall be unblocked and the selection tank and oxidation ditch and secondary
sedimentation tank shall be laid out in order, and the sewage shall be reused upon the treatment; the sludge
system shall be convenient to the sludge discharge and outward transportation, which shall be arranged in
the middle of the factory area. Switchgear room is located in the central load center of the factory area.
The front plant area is located in the north of the factory area and the leeward side with the minimum wind
direction frequency in summer, complying with the direction of pedestrian flow into the plant. Under the
77
precondition of meeting the fire prevention and transportation requirements, the roads in the plant shall
adopt the feeder roads, with a width of 7m, and the turning radius of road curb stones is 6m and the roads
shall be the urban concreted pavement.
Sewage Treatment
& Reuse Project of
Urat Front Banner
(Xianfeng Town)
Processing Park
The project covers a land area of
11.1ha, and a building area of 1.
18ha. Roads and square cover a land
area of 0.81ha, and the greening area
is 5.3ha.
According to the characteristics of sewage treatment process and function partitioning principle, the
project can be divided into the production area and front plant area. The production area is laid out as per
the process flow; coarse bar screen and intake pump house are arranged in the south of the factory area
and the selection tank and oxidation ditch and secondary sedimentation tank shall be laid out in order, and
the sewage shall be reused upon the treatment; the sludge system shall be convenient to the sludge
discharge and outward transportation, which shall be arranged in the middle of the factory area.
Switchgear room is located in the central load center of the factory area. The front plant area is located in
the north of the factory area and the leeward side with the minimum wind direction frequency in summer,
complying with the direction of pedestrian flow into the plant.
3
Harness
Project of
Wuliangsu
Lake
Pastoral Grid
Channel Project of
Wuliangsu Lake
Grid channels composed of the main drainage canals and branch canals out of the core area and buffer area
within the scope of 293km2 around Wuliangsu Lake.
Artificial wetland
project and Area-
Source
Demonstration
Project in Biologic
Transition Belt of
Wuliangsu Lake
Area-source pollution control
demonstration area of Beichang
Branch Ditch of Drainage Canal 9 is
3km. Artificial wetland includes the
wetland of General Drainage Canal,
Drainage Canal 8 and Drainage
Canal 9, with a total area of
7345.5ha
Wetland of general drainage canal occupies the reed marshes No. 2, 3 and 4, with a total area of 6034.3ha,
and the water of the wetland is discharged into military farm reed marsh No.4 via Honggepu pumping
station and into reed marsh No.2 via the diversion dam set up in the reed marsh and then into reed marsh
No.3, afterward flows into hydrologic buffer zone of the Lake from three outlets and finally flows into the
grid channels of the Lake. Drainage canal 8 only uses the reed marsh No.5, with an area of 571.3ha; the
water flows into the reed marsh and flows through the wetland along the diversion dam; Drainage canal 9
only uses the reed marsh No.6, with an area of 740.0ha; the water flows into the reed marsh and flows
through the reed marsh from the south to the north and finally flows into the catchment area from the north
to the south after flowing through the diversion dam.
78
Fig. 3.1-3 Plane Layout of Water Supply Project of Reclaimed Water for Drainage
Canal 3
Fig. 3.1-4 Plane Layout of Water Supply Project of Reclaimed Water for Drainage
Canal 7
79
Fig. 3.1-5 Plane Layout of Reclaimed Water Supply Project of Ganqimaodu
Processing Park
Fig. 3.1-6 Plane Layout of Sewage Treatment Plant Project of Ganqimaodu
80
Processing Park
Fig. 3.1-7 Plane Layout of Sewage Treatment Plant Project of Urat Rear Banner
Processing Park
81
Fig. 3.1-8 Plane Layout of Sewage Treatment Plant Project of Urat Rear Banner
Processing Park
Fig. 3.1-9 Plane Layout of Main Channels and Branch Channels of Wuliangsu Lake
82
Fig. 3.2-10 Plane Layout of Artificial Wetland Project for General Drainage Canal
Fig. 3.2-11 Plane Layout of Artificial Wetland Project for Drainage Canal 8
83
Fig. 3.2-12 Plane Layout of Artificial Wetland Project for Drainage Canal 9
3.1.6 Construction Progress Schedule and Staffing of the Project 3.1.6.1 Construction Progress Schedule
(1) Design principle for total construction progress
The project has a bigger work quantity and scattered construction areas, and the
construction shall be carried out as per the rational and orderly principle.
(2) Total Progress
The preliminary preparation of the project has been commenced since 2009 and
the construction period of the project is from 2010 to 2012. Construction progress is
shown in Table 3.1-4.
Table 3.1-4 Construction Progress Schedule of the Project
No. Activity Time (Month) Implementation Schedule
1 Preliminary preparation 15 2009.3-2010.5
2 Preparation Delegation of Experts
from World’s Bank
2 2009.8,2009.11
84
3 Evaluation Delegation of Experts
from World’s Bank
2 2010.1,2010.3
4 Executive Board 3 2010.7-2010.9
5 Prepare and review bidding
documents
6 2010.4-2010.9
6 Enter into the purchase&
contribution agreement
1 2010.10
7 Submission of tender 3 2010.11-2011.1
8 Drawing design 10 2010.3-2010.12
9 Civil engineering 22 2010.5-2012.5
10 Equipment installation 10 2011.12-2012.9
11 Commissioning 6 2012.5-2012.10
12 Trial run and final acceptance 6 2010.8-2012.12
3.1.6.2 Staffing of the Project
The staffing of the project is shown in Table 3.1-5.
Table 3.1-5 Staffing of the Project
No. Type Name of Subproject Personnel Quantity
(Person)
1 Supply of
Reclaimed WaterWater Supply Project
of Urat Rear Banner
Processing Park
Production staff 16
Management personnel 3
Auxiliary production staff 6
Subtotal 25
Water Supply Project
of Ganqimaodu Port
Processing Park
Production staff 18
Management personnel 5
Auxiliary production staff 7
Subtotal 30
Water Supply Project
of Reclaimed Water
for Drainage Canal 3
Administrative personnel 1
Technical management personnel 1
Production staff 6
Auxiliary production staff 3
Rear service staff 3
Subtotal 14
Water Supply Project
of Reclaimed Water
for Drainage Canal 7
Administrative personnel 1
Technical management personnel 1
Production staff 6
85
Auxiliary production staff 3
Rear service staff 3
Subtotal 14
2
Sewage
Treatment and
Reuse
Sewage Treatment
Project of Urat Rear
Banner(Hoh Town)
Processing Park
Production staff 15
Management personnel 3
Auxiliary production staff 2
Subtotal 20
Sewage Treatment &
Reuse Project of
Ganqimaodu Port
(Delingshan Town)
Processing Park
Production staff 25
Management personnel 5
Auxiliary production staff 2
Subtotal 32
Sewage Treatment &
Reuse Project of Urat
Front Banner
(Xianfeng Town)
Processing Park
Production staff 5
Management personnel 25
Auxiliary production staff 2
Subtotal 32
3Comprehensive Harness Project of
Wuliangsu Lake
Production staff 12
Auxiliary production staff 3
Subtotal 15
Total 182
3.1.7 Main Technical and Economic Indicators Main technical and economic indicators of the Project are shown in Table 3.1-6.
Table 3.1-6 Main Technical and Economic Indicators of the Project
No. TypeName of
SubprojectTechnical Indicator Quantity
1 Supply of
Reclaimed
Water Water Supply
Project of Urat
Rear Banner
Processing Park
Annual water selling volume 12,775.000 m3
Unit total cost 0.65Yuan/m3
Unit operation cost 0.42Yuan/m3
Suggested water price 0.86Yuan/m3
Internal rate of return (IRR) 6.95%
Payback period 12.91 years
Return on investment 5.24%
Capital profit margin 7.76%
Water Supply
Project of
Ganqimaodu Port
Processing Park
Annual water selling volume 14,600,000m3
Unit total cost 1.88Yuan/m3
Unit operation cost 1.27Yuan/m3
Suggested water price 2. 4Yuan/m3
Internal rate of return (IRR) 6.83%
Payback period 13.17 years
86
Return on investment 5.14%
Capital profit margin 8.56%
Reclaimed Water
Supply Project of
Drainage Canal 3
Annual water selling volume 7,300,000 m3
Unit total cost 1.38Yuan/m3
Unit operation cost 0.69Yuan/m3
Suggested water price 1.97Yuan/m3
Internal rate of return (IRR) 6.81%
Payback period 13.32 years
Return on investment 5.14%
Capital profit margin 7.98%
Reclaimed Water
Supply Project of
Drainage Canal 7
Annual water selling volume 7,300,000 m3
Unit total cost 1.98Yuan/m3
Unit operation cost 1.19Yuan/m3
Suggested water price 2.65Yuan/m3
Internal rate of return (IRR) 6.81%
Payback period 14.24 years
Return on investment 5.13%
Capital profit margin 8.10%
2 Sewage
Treatment
and Reuse Sewage Treatment
Project of Urat
Rear Banner(Hoh
Town) Processing
Park
Annual Treatment Volume of Water 7,300,000 m3
Unit Total Cost 1.54Yuan/m3
Unit operation cost 0.86Yuan/m3
Suggested unit charge 1.85Yuan/m3
IRR 6.25%
Payback period 12.21 years
Return on investment 3.84%
Capital profit margin 8.12%
Sewage Treatment
& Reuse Project
of Ganqimaodu
Port (Delingshan
Town) Processing
Park
Annual Treatment Volume of Water 10,950,000 m3
Annual water selling volume 7,300,000 m3
Unit total cost 1.51Yuan/m3
Unit operation cost 0.84Yuan/m3
Suggested unit charge 2.15Yuan/m3
IRR 6.16%
Payback period 12.31 Years
Return on investment 3.75%
Capital profit margin 7.84%
Sewage Treatment
& Reuse Project
of Urat Front
Banner (Xianfeng
Town) Processing
Park
Annual Treatment Volume of Water 10,950,000 m3
Annual water selling volume 7,300,000 m3
Unit total cost 1.62Yuan/m3
Unit operation cost 0.88Yuan/m3
Suggested unit charge 2.34Yuan/m3
Suggested water price 1.55Yuan/m3
IRR 6.26%
87
Payback period 12.20 Years
Return on investment 3.85%
Capital profit margin 7.86%
3Comprehensive Harness Project of
Wuliangsu Lake
Total investment425.05million
Yuan
Annual operating cost 4.60 million Yuan
Income from tourism14.00million
Yuan
Income from reed industry 4.50 million Yuan
Income from fishery industry15.00 million
Yuan
Social discount rate 12%Benefit-cost ratio 0.23
IRR 16.0%
3.2 Construction Proposal of the Project
3.2.1 Water Supply Subproject of Reclaimed WaterWater supply projects of reclaimed water use the water sources of general
drainage canal, drainage canal 3 and drainage canal 7 and the reclaimed water serves
as the industrial water of the related enterprises in the processing parks after the
treatment. Water planning, water demand, water supply situation and existing water
problems in the processing parks are shown in Table 3.2-1.
3.2.1.1 Engineering Characteristics
Main steps of various subprojects of reclaimed water are as follows:
Determine the water source → build the water delivery network → construct the
water plant → build the water distribution network → user.
Various subprojects of reclaimed water of the Project include reclaimed water
supply project of Urat Rear Banner Processing Park, reclaimed water supply project
of Ganqimaodu Port Processing Park, reclaimed water supply project of Drainage
Canal 3, and reclaimed water supply project of Drainage Canal 7, and the main
characteristics are shown in Table 3.2-2.
88
Table 3.2-1 Water Planning, Water Demand, Water Supply Situation and Existing Problems of Various Processing Parks
No.Name of
ParkPark Planning and Status Quo Water Demand Water Supply Situation and Problems
1 Urat Rear
Banner
Processing
Park
Urat Rear Banner Processing Park is about 8km in length and 2.5km in width, with a total area of
about 20km2. Relying on the solid mining and dressing basis of original charcoal kilns pyrite and
local rich mineral resources, it tries the best to develop the three mainstay industries, namely, a.
chemical industry supported by the mining& dressing and deep processing of sulfur iron ore; b.
nonferrous metal industry supported by the mining& dressing and deep processing of copper, lead,
zinc and iron, and c. high energy industry supported by the quartz stone and calcium carbide;
including 13 subprojects: 200,000t/a copper refining project, 50,000t/a lead refining project,
600,000t/a coal-based direct reduced iron project, 2×135MW combined heat& power project,
3,000,000 t/a coking project, etc.
At pre sent, Urat Rear Banner Processing Park is of the annual production capacity of mining
and dressing 1,600,000T of sulfur iron, lead, zinc and copper, with the sulfate processing capacity of
200,000 tons, coarse copper smelting capacity of 10,000tons, lead smelting capacity of 30,000tons
and zinc smelting capacity of 50,000 -100,000 tons. Western Mining Group Corporation will build
the project in the Park, with annual production capacity of 1,000,000 tons of selected irons, 600,000
tons of pig irons and 550,000 tons of molten steels and rolled steels, and meanwhile, a coking plant
with an annual production capacity of 300,000 tons and a blast furnace gas energy conservation
power plant with an annual production capacity of 15,000KW/h will be built in the park. There are
now 14 high energy enterprises, with a total construction scale of 16 12500KVA smelting furnaces
of silicon iron and calcium carbide, of which, 12 smelting furnaces have been completed by August
2004, with annual production capacity of 300,000tons of calcium carbides and of 30,000 tons of
crystal silicon. There was a power transmission and transformer substation of 110KVA, with a total
power transmission capacity of 576,000KVA in the park.
The water demand of
enterprises in the park that
put into production
recently is 1,475,000t/a,
the water demand of
enterprises in the park built
and under the construction
is 3,870,000 t/a, and the
water demand of
enterprises that entered
into the access agreement
with the Park is
4,400,000t/a. The total
reclaimed water demand of
industrial enterprises in the
park is 9,745,000t/a,
namely, 26,700t/d.
Considering the water for
roads and green land and
fire prevention as well as
the unforeseeable water
demand and penetrated
1. Water Supply Situation: Water supply
of the processing park mainly relies on
existing intake and water delivery
equipment. Water supply company sets
up a water intake pump station at Stake
No. 31500 of general drainage canal and
the terminal of the water pipe is a
circular underground water tank, with a
volume of 2000m3, for the water supply
of Feishang Copper Industry Company,
with a water supply capacity of
1,000,000t/a. Shuangli Corporation and
Qihua Corporation all adopts the self-
provided well for the water source, with
a water supply capacity of 6,000,000t/a;
other enterprises in the Park adopt the
small self-provided wells for the water
supply and there is no unified water
supply network in the Park.
2. Existing Problems: Poor water supply
capacity, diffused water sources, bigger
exploration of underwater, lack of
89
water, the maximum water
demand will be 35,000t/d. unified management and coordination.
2 Ganqimao
du Port
Processing
Park
The Park is located in the south of Yinshan Mountain, with a short-term planned area of 20
km2 and long-term planned area of 50 km2. The base –large-scale- integration-park
development mode is used to lay the stress on the development of coal chemical industry so as
to form the coking and tar processing industry chain; Part of coke oven gas is oxidized to
generate the methanol to form the coal-chemical industry product chain; the copper is refined
to generate the copper and meanwhile the local and surrounding coal, power, limestone and
salt resources are used to generate polyvinyl chloride via the calcium carbide method.
According to the internal/external resources of the Park, it is proposed to develop and
construct the 12,000,000t/a coke refining project, 1,200,000t/a methanol (into DME and coal-
chemical industrial product) processing project, 600,000t/a coal tar processing project,
200,000 t/a benzene hydrogenation project, 400,000t/a PVC project and 200,000t/a copper
refining project, etc.
At present, the park has introduced chromium chemical industry, coal coking industry and coal
chemical industry projects and 17 enterprises such as Yuanxin Nickel Industry, Fubon
Magnesium Industry, Hengde Coking, Yongxing Mining, Ronghua Mining, Yintai Iron Alloy,
Zhengxuan Chemical Industry, Silico Silicon Material, Jinnuo Chemical Industry, etc.
The water demand of
enterprises in the park that
put into production
recently is 5,230,000t/a,
the water demand of
enterprises in the park built
and under the construction
is 2,300,000 t/a, and the
water demand of
enterprises that entered
into the access agreement
with the Park is
8,670,000t/a. The total
reclaimed water demand of
industrial enterprises in the
park is 16,700,000t/a,
namely, 45,800t/d.
Considering the water for
roads and green land and
fire prevention as well as
the unforeseeable water
demand and penetrated
water, the maximum water
1. Water Supply Situation: Existing
water source of the processing park is
Delingshan Reservoir, Wubuliangkou
Reservoir, general drainage canal and
underwater. Delingshan Reservoir will
supply the industrial water of
3,000,000m3/year to the processing park,
Wubuliangkou Reservoir under
construction will supply the living water
of 5,000,000m3/year and general
drainage canal will provide some
industrial water, and the underwater shall
be exploited. At present, there is no
unified water supply network in the
Park.
2. Existing Problem: Poor water supply
capacity, diffused water source and lack
of unified management and coordination.
90
demand will be 60,000t/d
or so.
3
Hanggin
Rear
Banner
Processing
Park
The construction scale of Hanggin Rear Banner Industrial Park is now 179.60ha, with a short-
term construction size of 319.96ha and long-term construction scale of 630.75ha. it is
proposed to build the park into the layout structure of “one zone and two blocks”.
The Park is divided into 11 industry zones, namely, wine brewing industry zone, including
Hetao Liquor Industry Group, covering a land area of 52ha; Fresh-keeping dairy processing
industry zone, including Yili Dairy Group Shanba Branch, covering a land area of 36.12ha;
Tomato & fruits and vegetables processing zone, including COFCO Tunhe Tomato Products
Co., Ltd, covering a land area of 58.79ha; Meat food processing zone, including Prairie Xingfa
Food Co., Ltd, covering a land area of 37.09ha; Roasted seeds and nuts processing Zone,
including Dahaoda Food Company, covering a land area of 49.64ha; corn transformation
processing industry zone, including Inner Mongolia Tiancheng Animal Husbandry Company,
covering a land area of 43.39ha; bread flour processing industry Zone, covering a land area of
46.26ha, Refined oil processing industry zone, covering a land area of 28.14ha, wood
processing industry zone, covering a land area of 39.22ha, Grass Wolfberry processing
industry zone, covering a land area of 30.95ha, biomass combined heat & power industry
zone, covering a land area of 25.38ha, which is for the construction of 4×12MW biomass
(straw) heat power project and supplies the power to the whole park.
Total water demand of the
enterprises in the Park will
be 5,554,000t/a by year
2015, of which, the water
consumption by production
will be 705,000t/a, and the
water consumption by
cooling and circulation
will be 4,849,000t/a.
Considering the water for
roads and green land and
fire prevention as well as
the unforeseeable water
demand and penetrated
water, the maximum water
demand will be 20,000m3/d
or so.
1. Water Supply Situation: there is no
water plant in the Park, and the industrial
enterprises take the underwater for their
living and production water via the self-
dug wells, and they have built their own
water supply pipeline systems.
2. Existing problem: shortage of top-
quality water sources in the region,
obvious contradiction of supply and
demand, unbalanced and uncoordinated
construction of water supply facilities;
4 Wuyuan
Industrial
Park
Specific layout of Wuyuan Industry Park may be outlined as “one ring, two axes, two blocks,
two centers and multiple groups”. “One Ring” refers to the ring-like green belt from the
peripheral roads of the Park, serving as the ecologic buffer belt between the Park and
surrounding region. “Two Axes” refers to the two important development axes along
Xingyuan Road (S) and Jing’er Road, of which Xingyuan Road (S) is a south-north
development axis connecting the urban area and the Park; Jing’er Road is the east-west
Total water demand of the
enterprises in the Park will
be 5,561,700t/a by year
2015, of which, the water
consumption by production
will be 1,210,700t/a, and
1. Water Supply Situation: there is no
water plant in the Park, and the industrial
enterprises take the underwater for their
living and production water via the self-
dug wells, and they have built their own
water supply pipeline systems.
91
development axis communicating the Park with the outside. “Two Blocks” refers to two blocks
formed due to the separation of road greening belt and the water system, of which, the north
Jing’er Road is to develop the primary industry such as deep processing and auxiliary
processing of agricultural and livestock products and the south of Binhe Road is to develop the
secondary industry such as bio-chemical industry, bio-energy, etc. “Two Centers” refers to the
two centers of providing the supporting services to the enterprises in the Park: Comprehensive
service center serves as the administrative center and supporting business service center of the
Park, and Business trade and logistics center will provide the services to the park and county
urban area by relying on the regional business trade and logistic areas. “Multiple Groups”
refers to multiple functional groups formed due to the separation of roads, greening belts and
canals. Agricultural and livestock products deep processing group is divided into multiple
subgroups according to the category of processing products such as green food processing,
grain processing, TCM processing, livestock product processing, woods and fruits processing,
etc.; Biochemical group is divided into many subgroups as per the category of products such
as bio-based material manufacture, microorganism manufacture and biologic pesticide
manufacture, etc.; Bio-energy group has two subgroups: one is to develop the biomass power
industry via the straw power generation, and the other is to lay stress on the development of
biologic fuels such as fuel ethanol, bio-diesel oil, etc.; Supporting processing group is to
develop the supporting processing industries related to the leading industry of the Park and it
may serve as the carrying space of downstream extension industry of Jinquan Industry Park in
the future.
the water consumption by
cooling and circulation
will be 4,351,000t/a.
Considering the water for
roads and green land and
fire prevention as well as
the unforeseeable water
demand and penetrated
water, the maximum water
demand will be 20,000m3/d
or so.
2. Existing problem: shortage of top-
quality water sources in the region,
obvious contradiction of supply and
demand, unbalanced and uncoordinated
construction of water supply facilities;
92
Table 3.2-2 Main Characteristics of Various Reclaimed Water Supply Projects
Item Unit
Reclaimed Water
Supply Project of Urat
Rear Banner
Processing Park
Reclaimed Water
Supply Project of
Ganqimaodu Port
Processing Park
Reclaimed
Water Supply
Project of
Drainage Canal
3
Reclaimed Water
Supply Project of
Drainage Canal
7
Treatment Facilities
Nature —— Newly built Newly built Newly built Newly built
Scale 10,000m3/d 3.5 4 2 2
Service
Scope——
Urat Rear Banner
Processing Park
Ganqimaodu Port
Processing Park
Hanggin Rear
Banner
Industrial Park
Wuyuan
Rongfeng
Industrial Park
Water
Source——
General Drainage
Canal/Underwater
/Yongming Lake
General Drainage
Canal
Drainage Canal
3 sewage
treatment plant/
Drainage Canal
3
Drainage Canal 7
sewage treatment
plant/ Drainage
Canal 7/
underwater
Delivery
distance of
raw water
Km 5.0 3.0 0.1 0.1
Pipe
diameterMm 500 600 400 400
Piping Distribution
Piping
LengthKm
Ductile cast iron pipe/PE
pipe, 32.04
Ductile cast iron
pressure water pipe,
28.0
Ductile cast iron
pressure water
pipe, 3.0
Ductile cast iron
pressure water
pipe, 19.0
Quantity of
pump
stations
set 1 1 1 1
Construction Period
Construction
PeriodYear 4 4 4 4
3.2.1.2 Water Supply Project of Reclaimed Water for Urat Rear Banner
Processing Park
(1) Inlet/Outlet Water Quality
The reclaimed water supply projects of Urat Rear Banner Processing Park have
two water sources: one is from the sewage treatment plant and the other is from the
general drainage canal. Furthermore, Yongming Reservoir and underwater serve as
93
the standby water sources. In the wet seasons from May to November of following
year, the reclaimed water will mainly use the drained water from the general drainage
canal and the sewage treatment plant. From December to April, the water is
diversified from Yongming Reservoir to general drainage canal to supplement the
water of the general drainage canal, and in addition, some underwater shall be
pumped to meet the water supply requirement. According to the water source quality
of reclaimed water supply projects and in full consideration of the usage and standard
requirements of reclaimed water, the inlet/outlet water quality of reclaimed water
supply system is defined in combination with the use requirement on water quality,
treatment degree and treatment cost, with more details in Table 3.2-3.
Table 3.2-3 Inlet/Outlet Water System of Reclaimed Water Supply Projects in Urat Rear Banner
Processing Park
No. Indicator Inlet (mg/L) Outlet (mg/L)
1 COD 40 ≤50
2 BOD 15 ≤10
3 Ammonia 3.5 ≤5
4 TP 0.6 ≤0.5
5 TN 5.0 ——
6 SS 70 ≤10
7 Cl- 200 ——
8 SO2-4 180 ——
9 Ca2+ 60 ——
10 Mg2+ 50 ——
11 Total alkalinity 170 ——
12 Total hardness 280 ——
(2) Process Proposal
Through the comprehensive comparison of multiple proposals, the process flow
of the reclaimed water treatment of the Project is as follows: contact tank – clean
water tank – pumping station – water distribution network. Main buildings and
structures for the reclaimed water supply projects of Urat Rear Banner Processing
Park are shown in Table 3.2-4.
94
Table 3.2-4 Main Buildings and Structures for Reclaimed Water Supply Projects of Urat Rear
Banner Processing Park
No
.
Buildings
&
Structures
Process Description Main Equipment and Design Parameters
5Contact
Tank
To make sure of a full
contact of disinfectant with
supply water to realize the
sterilization, contact tank is
set up, and under the
condition of designed
chlorination quantity,
removal rate of escherichia
coli may be over 99.9%
1. Design Parameter
Design flow: Qmax=0.45m3/s; tank quantity:2; effective
volume: 810m3; residence time:30min
2. Main Equipment: manual cast-iron square gate: two
gates, specification: 1000*1000; manual cast-iron round
gate: one gate, specification:Ф700
8Chlorinatio
n Chamber
Chlorine dioxide is
recommended for the
disinfection of supply water
and the chlorination quantity
may be automatically
controlled or manually
adjusted.
1. Design parameter
Chlorination quantity for water supply treatment: 0.5mg/l
2. Main equipment: Chlorine dioxide equipment system,
3sets (two sets for use and one for standby), and stand-
alone output: 10kg/h, automatic control;
10Clean
Water Tank
Water quantity is adjusted to
ensure the safety of water
supply.
1. Design parameter
Design water quantity: 35000m3/d. Clean water tank
volume: 7000m3; tank quantity: 2tanks; size of single
tank: LXBXH=29.4*29.4*5;
2. Main equipment: one water level meter; one
submersible pump, with a flow of 100m3/h, and pump lift
of 9m, and electric motor power of 5.5kw.
11Pumping
House
1. Design Parameter
Design scale: 35000m3/d
2. Main equipment: six submersible pumps (4 for use and
2 for standby), with a flow of 350m3/h and pump lift of
25m, and electric motor power of 11kw.
(3) Water Intake Works
Two water intake pumps were set up at Stake No.31500 of general drainage
canal. The project will use the existing water intakes and one standby pump
(Q=580m3/h, H=35m) will be increased to ensure the water intake safety.
(4) Water Conveyance Project
In order to ensure the requirement of 100% water supply for the processing park,
95
the project will pave two pipelines, with a design flow of 255L/s. It is necessary to
newly increase a water pipe of DN500 (length of 5000m) based on the existing
pipelines. The minimum buried depth of water pipelines shall be 1.80-2.00m, and the
exhaust valves are set up at the vertical extrusions of water pipelines and the related
positions; Empty well shall be designed at the lowest position of the pipelines, and a
valve well shall be provided at the origin and the destination of the water pipeline.
(5) Water Distribution Network
The water distribution network shall be laid out along the planned route of the
processing park. After paved out from the pumping station, the water pipeline of
reclaimed water is diversified into three lines and extended toward the northwest,
southwest and southeast of the processing park, and water supply pipe network shall
be designed into the ring-like structure along the existing and planning routes to
ensure the water supply safety. The layout of reclaimed water distribution network is
detailed in Fig. 3-1.
Design parameter of water distribution network: design flow of 35,000m3/d;
hourly variation coefficient Kh=1.1; minimum service water head of the most
unfavorable point is not less than 20m.
PE pipes and ductile cast-iron pipes are used for the water distribution network.
(6) Demonstration and Analysis of Water Source.
There are four available water sources in the processing park: a. the water from
the sewage treatment plant; b. the water from the general drainage canal; c. the
underwater of the processing park; d. the water from the Yongming Reservoir at the
upper reach of General Drainage Canal.
According to the Feasibility Study Report of Sewage Treatment Project for Urat
Rear Banner Processing Park of Bayan Nur City, Inner Mongolia Autonomous
Region, the daily treatment capacity of the sewage treatment plant is 20,000m3/d. The
outlet water of sewage treatment plant reaches the class-I B discharge standard and
the drained water is relatively stable, which may serve as one of water sources of
water reclamation plant.
General Drainage Canal is 5km away from the processing park and it has a
96
better water quality and stable and abundant water quantity, and there exist the water
intake pipelines from the general drainage canal to the processing park, with a
convenient condition of using the water source, so it may serve as the water source of
water reclamation plant.
The underwater of the region refers to the shallow underwater and is used for
irrigation and living. The data of Comprehensive Planning Description of Water
Resources of Bayan Nur City show that the exploitable underwater quantity of Urat
Rear Banner is 9,100,000 m3 if the underwater salinity is less than 3g/L, and the
exploitable underwater of Urat Rear Banner is 3,400,000 m3 if the underwater salinity
is 3-5g/L. According to the provisions set forth in Report for the Definition of
Underwater Over-drafting Area in Bayan Nur City, the processing park belongs to the
serious underwater over-drafting area, and for this reason, the underwater cannot
serve as the eternal water source of the project, but it may serve as the standby water
source.
Yongming Reservoir is located at longitude 106°41′17″ and latitude 40°51′35″,
and the eastern fringe of Wulanbuhe Desert and at 5km in the lower reach of
Liushagou Trench. It is close to the general drainage canal and subject to the
combined scheduling with Guanglin Flood Detention Area. It is a small-scale plain
reservoir highlighting the flood prevention, and the operation mode of flood storage
and staggering flood peak and facing the flood by empty reservoir is applied, with a
total reservoir capacity of 2,602,000 m3. It may serve as the supplementary water
source of the Project if the water quantity of general drainage canal is not enough in
winter.
The water supply scale of water reclamation plant is 35,000m3/d, of which the
water of 15,000m3/d is from the sewage treatment plant and the water of 20,000 m3/d
is from the general drainage canal. Considering the self-consuming water quantity by
the factory area, it is necessary to intake the water of 18,000 m3/d from the sewage
treatment plant of Urat Rear Banner Processing Park and 24,000 m3/d from the
general drainage canal, and the available water quantity of general drainage canal is
97
calculated by 85%, and the water demand of general drainage canal shall be more
than 850,000t/month and the insufficient water quantity in winter can be
supplemented by the underwater and the water from Yongming Reservoir.
If the probability of water supply is calculated by 95%, the correlation between
available water quantity of water sources and water intake quantity of the Project is
shown in Table 3.2-5.
Table 3.2-5 Correlation between Available Water Quantity of Water Sources and
Water Intake Quantity of the Project (10,000m3)
Month 1 2 3 4 5 6 7 8 9 10 11 12
Water from
sewage
treatment
plant
55.8 52.2 55.8 54.0 55.8 54.0 55.8 55.8 54.0 55.8 54.0 55.8
Water from
General
Drainage
Canal
42.0 28.0 29.2 92.4 624.7 587.5 451.9 310.1 333.8 870.2 686.9 59.4
Yongming
Reservoir14.0 14.0 14.0 14.0 —— —— —— —— —— —— —— 14.0
Underwater 42.2 42.2 42.2 42.2 —— —— —— —— —— —— —— 42.2
Total
available
water
quantity
154.0 136.4 141.2 202.6 680.5 641.5 507.7 365.9 387.8 926.0 740.9 171.4
Quantity of
water intake130.2 121.8 130.2 126 130.2 126 130.2 130.2 126 130.2 126 130.2
From Table 3.2-5, we learn that the main intake water sources and standby water
source of the reclaimed water supply projects of Urat Rear Banner Processing Park
can guarantee the requirement of the water intake quantity of the Project and the
probability of water supply may be over 95%.
The result of water quality analysis reports of various intake water sources is
shown in Table 3.2-6 and Table 3.2-7.
98
Table 3.2-6 Outlet Water of Sewage Treatment Plant of Urat Rear Banner Processing Park
No. Water Quality Index Designed Outlet Water
Quality1 CODcr 60 mg/l2 BOD5 20 mg/l3 SS 20 mg/l4 Ammonia (metered by N) 8 mg/l5 TP (metered by P) 1 mg/l
99
Table 3.2-7 Main Water Quality Index of Raw Water of General Drainage Canal
Monitoring Item 2008.4 2008.5 2008.6 2008.8 2008.9 2008.10 2008.11 2009.2 2009.3 2009.4 2009.5 2009.6
pH Value 8.66 8.36 8.31 8.3 7.86 7.97 8.47 7.74 8.10 8.51 8.58 8.10
COD (mg/L) 38 14 1 19 9 19 19 23 29 33 17 9
Ammonia (mg/L) 1 0.4 0.7 <DL 0.1 <DL 0.3 0.4 0.2 0 <DL <DL
TP (mg/L) 0.02 0.52 0.22 0.29 0.3 0.15 0.15 0.51 0.57 0.6 0.27 0.42
TN (mg/L) 1.4 0.8 1.9 3.5 2.1 1 1.5 2.08 2.18 1.57 3.05
Total salt content
(mg/L)1971 1215 576 1198 1447 1710 2386 2035 1033 2344 1127 877
CO2-3(mg/L) 30 15 15 15 0 0 15 <DL 0 45 30 0
HCO-3(mg/L) 351 282 237 290 28 412 478 519 305 427 290 244
Total alkalinity
(mg/L)312 244 207 501 232 338 388 425 250 388 263 200
Cl-(mg/L) 532 230 27 266 301 372 674 479 284 674 266 213
SO2-4(mg/L) 432 324 144 252 420 408 492 432 132 456 192 156
Ca2+(mg/L) 110 105 55 80 70 135 120 140 105 90 85 90
Mg2+(mg/L) 109 67 33 52 82 80 146 128 55 152 58 43
K++Na+(mg/L) 406 191 66 244 291 294 481 338 150 500 206 131
Total hardness
(mg/L)726 538 275 413 513 701 901 876 488 851 450 400
100
From the monitoring result of water quality, we learn that the water from the
general drainage canal is polluted to somewhat extent, but its quality can reach the
provisions of Code for Design of Wastewater Reclamation and Reuse upon the
disinfection treatment together with the water from the sewage treatment plant, and it
can function as the cooling water and urban miscellaneous water.
3.2.1.3 Reclaimed water Supply Project of Drainage Canal 3
(1) Inlet/Outlet Water Quality
The water source of water reclamation plant of drainage canal 3 is mainly from
the water of sewage treatment plant of drainage canal 3, the water from the drainage
canal3 and the standby water source is the underwater. During non-frozen season, the
intake proportion of water reclamation plant from the tail water of the sewage
treatment plant and from the water of drainage canal 3 approaches to 6:5,, and
according to the weighted calculation and in full consideration of the usage and
standard requirements of various reclaimed water, the inlet water quality of water
reclamation plant is defined as shown in Table 3.2-8 in combination with the user’s
requirement on water quality, treatment degree and treatment cost.
Table 3.2-8 Inlet/Outlet Water Quality of Water Reclamation Plant of Drainage Canal 3
No. Water Quality Index Inlet Water Quality Outlet Water Quality
1 CODcr 70 mg/l ≤502 BOD5 16 mg/l ≤103 SS 16 mg/l ≤54 TN (Metered by N) 15 mg/l ≤105 TP (Metered by P) 2.1mg/l ≤0.5
(2) Process Proposal
The treatment structures, production buildings and ancillary buildings in the
water reclamation plant shall be built one-off as per the production capacity of
20,000m3/d, and the main buildings and structures for the water reclamation project of
drainage canal 3 are shown in Table 3.2-9.
According to the analysis of raw water quality characteristics, analysis of main
treatment processes, selection of purification structures and treatment proposal
comparison of sludge water, the treatment process flow of reclaimed water for
101
drainage canal 3 is shown in Fig. 3.2-1.
Fig. 3.2-1 Process Flow of Reclaimed Water Treatment of Drainage Canal 3
Table 3.2-9 Main Buildings and Structures of Water Reclamation Plant of Drainage Canal 3
No.Buildings &
StructuresProcess Description Main Equipment and Design Parameter
1Distributing
wellIncoming water is evenly distributed One well, L×B×H=4m×4m×6m
2Piping mixer
well
Mount the guide vanes in the piping to
diversify or guide the water flow to
increase the mixing effect.
Design parameter: one well; Design size:
L×B×H=6m×3m×4m
Main equipment: one piping mixer
3Small-hole
mesh reactor
Create certain hydrologic condition,
enable all colloidal particles to complete
the flocculation process in the shortest
time to realize the optimal flocculation
effect.
Design parameter: one reactor; Design size:
L×B×H=7m×7m×3m (effective depth); Residence
time: T=10min;
Main equipment: one small-hole mesh reactor.
4
Sloping plate
sedimentation
tank
Separate the bigger alum particles in the
water
Design parameter: one tank; design size:
L×B×H=15.5m×8.5m×5m;
Main equipment: four electric mud valves; two mud
scrapers; two sloping plates, with an interval of
25mm and area of 120m2.
5 Filter station Further remove the micro-particles from
the water after the suspended liquid
passes through the porous media, so as to
ensure the final outlet water quality.
Design parameter: one filter station (four partitions),
L×B×H=26m×20m×6m;
Main equipment: long-handle filter nob, 50nobs/m2 ,
totaling 7200nobs; quartz filter media, total volume:
175m3; three backwash pumps and three blowers,
102
two air compressors (one for use and one for
standby); two pneumatic inlet sluices and two
pneumatic outlet sluices; two pneumatic wafer
butterfly valves; one electric single-beam suspension
crane.
6
Reflux
equalization
basin
The collected water is processed after
returning to the front end of water
reclamation plant
Design parameter: one basin, L×B×H=8m×8m×4m;
Main equipment: two centrifugal pumps, one
submersible mixer.
7
Sludge
equalization
basin
Adjust the sludge quantity and flow the
municipal sewer network
Design parameter: one basin, L×B×H=8m×8m×4m;
Main equipment: 2 centrifugal pumps and one
submersible mixer.
8Chlorination
chamber
Chlorine dioxide is recommended for the
disinfection of supply water and the
chlorination quantity may be
automatically controlled or manually
adjusted.
Design parameter: one chamber, L×B =12m×10m,
chlorination quantity: 0.5mg/l;
Main equipment: 3 Chlorinators (two for use and one
for standby, Q=5kg/h), one chlorine dioxide
generator, Q=10kg/h
9Dosing
chamber
Provide the necessary and prepared
flocculants to the deep water treatment
structures and the proper reserve
quantity, to remove the phosphorus,
turbidity and organism from the water.
Design parameter: one dosing chamber, L×B
=12m×10m
10Clean water
tank
Control the water supply difference
between intake pump house and
pumping house; if the supply is surplus,
the water is stored in the clean water
tank, and if it is not enough, the water
will be supplemented by the clean water
tank.
Design parameter: one clean water tank, adjustable
volume is calculated by 10% of maximum daily
design water quantity, L×B×H =25m×16m×5m
(ultrahigh 0.5m)
11Pumping
house
Lift the reclaimed water to meet the
requirement of the whole water
reclamation plant on vertical hydrologic
flow
1. Design parameter: one pumping house, design
pumping capacity: 20000m3/d
2. Main equipment: three suction pumps.
12
Ultrafiltration
anti-seepage
chamber
Remove the salt from the water via the
ultrafiltration and anti-seepage process
Two ultrafiltration tanks, L×B×H =12m×10m×5m;
One anti-seepage chamber, L×B×H =42m×27m×9m;
13
Backwash
wastewater
tank
One tank, L×B×H =5m×5m×4m
14Neutralization
tankOne tank, L×B×H =5m×5m×4m
15Wastewater
basinOne basin, L×B×H =6m×5m×5m
(3) Water Intake Works
103
One water intake pump station was built at drainage canal 3, with a design
capacity of 33,000m3/d. Because the intake pump station is not far from the water
reclamation plant, the construction of raw water pipelines shall be subject to the
supporting construction with the water reclamation plant.
The suction well shall be built near the intake pump station, with a design size of
10m×8m and the center grill is set up; the intake pump house shall be built into the
rectangle shape, with a plane size of 20m×16m. It shall adopt the underground
reinforced concrete rectangle structure and the wellbore depth of pump house shall be
12m. Four horizontal centrifugal pumps shall be used.
(4) Water Conveyance Project
The raw water pipelines refer to the pipeline from the intake pump station to the
water reclamation plant. Because the distance from the intake pump station to the
water reclamation plant is only 100m, two PE pipes of DN300 will be paved from the
intake pump station to the water reclamation plant.
(5) Water Distribution Network
After paved out from the pumping house of water reclamation plant, the water
pipeline is diversified into two water lines to the water supply network of Hangjin
Rear Banner Industrial Park. The terminal pressure of reclaimed water pipelines may
not be less than 0.20MPa and the low-pressure fire-prevention system shall be
applied. During the fire prevention, the free water head of water supply piping
network at the most unfavorable point may not be less than 10m. The layout of
reclaimed water piping network is detailed in Fig. 3-2.
(6) Demonstration and Analysis of Water Sources
There are three available water sources for the water reclamation project of
drainage canal 3, namely, water from the sewage treatment plant of drainage canal 3,
underwater and surface water.
The underwater mainly relies on the phreatic water. The source of phreatic water
recharge is the leakage water of canals or channels and the irrigation leakage, and
then the flood water and precipitation water. The change of phreatic water in the
irrigation period mainly relies on the irrigation, and the underwater depth is 1.0-1.5m
104
during the irrigation period and 0.5m or so during the fall irrigation period. The
phreatic water is affected by the frozen soil during the freezing season, so the
underwater depth may be 2.5m or so. At present, the domestic and industrial water of
the main industrial enterprises in the Park are all the underwater.
There is no production area of surface water in Hanggjin Rear Banner. The
surface water are all the water from the Yellow River except for a little of flood water
in Urat Rear Banner. At 17km of the Yellow River in Hanggin Rear Banner, Wulahe
River, Yangjiahe River and Huangji Canal averagely diversify the water quantity of
880,000,000m3 from the Yellow River, and the general drainage canal passes through
the Hanggin Rear Banner in the north, with an annual water discharge of about
120,000,000 m3. The water-storing capacity of the lakes in the territory is about
5,000,000 m3. But these water sources are far away from the water reclamation plant
of drainage canal 3 and they cannot serve as the water source of the reclaimed water.
Drainage canal 3 runs through the Park in the east. Since its establishment (in
1992), its average monthly water discharge is 8,538,000 m3, and it can also reach
1,055,000 m3 in the unfavorable month, which may function as the water source of
water reclamation plant.
The treatment capacity of Hanggin Rear Banner Sewage Treatment Plant is
20,000m3/d, and the A2/O technology is used. The outlet water of sewage treatment
plant has reached the class-II wastewater discharge standard of Discharge Standard of
Pollutants for Municipal Wastewater Treatment Plants (GB18918-2002), and the tail
water quality of sewage treatment plant is stable, so it can function as the water source
of water reclamation plant.
According to the said analysis of water source, the outlet water quality of
Drainage Canal 3 sewage treatment plant is stable and is given the priority to function
as the first water source of the water reclamation plant. The insufficient water quantity
shall be supplemented or recharged by Drainage Canal 3 during the non-frozen season
and by the underwater during the freezing season.
The water supply scale of water reclamation plant is 20,000m3/d, of which the
105
water of 12,000m3/d is from the sewage treatment plant and the water of 8,000 m3/d is
from the drainage canal 3. Considering the self-consuming water quantity by the
factory area, it is necessary to intake the water of 21,000m3/d from the drainage canal
3. If the available water quantity of drainage canal 3 is calculated by 85%, the water
demand of drainage canal 3 shall be more than 190,000t/d during the non-frozen
season, which can meet the water-intake requirement of the project; the insufficient
water quantity in winter can be supplemented or recharged by the underwater and the
recharged water quantity is 21,000 m3/d.
According to the Demonstration Report of Water Reclamation Plant of Drainage
Canal 3, the underwater supplement of Drainage Canal 3 is 8,792,000m3/a, and if the
exploitable coefficient is 0.5, the exploitable underwater quantity will be
4,396,000m3/a. The correlation between available water quantity of water sources and
water intake quantity of the Project is shown in Table 3.2-10.
Table 3.2-10 Correlation between Available Water Quantity of Water Sources and Water Intake
Quantity of the Project (10,000m3)
Month 1 2 3 4 5 6 7 8 9 10 11 12
Water from
sewage treatment
plant
37.2 34.8 37.2 36.0 37.2 36.0 37.2 37.2 36.0 37.2 36.0 37.2
Water from
Drainage Canal 3 —— —— —— 105.5 1047.4 1031.5 954.4 672.4 652.1 1534.6 832.5 ——
Underwater 109.9 109.9 109.9 —— —— —— —— —— —— —— —— 109.9
Total available
water quantity147.1 144.7 147.1 141.5 1084.6 1067.5 991.2 709.2 688.1 1571.8 868.5 147.1
Water intake
quantity of the
Project
102.3 95.7 102.3 99.0 102.3 99.0 102.3 102.3 99.0 102.3 99.0 102.3
Tail water quality parameter of Drainage Canal 3 sewage treatment plant and water
quality parameter of Drainage Canal 3 are shown in Table 3.2-11 and Table 3.2-12.
Table 3.2-11 Tail Water Quality Parameter of Sewage Treatment Plant of Drainage Canal 3
No. Water Quality Index Designed Outlet Water Quality
1 CODcr 120 mg/l
2 BOD5 30 mg/l
3 SS 30 mg/l
106
4 TN (Metered by N) 25 mg/l
5 TP (Metered by P) 3 mg/l
107
Table 3.2-12 Monitoring Statistics of Water Quality of Drainage Canal 3 (mg/L)
S
a
m
p
l
i
n
g
D
a
t
e
pH
ValueCOD Ammonia TP TN
Total Salt
ContentBicarbonate
Total
alkalinityCl- SO42- Ca2+ Mg2+ K++Na+
Total
Hardness
2
0
0
8
-
4
-
2
5
7.91 111 16.3 0.15 / / 831 682 851 732 100 154 691 888
2
0
0
8.38 20 2.4 0.91 5.7 / 328.0 287.8 283.6 240.2 90.2 66.8 228.1 500.5
108
8
-
5
-
2
1
2
0
0
8
-
6
-
2
1
8.36 7 2.5 1 4.6 / 320.4 110.1 230.4 264.2 70.1 79.0 193.8 500.5
2
0
0
8
-
7
-
2
1
8.28 29 2.8 1.93 2.6 1435.6 411.89 337.84 354.5 228.14 65.13 75.94 300.00 475.48
2 7.8 62 5.9 2.66 6.8 2106.0 511.04 838.34 531.75 408.26 80.16 115.43 459.38 675.68
109
0
0
8
-
8
-
2
1
2
0
0
8
-
9
-
2
1
7.8 7.0 0.2 0.3 2.0 956.8 228.8 187.7 124.1 336.2 85.2 63.8 118.8 475.5
2
0
0
8
-
1
0
-
7.72 35 1.4 0.6 2.9 1976.67 457.60 375.38 460.80 444.20 135.20 91.10 387.50 713.21
110
2
1
2
0
0
8
-
1
1
-
2
1
7.7 30 3 1.26 4.2 2791.53 625.46 513.01 682.41 612.38 150.30 139.73 581.25 950.95
2
0
0
9
-
4
-
2
1
8.00 22 4.7 1.82 7.54 1712.61 465.28 381.63 460.25 264.17 100.20 100.24 321.8 663.16
2
0
0
9
8.32 24 2.2 0.73 4.4 1400.78 366.12 312.81 363.36 240.15 100.20 97.2 218.8 650.6
111
-
5
-
2
1
2
0
0
9
-
6
-
2
1
8.08 12 / 0.88 5.11 1012.09 320.36 262.76 265.88 132.08 80.16 69.86 143.8 488
T
o
t
a
l
88.35 359 41.4 12.23 45.85 13392.08 4865.91 4289.36 4608.08 3901.95 1056.89 1053.08 3644.18 6981.56
A
v
e
r
a
g
8.03 32.64 4.14 1.11 4.59 1674.01 442.36 389.94 418.92 354.72 96.08 95.73 331.29 634.69
112
e
V
a
l
u
e
113
According to the monitoring data of raw water quality as shown in Table 3.2-18,
the water quality of Drainage Canal 3 is better in 2008 through 2009, and COD,
Ammonia and TN have reached the water quality control index of the Code for
Design of Wastewater Reclamation and Reuse (GB50335-2002) with regard to the
reclaimed water as the cooling water, but the total salt content and TP shall be further
processed. This shows that the water quality of Drainage Canal 3 is better, which can
function as the water source of the water reclamation plant of Drainage Canal 3.
3.2.1.4 Reclaimed water Supply Project of Drainage Canal 7
(1) Inlet/Outlet Water Quality
The water source of water reclamation plant of drainage canal 7 is mainly from
the sewage treatment plant of drainage canal 7, drainage canal 7 and the standby
water source is the underwater. During non-flood season, the intake proportion of
water reclamation plant from the tail water of the sewage treatment plant and from the
water of drainage canal 7 approaches to 6:5, and according to the weighted calculation
and in full consideration of the usage and standard requirements of various reclaimed
water, the inlet water quality of water reclamation plant is defined as shown in Table
3.2-13 in combination with the user’s requirement on water quality, treatment degree
and treatment cost.
Table 3.2-13 Inlet Water Quality of Water Reclamation Plant of Drainage Canal 7
No. Water Quality Index Designed Outlet Water Quality Inlet Water Quality
1 CODcr 120 mg/l ≤50
2 BOD5 30 mg/l ≤10
3 SS 30 mg/l ≤5
4 TN (Metered by N) 25 mg/l ≤10
5 TP (Metered by P) 3 mg/l ≤0.5
(2) Process Proposal
The common treatment structures, production buildings and ancillary buildings
in the water reclamation plant shall be built one-off as per the production capacity of
20,000m3/d, and the main buildings and structures for the water reclamation project of
drainage canal 7 are shown in Table 3.2-14.
According to the analysis of raw water quality characteristics, analysis of main
114
treatment processes, selection of purification structures and treatment proposal
comparison of sludge water, the treatment process flow of reclaimed water for
drainage canal 7 is shown in Fig. 3.2-2.
Fig. 3.2-2 Process Flow of Reclaimed Water Treatment of Drainage Canal 7
Table 3.2-14 Main Buildings and Structures of Water Reclamation Plant of Drainage Canal 7
No
.
Buildings &
StructuresProcess Description Main Equipment and Design Parameter
1Distributing
well
Incoming water is evenly
distributed One well, L×B×H=4m×4m×6m
2Piping mixer
well
Mount the guide vanes in
the piping to diversify or
guide the water flow to
increase the mixing effect.
Design parameter: one well; Design size:
L×B×H=6m×3m×4m
Main equipment: one piping mixer
3Small-hole
mesh reactor
Create certain hydrologic
condition, enable all
colloidal particles to
complete the flocculation
process in the shortest time
to realize the optimal
flocculation effect.
Design parameter: one reactor; Design size:
L×B×H=7m×7m×3m (effective depth); Residence time:
T=10min;
Main equipment: one small-hole mesh reactor.
4 Sloping plate
sedimentatio
n tank
Separate the bigger alum
particles in the water
Design parameter: one tank; design size:
L×B×H=15.5m×8.5m×5m;
Main equipment: four electric mud valves; two mud
scrapers; two sloping plates, with an interval of 25mm and
115
area of 120m2.
5 Filter station
Further remove the micro-
particles from the water
after the suspended liquid
passes through the porous
media, so as to ensure the
final outlet water quality.
Design parameter: one filter station (four partitions),
L×B×H=26m×20m×6m;
Main equipment: long-handle filter nob, 50nobs/m2 , totaling
7200nobs; quartz filter media, total volume: 175m3; three
backwash pumps and three blowers, two air compressors
(one for use and one for standby); two pneumatic inlet
sluices and two pneumatic outlet sluices; two pneumatic
wafer butterfly valves; one electric single-beam suspension
crane.
6
Reflux
equalization
basin
The collected water is
processed after returning
to the front end of water
reclamation plant
Design parameter: one basin, L×B×H=8m×8m×4m;
Main equipment: two centrifugal pumps, one submersible
mixer.
7
Sludge
equalization
basin
Adjust the sludge quantity
and flow the municipal
sewer network
Design parameter: one basin, L×B×H=8m×8m×4m;
Main equipment: 2 centrifugal pumps and one submersible
mixer.
8Chlorination
chamber
Chlorine dioxide is
recommended for the
disinfection of supply
water and the chlorination
quantity may be
automatically controlled or
manually adjusted.
Design parameter: one chamber, L×B =12m×10m,
chlorination quantity: 0.5mg/l;
Main equipment: 3 chlorinators (two for use and one for
standby, Q=5kg/h), one chlorine dioxide generator,
Q=10kg/h
9Dosing
chamber
Provide the necessary and
prepared flocculants to the
deep water treatment
structures and the proper
reserve quantity, to remove
the phosphorus, turbidity
and organism from the
water.
Design parameter: one dosing chamber, L×B =12m×10m
10Clean water
tank
Control the water supply
difference between intake
pump house and pumping
house; if the supply is
surplus, the water is stored
in the clean water tank,
and if it is not enough, the
water shall be
supplemented by the clean
water tank.
Design parameter: one clean water tank, adjustable volume
is calculated by 10% of maximum daily design water
quantity, L×B×H =25m×16m×5m (ultrahigh 0.5m)
11 Pumping Lift the reclaimed water 1. Design parameter: one pumping house, design pumping
116
house capacity: 20000m3/d
2. Main equipment: three suction pumps.
12
Ultrafiltratio
n & anti-
seepage
chamber
One chamber, L×B×H =42m×27m×9m
13Ultrafiltratio
n tank Two tanks, L×B×H =12m×10m×5m
14
Backwash
wastewater
tank
One tank, L×B×H =5m×5m×4m
15Neutralizatio
n tankOne tank, L×B×H =5m×5m×4m
16Wastewater
basinOne basin, L×B×H =6m×5m×5m
(3) Water Intake Works
One water intake pump station was built one-off, with an intake capacity of
33,000m3/d. Because the intake pump station is not far from the water reclamation
plant, the construction of raw water pipelines shall be subject to the supporting
construction with the water reclamation plant.
The suction well shall be built near the intake pump station, with a design size of
10m×8m and the center grill is set up; the intake pump house shall be built into the
rectangle shape, with a plane size of 20m×16m. It shall adopt the underground
reinforced concrete rectangle structure and the wellbore depth of pump house shall be
12m. Four horizontal centrifugal pumps shall be used.
(4) Water Conveyance Project
The raw water pipelines refer to the pipelines from the intake pump station to the
water reclamation plant. Because the distance from the intake pump station to the
water reclamation plant is only 100m, two PE pipes of DN300 will be paved from the
intake pump station to the water reclamation plant.
(5) Water Distribution Network
The reclaimed water is pumped from the pumping house into the reclaimed water
distribution network of Wuyuan Industrial Park via two water pipelines. The terminal
pressure of reclaimed water pipelines may not be less than 0.20MPa and the low-
117
pressure fire-prevention system shall be applied. The water supply network adopts the
piping system for production and fire control simultaneously. During the fire
prevention, the free water head of water supply piping network at the most
unfavorable point may not be less than 10m. The layout of reclaimed water piping
network is detailed in Fig. 3-3.
(6) Demonstration and Analysis of Water Sources
There are three available water sources for the water reclamation project of
drainage canal 7, namely, water from the sewage treatment plant of drainage canal 7,
underwater and surface water.
The underwater mainly relies on the phreatic water. The source of phreatic water
recharge is the leakage water of canals or channels and the irrigation leakage, and
then the flood water and precipitation water. The change of phreatic water in the
irrigation period mainly relies on the irrigation, and the underwater depth is 1.0-1.5m
during the irrigation period and 0.5m or so during the fall irrigation period. The
phreatic water is affected by the frozen soil during the freezing season, so the
underwater depth may be 2.5m or so. At present, the domestic and industrial water of
the main industrial enterprises in the Park are all the underwater.
Wuyuan County is rich in water resources. The Yellow River runs through
Wuyuan County in the south, with a length of 60km in the territory and transit water
quantity of 31,500,000,000m3. There are 1989 rivers in the County, with annual water
diversion demand of 800,000,000 m3 - 1,160,000,000 m3, and the maximum water
diversion demand of 1,230,000,000 m3. There are five drainage canals in the county,
with a total length of 176.42km and annual water discharge of 110,000,000 m3.
Drainage Canal 7 runs through Wuyuan Industrial Park in the west. The statistics of
monthly water discharge of the pumping station of Drainage Canal 7 from 1997 to
2007 show that the mean annual runoff is 14,070,000 m3, the maximum runoff is
23,250,000m3, and the minimum runoff 6,950,000m3. Therefore, Drainage Canal 7
may function as the water source of water reclamation plant.
The treatment capacity of Drainage Canal 7 Sewage Treatment Plant is
118
22,000m3/d, and the A2/O technology is used. The outlet water of sewage treatment
plant has reached the class-II wastewater discharge standard of Discharge Standard of
Pollutants for Municipal Wastewater Treatment Plants (GB18918-2002), and the
outlet water quality of sewage treatment plant is stable, so it can function as the water
source of water reclamation plant.
According to the said analysis of water sources, the outlet water quality of
Drainage Canal 7 sewage treatment plant is given the priority to function as the first
water source of the water reclamation plant. The insufficient water quantity shall be
supplemented or recharged by Drainage Canal 7 during the non-frozen season and by
the underwater during the freezing season.
The water supply scale of water reclamation plant is 20,000m3/d, of which the
water of 13,200m3/d is from the sewage treatment plant and the water of 6,800 m3/d is
from the drainage canal 7. Considering the self-consuming water quantity by the
factory area, it is necessary to intake the water of 19,800m3/d from the drainage canal
7. If the available water quantity of drainage canal 7 is calculated by 85%, the water
demand of drainage canal 7 shall be more than 48,900t/d during the non-frozen
season, which can meet the water-intake requirement of the project; the insufficient
water quantity in winter can be supplemented or recharged by the underwater and the
recharged water quantity will be19,800 m3/d. According to the Demonstration Report
of Water Reclamation Plant of Drainage Canal 7, the underwater supplement of
Drainage Canal 7 is 9,532,000m3/a, and if the exploitable coefficient is 0.5, the
exploitable underwater quantity will be 4,770,000m3/a. The correlation between
available water quantity of water sources and water intake quantity of the Project is
shown in Table 3.2-15.
Table 3.2-15 Correlation between Available Water Quantity of Water Sources and Water Intake
Quantity of the Project (10,000m3)
Month 1 2 3 4 5 6 7 8 9 10 11 12
Water from sewage
treatment plant40.9 38.3 39.6 39.6 40.9 39.6 40.9 40.9 39.6 40.9 39.6 40.9
Water from Drainage —— —— —— 10.9 206.5 214 105.5 65.7 94.0 353.4 440.8 ——
119
Canal 7
Underwater 95.4 95.4 95.4 95.4 —— —— —— —— —— —— —— 95.4
Total available water
quantity136.7 133.3 135.0 135.0 247.4 253.6 146.4 106.6 133.6 394.3 480.4 136.3
Water intake quantity
of the Project102.3 95.7 102.3 99.0 102.3 99.0 102.3 102.3 99.0 102.3 99.0 102.3
Tail water quality of Drainage Canal 7 for water reclamation plant is shown in Table
3.2-16 and Table 3.2-17.
Table 3.2-16 Tail Water Quality Parameter of Sewage Treatment Plant of Drainage Canal 7
No. Water Quality Index Designed Outlet Water Quality
1 CODcr 120 mg/l2 BOD5 30 mg/l3 SS 30 mg/l4 TN (Metered by N) 25 mg/l5 TP (Metered by P) 3 mg/l
120
Table 3.2-17 Monitoring Statistics of Water Quality of Drainage Canal 7 (mg/L)
Sampling
Date
pH
Val
ue
CO
D
Ammon
ia
T
P
T
N
Total Salt
Content
Bicarbo
nate
Total
alkalinityCL- SO4
2- Ca2+ Mg2+K+
+Na+
Total
Hardness
2008-4-25 6.62 1968 1730.
2/ / 656 538 922 264 235 154 444 1226
2008-5-21 7.39 824 35.52.
9
1
1
7
/ 526.3 431.6 868.5 672.4 200.
4 121.5 678.1 1001.0
2008-6-21 6.72 658 556.
35
6
4/ 411.9 337.8 1169.9 864.5
190.
4 176.2 843.8 1201.2
2008-7-21 6.94 713 32.64.
36
4
03136.15 427.14 350.35 966.01
720.4
5
155.
31 160.99
706.2
5 1051.05
2008-8-21 6.69 496 41.74.
84
3
7.
6
3307.2 472.91 775.78 1063.5672.4
2
140.
28 151.88
806.2
5975.98
2008-9-21 6.84 487 69 7.
8
7
0 3537.1 465.2 381.6 1010.3 912.6
160.
3 179.2 809.4 1138.6
2008-10-21 7.22 92 1.80.
44
1.
54014.64 518.60 425.42
1488.9
0
648.4
0
170.
30 188.30
1000.
00 1201.20
2008-11-21 7.29 210 181.
05
2
1.
2
4360.53 671.22 500.55 1577.5
0
648.4
1
220.
40 200.48
1062.
50 1326.32
2009-4-21 7.18 955 167.2 11
.6
1
7
3127.32 869.54 713.21 771.04 504.3
2
195.
39
124.54 662.5
0
1001
13.
6
2009-5-21 7.69 269 25.62.
88
2
73080.31 457.65 375.38 1187.6
408.2
6
150.
30 164.03
712.5
0 1051.1
2009-6-21 6.65 2356 94.48.
2/ 3375.61 450.02 369.12 1063.5
744.4
7
150.
30 157.95
809.4
0 1026
Total77.2
39028 713.8
50
.6
3
5
5
1.
9
27938.86 5926.47 5198.8812088.
75
7060.
27
1968
.36
1779.0
5
8534.
6512199.49
Average
Value7.02
820.
73 64.89
4.
60
6
1.
3
2
3492.36 538.77 472.63 1098.9
8
641.8
4
178.
94 161.73
775.8
8 1109.04
Tail water quality of Drainage Canal 7 is better and reaches the class-II wastewater discharge
standard of Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant
(GB18918-2002). According to the monitoring data of raw water quality of Drainage Canal 7, the
water quality of Drainage Canal 7 is worse in 1999 through 2006, and COD, Ammonia, TN, salt
content and TP have far exceeded the standard. The main reasons are that the sewage treatment
plant of Draiange Canal 7 has not yet been built and the urban domestic and industrial wastewater
of Wuyuan County is directly discharged into Drainage Canal 7.
3.2.1.5 Water Supply Project of Ganqimaodu Port Processing Park
(1) Inlet/Outlet Water Quality
The water source of water reclamation plant of Ganqimaodu Port Processing Park is mainly
from the water of general drainage canal, the water from Wangba Reservoir and the standby water
source is the underwater. According to the water source quality and in full consideration of the
usage and standard requirements of various reclaimed water, the inlet water quality of water
reclamation plant is defined as shown in Table 3.2-8 in combination with the user’s requirement on
water quality, treatment degree and treatment cost. Table 3.2-18 Inlet/Outlet Water Quality of Water Reclamation Plant of Ganqimaodu Port Processing Park
No. Indicator Inlet (mg/L) Outlet (mg/L)
1 COD 80 ≤502 BOD 60 ≤103 Ammonia 10 ≤54 TP 2 ≤0.55 TN 13 ——6 SS 20 ≤107 Cl- 630 ——8 SO2-4 300 ——9 Ca2+ 120 ——10 Mg2+ 100 ——11 Total alkalinity 390 ——12 Total hardness 710 ——
(2) Process Proposal
Process flow of water reclamation plant of Ganqimaodu Port Processing Park: equalization
basin – flocculation – sedimentation – filter tank/RO – clean water tank – pumping house – water
distribution network. Main structures include grid flocculation tank, sloping-plate sedimentation
tank, and common filter tank. The main buildings and structures of water reclamation plant for
Ganqimaodu Port Processing Park are shown in Table 3.2-19.
Table 3.2-19 Main Buildings and Structures of Water Reclamation Plant for Ganqimaodu Port Processing Park
No. Buildings & Structures Process Description Main Equipment and Design Parameter
1 Lift pump house
Lift the incoming water to meet the requirement of follow-up treatment of vertical elevation linkage of buildings or structures
1. Design parameter Design scale: 56800m3/d; Design flow: 62500m3/d; Pump house size: L×B=27m×18m
2. Main equipment: 6 submersible pumps (four for use and two for standby).
2 Pre-aeration Tank
Degrade a part of COD, Ammonia and TP from the water via the pre-aeration tank in the months with a
Design parameter: design capacity : 56800m3/d; design flow: 62500m3/d; design size: L×B×H 有 效
123
poorer water quality. =30×19×5.5m(ultrahigh 0.5m)
3Flocculation
sedimentation tank
Flocculation sedimentation tank is composed of flocculation tank and inclined-tube sedimentation tank, integrated with the flocculation function and sedimentation function, to remove the COD, SS, P, chromaticity, germ, etc.
1. Flocculation tank: design water quantity: 0.72m3/s; Response time: 15min; 6 tanks, 14 grills for each tank; tank size: 7.5×5.5m; perforated sludge discharge pipe of DN200 is laid at the bottom of tank; 2. Sedimentation tank: design water quantity: 0.72m3/s; six tanks, and tank size: 12.0×6.0m; Lifting velocity: 1.75mm/s.
4 Filter tank
Further filtrate the outlet water of sedimentation tank. Common filter tank is used and single-layer uniform quartzite media are used. Little resistance underdrain system of long-handle filter nobs and air/water backwash system are used.
1. Design parameter: common filter tank, design water quantity: 0.52m3/s; six filter tanks, with filtration velocity of 6.5m/h; total filtration area: 288m2; Uniform quartzite media; controlled by PLC. 2. Main equipment: backwash pump, six single-step dual-suction pumps (four for use and two for standby); six backwash fans& Roots blowers (four for use and two for standby). 27648 long-handle filter nobs; 432 filter plates, and two cranes.
5 Contact tank
To make sure of a full contact of disinfectant with supply water to realize the sterilization, contact tank is set up, and under the condition of designed chlorination quantity, removal rate of escherichia coli may be over 99.9%
1. Design parameter: Design flow: 0.46m3/s; two tanks; effective volume: 350m3; residence time: 30min. 2. Main equipment: two manual cast-iron square gates; one manual cast-iron round gate.
6Sludge
discharge tank
Collect the sludge from the flocculation sedimentation tank and pump it by submersible sewage pump into sludge buffer tank of sewage treatment plant to be mixed with the surplus sludge in the sewage treatment plant
1.Design parameter: sludge quantity: 142m3/d; effective volume: 260m3
2. Main equipment: three submersible sewage pumps(two for use and one for standby)
7Backwash wastewater
basin
Collect the backwash wastewater of filter station and pump it by submersible sewage pump into coarse screen chamber to avoid the impact load against the treatment structures. Submersible mixer is set up to prevent the settlement of sludge.
1.Design parameter: backwash flow: 0.8m3/s; effective volume: 540m3; 2. Main equipment: three submersible sewage pumps (two for use and one for standby); two submersible mixers and two cast-iron square gates.
8 Chlorination chamber
Chlorine dioxide is recommended for the disinfection of supply water and the chlorination quantity may be automatically controlled or manually adjusted.
1. Design parameter: chlorination quantity: 0.5mg/l. 2. Main equipment: 3 chlorinators (two for use and one for standby, Q=5kg/h), one chlorine dioxide generator, Q=10kg/h
9 Dosing chamber
Provide the necessary and prepared flocculants to the deep water treatment structures and the proper reserve quantity, to remove the phosphorus, turbidity and organism from the water.
1. Design parameter: design water quantity: 0.72m3/s; feed the polyaluminium chloride and dosing quantity: 50mg/l. 2. Main equipment: four complete sets of flocculant mixers, volume of solution tank: 3m3; four metering pumps and diaphragm metering pumps; two electric hoists, with hoisting capacity of 1.0t.
10 Anti-seepage chamber
Remove the salt from the water via the micro-filtration and anti-seepage process
Design water quantity: Q=0.516m3/s; Size: L×B×H=120m×36m×5m
11 Clean water tank
Adjust the water quantity to ensure the safety of water supply
1. Design parameter: design water quantity: 40000m3/d; clean water tank volume: 4000m3; one water tank, with tank size of LXBXH=29.4*29.4*5. 2. Main equipment: one water level meter and one submersible pump.
12 Pumping house
Supply the water to the enterprises in the Park
1. Design parameter: design capacity: 30000m3/d2. Main equipment: six submersible pumps (four for use and two for standby, Q=350m3/h and H=5.5m); electric motor power = 11kw.
(3) Water Intake Works
The water intake capacity is 62,500m3/d and the intake pump house and the suction well are
built together in a rectangle structure of 20m×6m. Fine screens are set up in the intake chamber of
suction well, and six horizontal centrifugal pumps are provided (four for use and two for standby).
(4) Water Conveyance Project & Water Distribution Network
124
The water reclamation plant is to be built near Wangba Reservoir and the water pipelines are
paved directly to the water reclamation plant along the pathway from the intake pump station.
Water distribution pipeline adopts dual-pipe structure and it is proposed to pave two ductile
cast-iron pressure pipelines of DN600, with a design flow of 509 L/s and a length of 28km. they are
paved from the water reclamation plant to the clean water tank of sewage treatment plant in the
processing park.
The minimum buried depth of water pipelines shall be 1.80-2.00m, and the exhaust valves are
set up at the vertical extrusions of water pipelines and the related positions; Empty well shall be
designed at the lowest position of the pipelines, and a valve well shall be provided at the origin and
the destination of the water pipeline.
(5) Demonstration and Analysis of Water Source
There are three available water sources in the industrial park: underwater, water from general
drainage canal and water from Wangba Reservoir.
The underwater of this region mainly relies on the shallow underwater, which is used for
irrigation and domestic water. The statistics of Comprehensive Planning Description of Water
Resources in Bayan Nur City show that the exploitable underwater quantity of Urat Middle Banner
is 83,100,000 m3 when the underwater salinity is less than 3g/L, and the exploitable underwater
quantity of Urat Rear Banner is 30,900,000 m3 when the underwater salinity is 3-5g/L. Because the
region belongs to the serious underwater over-drafting area, the underwater cannot serve as the
eternal water source of the project.
Wangba Reservoir is located at longitude 106°41′17″ and latitude 40°51′35″, and in the
pastureland of Muyang Lake of Urat Middle Banner, Bayan Nur, Inner Mongolia, with a total
reservoir capacity of 4,540,000m3. It is a small-scale (class-I) plain reservoir highlighting the flood
prevention, and serves as the emergent flood detention area of Heishi Lake.
General Drainage Canal is 14km away from the industrial park, with a better water quality
and stable & abundant water quantity, and convenient condition of using the water sources, which
may function as the eternal water source of the water reclamation plant.
The water reclamation plant of Ganqimaodu Port Processing Park is located at the lower
reaches of General Drainage Canal, with an abundant water quantity. Because the water intake
projects at the upper reaches of general drainage canal will exert certain impact on the water intake
for the water reclamation plant of Ganqimaodu Port Processing Park, the monthly water flow at
Bridge 6 in the lower reaches of general drainage canal shall not be less than 4,050,000 m3. If the
available water quantity of general drainage canal is calculated by 85%, and the monthly water
demand of general drainage canal shall be more than 4,7600,000t. Correlation between available
water quantity of water sources and water intake quantity of the Project (an average of 21 years) is
shown in Table 3.2-20.
125
Table 3.2-20 Correlation between Available Water Quantity of Water Sources and Water Intake Quantity of the
Project (10,000m3)
Month 1 2 3 4 5 6 7 8 9 10 11 12
Water from general drainage
canal728.1 573.1 790.1 829.6 6029.5 5675.7 5670.6 4080.8 3708.2 7565.8 7663.5 2470.2
Water from upper reach 74.4 69.6 74.4 72.0 74.4 72.0 74.4 74.4 72.0 74.4 72.0 74.4
Water from drainage canal 3 74.4 69.6 74.4 72.0 74.4 72.0 74.4 74.4 72.0 74.4 72.0 74.4
Water from drainage canal 7 74.4 69.6 74.4 72.0 74.4 72.0 74.4 74.4 72.0 74.4 72.0 74.4
Total available water quantity 504.9 364.3 566.9 613.6 5806.3 5459.7 5447.4 3857.6 3492.2 7342.6 7447.5 2247
Water intake quantity of the
project 193.8 181.3 193.8 187.5 193.8 187.5 193.8 187.5 187.5 193.8 187.5 193.8
From Table 3.2-20, we learn that the general drainage canal as the water source for water
reclamation plant of Ganqimaodu Port Processing Park can guarantee the requirement of the water
intake quantity of the Project and the probability of water supply may be over 95%.
Analysis result of water quality of General Drainage Canal is shown in Table 3.2-21. Table 3.2-21 Main Water Quality Index of Raw Water of General Drainage Canal
2008.4
2008.5
2008.6
2008.8
2008.9
2008.10
2008.11 2009.2 2009.3 2009.4 2009.5 2009.6
pH 8.66 8.3 8.14 7.96 8.21 8.34 7.50 7.48 8.47 8.28 7.94COD (mg/L) 186 60 26 55 30.5 41 35 148 156 148 52 37
Ammonia(mg/L) 18.2 1.2 1 1.6 1.6 0.8 2.4 32.8 35.6 20.4 1.6 1.6
TP(mg/L) 6.15 1.7 0.73 0.23 0.5 0.31 0.33 7.05 5.01 2.04 0.72 0.67TN(mg/L) 13.5 3.4 2.9 4.2 2.4 3.2 33.8 36.9 26.7 5.09 8.29Total Salt
(mg/L) 2946 1957.6
1174.0 —— —— 2220.1
72836.5
62389.7
71889.6
72574.3
81545.8
11289.6
3CO2-
3(mg/L) 0 7.5 0.0 —— —— 0.00 22.50 ≤DL 0 22.5 15 0HCO-
3(mg/L) 656 396.6 320.4 —— —— 442.40 472.91 640.71 533.93 579.69 358.49 282.22Total
alkalinity(mg/L)
538 331.6 262.8 —— —— 362.86 406.67 525.52 437.94 494.24 306.56 231.48
Cl-(mg/L) 868 514.0 301.3 —— —— 638.10 886.25 762.18 691.28 788.76 478.58 372.23SO2-
4(mg/L) 468 420.2 192.1 —— —— 420.20 516.32 228.14 72 348.2 204.13 120.08Ca2+(mg/L) 150 100.2 65.1 —— —— 125.20 145.29 140.28 105.21 160.32 95.19 80.16Mg2+(mg/L) 128 100.2 63.8 —— —— 94.20 124.54 118.46 118.46 112.39 85.05 66.82
K++Na+(mg/L) 675 418.8 231.3 —— —— 500.00 668.75 500.00 369 562.5 309.4 278.1Total
hardness(mg/L)
901 663.2 425.4 —— —— 700.70 875.88 838.34 750.75 863.36 588.08 475.4
3.2.2 Processing park sewage treatment and reclamation sub-projects3.2.2.1 Features
The steps and contents of processing park sewage treatment and reclamation sub-projects are
as follows:
Determination of service scope→sewage collection (construction of sewage pipe
network)→treatment of sewage treatment plant→intermediate water reclamation (construction of
water distribution pipe network) →the consumer.126
For the Project, there are totally 3 processing park sewage treatment and reclamation sub-
projects. See Table 3.3-22 for the technical characteristics.Table 3.3-22 Main technical characteristics parameters of processing park sewage treatment and
reclamation sub-projects
Index of sub-project Unit
Wulate Houqi Processing Park (Huhe Town) Sewage
Treatment and Reclamation Sub-project
Ganqimaodu Port Processing Park
(Delingshan Town) Sewage Treatment and
Reclamation Sub-project
Wulate Qianqi Processing Park (Xianfeng Town) Sewage Treatment and
Reclamation Sub-project
Building property -- Newly built Newly built Newly built
Location -- In Wulate Houqi Processing Park
In Ganqimaodu Port Processing Park
In Wulate Qianqi Processing Park
Scale of sewage treatment
10,000m3/d 2 3 3
Scale of intermediate
water treatment
10,000m3/d -- 2.0 2
Service scope -- Wulate Houqi processing park
Ganqimaodu Port processing park
Wulate Qianqi processing park
Consumer of intermediate
water--
Water used for industrial production and
afforestation in the park
Water used for industrial production and
afforestation in the park
Water used for industrial production and
afforestation in the parkLength of
sewage pipe network
km 45.08 -- 9.0
Length of intermediate water pipe network
km -- 51.62 65.03
Building period 2 2 2
3.2.2.2 Wulate Qianqi Processing Park (Xianfeng Town) Sewage Treatment and Reclamation
Sub-project
(1) Design inflow water quality of sewage treatment plant
The inflow of sewage treatment plant will be the industrial sewage and domestic sewage from
Wulate Qianqi Processing Park. According to the feasibility study report, the industrial wastewater
flowing in the sewage collection system shall meet the requirements of Discharge Standard for
Municipal Wastewater (CJ3082-1999). Referring to the data on water quality of sewage from
processing park in similar area in the north, and in consideration of the uncertainties of enterprises
in the future and instability of the water quality, the indexes of inflow water quality of sewage
treatment plant are determined. See Table 3.2-34 for the details.
Table 3.2-23 Design inflow water quality of sewage treatment plantIndex CODCr
(mg/L)BOD5
(mg/L)SS
(mg/L)NH3-N(mg/L) Phosphate (P, mg/L) pH
Value ≤300 ≤150 ≤300 ≤25 ≤3 6-9
Note: other contamination indexes shall meet the requirements of Discharge Standard for Municipal Wastewater (CJ3082-1999) for limit value.
(2) Design outflow water quality of sewage treatment and renovated water plant
127
The renovated water of this sub-project will mainly be used as industrial cooling water and
process water. According to the feasibility study report, the main indexes of design outflow water
quality of sewage treatment and renovated water plant are determined and listed in Table 3.2-24.
Table 3.2-24 Standard design outflow water quality of sewage treatment and renovated water plantSN Item Value1 CODCr ≤50mg/L2 BOD5 ≤10mg/L3 SS ≤10mg/L4 TN ≤15mg/L5 NH3-N ≤ (5)8mg/L6 Petroleum etc. ≤1.0mg/L7 Total phosphorus (calculated as per P) ≤0.5mg/L8 Number of coliform bacteria group ≤103 groups/L9 PH 6-9
Note: for the other indexes, please refer to Control Index of Water Quality of Renovated Water Used as Cooling Water.
(3) Processing plan on sewage treatment and renovated water
According to the requirements for inflow and outflow water quality of this sub-project, it is
recommended that A/A/O process be selected for the secondary treatment, and for renovated water
treatment, a three-stage process of coagulation – sedimentation – filtration shall be adopted.
See Figure 3.2-3 for the process flow of sewage treatment and renovated water.
(4) Other processes
① Chlorine dioxide sterilizing method is adopted for sterilization process. For pathogenic
microbe, the extermination capacity of chlorine dioxide is higher than chlorine. As it does not react
with ammonia, it can be provided with high sterilizing power even though under alkaline condition,
and it can exterminate alga. Simultaneously, chlorine dioxide can cause high oxidization effect and
can remove chroma in water favorably, and this enables the outflow water quality to be improved
largely; furthermore, the removing effect can be improved further by combination use of chlorine
dioxide and coagulant.
② Biological method is selected for deodorization process. By this method, contaminations
including low concentration hydrogen disulfide, ammonia, and VOCS etc. can be removed
effectively; the deodorization effects are well without secondary pollution, and the operating cost is
very low.
③ Direct condensation and dehydration treatment is adopted for sludge treatment process.
For direct condensation and dehydration treatment, no digestion tank need be built, and this can
save a large number of capital construction investment and routine maintenance cost. Those
forming machineries with high performances and simper operating method shall be selected for
condensation and dehydration, so that floor area and unpleasant odor can be reduced. Before
condensation and dehydration, polyacrylamide shall be added, so as to be easy for sludge
condensation and dehydration.
128
3.2.2.3 Wulate Houqi Processing Park (Huhe Town) Sewage Treatment Sub-project
(1)Design inflow water quality of sewage treatment plant
The inflow of sewage treatment plant will be the industrial sewage and domestic sewage from
Wulate Houqi processing park. According to the feasibility study report, the main indexes of inflow
water quality of sewage treatment plant of the sub-project are determined. See Table 3.2-25 for the
details.
Table 3.2-25 Design inflow water quality of sewage treatment plantIndex CODCr
(mg/L)BOD5
(mg/L)SS
(mg/L)NH3-N(mg/L) Phosphate (P, mg/L) pH
Value ≤300 ≤150 ≤300 ≤25 ≤3 6-9Note: other contamination indexes shall meet the requirements of Discharge Standard for Municipal Wastewater (CJ3082-
1999) for limit value.
(2) Design outflow water quality of sewage treatment plant
According to the feasibility study report, the outflow from sewage treatment plant shall be
reclaimed as water resources. In combination with the requirements for sewage reclamation, the
outflow discharge shall meet Class A requirements of Discharge Standard of Pollutants for
Municipal Wastewater Treatment Plant. See 3.2-37 for the detailed discharge standards.
Table 3.2-26 Class A requirements of Discharge Standard of Pollutants for Municipal Wastewater
Treatment PlantSN Water quality index Design outflow water quality1 Chemical oxygen demand (CODcr) ≤50 mg/l2 Biochemical oxygen demand (BOD5) ≤10 mg/l3 SS ≤10 mg/l4 Ammonia nitrogen (以N计) ≤ (5)8 mg/l5 Total phosphorus (calculated as per P) ≤0.5 mg/l6 pH 6-9
(3) Processing plan on sewage treatment
The sewage treatment process of this sub-project is the same as that of Wulate Qianqi
Processing Park Sewage Treatment and Reclamation Sub-project. Please see Section 3.2.2.1 for the
details.
(4) Other processes
It is the same as that of Wulate Qianqi Processing Park Sewage Treatment and Reclamation
Sub-project. Please see Section 3.2.2.1 for the details.
3.2.2.4 Ganqimaodu Port Processing Park (Delingshan Town) Sewage Treatment and
Reclamation Sub-project
(1) Design inflow water quality of sewage treatment plant
The inflow of sewage treatment plant will be the industrial sewage and domestic sewage from
129
Ganqimaodu Port processing park. According to the feasibility study report, the main indexes of
inflow water quality of sewage treatment plant of the sub-project are determined. See Table 3.2-27
for the details.
Table 3.2-27 Design inflow water quality of sewage treatment plant
Index CODCr
(mg/L)BOD5
(mg/L)SS
(mg/L)NH3-N(mg/L) Phosphate (P, mg/L) pH
Value ≤500 ≤300 ≤300 ≤25 ≤3 6-9
Note: other contamination indexes shall meet the requirements of Discharge Standard for Municipal Wastewater (CJ3082-1999) for limit value.
(2) Design outflow water quality of sewage treatment and renovated water plant
The renovated water of this sub-project will mainly be used as industrial cooling water and
process water. According to the feasibility study report, the main indexes of design outflow water
quality of sewage treatment and renovated water plant are determined and listed in Table 3.2-28.
Table 3.2-28 Design outflow water quality of sewage treatment and renovated water plantSN Item Value1 CODCr: ≤50mg/L2 BOD5: ≤10mg/L3 SS: ≤10mg/L4 TN: ≤15mg/L5 NH3-N: ≤ (5)8mg/L6 Petroleum etc. ≤1.0mg/L7 Total phosphorus (calculated as per P): ≤0.5mg/L8 Number of coliform bacteria group: ≤103 groups/L9 PH: 6-9
Note: for the other indexes, please refer to Control Index of Water Quality of Renovated Water Used as Cooling Water
.(3) Processing plan on sewage treatment and renovated waterIt is the same as that of Wulate Qianqi Processing Park Sewage Treatment and Reclamation
Sub-project. Please see Section 3.2.2.1 for the details.
(4) Other processes
It is the same as that of Wulate Qianqi Processing Park Sewage Treatment and Reclamation
Sub-project. Please see Section 3.2.2.1 for the details.
3.2.3 Wuliangsuhai Lake Area Treatment Sub-project3.2.3.1 Features
The steps and contents of Wuliangsuhai Lake Area Comprehensive Treatment Sub-projects are
as follows:
Determination of treatment scope →comprehensive treatment (excavation of grid water
channel, and construction of biological transition zone artificial wetland)→restoration of favorable
ecological environment
The purposes of Wuliangsuhai Lake Area Comprehensive Treatment Sub-projects are to reduce
surface source pollution load, restore ecological functions of the lake area, slow down the biological
130
leveling up speed, and improve water circulation in the lake area.
For this project, there are totally 2 Wuliangsuhai Lake area comprehensive treatment sub-
projects, i.e., Wuliangsuhai Lake Area Pastoral Grid Water Channel Sub-project, and Wuliangsuhai
Lake Biological Transition Zone Artificial Wetland Sub-project.
(1) Wuliangsuhai Lake Area Pastoral Grid Water Channel Sub-project
(2) Wuliangsuhai Lake Biological Transition Zone Artificial Wetland Sub-project
3.2.3.2 Grid water channel excavation in the lake area
1) Arrangement of construction activities
(1) Construction time
The non-irrigation period of Wuliangsuhai Lake is from December to the next April. During
this period, water displacement is the lowest. Generally, the lake will ice up in the first Nov., and
ice out in the next March. During this period, the water body is exchanged slowly, and the
sediments are in static condition basically; the remains died alga and plankton are deposited on the
surface layer of the substrate sludge, while for living alga, the sporinite is deposited at the interface
between sludge and water due to low temperature and sunlight, and keeps a dormancy state. If
construction is carried out in this period, some alga and sporinite can be removed. The thickness of
ice layer in Wuliangsuhai Lake is 70-80cm; construction can be carried out in shallow area during
the congelation period, e.g., more shallow than 80cm. For those deep areas, in consideration of
excavation and the bearing capacity of transportation, construction shall be carried out after the
lake surface is iced out, i.e. from Nov. to the next Apr., and under such weather conditions that the
wind class is less than 6 and fog class is less than 2.
(2) Excavation work load
The sediments in the upper layer (as per a thickness of 40cm) are about 1,180,000m3, and the
undisturbed soil in the lower layer is about 2,170,000m3, totally 3,350,000m3.
(3) Section of dredging equipment
Conventional dredgers include grab dredger, bucket dredger, dipper dredger, cutter-suction
dredger, bucket wheel dredger, pump dredger, and multifunctional dredger etc. These dredgers are
commonly used implement for dredging and are held by many dredging companies, so the selection
scope is large. Additionally, there are also many environmental protection dredgers for selection,
e.g., environmental protection type closed grab dredger, dipper dredger, cutter-suction dredger,
bucket wheel dredger, pump dredger, and multifunctional dredger etc., which are newly built in
accordance with the requirements for environmental protection or are modified based on the
conventional dredgers. For these implements, the dredging precision is improved and the agitation
effects to water body during dredging are reduced, but the operating cost is higher, the quantity and
selection scope are smaller.
131
Figure 3.2-4 Density distribution of reed and float grassAccording Figure 3.2-4, float grass at the bottom of Wuliangsuhai Lake is flourishing;
especially the tough reed root system and developing float grass rootstalk will wind the cutter head
and disturb the work, so that the work efficiency is reduced. Therefore, for water channel
132
excavation in Wuliangsuhai Lake, cutter-suction dredger shall not be applicable. Grab dredger is
also a kind of dredging equipment for substrate sludge. However, due to the flourishing reed and
widely spreading root system in Wuliangsuhai Lake and according to the test results of dredging in
Suzhou River of Shanghai, if there is garbage or float grass, it is very easy for cutter-suction
dredger to be blocked up, and this usually causes shutdown and lower production efficiency.
Therefore, in combination with the dredging effects and environment impact, for the area where
reed and other float grass are flourishing, it is recommended that 0.8-1.2 m3 type hydraulic backhoe
dredger be adopted, whereas for the sediments in the upper layer where there are less float grass,
grab dredger shall be adopted. See Table 3.2-29 for the main specifications and parameters.
Table 3.2-29 Main specifications and parameters of selected dredger
SN Index 0.75 m3 grab dredger 0.8~.2 m3 backhoe dredger
1 Main diesel engine 100 kW 118 kW
2 Total length 22.3 m
3 Width 7.0 m
4 Maximum excavation depth 10 m Maximum excavation depth6.5 m
5 Sea gage 0.8 m 0.5 m
6 Maximum excavation radius 8.50 m 8.50 m
7 Bucket capacity 0.75 m3 0.8~1.2 m3
8 Design production efficiency 80 m3/h 80~100 m3/h
2) Technical proposals
(1) Grid water channel excavation work
① Environmental conditions for work in the lake
Environmental conditions for operation in Wuliangsuhai Lake are as follows: the lake is as
shallow as 0.5-3.2m, and the substrate sludge is about 40cm thick; the lake bottom is flat, and this is
easy for operation; the water flows slowly and the flow rate is mostly 1mm/s~1cm/s, and this is
favorable for reducing pollution spreading due to disturbance of operation to the substrate sludge;
the reed and float grass are flourishing, and this increases difficulties in construction.
② Excavation and transportation process
The process flow of water channel excavation is as follows:
Dredging →shipment →water carriage →loading/unloading at the pier →land carriage
→substrate sludge dumping
The excavation sequence shall be:
Zone 1 and Zone 2 can be excavated simultaneously, and Zone 3 and 4 can be excavated
simultaneously. As a whole, the excavation shall be from upper reaches to lower reaches, and can
be commenced simultaneously in the whole lake area if the construction period is short.
133
Water channel plane positioning:
GPS positioning stake and guy rope shall be adopted for marking out the trend of outflow
course. Longitudinal sign shall be arranged in the central line of dredged channel and designed
upper opening boundary, and transverse sign shall be arranged at the construction boundary of the
starting and stopping point of the dredged channel and in the straight reaches of curve bend.
Trend of the excavation line:
As shown in Figure 3.2-5, the whole lake area is divided into 4 zones, each of which is with a
corresponding substrate sludge dumping site. The dredger shall commence the excavation along the
water channel trend. As water in some areas is shallow, the dredger shall be driven along the
excavated water channel when going in/out the sludge zone for operation. The overall sequence of
water channel excavation shall be from the upper reaches to the lower reaches.
Dredging:
The dredger shall begin to work with support of tugboat. The bow shall be arranged in the
direction of the lower reaches; a traverse anchor shall be provided on both sides and a stern
retracting anchor is provided respectively, and totally 4 anchors to fix or move the ship position;
cable length is less than 50m. Before trial excavation, measure the water depth at the bottom, and
control the down letting depth of backhoe on the basis of the water level.
The sediments in the upper layer, which is about 40cm, and substrate sludge in the lower layer
shall be excavated respectively, and they shall be transported and stored separately.
During operation, firstly insert 3 work piles into water and hold them down to the water
bottom till the blow tilts to a height, so as to fix the hull; and then, start up the lifting, bulldozing,
and turning devices of dipper machine to carry out shoveling and excavation jointly. The work pile
at the end shall also be used for supporting the recoil caused by shoveling and excavation and
controlling the direction to move forward the ship position. For the shoveled substrate sludge, use
turning device to turn the dipper to be overhead the sludge barge, and use the dipper starting
mechanism to open the rod bolt and buffer spring, so that the dipper bottom can be open under
deadweight and the load, so as to discharge the sludge.
For the area with shallow water (e.g. less shallow than 80cm), construction may be carried out
in winter, so that excavator can be operating directly on the ice surface, and transporter can be
directly driven on the ice surface.
Shipment:
The dredged sludge shall be transferred and loaded onto the barge berthed beside. After a fleet
(5 barges) is loaded orderly, use tugboat to drag to the dumping site.
Transportation method:
Use sludge barge and sludge carrier jointly to transport the substrate sludge. Use backhoe
dredger to load the dredged substrate sludge directly into sludge barge berthed beside the dredger;
134
and then, use sludge barge to transport the sediments from the upper layer and undisturbed soil form
the lower layer separately. For this, the sediments from the upper layer shall be loaded into 5 barges
and be dragged by a tugboat to the temporary pier nearby, and the barge can be berthed for
discharge before the sludge is transferred to transporter and then be transported to the dumping site
nearby; the undisturbed soil from the lower layer shall also be loaded into 5 barges but be dragged
by a tugboat to the artificial island area as planned in the center of the lake. Finally, the tugboat
shall drag the empty barge from the site back to the dredging working area and wait for loading
again.
In winter, the transporter can directly be driven on the ice surface, so the transportation shall be
easier.
Dumping and stacking:
Use the grab bucket of fixed type tower crane to grab and excavate the substrate sludge from
the barge and unload to the dump truck in temporary pier, and then, transports the substrate sludge
to the dumping site to fill the wide trench, without further special anhydration treatment.
Figure 3.2-5 Layout of water channel excavation and substrate sludge stacking
(2) Substrate sludge dumping site
The substrate sludge in the upper layer of the lake bottom is mainly sediments, and the area is
about 1,180,000m3. After excavation, the substrate sludge from this part shall be transported to 4 135
dumping sites for temporary stacking.
The substrate sludge in the lower layer is mainly unpolluted soil, and the area is about
2,170,000m3. It shall mainly be used for stacking of artificial island in the lake area and shall not be
transported outwards. According to the tourism plan on Wuliangsuhai Lake, many artificial islands
will be built up in the lake area. see Figure 3.2-5 for the details of artificial islands.
① Location of substrate sludge dumping site
According to the space around Wuliangsuhai Lake area, earthwork of water channel in the lake
area and the space distribution, 4 substrate sludge dumping sites shall be arranged. See Figure 3.2-5
and Table 3.2-30 for the details.
Table 3.2-30 Details of substrate sludge dumping sites
SN OF
dumping
siteName Location Floor area (Mu)
Capacity (10,0
00m2)
1DawanggedanD
umping Site Near Dawanggedan (40°02’34’’N, 108°50’31”E) 150 15
2Beilongtai Dum
ping Site Near Beilongtai (40°57’39’’N, 108°50’19”E) 150 15
3Huihuigou Dum
ping SiteOn the south bank in the lake area, near Huihuigou
(40°49’53’’N, 108°47’04”E)400 40
4Yuchang Dumpi
ng siteIn the northeast of Wuliangsuhai Lake (40°52’03’’N,
108°51’35”E)500 50
Total 1200 120
Dumping Site 1 is located in the space near Dawanggedan between Reed Field 4 (Military
Farm) and the lake wall of the large lake, and the floor area is about 150Mu; Dumping Site 2 is
located in the space between Sifenchang and Beilongtai, and the floor area is about 150Mu;
Dumping Site 3 is located in the space on the south bank of Wuliangsuhai Lake and near
Huihuigou, and the floor area is 400Mu; Dumping Site 4 is located in the space in the northeast of
Wuliangsuhai Lake Fishing Ground, and the floor area is 500Mu. The total area is 1200Mu.
Around the 4 substrate sludge dumping sites, there are only a few residents, and little
environment impact will be caused. Highways are provided towards the outside, so the traffic
conditions are good.
② Design for substrate sludge dumping site
The sediments in the upper layer are with high water contents, and they shall be filled and
leveled up in wide trench. See Figure 3.2-6 for profile design for the substrate sludge dumping site.
Dimensions of the wide trench:
The trench is 30m wide, and each is 60m long. It shall be excavated locally downwards, and
the excavated earthwork shall be used for building dumping site embankment and isolation dam,
136
and then be leveled up. The substrate sludge shall be stacked up to 2m high.
Dimensions of embankment and isolation dam:
For the embankment, the top width is 4m, outside slope is 1:2.0, and inside slope is 1:1.5; for
the inside isolation dam of dumping site, the top width is 3m and slope is 1:1.5.
Anti-seepage system:
No drainage system shall be arranged in wide trench in the landfill area, and seepage
interception ditch shall be excavated around the landfill area; ditch slope shall be provided; the
ditch bottom is 1.0m wide, and excavation depth shall be 1.5m. After the filtering water is
collected in the effusion well, it shall be pumped to the near reed field or the lake.
As the filtering water is actually interstitial water of the substrate sludge, we can analyze the
content of dissolvable nutritive matter in the interstitial water. Select 10 points from the distribution
map of monitoring points for substrate sludge in the lake area, and analyze the content of nutritive
salt in the interstitial water of substrate sludge. See Table 3.2-31 for the analysis results.
Table 3.2-31 analysis of nutritive salt in interstitial water of substrate sludge in Wuliangsuhai Lake area
Sampling point and location Water body
TN NH3-N NO3- TP
mg/L
1Interstitial water 24.15 18.11 0.30 0.49
Overlying water 26.62 18.28 0.22 0.54
4Interstitial water 14.54 10.78 0.21 0.29
Overlying water 13.33 11.40 0.12 0.19
5Interstitial water 79.65 70.01 0.42 1.96
Overlying water 77.06 68.13 0.35 3.82
9Interstitial water 4.50 2.00 0.31 0.23
Overlying water 4.97 1.40 0.16 0.57
10Interstitial water 50.95 43.99 0.26 2.15
Overlying water 46.31 39.99 0.23 1.95
14Interstitial water 4.61 2.66 0.12 0.14
Overlying water 4.86 1.37 0.16 0.35
16Interstitial water 3.25 0.86 0.25 0.06
Overlying water 4.01 1.16 0.13 0.11
17Interstitial water 13.08 8.03 0.68 0.18
Overlying water 13.60 11.63 0.13 0.20
18Interstitial water 5.27 1.39 0.41 0.10
Overlying water 4.51 3.25 1.33 0.28
From Table 3.2-31, it can be found that the difference of concentrations of total nitrogen,
ammonia nitrogen, potassium nitrate, and total phosphorus in the interstitial water and overlying
137
water of substrate sludge is not large, so the filtering water can be directly drained into the reed
field nearby or into the lake and the effects on the water body will be small.
Design for road surface:
The major road in dumping site shall be clay bound macadam pavement, and the thickness
shall be 30cm.
Safety enclosure:In order to ensure safety of the landfill area, a 2.5m high fixed type wire mesh enclosure shall
be provided around the landfill area.
Temporary auxiliary production and administration zone:
The operating time period of landfill and treatment of substrate sludge shall be 5 years. In
order to ensure normal operation during sludge landfill and treatment, an auxiliary administration
zone shall be provided beside the landfill area, so as to manage routine operation and store
machineries, and provide back office service etc.
The area of temporary auxiliary production and administration zone is 250m2, mainly
including temporary buildings adopting light steel structure. 2-3 persons are arranged for
management of the site.
③ Landfill process
The substrate sludge landfill process shall include fix-point transportation, unloading along the
ditch, and flattening out etc. The process flow is as follows: Every day, use transporter to transport
the substrate sludge to the landfill area, and dump the sludge along both sides of the wide trench
within the dumping site; for any area stacked too high, use excavator to flatten out, so that the
substrate sludge can be distributed evenly in the wide trench, and the stacking thickness shall be
about 0.5m. After a channel is filled, the next one shall be considered for landfill, in turn. Though
the water content of substrate sludge is very high, it is unnecessary to compact and cover the sludge,
but utilize the local strong sunlight and evaporation action for natural anhydration, and then
commence the next stacking and filling. In order to prevent any propagation of fly and maggot in
the landfill area, spray liquid medicine or lime onto the surface layer of substrate sludge for a few
days, and provide labor safety protection for the employees, so as to avoid epidemic situation. After
the substrate sludge is filled to the given height, a layer of 30cm undisturbed soil shall be paved for
covering.
In consideration of the amount of substrate sludge treated every day and the effective operating
distance of excavator, the quantity of work carried out in one day shall be taken as an operation
unit. The treated substrate sludge shall be transported away in time, in which, the sludge in the
upper layer shall be used for improving the saline alkali soil, and that in the lower layer shall be
used for building the artificial island.138
(3) Temporary pier work
① Location of temporary pier
4 temporary piers shall be provided and used for loading the dredged substrate sludge from the
upper layer, which shall be transferred to 4 substrate sludge landfill areas. See Table 3.2-32 and
Figure 3.2-5 for the details.
Table 3.2-32 Details of temporary piers
SN LocationCorresponding dumping
siteBerth length
(m)Tonnage of
berth (t)
1 Near Dawanggedan (41°02’32’’N, 108°50’44”E)Dawanggedan Dumping Site
(Dumping Site 1)100 200
2 Near Beilongtai (40°57’33’’N, 108°50’29”E)Beilongtai Dumping Site
(Dumping Site 2)100 200
3On the south bank in the lake area, near Huihuigou
(40°50’06’’N, 108°47’01”E)Huihuigou Dumping Site
(Dumping Site 3)100 200
4In the northeast of Wuliangsuhai Lake (40°52’17’’N,
108°51’16”E)Yuchang Dumping Site
(Dumping Site 4)100 200
② Design for temporary piers
Design elevation and water depth:
The design elevation of berthing face shall be the design high water level plus superelevation.
The high water level is 1019.00 m and superelevation is taken as 0.5m, so the design elevation of
berthing face is 1019.00+0.5=1019.50m; the design water level of pier is 1018.05m, so the bottom
elevation of the berthing water area in front of the pier is 1018.05-1.60=1016.45m, and the design
water depth in front of the pier is 1.6 m.
Length and width of the pier:
There are totally 3 freight berths at the pier, so the water front of the pier shall be long enough
to enable 3 200t freight ships to berth simultaneously. The pier is 100m long and 20m wide.
③ Structural design of temporary pier
Take reinforced concrete buttress as main structure of the pier, of which the top surface
elevation is 1019.5m, riser thickness is 300 mm, and a 300 mm broken-stone course is provided.
Poured block stone is provided in front of the wall as washboard. For ship fender, D300×L2000
type is adopted; the space between berths is 3m, and 150KN single eave bollard is adopted. See Fi
gure 3.2-7 for the detailed section.
139
Figure 3.2-7 Section of the pier structure
3.2.3.3 Demonstrative project of agricultural non-point source pollution treatment
1) Significance of demonstration for non-point source pollution control
For treatment of aquatic environment in Bayannur City, many kinds of pollution shall be
revolved, but mainly includes point source and non-point source pollution. Along with the gradual
control over industrial and city point source pollution, agricultural source pollution is featured with
much more potentiality, randomness 、 universality complexity, and posteriority, it will be more
difficult to radically treat agricultural subsiding water pollution, and as a whole, non-point source
pollution will become a confinement factor for improvement of aquatic environment of the
irrigation area in the upper reaches of Huanghe River. Therefore, according to the basic agricultural
production state of Hetao Irrigation Area in Bayannur City, and on the basis of Control over
Farmland Subsiding Water Pollution in Irrigation Area in the Upper Reaches of Huanghe River and
Research and Demonstration of Key Technologies for Wetland Restoration, which has been started
for special national water project, in this project, local control and treatment for subsiding water
pollution are expanded, and a combined treatment concept of “reducing the number of sources,
controlling the process, and treating the terminals” is embodied. In the special demonstration plot in
Hetao Irrigation Area in Bayannur City, the demonstration of nitrogen and phosphorus control shall
be extended, so as to provide an action plan for further control over the subsiding water pollution in
the irrigation area.
2) Location of demonstration plot
140
Inner Mongolia Drainage Field 9 Beichang Branch Ditch Demonstration Plot is located in
Beichang Community of Xiangqinghua Village of Beigedu Township in Wulate Qianqi, Inner
Mongolia, and Tabu Community of Dengcundian Village. It is in the northwest of Wulate Qianqi,
and 30km away from Wulate Qianqi (108°33′47″E, 40°45′29″N). To the demonstration plot, the
east is National Highway 110, the south is Tabu Trunk Canal of Hetao Irrigation Area, and the west
is Branch Canal 4 and the north is Beigedu Township highway in Wulate Qianqi (Figure 3.4-1).
Figure 3.2-8 Demonstration plot of Beichang Branch Ditch in Drainage Field 9 of Hetao Irrigation
Area in Inner Mongolia
3) Backgrounds
For Inner Mongolia Drainage Field 9 Beichang Branch Ditch Demonstration Plot, water is
mainly diverted from Huanghe River for gravity irrigation; the farmland and ditch and road are
planned normatively, and the landform is flat. Irrigation canal system mainly is comprised of Tabu
Trunk Canal and Branch Canal 4; farmland subsiding water is mainly from open drainage, lateral
seepage, and seepage, and then is drained into Beichang Branch Ditch and finally into the Trunk
Canal 9. For the demonstration plot, there are 10 villager groups of Beichang Community in
Beigedu Township and 6 villager groups of Tabu Community in Dengcundian Village involved, the
cultivated area is about 4500Mu, 1100 farmer households, and the population is 3620.
In recent years, sunflower, corn, wheat, and oil sunflower are mainly planted in the
Demonstration Plot. Calculated as per straight gash canal, the annual water consumption has been
2,000,000-2,500,000m3. According to the soil fertileness, the farmland has been provided with
medium-high yield. The average yield of sunflower per Mu is 150kg, corn is 400kg, and wheat is
141
300kg. Pesticide and chemical fertilizer has been adopted at a high level, for which, the sunflower
per Mu is RMB120 Yuan, corn is RMB100 Yuan, oil sunflower is RMB100 Yuan, and wheat is
RMB360 Yuan.
This demonstration plot is very representative in the irrigation area in Inner Mongolia. For the
demonstration plot, the supporting facilities for irrigation and drainage are provided at a high level,
and investment in agricultural chemical fertilizer and production level are also high; supporting
facilities for channels at lower levels are provided well, and the gradient ratio of channel is 1/6000.
Therefore, the demonstration plot shall be an ideal site for research of the features of farmland
subsiding water pollution.
4) Contents of non-point source control demonstration and promotion
Control over agricultural source pollution in the irrigation area is a non-point source control
system project, which shall be carried out by stages and be promoted from experiment unit to the
whole irrigation area. For the demonstration, the key contents include demonstration and promotion
of key technologies for nitrogen and phosphorus control for the main crops on the basis of reduction
of nitrogen and phosphorus pollution in farmland subsiding water, and that of the integrating
technologies for wetland restoration polluted by farmland subsiding water in the irrigation area.
The promotion of controlling technologies for non-point source pollution in the demonstration
plot shall be combined in the appropriation budget of World Bank project, and the main contents are
as follows:
(1) Demonstration of promotion of water saving technologies to reduce running off of nitrogen
and phosphorus
On the basis of the irrigation management technology optimizing water saving in the
demonstration plot, utilize laser grader to level up and divide the farmland into blocks to optimize
water saving technology, so as to reduce farmland subsiding water amount and reduce funning off
of nitrogen and phosphorus contamination and farmland subsiding water pollution. The area is
4500Mu.
(2) Demonstration of fertilization technology
For the representative crops in the demonstration plot, under soil determination and fertilizing
142
technologies, utilize advanced fertilizing machines for accurate fertilization and demonstration, so
as to reduce the amount of applied fertilizer, improve utilization ratio of chemical fertilizer, and
reduce farmland subsiding water pollution caused by running off of nitrogen and phosphorus. The
area of accurate fertilization and demonstration by fertilizing machines is 1000Mu, and that
artificial fertilization and demonstration for nitrogen and phosphorus control is 200Mu.
(3) Economic considerations for farmers
The farmers participating in the non-point source pollution in the irrigation area must change
the former cultivation, fertilization, irrigation habits but put in more energy, labors, and financial
power, so it is necessary for an amount of economic grant to be provided for the farmers. During
execution of the project, random investigation should be carried out for the farmers, who are totally
150 households, and questionnaires of fertilization and feedback sheets of compounded fertilizing
farmland plot management and record shall be prepared, which are totally 1200 sheets; additionally,
sign board shall also be made to provide for the investigated farmer household. Furthermore,
sample 50 households of farmers for evaluation of irrigation water consumption, fertilization, and
effects of subsiding water reinjection and crop growing etc.(4) Field investigation and testing
Provide field investigation for the demonstration plot, divide sampling units; investigate the
basic properties of the sampled plots, production of foregoing crops, and fertilization state etc., and
the surface water environment conditions in the demonstration plot; investigate and sample the
background value of farmland subsiding water pollution state, and monitor, compare and test the
effects data after demonstration.
(5) Propaganda and promotion
On the basis of doing well technical training, deploy fertilizer supply systematically, distribute
the proposal card for fertilizing and subsiding water reinjection, and provide fertilization direction
for the farmers, so as to change any unreasonable habit, such as blindly fertilizing, excessive
fertilization, or preference for nitrogenous fertilizer, and improve the scientific fertilizing level.
According to the farmer fertilization questionnaires, analysis result of soil, and fertilizer demand of
crops, develop more than 40000 proposal cards for soil determination and compound fertilization,
which shall be distributed by the agricultural technicians and village committees, and be signed by
the householders for confirmation after receiving.
(6) Technical training
Firstly do well the technical training for the technicians. By improving the technical level of
143
the technician team, enhance further the training for the peasants and related technicians. Secondly,
by means of broadcasting, TV, newspapers and periodicals, technical information, teaching courses,
and on-the-spot meeting, enhance propaganda and training work, and direct the peasants to execute
subsiding water technologies, so as to improve the farmers' consciousness of fertilization and water
saving, and popularize scientific fertilization technologies and knowledge. It is planned that there
will be 75 training courses, more than 330 peasants and 40 technicians will be trained, and 750
banners will be prepared and hung up.
(7) Construction of software and hardware for database
On the basis of field investigation, farmers' fertilization state, field experiment, and analysis
and test data, collect and work up the field experiment of fertilizer and soil monitoring data on the
whole irrigation area in each year, by means of computer technologies, GIS, and GPS, establish
databases at all levels for physical and chemical properties of soil, fertilizer efficiency, routine
fertilization, irrigation water consumption, and subsiding water reinjection in different areas.
3.2.3.4 Wuliangsuhai Lake biological transition zone artificial wetland
1) Arrangement of construction activities
① Work load
See Table 3.2-33 for plan layout work load of Main Trunk Canal Wetland, Table3.2-34 for
plan layout work load of Trunk Canal 8 Wetland, and Table 3.2-35 for plan layout work load of
Trunk Canal 9 Wetland.Table 3.2-33 Work load of Main Trunk Canal Wetland
Name Work load Unit Remarks
1. Reinforcement of original lake wall 87500 m3 Including excavation, backfilling, and compaction
2. Reinforcement of original box dam 717000 m3 Including excavation, backfilling, and compaction
3. Newly built dike 90000 in the lake4. Main Trunk Canal inflow rubber dam 1 Set
Earthwork excavation 25000 m3
Earthwork backfilling 7000 m3
Backing concrete C10 350 m3
Concrete C25W6F150 6000 m3
Rebar fabrication and installation 350 tBase mat 1600 m2
Dam bag 1000 m2
Rubber sealing material, 651 type, and accessories 2 Batch
5. Wetland inflow rubber dam 1 SetEarthwork excavation 13000 m3
Earthwork backfilling 4000 m3
Backing concrete C10 170 m3
Concrete C25W6F150 3265 m3
Rebar fabrication and installation 150 tBase mat 700 m2
Dam bag 900 m2
Rubber sealing material, 651 type, and accessories 1 Batch
144
6. Water distribution canalEarthwork excavation and filling 75075.0Local concrete protective slope 5200 m3 Protective slope at canal crotch
7. Drainage lift pumping stationVertical axial flow pump 6 Set ZL5612-8
Earthwork excavation and filling 150000 m3
Reinforced concrete 5000 m2
Concrete mat 210 m3
Cement laid stone masonry 330 m3
Filter material 260 m3
Rebar 350 TonPower distribution and transmission line and
transformer 1 Set
8. Diversion dam 458400 m3
9. Stabilization pondEarthwork excavation and transportation 1262900 m3
10. Air and water channel 宽20m, 深1mEarthwork excavation and transportation 200000 m3
11. Wetland outflow rubber dam 3 SetEarthwork excavation 45000 m3Earthwork backfilling 7000 m3Backing concrete C10 900 m3Concrete C25W6F150 11000 m3
Rebar fabrication and installation 900 tBase mat 1500 m2Dam bag 2500 m2
Rubber sealing material, 651 type, and accessories 2 Batch
12. Aeration pondAeration hose 4000 m
Stay tube 3000 mOxygen increasing machine 20 Set
Earthwork excavation and transportation 37500 m3
Concrete foundation pier 300 BlockAir compressor house (including heating and
electric facilities) 800 m2
13. Protective slope of soil biological works 6.8 Km14. Vertical paving geomembrane 40 Km
Table 3.2-34 Plan layout work load of Trunk Canal 8 Wetland
Name Work load Unit Remarks
1. Reinforcement of original lake wall 42500 m3 Including excavation, backfilling, and compaction
2. Reinforcement of original box dam 96000 m3 Including excavation, backfilling, and compaction
3. Diversion dam 55200 m3
4. Alteration of afterbay of Trunk Canal 8 Lift Pumping Station
Newly built sluice (including shutdown) 2 座 4 orifice plates per set,1.5m
Concrete 50 m3
Fabrication of walkway slab 20 m3 10*0.6*0.15mEarthwork excavation and filling 100 m3
Exit channel earthwork excavation and filling 472.5 m3 Bottom 6m, 1.5m deep and 40m longExit channel concrete slab for protective slope 21 m3
5. Water distribution canalEarthwork excavation and filling 4950.0 km An exit per 500mLocal concrete protective slope 42 m2 Protective slope at canal crotch
145
6. Stabilization pondEarthwork excavation and transportation 193700 m3
7. Air and water channelEarthwork excavation and transportation 50000 m3
8. Outflow rubber dam 1 座Earthwork excavation 12000 m3
Earthwork backfilling 3000 m3
Backing concrete C10 150 m3
Concrete C25W6F150 3000 m3
Rebar fabrication and installation 150 tBase mat 800 m2
Dam bag 700 m2
Rubber sealing material, 651 type, and accessories 2 批9. Soil biological work protective slope 4 km
10. Vertical paving geomembrane 8.5 kmTable 3.2-35 Plan layout work load of Trunk Canal 9 Wetland
Name Work load Unit Remarks
1. Reinforcement of original lake wall 137500 m3 Including excavation, backfilling, and compaction
2. 90000 m3 Including excavation, backfilling, and compaction
3. Alteration of afterbay of Trunk Canal 9 Lift Pumping Station
Newly built sluice (including shutdown) 2 Set 4 sluice boards per set,1.5mConcrete 50 m3
Fabrication of walkway slab 20 m 10*0.6*0.15mEarthwork excavation and filling 80
Exit channel earthwork excavation and filling 472.5 m3 Bottom 6m, 1.5m deep and 40m long
Exit channel concrete slab for protective 21 m34. Water distribution canal
Earthwork excavation and filling 5625.0
Local concrete protective slope 42 m3 Protective slope at canal crotch
5. Stabilization pondEarthwork excavation and transportation 227500 m3
6. Air and water channelEarthwork excavation and transportation 60000 m3
7. Outflow rubber dam 2 SetEarthwork excavation 10000 m3
Earthwork backfilling 3000 m3
Backing concrete C10 150 m3
Concrete C25W6F150 3000 m3
Rebar fabrication and installation 140 tBase mat 700 m2
Dam bag 700 m2
Rubber sealing material, 651 type, and accessories 1 批
8. Soil biological works protective slope 5 km9. Vertical paving geomembrane 6.5 km
②Construction machinery
According organization and design for construction, the lake wall shall be constructed as a
key line, and the total construction period shall be controlled within 2 years; other works shall be
146
completed within the total construction period.
See Table 3.2-36 for the details of construction machinery.
Table 3.2-36 Main construction machineries
SN Name of machine Unit Quantity Remarks
Earthwork machines
Bulldozer (103 kW) Set 24
Cutter-suction dredger Set 6
Excavator (1 m3) Set 25
Tractor (74 kW) Set 15
Frog kick tamper Set 120
Concrete machines
Concrete mixer (0.8 m3) Set 15
Immersion vibrator Set 39
Transportation machines
Truck (5 t) 辆 26
Dump truck 辆 35
Diesel dumper 辆 45
Rubber wheel barrow 辆 10
auxiliary machines
Truck crane (5 t) Set 7
Diesel-engine generator Set 5
Submersible pump Set 202) Engineering proposal
(1) Process flow
See Figure 3.2-9 for process flow of biological transition zone artificial wetland
Being lifted from the original lift pumping station, the sewage from Main Trunk Canal, Trunk
Canal 8, and Trunk Canal 9 are sent into the time delay wetland system. The water canal from the
afterbay of Main Trunk Canal to the large lake can be used as sedimentation canal and be cleaned
up every 7 years, and aeration facilities shall be provided simultaneously. At the juncture between
the water canal and the large lake, 2 sets of rubber dams shall be provided, one of which is used for
controlling the sewage entering into the artificial wetland, and the other for temporary water release.
After flowing into the wetland, the sewage flows through the crossed zone of reed zone and pond
system (zone without reed and that excavated deeply); if necessary, aeration and oxygen increasing
measures may be taken (mainly for improving removal ratio of contamination in congelation period
of winter), so as to improve purification effects of wetland. After flowing through the circuitous
wetland passage, the sewage flows into the large lake from the juncture between the small lake and
large lake through 3 rubber dams, which bear 20%, 20%, and 60% of the outflow respectively. At
the outlet, a set of 30m3/s drainage pumping station shall be built up to reduce the wetland water
level and drain wetland sewage, so that reed yield can be improved on the one hand, and on the
other hand, after the sewage is drained, it will be advantageous for oxidization of the substrate 147
sediments, so as to improve the purification effects of wetland and reduce pollution release from the
substrate sludge. The outflow rubber dam, pump location, and water distribution shall be
determined by analog computation, and this will be more favorable for optimization of flow field.
For Trunk Canal 8 Wetland and Trunk Canal 9 Wetland, original lift pumping stations shall
also be utilized. After the afterbay is altered, the sewage shall flow into the wetland. For Trunk
Canal 8 Wetland, the outflow shall flow through a rubber dam and into the large lake, whereas for
Trunk Canal 9 Wetland, through 2 rubber dams and into the large lake (each bear the 50% of the
outflow respectively).
For the wetland, diversion dam shall be provided rationally according to water power
construction principles. The staying time of water shall be delayed as long as possible, and driving
flow type for the water flow shall be adopted; the wetland space shall be utilized, and the largest
purification function of wetland shall be carried out. In order to ensure growing up of reed, the
ventilation function of wetland shall be strengthened, and air and water channel in the wetland shall
be provided.
图中文字:排干退水 drainage of subsiding water
扬水泵站 lift pumping station
5-10年清泥 sludge removal for 5-10years
沉淀塘 sedimentation basin
芦苇带 reed zone
风能曝气 wind powered aeration
稳定塘 stabilization pond
出水位置和水量分配起到优化湖区动力条件作用 Outflow position and water
distribution shall optimize the power conditions in the lake area
148
海区缓冲带 buffer zone in the lake area
海区网格水道 grid water channel in the lake area
湖区 lake area
延时湿地系统 time delay wetland system
图中文字:反应机理 reaction mechanism
干沟排水 trunk canal drainage
生物过度带 biological transition zone
泥沙沉降 mud and sand sedimentation
植物吸收N、P plant absorption N, P
微生物降解 micro-biological degradation
植物吸收COD plant absorption COD
植物过滤 plant filtering
主海区 main lake area
Figure 3.2-9 Flow of artificial strengthening process in the wetland
149
Figure 3.2-10 Design for wetland works
(2) Original pumping station
For inflow of Main Trunk Canal Wetland, Trunk Canal 8 Wetland, and Trunk Canal 9, the
original Honggebo Lift Pumping Station (new), Trunk Canal 8 Lift Pumping Station (new), and
Trunk Canal 9 lift pumping station shall be adopted.
By model generalization of 3 wetlands and adopting MAKE 11 for analog computation, it is
obtained that the total water head loss from inlet to the outlet of Main Trunk Canal Wetland is less
than 30cm, the design water level of forebay of Honggebo Lift Pumping Station is 1017.5m, the
highest lift is 2.97m, the design lift is 2.19m, and the water level after lifting can reach 1019.69m.
Honggebo Lift Pumping Station can meet the inflow requirements of Main Trunk Canal Artificial
Wetland. The design lift of the lift pumping station of Trunk Canal 8 and Trunk Canal 9 is 4.8m and
4.7m respectively.
①Honggebo Lift Pumping Station (new)
See Table 3.2-37 for the operating characteristics of Honggebo Lift Pumping Station (new).Table 3.2-37 Operating characteristic of Honggebo Lift Pumping Station (new)
SN Name Unit Quantity Remarks
1Pump Set 6 2500ISKM diagonal flow type axial flow pump
Electric motor Set 6 TDXZ-630-36/2150
2 Transformer substation kv 35 S4-630/10
3 High voltage supply kv 6
4 Installed capacity km 3780
5 Design lift m 2.19
The highest lift m 2.97
150
The lowest lift m 1.6
6 Design flow rate m3/s 100
7 Design water level
Forebay water level m 1017.50
Afterbay water level m
②Trunk Canal 8 Lift Pumping Station (new)
See Table 3.2-38 for the operating characteristics of Trunk Canal 8 lift pumping station.Table 3.2-38 Operating characteristics of Trunk Canal 8 lift pumping station
SN Name Unit Quantity Remarks
1Pump Set 5 Type 700LB-125
Vertical electric motor Set 6 Y315-8, 90KW
2 Transformer Set 1 S4-630/10
3 Total installed capacity km 450
4 Design lift m 4.8
The highest lift m 4.9
The lowest lift m 1.1
5 Design flow rate m3/s 6.8
6 Design water level
Forebay water level m 1016.80
Afterbay water level m 1019.50
③Trunk Canal 9 Lift Pumping Station
See Table 3.2-39 for the operating characteristics of Trunk Canal 9 Lift Pumping Station.Table 3.2-39 operating characteristics of Trunk Canal 9 Lift Pumping Station
SN Name Unit Quantity Remarks
1Pump Set 8 Type 20ZLB-70
Electric motor Set 6 Y280M-6
2 Transformer Set 1 SJm560KV
3 Total installed capacity km 440
4 Lift\ m 4.7
5 Design flow rate m3/s 6.4
6 Design water level
Forebay water level m 1014.97
Afterbay water level m 1019.50
(3) Water distribution canal in Main Trunk Canal Wetland
For the water distribution canal Main Trunk Canal Wetland, the top width shall be 40m, water
depth shall be 1.5m, and gradient shall be 1:1 and length 1.3km. The high wall shall be precast
concrete block protective slope. An outlet shall be provided every 200m.
(4) Lake wall, box dam, and diversion dam
The lake wall between reed field and the large lake shall be reinforced on the basis of the
151
original lake wall, most of which has been 2.0-2.5m wide and 1019.0-1019.6m high, but some of
which has disappeared. The old wall to be reinforced is 22km long. On the basis of a normal lake
water level of 1018.5m, the lifted lake water level elevation shall be 1019.3m, and design lake wall
elevation is determined as per 1020.0; for the width, in consideration of stability in water and traffic
requirements, the top width shall be 5.0m, gradient 1:2.0, and height 2.5m. For the drainage
pumping station, soil biological works protective slope shall be adopted.
For the box dam between reed field in artificial wetland and external outside or the space,
reinforcement shall be carried out on the basis of the original dike; the top width shall be 5m,
gradient 1:2 and height 2.5m. At the place where water conditions are changed largely, soil
biological works protective slope shall be adopted.
When sewage flows from Reed Field 4 (Military Farm) to Reed Field 2, it shall be driven
along the large lake to the inner side, so a 4km dike shall be newly built in the large lake, and it will
form a passage for the flow with the original lake wall. The passage shall be 1000m wide and the
lake wall shall be 4.0m wide, and gradient 1:2.0 and height 2.5m.
For the diversion dam in reed field, the top width shall be 2.0m, gradient 1:2, and height 2m.
At the place where water conditions are changed largely, precast concrete block protective slope
shall be adopted.
(5) Vertical paving geomembrane
Between the box dam of artificial wetland and external outside or the space, vertical paving
geomembrane method shall be adopted for anti-seepage, and the buried depth shall be 8m. The
geomembrane shall be paved along the outside of box dam of Main Trunk Canal Wetland, and that
of Trunk Canal 8 Wetland and Trunk Canal 9 Wetland.
(6) Air and water channel
Air and water channel shall be provided for reed field. The top width shall be 20m, and
excavation depth 1m and gradient 1:1. The purpose of air and water channel shall mainly be
increase ventilation, and this is favorable for growing up of reed.
(7) Pond series
When reed field box dam, lake wall, and diversion dam are used in construction, the space or
water ditch formed by earthwork excavation or the original space in reed field shall be used as
stabilization pond system in wetland, and the earthwork excavation depth shall be controlled within
about 1m; the total volume of the pond is equal to the volume of earthwork required by the
structures, such as box dam, diversion dam, and lake wall, and the total is about 1,670,000m 3. The
earthwork shall be leveled up within the construction site and not transported to outside.
(8) Aeration pond
For aeration pond, water canal from the afterbay of Main Trunk Canal Lift Pumping Station to
the large lake, and hose and micropore shall be adopted for aeration. The hose shall be 4km long,
152
and there shall be 20 air compressors.
(9) Alteration of afterbay of Trunk Canal 8 and Trunk Canal 9 Lift Pumping Station
The current afterbay of Trunk Canal 8 and 9 shall be altered. According to the highest daily
water displacement, it is designed that the outflow rate is 0.6m/s, and there are 2 outflow sluices, for
each of which there are 2 sluice board of 1.5m width.
(10) Main Trunk Canal Wetland Drainage Pumping Station
Main Trunk Canal Wetland Lift Pumping Station is at the end of Main Trunk Canal Wetland,
and the design drainage flow rate is 30m3/s.
The inflow part of the pumping station is composed of diversion canal, intake sluice (also as
trash screen), forebay, and receiving basin. The forebay shall be in open style, similar to a rectangle,
inflow in forward direction, and 25m long; for side wall, RC cantilever type retaining wall shall be
adopted. In front of the intake sluice, cement laid stone masonry shall be adopted for covering. The
receiving basin of pumping station shall be in rectangle style, the length in downstream flow
direction shall be 10m; for the side wall, RC cantilever type wing wall shall be adopted. The intake
sluice shall be in open style, and the top elevation of sluice bottom board 1019.00m. There are
totally 4 sluice openings, for each of which, the net width shall be 5m. The length in downstream
flow direction of the sluice chamber shall be 9m. For the front section, 4 control gates shall be
provided, and for the rear section, 4 tilting trash screens be provided. Over the sluice, temporary
bridge and starting up and shutdown machine room shall be provided.
The pump chamber shall be behind the dam and be wet type. The upper part shall be in RC
framed structure, and the lower part RC pier wall structure. The top elevation of bottom board of
the pump chamber shall be 1011.65m, the length in downstream flow direction 12m, and vertical
23.4m. The auxiliary plant shall be arranged beside the lower reach of the main pump room, and in
parallel with the later.
The outflow part of the pumping station shall be composed of afterbay, an access bridge across
the dam, and exit channel. In which, the afterbay shall be in RC structure, and the length in
downstream flow direction shall be 16.6m. There are totally 3 openings for the access bridge, and
the net width of each opening shall be 4.2m; the bottom elevation shall be 1015.80m, and the length
in downstream flow direction shall be 5m; the exit channel shall be 15m long. The side wall shall be
RC cantilever type retaining wall, and spread section shall be connected to the exit channel.
In the station, 6 sets of vertical axial flow pump shall be installed, in which 5 sets shall be used
and 1 for standby. The type of axial flow pump shall be Zl5650-8, and the flow rate of single unit
6.00 m3/s. For each pump, 1 set of 6KV and 400kW vertical synchronous motor of type TL400-16-
××× shall be provided, of which the installed capacity shall be 2000 KW.
For the intake sluice, 4X5mX3m plane fixed steel gate shall be provided.
(11) Rubber dam
153
For Main Trunk Canal Wetland, 3 outflow rubber dams shall be provided, which shall bear
20%, 20%, and 60% of the outflow. At the juncture between Honggebo Lift Pumping Station and
the large lake, 2 rubber dams shall be provided; the one shall be used for controlling water entering
into the artificial wetland, of which the water flow rate shall be 29m2/sec, and the other shall be
drained directly into the large lake, and the water flow rate through rubber dam shall be 100m2/sec.
For drainage of Trunk Canal 8 Wetland, one rubber dam shall be provided; for drainage of Trunk
Canal 9, 2 rubber dams shall be provided, which shall bear 50% of the flow rate respectively.
After flowing through the artificial wetland, some of the sewage volume shall be lost due to
the evaporation of plant in the wetland and that from water surface. According to the reed
evaporation data from Zhalong Wetland Administration, the annual reed evaporation volume is
390mm; in consideration of evaporation from water surface and downward seepage, it is estimated
that the water volume loss is up to 20%.
According to the calculation of water volume, the design flow rate of the 3 outflow rubber dam
of Main Trunk Canal Wetland is 4.6m3/s, 4.6 m3/s, and 13.8 m3/s respectively; for the 2 rubber dams
at the juncture between Honggebo Lift Pumping Station and the large lake, the design flow rate into
the rubber dam is 29 m3/s and that into the large lake is 100 m3/s; for the 1 drainage rubber dam of
Trunk Canal 8 Wetland, the design flow rate is 3.9 m3/s, and for the 2 drainage rubber dams of
Trunk Canal 9 Wetland, the design flow rate is 1.55 m3/s. See Table 3.2-40 for the main parameters.Table 3.2-40 Main parameters of the rubber dams
Name Design
flow rate(m3/s)
Dam bag drainage mode
Dam height (m)
Dam length (m)
Outflow rubber dam of Main Trunk Canal Wetland
Dam 1 11.10 Drainage with dam bag filled 1.50 120.0
Dam 2 3.70 Drainage with dam bag filled 1.50 40.0
Dam 3 3.70 Drainage with dam bag filled 1.50 40.0
Rubber dam at juncture between Honggebo Lift Pumping Station and the large lake
Dam 1 100.00 Drainage with dam bag filled 2.00 90.0
Dam 2 29.00 Drainage with dam bag filled 2.00 30.0
Drainage rubber dam of Trunk Canal 8 Wetland Dam 1 3.90 Drainage with dam bag filled 1.50 40.0
Drainage rubber dam of Trunk Canal 9 WetlandDam 1 1.55 Drainage with
dam bag filled 1.50 20.0
Dam 2 1.55 Drainage with dam bag filled 1.50 20.0
3.3 Pollution source analysis3.3.1 Sub-project of reclaimed water supply3.3.1.1 Reclaimed water treating process and pollution factors analysis
Treating processes of reclaimed water supply projects are different because of water quality of
their sources. Except for the project of Urat Rear Banner Manufacture Park where raw water is only
154
treated by disinfection, the other projects add relative process units like the pre-aeration tank and
the RO workshop based on conventional treatment such as coagulation, sedimentation and filtration
to guarantee quality of reclaimed water. Refer to Fig. 3.3-1 for treating process of reclaimed water
and discharge nodes.
Main positions generating and discharging pollutants during construction and operation of the
project:
Construction period
The construction duration of this project is 4 year long, land and vegetation at site will be
occupied and impacted, local ecological environment will be destroyed. In addition to plenty of
excavation and filling, noise, dust emission and spoil, ambient environment will be impacted.
(1) Construction noise
Construction machinery including the excavator, crane, electric saw, electric welding machine,
mixer and vehicles with sound source level 90-110dB (A) may impact sensitive objects around the
site.
(2) Construction dust emission
Ambient air pollutant during construction is mainly dust emission from pipeline excavation,
backfill, and building construction of the plant.
Since the site for pipeline construction is long and decentralized, if the weather is dry and
windy, dust emission may impact sensitive objects around.
Construction waste water consists of sewage generated by the builders and production waste
water from concrete mixing, earthwork spray, construction machinery oil leakage and cleaning, etc.
(4) Solid waste
Solid waste includes domestic garbage, building garbage and spoil.
(5) Land procurement and relocation
The permanent floor area of all reclaimed water engineerings in this project is 317.55mou
totally (including the plants and pipelines), most currently used lands are undeveloped slopes in
addition to some farmlands, and reserved expanding lands. The farmlands occupied by this project
will lose the function of agricultural production completely, landscape there will be impacted during
certain period, and vegetation on the temporary occupied lands for this project will be destroyed
too, so local agricultural production will be impacted.
(6) Ecological environment
Land area vegetation is damaged by construction of the plant, pipeline laying and the
earthwork yard, in addition to soil erosion caused by construction.
(7) Social environment
Pipeline construction impacts people’s trip; transportation of materials and earthwork increases
vehicle flowrate thereby impacts traffic.
155
Fig. 3.3-1 Process flow and discharge nodes of the plant
156
Operation period:
(1) Waste gas
Waste gases of the reclaimed water supply project are chlorine dioxide G1 leaked from the
chlorine dioxide generator that runs with fault; and fugitive emission odor G2 from the sludge pump
house, the sludge thickener, sludge dewaterer house and the sludge yard;
In addition, the plant with pre-aeration process includes odor gas G3 from the pre-aeration
unit.
(2) Waste water
Waste water of the planned project during operation comes from the reaction sedimentation
tank for sludge thickening W1, filter backwashing W2, sludge dewatering and filter pressing W3
and sewage, containing main pollutants such as SS, CODcr and BOD5.
Otherwise, the plants with RO process also include saline tail water W4.
(3) Solid waste
Sludge S1 is generated by the flocculating tank, sedimentation, filtration sand cylinder,
automatic valveless gravity filter and so on. Furthermore, a little domestic garbage.
(4) Noise
Noise comes from the intake pump house N1, intermediate lift pump house N2, back wash
pump house N3, blower house N4, sludge pump house N5 and sludge dewaterer house N6.
3.3.1.2 Pollution source analysis for the project
According to intake water quality of the project, dosage, and the principle of material balance,
confirm pollution source intensity of each engineering.
(1) Waste gas pollution source intensity
H2S and NH3 are used as the characteristic pollutants of waste gas for environmental
assessment of odor from the plant. The analogy method is used to determine fugitive emission odor
pollution source intensity of each engineering, odor emission coefficient of each treating unit can be
characterized by emission in unit duration and on unit area. Based on data of Tianjin Jizhuangzi
WWTP, Hangzhou Sipu WWTP and Stage I of Shenzhen Baoan Gushu WWTP, determine odorant
emission coefficient of each plant in this project, refer to Table 3.3-1. Waste gas source intensity
can be estimated according to surface area of designed structures. The feasibility study report does
not provide any deodorizing measures, so the bio-deodorization method is recommended to treat
main odor pollution source. Refer to Table 3.3-2 for generation of odor pollution source and
emission intensity of each plant.
Table 3.3-1 Emission coefficient of odor pollutant on unit area of structures at the plantStructure NH3(mg/s.m2) H2S(mg/s.m2)
Coarse grille and intake pump house, thin grille and aeration sand tank 0.30 1.39×10-3
Sludge tank, sludge bin and sludge thickening and dewatering house 0.10 7.12×10-3
Table 3.3-2 Odor pollution source intensity of treating structures at each plant
No. Project Structure Are
a
Output of odor pollution source Measures for
deodorization
Efficiency of
deodorization
Emission of odor pollution source
NH3 H2S NH3 H2Smg/
s kg/h mg/s kg/h mg/
s kg/h mg/s kg/h
1
Reclaimed water supply
project of Drainage Canal 3
Pre-aeration
tank
——
——
——
——
——
Bio-deodorization
method
50~70%(take 50%)
——
—— —— —
—
Sludge tank,
sludge bin,
sludge thickenin
g and dewatering house
264 19.2 0.069 6.4 0.02
3 9.6 0.035 3.2 0.01
2
2
Reclaimed water supply
project of Drainage Canal 7
Pre-aeration
tank
——
——
——
——
——
——
—— —— —
—
Sludge tank,
sludge bin,
sludge thickenin
g and dewatering house
264 19.2 0.069 6.4 0.02
3 9.6 0.035 3.2 0.01
2
3
Reclaimed water supply
project of Ganqimao
du port manufactu
re park
Pre-aeration
tank570 171.
0 0.62 57.0 0.21 85.
5 0.31 28.5 0.11
Sludge tank,
sludge bin,
sludge thickenin
g and dewatering house
252 15.6 0.056 5.2 0.01
9 7.8 0.028
2.6
0.009
(2) Water pollution source intensity
Tail water of each reclaimed water plant (sludge water) mainly comes from the sedimentation.
For sustainable development of water resource, the measures of waste water recovery is adopted at
the clean water plant, sludge from the flocculation sedimentation is thickened at the thickener,
supernatant flows to the front end distribution well for recovery; at the same time, waste water from
sludge press filtration returns to the front end distribution well, which may not only reduce water
consumption in the plant, but also mitigate pollution to environment around by the plant for no
production waste water drain.
Because SS is the main pollutant in waste water from supernatant of the thickener and sludge
dewatering, which is smaller to compare with total water quantity of the plant, no impact to outlet
water quality, it is available for reusing.
According to the principle of material balance and analogy among similar enterprises, refer to
Table 3.3-3 for waste water quantity and water quality of reaction sedimentation tank for sludge
thickening waste water,filter backwashing waste water and sludge dewatering waste water.
Sewage from the planned project is calculated as 150L per capita, sewage discharge percentage
is 80%. Refer to Table 3.3-3 for details of producing and discharge.
Table 3.3-3 Production waste water quantity and quality of each reclaimed water plant
No. Project Coding Waste water name Discharge (m3/h)
Discharge feature of pollutantsDestination of discharge RemarkPollut
antConcentration (mg/L)
Output (kg/h)
1 Reclaimed water supply project of Urat Rear Banner Manufacture Park Sewage 0.13
COD 300 0.039To WWTPSS 200 0.026
NH3-N 35 0.005TP 5 0.0007PH 6-9 ——
2 Reclaimed water supply project of Drainage Canal 3
W1 Reaction sedimentation tank for sludge thickening waste water 1.61
COD 188.4 0.30 To the front distribution well after the thickenerSS 70 0.11
PH 7-9
W2 Filter backwashing waste water 20.25COD 69.4 1.41 To the front distribution well after
sedimentationSS 60 1.22PH 7-9
W3 Sludge press filtration waste water 0.71
COD 262.6 0.19 To the front distribution well after sedimentationSS 200 0.14
PH 7-9
W4 Tail water of ultrafiltration RO 416.7COD 67.1 27.96 To the front distribution well after
Coagulation and sedimentationSS 10 4.17PH 7-9
Sewage 0.07
COD 300 0.021
To Hangjinhouqi WWTPSS 200 0.014
NH3-N 35 0.0025TP 5 0.00035PH 6-9
3 Reclaimed water supply project of Drainage Canal 7 W1 Reaction sedimentation tank for
sludge thickening waste water 2.42COD 220.6 0.53 To the front distribution well after
the thickenerSS 70 0.17PH 7-9
W2 Filter backwashing waste water 20.25COD 122 2.47 To the front distribution well after
sedimentationSS 60 1.22PH 7-9
W3 Sludge press filtration waste water 1.06
COD 308.4 0.33 To the front distribution well after sedimentationSS 200 0.21
PH 7-9
W4 Tail water of ultrafiltration RO 416.7COD 67.1 27.96 To the front distribution well after
Coagulation and sedimentationSS 10 4.17PH 7-9
Sewage 0.07 COD 400 0.028 To Wuyuan WWTPSS 200 0.014
NH3-N 35 0.0025TP 5 0.0004
PH 6-9
4 Reclaimed water supply project of Ganqimaodu Port Manufacture Park
W1 Reaction sedimentation tank for sludge thickening waste water 3.94
COD 168.2 0.66 To the front distribution well after the thickenerSS 70 0.28
PH 7-9
W2 Filter backwashing waste water 50.4COD 60.9 3.07 To the front distribution well after
sedimentationSS 60 3.02PH 7-9
W3 Sludge press filtration waste water 1.68
COD 242.4 0.41 To the front distribution well after sedimentationSS 200 0.34
PH 7-9
W4 Tail water of ultrafiltration RO 591.67COD 44 26.03 To the front distribution well after
Coagulation and sedimentationSS 8 4.73PH 7-9
Sewage 0.15
COD 400 0.06
Septic tankSS 200 0.03
NH3-N 35 0.0053TP 5 0.00075PH 6-9
(3) Noise pollution source intensity
Noise of this project comes from various pumps (including the intake pump,
rinse pump and lift pump), blower, sludge dewaterer and so on, and noise of
mechanical, friction, impacting and so on during their operation, typically noise level
is about 95dB (A), and the wall may stop more than 10~20dB (A). Refer to Table 3.3-
4 for main noise source and source intensity.
Table 3.3-4 Main noise source and source intensity of each plant
No.Main noise
sourcesQty.
Noise level
(single machine)
dB(A)
Workshop
(section)
Measures of
noise reduction
Effect of noise
reduction
1 Intake pump N1 6 95Intake pump
house
Measures such
as silencing,
damping, indoor
sound insulation
and so on.
Noise reduction
25dB(A)
2 Line lift pump N2 4 95 Lift pump houseNoise reduction
25dB(A)
3Filter back wash
pump N32 95 Back wash
comprehensive
house
Noise reduction
25dB(A)
4Filter back wash
blower N42 110
Noise reduction
25dB(A)
5 Sludge pump N5 2 95 Sludge
dewatering
house
Noise reduction
25dB(A)
6Dewatering house
press filter N62 90
Noise reduction
25dB(A)
(4) Solid waste
In order to protect surface water bodies and use water resource reasonably, it is
necessary to separate solid and liquid of sludge water during operation of the plant.
Sludge water drained from the sedimentation should be collected in the balancing
tank, and then transport sludge after thickening and dewatering. Filter back wash
waste water is drained to the waste water tank and lifted to the front end for reusing
by the pump. Solid waste from each plant of the project is mainly sludge after
thickening and dewatering and domestic garbage. Sludge quantity of the reclaimed
water project is calculated according to SS concentration of inlet water and
consumption of flocculant. Sludge is treated by centrifugal dewatering with water
content 75%. Since there is no hazard chemicals, no poison, which may be used as
cover soil of landfills, backfill soil of municipal road construction and brickmaking.
While domestic garbage from the reclaimed water supply projects is calculated as
1.16kg/d·person, which should be collected and delivered to the environmental
sanitation administrations. Refer to Table 3.3-5 for solid waste of each reclaimed
water supply project.
Table 3.3-5 Solid waste of each reclaimed water supply project
No
.Project
Solid
waste
Outpu
t (t/a)
Compositions
and
characters
Water
content(%
)
Comprehensive
utilization and
quantity (t/a)
Treatment and
quantity (t/a)
1
Reclaimed
water supply
project of
Urat Rear
Banner
Manufacture
Park
Sludge3066.
0
Solid-liquid,
innocuity75.0
To the solid
waste treatment
center of Urat
Rear Banner
Manufacture
Park
——
Domesti
c
garbage
10.59Solid,
innocuity—— ——
Clean and
landfill by the
environmental
sanitation
administration
2
Reclaimed
water supply
project of
Drainage
Canal 3
Sludge339.8
8
Solid-liquid,
innocuity75.0
To the solid
waste treatment
center of
Hangjin Rear
Banner
Manufacture
Park
——
Domesti
c
garbage
5.93Solid,
innocuity—— ——
Clean and
landfill by the
environmental
sanitation
administration
3 Reclaimed
water supply
project of
Drainage
Canal 7
Sludge573.4
8
Solid-liquid,
innocuity75.0
To the solid
waste treatment
center of
Wuyuan
Manufacture
Park
——
Domesti
c
5.93 Solid,
innocuity
—— —— Clean and
landfill by the
garbage
environmental
sanitation
administration
4
Reclaimed
water supply
project of
Ganqimaodu
Port
Manufacture
Park
Sludge621.3
6
Solid-liquid,
innocuity75.0
To the solid
waste treatment
center of
Ganqimaodu
Port
Manufacture
Park
——
Domesti
c
garbage
12.7Solid,
innocuity—— ——
Clean and
landfill by the
environmental
sanitation
administration
3.3.2 Waste water treatment and reclamation projects in the
manufacture park3.3.2.2 Analysis of waste water treatment and reclaimed processing and pollution
factors
The secondary waste water treatment processing in each waste water treatment
and reclamation project adopts A/A/0, and reclaimed water treatment processing
adopts coagulation – sedimentation – filtration. Refer to Fig. 3.2-3 for waste water
treatment and reclamation processing.
Pollution factors during construction and operation of the waste water treatment
and reclamation project is similar with the reclaimed water supply project, refer to
Section 3.3.1.2.
3.3.2.3 Pollution source analysis of the waste water treatment and reclamation
project
(1) Odor pollution source
During operating of the WWTP, odor pollutants are generated by metabolism of
organism such as the microorganism, protozoan and zoogloea, main compositions are
H2S and NH3, the main emission sources are the grille house, the water intake pump
house, the rotational flow grit chamber, bio-reaction tank and sludge treatment
structures.
The bio-deodorization method is recommended for each waste water treatment
and reclamation engineering in this project, which may collect and exhaust odor from
the grille house, the intake water house, the rotational flow grit chamber and the
sludge treatment structures, in this evaluation, it is considered as the point source.
Because the bio-reaction tank of each WWTP has large area and large air quantity
during aeration, odor is hard to collection, it is considered as the area source in this
evaluation.
Since there is no systematic public data for estimation odor output of a WWTP in
China, the analogy method is used to determine odor source intensity here.
① Point source intensity
Shanghai Longhua WWTP has similar waste water source with WWTPs here,
where CAST bio-treatment processing is used with actual treatment quantity of 80,
000t/d.
Shanghai Environmental Science Institute measured strongest odor sources of
Hualong WWTP in 2002-2004 for many times, for example the sludge thickener, the
sludge yard and the grille well. Refer to Table 3.3-6 for the results of odor monitoring.
Table 3.3-6 Odor source intensity monitoring results at Longhua WWTP
Item
Sludge thickener and dewatering
house
(Strongest odor source)
Grille well
(Pre-treatment area)
H2S
(mg/m3)
Max. 0.35 0.046
Average 0.27 0.024
NH3
(mg/m3)
Max. 5.98 0.134
Average 3.01 0.108
Since odor emission of WWTPs is not stable, which depends on many factors
such as climate and weather conditions. In view of conservative engineering, the Max.
monitoring values are used for analogy in this environmental assessment, refer to
Table 3.3-7 for odor source intensity of each WWTP.
Table 3.3-7 Result of odor pollutant analogy
Item
Sludge thickener and
dewatering house
(Strongest odor source)
Grille well
(Pre-treatment
area)
Waste water treatment and
reclamation project of Urat
Rear Banner Manufacture
Park (Huhe Town)
H2S(mg/m3) 0.09 0.012
NH3(mg/m3) 1.50 0.034
Waste water treatment
project of Urat Front Banner
Manufacture Park (Xianfeng
Town)
H2S(mg/m3) 0.13 0.017
NH3(mg/m3) 2.21 0.05
Waste water treatment and
reclamation project of
Ganqimaodu Port
Manufacture Park
(Delingshan Town)
H2S(mg/m3) 0.13 0.017
NH3(mg/m3) 2.21 0.05
Odor from pollution sources of each WWTP will be collected and sent to the bio-
filter at the deodorization room and then exhausted through the exhaust mast.
Efficiency of bio-deodorization is about 90%, design blower air delivery of each
WWTP is 4500m3/h. After bio-deodorization, refer to Table 3.3-8 for odor exhaust
rate of each WWTP.
Table 3.3-8 Odor exhaust rate
Item Exhaust rate (kg/h)
Waste water treatment project of Urat Rear Banner
Manufacture Park (Huhe Town)
H2S 0.10×10-3
NH3 1.53×10-3
Waste water treatment project of Urat Front Banner
Manufacture Park
H2S 0.15×10-3
NH3 2.26×10-3
Waste water treatment and reclamation project of
Ganqimaodu Port Manufacture Park (Delingshan Town)
H2S 0.15×10-3
NH3 2.26×10-3
② Area source intensity
According to relative source intensity data of Fuzhou Yangli WWTP
(5×104m3/d), in consideration of intake water quality of the WWTP, because NH3-N
balance relation in water forms non-ion free ammonia, estimate free ammonia
concentration in the bio-aeration system and possible in-air NH3 in various pH and
water temperature in the gross, and refer to Table 3.3-9 for average NH3 exhaust
quantity of the bio-aeration system.
Table 3.3-9 Estimation of NH3 exhaust quantity of the aeration tank system
PHWater
temperature
Original waste water free
ammonia concentration mg/L
NH3 blow-off
(Gas-water ratio 6.19) (mg/L)
Bio-aeration system average NH3
exhaust quantity (mg/s)
℃Not consider
nitrification
Consider
nitrificationWaste water quantity 5×104t/d
730 0.14 0.11 0.03 8.7
5 0.06 0.02 0.01 2.9
830 2.24 0.179 0.054 15.7
5 0.28 0.06 0.02 5.8
Based on relative experts’ experience, exhaust intensity of H2S can be estimated
in the gross as about 10% of exhaust intensity of NH3. In view of conservative
engineering, the Max. monitoring values are used for analogy in this environmental
assessment, refer to Table 3.3-10 for odor source intensity of bio-aeration tank at each
WWTP.
Table 3.3-10 Odor exhaust rate
Item Exhaust rate (kg/h)
Waste water treatment and reclamation project of Urat Rear
Banner Manufacture Park (Huhe Town)
H2S 2.26×10-3
NH3 2.26×10-2
Waste water treatment project of Urat Front Banner
Manufacture Park
H2S 3.39×10-3
NH3 3.39×10-2
Waste water treatment and reclamation project of
Ganqimaodu Port Manufacture Park (Delingshan Town)
H2S 3.39×10-3
NH3 3.39×10-2
(2) Water pollution source
No waste water drain outside in each WWTP of this project, waste water will be
treated further and then used for production and planting in the parks. According to
discharge nodes analysis of each WWTP, main nodes producing water are sludge
thickening and dewatering, filter backwashing, sewage and equipment cleaning. Refer
to Table 3.3-11 for quantity of waste water.
Table 3.3-11 Waste water output (m3/a)
Item
Type
Urat Rear
Banner
Ganqimaodu
Port
Urat front
bannerFinal treatment
Sludge dewater 15×103 22.5×103 22.5×103Return to the front end of the
WWTP
Backwash -- 14.6×103 14.6×103Return to the front end of the
WWTP
Sewage 2100 2100 1140Return to the front end of the
WWTP
Cleaning 730 730 730Return to the front end of the
WWTP
(3) Solid wastes
When the project starts operation, solid wastes mainly are the grille dreg, grit
chamber sludge, excess sludge and domestic garbage.
① Grille dreg and sand
Most fine grille dregs are blocky solid materials, including both inorganic and
organic substances, like domestic garbage. Stop diameter of a fine grille is substances
with diameter more than 6mm; while grit is inorganic particles, such as argillaceous
silt and carpolite. The rotational flow grit chamber removes oily substances and sand
particles with specific gravity more than 2.65 and grain size more than 0.22mm
mainly.
According to Code of outdoor drainage design, grit quantity of urban waste
water can be calculated as 0.03kg/m3, while quantity of grille dreg can be calculated
as 0.1 kg/m3, refer to Table 3.3-12 for the output.
Treatment of dreg and grit is performed by the grille machine, the belt conveyor,
and the presser, which may avoid odor emission and vermination. After treatment,
they can be landfilled as urban garbage.
② Sludge
Excess sludge in the sludge tank will be lifted to the combined thickening and
dewatering machine with 0.5% high molecular organic flocculant PAM. Water
content of sludge after dewatering should be less than 80%, refer to Table 3.3-12 for
dewatering sludge quantity.
③ Domestic garbage
According to the Stat. data of Bayannur garbage station, average garbage output
per day per capita is about 0.8kg/d, it is reduced by half for employees. So garbage
quantity can be calculation by employees during operation of each plant. Refer to
Table 3.3-12 for details.
By calculation, refer to Table 3.3-12 for solid waste output of each waste water
treatment and reclamation plant.
Table 3.3-12 Main solid waste output of each plant (t/a)
Item
Type
Urat Rear
BannerGanqimaodu Port
Urat front
bannerFinal treatment
Grille dreg and
grit949 1265 1265 To the landfill
Sludge 1155 1576 1576 To the landfill
Sewage 3 5 5 To the landfill
Total 2107 2846 2846
(4) Noise pollution source
Noise sources of all waste water treatment and reclamation plants during
operation are same basically, main noise source comes from the pump house, the
sludge thickening and dewatering equipments, and the blower house. Refer to Table
3.3-13 for equipment quantity and noise values of equipments.
Table 3.3-13 Main equipments with high noise at the plant
Section Equipment with high noise Near-field sound level dB(A)
Water intake pump house Waste water pump 90-95
CAST tank or CASS tankReflux sludge pump 85-90
Excess sludge pump 80-85
Blower house Centrifugal blower 100-105
Sludge thickening and dewatering
house
Sludge thickening and dewatering
machine90-100
Flushing pump 90
Dosing pump 90
Deodorization roomBlower house 100-105
Flushing pump 90
3.3.3 Project of Wuliangsu Lake area comprehensive treatment 3.3.3.1 Pollution factor analysis of Wuliangsu Lake area comprehensive
treatment
Portions producing and discharge pollutants of Wuliangsu Lake area
comprehensive treatment sub-projects:
Construction period:
(1) Waste gas
Vehicle tail gas, odor from lake area network waterway dredge and bed mud
stacking (H2S and NH3), and dust emission.
(2) Waste water
Construction sewage; water pollutants from dredging of Wuliangsu Lake
network waterway, which may impact water quality of the lake, in addition, certain
waste water will be produced during bed mud transportation and stacking.
(3) Solid waste
Lake area pastoral network waterway bed mud.
(4) Noise
Noise is emitted by the construction vehicles and machinery.
(5) Land procurement and relocation
Permanent floor area of the project is 7345.5ha, where the current lands are fish
ponds, reed land and wild slope now.
Operation period:
Pollution factors during operation are mainly from operation of the Wuliangsu
Lake artificial wetland.
(1) Waste water
(2) Noise
Noise mainly comes from the artificial wetland pump station with noise source
intensity 80dB(A).
(3) Solid waste
Main solid wastes during operation of the artificial wetland are sludge in the
sedimentation pond, which will be dredged about every 7-10 years, transporting
outside to avoid secondary pollution.
3.3.3.2 Pollution source and main pollutants discharge analysis
Refer to Chapter 5 of this report for pollution sources and pollutants discharge
during construction of the project of Wuliangsu Lake area comprehensive treatment.
Main environmental impact during operation of the project of Wuliangsu Lake
area comprehensive treatment is pollution source discharge of Wuliangsu Lake area
artificial wetland.
1) Noise
Noise during operation comes from the pump station and the aeration pond
mainly. Refer to Table 3.3-14 for noise source intensity.
2) Solid wastes
Solid waste during operation of the artificial wetland is mainly sludge in the
sedimentation pond, which will be dredged about every 7-10 years; in addition,
people for management and maintenance of the wetland will produce domestic
garbage.
3) Pollution source intensity analysis
Refer to Table 3.3-14 for producing and estimated discharge of main pollutants
of the project of Wuliangsu Lake area comprehensive treatment.
Table 3.3-14 Producing and discharge of main pollutants of the project
TypeEmission
sourceMain
pollutant
Concentration and quantity
before treatment
(Unit)
Remedy
Noise
Mixed-flow
pump
Equipment
noise90-100dB (A) Sound insulation and damping
Air compressorEquipment
noise90-100dB(A)
Sound insulation, silencing and
damping
Solid
waste
Stabilization
pond and
sedimentation
pond
Bed mudDredging every 5
years
Use as fertilizer or send to the
landfill
Domestic
garbag
e
Domestic
ga
rb
ag
e
6.4 t/aDeliver to the environmental sanitation
administration to the landfill
3.4 Relative projects
Recently, in order to improve aquatic environment quality in Bayannur,
especially Wuliangsu Lake, aquatic environment treatment is reinforced continuously.
A batch of water pollution control projects is planned and constructed according to
relative water pollution control plans.
By now, there are 7 planned and constructed urban waste water treatment facilities, 1
rebuilding project in Bayannur during “The eleventh plan” with total investment
RMB960,000,000. Refer to Table 3.4-1 for planned and constructed WWTPs in
Bayannur.
Table 3.4-1 Planned and constructed WWTPs
ProjectConstruction
size
Investment
(Ten
thousands)
Construction unit Construction situation
Rebuilding of
Linhe WWTP100,000t/d
1795 for
rebuildingCity water authority
The project has been
finished, now for test run
Urat Front
Banner WWTP
20,000t/d in
Stage I8900
Baotou Hongdetai
Environmental Engineering
Development Company
Main part has been
finished, now for
equipment installation
Wuyuan
WWTP22,000t/d 8200
Hongzhu Environmental
Protection Waste Water
Treatment Co., Ltd.
Main part has been
finished, now for
equipment installation
Urat Middle
Banner WWTP10.000t/d 3000
Urban Construction
Investment Co., Ltd.Now start construction
Urat Rear
Banner WWTP10,000t/d 4400 Banner water authority Now start construction
Dengkou
WWTP30,000t/d 12000
Inner Mongolia Yujie Bio-
tech Co., Ltd.
Main part has been
finished, now for
equipment installation
Hangjin Rear
Banner WWTP20,000t/d
9000 for Stage
I
Hanghou Yiyuan Water Co.,
Ltd.Test run
Lihe No. 2
WWTP100,000t/d —— City water authority
Preparation has been
finished, now for
commencement
1) Rebuilding of WWTPs in Bayannur.
Lihe WWTP locates the north side of Xinhua Dong Street, Linhe City. The plant
came into being in May 2000 with the processing of oxidation pond, there are three
oxidation ponds designed. Since 2002, its treating capacity has been 100,000t/d. Now,
it treats sewage and industrial waste water from Linhe urban area 53,000t/d, serves
32km2, 300,000 population, and total waste water treatment quantity is 19,300,000t/a.
In 2008, Hetao Water Company rebuild this WWTP with total investment
RMB17,850,000. Now the rebuilding has been finished for test run. The rebuilding
engineering separates the inlet system of the WWTP into two parts: the rebuilding
engineering system treats industrial waste water of the park and then discharge in
compliance with the standard; the power plant reclaimed water system treats sewage
from the urban area, which should meet requirement of thermal power plant inlet
water quality. After technological transformation, industrial waste water and sewage
split flow is realized, which may be treated respectively. By this way, treating
capacity and efficiency of the WWTP is improved, and outlet water can meet
requirement of relative codes stably.
2) Dengkou WWTP
Total planned investment of the project is RMB120,000,000, where, investment
for WWTP construction is RMB56,000,000, and for pipeline construction is
RMB64,780,000. Now main parts of the project such as the office building, the
employees living building, relative waste water treatment facilities are finished,
equipment installation has been finished, the project has been complete and put into
service.
Construction size of Dengkou WWTP is 30,000t/d. The plant adopts advanced
“Mobile bed biofilm” processing is used there, which has not only advantages of
traditional biofilm such as impact resistance, long sludge age and less excess sludge,
but also advantage of active sludge such as high efficiency and free operation. The
sludge concentration can reach 30~40g/L with little head loss, no blockage, not need
back wash and reflux. In addition, it can remove P and N well. Construction of the
WWTP can meet requirement of waste water treatment at Dengkou county now and in
future, change the history that production waste water and sewage drain to Yellow
River at Dengkou county, so water quality in Yellow River can be improved
effectively, and drinking water safety and cleaning downstream can be guaranteed.
3) Wuyuan WWTP
The construction size of Wuyuan WWTP is 22,000t/d with total investment of
RMB82,000,000. Now all civil works have been finished, in addition to 95%
equipment installation. It will be put into service on September 15, 2010.
The WWTP adopt advanced Germany BIOLAK’s processing, which uses low
load active sludge processing to make a wave type mixing oxidation effect by a
mobile aeration chain, thereby create good habitat for all special microorganism with
good effect of N and P removal. Construction of this WWTP enables sewage and part
industrial waste water in Wuyuan to drain directly in compliance with national codes,
or reusing to saving water resource.
4) Hangjin Rear Banner WWTP
The construction of Hangjin Rear Banner WWTP is 20,000t/d for Stage I, and
50,000t/d for Stage II. Total investment is RMB120,000,000, and RMB89,000,000 for
Stage I, where, RMB32,000,000 for construction of WWTP, and RMB57,000,000 for
pipeline. Now, the project has been complete, all equipments are installed, all
pipelines are laid, road surface hardening and plant area afforestation are finished too.
The project starts test running and will be put into service in October 2010.
The WWTP uses the advanced Germany BIOLAK’s processing too, with outlet
water quality in Grade 1, B, which can be used for urban planting, farmland irrigation
and industry after further reclamation treatment.
5) Urat Front Banner WWTP
The construction size of Urat Front Banner WWTP Stage I is 20,000t/d with total
investment RMB85,500,000, where RMB39,850,000 for construction of the WWTP,
and RMB45,650,000 for pipeline. The project commenced in May 2008, all civil
works and installation have been finished, and started test run in September 2009 for
three months, all operating indexes reach the standard, and it was put into service on
November 30, 2009.
The WWTP uses the advanced Germany BIOLAK’s processing too, with outlet
water quality in Grade 1, A, which can be used for farmland irrigation, urban planting,
and industry, for water resource cyclic utilization .
6) Urat Middle Banner Hailiutu Town WWTP
Urat Middle Banner Hailiutu Town WWTP locates 2km south from Hailiutu
town with design capacity of 10000t/d for sewage, and 29.65km pipelines. Total
investment of the project is RMB50,180,000, and pipeline construction investment is
RMB29,960,000. Now civil works is constructing, the oxidation ditch, oxidation
pond, secondary sedimentation tank have excavated and rolled, in addition, 12km
urban pipeline has been laid.
Carrousel oxidation ditch processing is used for treatment, which has simple
process flow, less structures and civil work cost; advanced and proven technology and
simple management and maintenance; reliable and stable operation, good treatment
effect, good COD removal rate, stable N and P removal capacity; and better capacity
of impact resistance. Construction of the project, can not only improve urban aquatic
environment quality, but also provide good life and working environment to the
towner. In addition, it may improve environment of investment, and promote healthy
and fast development of economy and society.
7) Urat Rear Banner WWTP
The Stage I size of Urat Rear Banner WWTP is 6000t/d, while Stage II is
12,000t/d. Total investment of the project is RMB64,890,000, where RMB35,600,000
for the WWTP, and RMB29,290,000 for pipeline. Now, 25% civil works has been
finished, including the office building, the machine repair shop, the garage. The
distribution room and the anaerobic tank are under construction. Purchasing of
production equipments has been finished, it will be put into service by November,
2010.
Urat Rear Banner WWTP adopts improved Orbal oxidation ditch process, which
is applicable for conventional secondary bio-treatment, at the same time of carbon
source pollution removal in waste water, bio-denitrogenation and bio-phosphorus
removal are also available. The process has strong impact resistance, low energy
consumption, simple management and operation and good effect of N and P removal.
The project enable water quality after two-stage bio-chemical treatment to reach
Discharge standard of pollutants for municipal wastewater treatment plant (GB
18918-2002), Grade 1, B.
8) Linhe No. 2 WWTP
Recent waste water treatment size of Linhe No. 2 WWTP is 100,000m3/d, and
60,000m3/d reclaimed water. Total investment is RMB623,697,000, where
EUR35,000,000 is from the loan of German promotional bank, the rest is from China
Development Bank and self-financing. The project will upgrade and rebuild more
than 200km urban pipeline, and build 2 lift pump stations. Total floor area of the plant
is 18.587ha, where recent floor area is 11.277ha.
The WWTP adopts the solution of hydrolysis acidification and A2O bio-
treatment; water reclamation adopts the fiber disc filter solution; and sludge treatment
adopts the mesophilic digestion solution. The project will treat industrial waste water
from Bayannur Linhe Industrial Park, which may moderate situation that Linhe No. 1
WWTP lacks capacity effectively.
The above mentioned projects can add 222,000t/d waste water treatment capacity
for Bayannur, reduce discharge of water pollutants, provide supplement each other
with the project of Bayannur aquatic environment comprehensive treatment with WB
loads. Combination of source control and terminal treatment can improve aquatic
environment quality in Bayannur, which is very important for improving aquatic
environment quality of the General Drainage Canal and Wuliangsu Lake, even
pollution control and ecological environmental protection of Yellow River.
4. Environmental Baseline
4.1 Profile of Regional Environment
4.1.1 Environmental Profile of Bayannur City 4.1.1.1 Natural Environment
1) Geographic Location
Bayannur is located in north China’s frontier in west of Inner Mongolia
Autonomous Region between 40°13′-42°28′N and 105°12′-109°53′E. It is bounded on
the east by Baotou City and Ulanqab League, on the west by Alashan League and on
the north by Mongolia and faces Ikchor League across Yellow River to the south.
About 378km long from east to west and about 238km wide from north to south, it
covers an area of 65,551km2, accounting for 5.46% of the total area of Inner Mongolia
Autonomous Region and ranking 7 among 8 leagues and 4 cities. The north part of the
city, from north foot of Yinshan Mountains to national boundary, is gentle rolling high
plain with altitude between 1,020m and 1,400m. This part is a vast natural pasture,
which is commonly referred to as Urad Prairie. Urad Prairie, a desert or semi-desert
grassland, covers an area of more than 30,600 km2, taking up 46.7% of total land area
of the whole city. It is a base for development of animal husbandry of the city.
2) Geological Structure
Bayannur geological position steps astride two primary geotectonic elements,
namely, Tianshan Mountain-Inner Mongolia-Hinggan Palaeozoic geosynclinal fold
region to the north and Sino-Korean paraplatform to the south, which are bordered
by Badain Jaran- Urad Back Banner-Kangbao- Chifeng- Changtu Major Fracture
(close to about 42°N). According to different internal structural features, it can be
further divided into four secondary and five tertiary tectonic elements. In the long
geological age, these tectonic elements underwent different evolvement, showing
distinct and different structural features. The complicated geotecture and active
tectonic movement here exert a control action on age base, sedimentary formation,
magmation and even formation of minerals in this area.
Sino-Korean Paraplatform: The south part of the area is component of Sino-
Korean paraplatform. The platform itself is a relatively stable region, but its internal
growth is not uniform, having long-term upwelling area and long-term downwarping
area as well. According to different developing history and structural features, the
platform can be further divided into two secondary tectonic elements: Inner Mongolia
axis (Inner Mongolia platform uprise) and Langshan Mountain-Baiyunebo platform
margin rifted depression. Located in the south side of Langshan Mountain-Baiyunebo
platform margin rifted depression, Inner Mongolia axis spreads in an east-west strip
land. The base of it is composed of Archaean Ural Mountains and late Algonkian.
Located in the north side of Inner Mongolia axis, Langshan Mountain-Baiyunebo
platform margin rifted depression is a long and narrow strip land, spreading from east
to west. Bordered on the north by Badain Jaran- Urad Back Banner Major Fracture
and Tianshan Mountain-Inner Mongolia-Hinggan Palaeozoic geosynclinal fold region,
it is a relatively active zone in the northern margin of Sino-Korean paraplatform.
Tianshan Mountain-Inner Mongolia-Hinggan Palaeozoic geosynclinal fold
region: it is subject to Hercynian geosynclines in the northern vast area in this region.
This region went through complicated geological experience, showing the course of
developing from geosynline to platform. The tectonic movement and magmation are
so frequent that stratigraphic distribution of Paleozoic era and before is scattered.
According to different developing history and structural features, it can be further
divided into two secondary tectonic elements: Saihantala Late Hercynian geosynclinal
fold belt and Beishan Mountain Late Hercynian geosynclinal fold belt. Located in
most part of northern Badain Jaran- Urad Back Banner Major Fracture, Saihantala
Late Hercynian geosynclinal fold belt spread from east to west and from north to east.
To the north of Badain Jaran- Urad Back Banner Major Fracture, Beishan Mountain
Late Hercynian geosynclinal fold belt runs across the northwest of the region and
Saihantala Late Hercynian geosynclinal fold belt, spreading from east to west.
3) Landform
The landform in the whole city clearly falls into three categories: high plains in
the north, hills in the middle and plains in the south.
(一)Urad Plateau
Located in the north part of the city from hills at the foot of north Yinshan
Mountain to the south to the national boundary to the north and covering an area of
30,600km2 with an elevation of 1,000-14,00m, it is a part of Inner Mongolian Plateau.
It is mainly composed of tertiary river-lake red sandstone and sandy mudstone and
quaternary glutenite. Due to strong dry denudation, stony monadnock and deflation
hollow are formed. Owing to the lack of rain, wide and shallow riverbed has flows
only in wet season to converge at the northern depression to form an interior drainage.
To the north of the depression, in the region of frontier of China and Mongolia are
sprinkled with dryly denuded monadnocks joining intermittently.
(二)Hilly Area of Yinshan Mountains
Located in the south of Urad Plateau, it lies in the middle and southeast parts of
Bayannur from east to west. In terms of the distribution position, it can be divided
into three parts: Longshan Mountain, Serteng Mountain and Ural Mountain.
Langshan Mountain, also known as Hanalin Ural (black hill in meaning) at
west side of Yinshan Mountains, about 280km long and 30-60km wide, east-west-
trending to the east of 107°30′E and northeast-trending to the west of 107°30′E,
encircles northern Houtao Plain, covering an area of 7,990km2 and standing at an
elevation ranging from 1,500m to 2,200m. Most rocks of the mountains are hard
Archaean metamorphites. Ridges and peaks rise one after another. Most of the peaks
are of ridge shape or dentation. With so many cliffs and bare rocks, the vegetation is
so sparse that only in the shady slopes grow low weed and shrub. Woods can be
visible in the east section of Langshan Mountains and the west section has the
elevation dropped down into the desert. The intermountain basin is at an elevation of
1,200-1,400m, with tertiary sedimentary formation covered with quaternary wind-
blown sand formation. Those who boast large area are Hailiutu Basin and Hulusitai
Basin. There are some strip depressions composed of Jurassic with coalfield
embedded in.
Serteng Mountain, to the east of Langshan Mountain and bordered by Hailiutu
Basin, covers an area of about 10,100km2. Approximately to the east of Hailiutu, the
mountain spread out in three branches with the north and south in parallel. The
northernmost one, called Hadate Mountain and located in the northeast of Hailiutu
Basin, about 120km long and 1,600-1,800m above sea level, is gentle low hills and
mounds. Most of the rocks are gneiss and granite. Rocks on top and adret are bare and
on the shady slop grow sparse weeds.
Ural Mountain is located to the south of Ming’an River and the north of Yellow
River. From Xishanzui to the west to the Kundulun River to the east, it shows a clear
east-west trend. It, 94km long and 12-20km wide, takes an area of 1,100 km2.
Standing at a height of about 2,000m above sea level, its relative height is 700-
1,000m, with the prominent peak Dahuabei at an elevation of 2,324m. Most of the
rocks are schist, gneiss, marble, quartzite, granite, sandstone, conglomerate and so on.
With the strong upward axis which causes strong erosion, the ridge is narrow and
rugged. The peaks are subject to indention. The rocks on adretto are bare so that the
vegetation is sparse, while the shady slope, with thin cohesive soil, boasts thicker
plants, forest coverage reaching 27.75%. Large gullies contain Dianlisitai Gully,
Dalagai Gully and Daba Gully. The south slop of the mountain has obvious faults
overhanging Yellow River. Proluvial fan groups and multilevel terraces at the foot of
the mountain are particularly pronounced. On the north slopes, there are also proluvial
fan groups and multilevel terraces, but not as obvious as the south slope.
(三)Hetao Plain
Located in the south part of the city, it can be divided into four parts in terms of
landform: Wulanbuhe Desert, Houtao Plain, Ming’an River and Sanhuhe Plain.
Wulanbuhe Desert: spreading out in the southwest of the city, between Langshan
Mountain and Baotou-Lanzhou Railway, including most Dengkou County and
southwest Hangjin Back Banner, it covers an area of 3,400km2. With an elevation
between 1050m and 1030m, it gradually drops down from southeast to northwest,
gradient ratio being 1/5000. Quaternary Yellow River alluvial deposit and proluvial
deposit are covered with modern aeolian dune with complicated shapes, such as
barchan chains, escarpment-shaped dunes, hill dunes and flat dene.
Houtao Plain: from Bayan Gol-Siba-Taiyangmiao to the west to Xishanzui,
Ulansuhai Nur to the east and to 1200m contour of the south foot of Langshan
Mountain to the north and to the Yellow River to the south, it, about 180km long from
west to east and about 60km wide from north to south, is a fan with an area of
10,000km2 and average elevation of 1,050m. It forms a strip of depression belt
between the alluvial plain high in the south and low in the north and the proluvial
plain high in the north and low in the south, which now is the location of the general
arterial drainage of Ugab River and the marsh. Yellow River alluvial plain is the
principal part of Houtao Plain, taking up about 3/4 of the plain’s total area. Bordered
by Ugab River, it is 40-50km wide from north to south. With flat terrain, the elevation
is usually 1,020-1,040m. High in the west and low in the east, the gradient is 1/3,000-
1/5,000; High in the south and low in the north, the gradient is 1/4,000-1/8,000; only
local part shows gentle rolling. The constructional materials include fine sand, silt,
sandy loam and loam interbed. The size distribution of sediment varies from north to
south. Thick coarse materials are often seen in ancient riverway of Yellow River with
sand sediments as mainstay; between the ancient riverways are loam and clay
sediment.
Ming’an River is located in the intermountain basin to the south of
Baiyunchahan Mountain and to the north of Ural Mountain. From the Ulansuhai Nur
to the west to the 1200m contour to the east of Tailiang, it is about 50km long from
east to west, taking an area of 1,800km2. The middle part of the basin is fluvial plain,
and the north and south parts are fluvial-alluvial plain and piedmont proluvial inclined
plain.
Sanhuhe Plain is located between Ural Mountain and Yellow River. From
Xishanzui to the west to the boundary of Bayannur and Baotou, it is a narrow strip,
about 70km long from east to west and 3-15km wide from north to south, taking an
area of 700km2. The relief has two tilt directions, one inclining to Yellow River from
mountain foot, and one consistent with Yellow River’s flow direction from west to
east. The ground gradient averages about 1/7 000 with an elevation of 1,025-1,200m.
The landform shows obvious zonation, divided into four zones of flood plain, Yellow
River alluvial plain, piedmont fluvial-alluvial plain and torrential plain from Yellow
River to Ural Mountain.
4) Hydrogeology
Ground water mainly comes from precipitation infiltration and little
condensation recharge, its distribution regularities mainly having close relation with
such factors as geological structure, lithology, terrain and weather. The distribution of
ground water in the city features with gradual decrease from east to west and from
south to north.
In terms of distributed burial and water conservation feature, ground water is
divided into perched water, phreatic water and confined water (artesian water). In
terms of the rock feature of water carrier, ground water in the city can be divided into
bedrock fissure water, plateau red earth pore water, quaternary loose rock pore water,
quaternary desert aeolian sand pore water, Hetao Plain aeolian quaternary alluvial-
proluvial lacustrine formation pore phreatic water and confined water.
Bedrock fissure water is located in the Yinshan Mountain hydrogeology area.
The terrain here is high in the west and low in the east, steep in the south and gentle in
the north. Hill bedrock fissure water is widely distributed, mainly spreading to
Langshan Mountain, Ural Mountain region and low hilly region in the China-
Mongolia boundary in the north.The abundant and deficient situation of ground water
is greatly different, the water inflow of single pore in water abundant zone reaching
up to over 60t/h; such kind of area, however, takes a small area; the water inflow of
single pore in zones with medium water is 10-30t/h; and the water inflow of single
pore in water deficient zone is less than 1t/h. The water quality in most regions is
better with salinity less than 3g/l.
Plateau red earth pore water is distributed in long-strip depression basin
composed of red earth between hills of Yinshan Mountain and hillock of Dishan
Mountain. The lithology of main water carrier is subject to glutinite of Cretaceous
System. Water carrier is usually buried over 15m below the surface. Water in the
central basin is abundant, maximum water inflow of single pore reaching over 70t/h;
in the fringe region, water amount is small, inflow of single pore being 10-30t/h; the
zone contacting the basin and surrounding rock is extreme water-poor belt, inflow of
single pore being 1-5t/h, or less than 1t/h. The salinity of water often is less than 2g/l,
but may exceed 2g/l in the central basin, dominated by HCO3-Cl-Na.
Quaternary loose rock pore water is mainly distributed among ravines of bedrock
hills and alluvial-pluvial plains at the tail of river valley. The water carrier is
composed of medium coarse sand, find sand, grit stone and sandy pebble. In the area
of Langshan piedmont alluvial and pluvial plains, water carrier is often 5-25m thick,
water inflow of single pore reaching more than 100t/h; in the area of medium water
amount, water inflow of single pore is 10-30t/h; water deficient zone is mainly located
in smaller ravines in hills and the upstream of large ravines, as well as alluvial and
pluvial plains of plateau regions and developmental ravine in basins. As the ravines of
such kind are shorter, the water yield property of water content is poor, water inflow
of single pore being 1-5t/h or 1t/h or below. The salinity is often less than 2g/l. It is
subject to HCO3 water, applicable to exploitation and utilization.
Quaternary desert aeolian sand pore water is mainly distributed in the desert
region in Dengkou County in the west of the city. In such region, water buried depth
is small, often less than 10m. The water carrier is composed of fine aeolian sand,
medium-fine sand and sandstone, thickness being 5-30m and water inflow of single
pore going up to 40-80t/h; in the area of medium water amount, water inflow of single
pore is about 10t/h; in water deficient zone, water inflow of single pore is less than
1t/h. The salinity is often less than 2g/l. It is subject to HCO3. The salinity at the
fringe of a tract of low lying land and oasis is larger than 2g/l.
Hetao Plain aeolian quaternary alluvial-proluvial lacustrine formation pore
phreatic water is located in the plain area to the south of Yinshan Mountain area and
to the north of Yellow River. This area is a fault basin, with water-content rock series
including quaternary alluvial-proluvial grit pore phreatic water and confined water,
quaternary alluvial lacustrine formation fine silt pore phreatic water and quaternary
alluvial lacustrine formation fine silt pore confined water. The piedmont water yield is
often larger than 100t/h. The salinity is often less than 2g/l. It is subject to HCO3,
HCO3-SO4 and HCO3-Cl water. The salinity in the downstream section of Houtao
Plain and the south of Ugab River is often larger than 3g/l, some up to above 10g/l,
subject to Cl and Cl -SO4 water.
Ground water in hilly area of Yinshan Mountain and other hilly areas is mainly
recharged by atmospheric water. Due to structural condition and weathering, rocks
developed joint fissures in different degree, which is the condition to receiving
precipitation infiltration. Some areas of Ural Mountain boast good vegetational cover,
which is favorable to precipitation infiltration and water conservation. Precipitation,
after infiltrating the ground, is stored and transported by rock fractures, creating good
runoff conditions. Ground water discharge in hilly areas are mainly in the form of
runoff, some discharged to valleys in the mountain to changed into river runoff, some
flowing to riverbed deposit to form submerge flow and then discharged to
mountainous depression and basin. Most of them are stored in water carriers of
depressions and basins, some consumed for evaporation. In the juncture of hill and
plain, ground water of hilly area is discharged to the water carrier of plain area in the
form of lateral runoff.
The cycle conditions of ground water in plain terrain are complicated. They are
subject to tremendous influence of human activities except natural factor. Apart from
atmospheric precipitation infiltration, ground water is also compensated by lateral
runoff in hilly area, seepage of plain rivers and return flow of irrigation. The recharge
from return flow of irrigation of Hetao Plain takes up a large proportion. In piedmont
alluvial- pluvial plain terrain, the terrain slope is relatively steep, lithological grain,
mainly composed of sandy pebbles and coarse sand, is coarse, runoff conditions of
water carrier being good and dominated by horizontal alternation. In alluvial
lacustrine plain area, the land is flat, lithological grain in water carrier becoming fine.
Except the smooth runoff in the upstream section, the general runoff conditions are
poor. The horizontal discharge is slight, and is dominated by vertical evaporation.
Recharge of ground water in desert area mainly comes from rainfall and
condensation water, which are stored in the depression in the confining bed under the
desert bed. They form desert phreatic water and consumed by evaporation. Some of
them can infiltrate into the lower water carrier.
The inland area, dominated by dry climate, has little precipitation and the source
of ground water recharge is limited, thus the ground water is deficient. Only in some
closed basins and depressions form accumulation areas of ground water, which will
gain lateral recharge from surrounding except precipitation recharge. The discharge
form is subject to local evaporation to maintain water balance.
5) Climate
Bayannur, far away from ocean, dwells on plateau in inland. The climatic
characteristics: four distinct seasons, less snow in cold winter, much wind in dry
spring, little rain in heated summary and mild and cool autumn. It is typically
continental monsoon climate in medium temperate zone.
The annual average temperature in Bayannur is 3.7-7.6℃. The temperature
decreases progressively from southwest to northeast, with the west higher than the
east. The annual average temperature of Bayan Gol Township, Dengkou County at the
southernmost side is 7.6℃, and that in Woodlands, Urad Middle Banner to the
northernmost part is 3.7℃.
With many hills and hillocks in the city and complex terrain, the geographical
distribution of precipitation varies wildly. The feature of it is that the precipitation
decreases gradually from southeast to northwest, forming a situation that the east is
more than the west and the hilly area is more than the plain. The average annual
precipitation of the city is 188mm, and 177-285mm in the east and 99-184mm in the
west.
Located in westerlies, and perennially affected by zonal circulation, Bayannur is
long controlled by continental polar air. In addition, the ground is so higher that
vegetation is sparse. Thus the wind speed is high and the wind period is longer.
Markedly affected by monsoon, the city has its wind direction varied greatly with
season in a year. Under control of Mongolia cyclone during October to the next
March, the city is dominated by north wind or northwest wind.
In terms of general trend, the distribution of relative humidity within the city
decreases from southeast to northwest. The average annual relative humidity is 42-
54%, where that in Hetao area is 47-54%, and 42-48% to the north of Yinshan
Mountain.
The evaporation in Bayannur increases gradually from southeast to northwest.
The average annual evaporation is 2,032-3,179mm. Hailsu area has the maximum
evaporation in Urad Back Banner, with average annual evaporation of 3,178.8mm.
Chengguan Town, Wuyuan has the minimum evaporation, with average annual
evaporation of 2,032.2mm.
Sunshine distribution in the city features with much sunlight in the north and
west and less in the south and east. To the north of Yinshan Mountain, the average
annual hours of sunshine is 3,215.1-3,401.8hrs, and in Hetao area, 3,184.6-3,221.0hrs.
The cloud cover in the city is slightly more in the north than the south, but the
difference is indistinct. The total average annual cloud cover is 40%,-42% in Urad
Front, Middle and Back Banner, and the rest areas 38-39%. The number of sunny day
in the city in a year is 109-31, and cloudy day, 42-63. The cloud cover is maximum in
summer and minimum in winter in a year, and much in day and less in night.
6) River and Hydrological Features
There are many rivers in Bayannur and are divided into two drainage systems by
the divide of Yinshan Mountain: Yellow River system to the south and inland river
system.
(1)Rivers
Yellow River system: originated from the north foot of Bayan Har Mountains,
Qinghai Province, Yellow River flows through Gansu and Ningxia to the city.
Tributaries converging at north bank of Yellow River are gully rivers from
Langshan Mountain and Ural Mountain. There are a total of 147 gullies, large or
small, in Langshan Mountain, with a catchment area of 13,000 km2, where those
whose catchment area is above 250 km2 number 15, taking up 90% of the total
catchment area. Gullies in Ural Mountain totals 28, with a catchment area of 388 km2,
where those whose catchmen area is above 10 km2 count up 11.
Inland river system: the inland river system in the city spread out over the
pateau to the north of Yinshan Mountain. Its drainage area is 31,000 km2, including 34
inland rivers, of which, most are seasonal stream.
Lakes: there are 318 lakes taking an area of more than 2ha, with water area of
3,141,555mu. These lakes are scattered over Hetao Plain. To the north of Yinshang
Mountain, there are only few seasonal lakes such as Sanggendalai Zhuoer and
Chagantaoligai Nuoer. Ther are 21 lakes and reservoirs with an area over 1,500mu.
Ulansuhai Nur, water surface of 44,985mu, the average depth 0.7m, and the storage
capacity 209,930,000 m3, is the largest lake in the city, and is the drainage and
mountain torrent receiver of Yellow River irrigation region in Hetao Plain as well.
(2)Hydological Features of Rivers
Except Yellow River, the hydrological features of Bayannur’s rivers depend on
local conditions of precipitation, evaporation and geological geomorphology.
① Yellow River
Flowing from Ningxia to Bayannur, Yellow River’s average annual transit water
quantity is 31,500,000,000m3. Inspite of many tributaries converging the city, most of
them are seasonal rivers, supply water being less. Only torrential flood after flood
seaon and rainstorm exerts some impact on water level. Yellowe River experiences
two flood seasons, namely summer flood and ice flood.
In terms of cause of formation, floods occurred in Yellow River are mainly
divided into ice flood and storm flood. Ice flood is a result of melting ice in riverway
and release of stored water in river channel. It often occurs in March, also is called ice
flood.
Storm foold often occurs from July to September. The flood may happen twice to
three times a year, and even 5 times in few years. The average volume of flood is
3,000-4,000 m3/s.
Yellow River is a world-known sediment-laden river, containin much more sand
in midstream and downstream. The sediment concentration in the stretch in Bayannur
is about 6kg/m3.
② Other Rivers within the City
Brooks in the city are mountain stream, usually with extremely less volume of
fresh water. Summer rainstorms result in outbreak of flash flood. With incoming water
and flood under control of rainstorm, the brooks experience steep rise and drop in
short time.
Based on Inner Mongolia Water Temperature Manual and investitaion
information of water resource in Inner Mongolia and exiting data, annual average
depth of runoff in the city is 3-10mm by statistical analysis. The distribution
trend of annual runoff depth is basically consistent with the precipitation
distribution, decreasing from southeat to northwest and higher in mountain area
than in hilly area and plains.
The annual average runoff in the city is 331,000,000m3, where Yellow River
system takes up 237,000,000 m3, 71.6% of the total runoff and the inland river system
accounts for 94000,000 m3, 28.4% of the total.
(3)Hetao irrigation area
Hetao irrigation area in Bayannaoer has formed a pattern of having irrigation system,
having water discharge route and having stable irrigation and discharging, it has become the
largest large-scale gravity irrigation area.
Hetao irrigation area involves to all counties in the Bayannaoer, including 108 towns, farms
and stations with a total area of 11195.4km2,the irrigation area is 5743.6km2.The drainage system
in the Hetao irrigation area includes 7 levels, there are one general drainage ditch ,12 drainage
ditches, 60 drainage sub-ditches, 225 branch ditches and about 22000 small ditches, the general
drainage ditch is the main project of drainage system, the total length is 257.283km, the drainage
area under control is 7583.7 km2,the mountain torrent area under control is 13313 km2 ,the
drainage volume accounts for 93% of the total drainage volume in the irrigation area ,the
remaining is directly drained into Yellow River through other drainage ditches. The water is
flowed into the Ulansuhai at the end of truck, Ulansuhai is main part of irrigation works in Hetao
area, it is the only acceptance water body and drainage channel for withdrawal of agriculture
irrigation water in the Hetao area, it has accepted more than 90% drainage water in the irrigation
area, the drainage water from the Bapaigan and Jiupaigan are directly run into the
Ulansuhai ,which account for 14% of the drainage capacity of the general drainage ditch; the total
length of export section is 24 km, the drainage area under control is 232.67km2,which account for
3% of the drainage area, the water is excluded into the Yellow River through the export section of
general drainage ditch. Shipaigan is directly excluded into the export section, which account for
2% of the drainage capacity of the general drainage ditch.
7)Natural Resources
(1) Land Resources
The total land area of the city is 65,551.5 km2 (98,327,000 mou), which can be
classified into seven main categories, including cultivated land, garden plot, wood
land, grass land, non-agricultural land, water area and hard-to-use land.
The cultivated area of the city is 7,170,362 mou, totaling 7.3% of the gross land
area, about 5.1 mou per capita, which is mainly distributed in Hetao Plain and
Northeast Hilly Country. The fruit garden (inclusive of sprinkling garden fruit trees) is
26,471 mou, taking up 0.027% of gross land area, which is mainly distributed in
Linhe City, Northwest of Hangjin Back Banner, Bayantela and Chengguan Villages of
West Wuyuan County, and Siba, Baleng and Gongdi Villages of Dengkou County. The
available forest land area is 1,338,554 mou, occupying 1.36% of gross land area. And
the grassland area is 54,622,000 mou, taking up 55.55% of gross land area, among
which 3,836,000 mou is agricultural grassland and 50,786,000 mou is pastoral
grassland. Because of the difference of regional precipitation and water resources
allocation, a varying of vegetation form from east to west is formed, making
regularities of distribution of steppe-desertification steppe-steppe desert-desert. The
land for urban residents and industrial and mining purposes is 1,059,000 mou,
occupying 1.078% of gross land area. The water area is 3,141,500 mou, taking up
3.2%. The hard-to-use land is 30,212,500 mou, occupying 30.73%, which mainly
includes 2,799,200 mou saline land, 3,973,500 mou flowing aeolian sandy soil,
23,243,200 mou bare rock and gravel, 1,535 mou marsh and 193,100 mou bare soil.
(2) Water Resources
The water resources of city are made up of surface, underground and cross-
border water.
The surface water is from Continental River and Yellow River. The drainage area
of Yellow River water system is 34,000 km2, taking up 52% of total city area. The
normal runoff is 237 million m3, occupying 71.6% of that of the whole city. The
endothermic river is 31,000 km2, taking up 48% of the whole city. And its normal
runoff is 94 million m3, taking up 28.4% of the whole city.
The underground water comprehensive recharge capacity of the whole city is
3.21 billion m3 with 1.81 billion m3 workable reserves. The underground water is
distributed from east to west and south to north. Along the lower course of Hetao
Plain and south of Ugab River, the underground water mineralization degree is more
than 3g/l with some area even above 10g/l. Therefore, the water is bad in quality and
less in quantity. The hydration type of water is Cl—SO4.
The cross-border water is mainly from Yellow River with a normal runoff of
31.50 billion m3. The interannual and inter-monthly change of annual runoff of Yellow
River is great with maximum 50.50 billion m3 and minimum 18.30 billion m3.
Since the establishment of China, Bayannur has constructed a lot of projects to
make good use of water resources, including 1 Yellow River Sanshenggong Key
Project, one 228.9 km general main cannel, 9 sectional projects, 13 main canals
totaling 790.1 km, 43 sub-canals totaling 958.30 km and 249 branch canal totaling
1,750 km. Even the piping engineering under Dounong Canal has been provided with
some supporting facilities becoming the largest irrigation area controlling canal in
China. The existing irrigation area is 6 million mou, which is the foundation for
Bayannur to develop agriculture. The drainage system has one main arterial drainage
totaling 206 km, 13 main stream gullies totaling 508.5 km, 62 sub-main stream gullies
totaling 1,032.3 km and 139 branch gullies totaling 206 km. Therefore, the drainage
major projects have taken shape. For the sustainable and stable development of
agricultural production in Hetao Irrigation Area, the water diversion irrigation from
Yellow River is a major condition.
4.1.1.2 Social Environment
1) Administrative Division
At present, Bayannur administrative division has 4 banners (Urad Front, Middle
and Back and Hangjin Back), 2 counties (Wuyuan and Dengkou) and 1 district
(Linhe), covering 106 villages and towns and offices, among which there are 19 sumu
(villages), 32 villages, 45 towns (all 96) and 10 offices. The banners, counties and
cities administer 18 towns, 82 villages, 23 sumu (villages), 795 villagers’ committees,
141 administrative villages, forming a town layout of one village in 30 Li (half of km)
and one town in 50 Li.
2) Urban Population
The fertility rate, death rate and natural growth rate of Bayannur City are 5.68‰,
2.99‰ and 2.68‰. By the end of year, the gross population of domicile has reached
1,761,300, an increase of 1.15% over the previous year. According to the statistics of
family planning departments, the average annual natural population growth is 5,000-
6,000 persons with a low mechanical growth rate. According to the statistics of
municipal public security bureau, the population growth rate, inclusive of floating
population, in central city of Bayannur has exceeded 10,000/year.
3) Socioeconomic Development
The total output value of Bayannur area in 2005 was 21.70 billion Yuan, an
increase of 1.1 over 2000 on comparable basis, among which the later two years’
average growth rate was more than 20% experiencing the highest level since the
Reform and Open Up. The agricultural production continued to be rich harvest in
successive years and service industry continued to expand in scale and gross amount
at the time of industrial optimization and updating. The industrial output doubled in
two years and increased by two times in three years becoming an active force to bring
along the economic growth.
The municipal financial revenue in 2005 reached 2.123 billion Yuan, an increase
of 2 times over 2000, which remained a relatively high growth rate under a condition
of overall deductions and exemptions of agricultural tax, decline of non-tax revenue
proportion and new projects under breeding. Now, the municipal economy has taken
on a great-leap-forward development and stepped into a new phase of per capital GDP
from USD 1,000 to 3,000. The industrial structure experienced profound changes
making the structure of three industries change from 39:26:35 to 30.6:38.5:30.9,
among which the primary industry went down 8.4% and secondary industry up
12.5%. The internal industrial structure continued to optimize. The strategic
adjustment and industrialization operation of agriculture structure made a substantive
progress. The industrial pillar industry developed in diversification. New industrial
framework was forming. The development of urban and village structure experienced
a significant change. The urbanization proportion was improved to 41% from 36.9%.
Through reforming state-owned enterprises, national economy stepped out completive
fields to some extent making a further-improved ownership structures. With the rapid
growth of economy, the income of urban and rural residents was largely improved.
The per capita disposable income of urban residents reached 8,022 Yuan and per
capita net income of farmers and herdsmen was 4,265 Yuan in 2005, an increase of
67% and 76.4% over 2000 respectively. The growth rate was higher than the national
average level, especially a net growth of more than 500 Yuan for farmers for two
years in a row. The growth was the third peak since the Reform and Open Up. The
outstanding of deposits from urban and rural residents increased by 100% over 2000.
The poverty-stricken population in agricultural and pastoral areas went down to
150,200 in 2005 toward 259,200 in 2000. Housing, education and tourism became
new consumption points. More than 60,000 people entered the labor force. The
payout ratio of pension was 100%. The registered unemployment rate of urban
residents was controlled at 4.25%. And urban minimum living standard was
completely and well implemented.
4.1.2 Environmental Profile of Subitem Location4.1.2.1 Urad Front Banner
1) Natural Environment
(1) Geographic Location
Urad Front Banner is located at the southeast of Bayannur City, Inner Mongolia
Autonomous Region, whose geographical coordinates is E108° 12′ -109° 54′ and
N40° 26′ -41° 16′ and east side is next to Baotou City, south next to Dalate Banner
and Hangjin Banner of Erdos City across Yellow River, west close to Wuyuan County
and North bordered on Urad Middle Banner. The banner location, Ural Mountain
Town, is 288km from Hohhot City and 142km from the Bayannur Municipality.
(2) Landform and Physiognomy
The project area is a part of Hetao Plain located between Ural Mountain (west
section of Yinshan Mountains) and Yellow River. Influenced by regional structure, the
area extends in east-west. The plain terrain topography slopes from northwest to
southeast, yet, is even and wide with slightly fluctuation at local parts. The
topography in front of mountains is a dip plain high in north and low in south, which
is formed by the Ural Mountain Front Flood Plain and Yellow River Alluvial Plain.
① Ural Mountain Front Flood Plain
The Ural mountain front proluvial fan plain has 201.7km2 area in the project area,
which runs nearly from east to west and is banding distributed in front of Ural
Mountain, 67km from east to west and 0.5 ~ 5.1km from south to south. The near
piedmont belt has a relatively large ratio of slope, slightly flatting slope toward
alluvial fan leading edge. Because of valley cutting, the land is of slightly fluctuation
with gradient ratio between 0.006~0.017 and elevation between 979~1,142m. It is
made of Epipleistocene~Holocene series sand, sandy gravel and clay sand.
② Yellow River Alluvial Plain
The yellow river alluvial plain has 468.09km2 area in the working area. The
topography is even and wide running from west to east and lowering from north to
south. The region of interest running from east to west is banding distributed between
Yellow River and Ural Mountain Front Flood Plain, 63km from east to west, 2.3 ~
13.5km from south to north, gradient ratio between 1/5,000 ~1/8,000 and elevation
972~1,014m from north to south. Because Yellow River changes its course for many
times, the flood has formed some micro-geomorphology, such as Niu’e Lake, slot-
form and butterfly soak and freely running cannels and trenches. It is a traditional
irrigation area using water from Yellow River, yet, with shallow groundwater
occurrence and serious water-logged soil, especially in the two sides of Sanhu River
Main Cannel. It is made of Epipleistocene~Holocene series sand, lacustrine silty fine
sand and clay sand.
(3) Geology
Urad Front Banner is complex in geological structure with fold, fracture and
great block mountain developed by deep fracture. The basement rock is made up of
Sangkan and Wutai groups of Archean Group and Zhaertai group of Proterozoic
Group. Yanshan movement developed front deep fracture from original one. Because
of the existence of deep fracture, three stair block mountains, Chashitai, Bayinchagan
and Ural, from north to south were formed along with Ming’an, Large and Small
Shetai Rivers and different table-top piedmont benchlands. Along the north side of
Yellow River Irrigation Area, there is a deep fracture zone extending to Ural River
and the new fracture cutting in front of Ural Mountain, which has enlarged and
deepened Hetao fault depression. The north part rise relatively forming high
mountains leaving the south part for Hetao Plain. The Ural Mountain Fault
Depression is under the latency of Ural Mountain umbos from Xishan Mouth to
Sanshenggong along railway. The geotectogene of Ulansuhai Nur and Sanhu River
trough valley formed inland close-type fault basin.
From Tertiary to early Quaternary period, the original fracture was further
developed into stair-type fracture and undergone the sedimentation of thick and
alluviation lacustrine, and alluviation diluvium. The middle and lower Pleistocene
Epoch is of successive gyttja and Epipleistocene is of recession of lake water. Yellow
River began to develop and experienced gyttja and fluvial facies sedimentation. Later,
the diluvial of Yellow River and Front Mountain alluviation formed Hetao Plain.
Under the action of human productive activities and Yellow River water, the surface
layer was coated with irrigation-warping horizon alluvium. The enclosed geological
structure of long-term lacustrine action of Hetao Basin accumulated a very high saline
matter in stratum. This gyttja geographical environment has been preventing the
smooth running of groundwater runoff leaving an enriched water and soil salt and
putting a great influence on the formation of saline soil.
(4) River Water System ① Surface WaterThe main surface waters in Urad Front Banner are Ulansuhai Nur, Yellow River
and waste cannels and ephemeral streams connecting Ulansuhai Nur and Yellow
River.
Ulansuhai Nur: Ulansuhai Nur is located at the east end of Hetao Irrigation Area
and north of Xishan Mouth Town of Urad Front Banner, which is south-narrow and
north-wide and submarine-declining from north to south. It has a total area of
29,333×104m2 occupying 6l.35% of Urad Front Banner Water Area, which is the
largest fresh water lake in west Inner Mongolia. It is celebrated for fish and reed and
the raw material site of Urad Front Banner paper making enterprises. As a part of
drainage works in Hetao Irrigation Area, Ulansuhai Nur mainly takes up agricultural
drainage, flash flood water and upstream industrial water drainage, which are led into
Yellow River through waste cannel.
Waste Cannel: The waste cannel is a main hydro junction to link Ulansuhai Nur
and Yellow River, which not only plays an important function on Hetao Plain
agricultural drainage, flash flood water discharge but drainage of along-line industrial
enterprises. The mean annual flow is 6.34m3/s, average flow velocity 0.37m/s and
average depth 1.4lm.
Table 4.1-1Statistical Table of Annual Depletion Rate from Waste Cannel of
Ulansuhai Nur to Yellow River
YearAverage flow
m3/s
Depletion rate of
Yellow River
100 million m3
YearAverage flow
m3/s
Depletion rate of
Yellow River
100 million m3
1984 3.2 1.01 1996 5.44 1.72
1985 2.77 0.87 1997 3.50 1.11
1986 3.97 1.25 1998 8.49
1987 8.53 2.69 1999 10.8 3.42
1988 7.44 2.35 2000 6.63 2.09
1989 8.07 2.54 2001 6.68 2.11
1990 6.63 2.09 2002 3.99 1.26
1991 10.00 3.16 2003 2.37 0.75
1992 10.50 3.32 2004 1.41 0.45
1993 9.30 2.93 2005 1.27 0.40
1994 7.96 2.51 2006 1.41 0.44
1995 4.53 1.43 2007 0.85 0.27
Remark: The annual mean depletion rate of Yellow River in 24 years is 179 million m3 and average flow is 5.66m3/s.
Yellow River: The Yellow River runs across the south of Urad Front Banner from
west to east leaving a full length of 160km within Urad Front Banner territory. Yellow
River is the boundary of Bayannur and Erdos City. According to the data from Sanhu
River Mouth Yellow River hydrologic station, the annual mean water flow of Yellow
River is 830.9m3/s; average flow velocity is 1.34m/s and average sediment
concentration 5.26kg/m3, which is the main water source for agricultural water of
region of interest.
Ephemeral Stream: The region of interest has 18 ephemeral streams with low
water season flow about 46~115m3/h for the larger Wulanbulagean ditch and 25 m3/h
for Huhebulagean ditch. In addition, the south of working region has irrigation ditches
and canals.
In wet season, the region has flood from Ural Mountain, among which there are
9 main floods with a normal runoff over 400,000 m3 and other 9 small ones with a
normal runoff less than 300,000 m3. The flood after running into Yellow River alluvial
plain part affluxes into Sanhu River main cannel and part stays in the flood retarding
basin formed by front proluvial fan and Yellow River alluvial plain and finally are
consumed, infiltrated and evaporated.
(5) Hydrogeology
The region of interest is located at the east zone of Hetao Plain with the north for
Ural Mountain Front Flood Plain and south for Yellow River alluvial plain. The
Epipleistocene-Holocene Series water-bearing formation of region of interest (Q3 and
Q4 water-bearing formation, No. 1 water-bearing formation for short) is well
developed and abroad distributed with great thickness, rich water content, shallow
bury and close relationship with surface water, which is the main water supply water-
bearing formation. The underlying Pleistocene Series upper and lower water-bearing
formation (Q2 water-bearing formation, No. 2 water-bearing formation for short) is
gyttja pile. The Pleistocene Series upper group is mainly silt deposition. The middle
Pleistocene Series lower group (Q21)aquifer is great in thickness, shallow in bury,
fine in aquifer grain and small in water quantity. Therefore, it is of no consequence for
total water supply and of exploitation value in some zone.
① Yellow River Alluvial Plain
The water-bearing formation of south Yellow River alluvial plain of region of
interest is mainly of fine sand, which is fine in grain, rich in stratum salinity. The near
mountain front flood plain contains rough sand along with some fine sand grit stone,
which is fine sand phreatic water. Its main characteristics are of cycling for
underground water upright alternation. Its hydrochemical type is HCO3-Ca·Na.
② Ural Mountain Front Flood Plain
The water-bearing formation of Ural Mountain Front Flood Plain of region of
interest is mainly of diluvial deposits, which is rough in grain containing grit stone
and partial paper clay, 20~50m in thickness. The Epipleistocene (Q3) of upper region
of interest is mainly pluvial phase and lower is Lake Facies sand bed. The upper
lithology is of yellow and sallow medium and fine sand and fine sand, which is rough
in grain, great in thickness. The lower bench is narrow containing silt and clay sand
bands and is of Lake Facies sedimentary deposit containing rich organic matter
humus. Water is dissolved with H2S and CH4 bearing putrefactive odor. The aquifer is
rough in grain and great in thickness, usually between 30~50m, which has rich water
quantity, low mineralization of water, shallow bury between 70~90m, water level
between 5~20m. It is a fine water supply aquifer.
(6) Water Resources
Deducting the double counting amount between the surface water and ground
water, the multi-year average gross amount of self-produced water resources in the
region of interest is 4183.34×104m3/a; under present situation, the utilizable amount of
water resources is 5839.2×104m3/a, of which 2898.24×104m3/a is the utilizable amount
supplied by the irrigation of the Yellow River; the amount of ground water resources
in salt water area is 2610.25×104m3/a, the utilizable amount of the ground water in salt
water area is 1957.69×104m3/a.
(7) Climate Features
Urad Front Banner has a temperate continental arid and semiarid climate.
Scarce rainfall, strong evaporation, dry and windy, large daily temperature range and
long sunshine duration are the main climate features. According to the data of Urad
Front Banner weather station, the multi-year mean precipitation is 211.6mm. The
annual maximum precipitation is 359.4mm in 1973; the minimum is 74.8mm in 1965.
The multi-year average evaporation capacity is 2379.4mm, the maximum wind speed
is 20.3m/s (in 1972) and the average wind speed is 3.10m/s; the multi-year mean
temperature is 7.5°C (1960~2000), the extreme maximum temperature is 37.7°C and
the extreme minimum temperature is -30.74°C. The maximum depth of frozen ground
is 1.19m and the maximum snow depth is 18cm.
(8) Soil and Vegetation
Due to the complex topography, landform and geological structure as well as
the differences in bio-climate, different soil parent materials are formed in arid
mountain areas and Yellow River irrigation areas of Urad Front Banner. Soil parent
materials are generally classified into sedentary, drift bed, pluvial, alluvial and aeolian
loess or loess-like, laterite or laterite-like, salt silt loamy texture, sandy and bedrock
differentiation crumb parent materials. Soil in Urad includes total 6 types, 18
subtypes, 49 soil genera and 395 soil species. The meadow irrigation-silting soil,
saliniferous irrigation-silting soil, irrigation-silting chestnut soil and irrigation-silting
light-colored meadow soil in Urad Front Banner are mainly the cultivated soils.
Except the part of light chestnut soil and haplic kastanozems which are wastelands
and pasture lands, the rests are dry cultivated lands. The gray cinnamonic soil is forest
soil. The saline soil and aeolian sandy soil have sparse vegetation, most of which are
wastelands. In addition, soil salinization within the territory is very serious with the
trend of deteriorating year by year.
Due to the complex topography and landform, various soil types and significant
differences in microclimate of Urad Front Banner, the distribution of plant
communities has significant zonality and regionality.
Vertical distribution: Ural Mountains have xeric forest-type vegetation. It had
dense virgin forests in ancient times, which has been replaced with natural secondary
vegetation in modern times. The plant community includes the mixed coniferous
forest and broadleaf forest and the symbiotic evergreen and deciduous trees, which
has certain vertical distribution regularity and geographic distribution features. At the
sunny slope and shady slope with the altitude above 1,700m, it mainly includes the
trembling aspen, white birch, Chinese pine, arborvitae and other arbores accompanied
by shrub and tussock. The vegetation coverage is 70-85%. The area with the altitude
below 1,700m is the borderland of forest vegetation with very little forest area; most
of arbores scatter with those at the shady slope more than those at the sunny slope; it
mainly includes shrubs and herbal plant and the vegetation coverage is 50-70%. At
the pluvial fan zone with the altitude of 1200-1400m, the main vegetation includes
herbal plant and fruticeta, accompanied by scotch elm, Zizyphus jujube and other
arbores at the foot of the hillside or ravine mouth. The vegetation coverage is 35-90%
and the height of grass sward is 15-45cm. Soil salinization in the Yellow River
irrigation areas is related to the ground water level and degree of mineralization.
Seerteng Mountain also had virgin forest vegetation in ancient times. Under the
influences of dry and cold climatic conditions, it has already become the soil erosion
area with sparse vegetation. There is only small area of alternate shrub light forest and
tussock in the mountain area of Zhashitaishan Mountain.
Geographic distribution: in arid areas of the mountain back, the rainfall decreases
significantly from east to west, the plant communities have significant directivity,
accompanied by arid and semi-arid grassland vegetation. The grass coverage is 30-
70% and the height of grass sward is 10-110cm.The irrigation-silting chestnut soil
areas with irrigation conditions are covered with farm crops and various natural
grasses. Under the influences of the ground water, salinization, irrigation and
sandstorm, etc., different plant communities are formed in the Yellow River irrigation
areas. Large area of irrigation-silting soil is covered with farm crops, man-made
forests and various natural grasses. There is kalidium foliatum, Nitraria tangutorum,
Chinese tamarisk and other halophilic vegetation growing in meadow saline soil and
marsh saline soil; there is agriophyllum pungens, sand sagebrush, Nitraria tangutorum
and other psammophilous vegetation growing in aeolian sandy soil; there is reed, stem
or leaf of cattail, aquatic plant and other aquatic vegetation growing in sea moat; there
is salix chaenomeloides Kimura, purple osier and other deciduous bushy shrubs as
well as xeric herbaceous vegetation growing in the floodplain at the north bank of the
Yellow River. Most of it is covered with man-made forests and farm crops.
(9) Natural Resources
Land①
The total land area in Urad Front Banner is 7,476 km2, equivalent to 11.214
million mu. In 1989, the land holding per capita was 36.5 mu and the arable land area
was 3.45 million mu, accounting for 30.8% of the total area. The present arable area is
1.035 million mu, the grassland area is 6.3594 million mu, accounting for 56.7%,
including part of the arable land and suitable land for forest. The existing forest area is
0.9635 million mu. The water area is 0.723 million mu, of which 0.163 million mu is
covered by the Yellow River and 0.551 million mu is covered by Ulansuhai Nur. The
non-agricultural land area is 0.9297 million mu, accounting for 8.3%, of which:
0.1907 million mu is the village and urban area, 0.25 million mu is the land for special
use, 0.236 million mu is the land for transportation, 0.253 million mu is the trench
area. The area of land difficult to be used is 0.43 million mu, accounting for 3.8%, of
which: 15,000 mu is saline-alkali wasteland, 0.172 million mu is desert and 0.243
million mu is the exposed rock area.
②Wild Plants and Animals
There are total 19 families, 33 genera and 69 species of woody plants in the
banner, of which there are natural forests such as Chinese pine, juniper, arborvitae,
white birch, Morus mongolica and Tilia mongolica, etc.; there are total 75 families,
280 genera and 503 species of woody plants in the banner, of which the compositae,
gramineae, leguminosae, rosaceae, and chenopodiaceae have the largest quantity ratio,
accounting for 48.2%. There are 240 species of forage plants, of which more than 100
species have large quantity and high quality. There are 305 species of wild plant
medicinal materials, of which more than 100 species are very important, most of
which are produced in Ural Mountains. The phytoplankton mainly grows in
Ulansuhai Nur, etc. and includes total 86 genera, of which there are 28 genera of
chlorophyta, 25 genera of bacillariophyta, 18 genera of cyanophyta, 5 genera of
euglenophyta, 4 genera of pyrrophyta, 3 genera of chrysophyta, 2 genera of
cryptophyta and 1 genus of xanthophyta. The fungi include mushroom, puffball, long
thread moss and nostoc commune, etc.
At present, wild animals living in Ural Mountains and other regions include
Tuanyang, goral, roe deer, fox, badger, stoat, wild fox, hare, hedgehog and ground
squirrel, etc., of which Tuanyang and goral are the national second class protection
animals. There are a large number of birds in Ural Mountains and Ulansuhai Nur,
which is one of China's important treasure houses for bird resources. It has been listed
as the national bird sanctuary. Birds under the national protection include mute swans,
whooper swan and spot-billed pelican the three kinds. There are 65 species of
zooplankton in Ulansuhai Nur, including 14 species of protozoa, 33 species of rotifer
and 10 species of cladocerans.
(3) Mineral Resources
There are abundant mineral resources in the banner. There are more than 30
kinds of minerals known, including iron ore, gold, coal, potash feldspar, mica,
dolomite, bentonite, gypsum, fluorite and pyrite, etc. In addition, there is lead, zinc,
niobium, tantalum, beryl, allanite, phosphate ore, marble, perlite, ore sand, swelling
powder, salt, saltpetre, oxytetracycline dihydrate and other mineral reserves.
2) General Situation of Social Economy
In recent years, Urad Front Banner gives full play to its advantages in resources,
accelerates the industrialization, urbanization and agriculture & livestock husbandry
industrialization. Its economic development has stepped into the "fast track" and the
comprehensive competitiveness continues increasing. The banner has continued to
hold the title of China Western top 100 banners (counties) for four consecutive years.
In 2007, the gross value of production of the whole banner reaches 5.5 billion Yuan,
with an average annual growth of 19.2%; GDP per capita reaches 2,227 U.S. dollars.
The financial revenue is doubled 1 year ahead, which was expected to reach 730
million Yuan last year. The per capita disposable income of urban residents and per
capita net income of farmers and herdsmen are expected to reach 10,400 Yuan and
5,300 Yuan respectively. Fixed investment of 12.5 billion Yuan is achieved in four
years, which is 2.4 times more than the gross investment in the previous five years.
(1) Industrial economy increases powerfully, economies of scale improve
significantly
In 2007, the gross industrial output value of the whole banner reaches 5.77
billion Yuan and the five major pillar industries including chemical industry, electric
power, mining building materials, paper making, and agricultural & livestock
products processing are formed; the taxation of Urad Electric Power and Dazhong
Mining Industry exceeds 1 billion Yuan respectively, Urad Chemical and Linhe
Chemical rank among the top 100 industrial enterprises of Inner Mongolia, Wulashan
Industrial Parks and Shadege Industrial Park begin to take shape, the clustering and
bearing capacity is enhanced significantly. The development order of mineral
resources becomes better and the taxation of small mining enterprises exceeds 80
million Yuan, which is becoming the important support for the new round of
economic growth.
The economic foundation of agriculture and livestock husbandry becomes firmer
and the new countryside construction is earnestly propelled
In 2007, the total livestock quantity of the whole banner is expected to reach
3.802 million heads, which is 2.043 million heads more than that in 2003. The gross
output value of livestock breeding reaches 604 million Yuan. In 2006, it was awarded
the "National Advanced Banner (County) in Food Production". The finely cultivated
tomato, sunflower, medlar and other major economic crops achieved large-scale
planting and the economic benefits improved significantly. The total investment in
four years is 305 million Yuan and six stages of agricultural development, land
reallocation, human and livestock drinking water, drain dredging, water-saving
irrigation and other construction projects of water conservancy works have been
successively completed. The auxiliary construction of farmland of 0.3 million mu is
completed, the newly increased irrigation area is 0.568 million mu, which solves the
drinking water safety problem of 61,000 persons and 196,000 heads of livestock.
984,000 mu of passage, market town and village greening as well as farmland shelter-
forest is completed in four years with the forest coverage increased by 4%. Actively
implement the projects of enriching the people by industry, strengthening farmers by
foundation, home management, improving quality and transfer, and harmonizing the
villages, which effectively alleviates the problems such as the "water expansion and
water deficit" restricting the development of agricultural and pastoral areas.
(2) Urban construction is accelerated comprehensively, infrastructure is
improved significantly
Urad Front Banner invests initiation fund of total 310 million Yuan in four years
and drives the investment of 2.1 billion Yuan in urban construction through the
method of city management. 13,000m of urban roads and 400,000m2 of greening area
are constructed, 820,000m2 of residence is developed, 273,000m2 of public buildings
is completed, the urbanization rate increases from 27.7% in 2003 to 31.7%. Five
major function areas including commerce, administration, residence, public services
and entertainment have been basically formed in Wulashan Town. Under the premise
of "zero liability", achieve the asphalt pavement in each town and comprehensively
carry out the project of extending asphalt pavement to each village. The asphalt
pavement rate of administrative village and natural village has reached 72% and
35.5% respectively.
(3) Develop strategic strength, promote development and the vitality is enhanced
significantly
The total paid-in investment in the four years of attracting investment is 6.28
billion Yuan, which is 4 times more than that of the previous five years. It has
successively introduced many foreign and domestic famous enterprises such as APP,
COFCO, Baotou Steel, ELION and Guoxi, etc. The expressway, tomato processing,
Yellow River Bridge, sewerage treatment, coal logistics parks and other large number
of key projects have been built in Urad Front Banner, which greatly enhances the
economic strength and development vitality. Actively enlarge the financing platform,
set up urban development investment company and get total 52 million Yuan of loans
from China Development Bank and 60 million Yuan of loans from other financial
institutions, which effectively alleviate the situation of no money for construction.
4.1.2.2 Urad Middle Banner
1) Natural Environment
(1) Geographic Location
The project is located in Delingshan Town, Urad Middle Banner, Bayannur City
of Inner Mongolia Autonomous Region. Urad Middle Banner is located in the west of
Inner Mongolia and the northeast of Bayannur City with the geographic coordinate of
E107°16′~109°42′ and N41°07′~42°28′. It marches with Mongolia in north, neighbors
Damao Banner of Ulanqab League and Guyang County of Baotou City in east,
neighbors Urad Front Banner, Wuyuan County, Linhe City and Hanggin Rear Banner
in south, adjacent to Urad Back Banner in west. The whole banner is 203.8km long
from east to west, 148.9km wide from north to south, with a total area of 22,606
square kilometers.
(2) Geological Features
Urad Middle Banner has complex geological structure, including two first-level
tectonic units, i.e. with the boundary of the south edge of Chuanjing—Sanggendalai
Mesozoic depression, its north is Greater Khingan Mountains geosynclinal folded
system and its south is North China Platform. Due to the influences of tectonic
movements, plus the affects of several large-scale magmatic activities, the geological
structure is seriously damaged and some strata has flaws, folds, bends or even upside
down and breaking, which result in the generation and occurrence of various mineral
deposits with industrial value. This project is located in the Wolf Mountain—
Zhasitaishan Mountain Fold Belt with very complex geological structure, strata
changes and sedimentary formation, strong topography cutting and large relative
height difference. The rock constituents include: carbonaceous slate, limestone, mica-
quartz schist, quartzite, sericite schist, phyllite as well as the granite, pegmatite, quartz
veins and volcanic-sedimentary rock, etc. immersed in different periods.
Urad Middle Banner consists of 3 basic landforms: southern piedmont plain,
central mountains and northern hilly plateau, with significant regional differences and
transition changes. This project is located in the piedmont plain area of Urad Middle
Banner. The piedmont plain area, a panhandle of 120km long from east to west and
2~10km wide from south to north, belongs to Hetao Plain. It consists of piedmont
pluvial fan and Hetao alluvial plain with the south edge adjacent to the deposition
plain of the Yellow River. The overall topography is high in the west and low in the
east; in longitudinal direction, it is high in the south and north and low in the middle.
Its altitude is 1,020~1,048 m.
(3) Meteorological Conditions
Urad Middle Banner is a strong monsoon region in western China and sub-arid
region in mesothermal zone with significant continental monsoon climate, adequate
sunlight, rich heat, small quantity of precipitation, large evaporation capacity, strong
wind and much sand, short frost-free period, large temperature difference and four
distinct seasons. The meteorological data of the area where the project is located is
shown in Table 4.1-2.
Table 4.1-2 Meteorological Data of Urad Middle Banner
No. Content Value
1 Annual mean temperature 5.9 ℃
2Mean temperature in the coldest
month-11 ℃
3 Mean temperature in the hottest month 22~24 ℃4 Extreme minimum temperature -27.5 ℃5 Extreme maximum temperature 38.7 ℃6 Annual mean atmospheric pressure 87.12 kPa
7 Annual mean relative humidity 50%
8 Annual mean sunshine duration 3102 h
9 Mean annual precipitation 194.5 mm
10 Annual average wind speed 3 m/s
11Predominant wind direction
throughout the yearWN
12 Maximum depth of frozen soil layer 1.7 m (below ground)
13 Maximum snow depth 6 cm
14 Annual mean thunderstorm days 22.2 d
15 Maximum ice period 231 d
16 Minimum ice period 197 d
17 Mean ice period in 10 years 213.2 d
(4) Hydrological Features
Urad Middle Banner is divided into two water systems with the watershed of the
junction of Wolf Mountain hills with Ulanqab plateau. It is the Yellow River water
system in the south of the mountain and the continental river water system in the
north. Surface water resource is very poor in the banner and the total surface water
resources in the whole banner are 258 million m3, including 220 million m3 of water
from the Yellow River which is stable and reliable and used for the development of
agriculture. The project location belongs to the alluvium and diluvium phreatic water
of Hetao Plain, located in the piedmont alluvial-pluvial fan skirt area in the north of
Delingshan Town. Due to the hydrodynamic differentiation of ravine flood, the
distribution of the aquifer has obvious horizontal zonality from north to south, which
finds expression in that from north to south, i.e. from the top of the fan skirt to the
frontal zone, the aquifer particles change from coarse to thin and the aquifer thickness
becomes thinner, changing from 50-80m to 20-40m. The clay courses become thicker
and more and the water yield changes from large to small, from more than 1000m3/d
to 500-1000m3/d. The water level changes from deep to shallow, from 20-40m to 3-
5m; the water quality decreases with the degree of mineralization gradually changing
from less than 1 g/L to 1-3 g/L. However, generally speaking, the piedmont alluvial
fan aquifer, with coarse particles, large thickness, abundant water quantity, the buried
depth of most water levels of 5-20m and good water quality, is a good aquifer for
water supply.
River in the north of the project has three branch gullies, flowing across Hailiutu
Basin from north to south and flowing into Delingshan reservoir in the south, with the
drainage area of 1900km2. The upper main gully is intermittent river; there is clear
water trickle at the downstream; the river valley becomes narrow in mountain area
and becomes wide after flowing into Hailiutu Basin, generally 600~80 m and the
widest reaching 2000m.
(5) Soil and Vegetation
Soil types of Urad Middle Banner include irrigation-silting soil, aeolian sandy
soil, saline soil, meadow soil, chestnut soil and brown soil the 6 types. The irrigation-
silting soil is the main soil type in the irrigated areas of Urad Middle Banner with the
water diversion from the Yellow River and also the main soil type of the project
location; the aeolian sandy soil mainly distributes in the zone along the outer edge of
torrents alluvial fan in irrigated areas; the saline soil mainly distributes in the both
sides of the low-lying terrain, poor drainage areas and drained gullies in piedmont
plain; the meadow soil scatters in terraces along river and some saliferous wastelands;
the chestnut soil mainly distributes in the southeastern hilly regions; the brown soil is
the most major soil type of the whole banner and the main type of pastoral soil.
Urad Middle Banner is located in semi-desert zone with serious desertification,
sparse vegetation, small quantity of arable land, large quantity of wasteland and the
main body of desert steppe. The natural grassland has sparse and low vegetation, with
the main body of perennial under-shrubs and perennial tufted grasses.
(6) Animal and Plant Resources
The wild seed plants in Urad Middle Banner include 67 families, 255 genera and
426 species, of which: the plants with feeding value include 42 families, 150 genera
and 289 species with the pasture of grass family ranks top among the forage seed, 29
genera and 58 species; the secondary is compositae, 20 genera and 49 species; the
plants with introduction value include 5 families, 7 genera and 12 species; the plants
with medicinal value include 186 species, mainly including Ephedra, Rheum
Rhaponticum, purslane, stellaria root, Vaccaria, Root of Erect Hypecoum, Prunus
Mongolica, licorice, Bunge Corydalis Herb, Polygala, Cynomorium, dodder seed,
anemarrhena, henbane, rehmannia root, plantain seed, root of straight ladybeel,
oriental wormwood, dandelion, cocklebur, the stem or leaf of cattail, large-leaf
gentian root, desert cistanche and gromwell, etc.
According to the preliminary survey, wild animals living in the whole banner
include: wild ass, blue sheep, Mongolian gazelle, Tuanyang, goral, wolf, leopard, fox,
pheasant, chukar, quail, wild duck, Difu, white stork, magpies, crow, eagle, owl,
glede, common crane, swan, hare, Steppe Cat, badger, lynx, hedgehog, ground
squirrel, squirrel, and snake, etc.
2) Brief Introduction to Social Environment
(1) Administrative Population
Urad Middle Banner includes 3 villages: Hongfeng, Shilanji and Wuliangsutai; 5
towns: Delingshan, Hailiutu, Shihahe, Wengeng and Wujiahe; 8 Sumu: Bayin,
Bayinhatai, Bayinhanggai, Chuanjing, Hulesitai, Sanggendalai, Wulan and Xinhure.
Till the end of 2004, the total population of the whole banner is 139,867, increasing
by 1.12% comparing with the previous year. Among the total population, urban
population is 29,851, increasing by 7.26%; non-urban population is 110,016,
increasing by 0.42%. Among the non-urban population, rural population is 83, 615,
reducing by 0.47%; pastoral population is 24,762, increasing by 0.11%.
(2)Economic and Industrial Structure
Urad Middle Banner has been adhering to the development strategies of
"developing the banner with ecology, surviving the banner with opening,
strengthening the banner with industry, enriching the people with livestock breeding
and promoting the industrialization", which has brought about the steady growth of
national economy. In 2006, GDP of 876.85 million Yuan was completed, 10.9% more
than that of the previous year calculated according to comparable prices. Of which:
the added value of the primary industry was 468.06 million Yuan, increasing by 3.4%;
the added value of the secondary industry was 212.73 million Yuan, increasing by
33.6%; the added value of the tertiary industry was 196.06 million Yuan, increasing
by 9.1%. The industrial structure has been further adjusted, from 56.8: 20.4: 22.8 of
the previous year to 53.4: 24.3: 22.4.
(3) Enterprises and Industrial Park Economy
Jinquan Industrial Park is the heavy chemical industry base planned in Bayannur
City, which was approved by the People's Government of Inner Mongolia
Autonomous Region in 2003. Its long-term planning area is 50km2 and the short-term
planning area is 20km2; Jinquan Industrial Park has introduced 17 enterprises such as
Yuanxin Nickel Industry, Fubang Magnesium Industry, Hengde Coking, Yongxing
Mining, Ronghua Mining, Yintai Ferro Alloy, Zhengxuan Chemical Industry, Xilike
Silicon Material and Jinnuo Chemical Industry, etc. developing coal chemical
industry, chromium chemical industry and nickel smelting, with the fixed assets
investment reaching 320 million Yuan and the employees more than 1,800.
(4) Port Economy
Urad Middle Banner owns the national category-1 seasonal landway port-
Ganqimaodao Port. Its import and export growth is rapid. In 2006, the total volume of
foreign trade of the whole banner achieved 36.26 million Yuan. Of which: the total
import was 17.46 million Yuan and the total export was 18.8 million Yuan.
4.1.2.3 Urad Back Banner
1) Natural environment
(1)Geographic location
This project is located at the Industrial Park of Urad Back Banner, which is in the
northwest of the city of Bayannao'er in Inner Mongolia autonomous region at the
north latitude of 40°40′~42°22′and the east latitude of 105°14′ ~107°36′, with the
Yinshan Mountains crossing the region from west to east, next to Urad Front Banner
and Urad Middle Banner at the east, abutting on Alxa Left Banner at the west,
connecting with Hangjin Back Banner and Dengkou County, bordering the State of
Mongolia at the north with a 195.25km borderline. With the length of 210km from
east to west and the width of 130km from south to north, covering an area of 24925
km2, Urad Back Banner has the largest land area within Bayannao'er with its
governmental office 50km away form the Linhe District of Bayannao'er.
(2)Topography and physiognomy
The topography and physiognomy in Urad Back Banner are complicated with the
Yinshan Mountains crossing the southern area, forming a watershed between Hetao
Plain and the Northern Plateau. The entire landform can be divided into mountainous
region, by 15.1%, low mountains and hills, by 10.3%, sand gravel Gobi Plateau, by
52.9%, Gobi dunes and sands, by 20.4%, and piedmont alluvial plain, by 1.3%. There
are six major runways within the region, featured by flash flood when heavy raining
while in dry season, dried up. The physiognomy is higher in the southern part than
that in the northern part of the region, averaging over 1500 meters above sea level
with a peak at 2365 meters, belonging to high and cold zone. The major mountains
are Erlangshan Mountain and Zagela Mountain.
(3)Meteorological conditions
Located at the desert zone of Inner Mongolia plateau, belonging to continental arid
and semiarid region in temperature-tropic zone, Urad Back Banner is featured by
continental climate, where the climate is arid, less but concentrated rainfall, high
evaporation, dry and windy, great difference in temperature during day and night and
plenty of sunshine, with the annual mean air temperature of 3.0-6.8℃, the yearly
maximum mean air temperature of 37.4℃ and the yearly minimum mean air
temperature of -37.1℃ according to yearly meteorological data. The annual freeze-up
period is five months with a maximum depth of frozen ground by 1.8m. The yearly
mean amount of precipitation is 115-250mm, asymmetrically concentrating on June to
August, accounting for about 70% of the total rainfall in the year. The yearly mean
evaporation is 2014mm, the annual mean sunshine duration is 3098-3250 hours and
the yearly strong wind (wind velocity) is ≥17.0m/s.
(4)Hydrogeology
The surface water within the region of Urad Back Banner is divided into two
major water systems, south of the watershed is the external drainage on the Yellow
River erosion basis, totally 13 runways, most of which are intermission rivers with
less water; north of the watershed is the interior drainage, running from south to north,
finally flowing into the Gobi and deserts areas within the Banner and Mongolia,
almost no surface runoffs can be seen owing to less water amount. The underground
water is mainly comprised of water from atmospheric condensation infiltration,
leakage from irrigation channels and mountain lateral seepage. The total amount of
the average water resource of the Banner is 21297m3,of which the annual surface
runoff is 5427 m3,and the underground water is 15980 m3,with a total workable
underground water resource of 8910 m3. In terms of geology, the formation lithology
is mainly made up of loam soil, sandy loam and fine sand, under the stratum below
2m-50m is sandy loam and fine sand, below 50 meters is coarse sand, gravels and
pebbly sand.
(5)Vegetation and creatures
Of abundant wildlife resources, there is Ovis ammon, bharal, wild ass,
Mongolian gazelle, fox and wolf and there are 430 species in 63 families of wild
plants, of which cynamorlum herba cistanches, known as the “Ginseng in desert”, is a
precious medicinal herb with an annual output to 100000 kg. In addition,
Cynomorium coccineum and black moss have long enjoyed a good reputation, selling
all over the country. At present, the primitive ecosystem in this region does not exist
any longer; the surface vegetation has been basically replaced by artificial vegetation
due to severe desertization.
(6)Soil
The soil in Urad Back Banner has 6 soil groups, 13 subgroups, 60 soil genus and
4 non-pedological features, totally in 16 soil mapping units. The distribution of
agrotype from southeast to northwest in turn is brown soil, weak brown desert soil
and gypsum brown desert soil and even a small quantity of mountain chestnut soil in
the areas above 2000 meters. The mound meadow soil is formed along intermittent
rivers, in flood plains and at the edges of mountain diluvia sectors under the influence
of underground water. There is a small amount of swamp soil and meadow soil
distributing over the low-lying wetlands, among which solonchak scatters. The grey-
brown desert soil covers the largest area in the Banner, by 50%, and the brown oil, by
25% and non-pedological features, by 17% and other soil, by 1%.
2) Profile of social environment
(1)Posture of economic development
Since the reform and opening, the gross amount of GDP of Urad Back Banner has
been hovering at the backward of Bayannao'er. Since 2000, especially since 2002, the
gross amount of economy and per capita index of Urad Back Banner have presented
the impetus of rapid growth.
In 2005, the gross amount of economy of Urad Back Banner increased from
0.44676 billion Yuan at the end of the Ninth Five-Year Plan to 1.5 billion Yuan, equal
to the summation of the entire Ninth Five-Year Plan period, reaching 3400 dollars per
capita, yearly increasing by 33%, with the proportion of the three industries reaching
to 7.6:66.7:25.7, resulting in financial total revenue of two hundred and seventy five
million Yuan, 9.3 times of that at the end of the Ninth Five-Year Plan, increasing by
74%,with the economic output leaping to fourth of the City.
In 2005, the urban per capita disposable income and the per capita net income of
farmers and herdsmen of the Banner respectively reached 7283 Yuan and 2097 Yuan,
keeping the double-digit growth. The growth rate of the five indexes of GDP,
financial revenue, industrial added value, urban per capita disposable income and
fixed asset investment for the third consecutive year ranked among the forefront of
the city and in 2004, the Banner stepped into Top 100 of the national counties with
countrywide economy fast increased,
(2)Urbanization development
During the period of the Tenth Five-Year Plan, one hundred and ten million
Yuan was invested in traffic and road construction, newly, alterably and additionally
constructing the road of 340 km with the total length of highways open to traffic
throughout the Banner reaching 1000 km, initially shaping the “four-horizontal-three-
vertical” traffic network. The Gu-Cha Line and Shan-Qing Line had been altered into
Asphalt pavement while Chuan-Ao Highway, Sai-Na Highway and Border Protection
Highway had been thoroughly refitted. The traffic conditions in farming and
stockbreeding areas had been further improved with 16 rural roads of 340km been
repaired. As of the end of the Tenth Five-Year Plan, there was one 220 kilovolt power
transmission station with one under construction, two 110 kilovolt power transmission
stations and 35 kilovolt power transmission stations within the Banner with the total
mileage of distribution lines reaching 1100 km and the yearly total capability for load
increasing to 350,000 KW.
(3)Economy in farming and stockbreeding areas
At the end of the Tenth Five-Year Plan, the total cultivated area of the Banner
reached 70,000 mu and the livestock population reached 727,200. 250 million Yuan
had been accumulatively invested in the development and construction in farming and
stockbreeding areas, focusing on the projects such as return grazing land to grassland,
ecological migration, sand source control, ecological bond, natural forest protection,
returning land for farming to forestry, agricultural comprehensive development,
human and cattle drinking water, conservation of water and soil and irrigation and
water conservancy construction, constructing 1360 standardized sheds, 560 silage
pits, 80 drinking water projects, 214 electromechanical wells. The newly increased
forest eco-construction area had been accumulatively reached to 1,312,000 mu in five
years, of which afforestation is 36,000 mu, the enclosed area, 1,006,000 mu and the
air seeding, 27,000 mu.
(4)Social undertakings
During the period of the Tenth Five-Year Plan, the fiscal expenditure used for
science and technology, education, culture, sanitation and sports reached 160 million
Yuan, an average increase of 18% year by year. Based on the thinking of “integrated
resources and centralized education”, after removing and incorporating nine schools,
the government invested 11,100,000 Yuan in building up the Mongolian nationality
Middle School, No.2 High School of the Banner and the teaching building of Huhe
Central School and invested 3,100,000 Yuan in advanced teaching equipment for such
schools. With further improvement of medical and health conditions, 11,900,000
Yuan was invested to strengthen the rural three-tertiary medical and preventive health
care network, initially establishing the emergency mechanism for sudden attacks of
public health events, effectively preventing the spread of SARS epidemic. With the
health development of culture, sports, broadcasting and TV undertakings, 871
medium-waves broadcasting transmitting station had been restored and the cable TV
network had been reformed with the coverage of broadcasting and TV respectively
reaching 98% and 95%.
(5)People's Livelihood
During the period of the Tenth Five-Year Plan, 6801 urban employment
positions had been added to in five years, the re-employment of the laid-off and
unemployed person was 3030 persons (times), controlling the registered
unemployment rate in cities and towns under 4.7%, accumulatively transferring 4363
surplus labor force in farming and stockbreeding areas. The standard of urban
subsistence allowance program had been increased for three times during five years,
effectively guaranteeing the basic living demands of 8371 person in 2982 households.
The government took the lead in piloting the minimum living standard security
system for farmers and herdsmen, including 671 persons in 200 households into the
first coverage. The project of poverty-relief development subject to “village-based
poverty-relief development” and “village-integration advance” achieved positive
results, from which 10,600 persons benefited. And all the policies benefiting the
people had been fully implemented.
(6)Cultural relics and historic sites
Cultural relics and historic sites include Yinshan rock paintings, stone-
chambered tomb groups, the inner and outer city walls and wall barriers of the Great
Wall in the Zhao, Qing and Han Dynasties as well as the fossils of Protoceratops and
the fossils of Ceratopsian eggs in three places.
4.1.2.4 Wuyuan County
1) Natural environment
(1)Geographic location
Wuyuan County is located o n the west of Inner Mongolia Autonomous Region,
at the middle of Bayannao'er, on the north bank of the Yellow River and in the middle
of Hetao Plain, at the east longitude of 107° 35′20〞-108° 37′50〞 and north latitude of
40° 46′30 〞 -41° 16′45 〞 , next to Urad Front Banner at the east, bordering Linhe
District at the west, across the Yellow River from Hangjin Banner at the south, north
of Yinshan Mountain, bordering Wujia River and connecting with Urad Middle
Banner, covering an area of 2493km2 with the total population of 280,000 (2004),
governing seven townships: Longxinchang Town, Taerhu Town, Xinzhonggong
Town, Tianjitai Town, Shengfeng Town, Bayintaihai Town, Yindingtu Town and
state-own Jianfeng Farm.
(2)Topography
The territory of Wuyaun County belongs to the Yellow River alluvial plain since
the Yellow River is running through the region from west to east at the south-
southwest. The topography is featured by a slight slope, high southwest and low
northeast, with a natural slope at 1/5000 ~1/7000 from west to east and 1/8000 ~
1/10000 from south to north, and the ground level is 1 019~1 035.3 meters and the
highest point above sea level is 1042 meters. The physiognomy can be divided into
terrace, erosion accretion topography, the aeolian dune in accretion topography
according to the cause of formation or alluvial plain, dunes, lake, high land and low-
lying land according to conformation.
Plain land: shaped by deposition and erosion and warping irrigation from the
Yellow River for a long time, covering 91.8% of the total land area of the county.
Highland: flood-plain bench formed by river beds and courses variance and the
hillocks by wind deposition, distributing all over the county.
Dunes: developed over the alluvial plain piled up by aeolian deposit, alternating
with lakes and deflation hollows. It can be divided into fixed, semi-fixed and flowing
dunes according to the height and vegetation density, where the fixed dune is low,
even and undulating, the semi-fixed one is often 1~1.5 meters at height with less
vegetation and the flowing one is much higher at the height of 2~15 meters, taking
shape of new moon with less vegetation but enclosed by artificial grass planting and
afforestation in recent years. There are totally 222200 mu sandlot in the county, of
which 120000 mu is unemployed, covering 3.33% of the total area, mainly
distributing over Minzu village, Bayan village, Haiziyan village, Yindingtu village
and Bashi village in the west and Jinqi village and Chengnan village in the south, also
scattering over other villages.
Lakes: often formed in deflation hollow, residual sandpits and ancient riverbed by
rising of underground water and irrigation impoundment, covering 1.4% of total area.
Low-lying land: often refers to the mounds and trenches, formed by vestiges of
ancient riverbeds and deflation hollow, zigzagging and scattering, where the land was
exploited in early time and now becomes wasted kaline soil and swampy land covered
with salinization due to the reclamation of highland and the increase of water level.
The landform along the bank of the Yellow River in Jinqi village, Jingyanglin village
belongs to floodplain, featured by narrow and long from west to east with width
between 150~300 meters, higher than the water level in the Yellow River by about 3
meters. Outside the floodplain is terrace of the Yellow River, 0.5~1 meter higher than
the floodplain, where the property line among the floodplain, terrace and the alluvial
plain is confused due to the reclamation for many years.
The soil structure in Wuyuan is formed based on the development and variation of
the alluvial deposits from the Yellow River, belonging to intrazonal soil, generally
through the stages of deposition and erosion, meadow, salinization, paludification and
irrigation slaking. According to the result of the second soil census in 1983, the soil
can be divided into 5 soil groups of irrigation-silting soil, solonchak, alkali soil,
aeolian sandy soil and meadow soil in 8 subgroups, 26 soil genus and 268 soil local
types.
The bulk density of soil is between 1.32~1.51 with the scope of porosity by 41.6~49.81%, commonly in basicity. The soil nutrients comprise of rich kalium, medium
phosphorus and lower OM and total nitrogen, where the equilibrium content of
available K is 305.2ppm, exceeding the standard of Class I, the equilibrium content of
available P is 11.26ppm, belonging to Class III, the equilibrium content of total
nitrogen is 0.0732%, belonging to Class IV, the equilibrium content of OM is 1.109%,
belonging to Class IV, according to the grading standards of national soil nutrient
contents.
The soil texture and configuration is very complicated in terms of areal distribution,
featured by: much sandiness soil covering 40.41% of the total area, over Minzu
village, Fengyu village, Bayan village, Haiziyan village and Bashi village in the west
or northwest area of the county; much red mud soil covering 40.87% of the total area,
over Shengfeng, Hesheng, Chengguan and Meilin villages; the proportion of the
mineral soil and loamy soil is much larger, respectively covering 38.5% and 38.2% of
the total area, over Jinqi and Jingyanglin villages close to the Yellow River; the loamy
soil is of the largest area covering 59.23 of the total area in the eight villages of Nairi,
Yongli, Shanhe, Xiangyang, Fuxing, Taohai, Rongfeng, Chengnan in the middle of
the county. With severe soil salinization, the salinization area is 249,500 mu,
covering69.11% of the total area in the county.
(3)Engineering geology
As for geotectonic element, Wuyuan belongs to the latitudinal tectonic belt from
Yinshan Mountain and Tianshan Mountain, and changes into inland downfaulted
basin under the impact of Neocathaysian tectonic system, becoming part of Erdos
platform depression, where the base is Archean metamorphic rocks. Depressed at the
end of Mesozoic Era, the landform receives continental deposit; during the Himalayan
orogeny in the Tertiary period, massive and thick deposits from the Tertiary period
piles up since the piedmont depression begins to break and the Hetao Basin rapidly
sinks due to heavily swelling of Yinshan Mountain, when the climate is dry and hot,
the deposits are oxygenized into red stratum with higher salinity.
At the beginning of the Quaternary Period and Lower Pleistocene Epoch, the Hetao
Basin sinks greatly, causing much flood infusion, where the all the tidewater stops at
the basin due to poor drainage conditions, forming massive and thick lacustrine
deposits that further develop in Medio-Pleistocene. After so many times of changes of
depths, the chemical salty materials such as the lime concretion, gypsum and Glauber
salt have been formed when the lake water move back, increasing the salinity in the
stratum.
At the end of Medio-Pleistocene to Plio-Pleistocene (about two million years ago),
the Hetao Depression gradually increases and the rivers at the edge of lake basin are
eroded by headwater, so the Hetao Basin, Wulanbuhe Basin and the basins outside the
region are gradually connecting with each other, forming the beads-shaped river
course during the Yellow River infancy, which corrodes heavily without any
accumulations. Till Holocene Epoch, (about 500,000 years ago), the Yellow River
began to deposit, generally covering the lacustrine formation with the alluvial deposits
from Yellow River, mainly comprising of clayey loam, subclay, and interbedding of
silt and medium and fine sand. During this period, piedmont proluvial deposits
develop rapidly to form lacustrine formation sector groups and gradually forming
piedmont aggraded flood plain due to dry and hot climate. During the development of
piedmont aggraded flood plain and the Yellow River alluvial plain, the two gradually
connects with each other to form Hetao Plain.
The entire territory belongs to Hetao Plain, covered with loose stratum of the
Quaternary Period, depositing thicker lake facies stratum, where the upper is the
alleviation and aeolian deposits with the main lithology of interbedding of fine sand,
silt and sand clay, featured by clear sand bedding by 10-70m of thickness; the middle
is the alternating layer between lake and river, with the main lithology of interbedding
of sludge fine sand and clay; the bottom is the massive and thick lacustrine deposits
layer from the Quaternary Period, with the main lithology of sludge and sand clay.
The base landform belongs to Yellow River alluvial plain and the engineering
geology is basically the same as that at the county seat, where the surface layer is
mainly comprised of Yellow River alluvial deposits, with the lithology of fine sand,
silt and clay, under which is the lacustrine deposits, with the lithology of sub-clay and
clay with gravel layer among them. The base holding capacity: it is 10-14t/m2 for sub-
clay with maximum frozen depth of 1.23m and the underground water of 1-2m, from
the overall perspective, the base engineering site is very good without obvious
unfavorable geology, basically suitable for use of land in construction.
(4)Gydrologic condition
There are so many deflation hollows formed by Yellow River aluvial deposit
under the impact of aeolian erosion for a long time and the natural moats formed by
erosion of Yellow River’s change its course, which gradually form into various lakes
(locally called Boer Holes) due to water accumulation all year around. There are 171
lakes with the area more than three mu, covering a total area of 54,500 mu, of which
there are five lakes with the area more than 1000 mu, covering an total area of 10,600
mu, 37 lakes with the area more than 100 mu, covering a total area of 13,300 mu.
There are 116 lakes with the depth mare than 1.5m, covering a total area of 27,100
mu. In 1986, the used lake area was 38,000 mu, accounting for 70%. Most of the
lakes distribute over the towns of Taerhu, Yindingtu and Xingongzhong in the west
and Taohai town in the south and occasionally scattering in Shengfeng town and
Longzhen town in the east of the county.
(5)Hydrogeological condition
The underground water distribution is broad and abundant, comprising of
phreatic water, shallow confined groundwater and deep confined water. The shallow
water and phreatic aquifer from the Quaternary aquifer have an average thickness of
60m with the peak at 120m, where the embedding depth of phreatic water is relatively
shallow and the LWL is 2~3m away from the surface with an annual variation of 1~2.7m, deeper in higher land and shallower in low-lying land and irrigated area. The
monthly variation of the embedding depth changes greatly due to the leakage of
irrigation channels and irrigation water, featured by the underground water level rises
during irrigation and decreases when irrigation is stopped.
The deep confined water in the settled layer of Lower Pleistocene at the mid-
Mesozoic Quaternary is mostly buried under the stable dirt bed, where the semi-
confined aquifer (Q+4 aquifer in short) has the most thickness. Under the impact of
tectogenesis, the county can be divided into three hydrogeological zones: the latent
uplift zone in the south along the Yellow River where the base is latent uplifting and
the buried depth of aquifer plate is 50~130m and the thickness is 30~100m and the
specific capacity per well is 5~ 10m2/h; the deep depression zone centered on
Yongsheng at Yongli village and Liansheng at Yindingtu village in the middle of the
county, where the buried depth of aquifer plate is 130~210m and the thickness is 100
~160m and the specific capacity per well is 10~20m2/h; and the shallow depression
zone in the north and east areas of the county, where the buried depth of aquifer plate
is 160m and the thickness is 90~100m and the specific capacity per well is 5 ~10m2/h. According to the distribution of phreatic water, the county can be divided into
bittern zone, salt water zone, upper-fresh-bottom-salt water zone and fresh water
zone.
Bittern zone: mainly distribute the south and southwest uplifts , including
Fuxing, Jingyanglin and Jinqi villages, taking the shape from east to west, with the
scope of 6~10km, the thickness of 30.53~166.68m, the total dissolved solid of 10g/l
and the hydrochemical type is Cl-Na brine with higher salinity in the soil. According
to the analysis on the soluble salt drilled from Nianfang, Gedan in Jinqi village, the
salinity in the earth layer from 0~20m is 0.25~0.50%, and 0.42~0.57% from 30~
50m, more than 0.5~0.75% in the deeper part and 0.25 ~0.5% at the lowest part,
where the salinity in water is the same as that in soil. The salt source is caused by
deep brine contamination under the influence of subsidence tectogenesis, where the
mineralization of groundwater is up to 50 ~ 76g/l, mainly comprised of CaCl2 and
MgCl2 , including bromine, iodine and boron. The severe soil salinization leads to salt
lake and benches.
Salt water zone: distribute from south to north, taking the shape of a standing
cup, covering an area of 2~9km, including Meilin, Shahe, Hongwei in Xiangyang
village, Fnegle in Yindingtu village and Heping and Heyi in Hesheng village, with
mineralization of water of 5~10g/l, and the hydrochemical type is Cl-Na ,Cl-Na·Mg
and Cl·HCO3-Na·Mg and the thickness of salt water is 85.88m.
Upper-fresh-bottom-salt water zone: distribute from Chengnan village stretching
from east to west to Yongsheng in Xiangyang village and then turning to west to
Qingfeng in Fuxing village in the form of a strip, including Jianfeng Farm in the east,
with mineralization of water of 1-3g/l, and the hydrochemical type is Cl-Na, Cl-
Na·Mg and Cl·HCO3-Na·Mg and the interface of salt and fresh water is averagely
65m and the mean aquifer thickness is 54.5m.
Fresh water zone: distribute in Nairi and Yongli villages and in the east of the
county seat, with mineralization of water of 0.54~2.99g/l, most of 1g/l and 2.99g/l in
local areas. The thickest fresh water layer is 166.68m with the base plated buried in
212.94m at Yonglian in Yongli village and the thickness of the aquifer centered on
Changfeng village is about 78.33m and the hydrochemical type is HCO3-Na·Mg,
Cl·HCO3-Na·Mg and HCO3·Cl-Na·Mg·Ca with a lower content of soluble salt in the
soil.
Replenishment runoffs and drainage conditions: the supply of underground
water is mainly from irrigation water, annual average of 669.5 million m3/h, and then
annual average of 111 million m3/h from infiltration of atmospheric precipitation, and
the comprehensive replenishment of annual average of 780.5 million m3/h. the inflow
and outflow of groundwater runoff is basically the same, featured by seeping when
the Yellow River water level is high and regressing when the level is lower with a less
difference.
Located at the lower reaches of Hetao, Wuyuan is the borderland of the
collection area of underground water, where the groundwater is flat and slow and
inadequate drainage that is mainly by vertical transpiration, crop evaporation and then
by open drainage so as to reduce leakage of irrigation water.
Dynamic variation of groundwater: the dynamic variation of groundwater is the
result of the comprehensive integration of various elements, mainly affected by
irrigation and rainfall evaporation, the annual variation of the water level is basically
equal to the variation of irrigation water. During the autumn irrigation period from the
late of Oct to the beginning of Nov when the water demand is the largest while the
temperature is declining and the evaporation is weaker, the groundwater level is the
highest with 0.5~1m to the ground surface. After that, the soil is frozen and irrigation
stops, the groundwater level gradually decreases to the lowest during Feb to March
with 2~3m. From the beginning of April to the beginning of May, the temperature is
gradually increasing and the frozen layer is melted, so the groundwater level is
gradually increasing to 1.5~2.5m. At the middle of May when irrigation begins, the
groundwater level increases greatly to1 ~ 1.5m from the ground surface in June to
Oct, which indicates the cyclic variation of the embedding depth of phreatic water.
(6)Climate and weather
Wuyan County has four distinct seasons with fine weather more than rainy
weather and the transmittance of light of the air is very good with abundant light, the
intension of solar radiation is very strong with plentiful light energy resources and
heavy evaporation capacity; the total annual average sunshine hours are 3230.9 and
the percentage of sunshine in an average is 73%, the total solar radiation averaged for
many years is 153.439 kcal /cm2 and daily mean radiation amount is 420.4 cal /cm2
and the total amount of the annual physiological radiation is 75.185 kcal /cm2.
The annual mean temperature is 6.1℃ and the extreme maximum temperature,
36.4℃, extreme minimum temperature, -36.7℃; the amplitude of annual extreme air
temperature is 73.1℃, the annual amplitude is 35.9℃, daily amplitude is 14.2℃; the
annual evaporation is 2039.2mm; annual mean frost-free period is 158 days, of which
the shortest is 99 days and the longest is 220 days; the average annual thickness of
frozen soil layer is 100~120cm, where the plow layer is frozen in late Oct and melted
in late April with a frozen period of 180 days; the annual accumulated temperature
greater than or equal to 10℃ of daily mean temperature is 2 896.3℃, averagely for
years; the general trend of air temperature in the county is the higher in west part than
that in east part, descending from southwest to northeast with a difference of 0.8℃;
the past years’ average surface temperature is 8.7℃; located at inland, under the mild
influence of warm-moist current, the rainfall in Wuyuan County is less but
concentrated with an annual total amount of precipitation of 177mm; belonging to
arid area, the annual mean extreme absolute humidity of Wuyuan County is 0.16 HPA
and the relative humidity is 54%; being windy, the annual mean wind velocity of
Wuyan is 2.7 m/s.
The prevailing wind is northeaster in the year with frequency of 31%, most in
winter while southeaster is prevailing in summer and autumn. The orderliness of wind
velocity in a day is featured by gradually increasing after sunrise to maximum from
12~15 o’clock, and then deceasing gradually to minimum at 2~3 o’clock at night.
(7)Natural disasters
Flood: located in the arid desert area of the north temperate zone, Wuyuan has
less rainfall but greater evaporation with an annual mean rainfall of 177mm,
accounting for 8.7% of the annual evaporation amount of 2 039.2mm. All the water
needed by agriculture, herd and forest is from the Yellow River, belonging to Hetao
Irrigation Area where irrigation from Yellow River has adopted in earlier time. But
due to poor channel engineering and the variation of water level in Yellow River, the
flux in spring is the minimum of 148 cubic meters per second and the maximum in
autumn of 5100 cubic meters per second with a difference of 34 times, which causes
either the advantages or the disadvantages, resulting in floods, especially before
liberation.
Hailstone: one of the major natural disasters in this county, severer in west part
than in east part; severer in autumn than in summer; severer in the area with less
forests than that with more forests with an annual mean times of 7.2, the maximum of
18 times, concentrating on June to Sept, accounting for 81.7% of the total
occurrences.
Frosting: featured by longer cold period and shorter frost-free period, calculated
by 80% of the assurance rate, the frost-free period is 113 days, frosting year occurs
sometimes in Wuyuan County.
Rainstorm: though less rainfall, the rainfall concentrates on July to Sept, together
with low temperature and hails, causing the crops suffering from waterlog, which can
be divided into rainstorm, low temperature long range rainfall and crop-rotten rain
according to the difference seasons of crop seeding, growth and harvest.
Insects: the major pests of crops in Wuyuan include locust, wheat stem maggot,
cutworm, armyworm, weevil, mole criket, wireworm, ant cow, heart-eating worm,
spider mite and cabbage caterpillar, which are hard on agricultural production,
causing insect attack every year in Wuyuan County.
Earthquake: located at the Hetao fault, the geological structure of Wuyuan
County belongs to east-west direction fold and compressive zone of pressure fracture
with active tectogenesis, in a major earthquake zone.
Other natural disasters include rust disease (locally called jaundice), rodent,
snow damage, wind damage and dry-hot wind.
(8)Land resource
The total area of various land classifications within the Territory of Wuyuan
County is 3,739,300 mu, converting into 2492.9 km2, which can be classified into 39
kinds in 8 classifications according to the classification standards in national
Technological Rules of Survey About The Present Situation of Land Use.
The arable land is 1,607,600 mu, accounting for 42.99% of the total land area, of
which acreage planted is 1,561,500 mu, alternate field, 16,100 mu, reclaimed but not
planted field, 25,900 mu, flood land 600 mu, dry farmland (without irrigation) 2,300
mu and vegetable plot (arable land for vegetables including land used for greenhouse
and plastic tunnel), 1,100 mu.
Garden plot is 1000 mu, accounting for 0.03% of the total land area, of which
orchard is 550 mu and other garden plot is 460 mu;
Woodland is 128,200 mu, accounting for 3.43% of the total land area, of which
forest land is 90,000 mu, shrub land, 240 mu, open forest land, 17,900 mu, young
afforestation land, 14,500 mu, slash, 1000 mu, nursery, 4,600 mu;
Meadowland is 297,500 mu, accounting for 7.95% of the total land area, of
which natural meadow is 281,000 mu, amended meadow, 6,000 mu, artificial
meadow, 10,500 mu;
Residential, industrial and mining land is 144,600 mu, accounting for 3.87% of
the total land area, of which urban land is 10,200 mu, rural residential land, 129,900
mu, independent industrial and mining land, 1,300 mu, land for special use(graveyard,
cemetery and national defense), 3,200 mu;
Lands used for transportation is 24,100 mu, accounting for 0.64% of the total
land area, of which railway is 1,400 mu, highway, 5,800 mu and rural road, 16,800
mu;
Water area is 350,000 mu, accounting for 9.37% of the total land area, of which
river surface is 33,100 mu, lake surface, 25,400 mu, pool, 29,600 mu, unused pool,
14,200 mu, aquatic breeding pool, 15,300 mu, reed wetland, 100 mu, flood plain,
72,400 mu, canal and channels, 186,800 mu, moisture and soil construction, 2,700
mu.
Unused land (including the land hard to use) is 1,186,400 mu, accounting for
31.27% of the total land area, of which uneven ground is 11,700 mu, saline-alkali
land, 999,800 mu, swampland, 1,300 mu, sandlot, 120,700 mu, naked land(hardened
surface) 19,400 mu, ridge of field under two meters, 33,400 mu.
(9)Vegetations
At the beginning of [reclamation, the wild plants are luxuriate in here, as
reflected by the famous poetry of “Between the vast sky and the boundless earth,
flocks and herds appear as grass bends to wind”, where the natural vegetations include
Cacumen Tamaricis, dryland willow, precarious, reeds, Chinese wildrye, Tribulus
terrestris and wormwood. Since the reclamations from the Qing Dynasty, the
population has been gradually increasing together with the frequent reclaiming and
cultivating the wasteland, thus incurring to the declining of original vegetation
predominance. With the expansion of arable and irrigated area, the rising of
groundwater level and the aggravation of soil salinization, the vegetation communities
have been superseded by artificial vegetations.
According to census, there are more than 200 wild plants in 99 species of 15
families in the county with a vegetation coverage rate of 30 ~ 50%, where the
artificial vegetation is mainly comprised of farm crops and forest plantation. In 1994,
the area for farm crops was 1,019,900 mu, the forest land area was 254,500 mu, which
accounts for 33.8% of the territory.
There are six kinds of natural vegetations at present, respectively including: the
sand vegetation distributing over aeolian sandy soil and sandlot (such as white
Tribulus terrestris, caltrop, Agriophyllum aranarium, Artemisia desertorum and
liquorice); the drought-resistance meadow vegetation distributing over relatively
highland (such as Peganum harmala, Sophora alopecuroides and celery wormwood);
the wetland meadow vegetation distributing over the low-lying places under the high
mounds (such as Chinese wildrye, Melilotus officinalis (L. ) Pallas, chickling, reeds,
Xanthium sibiricum Patrin, Cirsium segetum Bunge, dandelion, China ixeris, semen
plantaginis, Herba Polygoni Avicularis, Johnson evening primrose and sedge); the
aquatic meadow vegetation distributing over the flat bogs with perennial or seasonal
water (such as reeds, polboschoenus sp, and Typha angustifolia); the salt-resistance
vegetation(such as Cacumen Tamaricis, Achnatherum splendens, white Tribulus
terrestris, narrow-leaved oleaster, and crawling reeds); the halophytic vegetation
distributing over the solonchak (such as Kalidium foliatum, Suaeda and
Halimocnemis).
(10)Wildlife
According to census, except the vanished Mongolian gazelle and wolf, the
wildlife in Wuyuan County includes fox, badger, rabbit, Pallas cat and hedgehog and
there are more than 200 wild plants, belonging to 146 species in 99 genuses of 35
families.
Where the wildlife includes rodents, birds, migrators, fish and frogs, of which the
fish belongs to two orders of Cyprinus-type and silurids-type and three families of
Cyprinidate, loach and silurids in 12 species of 11 families. Frog has the most
quantity with fewer turtle, mussel and shrimp.
Hydrocole animals include 12 species of hexapeopoda, 13 species of Cladoceran,
16 species of copepod and 16 species of protozoan. The benthonic animals belong to
three phyla of (mollusks, Annelida and arthropods) in four classes, mainly including
lake snails, Planorbis, Tubificidae, Black Tiger Shrimp and chironomus larva, which
are the natural baits for fish.
Wild plants mainly include purslane, Hippochaete ramosissimum, Iris ensata
Thunb, Cynanchum chinense, Lycopus lucidus Turcz, henbane, stramonium and
snakeweed, of which there are over 80 medicinal plants, including dandelion,
liquorice, cynomorium songaricum, Asiatic plantain seed and dodder; four species of
aquatic plants, including phytoplankton(such as frog spawn, diatom, Scenedesmus,
blue green algae, chlorella and Tetraedron spp); emergent aquatic plants (such as
Typha angustfolis L, Dysophylla yatabeana, reeds and scirpus maritimus); floating
plants (such as Myriophyllum spicatum, Umbrella plant, hornwort); submerged plants
(such as Potamogeton pectinatus, P .Malalanus and ottelia alismotdes). (Details in
attached Wild Plants Table)
2)Social environment
Wuyuan County is situated at the middle of Hetao Plain in Bayannao'er League,
close to Yellow River at south and next to Yinshan Mountain at north, neighboring
Urad Front Banner at east and bordering Linhe City at west, where the landform
belongs to Yellow River developing alluvial land, taking the shape of higher
southwest and slight low northeast with an average altitude of 1035m, covering an
area of 2492.9 km2. The total population is 297,872, of which urban population is
40,623, rural population, 257,249; including nonagricultural population of 86,364 and
agricultural population of 211,508; consisting of 19 nationalities, of which the Han
Nationality is 287,321, the Mongolian nationality, 6,417, the Hui nationality, 3,321,
Mandchous, 671 and others, 142.
In 2008, the total output value in Wuyuan achieved 4.659 billion Yuan, a growth
of 21.3 percent year-on-year, higher than the average level of Bayannao'er, of which
the primary industry achieved 1.498 billion Yuan, increasing 9.8% year-on-year; the
second industry achieved 1.769 billion Yuan, increasing 28.1% year-on-year; the
tertiary industry achieved 1.393 billion Yuan, increasing 25.1% year-on-year; the
structure of the three industries was adjusted from 35.9∶36.1∶28 of the last year
to 32.2∶38∶29.8. The investment in fixed assets reached 3.5 billion Yuan, increasing
15% year-on-year; the financial revenue reached 200,640,000 Yuan according to new
standard. The urban per capita disposable income reached 11,954 Yuan, increasing
22.2% year-on-year; the rural per capita net income reached 7,189 Yuan, increasing
33.7% year-on-year. The energy consumption per 10000 Yuan GDP decreased by
5.1%, the sulfur dioxide emissions decrease by 917t, the emission of chemical oxygen
demand decreased by 5029t and various indexes concerning energy conservation and
emission reduction were controlled within the scope of the requirements by the City
of Bayannao'er.
As the county seat of Wuyuan, Longxingchang Town, an important town of
commerce and trade at rural-urban fringe, is the political, economic and cultural
center in Wuyuan County with the most population, located at the northeast part of
the county, next to Hesheng village at east, Shengfeng village at the southeast;
bordering Shahe and Xaingyang villages; adjoining to Rongfeng village at south and
close to Meilin village at north, taking the general trunk canal as the border with Urad
Middle Banner. With State Highway 110 through the town and Bao-Lan Railway
setting a station in Wuyuan, Longxingchang Town governs 31 villages, 187
communities, 5 sub-district offices, 30 neighborhood committees with a total
population of 118,000, of which the agricultural population is 46,358 in 11624
households, employing 26,090, covering an area of 504km2 , of which the arable land
is 282km2,the urban area is 11.8km2.
4.1.2.5 Hangjin Back Banner
1) Outlines of natural environment
(1)Geographic location
Located at the west of the City of Bayannao'er, Hangjin Back Banner is situated
in the Hetao Plain, bordering Linhe Town at east, close to Wulanbuhe Desert and
Dengkou County at west, opposite to Hangjin Banner in Erdos City at south, backing
to Yinshan Mountain at north close to Urad Back Banner, with geographical
coordinates of east longitude 106°34′to 107°34′, north latitude 40°26′to 41°13′,
covering an area of 1644km2, and 87km in length from the south to the north and
52km in width from west to east.
Located at the middle-east part of Hangjin Back Banner, Shanba Town, the seat
of Banner government, is the political, economic, scientific, educational, cultural
center of the whole Banner, bordering Linhe Town at east, adjoining to Sandaoqiao
and Shahai towns at west, connecting to Erdaoqiao Town at south and close to
Manhui Town at north, with geographical coordinates of east longitude 107°02′to
107°14′, north latitude 40°48′to 40°59, covering an area of 206km2, and 20km in
length from the south to the north and 18km in width from west to east, of which the
arable land is 9363ha. The town governs 8 towns, 107 villages, 27 neighborhood
committees with a total population of 308,324, of which there are minority groups of
the Mongolias, Hui nationalities, Manchu and Daur, accounting for 1.6% of the total
population.
(2)Topography and physiognomy
The landform of Hangjin Back Banner is mainly comprised of three forms of
alluvial plain , aggraded flood plain and floodplain, taking the shape of higher
southwest and lower northeast, slightly declining from southwest to northeast with an
altitude of 1032-1050m.
(3)Characteristic of the climate
Located above north latitude 40°, Hangjin Back Banner belongs to continental
climate in temperate zone, featuring with desiccation, longer sunlight, strong diurnal
amplitude, the annual mean air temperature of 8.5℃, the annual mean rainfall of
138.2mm, the evaporation capacity of 2096.4mm, the day-night average temperature
difference of 8.2℃, the annual mean frost-free period of about 130 days, the average
wind velocity of 2.3m/s and the annual mean bold wind days of 19.9; in general, it is
featured by larger temperature difference between day and night, longer frost-free
period and the prevailing southwester and northeaster; the annual sunshine duration is
more than 3220 hour and the accumulated temperature is more than 3520℃,with a
sunlight rate of 73%, it is one of the areas with the most abundant light energy
resource in the country; it is one of the eight major gravity irrigation areas of the
country with 17 km of Yellow River flowing through the Banner, resulting in an
annual flow to cross the border of 22.6 billion m3.
(4)Land resource
The land area of the whole Banner is 2,650,000 mu, of which farming land is
1,750,000 mu, land for construction is 185,000 mu, land for residents and industry
and mining is 173,000 mu, traffic land is 12,000 mu, the unused land is 714,000 mu
and the reserve land for other projects industry is 2000ha, converted about 30,000 mu.
(5)Water resources
The Yellow River flows through the Banner for 17 km, where Wula River,
Yangjiahe River and Huang-ji Channel can averagely channel water amount of 0.88
billion m3; the general trunk draining canal flows through the north part of the
Banner, discharging an annual delivery volume of 0.12 m3,and the pondage of the
lakes and pools within the territory reaches 5,000,000 m3.
The groundwater resource is very rich with the annual gross amount of water
resources reaching 265,000,000 m3, of which the groundwater available yield is
45,100,000 m3,the groundwater resource with the mineralization of water less than
2g/L is 55,730,000 m3. At present, the annual groundwater available yield is
9,000,000 m3,buried at a mean depth of 1.93m, differing from mean 1.11m during
high flow period to mean 2.5m during low flow period with an annual mean variation
of 1.89m.
2) Outlines of social environment
The industrial economy in Hangjin Back Banner develops very rapidly and
industries such as wine and liquor manufacturing, tomato and vegetable, high-
preserved dairying, Strong flour and paper making form wood have gradually became
systematic, building up series leading enterprises represented by Hetao Liquor
Industry Group, including Yili, Tunhe, Hetao wood industry, Fumeng, Dahaoda,
Temier, Dahoutao and Mingxing. In 2007, the GDP of the Banner reached 5.788
billion Yuanand the financial revenue reached 372,000,000 Yuan.
Hangjin Back Banner is one of the important production bases for grain and oil
in our country, where the soil is fertile, featuring with favorable irrigation, strong
diurnal amplitude and full sunlight with unique conditions for development of
agriculture and animal husbandry, rich in producing high quality agricultural products
such as wheat, corn, apple and pear, tomato, honeydew melon, medlar, black and
white melon seeds with annual grain output of 400,000 t, of which wheat is 167,000 t,
corn, 228,000 t; vegetables, 300,000 t, oil materials, 25,000 t, tree mallow, 85,000 t,
melons, 88,000 t, medicinal materials 5,500 t; annual crop straw productivity reaches
1.6 billion jin, high quality pasturage is 200,000 y; the forest coverage of the Banner
is 27.7% and the total reserve amount of the vivid stumpage is 950,000 m3; the
livestock population of the Banner is 1,820,000, of which cattle is 44200, sheep,
1,580,000 and live pig, 170,000, annually producing 15,330,000 kg of mutton,
14,200,000 kg of pork, 90000 t of milk, which are the green and special products with
high quality. The Banner has great potential in the deep utilization process of grains
and oils, fruit series development, meat-packing, wood working, green food series
development and preserved warehousing and transportation.
With highways connected, transportation in Hangjin Back Banner is very
convenient, totally with three highways of Huang-Tuan, Lu-Ha and Bie-Deng from
south to north and Wu-Wu highway from west to east, reaching the mileage of
1700km, of which the black road surface is 410km, actualizing asphalt road
connecting to every town and the highway density of 1.03km per km2 . Ha-Deng
Expressway, State highway 110 and Jing-Lan Railway run through the territory and
Lin-Se Railway traverses through the Banner.
The education and medical treatment and sanitation undertakings in Hangjin
Back Banner are flourishing, having 13 middle schools, 3 vocational middle schools,
84 primary schools, 2 county-level hospitals, 8 health clinics in towns and townships
and Fendou Middle School is one of Top 100 in the country and the key school of the
autonomous region; the enrolled students in the Banner is 6330; Hangjin Back Banner
Hospital is the sole hospital of Class II, Grade A at the Banner or County level within
the city, with 280 beds.
The built-up urban area of Shanba Town, the seat of Banner government, is 7.74
km2 with an urban population of 105,000 and the population urbanization by 35%,
where the black topped road is 36 km in total, covering an area of 410,000 m2, 6.8m2
per capita, accounting for 97% of the total road area of the built-up urban area,
forming four-horizontal-and-four-vertical black topped road network. The green shade
coverage rate of the urban area is 25%, the public green land per capita is 5.3m2. The
underground drainage pipe is 64km in length, of which the drainage pine in
backstreets and lanes is 33 km, with a daily drainage capacity of 17,200 t; the
benefiting area from drainage in the build-up area is 90%. The popularizing rate of
urban tap water is 100%, with a daily water supply capacity of 14,000 t. The area of
centralized heat supply is 900000 m2 with a popularizing rate of heat supply by 65%.
The power supply lines have been alternated by 24 km with power supply assurance
by 100%. Pipe-lines of telecom communications have been alternated by 25km with
the popularizing rate of telephone by 50%. 2100 street lights have been installed,
achieving lighting engineering.
4.2 Evaluation on the situation of regional environment quality
4.2.1 Evaluation on the situation of air environment quality4.2.1.1 Monitoring items
According to the characteristics of the pollution source of the items and the
surrounding environment outlines, the monitoring items for the present situation of
the air and environment quality include conventional factors of TSP, SO2, NO2 and
H2S and NH3. At the same time, the observation of the meteorological elements such
as surface wind direction, wind velocity, air temperature and total cloud cover as well
as weather conditions and unusual circumstances have been recorded.
4.2.1.2 Monitoring spots
The monitoring sampling points for this situation monitoring have been set up at
the up wind and down wind directions of the proposed sites of the sewage disposal
project and recycled water supply project within the industrial zone as well as the
nearby residential settlements. Specific monitoring spots are shown in Fig. 4.2-1-4.2-
5.
Fig. 4.2.1: Monitoring spots for air environment within Urad Back Banner
Industrial Zone
Fig. 4.2.2: Monitoring spots for air environment within Ganqimaodao Industrial
Zone
Fig. 4.2.3: Monitoring spots for air environment for water supply engineering of
recycled water of the third drainage canal
Fig. 4.2.43: Monitoring spots for air environment for water supply engineering of
recycled water of the seventh drainage canal
Fig. 4.2.5: Monitoring spots for air environment for the sewage disposal project
within Urad Front Banner
Totally six monitoring spots have been set up, respectively two at the place one
km away from the up wind direction of the prevailing wind at the proposed site of the
treatment project of Ulansuhai Nur lake, two at the construction area and two at two
km away from the down wind direction of the construction site. (See Fig. 4.2-6)
Fig. 4.2.6: Monitoring spots for air environment for Ulansuhai Nur lake area
4.2.1.3 Monitoring time and frequency
At least seven days have been monitored during the whole period with a
frequency of four times per day and the sampling time is 08:00-09:00,11:00-
12:00,14:00-15:00 and 16:30-17:30, which is conducted in accordance with relevant
national norms.
4.2.1.4 Analysis method
The national standard methods have been adopted for monitoring of
environmental air quality and the analysis method for TSP, SO2 and NO2 is carried
out according to Table 2 of Ambient Air Quality Standard(GB3095-1996)and the
analysis method for,H2S and NH3 is carried out according to Table 8 of Discharge
standard of pollutants for municipal wastewater treatment plant(GB18918-2002).
4.2.1.5 Monitoring results
The results of ambient air quality monitoring for each sub-project of this project
are shown in Table 4.2-1-4.2-6。
Table.4.2-1 Monitoring results of the sewage disposal project and water supply engineering of recycled water within the Industrial
Zone of Urad Front Banner
Pollutants
Items
SO2 NO2 H2S NH3 TSP PM10
Daily
mean
Hour
mean
Daily
mean
Hour
mean
Hour
mean
Hour
mean
Daily
mean
Daily
mean
Proposed site
Concentration scope
mg/m3
0.014-
0.028
0.011-
0.051
0.007-
0.016
0.008-
0.024
Undetect
ed
Undet
ected
0.126-
0.364
0.078-
0.156
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 28.57 14.29
Shahaixinhong
Concentration scope
mg/m3
0.013-
0.027
0.012-
0.050
0.005-
0.015
0.005-
0.019
Undetect
ed
Undet
ected
0.145-
0.315
0.050-
0.164
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 28.57 14.29
Qingshan town
Concentration scope
mg/m3
0.019-
0.028
0.013-
0.051
0.009-
0.017
0.010-
0.041
Undetect
ed
Undet
ected
0.215-
0.379
0.082-
0.212
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 14.29 28.57
Agr-team, Hongqi
village
Concentration scope
mg/m3
0.013-
0.026
0.003-
0.054
0.007-
0.016
0.005-
0.024
Undetect
ed
Undet
ected
0.215-
0.312
0.075-
0.164
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 14.29 14.29
Menglian Team 3
Concentration scope
mg/m3
0.014-
0.027
0.010-
0.065
0.009-
0.016
0.004-
0.032
Undetect
ed
Undet
ected
0.228-
0.316
0.096-
0.165
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 14.29 28.57
stock-team, Hongqi
village
Concentration scope
mg/m3
0.013-
0.019
0.011-
0.031
0.008-
0.012
0.007-
0.027
Undetect
ed
Undet
ected
0.129-
0.298
0.053-
0.170
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 14.29
Table .4.2-2 Monitoring results of the sewage disposal project and water supply engineering of recycled water within the Industrial Zone of
Ganqimaodao
Pollutants
Items
SO2 NO2 H2S NH3 TSP PM10
Daily
meanHour mean
Daily
meanHour mean
Hour
mean
Hour
meanDaily mean Daily mean
WubulangkouConcentration
scope mg/m3
0.008-
0.0190.012-0.029
0.006-
0.0130.006-0.022
Undetec
ted
Undetecte
d
0.197-
0.3110.136-0.169
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 14.29 42.86
Office area of
the Zone
Concentration
scope mg/m3
0.017-
0.0270.018-0.042
0.010-
0.0130.006-0.025
Undetec
ted
Undetecte
d
0.134-
0.4110.086-0.186
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 28.57 28.57
Reservoir
control office
Concentration
scope mg/m3
0.030-
0.0210.014-0.033
0.005-
0.0120.004-0.024
Undetec
ted
Undetecte
d
0.125-
0.2360.070-0.101
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
SiyitangConcentration
scope mg/m3
0.016-
0.0340.012-0.056
0.005 -
0.0160.005-0.032
Undetec
ted
Undetecte
d
0.211-
0.3960.085-0.206
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 42.86 14.29
No.1 split Concentration 0.005- 0.014-0.056 0.005- 0.005-0.028 Undetec Undetecte 0.177- 0.094-0.176
field, Muyanghai scope mg/m3 0.018 0.015 ted d 0.314
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 14.29 28.57
Table.4.2-3 Monitoring results of water supply engineering of recycled water of the third drainage canal
Pollutants
Items
SO2 NO2 H2S NH3 TSP PM10
Daily mean Hour meanDaily
meanHour mean
Hour
mean
Hour
mean
Daily
meanDaily mean
Traffic
team 6
Concentration
scope mg/m30.019-0.031 0.016-0.062
0.007-
0.0170.011-0.030
Undetect
ed
Undetect
ed
0.155-
0.2780.062-0.151
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 0.0 14.29
Proposed
site
Concentration
scope mg/m30.027-0.064 0.022-0.177
0.011-
0.0290.011-0.044
Undetect
ed
Undetect
ed
0.231-
0.2970.072-0.207
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 0.0 57.14
Unity
Team 3,
Concentration
scope mg/m30.017-0.029 0.022-0.057
0.007-
0.0150.007-0.029
Undetect
ed
Undetect
ed
0.219-
0.2780.092-0.144
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Dasong Concentration 0.016-0.029 0.016-0.051 0.009- 0.005-0.027 Undetect Undetect 0.114- 0.094-0.135
village
scope mg/m3 0.024 ed ed 0.257
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Shawan
village
Concentration
scope mg/m30.013-0.031 0.025-0.062
0.004-
0.0150.005-0.032
Undetect
ed
Undetect
ed
0.196-
0.2840.098-0.137
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Table.4.2-4 Monitoring results of water supply engineering of recycled water of the seventh drainage canal
Pollutants
Items
NO2 H2S NH3 TSP PM10 NO2
Daily
meanHour mean Daily mean Hour mean
Hour
mean
Hour
mean
Daily
meanDaily mean
Liuwenged
an
Concentration
scope mg/m3
0.011-
0.0310.014-0.025
0.005-
0.016
0.007-
0.018
Undetecte
d
Undetect
ed
0.189-
0.2700.098-0.144
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Lianyue
Society 4
Concentration
scope mg/m3
0.011-
0.0170.011-0.031 0.004-0.010
0.006-
0.018
Undetecte
d
Undetect
ed
0.212-
0.2780.099-0.150
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 14.29
Electric
power plant
Concentration
scope mg/m3
0.017-
0.0250.015-0.041 0.009-0.015
0.010-
0.024
Undetecte
d
Undetect
ed
0.217-
0.3210.113-0.137
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 42.85 0.0
Wuxing
team 2
Concentration
scope mg/m3
0.013-
0.0200.011-0.028 0.009-0.013
0.004-
0.019
Undetecte
d
Undetect
ed
0.219-
0.3010.095-0.186
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 14.29 14.29
Old city
team 1
Concentration
scope mg/m3
0.011-
0.0210.009-0.033 0.004-0.014
0.004-
0.021
Undetecte
d
Undetect
ed
0.217-
0.3040.098-0.169
Over-limit ratio % 0.0 0.0 0.0 0.0 0.0 0.0 14.29 14.29
Table .4.2-5 Monitoring results of the sewage disposal project and water supply engineering of recycled water within the Industrial Zone of
Urad Front Banner
Pollutants
Items
SO2 NO2 H2S NH3 TSP PM10
Daily mean Hour meanDaily
meanHour mean
Hour
mean
Hour
mean
Daily
meanDaily mean
Lihuiqua
n village
Concentration
scope mg/m30.013-0.022 0.011-0.031
0.004-
0.0140.006-0.018
Undetect
ed
Undetect
ed
0.148-
0.2890.095-0.135
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Zhongta
n Farm
Concentration
scope mg/m30.011-0.031 0.017-0.037
0.004-
0.0180.006-0.029
Undetect
ed
Undetect
ed
0.210-
0.3410.097-0.141
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 14.29 0.0
Proposed Concentration 0.018-0.022 0.016-0.041 0.010- 0.008-0.039 Undetect Undetect 0.234- 0.114-0.194
site
scope mg/m3 0.016 ed ed 0.297
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 0.0 14.29
Shageda
n village
Concentration
scope mg/m30.024- 0.038 0.032-0.099
0.008-
0.0180.011-0.029
Undetect
ed
Undetect
ed
0.186-
0.3480.095-0.152
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0 14.29 14.29
Table .4.2-6 Monitoring results of the treatment project of Ulansuhai Nur Lake
Pollutants
Items
SO2 NO2 H2S NH3 TSP PM10
Daily mean Hour mean Daily mean Hour meanHour
mean
Hour
mean
Daily
meanDaily mean
15th
Branch
Concentration
scope mg/m30.011-0.031
0.009-
0.0450.015-0.027 0.010-0.031
Undetecte
d
Undetect
ed
0.194-
0.3570.082-0.175
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0
100100
5th
Branch
Concentration
scope mg/m30.014-0.024
0.018-
0.0400.015-0.029 0.010-0.032
Undetecte
d
Undetect
ed
0.241-
0.3120.093-0.159
Over-limit ratio 0.0 0.0 0.0 0.0 0.0 0.0 100 100
%
9th
Branch
Concentration
scope mg/m30.011-0.021
0.019-
0.0370.010-0.030 0.005L-0.028
Undetecte
d
Undetect
ed
0.182-
0.3100.073-0.183
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0
100100
12th
Branch
Concentration
scope mg/m30.012-0.028
0.014-
0.0620.019-0.026 0.005L-0.040
Undetecte
d
Undetect
ed0.20-0.308 0.087-0.182
Over-limit ratio
%0.0 0.0 0.0 0.0 0.0 0.0
100100
4.2.1.6 Assessment method
Single gene index method is used to evaluate the situation of air environment of the
construction site. The calculation formula is as follows:
where : Ci——Daily or annual mean concentration of a
pollutant ( mg/m3) 。Si——Evaluation criterion of a pollutant ( mg/m3) 。
Pi——Single pollution index of a pollutant.
4.2.1.7 Evaluation results
The evaluation criterion of TSP, SO2, NO2 for the sewage disposal project and water
supply engineering of recycled water within the Industrial Zone of this project will adopt the
Class II Standard in the revised sheet in Ambient Air Quality Standard (GB3095-1996) and in
the revised sheet; the evaluation criterion of SO2, NO2 for the treatment project of Ulansuhai
Nur Lake will adopt the Class I Standard in Ambient Air Quality Standard (GB3095-1996);
the evaluation criterion of H2S, NH3 will adopt the standard of maximum allowable
concentration of the harmful substances in the air of residential area in Hygienic Standards
for the Design of Industrial Enterprises (TJ36-79). The evaluation results of the sub-projects
under this project are shown in Table 4.2-7-4.2-12.
Table 4.2-7 the evaluation results of air environment quality of the sewage disposal project
and water supply engineering of recycled water within the Industrial Zone of Urad Back
Banner
Monitoring spotsEvaluation factor
Proposed site
Shahaixinhong Qingshan town
Agr-team, Hongqi village
Menglian Team 3
Stock team, Hongji village
SO2
Hour mean0.022-
0.1020.016-0.1 0.026-0.102 0.006-0.108 0.02-0.13 0.022-0.062
Daily mean0.093-
0.1870.087-0.18 0.127-0.187 0.087-0.173 0.093-0.18 0.087-0.127
NO2
Hour mean 0.033-0.1 0.021-0.079 0.042-0.171 0.021-0.121 0.017-0.133 0.029-0.12
Daily mean0.058-
0.1330.042-0.125 0.075-0.142 0.058-0.133 0.033-0.133 0.067-0.1
TSP Hour mean0.42-
1.2130.483-1.05 0.717-1.263 0.717-1.04 0.76-1.053 0.43-0.993
PM10 Daily mean 0.52-1.04 0.333-1.093 0.547-1.413 0.5-1.093 0.64-1.1 0.353-1.133
H2S Hour meanUndetected
Undetected
Undetected
Undetected Undetected Undetected
NH3 Daily meanUndetected
Undetected
Undetected
Undetected Undetected Undetected
Table 4.2-8 the evaluation results of air environment quality of the sewage disposal project
and water supply engineering of recycled water within the Industrial Zone of Ganqimaodao
Monitoring spotsEvaluation factor
MabulangkouOffice area of the
Zone
Reservoir control
officeSiyitang
No.1 split field,
Muyanghai
SO2
Hour mean 0.024-0.058 0.036-0.084 0.028-0.066 0.024-0.112 0.028-0.112
Daily mean 0.053-0.127 0.111-0.178 0.03-0.2 0.109-0.224 0.027-0.12
NO2
Hour mean 0.025-0.092 0.025-0.105 0.017-0.1 0.021-0.133 0.021-0.117
Daily mean 0.05-0.108 0.083-0.158 0.042-0.1 0.042-0.133 0.042-0.125
TSP Hour mean 0.657-1.037 0.417-1.37 0.417-0.787 0.703-1.32 0.59-1.047
PM10 Daily mean 0.907-1.127 0.573-1.24 0.353-0.673 0.567-1.373 0.627-1.173
H2S Hour meanUndetected
Undetected Undetected Undetected Undetected
NH3 Daily meanUndetected
Undetected Undetected Undetected Undetected
Table 4.2-9 the evaluation results of air environment quality of the water supply engineering
of recycled water of third drainage canal
Monitoring spotsEvaluation factor
Traffic team 6 Proposed site Unity team 3 Dasong village Shawan village
SO2
Hour mean 0.032-0.124 0.044-0.354 0.044-0.114 0.032-0.102 0.05-0.124
Daily mean 0.107-0.207 0.18-0.427 0.113-0.193 0.107-0.193 0.087-0.207
NO2
Hour mean 0.046-0.125 0.046-0.183 0.029-0.121 0.021-0.113 0.021-0.133
Daily mean 0.058-0.142 0.092-0.242 0.058-0.125 0.075-0.2 0.033-0.125
TSP Hour mean 0.517-0.927 0.77-0.99 0.73-0.927 0.38-0.857 0.653-0.947
PM10 Daily mean 0.413-1.007 0.48-1.38 0.613-0.96 0.073-0.9 0.513-0.913
H2S Hour mean Undetected Undetected Undetected Undetected Undetected
NH3 Daily mean Undetected Undetected Undetected Undetected Undetected
Table 4.2-10 the evaluation results of air environment quality of the water supply engineering
of recycled water of the seventh drainage canal
Monitoring spots Liuwengedan Liyue Society 4 Proposed site Wuxin team 2 Old city team 1
Evaluation factor
SO2
Hour mean 0.028-0.05 0.022-0.062 0.03-0.082 0.022-0.056 0.018-0.066
Daily mean 0.073-0.207 0.073-0.113 0.113-0.167 0.08-0.133 0.073-0.14
NO2
Hour mean 0.029-0.075 0.025-0.075 0.042-0.1 0.017-0.079 0.017-0.088
Daily mean 0.042-0.133 0.033-0.083 0.075-0.125 0.075-0.108 0.033-0.117
TSP Hour mean 0.63-0.977 0.707-0.927 0.723-1.07 0.687-1.00 0.723-1.013
PM10 Daily mean 0.653-0.96 0.66-1.00 0.753-0.913 0.633-1.24 0.653-1.127
H2S Hour mean Undetected Undetected Undetected Undetected Undetected
NH3 Daily mean Undetected Undetected Undetected Undetected Undetected
Table 4.2-11 the evaluation results of air environment quality of the sewage disposal project
and water supply engineering of recycled water within the Industrial Zone of Urad Front
Banner
Monitoring spotsEvaluation factor
Lihuiquan village Zhongtan Farm Proposed site Shagedan village
SO2
Hour mean 0.022-0.062 0.034-0.074 0.032-0.082 0.064-0.198
Daily mean 0.087-0.147 0.073-0.207 0.12-0.147 0.16-0.253
NO2
Hour mean 0.025-0.075 0.025-0.121 0.033-0.163 0.046-0.121
Daily mean 0.025-0.117 0.033-0.15 0.083-0.133 0.067-0.15
TSP Hour mean 0.493-0.963 0.7-1.137 0.78-0.99 0.62-1.16
PM10 Daily mean 0.633-0.9 0.647-0.94 0.76-1.293 0.633-1.013
H2S Hour mean Undetected Undetected Undetected Undetected
NH3 Daily mean Undetected Undetected Undetected Undetected
Table 4.2-12 the evaluation results of air environment quality of the treatment project of
Ulansuhai Nur Lake
Monitoring spotsEvaluation factor
15th Branch 5th Branch 9th Branch 12th Branch
SO2
Hour mean 0.06-0.3 0.12-0.27 0.13-0.15 0.09-0.41
Daily mean 0.22-0.62 0.28-0.48 0.22-0.42 0.24-0.56
NO2
Hour mean Undetected-0.26 Undetected-0.27 Undetected-0.23 Undetected-0.33
Daily mean 0.19-0.34 0.19-0.36 0.13-0.38 0.24-0.33
TSP Hour mean Undetected Undetected Undetected Undetected
PM10 Daily mean Undetected Undetected Undetected Undetected
H2S Hour mean 1.64-3.5 1.86-3.18 1.46-3.66 1.74-3.64
NH3 Daily mean 1.62-2.98 2.01-2.6 1.52-2.58 1.67-2.57
According to the monitoring results tables from 4.2-1 to 4.2-6, and the evaluation
results tables from 4.2-7 to 4.2-12 for various sub-projects, the hour mean and daily mean of
SO2, NO2 at each sub-project monitoring spot can meet relevant requirements of the
standards; except that some of the monitoring spots at Lihuiquan village nearer to the sewage
disposal project and water supply engineering of recycled water within the Industrial Zone of
Urad Front Banner, Liuwengedan of the water supply engineering of recycled water of the
seventh drainage canal, Reservoir control office of the sewage disposal project and water
supply engineering of recycled water within the Industrial Zone of Ganqimaodao, Unity team
3, Dasong village and Shawan village of the water supply engineering of recycled water of
the third drainage canal don’t exceed the standards, the daily mean of TSP, PM10 at the sub-
project monitoring spots in most areas exceed the standards, of which the over-limit ratio of
the treatment project of Ulansuhai Nur Lake reaches 100%. The evaluation results indicate
that the proposed sites of the sewage disposal project and water supply engineering of
recycled water within every Industrial Zone suffer from the particle's pollution at a certain
extent, especially the Ulansuhai Nur Lake area has suffered from severe particle's pollution.
The particle and PM10 exceed the standards, on the one hand, because the construction area of
the project belongs to aria area in the north, dry and windy all through the year, with sparse
vegetation and more naked soil surface, on the other hand, the winter of the construction area
of the project is cold and long, resulting in longer heating period and more coal consumption,
which is the main cause. This monitoring of air environment quality has been conducted in
the cols and arid winter, directly resulting in the particles over the sub-project construction
area exceeding the standards and especially when the Ulansuhai Nur Lake area is at the reeds
harvesting season, the particles over Ulansuhai Nur Lake exceed the standards seriously.
With the gradual improvement of the regional eco-environment and the implantation of
centralized heat supply, the particle pollution in the region will be reduced.
The character pollutants such as NH3 and H2S relating to this project can meet the
requirement of environmental quality standard and no index is detected.
As stated previously, the air environment quality over the construction area of each
sub-project is just so so, suffered from the particle pollution at a certain extent; and greater
efforts should be made to restore the vegetation around the area of the sub-project plants.
4.2.2 Current surface water environmental quality assessment 4.2.2.1 The water environmental quality assessment in Sanpaigan, Qipaigan and
Zongpaigan
The environmental monitoring station in Bayannaoer City has conventional monitoring
points in Sanpaigan, Qipaigan and Zongpaigan. This environmental assessment has taken the
water quality monitoring results from 2004 to 2008 to be assessed, the details of which refer
to Table 4.2-13~ Table 4.2-15.
Table 4.2-13 The water quality monitoring results in Sanpaigan from 2004 to 2008
Yea
r
Pollutants
ItemspH DO COD BOD TN
Ammonia
-NTP
200
4
Range6.89-
7.42
0.00-
2.5658.5-636.0
10.4-
322.017.1-145
8.67-
110.00.26-1.86
Annual
Average7.14 0.85 306.0 140.0 62.8 47.3 1.05
Standard Rate 0 100 100 100 100 100 67
200
5
Range7.32-
7.50
0.01-
2.5773.5-287
7.78-
128.030.6-242 28.3-213
0.349-
3.11
Annual
Average7.42 1.29 183.17 52.16 107.17 95.27 1.32
Standard Rate 0 100 100 100 100 100 100
200
6
Range6.50-
7.650.10
100.0-
902.0
18.4-
243.0
42.3-
425.0
41.1-
397.0
0.591-
2.84
Annual
Average7.17 0.10 378.7 97.93 173.3 162.7 1.54
Standard Rate 0 100 100 100 100 100 100
200
7
Range7.61-
8.11
0.01-
7.0531.1-298.0 3.40-29.8 2.57-44.7 1.44-34.0 0.14-3.17
Annual
Average7.84 2.36 133.0 13.1 20.3 14.0 1.54
Standard Rate 0 67 100 67 100 67 67
200
8
Range7.75-
7.901.4-4.2 30.0-64.0 5.5-8.6 2.57-10.8 1.17-7.08 0.219-4.8
Annual
Average7.84 2.7 50.5 7.03 5.25 3.22 1.54
Standard Rate 0 75 100 50 100 50 50
Table 4.2-14 The water quality monitoring results in Qipaigan from 2004 to 2008Y
e
a
r
Pollutants
ItemspH DO COD BOD TN
Ammonia
-NTP
2
0
0
4
Range7.54-
8.150.00-0.46 218.0-2228.0 23.3-649.0 6.32-118.00 2.84-54.2 0.67-2.01
Annual
Average7.83 0.15 891.0 238.77 58.2 20.0 1.46
Standard Rate 0 100 100 100 100 100 100
2
0
0
5
Range7.63-
8.100.01-4.48 106.0-723.0 38.7-247.0 39.6-144.0
27.4-
132.00.79-3.28
Annual
Average7.50 2.24 428.0 131.9 87.9 77.6 1.91
Standard Rate 0 50 100 100 100 100 100
2
0
0
6
Range7.58-
7.820.10 300.0-1610.0 41.3-303.0 27.0-212.0
24.7-
209.01.14-2.01
Annual
Average7.71 0.10 1091.7 199.4 117.3 112.6 1.50
Standard Rate 0 100 100 100 100 100 100
2
0
0
7
Range7.45-
7.620.0-2.0 168.0-1419.0 19.1-428.0 13.4-182.6
6.59-
176.00.23-3.17
Annual
Average7.56 0.67 596.0 161.0 70.2 65.1 1.55
Standard Rate 0 100 100 100 100 100 67
2
0
0
8
Range6.50-
7.600.01-5.9 542.0-1126.0 74.5-194.0 17.8-150.3
13.9-
103.0
0.186-
3.64
Annual
Average7.12 1.5 819.0 152.0 69.6 49.7 2.06
Standard Rate 0 75 100 100 100 100 75
Table 4.2-15 The water quality monitoring results in Zongpaigan from 2004 to 2008Y
ea
r
Pollutants
ItemspH DO COD BOD TN
Ammonia-
NTP
20
04
Range 7.57-
8.87
0.00-8.81 21.6-
329.0
1.00-56.8 1.06-188 0.19-59.5 0.05-
1.36
Annual
Average8.27 3.79 85.4 14.3 27.7 7.35 0.38
Standard Rate 0 76 82 54 82 92 76
20
05
Range6.75-
8.940.01-8.54
20.8-
1891.00-28.1 0.73-74.7 0.26-57.3
0.037-
1.35
Annual
Average8.11 6.00 75.8 6.6 15.9 10.60 0.337
Standard Rate 0 25 80 46 87 47 33
20
06
Range7.76-
8.760.1-8.5
43.7-
351.01.00-40.4
1.33-
113.00
0.187-
103.0
0.114-
3.10
Annual
Average8.19 4.46 113.3 6.9 20.8 17.74 0.639
Standard Rate 0 33 100 27 67 53 40
20
07
Range7.60-
9.100.01-8.40
26.3-
260.01.00-73.1 1.01-87.6 0.225-83.0
0.046-
1.24
Annual
Average8.23 4.44 114.3 17.2 17.4 12.3 0.45
Standard Rate 6.3 31.3 93.8 75 64.3 25 31.3
20
08
Range7.25-
8.670.6-7.6
26.0-
194.01.00-18.0 0.89-60.2 0.039-25.6
0.014-
3.03
Annual
Average8.16 3.98 59.6 6.52 5.03 2.11 0.54
Standard Rate 0 35 90 30 65 15 25
The standard index method is used for this assessment.
1 ) pH standard index : Or
wherein : pHsd——the pH lower limit in surface water quality standards;
PHsu——the pH upper limit in surface water quality standards;
2 ) DO standard index :
Or
Of which
wherein : — — the saturated DO concentration , mg/L ; ——the surface water quality standards of DO , mg/L ;3 ) The expression of other items :
wherein : — — the single-factor index of i type pollutants ;——the actual concentration average value of i type pollutants
, mg/L ; ——the assessment standard value of i type pollutants , mg/L 。
When the standard index of water quality parameter , it shows that the water
quality parameters exceeded the required quality standards, which has been unable to meet
the requirements to use ; it will meet the requirements when . The water quality
evaluation results in Saanpagan, Qipaigan and Zongpaigan from 2004 to 2008 refer to Table
4.2-16~ Table 4.2-18 。
Table 4.2-16 The water quality evaluation results in Sanpaigan from 2004 to 2008
Y
e
a
r
Pollutants
ItemspH DO COD BOD TN
Ammonia
-NTP
2
0
0
4
Standard Index 0.11-0.21 2.32-10 1.95-21.2 1.73-53.67 11.4-96.675.78-
73.330.87-6.2
Average Value 0.07 7.45 10.2 23.33 41.87 31.53 3.5
2
0
0
5
Standard Index 0.16-0.252.29-
9.972.45-9.57 1.29-21.33
20.4-
161.33
18.87-
142
1.16-
10.37
Average Value 0.21 6.13 6.11 8.69 71.45 63.51 4.4
2
0
0
6
Standard Index 0.32-0.5 9.7 3.33-30.07 3.07-40.528.2-
283.33
27.4-
264.671.97-9.47
Average Value 0.09 9.7 12.62 16.32 115.53 108.47 5.13
2
0
0
7
Standard Index 0.31-0.560.43-
9.971.04-9.93 0.57-4.97 1.71-29.8
0.96-
22.67
0.47-
10.57
Average Value 0.42 2.92 4.43 2.18 13.53 9.33 5.13
2
0
0
8
Standard Index 0.38-0.45 0.83-5.8 1.0-2.13 0.92-1.43 1.71-7.2 0.78-4.72 0.73-16
Average Value 0.42 1.9 1.68 1.17 3.5 2.15 5.13
Table 4.2-17 The water quality evaluation results in Qipaigan from 2004 to 2008
Year Pollutants
ItemspH DO COD BOD TN Ammonia-N TP
2004Standard Index
0.27-
0.578.62-10 7.27-74.27 3.88-108.17 4.21-78.67 1.89-36.13 2.23-6.7
Average Value 0.42 9.55 29.7 39.79 38.8 13.33 4.87
2005Standard Index
0.32-
0.55
0.79-
9.973.53-24.1 6.45-41.17 26.4-96 18.27-88
2.63-
10.93
Average Value 0.25 3.28 14.27 21.98 58.6 51.73 6.37
2006Standard Index
0.29-
0.419.7 10.0-53.67 6.88-50.5 18-141.33 16.47-139.33 3.8-6.7
Average Value 0.36 9.7 36.39 33.23 78.2 75.07 5
2007Standard Index
0.23-
0.314-10 5.6-47.3 3.18-71.33
8.93-
121.734.39-117.33
0.77-
10.57
Average Value 0.28 7.99 19.87 26.83 46.8 43.4 5.17
2008Standard Index 0.3-0.5
0.59-
9.9718.07-37.53 12.42-32.33
11.87-
100.29.27-68.67
0.62-
12.13
Average Value 0.06 5.5 27.3 25.33 46.4 33.13 6.87
Table 4.2-18 The water quality evaluation results in Zongpaigan from 2004 to 2008
Ye
ar
Pollutants
ItemspH DO COD BOD TN
Ammonia-
NTP
20
04
Standard
Index
0.29-
0.940.19-10 0.72-10.97 0.17-9.47 0.71-125.33 0.13-39.67 0.17-4.53
Average
Value0.64 0.89 2.85 2.38 18.42 4.9 1.27
20
05
Standard
Index
0.25-
0.97
0.22-
9.970.69-6.3 0.17-4.68 0.49-49.8 0.17-38.2 0.12-4.5
Average
Value0.56 0.58 2.53 1.1 10.6 7.07 1.12
20
06
Standard
Index
0.38-
0.88
0.23-
9.71.46-11.7 0.17-6.73 0.89-75.33 0.12-68.67 0.38-10.33
Average
Value0.59 0.79 3.78 1.15 13.87 11.83 2.13
20
07
Standard
Index0.3-1.05
0.24-
9.970.88-8.67 0.17-12.18 0.67-58.4 0.15-55.33 0.15-4.13
Average
Value0.62 0.79 3.81 2.87 11.6 8.2 1.5
20
08
Standard
Index
0.13-
0.84
0.36-
8.20.87-6.47 0.17-3 0.59-40.13
0.026-
17.070.047-10.1
Average
Value0.58 0.86 1.99 1.09 3.35 1.41 1.8
From the water quality monitoring results in Table 4.2-13 ~ Table 4.2-15 and the
water quality evaluation results in Table 4.2-16 ~ Table 4.2-18, which should be known
that:
1 ) From 2004 to 2008, the water in Sanpaigan has been seriously polluted, the
major pollution indicators, COD 、 BOD 、 TN 、 Ammonia-N and TP, were all
exceeded, of which, the Standard Rate of COD and TN over the years all were 100%, the
maximum Pollution Standard Index of TN and Ammonia-N in 2006, respectively, reached
283.33 and 264.67, and their Standard IndexAnnual average is 115.53 and 108.47
respectively; however, it shows a yearly decreasing trend seeing from the Pollution
Standard Index changes over the year, therefore, with the continuously intensifying
environmental protection in Bayannaoer City, the water quality in Sanpaigan improved.
2 ) The water quality in Qipaigan has also been seriously polluted, the major
pollution indicators, COD 、 BOD 、 TN 、 Ammonia-N and TP, are far beyond the
standard, except for TP, the pollution indicators standard rate of others over the year all were
100%, the pollution Standard Index average value of COD is 14.27-36.39, that of BOD is
21.98-39.79, that of TN is 38.8.27-78.2, and that of Ammonia-N is 13.33-75.07, this shows
that , the water quality in Qipaigan has remained a serious state of pollution, as well as
threaten the water environment quality security of Ulansuhai Nur.
3 ) Although the water quality in Zongpaigan has been polluted certainly, compared
with the water environment quality in Sanpaigan and Qipaigan, it has the relatively light
pollution, the major pollution indicators are COD 、 BOD 、 TN 、 Ammonia-N and
TP etc., of which, COD and TN are polluted more seriously, their Standard Rate over the
yaer are above 50%, the pollution Standard Index average value of COD is 1.99-
3.81, and that of TN is 3.55-18.42; while that of BOD and TP are relatively better,
the pollution Standard Index average value of them is respectively between 1.09-2.38 and
1.12-2.13; it also shows a yearly decreasing trend seeing from the annual average pollution
index over the year, but the water environment quality in Zongpaigan is gradually
improved.
4.2.2.2 Current water quality assessment in Ulansuhai Nur sea area
1 ) Monitoring project
Each monitoring section all selects Water temperature, Depth of water, pH, and SS,
DO, COD, Chlorophylla, BOD, TN, Ammonia-N, Nitrate-N, TP and Soluble orthophosphate.
2 ) Monitoring time and frequency
The current water quality assessment in Ulansuhai Nur sea area is resctively carried on
two periods of monitoring in Dry Season and Wet Season, and each sampling and
monitoring should be carried on for 3 consecutive days.
3 ) Sampling locations layout
According to "Surface Water Environmental Impact Assessment Technology
Guidelines" and relevant water environmental standards, every 4km2 laid a sampling point,
and a total of 12 sampling points are required , refer to Figure 4.2-7 。
Figure 4.2-7 The monitoring sites of courrent surface water qualityBecause the average depth of water is less than 10m, the sampling points should be
laid in the underwater 0.5m, but should not be less than 0.5m from the bottom of the lake.
4 ) Detection
It should be in accordance with "Environmental Monitoring Standards" and "Water and
Wastewater Monitoring Analysis Method" published by National Environmental Protection
4# Dongdatan
5# Xidatan
3# Wayaogeliang
6# Bapaigan
7# Zongpaigan
9# Jiupaigan2# Dabodong
8# Xiaohai
1# Xiaowa10# Erdian
11# Haihao
12# Hekou(Wumaoji)
Agency.
5 ) Evaluation
It should adopt single standard index formula to evaluate the current water
environment quality of major rivers. The evaluation formula is as follows:
Si,j=Ci,j/Csi
Wherein, Ci,j――Monitoring value of i-species pollutants at j point, mg/L;Csi――Evaluation standard limit of i-species pollutants, mg/L;Si,j――Standard Index of i-species pollutants.
pH standard index :
Or
wherein : pHsd——the pH lower limit in surface water quality standards ; pHsu——the pH upper limit in surface water quality standards ;
DO standard index :
sjsf
jfjDO DODO
DODO
DODOS
,,
sjs
jjDO DODO
DODO
S ,910,
wherein , SDO,j: Standard Index of DO at j point;
DOf : the saturated DO concentration , mg/L ;DOj : Monitoring concentration of DO at j point, mg/L;
DOS : the surface water quality standards of DO , mg/L 。If he Standard Index of water quality parameters >1 , it shows that this water quality
parameters exceeded the required quality standards. The bigger the water quality parameter is, the more serious this water quality parameter exceeded.
6 ) Monitoring results
Monitoring results refer to Table 4.2-19 。
Table 4.2-19 Water Quality Monitoring Results ( mg/L )Locatio
nPeriod pH SS DO
CO
D
BOD
5
TNNH3-
N
N
O
3-
TP PO43-
Chla
(mg/
m3)
Xiaowa
Wet
Season
8.
38
262
.332.53
36.3
7
10.7
91.37 0.79
0.
1
2
0.0
5
Not
detected
Not
detect
ed
Dry
Season
7.
80
16.
670.77
66.9
3
18.0
07.18 4.32
0.
3
7
0.1
0
Not
detected7.55
Dabud
ong
Wet
Season
8.
73
269
.673.33
35.0
79.72 1.33 0.25
0.
3
3
0.0
5
Not
detected
Not
detect
ed
Dry
Season
7.
69
13.
331.75
56.1
0
12.5
0
14.6
511.75
0.
1
5
0.2
6
Not
detected21.63
Wayao
geliang
Wet
Season
8.
25
218
.003.80
41.7
3
12.5
71.35 0.98
0.
0
6
0.0
6
Not
detected
Not
detect
ed
Dry
Season
7.
63
29.
670.47
55.8
0
13.1
3
12.8
79.30
0.
1
3
0.1
9
Not
detected36.93
Dongd
atan
Wet
Season
8.
20
244
.33
3.37 43.8
3
12.8
0
1.27 0.75 0.
0
8
0.0
5
0.01 Not
detect
ed
Dry
Season
8.
93
7.0
00.65
50.1
0
10.5
63.64 1.67
0.
2
6
0.1
80.09 38.70
Xidata
n
Wet
Season
7.
93
222
.331.20
35.5
78.61 4.22 3.01
1.
2
6
0.2
60.14
Not
detect
ed
Dry
Season
7.
62
89.
000.47
95.5
0
23.2
7
44.8
339.21
0.
2
3
1.9
30.96 42.03
Bapaig
an
Wet
Season
8.
41
328
.674.53
29.5
07.20 1.64 1.08
0.
4
0
0.2
5
Not
detected
Not
detect
ed
Dry
Season
7.
69
35.
674.26
31.6
77.35 4.06 2.35
0.
1
1
0.1
20.01 0.48
Hongg
ebu
Wet
Season
8.
31
348
.673.23
44.5
7
12.9
01.58 1.09
0.
2
6
0.1
30.02
Not
detect
ed
Dry
Season
6.
94
11.
50
Not
detected
158.
00
46.2
7
74.8
367.15
0.
3
6
3.7
81.81 0.00
Xiaoha
i
Wet
Season
8.
21
291
.001.47
35.4
09.23 1.17 0.81
0.
1
2
0.1
10.14
Not
detect
ed
Dry
Season
7.
54
27.
330.66
53.5
7
17.1
0
25.2
317.56
0.
2
1
0.5
20.44 41.10
Jiupaig
an
Wet
Season
8.
21
349
.675.60
34.2
09.13 0.55 0.13
0.
0
7
0.0
4
Not
detected
Not
detect
ed
Dry
Season
7.
47
289
.332.06
44.6
3
11.2
03.09 1.32
0.
0
8
0.0
90.02 0.45
Erdian
Wet
Season
8.
64
345
.333.90
41.0
7
12.7
31.31 0.59
0.
0
5
0.0
4
Not
detected
Not
detect
ed
Dry
Season
7.
82
78.
001.30
54.9
7
10.9
04.82 1.35
0.
1
5
0.5
30.02 41.03
HaihaoWet
Season
8.
86
340
.673.70
44.0
3
11.8
31.07 0.72
0.
1
2
0.0
2
Not
detected
Not
detect
ed
Dry 6. 8.0 0.63 57.7 17.7 2.78 0.75 0. 0.0 0.01 36.70
Season 89 0 7 02
35
Hekou
Wet
Season
8.
60
263
.333.07
44.0
0
13.0
70.75 0.52
0.
0
9
0.0
2
Not
detected
Not
detect
ed
Dry
Season
7.
92
33.
000.75
54.0
39.94 3.95 0.47
0.
1
3
0.1
20.02 39.27
7 ) Assessment results
Implementation of the "Surface Water Environmental Quality Standard" (GB3838-2002) in class Ⅳ standard. Using the simple index method to assess the current water environmental quality in Ulansuhai Nur, the results refer to Table 4.2-20.
Table 4.2-20 Single-factor evaluation results of water quality in Ulansuhai Nur
Location Period pH DO COD BOD TNAmmonia
-NTP
Xiaowa Wet Season 0.69 2.41 1.21 1.79 0.91 0.530.17
Dry Season 0.4 7.69 2.23 3 4.79 2.880.33
Dabudong Wet Season 0.87 0.94 1.17 1.62 0.89 0.170.17
Dry Season 0.35 4.75 1.87 2.08 9.77 7.830.87
Wayaogeliang
Wet Season 0.63 0.85 1.39 2.09 0.9 0.65 0.2
Dry Season 0.32 8.59 1.86 2.19 8.58 6.20.63
Dongdatan Wet Season 0.6 0.932 1.46 2.13 0.85 0.50.17
Dry Season 0.97 8.05 1.67 1.76 2.43 1.11 0.6
Xidatan Wet Season 0.47 6.4 1.19 1.44 2.81 2.010.87
Dry Season 0.31 8.59 3.18 3.8829.89
26.146.43
Bapaigan Wet Season 0.71 0.72 0.98 1.2 1.09 0.720.83
Dry Season 0.35 0.77 1.06 1.23 2.71 1.57 0.4
Honggebu Wet Season 0.66 0.96 1.49 2.15 1.05 0.730.43
Dry Season 0.06 10.0 5.27 7.7149.89
44.7712.6
Xiaohai Wet Season 0.61 5.59 1.18 1.54 0.78 0.540.37
Dry Season 0.27 8.02 1.79 2.8516.82
11.711.73
Jiupaigan Wet Season 0.61 0.52 1.14 1.52 0.37 0.0870.13
Dry Season 0.24 3.82 1.49 1.87 2.06 0.88 0.3
Erdian Wet Season 0.82 0.84 1.37 2.12 0.87 0.390.13
Dry Season 0.41 6.1 1.83 1.82 3.21 0.91.77
Haihao Wet Season 0.93 0.87 1.47 1.97 0.71 0.480.07
Dry Season 0.11 8.11 1.93 2.95 1.85 0.50.17
Hekou Wet Season 0.8 0.99 1.47 2.18 0.5 0.350.07
Dry Season 0.46 7.75 1.80 1.66 2.63 0.31 0.4It can be seen from the Table 4.2-1 and Table 4.2-2 that:
1 ) In wet season, DO, CODCr, BOD5, NH3-N and TP in 12 monitoring sections
exceed standard partly. DO pollution index is 0.52-6.40, COD pollution index is 0.98-1.49, BOD5 pollution index is 1.2-2.18, TN pollution index is 0.37-2.81, NH3-N pollution index is 0.087-2.01, and TP pollution index is 0.07-0.87, COD pollution standard indexe are all greater than 1 expect for that in Bapaigan monitoring point, BOD5 pollution standard indexes are all greater than 1, TN pollution standard indexes are all less than 1 expect for that in Xidatan, Bapaigan and Honggebu, and TP pollution standard indexes are all less than 1. This shows that, lake water of Ulansuhai Nur in wet season is mainly polluted in organic mode, while be relatively light polluted by eutrophic pollutant as N and P.
2 ) In dry season, all of CODCr, BOD5 and TN in 12 monitoring sections exceed
standard, and DO, NH3-N and TP exceed partly. DO pollution index is 3.82-10.00, COD
pollution index is 1.06-5.27, BOD5 pollution index is 1.23-7.71, TN pollution index is 1.85-
49.89, NH3-N pollution index is 0.31-44.77, and TP pollution index is 1.17-12.6, the lake
water has been polluted seriously.
3 ) Known from the evaluation results of Ulansuhai Nur in wet season and dry
season that, the water quality of Ulansuhai Nur in dry season (winter) is worse than that in wet season (summer), it has been polluted relatively heavier in dry season.
4 ) The water in Zongpaigan are mainly urban domestic sewage and industrial
wastewater, while the water in Jiiupaigan and Bapaigan are mainly Yellow River ecological
water supplement, and less domestic sewage and industrial wastewater, so the water quality
here is relatively better than that in Zongpaigan, the pollutants import in Ulansuhai Nur are
mainly from Zongpaigan, therefore, the water quality in western Ulansuhai Nur is worth than
that in eastern.
4.2.3 Assessment of current groundwater environmental quality4.2.3.1 Monitoring items
The evaluation factors of current groundwater environmental quality of
wastewater treatment and reuse project and renovated water supply project in
Industrial Area are: pH, Ammonia-N, Nitrate-N, NOz-N, Sulfate, and CODMn, As,
Cd, Cr VI, Cu, Pb, Zn, Total coliform, Fluoride, Chloride and Total hardness.
Every monitoring point of treatment project in Ulansuhai Nur sea area selects
pH value 、 Salinity 、 Total hardness (for CaCO3), Ammonia-N, Nitrate,
Chloride, As, Cr, CODMn, Cyanide, As, Hg, Fe and Mn as the evaluation factors.
4.2.3.2 Monitoring time and frequency
One time and for one day. The monitoring well sampling time of the same
hydrogeological unit should be relatively concentrated as much as possible, and the
date span should not be too big.
4.2.3.3 Sampling location layout
Groundwater monitoring of wastewater treatment and reuse project and
renovated water supply project in Industrial Area of this item layout one sampling
point at the proposed site.
According to "Technical specifications of groundwater monitoring" (HJ/T164-
2004) that in generally, it should place 0.2 wells for every 100km 2 in plain area
(including basin area), because Ulansuhai Nur is an important water source,
combining with its hydrogeological conditions, it should be laid along the seawall,
and its sampling point should distribute in a ring. The treatment project in Ulansuhai
Nur sea area laid a total of 8 sampling points.
Figure 4.2-8 The monitoring sites of current groundwater quality4.2.3.4 Monitoring
The test method should be implemented according to the national satandards
GB 5750 “The test method of drinking water standard”.
4.2.3.5 Monitoring results
The groundwater monitoring results of wastewater treatment and reuse project
and renovated water supply project in Industrial Area refers to Table 4.2-21, and the
Wayaotan
Wayaotan
First field
Fifth work area
Sixth field
Fifth field
Ninth fieldFifteenth field
Second field
Third field
Eighth field
Ninth field of Xinan farm
Eighth field of Xishanzui farm
Seed multiplication farm
Erdenii Prague Sumu
monitoring results of the treatment project groundwater in Ulansuhai Nur sea area
refer to Table 4.2-22.
Table 4.2-21 Groundwater monitoring results of wastewater treatment and reuse and renovated water
supply project
Monitoring
points
Items
Renovated
water
supply
project in
Qipaigan
Wastewater treatment and
renovated water projects
in Ganqimaodu
Processing Zone
Wastewater treatment and
renovated water projects in
Urad Back Banner
Industrial Area
Renovated
water supply
project in
Sanpaigan
Wastewater
treatment projects in
Urad Front Banner
Industrial Area
Well depth m 12 60 20 — —
pH 7.60 7.31 7.74 7.25 8.03
Ammonia-N 1.24 0.044 0.23 0.199 0.296
Nitrate-N (0.0015) 1.86 1.41 0.86 0.298
NOz-N (0.0015) (0.0015) (0.0015) (0.0015) (0.0015)
Sulfate 334.1 293 317 596 196
CODMn 2.25 1.21 0.48 1.54 1.86
As 2.43E-03 2.70E-04 2.55E-04 1.09E-04 6.96E-04
Cd 0.002L 0.002L 0.002L 0.002L 0.002L
Cr VI 0.004L 0.004L 0.004L 0.004L 0.004L
Cu 0.01L 0.01L 0.01L 0.01L 0.01L
Pb 0.05L 0.05L 0.05L 0.05L 0.05L
Zn 0.032 0.056 0.041 0.035 0.05
Total hardness 509 430 378 859 657
Fluoride 0.375 1.01 1.510 0.272 0.23
Chloride 233 222 127 296 1090
Total coliform < 3 < 3 < 3 < 3 < 3
Table 4.2-22 Groundwater quality monitoring index value in Ulansuhai Nur sea area
Sampling point
position
Eight
h
field
Motor-pumped
well in
Geerdengbulage
sumu
Pressuriz
ed water
well in
twelfth
field
Pressur
ized
water
well in
ninth
field
Pressuri
zed
water
well in
first
field
Pressu
rized
water
well in
Fifth
work
Pressuri
zed
water
well in
sixth
field
Third
field
area
Well
depth( m ) 90 60 10 10 30 23 18 12
pH 8.03 7.91 8.85 8.26 8.41 8.16 8.03 7.83
Salinity 473 490 488 490 696 1280 2400 2250
Total hardness 212 222 111 233 81 212 455 768
Ammonia-N 0.029 0.028 3.260 2.316 1.124 0.993 1.445 0.625
NOz-N(0.002
5)(0.0025) (0.0025)
(0.002
5)0.010 0.006
(0.0025
)
(0.002
5)
Nitrate-N 3.21 5.44 0.287 0.264 0.534 0.264 0.393 0.231
Chloride 19.5 53.4 9.4 32.1 42.7 556 1100 285
Fluoride 0.22 0.24 0.24 0.22 0.69 0.90 0.73 0.26
Cr VI 0.019 0.018 0.010 0.017 0.015 0.008 0.013 0.018
CODMn 0.56 0.57 1.47 1.08 3.92 2.94 6.69 1.96
Cyanide(0.002
)(0.002) (0.002) (0.002) (0.002)
(0.002
)(0.002) (0.002)
Mn 0.021 0.039 0.031 0.167 0.037 0.063 0.042 0.031
Fe 0.151 0.089 0.108 0.092 0.156 0.251 0.366 0.118
As3.88E-
043.25E-04 4.47E-04
8.38E-
04
1.34E-
02
9.08E-
03
2.21E-
02
6.59E-
04
Hg1.82E-
041.43E-04 1.24E-04
1.65E-
04
1.43E-
04
1.01E-
04
3.58E-
04
2.23E-
04
4.2.3.6 Evaluation
The evalution should adopt the standard index method, and perform (GB/T14848-93) Ⅲ
class standards of "Groundwater Quality Standard".
4.2.3.7 Evaluation results
The groundwater evaluation results of wastewater treatment and reuse project
and renovated water supply project in Industrial Area refers to Table 4.2-23, and the
monitoring results of current groundwater quality in Ulansuhai Nur surrounding refer
to Table 4.2-24.
Table 4.2-23 Groundwater standard index value of wastewater treatment and reuse and renovated water
supply project
Monitoring
points
Items
Renovated
water supply
project in
Qipaigan
Wastewater treatment
and renovated water
projects in
Ganqimaodu
Processing Zone
Wastewater treatment and
renovated water projects
in Urad Back Banner
Industrial Area
Renovated
water
supply
project in
Sanpaigan
Wastewater
treatment projects
in Urad Front
Banner Industrial
Area
pH 0.4 0.21 0.49 0.17 0.69
Ammonia-
N6.2 0.22 1.15 0.99 1.48
Nitrate-N —— 0.093 0.071 0.043 0.015
NOz-N —— —— —— —— ——
Sulfate 1.34 1.17 1.27 2.38 0.78
CODMn 0.75 0.40 0.16 0.51 0.62
As 4.86E-02 5.40E-03 5.10E-03 2.18E-03 1.39E-02
Cd —— —— —— —— ——
Cr VI —— —— —— —— ——
Cu —— —— —— —— ——
Pb —— —— —— —— ——
Zn 0.032 0.056 0.041 0.035 0.05
Total
hardness1.13 0.96 0.84 1.91 1.46
Fluoride 0.38 1.01 1.51 0.27 0.23
Chloride 0.93 0.89 0.51 1.18 4.36
Total
coliform< 1 < 1 < 1 < 1 < 1
Table 4.2-24 Groundwater standard index value in Ulansuhai Nur sea area
Samplin
g point
position
Eighth
field
Motor-pumped well
in
Geerdengbulagesum
u
Pressuriz
ed water
well in
twelfth
field
Pressuriz
ed water
well in
ninth
field
Pressuriz
ed water
well in
first field
Pressuriz
ed water
well in
Fifth
work
area
Pressuriz
ed water
well in
sixth
field
Third
field
pH 0.69 0.61 1.23 0.84 0.94 0.77 0.69 0.55
Total
hardness0.47 0.49 0.25 0.52 0.18 0.47 1.01 1.71
Ammoni 0.15 0.14 16.3 11.58 5.62 4.97 7.23 3.13
a-N
NOz-N — — — — 0.5 0.3 — —
Nitrate-
N0.16 0.27 0.014 0.013 0.027 0.013 0.019 0.012
Chloride 0.078 0.21 0.038 0.13 0.17 2.22 4.4 1.14
Fluoride 0.22 0.24 0.24 0.22 0.69 0.90 0.73 0.26
Cr VI 0.38 0.36 0.2 0.34 0.3 0.16 0.26 0.36
CODMn 0.19 0.19 0.49 0.36 1.31 0.98 2.23 0.65
Cyanide — — — — — — — —
Mn 0.21 0.39 0.31 1.67 0.37 0.63 0.42 0.31
Fe 0.50 0.29 0.36 0.31 0.52 0.84 1.22 0.39
As7.76E-
036.50E-03 8.94E-03 1.68E-02 2.68E-01 1.82E-01 4.42E-01
1.32E-
02
Hg1.82E-
011.43E-01 1.24E-01 1.65E-01 1.43E-01 1.01E-01 3.58E-01
2.23E-
01
It can be seen from the Table 4.2-23 and Table 4.2-24 that:
1 ) The proposed site groundwater quality of wastewater treatment and reuse
project and renovated water supply project in Industrial Area mainly exceed standard
in inorganic indicators as Ammonia-N, Sulfate, Total hardness, etc., of which, in
renovated water supply project site groundwater in Qipaigan, Ammonia-N Standard
Index, Sulfate Standard Index and Total hardness Standard Index are 6.2, 1.34 and
1.13, respectively, in wastewater treatment and reuse project and renovated water
supply project groundwater in Urad Back Banner Industrial Area, Ammonia-N
Standard Index, Sulfate Standard Index and Fluoride Standard Index are 1.15, 1.27
and 1.51, respectively, in renovated water supply project site groundwater in
Qipaigan, Sulfate Standard Index, Total hardness Standard Index and Chloride
Standard Index are 2.38, 1.91 and 1.18, respectively, and in wastewater treatment
and reuse project groundwater in Urad Front Banner Industrial Area, Ammonia-N
Standard Index, Total hardness Standard Index and Chloride Standard Index are 1.48,
1.46 and 4.36, respectively. This shows that, the water quality characteristics of
every proposed project site groundwater is accordance with that of groundwater
throughout the region, which is with higher Salinity, but to some extent, there are
also exogenous pollution.
2 ) The water quality of confined groundwater (PumPing well) in
Ulansuhai Nur sea area surrounding is better, Ulansuhai Nur is the main recharge
source of its surrounding groundwater, which is impacted by Ulansuhai Nur water
quality, so its surrounding subsurface water quality is relatively worth, some
groundwater indicators in Twelfth field, Ninth field, First field, Fifth work area,
Sixth feld and Third field exceeded sdandard, of which, Ammonia-N Sdandard
Index exceeded seriously, and its Pollution Standards Index is between 3.13-16.3;
Chloride Standard Index in Fifth work area, Sixth feld and Third field all exceeded,
and the highest standard pollution index value is 4.4. Therefore, Ulansuhai Nur
affected significantly on its surrounding groundwater environment, especially for
subsurface water quality.
4.2.4 Evaluation of current acoustic environmental quality4.2.4.1 Monitoring Sites
To fully understand and analyze the noise environment in this region, it laid
four noise monitoring points in this evalution at the proposed site of wastewater
treatment and renovated water supply project in Industrial Area, which were located
all around the boundary, for the schematic diagram of monitoring sites, refer to 4.2-
9; it laid nine monitoring points for the treatment projec in Ulansuhai Nur sea area,
and the distribution of monitoring points refer to Figure 4.2-10.
Figure 4.2-9 The schematic diagram of wastewater treatment and renovated water supply project acoustic environment monitoring sites
Figure 4.2-10 Acoustic environment quality monitoring sites in Ulansuhai Nur sea area4.2.4.2 Monitoring factors
Equivalent consecutive sound level A.
4.2.4.3 Monitoring
In accordance with GB12349-90, adopt slow "A" sound level, then read one
instantaneous value for five seconds, and sequential read 100 data, it’s sunny day
when measured, with 2-3 grade wind, the sound level meter is hand-hold, and 1.2m
high from the ground.
4.2.4.4 Monitoring time and frequency
Xinmin
First field
Sixth field
Fifth field
Third field
Seventh field
Beilongtai
Fourth field
Fifteenth field
Noise monitoring sites
It has been continuous monitored for two days on November 19 th, 2009 and
November 20 th, 2009, and twice a day for day and night, monitoring respectively
from 8:00am ~ 11:00am in the daytime and from 22:00pm ~ 6:00am at
night.
4.2.4.5 Monitoring results and evaluation
For the monitoring results and evaluation of every subproject acoustic
environment, refer to Table 4.2-25 and 4.2-26.
Table 4.2-25 Sound environment monitoring results of wastewater treatment project and
renovated water project in Industrial Area
Test Site No. Test Site
Daytime dB(A) Night dB(A)Nov. 19th, 2009
Nov. 20th, 2009
Nov. 19th, 2009
Nov. 20th, 2009
Delingshan water supply project site
East Plant Bound 42.9 42.2 34.2 33.6South Plant
Bound41.7 42.8 35.3 35.9
West Plant Bound 43.2 42.4 38.1 38.8North Plant
Bound40.9 41.2 34.2 33.8
Shanba town water supply project site
East Plant Bound 54.7 55.4 47.7 48.6South Plant
Bound51.2 50.6 42.1 42.5
West Plant Bound 50.2 49.8 40.9 41.6North Plant
Bound53.9 54.6 45.8 46.2
Huhe town water supply project site
East Plant Bound 39.3 38.3 34.6 35.4South Plant
Bound46.1 46.9 38.7 37.8
West Plant Bound 46.5 47.4 42.2 41.7North Plant
Bound41.7 41.3 35.0 35.4
Longxingchang town water supply project site
East Plant Bound 53.1 52.6 49.2 48.9South Plant
Bound50.9 50.5 45.8 46.3
West Plant Bound 49.7 49.4 45.9 46.1North Plant 51.8 52.3 48.7 49.2
Bound
Xianfeng town water supply project site
East Plant Bound 51.6 51.8 50.0 50.4South Plant
Bound53.1 52.9 38.9 39.5
West Plant Bound 45.2 44.3 41.5 42.8North Plant
Bound44.7 45.6 42.8 42.4
Table 4.2-26 Sound environment monitoring results in Ulansuhai Nur sea are
No.
Test Site No.
Daytime dB(A) Night dB(A)Nov. 19th, 2009 Nov. 20th, 2009 Nov. 19th, 2009 Nov. 20th, 2009
1 Third field 50.6 50.4 47.0 46.52 Xinmin 45.4 46.5 35.9 37.3
3Seventh
field45.8 44.6 32.6 32.0
4 Beilongtai 49.3 49.3 39.6 40.0
5Fourth field
45.3 45.4 42.1 41.2
6Fifteenth
field46.4 47.7 39.8 41.6
7 Fifth field 49.3 49.7 39.6 40.48 Sixth field 39.6 40.6 31.6 30.89 First field 45.3 47.9 36.5 34.5
It can be seen from Table 4.2-25 that, acoustic environment quality at the
proposed site of wastewater treatment and renovated water supply project in
Industrial Area was better, only the noise at night of East Plant Bound of wastwater
treatment and reuse project in Urad Front Banner Industrial Area was 50.4 dB (A),
and the noise of other monitoring sites did not exceed the standard limit of Class 2 in
accordance with “Standard for Acoustic Environmental Quality”.
It can be seen from Table 4.2-26 that, in the lake shore village of Ulansuhai Nur area,
the equivalent sound level in daytime was 39.6 ~ 50.6dB(A), and 30.8 ~ 47.0 dB(A) at
night, excepted for Third field noise at night, other monitoring sites all met the acoustic
environment function requirements of Class 1 district in accordance with “Standard for
Acoustic Environmental Quality” ( GB3096-2008 ) .
4.2.5 Sediment Monitoring4.2.5.1 Monitoring project
The Sediment Monitoring Project including
H2S 、 NH3 、 As 、 Hg 、 Chromium
(VI) 、 Cd 、 Pb 、 Bulk density 、 pH 、 Moisture
content 、 TN 、 TP 、 NH3-N 、 NO3-N 、 NO2-
N 、 Organic carbon 、 Organic content.
4.2.5.2 Sampling location layout
In accordance with the provisions of GB3838-2002, for sampling distribution,
refer to Figure 4.2-11.
Figure 4.2-11 Monitoring sites of current sediment4.2.5.3 Sampling analysis methods
The analysis methods should be implemented according to “Agricultural
Sludge Monitoring and Analysis”.
4.2.5.4 Monitoring Results
For the analysis result of lake sediment sampling in Ulansuhai Nur, refer to
2 sites in stable region
10 sites inseverely polluted region
4 sites in moderately polluted region
3 sites in slightly polluted region
Table 4.2-27.
Table 4.2-27 Sediment analysis of Ulansuhai Nur sea area
Sampling point position
Ammonia-N
TN TP Hg As Cu Pb Cd Zn
mg/kgg/kg
mg/kg
mg/kg
1 113.59 2.6 639.60.070
0.040
20.80
18.30
1.750
49.10
2 48.05 1.5 638.40.125
0.012
30.00
20.30
1.820
57.93
3 77.62 2.4 438.10.155
0.020
23.60
14.70
1.410
44.50
4 129.36 1.3 423.40.05
0.032
22.95
16.96
1.9448.68
5 213.64 1.2 355.40.082
0.035
25.94
12.77
1.6953.44
6 163.86 1.1 400.10.06
0.027
30.39
16.55
1.9551.57
7 44.60 1.5 504.30.050
0.011
7.118
11.75
0.908
33.43
8 57.90 1.6 603.80.048
0.032
16.78
14.99
1.669
47.33
9 60.37 2 245.20.047
0.030
10.96
13.61
1.111
34.32
10 93.39 2.3 368.60.046
0.036
10.86
13.08
1.284
38.40
11 58.4 1.2 544.60.055
0.017
10.8
10.51
1.2833.76
12 53 1.5 528.70.048
0.022
14.82
14.41
1.357
46.23
13 43.12 1.1 447.20.048
0.025
14.25
14.19
1.2745.49
14 75.77 1.1 521.30.024
0.018
9.106
5.900
0.584
16.25
15 86.86 1 344.90.058
0.059
10.56
10.85
0.904
31.25
16 40.66 0.9 271.60.074
0.042
21.60
19.10
1.540
51.21
17 102.5 3.3 586.20.056
0.059
9.280
14.30
1.220
38.51
18 35.79 2.6 432.40.034
0.041
10.18
13.52
1.245
38.69
19 55.44 2.1 312.60.047
0.086
11.31
12.18
1.356
40.64
4.2.5.5 Evaluation results
According to “Contaminants Control Standard for Agricultural Sludge” (GB
4284-84), Hg≤0.155 (Max=15mg kg-1), Cu≤30.39 (Max=500mg kg-1), Pb≤20.3
(Max=1000mg kg-1), Cd≤1.95 (Max=20mg kg-1) and Zn≤57.93 (Max=1000mg kg-1). It can
be seen that, the content of heavy metals didi not exceed the “Contaminants Control
Standard for Agricultural Sludge”, so Saline soil can be improved.
4,2.5.6 Analysis of sediment release
Sediment endogenous pollution and its potential ecological risk are two key problems
to decide whether to excavate and how deep to excavate. overlying water whether to be
affected by sediment endogenous pollution can be reflected by the intensity factor that is
target pollutant release rate; Sediments whether to have a higher potential ecological risk can
be evaluated by the breadth factor that is occurrence of pollutants which has an important
impact on biological in sediment. The former focuses on reflecting the effect on new surface
overlying water after dredging, while the latter reflects the possible potential ecological risk
on new surface environment. In order to master the details above before scientifically
understand the decision of grid water channel excavation; it must understand the spatial
distribution of pollutants in sediments and the release of sediment endogenous.
In January 2010 the sediment sampling was conducted at 19 sample points in
Ulansuhai Nur, and simulated the release of N and P in sediment under 25 ℃ indoor.
Analysis shows that: the release rate of N in other regions of Ulansuhai Nur was relatively
low, excepted for that in 5# sample point (64.34mg/m2 d on average); while the release rate of
P were generally higher, excepted for 19# sample point in fringe of dredging area, the release
rate in many other regions were about 2 mg/m2·d, of which, the release rate of P at 5# sample
point reached 8.76mg/m2·d, P in Ulansuhai Nur is the restrictive nutrient element for
biological, so it would be extremely important to control the release of P in sediment.
It can be seen form the result of N and P release (Figure 4.2-12) that, N release in
excavation area show forward and reverse, and forward is greater than reverse. Of which, the
Release rate of
N
Sampling points
release rate is relatively faster in vicinity of Xidatan. However, in terms of P release, all of the
sampling points released forward, and the release rate was almost beyond 2.0mg/m2·d, which
reflected that the entire excavation area had a obvious character of endogenous pollution in
sediment. P is the main substance source to the eutrophication of Ulansuhai Nur, so it’s
necessary to control the pollution of P in sediment with dredging.
Figure 4.2-12 N and P release experiment of Ulansuhai Nur sediment
4.2.6 Current status of ecological environment4.2.6.1 Terrestrial environment
1) Soil
( 1 ) Soil type
According to the second soil survey in 1985, there are more soil types in the city, and
there are 14 soil types, 32 subtypes, 94 soil genera and 348 soil species, such as irrigated soil,
saline soil, solonetz, aeolian sandy soil, moisture soil, fluvent soil, swamp soil, spodosol,
chestnut soil, calcic brown soil, desert grey soil, gray brown desert soil, lithosol, skeleton
soil, etc..
( 2 ) The formation and distribution of soil
Due to the changing climate and complex topography, soil formations are also
different. There are dry and peeling and residual formed grassland in the northern;
Sampling points
Release rate of
P
decadent and accumulative formed sloping fields and valleys; piedmont torrents alluvial
fan; wind formed Ulan Buh Desert; Yellow River alluvial formed Hetao Plain and zonal
flood land along the river, and its soil parent materials can be divided into the following
types:
1. River alluvium
Alluvial deposit of Yellow River is the main types of city’s soil-forming rock. Yellow
River is from Qinghai, Gansu and Ningxia, passing through the Loess Plateau, with rapid
flowing, and due to the scouring effect, the river carries huge amounts of silt, and the velocity
of flow slow down after into Hetao, then the alluvial deposit deposits with obvious levels in
accordance with the regular pattern of “the red mud deposit in slack water and the sand
deposits in flowing water”. The major soil of the rive bed in upper river shoal are sandy
soil and sandy loam, and that in downriver or depression is red mud-- clay soil. Therefore, the
farmers used to say that “deposit red mud far away, and deposit sand nearby”.
2. Irrigation deposit
Water of Yellow River contains huge amounts of silt, which flows into irrigation with
water, then the farmland is deposited, and the soil layer is thicken. Artificial Irrigation with
Yellow River has been conducted for long-term in Hetao, and together with artificial
production activities as farming and fertilizing, etc., the unique agricultural soil is formed--
irrigated soil.
The irrigated soils have evolved with some human factors as long-term farming,
irrigation and sedimentation, etc. after light-colored meadow soil had been reclaimed. The
main representative soil of it are sandy soil, desert soil, soft loess, hard loess, red mud, white
alkali soil, saline soil, etc..
Yellow River irrigation area of Hetao is west from Ulan Buh region and east to
Baiyanhua town, south to the Yellow River and north to the south slope of Wolf Mountain, all
of where are distributed with irrigated soil,and the total area of it is 7,561,063 acres.
3. Torrent alluvium
Torrent alluvium formed gradually by Yin Mountain flash floods, mixed with gravel
sediment, cattle manure and litter. The upper alluvial fan is dominated by gravel and grit, and
alluvial plains are mostly sandy loam to light loam. The soil there is deep and fat.
Torrent silt plain located in the north of the Ugab River and in the hillside area of
eatern Urad Front Banner, which is in zonal distribution, and the representative soil there is
torrent alluvium irrigated soil, and its area is about 296,760 acres.
4. Aeolian deposit
Aeolian soil is formed as the wind effect. Which mainly lacated in Ulan Buh region
and the edge of Charles Khan Desert in Baiyin city and near the isolated sand dune in Hetao
irrigation area, and its total area is about 10,656,739 acres. The representative soils there are
sandy soil and sandy loam.
5. Residual soil
Residual soils include chestnut soil, brown soil, grey desert soil, gray cinnamonic soil,
gray-brown desert soil, etc. Which mainly located in urban mountain dry region, and its area
is about 24,087,551 acres. The representative soils there is leaching gray cinnamonic soil, of
which area is about 384,459 acres, and located in Urad Front Banner Erdenii Prague, Bai
Yinhua, Sha Degai and Huh Bulag, etc; the area of general gray cinnamonic soil is about
430,958 acres, which is located in above region; the area of brown calcium soil is about
5,850,993 acres, which is located in farming-pastoral area of Urad Middle Banner and
pastoral area of Urad Front Banner; the area of chestnut silt is about 728,253 acres, which is
located in Chaoyang Township, Ming Heung Township and other township of Urad Front
Banner; the area of irrigated meadow chestnut soil is about 98,621 acres, which is located in
Da Shetai and other regions of Urad Front Banner.
( 3 ) Classification area of soil and its physicochemical property
①Classification area of soil
The soil in Bayannaoer is classified according to soil texture (V level), there are sand,
sandy loam, medium loam, light loam and clay. According to soil layer, the soil is classified
into surface soil layer ( 0—30cm ) , subsoil layer ( 30—60 cm ) and bottom
layer ( 60—100 cm ) , the soil profile pattern is very complex.
The individual differences of the irrigated soil in Hetao alluvial plain mainly depend on
the soil profile pattern, which is composed of various soil textures and their arrangement, and
the soil profile pattern not only limits the running of the water and nutrient in soil, but also
influences the agricultural production characteristics of soil. The soil profile pattern subjects
to 1 meter in depth, and can be classified into three basic layers, that are (The Topsoil, the
subsoil, the bottom soil ) top, middle and bottom, according to the thickness of different soil
textures, the soil profile pattern has been approximately classified into five categories:
Homogeneous pattern: the full profile is coposed of uniform texture. Such as Sandy,
desert soil, red mud, etc.
Thick body pattern: another soil texture with thick layer (>40 cm) under the topsoil,
such as Sand drain two loess, Viscous body two loess, etc.
Bandwich pattern: another soil texture with middle thick layer (20—40 cm) in the
subsoil layer, such as two loess with sand, two loess with clay, etc.
Bottom pattern: another soil texture with middle thick layer under the bottom soil, such
as sandy soil with clay bottom, two loess with sand bottom, etc.
Three segmental patterns: the three layer segments of top, middle and bottom are three
kinds of soil texture, such as two loess with sand bottom and clay, two loess with clay
bottom and sand, etc.
Each of above soil profile pattern has a different fertility properties, production
characteristics, profile morphology, thickness and layer, and there are also significant
differences in each growth layer of soil.
The soil types in hill arid area include gray desert soil, chestnut, chestnut silt soil, etc.
The soil profile pattern there is more complex, such as residual leached gray cinnamonic soil,
which has thicker litter layer on the top, dark gray or black humus layer in sequence and
caliche at bottom, all profiles of it are with calcium carbonate reaction, and its parent
materials are gneiss and granite.
2) Vegetation
The type of the vegetation in Bayannaoer is quite complex due to the influence of
climat and topographic condition. It can be classified generally into mountain vegetation,
desert vegetation, sandyland vegetation, crops, etc. Grassland vegetation includes dry steppe
and desert steppe. Desert vegetation includes steppe desert and stony desert. Its distribution is
grassland—dry steppe—desert steppe—steppe desert—desert from east to west. And is
meadow vegetation—mountain vegetation—plateau dry steppe—desert from south to north.
It showed obvious latitude and longitude zonality, which is consistent with the distribution of
soil. In addition, there are psammophytic vegetation, halophytic vegetation, meadow
vegetation and other non-zoneal vegetations. Accrding to the vegetation type and floristic
characteristics, the vegetation of the whole city can be classified into six districts.
Due to the farming, almost no original vegetaions were preserved in Hetao plain, and
the existing arbors were planted artificially. Herb is the main vegetation there, of which, there
mainly are Meadow vegetations which is dominated by Gramineae, Chenopodiaceae,
Polygonaceae and Asteraceae. In the low-lying area there are Halophytic vegetations. Around
the sparkling lakes there are aquatic and wetland plants. In the arid area of piedmont there are
xeric prickly shrubs.
①Meadow vegetation
It is distributed in flood land, and is mainly composed of grasses, such as small reed,
Crypsis aculeate, serrated melilotus, Xanthium, etc. The Meadow vegetation in sea water is
dominated by floatingheart.
There is fewer natural vegetation in alluvial plain, and a small amount of wild plants
can be seen only in the unoccupied place of farmland. The main vegetations are dominated
by Equisetum ramosissimum, Eragrostis and Chloris. In addition, there are also a lot of Ixeris
denticulate, Digitaria, Aster altaicus and Setaria. The wild plants which are dominated by
Digitaria and Carex, is distributed in lower and wet area, of which, internodes take root
sometimes down to the ground with strong spreading force. Xanthium and Chenopodium
album L., which consume large amounts of nutrients, are the main weeds in the farmland. In
the flat area there are Callitriche Verna, Barnyard grass and Semen Cuscutae.
Wild plants which are dominated by Reeds and Barnyard grass are distributed in the
shallow depression. The root of reed is corm, and its regeneration capacity is very strong,
which prevails over other weeds; the symbiosis grasses include Barnyard grass,
Bolboschoenus maritimus and Imperata.
Wild plants which are dominated by Imperata, Drought Polygonum, Equisetum
ramosissimum and Reeds, are distributed in flood plain, river channel, and sandy soil with
high groundwater or coarse sandy meadow soil with slightly saline soil.
Many of the Imperata are wild, and have strong growth vigor, which plays a good role
in fixing the sand and diking the dam. Drought Polygonum grows in river often flood areas,
and willow is its symbiosis grass.
②Halophytic vegetation
The vegetations, which are distributed in the saline soil with hight salinity, include
Suaeda, Kalidium foliatum, Red Woodsorrel ( Karelinia caspica ) , small reed,
Polygonum sibiricum, Alkali grass, Allium fistulosum, basio, stubbed rock grass, etc.. The
vegetations which are are distributed in less saline areas include sea milkweed, Chinese
tamarisk and Halerpestes ruthenica. And the vegetations which are are distributed in lowland
saline soil includesalt absorption ( suaeda salsa ) , which has strong salt tolerance and
adapted to wide rang of area. In the salt accumulation area there is Nitraria
tangutorum ( jujube ) . And in the edge of depressions where are easy for salt
accumulation there is saline Chenopodiacea.
③Aquatic vegetation
It is mainly distributed in water zone or moat, the common species include Reed,
Typha, yagara and Bolboschoenus maritimus, along the river bank, there are willow and
Chinese tamarisk.
④Desert vegetation
There is Agriophyllum squarrosum in the wandering dune , and in the fixed dune or
sandpile, there mainly is Nitraria tangutorum, and a small amount of Achnatherum sptendens.
In the area with thin sand layer and higher humidity, there are Alopecuroides L,
Agriophyllum pungens, Artemisia desertorum, Licorice, Inular flower and Peganum
nigellastrum.
⑤Farmland weed
Hetao plain is irrigated agricultural area. The main weeds of summer crops include
Plaque bamboo, Wild Oats, Vetch, Chenopodium album L., etc.. The main weeds of autumn
crops include Agropyron, Calamagrostis, Reed, Cirsium setosum and Thistle.
⑥Desert grassland vegetation
It is mainly distributed in the foothills terrace of Wolf Mountain , composing of
drought-tolerant small semi-shrub grasses. The common species include Caragana
stenophylla, Saffranine, Pearl, Artemisia frigida, Ziziphus jujube, Caragana intermedia,
Lamerei and Nitraria tangutorum.
3) Wild plants
The climate in Bayannaoer is cold, drought and windy, and precipitation there decrease
gradually from southeast to northwest, which led to that from southeast to northwest the
vegetation taken on the distribution series of the dry steppe – the desert steppe – the steppe
desert - the desert in sequence. And of which, the desert steppe and the steppe desert make up
the main body of zonal vegetation in this area.
It is quite lacking of wild plants in Bayannaoer, and the mian plants there is Xerophyte,
there are about 94 families 378 genera and 918 species of wild plants, of which, there are 7
families 7 genera and 12 species of Pteridophyte, and the seed plants are remained. The Herbs
are the main seed plants there, and there are 728 species of Herbs, which are dominated by
Perennial herbs in total of 566 species, and account for 61.65% of the total number of wild
plants. In addition, there are 36 families 78 genera and 178 species of xylophyta, most of
which are shrubs, and only 31 species of arbors.
4.2-28 The statistical table of wild plant in Bayannaoer City
QuantityCategory
Families
GeneraSpecies
Spermatophyte
AngiospermDicotyledon 71 296 712
Monocotyledon 13 70 185Gymnosperm 3 5 9Subtotal 87 371 906
Pteridophyte 7 7 12Total 94 378 918
The total number of wild plants in Bayannaoer is not rich, but there are more
families and genera. The total number of wild plants there is 40.2% of that of Inner Mongolia
Autonomous Region, while the number of sepecies there is 73.4% of the total number of
families. Thus increases the complexity of plantage, and plant species are more concentrated
in a small number of plant families and genera, which led to a lot of single, few species,
genera and families. The wild plantage in the city contains 49 single subjects, which account
for 52% of the total number of the subjects, in which, there are 28 single species, more than
20 species of 12-family, in total of 643 species of plants, which account for 67.4% of the total
number of wild plants in the city, of which, there are 430 species of plants in Compositae,
Gramineae, Leguminosae, Rosaceae and Chenopodiaceae, accounting for 45% of the total
number of wild plants in the city. There are 196 genera of single species, while only 9 species
of genera more than 10, of which, there are 26 species of Artemisia which is the most, and
secondly, there are 23 species of Astragalus and 22 species of Wilt Potentilla, Carex, Allium,
Polygonum, Oxytropis and Saussurea are remained.
Hetao plain is located in the southern border city, the vegetation type there is the
steppe desert, and there are about 200 species of wild plants, mainly are farmland weed, and
aquatic, salt and sand plants, most of wild xylophyta are distributed in shoaly land along the
Yellow River, depression before the hill and depression of ancient river, where there mainly
are Populus euphratica, Elaeagnus angustifolia L., Elm, Chinese tamarisk, a variety of shrub
willow, Myricaria germanica, Nitraria tangutorum, Caragana intermedia, Kalidium foliatum,
etc.. In the plain farmland, there are Alopecuroides L, Taraxacum, Chenopodium album L.,
Xanthium Fructus, Lactuca chinensis and Eragrostis poaeoides; in the waters, there are Reed,
Typha, Bolboschoenus maritimus, Duckweed, etc.; in the alkaline land, there are a variety of
grasses as Salsola ruthenica and so on. There are more than 150 species of resources plants,
of which, more than 130 species can be feed and more than 100 species can be used
medicinally. The common species include Taraxacum, Patrinia villosa, Plantain Seed, Semen
Cuscutae, Cirsium setosum, Kochia scoparia, Xanthium Fructus, Capillary artemisia,
Alopecuroides L, etc.
4) Wild animals
The climate of Bayannaoer is dry and cold, and the vegetation there is dominated by
low vegetation and shrubs, and there is with high proportion of sandy and gavel surface, so
the natural condions there is harsh, and there belongs to the Palaearctic in Asia and Asia's
new Mongolian border area based on geographical divisions on the animal. Due to the limit
of natural condition, the wild animal species there are lacking. According to incomplete
statistics, there are 7 orders, 15 families and 49 species of animals within the city, which is
43% of the total number of animals in Inner Mongolia Autonomous Region; there are 17
orders, 44 families and 199 species of birds, which is 55% the total number of birds in the
Autonomous Region; There are 13 species of reptiles; 4 species of batrachia; and many other
insects.
Due to the effect of the long-term human activities, wild animals in Hetao plain had
disappeared, only over ten kinds of rodents existed in this plain, such as hamster, jerboa,
gerbil, field mouse, etc., as well as rabbit, pika and so on. Many kinds of lizards can be found
everywhere on isolated sand, as well as snakes and hedgehogs, and dozens of species of
birds, such as swallows, warblers, sparrows, crows, upupa epops, long tailed shrikes, pigeons,
woodpeckers, cuckoo, quail, bustard, eagle, etc. There are also muskrat living in every
waterspace.
Ulansuhai Nur, at the eastern end of Hetao plain, is an important place in western Inner
Mongolia for migratory birds to stop for a rest, for waterfow to moult and to reproduce.
According to incomplete statistics, there are more than 150 species of birds in this area,
which include Whooper Swan, Mute Swan and other birds under State protection( category
II), and 97 species under “Sino-Japanese agreement on protection of migratory birds and thier
habitats”. The most birds in this area are migratory birds or passing migrant birds with going
in winter and coming in summer everyyear, and due to the protection of bird resources,
Municipal Government issued a Notice in 1984 to protect bird resources of Ulansuhai Nur,
and this area was designated as a suspended hunting area.
5) Soil erosion
The soil ersion areas of Bayannaoer are distributed within Urad Front Banner, Urad
Middle Banner, Urad Back Banner and Dengkou County, which belongs to Yellow River
basin and inland river basin. There are 35 townships and Sumu in this area, the total
population there is 192 610, and the population density is 9/ km2.
The natural features of soil ersion area are divided into rocky mountain area and windy
and sandy area. The rocky mountain area is used to call arid mountain area, and its total area
is 18687 km2, all of which are soil ersion area, this area is located between 106°08’—
109°45’E. Longitude and 40°26’—42°20’N. Latitude. The windy and sandy area mainly
refers to Ulan Buh Desert within Dengkou County, and its total area is 2747.2 km2, which is
located between 106°11’—107°06’E. Longitude and 40°46’—40°08’N. Latitude. The soil
ersion mainly are wind erowion, which is more in winter, and water erosion, which is more in
June and July. The annual erosion modulus is 2527-6075t/ km2.
4.2.6.2 Existing condition analysis of biological diversity in Lake Wuliangsuhai
1) Zooplankton
(1) Role of zooplankton
Zooplankton play a key role in the material cycling and energy flow of the aquatic
ecosystem. It has a significant impact on carrying capacity and biological resource
recruitment in the aquatic ecosystem as follows: Zooplankton feed on phytoplankton and①
micro-organisms, therefore, they can purifiy water. Zooplankton dominant species are used②
to assess water quality, therefore, zooplankton can be used as indicators for humification of
the aquatic environment. Zooplankton are also food sources for fish fry and mature fish.③
Fish productivity of aquatic ecosystem is determined by the zooplankton species diversity,④
abundance and biomass.
(2) Zooplankton survey in 2004-2005
① Zooplankton community composition and dominant species
A, Zooplankton community composition in the whole lake and features of
dominant species
There are totally 4 categories and 62 species of zooplankton in Lake Wuliangsuhai
and there are 33 species of rotifers at most, 16 species of protozoa, 9 species of
copepods and 4 species of cladocerans. (See Table 4.2-29)
Table 4.2-29 Lists of zooplankton and benthonic animals in Lake Wuliangsuhai
动 物 名 称(Name of the animal)
门类(Phylum) 纲 / 科(Class/family)
种类(Species)
浮 游 动 物(zooplankton)
原 生 动 物 (Protozoa)
肉 足 虫(Sarcodina)
盘表壳虫 (Arcella discoides)圆滑表壳虫 (A. rotundata)盘状匣壳虫 (C. discodides)巧砂壳虫 (Difflugia elegam)瓶砂壳虫 (D. urceolata)大变形虫 (Amoeba proteus Leidy)
蛞蝓变形虫 (A. 1imaz)放射太阳虫 (Actinophrys sol)
纤 毛 虫(ciliate)
团焰毛虫 (Askenasia volvox)圆缨球虫 (Cyclotrichium sphacricum)毛板壳虫(Coleps hirus Hitzsch)沟钟虫 (Vorticella convallaria)小口钟虫 (V. microstoma)大弹跳虫 (Halteria grandinella)湖累枝虫 (Epistylis lacustrls)
轮虫 (Rotifera) 颤动疣毛轮虫 (Synchaeta trernula)尖尾疣毛轮虫 (S. stylata)角突臂尾轮虫 (Brachionus angularis Cosse)萼花臂尾轮虫 (B.calyciflorus Pallas)壶状臂尾轮虫 (B. urceus)蒲达臂尾轮虫 (B. budapestiensis)花箧臂尾轮虫 (B. capsuliflorus)螺形龟甲轮虫 (Keratella cochlearis)曲腿龟甲轮虫 (K. valga)矩形龟甲轮虫(K. quadrata)尖削叶轮虫 (Notholca acuminata)囊形单趾轮虫 (Monostyla bulla)精致单趾轮虫 (M. elachis)盘镜轮虫 (Testudinella patina)微凸镜轮虫 (T. mucronata)长三肢轮虫 (Filinia longiseta)针簇多肢轮虫(Polyarthra trigla)钩状狭甲轮虫 (Colurella uncinata)钝角狭甲轮虫 (C. obtusa)卵形鞍甲轮虫 (Lepadella ovalis)裂足轮虫 (Schizocerca diversicornis)月形腔轮虫 (Lecane luna)没尾无柄轮虫 (Ascomorpha ecaudis)团藻无柄轮虫 (A. volvocicola)大肚须足轮虫 (Euchlanis dilatata)三翼须足轮虫 (E. triquetra)小须足轮虫 (E. parva)卜氏晶囊轮虫(Asplanchna brightwelli)暗小异尾轮虫 (Trichocerca pusilla)鼠异尾轮虫 (T. rattus)冠饰异尾轮虫 (T. lophoessa)环顶巨腕轮虫 (Pedalia fennica)尖尾环顶巨腕轮虫尖 (P. fennica)
枝角类 (Cladcera)
长 肢 秀 体 溞 (Diaphnosoma leuchtebergianum)
蚤状溞 (Daphnia pulex)长额象鼻溞 (Bosmina longiroustris)
桡足类 (Copepode)
圆形盘肠汪(Chydorus sphaericus)英勇剑水蚤(Cyclops strennus)近邻剑水蚤 (C. vicinus)角突刺剑水蚤 (Acanthocyclops thomasi)大尾真剑水蚤(Eucyclops macraroides)如愿真剑水蚤 (E. speratus)锯齿真剑水蚤 (E. macruroides)台湾温剑水蚤 (Thermocyclops taohokuensis)直 刺 北 镖 水 蚤 (Arctodiaptomus rectispinosus)
咸水北镖水蚤(A .salinus)
B, Zooplankton community composition in small sea and features of dominant
species
The small sea areas occupy 36km2. There is about 10km2 shallow in the northeast.
The areas where small sea connects with lake are marshlands and reedlands. There are
20km2 of reedlands and 6km2 of marshlands. Water exchange takes a long time
between small sea and the lake. Therefore, the water is relatively stable. The average
water depth is 0.5m, not deep. According to the survay at site 1 and site 2, there are
totally 4 categories and 60 species in small sea. Among these, there are 32 species of
rotifers at most, 16 species of protozoa, 8 species of copepods and 4 species of
cladocerans.
C, Nature Reserve - zooplankton community composition in core areas and features of
dominant species
There are 16 km2 of core areas and average water depth is 1.2m. Most of the areas are
open waters in core areas. There are a small number of reeds in the northwest and south.
According to the survay at site 3, 4, 5, 6, 7, There are 4 categories and 49 species in core
areas. Among these, there are 26 species of rotifers at most, 10 species of protozoa, 9 species
of copepods and 4 species of cladocerans.
② Zooplankton abundance and biomass
There are high zooplankton abundance and biomass in Lake Wuliangsuhai. Since some of
zooplankton are large and some are very small, therefore, they are divided into 2 parts when
counted: large zooplankton (including cladocerans, copepods, nauplii and rotifers) and
protozoa. The annual average abundance of large zooplankton and protozoa are respectively
687 L-1 and 2.508×l04 L-1. The annual zooplankton biomass is 3.624 0 mg L-1 on average.
See Table 4.2-13 for zooplankton abundance and biomass:
Fig. 4.2-13 Abundance and biomass of large zooplankton
Zooplankton biomass and abundance in small sea is higher than that in the whole lake,
while zooplankton biomass and abundance in the core area is lower than that of the whole
lake. See details in Fig. 4.2-14.
/
Fig. 4.2-14 Zooplankton abundance in small sea and core area
Fig. 4.2-15 Zooplankton biomasses in small sea and core area
③ Seasonal changes of zooplankton abundance and biomass
Abundance of protozoa and large zooplankton in Lake Wuliangsuhai reaches the
highest level in summer with an average abundance of 1 874.05 and 3.978 × 10 4L-1
respectively. And the second highest abundance appears in spring, respectively 809.83 and
3.881×10 4 L -1. Lowest abundance of protozoa appears in autumn with an abundance of
only 0.693 3 × 104L-1, while the lowest abundance of large zooplankton appears in winter
with an abundance of 12.21 L-1. The zooplankton abundance and biological changes in samll
sea and core area are of the same trend with that in the whole lake.
Table 4.2-30 Seasonal changes of zooplankton abundance
Spring Summer Autumn Wintermg L-1
Protozoa 0.36 0.37 0.06 0.09Cladocera 0.43 0.64 0.3 0.016Copepods 5.3 6.40 0.48 0.21Nauplius 1.2 1.20 0.12 0.05Rotifer 0.6 1.10 0.12 0.4
Fig. 4.2-16 Seasonal changes of zooplankton biomass
3) Evaluation methods
It has significantly valuable to take advantage of zooplankton community structure,
biomass changes and distribution of dominant species to monitor and evaluate water
environment. This method has been used for long both at home and abroad. It is more
objective to evaluate the eutrophication and pollution states by zooplankton species, density
and diversity. After a comprehensive survey of 211 inland waters in China, Zhihui He has
discussed in detail the nutritional type classification of Chinese lakes and reservoirs. He put
forward a standard to evaluate the water trophic level by zooplankton biomass. The standard
are as follows: 0.16-2 .19 mg/L (average 0.96 mg/L) for the poor trophic level; 0.28-
17.60mg/L (average 2.10 mg/L) for the medium trophic level; 0.59-9.52mg/L (average
3.59mg/L) for trophic level; According to the investigation at the Yuqiao reservoir, Mingde Li
concluded the annual average zooplankton biomass in non-ice period: <1 mg / L for the poor
trophic level; 1.1-3.4 mg / L for the medium trophic level; 3.5-8.0 mg / L for the high trophic
level; > 8.0 mg / L for the super trophic level.
(3) Evaluation results
According to the above evaluation standard, annual average zooplankton biomass of
Lake Wuliangsuhai is 3.624 0 mg / L, changing in the range of 0.220 7-7.809 9 mg / L, Water
in Lake Wuliangsuhai is in trophic level. The annual average biomass of small sea and core
area are 4.424 0 mg / L and 3.224 0 mg / L. It is obvious that the trophic level of small sea is
higher than that of core area.
The number of zooplankton species in Lake Wuliangsuhai are rotifers > protozoa>
Cladocera> copepod. The number of average zooplankton biomass are copepods> nauplii>
rotifers> Cladocera> protozoa. Zooplankton abundance and biomass are at its highest level in
summer and spring, but decline sharply in autumn and reach to lowest level in winter (except
protozoa). The main reason is that local temperature declines sharply. Then there comes the
cold winter.
2) Benthonic animals
(1) Role of benthonic animals
Benthonic animals are one important composition of freshwater ecosystem. It is theoretical
significant to learn the structure and function of the ecosystem. Benthonic animals can also be
used as natural food for economic aquatic life, such as fish. Some of the benthonic animals
are of high economic value themselves (such as river crab and etc.). In addition, the
benthonic animals are also often used as biological indicators for environmental monitoring.
With this method, not only the water quality can be reflected over a period, but also synergic
and antagonistic effects of the pollutants can be reflected in the water and namely the
comprehensive toxicity of each pollutant. Therefore, benthonic animals can provide valuable
reference to prevent pollution and protect biodiversity.
(2) Survey of benthonic animals
① Community composition and dominant species of benthonic animals
2 sampling surveys are carried out in August and October. Total 11 species of
benthonic animals are found. They belong to 3 phylum, 3 classes and 4 families. Among
them, there are 8 chironomidaes of arthropoda, 1 lymnaeidae and 1 planorbidae of mollusca,
1 tubificidae of annelida (See Table 4.2-31). The community composition of benthonic
animals in small sea and core area are the same.
Table 4.2-31 Composition of benthonic animals in Lake Wuliangsuhai
动 物 名 称(Name of the
animals)
门 类 (Phylum) 纲 / 科 (Class/family) 种 类 (Species)
底 息 动 物(Benthonic
animals)
节 肢 动 物 门(Arthropods)
摇 蚊 科(Chironomidae)
隐 摇 蚊 (Cryptochironomus sp.)
拟 长 跗 摇 蚊 (Paratanytarsus spl)
羽 摇 蚊 (Chironomus plumosus)
塞氏 摇 蚊 (Tendipes gr.)
大红羽 摇 蚊 (Tendipes gr. Reductus)
梯形 摇 蚊 (Polupedilum scalaenum)
花翅前突 摇 蚊 (Procladius chorens)
雕翅摇 蚊 (Glyptotendipus)
软体 动 物 门(Mollusca)
椎实螺 科(Lymnaeidae)
萝卜 螺 (Radix)
旋螺 (Gyraulus)
环 节 动 物 (Annelida) 颤蚓科 (Tubifcidae) 霍莆水丝蚓 (L. hoffmeisteri)
1 ) Abundance and biomass of benthonic animals
According to the surveys in August and October, 2004, the average abundance of
benthonic animals in Lake Wuliangsuhai is 3 031.4 m2, among which the abundance
of chironomidae is the highest, occupying 93.58 % of the total. The next is the
mollusca with 6.07 % and there are very few oligochaeta, only 0.35 % . The
average biomass of benthonic animals is 71.672 g m2. The biomass of chironomidae is
at most with 50.30 % of the total. The biomass of mollusca takes up 49.64 %
and there are almost no oligochaeta, only 0.06 % of the total.
Fig. 4.2-17 The abundance and biomass of benthonic animals
Abundance of benthonic animals in small sea is much higher than that in core area,
1474.2L-1 of chironomidae, 188L-1 of mollusca and of 10.9L-1 oligochaeta more, nearly 10
times.
Fig. 4.2-18 Abundance of benthonic animals
Biomasses of benthonic animals in small sea is also much higher than that in core area,
13.6mg L-1 of chironomidae, 112.7mg L-1 of mollusca and 0.128mg L-1 of oligochaeta
more, nearly 12 times.
Fig. 4.2-19 Biomasses of benthonic animals
(3) Evaluation methods of benthonic animals
Benthonic animals are one of the important compositions of freshwater ecosystems.
They are very sensitive to pollution and can reflect change of water quality more directly;
therefore, they are often used as biological indicator of water conditions. According to the
classification of Carlander in 1952, if biomass of benthonic fauna in reservoir are between
0.20-1.70 g/m2, the water are classified as poor trophic type, 2.50-6.25 g/m2 as medium
trophic type and 10.00-25.00 g/m2 as trophic type. In 1980, Russian scholar A.H. Sayyaf
classified the reservoir eutrophication in Soviet Union into 5 types as follows : <1.5
g/m2 , 1.5-3.0 g/m2, 3.0-6.0 g/m2, 6.0-12.0 g/m2 and >12.0 g/m2.
(4) Evaluation results of benthonic animals
The average biomass of benthonic animals in summer and autumn are up to 71.672
g/m2 in Lake Wuliangsuhai. Water in Lake Wuliangsuhai during the two seasons is in trophic
level. The biomass in small sea and core area are 84.4237 g/m2 and 62.2432 g/m2
respectively. The trophic level of core area is lower than that of small sea. The sequences of
average benthonic animal biomass are: chironomidae > mollusc> oligochaetes.
3 ) Phytoplankton
(1) Role of phytoplankton
Phytoplankton is autotrophic plankton. They have chlorophyll or other chromatophore,
which can absorb sunlight energy (solar radiation) and carbon dioxide for photosynthesis to
synthesize organism (mainly carbohydrates). Therefore, phytoplankton is the main
productivity in water and also the basis for food chain and trophic structure. Some
phytoplankton can also be used as indicator for environmental monitoring. Comparing with
the physiochemical conditions, trophic level can better reflected by the density, biomass,
species composition and diversity of phytoplankton.
(2) Phytoplankton survey
Phytoplankton community composition and dominant species ①
With sampling in spring, summer, autumn and winter, it is preliminary known that
there are 7 phylum and 58 genera in Lake Wuliangsuhai. There are 22 genera of chlorophyta
at most, accounting for 37.9 % of total. Bacillariophyta comes the next with 14 genera,
accounting for 24.1 % . There are 13 genera of cyanophyta, accounting for 22.4%. The
numbers of chrysophyta, cryptophyta and euglenophyta are small, 4 genera, 2 genera and 2
genera respectively, accounting for 6.9%, 3.4% and 3.4%. There are only 1 genera of
pyrrophyta at least, accounting for 1.7% of the total (Table 4.2-20). All above phytoplankton
communities can be found in small sea and core area.
Table 4.2-32 Phytoplankton composition
门 类 (Phylum)属 类 (Genera)
百 分 比 Percentage (%)
绿 藻 门 (Chlorphyta) 22 37.9
硅 藻 门 (Bacillariophyta) 14 24.1
蓝 藻 门 (Cyanophyta) 13 22.4
裸 藻 门 (Euglenophyta) 4 6.9
隐 藻 门 (Cryptophyta) 2 3.4
金 藻 门 (Chrysophyta) 2 3.4
甲 藻 门 (Pyrrophyta) 1 1.7
总 计 (Total) 58 100
Phytoplankton density and biomass②
The annual average density and biomass of the phytoplankton in Lake Wuliangsuhai is
33.01×106ind L-1 and 26.33 mg L-1. See Table 5.6-8 and 5.6-9 for the all algae density and
biomass percentage.
Fig. 4.2-20 Algae biomass in Lake Wuliangsuhai
Annual average abundance of phytoplankton in small sea and core area are 53.4×106
ind L-1 and 29.84×106ind L-1. The abundance of phytoplankton in small sea are
24.56×106ind L-1 more than that in core area.
Fig. 4.2-21 Abundance of all kinds of algae
Average phytoplankton biomass in small sea and core area are 40.14mg L-1 and
20.04mgL-1. The biomass of phytoplankton in small sea is 20.1mgL-1 more than that in core
area.
Fig. 4.2-21 Biomasses of different types of algae
③ Seasonal changes of phytoplankton density and biomass
It is known from Fig. 5.6-11 that seasonal density changes of cyanobacteria,
chlorophyta and diatom chrysophyta are the same. The density is relatively high in spring and
reaches its highest level in summer and falls to the lowest level in autumn and begins to
increase again in winter. The density of chrysophyta, cryptophyta and euglenophyta are up to
its highest level in spring and then decrease gradually to its lowest level in winter, almost
zero. (Density of chrysophyta increase a little bit) There are only a few pyrrophyta found in
summer and winter. Almost no pyrrophyta can be found in spring and autumn. In addition,
chrysophyta is the dominant one in spring with the largest density. But summer is
overwhelmingly dominated by cyanobacteria and the situation continues until winter comes.
It is known from Fig. 5.6-12 that the seasonal changes of biomass and density are basically
the same. Chlorophyta and diatom chrysophyta are the only ones, of which the seasonal
changes of biomass and density are different in spring and summer. In additional,
euglenophyta has the largest biomass due to its large number and body. In summer,
cyanobacteria increase rapidly to its highest level and take place of euglenophyta and
cryptophyta. In autumn and winter, most of other algae will die and biomass of diatom
chrysophyta is the largest of all. Throughout the year, diatom chrysophyta has the smallest
changes in biomass and density, while changes of the other 6 algae are large.
Fig. 4.2-23 Seasonal changes in algae density
Fig. 4.2-24 Seasonal changes of algae biomass
(3) Evaluation method of phytoplankton
Since different waters are suitable for different algae, the algae species can be used
as the indicator to evaluate water trophic level. In 1949, Nygaard put forward the theory PCQ
(phytoplankton compound quotient) and it was used to reflect the ecological status of the
lakes and have achieved good results. Ott & Laugaste (1996) further developed the formula
for the evaluation of lakes in Estonia. The evaluation accuracy has been further improved.
The formula is as follows:
In the formula : * represents number of different kinds. See table 4.2-33 for its
eutrophication state classification.
Table 4.2-33 Classification of lake ecological status by PCQ
营 养 状 况 (Eutrophication state) PCQ
贫 营 养 型 (Poor trophic state) <2
中 营 养 型 (Mesotrophic state) 2-5
富 营 养 型 (Eutrophic state) 5-7
超 富 营 养 型 (Ultra-eutrophic
state)>7
(4) Evaluation results of phytoplankton
This formula is used in the article to evaluate the trophic level in Lake Wuliangsuhai
and it is calculated that PCQ value of the lake is 6.6, which means Lake Wuliangsuhai is in
eutrophic state. The PCQ value in small sea is 7.3, which means water in small sea are in
ultra-eutrophic state. The PCQ value in core area is 5.7 and the water is in eutrophic state.
① According to the research results, phytoplankton density throughout the year are:
cyanobacteria> chlorophyta > chrysophyta > diatom chrysophyta > cryptophyta >
euglenophyta> pyrrophyt. The biomass of dominant species are euglenophyta >
chlorophyta > cyanobacteria > diatom chrysophyta.
② Lake Wuliangsuhai is located in the North China, the weather of which has following
features: dry and cold, large difference of annual temperature, high temperature in summer,
long and cold in winter. Therefore, algae density and biomass change greatly, high in spring
and summer, but low in autumn and winter. In addition, seasonal change of diatom
chrysophyta is relatively stable, which may be because diatom chrysophyta is not very
sensitive to climate impact.
③ According to the PCQ formula results, it is known that water in Lake
Wuliangsuhai is in eutrophic state, which is caused by the following 4 reasons:
Irrigation return flow from Hetao irrigation region: as of now, there are 43.7×104 t
fertilizer used in Hetao irrigation region, but the utilization rate is only about 35 % . About
28.4×104 t nutrients flow into Lake Wuliangsuhai every year, which has caused the
increasing primary productivity of the lake. According to water quality monitoring results in
estuary, total average nitrogen content is 1.74 mg/L, 8 times of common international
standard. The total average phosphorus content is 0.07mg/L, which is 3.5 times of common
international standard.
Industrial wastewater: Pollution in Hetao region is very serious due to industrial
structure. Paper making and chemical industries are the leading industries in Hetao region,
but these industries cause serious pollution. There are a very small proportion of high-tech
and low polluting industries in this region. A large number of untreated wastewater flows into
Lake Wuliangsuhai through irrigation drainages every year, which greatly accelerate the
degree of its eutrophication.
Domestic sewerage: A large number of high phosphorus domestic sewerage is
discharged directly into Lake Wuliangsuhai from Hetao irrigation region.
Pollution from rural areas in Hetao region: every year a large number of human and
animal feces and straw putrilage flow into Lake Wuliangsuhai with the rainfall. This also
contributes to the pollution.
4 ) Fish
(1) Species of fish and its faunal features
According to fish survey and samples collected in 2000 – 2002 and " China fish retrieval
system", it is preliminarily known that the number of fish in Lake Wuliangsuhai are not large,
about 8-10 species, belonging to 2 orders, 3 families. There are mainly cyprinid, 5 species,
accounting for 62.5%. 2 species of cobitidae and 1 species of catfish exist in Lake
Wuliangsuhai, accounting respectively 25% and 12.5% of the total. See Table 4.2-34 for fish
survey details in Lake Wuliangsuhai.
Table 4.2-34 Fish composition in Lake Wuliangsuhai
调查时间 ( Survey time) 调查时间(survey time)序 号 (No)
中 文 名 (Chinese Name)
1960 1980 1981-1983 2000-2002
1 青鱼(Catfish) +
2 草鱼(grass carp) + + +
3 瓦氏雅罗鱼(Leuciscus waleckii)
+ + +
4 赤眼鳟(Squaliobarbus) + + +
5 鲦 (hemiculeer leucisculus)
+ +
6 团头鲂(Megalobrama amblycephala ) + + +
7 长春鳊( Parabramis pekinensis ) +
8 麦 穗 鱼 ( Rajah Cichlasoma ) + + +
9 似鱼句(Pseudogobio vaillanti (Sauvage) ) + +
10 棒花鱼(Abbottina) +
11 中 化 鲚 自 (Zhonghuajizi ) + +
12 鲤鱼 (carp ) + + + +13 鲫鱼(crucian carp) + + + +
14 鳙 ( aristichthys nobilis ) + + +
15 鲢(chub) + + + +16 花鳅(loaches) + + +17 泥鳅(loach) + + + +
18后 鳍 巴 鳅( Nemachilus posteroventralis. )
+ + + +
19 董 氏 须 鳅(Dongshixuqiu ) +
20 鲶(silurid ) + + + +
21 黄 鱼 囊 ( Yellow Croaker ) +
22 青懿(Qingyi ) + +
23 黄 鳓 ( Chinese herring) + +
24 克 氏 童 段 虎 鱼 +
( Keshitongduanhu Fish )
总计 (Total ) 12 18 21 8
(2) Fish stocks changes
Lake Wuliangsuhai has a history of more than 100 years. The lake has been in natural
state till 1958 and the fish stocks during that period are mainly carp, crucian carp, catfish and
etc. The number of carp is the most. There are no fishery production, but only individual fish
men and seasonal fishing later on. Fishery production started in 1954. With the expansion of
fishery production, people begin to cultivate black carp, grass carp, silver carp, bighead carp
and blunt head bream in Lake Wuliangsuhai. But for various reasons, none of the 5 fish
stocks have produced stable biomass. As the water environment in Lake Wuliangsuhai
changes, the biomass of fish stocks also changes. According to survey, there are 90% carp of
the fish catch before 1955, but 50-60% in 1960. After 1960, the percentage of carp in the fish
catches decreases year by year. On the contrary, the percentage of crucian carp increases year
by year, from 50-60% in 1983 to 78% in 1999. Meanwhile, some other fish stocks gradually
disappear or only account for a very small percentage. This change has to do with over-
fishing and water environment changes.
(3) Evaluation results of fish
Comparing with former surveys, the species and numbers decease significantly
according to this fish survey. Some of the fish has even disappeared. As of now, there are just
a few species of fish in the lake. Most fish is crucian carp, accounting for more than 80% of
total. Numbers of all other fish are small and actually not many fish species. Numbers of the
crucian carp are much larger than others.
5 ) Birds
According to information collected and field study, there are 181 species and 4
subspecies of birds, belonging to 16 orders, 45 families and 103 genera. In the year 2000,
there are 197 species and 4 subspecies of birds, belonging to 17 orders, 47 families and 110
genera in record, while in 2005, the record changes to 221 species and 4 subspecies of birds,
belonging to 17 orders, 47 families and 116 genera. Based on previous data and field study, a
preliminary analysis is conducted for wetland bird fauna evolution in Lake Wuliangsuhai.
Due to the impact of weather and human being, the wetland environment is deteriorating year
by year. Species of birds, which likes to live on marsh, increase these years, but species of
birds, which prefer living on vast waters, decrease on the contrary. Large numbers of panurus
biarmicus used to be resident birds on Lake Wuliangsuhai. But now they are rarely found in
field studies.
1 ) Composition of bird fauna
There are totally 1 order, 2 families, 13 genera and 40 species increased from
1995 to 2005. The number of charadriiformes increases 14 species at most and the
next is passeriformes increasing 11 species and third is falconiformes increasing 7
species. See Table 4.2-35 for bird composition
Table 4.2 -35 Birds composition in Lake Wuliangsuhai
目 (Order)
1995 年 (year) 2000 年 (year) 2005 年 (year)
科(famil
y)
种(speci
es)
%
科(fami
ly)
种(species
)
%
科(family
)
种(specie
s)
%
潜 鸟 目( Gaviiformes
)1 1 0.51 1 1 0.45
目 1 3 1.66 1 3 1.52 1 3 1.36
鹈 形( Pelecaniformes
)2 2 1.1 2 2 1.02 2 2 0.9
鹳 形( Ciconiiformes
)3 10 5.52 3 10 5.08 3 10 4.52
雁 形( Anseriformes
)1 23 12.71 1 23 11.68 1 26 11.76
隼 形( Falconiformes
)2 19 10.50 2 20 10.15 2 26 11.76
鸡 形( Galliformes
)1 4 2.21 1 4 2.03 1 4 1.81
鹤 形( Gruiformes) 3 5 2.76 3 5 2.54 3 7 3.17
鸻 形( Charadriiforme
s )5 33 18.23 6 43 21.83 6 47 21.27
沙 鸡 ( Pterocles
orientalis ) 1 1 0.55 1 1 0.51 1 1 0.45
鸽 形( Columbiformes
)1 2 1.1 1 2 1.02 1 2 0.9
鹃 形( Cuculiformes
)1 2 1.1 1 2 1.02 1 2 0.9
鸮 形( Strigiformes
)1 4 2.21 1 4 2.03 1 4 1.81
雨燕( Swift ) 1 1 0.55 1 1 0.51 1 2 0.9
佛 法 僧( Uratelornis
chimaera )1 1 0.55 1 1 0.51 1 1 0.45
戴胜 (Hoopoe) 1 1 0.55 1 1 0.51 1 1 0.45
䴕形 (Piciformes) 1 1 0.55 1 1 0.51 1 1 0.45
雀 形(Passeriformes)
18 69 38.12 18 73 37.06 18 80 36.2
2 ) Ecological distribution of birds
Float grass in open water ①
Lake Wuliangsuhai is an oxbow Lake and depth of open water is no more than 1m.
There is sufficient sunlight under water with a high degree of eutrophication. Therefore, the
submerged plants and floating plants flourish in the water. All these plants have provided a
very good place for the aquatic animals to live and feed. So there are many benthonic
animals, phytoplankton, insects and their larvae living in the water. They are good food for
many kinds of birds. Many phytophagous birds feed and hover around float grass in open
water, such as gulls and herons.
Float grass in open water are also the breeding place for birds, which like to build nest
on water, such as chlidoniashybridus and coot.
② Reed and cattail areas
There are more reed than cattail in reed and cattail areas. Large areas of reed and cattail
distribute in the lake in different shapes. The lake is in eutrophication state and suitable for
reed. The height of the plants over water surface is up to 5.5-6.0m. Reed areas are not only
good places for birds to build nest, brood and hide when moulting, but also feeding places for
many birds, such as panurus biarmicus.
③ Shoal areas in the lake
Most of the shoal areas are surrounded by reed and cattail. Many grasses grow on the shoal.
Birds such as vanellus, wagtail and some ducks nest on the shoal. Some passerine birds also
feed here, such as redstart. In addition, shoal areas are also places for anseres, umbrette and
laridae to rest and spend the night.
Shallow and marsh area on the coast④
Shallow and marsh areas are mostly around the lake and water depth is no more than 40cm.
There are sparse reed or cattail and some other water plants. Many of the aquatic animals live
in this area. There are large numbers of various worms and insects and their larvae. This is
also a living and feeding place for umbrette. Anseres and coot also come here to feed.
Surrounding areas around the lake and wetland⑤
Surrounding areas can be divided into following areas: salt marsh areas, nitraria
tangutorum desert areas, agricultural areas, residential areas and plantation areas.
Salt marsh area: exposed lake bed after water level decreases. When there is sufficient
rainfall, it become shallow and marsh land again. There are saline-alkali tolerant plants living
in this area, such as kalidium foliatum and suaeda gtauca. Some birds feed in this area, such
as wagtail, water pipit, grey-headed Lapwing and etc. Birds such as vanellus, charadrius
alexandrinus and etc often nest and brood here.
Nitraria tangutorum desert areas: sandy soil on the surface. There are clusters of
drought-resistant plants nitraria tangutorum. Sand soils pile up at the root of nitraria
tangutorum year by year. Nitraria tangutorum is an ancient mediterranean plant, resistant to
salinity and drought with many hard stabs on the surface. This environment is the feeding and
living place for birds like lark, laridae and etc. The hard stab is the nesting and feeding place
for small birds like malaconotus alius. It is also a haven for birds like partridges to hide from
the prey birds.
Farmland areas: wheat, corn, sunflower and others are the main corps in the farmlands
around the lake. There are birds like sparrow, jackdaw and etc living in this area in spring,
autumn and winter. In spring, summer and autumn, the common birds in the farmland are
black-headed gull, mallard, grey goose, quail and so on. Owls and other birds of prey rest and
hunt in the open farmland.
Residential areas: There are many scattered villages around the Lake Wuliangsuhai
with at least several families or dozens of families at most. The common species in residential
areas are crested lark, hoopoe, tree sparrow, little owl, eurasian collared dove and etc.
Plantation areas: There are often some small pieces of the plantation around the village
in the plantation. The trees in the plantation are mainly poplar, willow and sand jujube trees.
Weeds grow on the ground of the plantation. The birds here are mainly forest dwellers, such
as sparrow hawks, falcon, quail, fieldfare, and brambling and so on.
(3) Analysis of ecological distribution of birds
① Numbers of anseres reduce, while the numbers of sandpiper, falcon and songbirds
increase rapidly. The wetland environment in Lake Wuliangsuhai is of high heterogeneity.
Spatial and temporal structures of bird community are of unique features due to the
appropriate allocation of many kinds of different landscapes, such as wetlands, shrub steppe
and uplands. the original structure is broken down by the marsh acceleration.
Falconiformes birds and waders, such as charadriformes and gruiformes which like to live on
wetland, increase rapidly. The species of anseres breeding here is increasing but the number
percentage is decreasing on the contrary.
Increase of falconiforme indicates that the wetland, marsh, sparse woodland and
cultivated land are increasing in this area, but the large and open lake areas are decreasing.
The wetland in Lake Wuliangsuhai is the marsh evolution process.
Charadriiformes and gruiformes are waders. They brood and feed in wetland, reed
beds, grassland and river shoal. From Table 5.6.5-1, it is concluded that there are 10 species
of charadriiformes increased from 1996 to 2000 and 4 species of charadriiformes increased
from 2001 to 2005. There are 2 species of gruiformes increased. Over the past 10 years, the
species of waders increase rapidly. Not only avoset and tringa totanus live in wetland of Lake
Wuliangsuhai, but even Greater Painted-snipe from Japan. This proves that the environmental
conditions in the wetland are suitable for waders. Therefore, it can be referred that areas of
wetland and marshes are becoming larger and larger and marshland evolution has been
intensified in past decade, which is in accordance with the actual situation.
According to field study, reed areas are occupying 40% of the areas of Lake
Wuliangsuhai and the total reed output in 2000 is 30000-40000 tons more than that in 1996.
The wetland dominant species in Spring, summer and autumn are passeriformes.
Changes in the species and number have a greater influence on the bird fauna in this area.
There are 3 species of anseriformes increased from 2001-2005, but anseriformes species
percentage decline due to the increase of wader species. migratory birds like Sarcelle,
Common Pochard, shoveller duck and gadwall now also brood here. The increase of
anseriformes species indicates the wetland in Lake Wuliangsuhai can provide a good place
for migratory anseriformes to nest and feed. But the declining percentage of numbers
indicates that its dominant position is becoming weaker and weaker. The water environment,
which is suitable for its living, is decreasing. During the study in Lake Wuliangsuhai in April
September, 2004, it is seen that there are prosperous reed in the lake. The lake is full of water
plants. Many spirals in the sunshine are attaching to the water plants and breathing the
oxygen. There are a lot of aquatic insects on the water surface. Tens of thousands of insects
are flying above the water. Ducks and snipe are feeding on the water where water plants are
prosperous. Reed bed is perfect place for the anseriformes to nest and brood, while the open
water environment is good food sources. However, the prosperous water plants are is just the
reason why open water areas are decreasing. These water plants cause the marsh evolution
and the extinction of the lake. If the situation continues to decline, the marsh evolution in
Lake Wuliangsuhai will be more serious. At that time, there will be no prosperity of
anseriformes any more. These anseriformes could not live in this area due to the large habitat,
but smaller and smaller feeding areas.
② Significant number change in the birds fauna composition
Comparing with the document record in 1980s, the field study finds below changes:
The number of mute swans has increased; Number of gray geese and mallards① ②
continues to decrease; Number of water birds breeding in the salt marshes, such as Little③
tern and snipe increase significantly; It is hard to find reedling parrotbill living around.④
Changes in bird number are mainly due to the great changes in the living environment.
There are about 200 couples of mute swans breeding in Lake Wuliangsuhai. The number is
much more than before. The reason is that fishermen are aware the necessity to protect the
birds. There are fewer fishermen to pick the eggs and hunt for birds; therefore, the hatching
and survival rate of mute swans is relatively higher.
The document (Lake Wuliangsuhai birds record in Inner Mongolia) say that Yinsun
Zhang saw 12000 Grey Geese resting in foot of Ural mountains between Hayehutong and
Baiyanhua. however, throughout the field study, only 2 Grey Geese and 8 mallards were seen,
which is much less than former record. One of the reasons is that the large number of local
residents have poisoned geese and ducks and caused the sharply decrease in number. In
addition, with the marsh evolution of lakes and increase of salina, numbers of grass or mud
nesting birds increase a lot, such as little tern, common redshank, charadrius alexandrinus and
Black-headed Gull.
In last decade, bird species are increasing in Lake Wuliangsuhai. But the newly
increased birds are mostly charadiiformesand falconiformes living on shallow and marsh
lands and desert grasslands. The change trend of birds fauna indicates that wetland in Lake
Wuliangsuhai is shrinking at a startling rate. The marsh evolution increases and areas of open
water is becoming smaller and smaller. Shallow marsh areas are increasing. Due to these
reasons, the numbers of snipe increase greatly and numbers of anseres also increase. But this
excessive reproduction of some plants shall be a temporary phenomenon caused by
eutrophication. If marsh and desert evolution situation deteriorate even further, these ducks
will have no place to live. There is less living space for swimming birds in the decreasing
open water areas. Therefore, the numbers of anseres will inevitably decrease.
Panurus biarmicus is a passerine bird, tiny and pretty lovely, mainly feeding on reed
seeds. There used to be a great number of panurus biarmicus in Lake Wuliangsuhai and most
are resident birds. However, no one is seen during field study in 2004-2005. This may be
because tall plants over the ice as reed and cattail are all cut harvest and no panurus biarmicus
live here in the winter.
(4) Evaluation resultNatural environment breeds life of biological species. On the contrary, biological
species reflect characteristics of natural environment. Birds are very sensitive to environmental changes; therefore, they can be used as indicators to environment evolution.There are many changes of bird composition in Lake Wuliangsuhai during past decade. Due to the rapid spread of water plants, sharp decrease of open water areas, increase of marsh areas and speed up of the marsh evolution, changes of bird species, numbers and community structure in past decade and near future are warning us that: there are serious wetland environmental crisis in Lake Wuliangsuhai. It is hard for the ecosystems to maintain the order by its own self-control ability. Biological diversity will be gradually destroyed. Therefore, scientific management is needed to protect the wetland and exploitation shall be reasonable, so that the lake can function properly and sustainably.
4.3 Balance analysis on the project water resource
4.3.1 Balance analysis on the regional water resources
1 )Current status of water resources
In recent years, the average water resource capacity of the city in several years is 5,574,200,000
m3,where the surface water resource capacity is 4,779,100,000 m3 ( which is mainly composed by
4,674,800,000m3 water from Yellow River ,the secondary water resource is from surface runoff capacity
with 104 ,300,000 m3 that mainly in mountain dry region ) ,the underground water capacity is
2,419,600,000 m3, in the underground water resources, the annual production volume is 850, 000,
000m3.For water resource conditions in Bayannaoer please see table 4.3-1.
Table 4.3-1 Water resource conditions in Bayannaoer(million m3 ).
Year
Surface water
resource capacity
Underground water
resource capacity
Total water
resource capacity available
Water resource capacity
from Yellow River
Total water
resource capacity
used
Total water consumptio
n
Surplus and
deficiency
2002 50.947 26.235 60.278 49.688 50.562 35.196 9.7162003 42.126 24.546 51.987 41.011 45.409 31.849 6.5782004 46.270 24.344 54.763 45.312 48.130 33.547 6.6332005 50.184 22.474 55.396 49.662 51.274 35.722 4.1222006 49.518 23.917 56.525 48.790 49.985 34.639 6.542007 49.245 23.285 55.967 48.114 49.192 34.188 6.7752008 46.244 24.568 55.277 44.661 48.888 33.934 6.389
Average 47.791 24.196 55.742 46.748 49.054 34.154 6.688
2 )Utilization and drainage
The water resources in the Bayannaoer are mainly used for industrial and agricultural production,
resident living in the urban and rural area and ecological water. Take the normal year 2008 as an example,
the total usage water capacity in the whole year is 4,888,800,000 m 3,where the total water consumption in
the agriculture is 4,714,400,000m3,which account for 96.4% of the total water consumption; the total water
consumption in industry is 95 800 000 m3,which account for 2.0%the total water consumption; the water
consumption for living is 78 600 000m3,which account for 1.6% of the total water consumption. The total
water consumption volume of the whole city in 2008 is 3,381,200,000 m3,the comprehensive water
consumption rate is 69.2% ;The water consumption in agriculture, industry and living are respectively:
3,276,900,000 m3, 48, 200, 000 m3 and 56, 100, 000 m3.
The total discharge volume of waste water of the whole city in 2008 is 70,090,700 t, the discharge volume
of waste water is 22,564,000 t. The discharging volume of main pollutants COD is 58525.39t, which has
reduced 3366.43t compared with 2007,where the discharging volume of COD in industry is 48506.85t,the
discharging volume of COD in living is 10018.54t;the discharging volume of ammonia nitrogen is
1902.49t,which has reduced 669.51t compared with 2007, where the discharging volume of ammonia
nitrogen in industry is 564.87t,the discharging volume of ammonia nitrogen in living is 1337.62t.
3 )Water quality of water resource
Carry out assessment on the water quality of rivers of the whole city in 2008 according to the
GB3838-2002 Surface Water Quality Standards, the water quality of water run into the Ulansuhai from the
general drainage ditch can reach Class V, the main items that exceed the standard are permanganate index,
COD, ammonia nitrogen, fluoride and mercury, the average annual mineralization degree is 1.700g/l,which
has increased 0.08g/l compared with 2007;the water quality in Ulansuhai is Class V and belong to organic
contamination, the main items that exceed the standard are COD, permanganate index,BOD5,TP, total
nitrogen, ammonia nitrogen etc.. Carry out evaluation according to the class V water quality of surface
water, the exceeding standard rate of BOD5 in the whole year is 66.7%,the exceeding standard rate of COD
is 50%,the exceeding standard rate of total nitrogen is 33.3%,the exceeding standard rate of total
phosphorus is 16.7%. On the aspect of nutrition, the water body of Ulansuhai is heavy eutrophication,
where the total nitrogen has reached heavy eutrophication level; the total phosphorus has reached heavy
eutrophication level.
The average annual mineralization degree of underground water in the Hetao area in 2008 is 3.920 g/l,
which has reduced 0.200 g/l compared with 2007.The freshwater area that the mineralization degree of
underground water of irrigation area in the drought period of 2008 is less than 3g/l is 5956.6 km 2,which
account for 56.7% of the total irrigation area ; the freshwater area of underground water during the wet
season is 5848.8 km2,which account for 55.7% of the total irrigation area, the freshwater area during the
drought period is a little larger than those in 2007, the freshwater area during the wet season has a little
reduction compared with those in 2007.
4 )The existing problems of water resources
In recent years, along with the rapid economic development and the rapid increasing of urban
population, the resident living water in the urban and rural area over the whole city in 2008 has reached
78, 600, 000m3.Until now, the water quality existing problems in 3 counties of the total 7
counties ,including Urad Front Banner , Wuyuan county and Urad Back Banner ,the water for living in the
urban and rural area has been significantly affected. Where the water level in the Allah Ben region that is
the water source area of Urad Front Banner, a relatively large groundwater extraction funnel has been
formed, the water for industrial production and living of residents in the urban and rural area has existed
crisis ;good water that meet the drinking water standard for human and animal is lacking in the Wuyuan
county, most of the water are brackish water ,the water for living of residents in the urban and rural area
has already existed difficulties ;for the Dishaiwusu town where the government of Urad Back Banner is
located, the main reason of removing the government of town is due to the extremely lacking of
groundwater. So that the shortage of water resources has became the main factor of restricting the city's
economic and social development currently.
According to the Yellow River water allocation plan approved by GBF (1987)No.61 issued by
state council, the water capacity allocated to the autonomous region in the normal water supply year of
Yellow River is 5,860,000,000m3.In October,1999,the president conference office in the autonomous
region has initially determined that the water capacity from Yellow River is 4,000,000,000 m3 after the
implementation year of water-saving project in the Hetao irrigation area of Bayannaoer according to the
water-saving project plan in the Hetao irrigation area. Due to the historical reasons and the actual situation
of agriculture water usage in the Hetao irrigation area, the average amount of water from Yellow River in
several years is 4,674,800,000m3, based on the water allocation program approved by the country and
autonomous region ,now the Hetao irrigation area has introduced 674 800 000 m3 water from Yellow River
in each year of which has exceeded the plan.
5 )Balance analysis on the water capacity supply and demand
Due to the water demand prediction calculation zone in the first industry agriculture is five irrigation
zones, but the water demand calculation zones for secondary industry, tertiary industry, living and
ecological environment are administrative divisions in all counties. After conversion, carry out summary
on the prediction results of water demand in the first industry, secondary industry, tertiary industry, living
and ecological environment respectively according to the irrigation area and administrative division, for
results please see table 4.3-2 (water resource evaluation on the water source comprehensive management
project in Bayannaoer ,Beijing University of Technology ,2010 )
Table 4.3-2 Water demand and water supply prediction in all administrative divisions
年份 临河区 五原县 磴口县 乌前旗 乌中旗 乌后旗 杭后旗 合计 引黄 地下水 再生水2007 118367 105094 19501 44722 23280 1040 86983 398988 3989882010 113245 100546 18657 42787 22273 995 83219 381721 3817212015 112147 99571 18476 42372 22057 985 82412 378021 3780212020 111049 98597 18295 41958 21841 976 81606 374321 3743212030 102771 91247 16931 38830 20213 903 75523 346418 3464182007 783 306 697 113 94 872 324 3190 31902010 4495 1084 2237 1052 1037 2871 1378 14153 141532015 6837 1514 2721 1687 1730 3499 1965 19952 11323 86292020 13009 2453 4816 3546 3197 6143 3823 36987 9058 279292030 18611 3150 6388 5003 4447 8057 5849 51504 5000 465042007 1521 614 344 393 328 155 657 4013 40132010 1955 856 404 505 425 179 841 5165 51652015 2198 977 458 576 485 199 967 5861 58612020 2454 1106 515 652 549 220 1100 6596 65962030 2979 1369 631 807 679 268 1373 8107 81072007 73 33 12 8 8 15 33 181 1812010 289 109 43 33 26 34 122 656 6562015 473 163 60 50 37 51 205 1040 10402020 545 179 57 46 34 53 247 1160 11602030 740 209 69 50 37 52 304 1461 14612007 326 91 74 68 56 37 102 753 7532010 433 152 81 90 75 40 134 1004 10042015 514 187 97 110 92 46 167 1212 12122020 587 219 112 129 108 51 198 1404 14042030 761 293 148 173 145 67 271 1858 18582007 121070 106138 20628 45305 23766 2119 88099 407125 398988 7384 7532010 120416 102747 21422 44466 23836 4119 85695 402700 381721 19975 10042015 122169 102412 21812 44795 24401 4781 85716 406085 378021 18223 98412020 127644 102553 23796 46330 25729 7443 86974 420468 374321 16814 293332030 125862 96269 24168 44863 25521 9346 83320 409348 346418 14568 48362
合计
项目区供水预测部门
项目区需水预测汇总
灌溉
工业
生活
服务
城镇生态
4.3.2 Water capacity balance in Ulansuhai1) Annual changes of water capacity in or out of Ulansuhai
The table 4.3-3 is the incoming and outgoing water capacity statistics for Ulansuhai in 1988-2008,it
can be seen from the table that the drainage water capacity from the general drainage ditch ,Bapaigan ,
Jiupaigan and four truck channels to the Ulansuhai are respectively 0.307 billion-0.627 billion m 3 ,0.025-
0.062billion m3,0.005-0.036 billion m3 and 0.023-0.103 billion m3 ,the average value respectively are 0.461
billion m3,0.042 billion m3,0.022 billion m3 and 0.044 billion m3,where the general drainage ditch is the
truck ditch for drainage, the drainage capacity accounts for 81% of the total water drainage capacity.
Average water capacity run from Ulansuhai into Yellow River is 154 000 000 m3 in every year, the net
water capacity run from the drainage ditch and truck channel to the Ulansuhai is 415 million m3.
The drainage water in the general drainage ditch, Bapaigan and Jiupaigan are polluted by the urban
sewage and industrial and agricultural wastewater, these water should be discharged into Ulansuhai before
carrying out purification through constructed wetland in the biological transition zone. Due to the
replenishing water of the four truck channels are relatively clean water from Yellow River, they can be
directly flow into the Ulansuhai area without treatment in the biological transition zone.
Table 4.3-3 The incoming and outgoing water capacity of Ulansuhai during 1988-2008(billion m3)
Year
General drainage ditch to Ulansuh
ai
Bapaigan to Ulansuh
ai
Jiupaigan to
Ulansuhai
Replenishing water from 4 truck
channels
Water capacit
y run
into Yellow River
Total capacity
run into
Ulansuhai
Net capacity run into
Ulansuhai
1988 5.44 0.25 0.1 0.52 3.30 6.31 3.011989 5.51 0.30 0.15 0.51 2.88 6.47 3.591990 5.20 0.40 0.16 0.6 2.51 6.36 3.851991 3.75 0.43 0.16 0.32 1.43 4.66 3.231992 4.16 0.54 0.12 0.34 1.72 5.16 3.441993 4.40 0.40 0.05 0.42 1.10 5.27 4.161994 6.10 0.43 0.16 0.41 2.68 7.10 4.431995 6.80 0.58 0.36 0.44 3.42 8.18 4.761996 6.27 0.42 0.33 0.29 3.28 7.31 4.031997 5.39 0.40 0.29 0.35 2.07 6.43 4.351998 5.08 0.41 0.3 0.32 1.31 6.11 4.801999 4.19 0.50 0.28 0.33 0.76 5.30 4.542000 4.09 0.49 0.28 0.33 0.45 5.19 4.742001 3.79 0.47 0.31 0.39 0.37 4.96 4.602002 4.19 0.37 0.22 1.03 0.43 5.81 5.382003 3.08 0.27 0.19 0.43 0.08 3.97 3.892004 3.97 0.38 0.24 0.38 0.74 4.97 4.242005 2.86 0.33 0.18 0.32 0.11 3.69 3.582006 3.49 0.32 0.16 0.49 0.41 4.46 4.052007 4.00 0.59 0.29 0.74 1.31 5.62 4.312008 5.09 0.62 0.29 0.23 2.03 6.23 4.19
Average
4.61 0.42 0.22 0.44 1.54 5.69 4.15
2 )Water capacity balance in Ulansuhai
Under the premise of ignore the storage capacity changes caused by other reasons in Ulansuhai area,
the changes of water capacity in Ulansuhai can be expressed by following formula:
Where: —— water capacity of general drainage ditch; —— water capacity of Bapaigan;
——water capacity of Jiupaigan; —— replenishing water capacity of truck channel; ——water
capacity run into Yellow River; ——infiltration capacity on the bottom of lake; —— Evaporation
water capacity; ——precipitation on the water surface; —— runoff capacity on the ground surface;
—— replenishing of groundwater
Without calculating the changes of storage capacity, the current water level operates on the place of
1018.5 m, i.e. [Dv/dt]=0.
(1 )Incoming water capacity
According to the incoming and outgoing water capacity statistics for Ulansuhai during 1988-2008,the
average annual drainage water capacity from the general drainage ditch ,Bapaigan , Jiupaigan and four
truck channels to the Ulansuhai are respectively 0.461 billion m3 ,0.042 billion m3,0.022 billion m3 and
0.044 billion m3 ,the total annual drainage capacity to the Ulansuhai is 0.569 billion m3.
(2 )Water capacity run into Yellow River
According to the incoming and outgoing water capacity statistics for Ulansuhai during 1988-2008,the
average annual water drainage capacity from the Ulansuhai to the Yellow River is 154 000 000m3 .
(3 )Evaporation capacity
The annual evaporation capacity of Ulansuhai is 1234 mm, the estimated annual total evaporation capacity
is about 361 million m3 (data from Inner Mongolia Water Resources Design Institute ).
(4 )Precipitation
The precipitation adopts the average value in several years from Xi Shanzui weather station during
1968~1997,the annual precipitation is 244 mm, the total precipitation capacity is about 66 000 000 m3.
(5 )Seepage amount
The annual seepage amount is about 66 000 000 m3.
(6 )Surface runoff
The annual surface runoff is about 52 000 000 m3
(7 )Groundwater replenishing
According to the measured data in the 1980s of last century, the replenishing groundwater capacity is
about 18 000 000m3.
In addition to the incoming and outgoing water, the multi-year changes of other hydrologic processes
such as water, surface runoff, groundwater replenishing, seepage , evaporation and other processes are not
very large. The water capacity balance of Ulansuhai can be seen from figure 1.1-1.
Figure 4.3-1 Water capacity balance in Ulansuhai
According to the analysis on the water capacity balance in Ulansuhai, it can maintain the current
ecological water and water surface area of Ulansuhai when the net water capacity entering the Ulansuhai is
larger than 515 million m³ .If the net water capacity is reduced, under the premise of maintain evaporation
and precipitation, it may cause the reduction of water level and reduction of water surface area in
Ulansuhai.
According to the conclusion of Comprehensive Planning Report On Water Resources In Bayannaoer
Of Inner Mongolia Autonomous Region(Wu Han University,2006):when the net water capacity from the
UlansuhaiCapacity run into Ulansuhai is
0.569billion m³
Precipitation0.066billion
m³
Evaporation capacity
0.361billion m³
Capacity run into Yellow River
0.154billion m³
Seepage amount0.066 billion m³
Groundwater replenishing
0.018billion m³
Surface runoff
0.052billionm³
irrigation area to the Ulansuhai is 0.36 ~ 0.39billion m³ ,it can basically maintain the current water
surface level of Ulansuhai at 1018.5m.the conclusion of Lake Recovery And Management Project In Inner
Mongolia-Comprehensive Treatment Study In Ulansuhai (Environmental Science Research Institute of
Inner Mongolia Autonomous Region, Swedish Environmental Research Institute, Norwegian Institute for
Water Environment):the water capacity coming into the Ulansuhai can not be less than 400 000 000
m³.Only can maintain the water level of lake at 1018.5m.According to the figure 1.1-1 Water Resource
Balance Condition And Analysis In Ulansuhai, it maintains 515 million m³ ecological water demand in
Ulansuhai after the comprehensive analysis (pay more attention on the safety),the water level of lake
should be maintained at 1018.5m.
4.4 The pollution source in the project area and its treatment overview
4.4.1The water supply and consumption in the project area and the sewage
pollution sourceThe total water source capacity of Bayannaoer in 2007 is 5,596,700,000m3,the total utilization
capacity of water source in administrative divisions is 4919200000 m3,where, the water from Yellow River
is 4236800000m3,other surface water capacity is 57 500 000m3,the groundwater used is 624 900 000 m3;In
the total water utilization capacity, the water capacity in agriculture is 4744700000m3,which accounts for
96.5% of the total utilization water capacity, the water capacity in industry is 96 500 000m3,which accounts
for 2.0% of the total utilization water capacity, the utilization water capacity for living is 78 000
000m3,which accounts for 1.5% of the total utilization water capacity .The total water consumption volume
is 3418800000 m3,the comprehensive water consumption rate is 69.5% ; the water consumption in
agriculture, industry and living are respectively :3,295,900,000 m3, 60 ,900 ,000 m3 and 62 ,000, 000 m3.
The sewage drainage volume of Bayannaoer in 2007 is 51,497,000 t, which has reduced 1,399,900 t
compared with those in 2006.Where the sewage drainage capacity in industry is 35,575,300 t, which has
reduced 1,691,500 t compared with those in 2006,Qualified drainage capacity is 24,866,600t,the standard
rate is 69.90 %;the drainage capacity from living and other sewage is 15,921,700 t, which accounts for
30.92% of the total sewage drainage capacity .
There are 128 enterprises in the Bayannaoer, there are 75 sets of wastewater treatment facilities, the
wastewater discharged into Sewage Treatment Plant is 3,531,800t,which only accounts for 9.93% of the
total wastewater drainage capacity. The main pollutants in the wastewater are COD, ammonia nitrogen and
suspended solids.
4.4.2 Industrial solid wasteThe production capacity of industrial solid waste in Bayannaoer is 5,525,100t,which has increased
1,110,400 t, where the comprehensive utilization capacity is 1,778,300 t, which has increased 812, 700
t,the comprehensive utilization capacity is 32.19% ;The storage capacity is 23,100 t, the disposal
capacity is 3,812,600 t.
Comprehensive Utilization Rate
Storage Rate Disposal Rate
5 Comprehensive Environment Impact Assessment
5.1 Analysis on Environment Impact during Construction
The project to be constructed includes civil works, pipe laying, and installation,
debugging and trial run of M&I equipment, etc. During construction, various construction
activities, transport and equipment debugging will inevitably generate waste gases,
wastewater, noises, solid wastes, etc. and the surrounding environment will be surely
impacted, especially the impact of construction noises and dust are the most. The chapter will
analyze the pollutions and their environmental impacts.
5.1.1 Ambient Air Impact AnalysisMain ambient air pollution sources during construction of the project include odor,
dust and vehicle exhausts.
5.1.1.1 Odor Impact Analysis
Odors emitted during grid excavation and sediment transport of Wuliangsu Lake will
impact the surrounding environment.
(1) Odor Intensity Level
Odor intensity is classified based on odor threshold value. Odor intensity is classified
into six levels (see Table 5-1-1) in China. The limitation criteria are generally equivalent to
class 2.5-3.5 of odor intensity. If beyond the intensity range, odor pollution will be identified
and corresponding measures shall be taken.
Table 5.1-1 6-class Classification of Odor Intensity
Classification of Intensity Sensory Intensity of Odor
0 No Odor
1 Vary Faint Oder (Detect threshold concentration)
2Weak odor which can determine the property of gas (Confirm threshold
concentration)
3 Significant odor to smell easily
4 Strong Odor
5 Strong Odor
(2) Odor Impact Analysis
The project adopts analogy method to analyze the class of odor pollution intensity.
① Refer to Mudanjiang Nanpaozi Dredging Project (dry excavation in summer) and
the investigation analysis of pollution source odor class is referred to Table 5-1-2.
Table 5.1-2 Odor Intensity of Mudanjiang Nanpaozi Sediment Dredging (Dry Excavation of Dry Pond)
Distance Sensory Intensity of Odor Class
Shore Apparent Odor Class 3
30m away from shore Slight Class 2
80m away from shore Slight Class 1
Above 100m away from shore N/A Class 0
② Nanning Nanhu Lake Treatment Project adopts wet dredging, only slight odor can
be smelled around the lake and no odor beyond 50m.
③ Conclusion
Through analogy analysis, there will be apparent odor in the lake area during dredging;
the odor intensity reaches class 2 with slight odor beyond 30m, lower than limitation criteria
(class 2.5-3.5) of odor intensity; and there is basically no odor beyond 50m.
There are many residential areas around Wuliangmei Lake, however, all the sensitive
point distribution is relatively scattered and beyond 100m, so the grid excavation and
dredging process in Wuliangmei Lake area will not impact surrounding residents.
In order to avoid odor impact caused by grid excavation and dredging in Wuliangmei
Lake area, the removed sediments and trashes shall be transported to local refuse landfills for
landfill treatment timely. If sediments be cannot removed and transported timely, load them
to straw bags for storage, thus reducing dust and odorous gas emission, avoid impact on the
living quality of nearby residents. Furthermore, transport sediments in closed tank wagons to
prevent scattering along the way and impacting urban landscaping.
5.1.1.2 Dust Impact Analysis
Construction dust mainly includes dust generated by construction vehicle driving, dust
in laydown area and stirring dust, etc.
(1) Dust Generated by Vehicle Driving
According to the introduction of related references, dust generated by vehicle driving
covers above 60% of total dust during construction. Dust generated by vehicle driving can be
calculated according to the empirical formula below under absolutely dry condition:
Where,
Q ——Dust generated by vehicle driving, kg/km·Vehicle;
V ——Vehicle driving speed, km/h;
W ——Vehicle load weight, t;
P ——Road surface dust, kg/m2.
Road dust generated by vehicles are related to many factors like vehicle speed, vehicle
model, vehicle flow, wind velocity, road surface dust volume and others. Table 5.1-3 gives
dust volume generated when a 10t truck passes across a 1km road surface according to
different road cleanness and driving speed. We can see from Table 5.1-3 that under the same
condition of road cleanness, the faster the driving speed, the more the dust volume; under the
same driving speed, the more the road dust volume, the more the dust. Therefore, limiting
construction vehicle speed and maintaining road surface cleanness is an effective means to
reduce dust.
Table 5.1-3 Dust Volume Generated by 10t Truck at different speeds
Dust Volume
Vehicle
Speed
0.1kg/m2 0.2kg/m2 0.3kg/m2 0.4kg/m2 0.5kg/m2 1.0kg/m2
5km/h 0.0511 0.0859 0.1164 0.1444 0.1707 0.2871
10km/h 0.1021 0.1717 0.2328 0.2888 0.3414 0.5742
15km/h 0.1532 0.2576 0.3491 0.4332 0.5121 0.8613
25km/h 0.2553 0.4293 0.5819 0.7220 0.8536 1.4355
According to preliminary estimate, road dust on construction site within 80-120m
range of downwind exceeds Ambient Air Quality Standard (GB3095-1996) Level II
Standard, and road dust of transportation spoil within 30-60m range of downwind exceeds
GB3095-1996 Level II Standard.
(2) Laydown Area Dust
Another source of dust during construction stage is wind dust in open laydown area
and open site. Due to the construction needs, some building materials and excavated
earthwork shall be temporarily piled up. Under the condition of dry and windy climate, dust
will be generated and dust volume can be calculated according to the empirical formula of
dust in laydown area:
Where,
Q ——Dust volume, kg/t·a;
V50 ——Wind velocity at height where is 50m away from ground, m/s;
V0 ——Dusting wind velocity, m/s;
W——Moisture content of dust particle, %.
Dusting wind velocity is related to particle size and moisture content, so reducing open
laydown area, ensuring certain moisture content, and reducing open ground are effective
means to reduce dust caused by wind. The diffusion and dilution of dust in air is related to
wind velocity and other climate conditions and related to the sediment velocity of dust as
well. The sediment velocity of different particle sizes is referred to Table 5.1-4. We can see
from the Table, the sediment velocity of dust increases rapidly along with the increase of
particle size. When particle size is larger than 250μm, the main impact range is within the
close distance range of downwind of dust generation point, while some tiny particle size of
dust has big impact on ambient environment.
Table 5.1-4 Sedimentation Velocity of Different Particle Sizes
Dust Particle Size (μm) 10 20 30 40 50 60 70
Sedimentation Velocity
(m/s)
0.0
03
0.012
0.0
27
0.0
48
0.075
0.10
8
0.147
Dust Particle Size (μm) 80 90
10
0
150 200 250 350
Sedimentation Velocity
(m/s)
0.1
58
0.170
0.1
82
0.2
39
0.804
1.00
5
1.829
Preliminarily estimated according to related data, the dust in dump laydown area
exceeds GB3095-1996 level II standard within range of 100-150m downwind.
(3) Stirring Dust
Through analogy analysis on dust monitoring data on the construction lime stirring
site, near the lime stirring station, the concentration at 50m downwind at TSP hour is 8.10
mg/m3, the concentration at 100m downwind at TSP hour is 1.65 mg/m3, and there is
basically no impact at places 150m far away.
(4) Construction Dust Impact
According to above analysis and preliminary estimate, road dust on construction site
within 80-120m range of downwind exceeds Ambient Air Quality Standard (GB3095-
1996) Level II Standard, road dust of transportation spoil within 30-60m range of downwind
exceeds GB3095-1996 Level II Standard; dust on spool laydown area within 100-150m range
of downwind exceeds GB3095-1996 Level II Standard; Through analogy analysis on dust
monitoring data on the construction lime stirring site, near the lime stirring station, the
concentration at 50m downwind at TSP hour is 8.10 mg/m3, the concentration at 100m
downwind at TSP hour is 1.65 mg/m3, and daily average value concentration of GB3095-
1996 level II standard are basically met at places 150m far away.
According to related test results, if spray water frequently (4-5 times/day) onto car
driving road surface during construction, the dust volume can be reduced by 70% or so and
get good dust sediment effects. Table 5.1-5 gives the actual test results of sprinkler dust on
construction site.
Table 5.1-5 Sprinkler Dust Test Result
Distance from Construction Source/m 5 20 50100
TSP Concentration Value
(Hour Average )/mg·m-3
No Sprinkler10.14
2.89
1.15
0.86
Spraying Water2.01
1.40
0.67
0.60
GB3095-1996 Ambient Air Quality Standard Level II Standard
0.9
We can see from data given in Table 6.1-5, after the sprinkler dust measure (sprinkler
4-5 times per day) is taken, the dust concentration (calculated in TSP) is reduced greatly, and
the impact range is also reduced from 5-100m to 5-50m. Within the range of 50-100m, the
TSP concentration value of ambient air reaches level II standard of GB3095-1996 Ambient
Air Quality Standard (suitable for residential area, commerce, transport and resident mixed
area).
In a word, construction dust will have certain impact on residents, schools, enterprises
and public institutions and construction personnel around the construction boundary, among
which, construction personnel are affected the most. As the pipe network construction
involves a wide range and the range affected by construction dust is wide, construction dust is
mainly concentrated on both ends of pipe works and the roads where construction and
transport vehicles drive across, however, the distance between project pipe network
construction point and residential area and enterprises and public institutions is above 100m.
So though construction dust has certain impact on ambient environment, by taking necessary
measures, the impact of construction dust will be reduced greatly. And the impact is
temporary, along with the execution of landscaping and rehabilitation, the impact will be
reduced greatly and even disappear after the completion of construction.
5.1.1.3 Vehicle Emissions
Construction machinery and equipment for the project includes face shovel, back
shovel, bulldozer, dump truck, pile driver, and stirrer, etc. The construction machinery uses
diesel and gasoline and exhaust emissions by fuel oil mainly includes SO2, NOx, CO and
hydrocarbons, etc. Exhaust emissions during construction are referred to Table 5.1-6.
Table 5.1-6 Exhaust Emissions during Construction
Fuel
Name
Fuel
Consumption
(t)
Polluta
nts
Emission
Factor (kg/t)
Emission
(t)
Total Exhaust Emissions of Construction
Machinery (t)
Gasoline 649
SO2 0.40 0.260 SO2: 22.233
NOx: 323.547
CO: 331.844
CnHm: 59.088
NOx 28.13 18.256
CO 225.33 146.239
CnHm 44.40 28.816
Diesel 5844 SO2 3.76 21.973
NOx 52.24 305.291
CO 31.76 185.605
CnHm 5.18 30.272
As smaller intensity of exhaust emissions and flat terrain which are favorable to waste
gas dilution and diffusion, tail gases generated by construction machineries, transport
vehicles have small impact on ambient atmospheric environment.
5.1.2 Water Environment Impact Analysis and Assessment 5.1.2.1 Construction Wastewater Environment Impact Analysis
During construction, as the execution of site cleaning, pipe laying, concrete mixture,
building and installation, etc. a certain amount of construction remained water and spools will
be brought. In addition, as a large number of construction personnel will be needed during
construction, a certain amount of sanitary sewage will be generated.
(1) Construction Wastewater
Main pollutants in construction remained water and spools are COD, SS and
petroleum. The analogy data show that the concentration of COD and petroleum are both
lower than 150 mg/L for COD and 10 mg/L for petroleum required by level II standard in
Integrated Wastewater Discharge Standard (GB8978-1996), but cause SS increased in short
time. According to analogy investigation, the concentration of wastewater suspended matters
during construction is 500-1300 mg/L, after preliminary treatment of sediment and others, the
concentration of suspended matter is greatly reduced and can reach discharge standard after
holding for above 2h and will not cause remarkably unfavorable impact on water body.
(2) Sanitary Sewage
The calculation formula of sanitary sewage on construction site is as below:
Q = (k × q × n) /1000
Where, Q——Sanitary sewage volume, t/d;
k——Sewage emission coefficient, the project takes 0.8;
q——Per capital sanitary household water consumption, L/cap·d;
n——Number of daily construction site personnel, cap.
According to analogy data, the COD concentration in sanitary sewage on construction
site is around 300 mg/m3, BOD5 concentration is around 150 mg/m3, and SS is 150mg/l.
Water consumption takes 50 L/cap·d for calculation and the calculation results are shown in
table. According to the requirements of construction scale and construction period of each
pollution project, estimate the construction personnel required and sanitary sewage emissions,
refer to Table 5.1-7.
Table 5.1-7 Sanitary Sewage Emissions during Construction
S/
NProject Name
Number of
Constructi
on People
Water
Consumptio
n (t/d)
Sanitary Sewage
Emissions (t/d)
1Urat Rear Banner Processing Park Regenerated Water
Supply Project90 4.5 3.6
2Ganqimaodu Port Processing Park Regenerated Water
Supply Project100 5.0 4.0
3 Drainage Canal 3 Regenerated Water Supply Project 80 4.0 3.2
4 Drainage Canal 7 Regenerated Water Supply Project 80 4.0 3.2
5Urat Rear Banner Processing Park (Huhe Town) Sewage
Treatment and Reuse Project90 4.5 3.6
6Ganqimaodu Port processing Park (Delingshan Town)
Disposal Treatment and Reuse Project100 5.0 4.0
7Urat Front Banner Processing Park (Xianfeng Town)
Sewage Treatment and Reuse Project120 6.0 4.8
8 Wuliangsu Lake Idyllic Grid Waterway Project 50 2.5 3.0
9
Wuliangsu Lake Biological Transition Zone Constructed
Wetland Project and Area Source Demonstration and
Promotion Project
70 3.5 2.8
As all itemized works of the project are not developed simultaneously, actual sanitary
sewage emissions are not the sum of simple addition of figures in above table. From above
table, it can be reflected that sanitary sewage emissions during construction are not big.
The existing living facilities near the construction site shall be used for sanitary sewage
emissions during construction as far as possible. The unconditioned area shall be set up with
temporary toilets and cesspool on site to collect stools which shall be transported by pumping
tumbrel provided by construction companies or consigned sanitation department to sewage
treatment plant for treatment periodically.
5.1.2.2 Assessment of Impact on Water Environment of Grid Excavation and Sediment
Release in Lake Area
Environment-friendly dredging machineries are used for this work to dredge grid
waterways in Wuliangsu Lake. Disturbance brought by the dredging will facilitate the mix
and exchange between mud and water, causing the increase of pollutants and SS content in
water body, as well as the increase of organic matters and nutrients, also interfering the living
environment for benthic organism to a certain degree. Backhole dredgers and grab dredgers
will be used for this dredging operation that can effectively reduce the second pollution
caused by the diffusion of pollutants and SS around water body. Dredgers will conduct
stationary operation, so that they won’t disturb bed mud in the Lake are too much, and there
will be less bed mud leakage during the dredging operation. Construction impact on water
environment will be within the range of 50-60m that it won’t affect water environment
significantly.
(1)Analysis on Suspended Matter Diffusion Impact
Factors like comprehensive dredging effects and impact on environment. It’s
recommended to deploy 0.8~1.2 m3 hydraulic backhole dredgers. For sediments excavation at
the upper layer in the area having less aquatic weeds, grab dredgers can be used.
Basically, hydraulic backhole dredgers and grab dredgers will conduct stationary
operation during the construction. Diffusion mechanism of suspended dredged materials is
similar to the diffusion of continuous point source. This environmental evaluation will refer
to the forecast results of impact on suspended matters diffusion in dredging operation in
relevant lake area of Meiliang Lake under the Report on the Impact on Polluted Bed Mud
Dredging Test Work Environment in Tai Lake, where the construction process is similar to
that of this work, and the forecast results in which can reflect the impact range of this work.
The forecast results indicate that at 50m of excavation circumference, the impact values of
suspended matters content in water body are all below 10mg/L. And such impact mainly
works on dredging. About one hour after dredging, the content of suspended matters
increased artificially will fall off under 1mg/L quickly. Therefore, it is reasonable to say that
the operation of hydraulic backhole dredgers and grab dredgers won’t disturb bed mud too
much, and basically there is no bed mud leakage during dredging operation. Bed mud
dredged will be transferred above the dredging barge with the slewer. Then the device for
opening the bucket will pull the latch off and compress the buffer spring. Bucket bottom will
be opened under deadweight and loading force to unload the mud. Mud excavated will be
transferred directly into the barges calling beside. Then a barge train (including five barges
filled with mud in turn) will be towed to material discharge area by a towboat.
The excavation and dredging can facilitate the mix and exchange between mud and
wter in the system effectively, enhance the release of organic matter, TP and TN in bed mud,
and cause the increase of contents of COD, TP, and TN in the water body. According to the
test data of bed mud resuspension in relevant water body, the disturbance brought by mud
excavation will increase the contents of aerobic organic matters, TP and TN by around 10%.
Short after mud excavation, due to the effects caused by oxide and hydroxide, the contents of
aerobic organic matter, TP and TN will decline gradually to the background level, which will
not affect the water body in area being excavated too much.
(2)Analysis on Impact of Remained Water at Laydown Area
Pollutants in remained water from waterway excavation operation mainly refer to the
pollutants contained in the water body of construction area, as well as nitrogen, phosphorus,
and heavy metal pollutants enriched in bed mud particles. Controlling the discharge content
of suspended matters in waters during construction will control the discharge contents of
other pollutants effectively.
According to the results of simulation test on silt in Caohai, Dianchi in Table 51-8:
Pollutant content in remained water declines as the time of slurry sedimentation increases, but
the content of suspended matters might not meet the requirements under Standard-I. If
stationary time is shorter than 48h, pollutant content in remained water will exceed Standard-
I under Slurry Comprehensive Discharge Standard. According to laydown area design for this
work, slurry sedimentation time is normally longer than 48h.
Table 5.1-8 Components of Remained Water from Bed Mud Dredging in Caohai (simulation test
results) (mg/L)
Test Conditions pH
SSChromati
cityCOD
Mn
TN
TPNH4
-NCu Pb Zn Cd As
Slurry at Estuary of
Daguan River
Stationary for 1h
6.0
932 41 26.4 23.3
0.253
17.8
0.05 0.03
<0.01
<0.01
0.019
Stationary for 48h
6.0
71 34 7.6716.9
0.080
12.9
0.01<0.01
<0.01
<0.01
0.006
Lake Water
Background
6.4
86 8 6.7411.8
0.750
8.91
0.0020.02
0.039
0.003
0.007
Slurry at Estuary of Yunliang River
Stationary for 1h
6.0
1013 63 65.825.2
0.100
21.7
0.110.04
0.080.01
0.068
Stationary for 48h
6.2
83 58 10.624.3
0.042
21.4
0.020.02
0.01<0.01
0.029
Lake Water
Background
6.4
68 9 7.589.75
0.857
7.49
0.0080.03
0.046
0.006
0.026
Comprehensive Discharge Standard Level I
6-9
70 50 100 — 0.5 25 1.01.0
4.0 0.1 0.5
Therefore, there are cutoff trenches in bed mud laydown area where perlocating water
will be extracted in time and delivered into the reed wetland for treatment.
(3) Analysis on Secondary Pollution of Waterway Excavation Work
Bed mud excavation is one of the significant measures to control internal pollution
source in the lake. However, bed mud excavation is a large-scale man-made interference
which will facilitate pollutant release such as nutrient and heavy metal, bringing negative
impact on the quality of water body environment to a certain degree.
For bed mud excavation is similar to bed mud dredging, therefore, the Analysis on
Risks of Water Environment Quality of Bed Mud Dredging in Tai Lake (written by Liu
Aiju, Kong Fanxiang, Wang Dong) can be used for analogy, which indicates that during
dredging operation and during a short while after dredging finishes, the contents of total
suspended matters, toxic heavy metal ions, nitrogen nutrient and phosphorus nutrient in the
water body increase, while the transparency of water body declines. That’s mainly because
dredging operation causes resuspension of surface sediments, facilitating the release of
nitrogen nutrient, phosphorus nutrient, and toxic heavy metal ions from sediments. Such
impact on environment will continue that two months after dredging operation finishes,
suspended matters content, heavy metal pollution level, nitrogen nutrient content, and
phosphorus nutrient content in the water body start to decline, meaning that suspended
matters, as well as nutrients and heavy metal ions suspended matters absorbed in the water
body after dredging operation will start to precipitate quickly. However, compared to the
situation before dredging, the quality of lake water environment nine months after dredging is
not as good as that before dredging. One year after dredging, water body quality improves,
and all indicators can’t compete with those before dredging, which means that bed mud
excavation will somehow facilitate the improvement and enhancement of lake water body.
5.1.3 Analysis of Acoustic Environmental Impact The construction noise is mainly generated by construction machineries and
transportation vehicles. The noise intensity is different in different construction stages, sites
and operation types. During construction, there are many construction machineries, besides,
the construction is outdoor working without noise reduction measures, and therefore the noise
is spread far and the affected area is large. Main noise sources during construction are
excavators, transportation vehicles, pipelayers, concrete mixers, dump trucks, vibrators,
electric welding machines and bulldozers etc. Main noise sources of machineries and the
source intensities are as shown in table 5.1-9.
Table 5.1-9 Main Noise Sources of Machineries and the Source Intensities
No. Equipment Name Intensity dB(A)
1 Air compressor 110
2 Crusher 97
3 Excavator 79 ~ 83
4 Bulldozer 85
5 Loader 85
6 Lifter 72
7 Winder 97
8 Truck (above 10t) 79 ~ 83
9 Crane 76
10 Electric saw 90
11 Welding machine 78
12 Grafter 80
13 Pavement roller 84
14 Pile driver 110
15 Vibrator 105
16 Concrete pump 85
17 Dredger 92
(2) Analysis of environmental impact of noise on construction site
The analysis of engineering pollution sources shows that the noise sources on
construction site are machineries with high noise and during construction, and a lot of
machineries are operated on site, and therefore the intensity of single unit equipment source is
between 76 dB(A) and 110 dB(A). The construction equipment can not be prevented, because
they are used outdoor. The attenuation of noise with the distance increase is as follows:
L2 =L1- 20log( r2/r1)
Wherein:
L2 、 L1——noise level at r1 and r2 away from the noise source;
r1 、 r2——the distance away from the noise source;
In calculation, r1 = 1m.
Refer to table 5.1-10 for attenuation of equipment noise with the distance increase.
Table 5.1-10 Attenuation of Equipment Noise with the Distance Increase
N
o.
Name of
Noise
Source
Noise
Intensity
Noise level at different location from the noise source
20m 40m 60m 80m 100m
20
0
m
300m500
m
1
Air
compress
or
110 84 78 74 72 70 64 60 56
2 Crusher 97 71 65 61 59 57 51 47 43
3 Excavator 83 57 51 47 45 43 37 - -
4 Bulldozer 85 59 53 49 47 45 39 - -
5 Loader 85 59 53 49 47 45 39 - -
6 Lifter 72 46 40 36 - - - - -
7 Winder 97 71 65 61 59 57 51 47 43
8 Truck 83 57 51 47 45 43 37 - -
9 Crane 76 50 44 40 38 36 - - -
1
0
Electric
saw90 64 58 54 52 50 44 40 36
1
1
Welding
machine78 52 46 42 40 38 - - -
1
2Grafter 80 54 48 44 42 40 34 - -
1
3
Pavement
roller84 58 52 48 46 44 38 - -
1
4Pile driver 110 84 78 74 72 70 64 60 56
1
5Vibrator 105 79 73 69 67 65 59 55 51
1
6
Concrete
pump85 59 53 49 47 45 39 - -
1
7 Dredger 92 77.5 70.4 65.9 63.8 58.255
.852.1
49.
9
During construction, the machineries are main noise sources, if not considering the
influence of houses, trees and air etc., at 100m away from the boundary of construction site,
the maximum noise level is 70 dB(A), while at 500m away, the maximum noise level is 56
dB(A), which basically meet the daytime noise level of construction site. If considering the
noise reduction of houses, trees and air etc., the reduced noise is 15 dB(A). At 100m away
from both sides of the construction site, the noise level can meet the daytime limit for
construction site.
No. 3 Drainage Line Reclaimed Water Supply Works will impact the acoustic
environment around the adjacent Shanba Feeding Farm and No. 3 Drainage Line Sewage
Treatment Plant; No. 7 Drainage Line Reclaimed Water Supply Works will impact Wuyuan
Brick Yard and other enterprises; Sewage Treatment and Reuse Works of Urat Front Banner
Processing Park will impact the acoustic environment of Shagedan Village; there is a few
environmental sensitive spots around other proposed works and the impact of construction
noise is little. Therefore, during construction, the operation time of machineries shall be
rationally arranged to avoid many equipments with high noise are operated simultaneously as
much as possible and to avoid the sensitive period of noise on environment, such as,
construction of equipments with high noise shall be arranged at daytime, transportation at
night shall be reduced, and construction at night (22:00 ~ 6:00) shall be prohibited. The
construction activities which must be carried out at night shall be approved by the local
environmental protection administration and shall be provided with noise barriers between
noise sources and sensitive spots.
The table 5.1-10 shows that the level of noise generated by machineries is high; the
impingement power is strong even lasting a long period with strong shock, which greatly
impact the ambient environment. Only the place 300m or farther away from the construction
site can meet the standard of acoustic environmental function zone of Wuliangsu Lake. The
construction site is at least 2km away from the core zone, and therefore, it will not impact the
birds in the reserve area.
The above mentioned analysis shows that during construction, try to reduce the man-
made noise, adopt proper sound insulation measures, set up construction enclosures,
rationally arrange the operation time of equipment with high noise and try to avoid
construction at night for reducing the impacts on environment. Meanwhile, select the
equipment position and use the natural condition for noise reduction to minimize the noise
during construction.
5.1.4 Analysis of Solid Waste Environmental ImpactThe solid waste generated during construction mainly includes bed mud generated
during grid excavation of Wuliangsu Lake area, dregs and gravels excavated during
earthwork construction, material lost during transportation including sands, stones and
concrete etc., and domestic waste produced by construction personnel.
(1) Bed mud and waste generated during grid excavation of Wuliangsu Lake area
The works of this project mainly include excavation works of watercourse in the lake
area and construction of temporary pier and mud heap yard. The construction area of grid
excavation of Wuliangsu Lake area is 2.451×106m2, the bed mud generated is 2.295×105m3.
Except for natural reasons (such as blowing, dust falling etc.), main reason of the bed mud is
the sediment caused by great soil and water loss, filled by the aquatic plant and the sediment
of suspended matter in industrial waste water and domestic sewage. The moisture content in
sludge is high. If don’t adopt proper protective measures, the secondary pollution may be
generated. The Bayannur Environmental Monitoring Station monitors the heavy metal
content in the bed mud. The monitoring result shows that the heavy metal content at all
monitoring points meet the GB4284-84 Control Standards for Pollutants in Sludge from
Agricultural Use. Thus, the bed mud can be used as the fertilizer. The upper bed mud can be
used for improving the saline alkali soil; the lower bed mud is mainly the non-polluted
undisturbed soil about 2.17 million m3, and used for building the artificial island in the lake
area. The lower bed mud is consumed internally and not transported outside. In accordance
with the tourism planning of Wuliangsu Lake, many artificial islands shall be constructed in
the lake area.
(2) Works Spoil
During construction, spoil will be generated from the earth excavation. During
transportation and disposal, the spoil may impact the environment. Based on the estimation,
earth in all works of this project is basically balanced without shortage of soil. But the
construction of water supply and distribution pipeline network will generate the spoil. During
pipe-laying, the soil generated during pipe trench excavation is heaped at one side of the pipe
trench. At the bottom of the trench, firstly fill the foundation stuffing with the thickness of
400mm and then laying the pipeline. Therefore, the works spoil volume is at least equal to
addition of pipeline volume and volume of foundation depth. In accordance with the
estimation of pipeline work earth volume, the spoil volume of works lines of this project is as
shown in table 5.1-11.
Table 5.1-11 Spoil Volume of Works Lines
No. Works Name
Length of the Water Supply
and Distribution Pipeline
Network (km)
Spoil
Volume
(m3)
1Urat Rear Banner Processing Park Reclaimed Water Supply
Works 35.5(500) 14066.88
2Ganqimaodu Port Processing Park Reclaimed Water Supply
Works 28.0(600) 14632.8
3 No. 3 Drainage Line Reclaimed Water Supply Works 11.6(300) 2211.54
4 No. 7 Drainage Line Reclaimed Water Supply Works 11.8(700) 7842.87
5 Urat Rear Banner Processing Park (Huhe Town) Sewage 67.6(400) 19306.56
Treatment Reuse Works
6Ganqimaodu Port Processing Park (Delingshan Town)
Sewage Treatment Reuse Works 45.08(400) 12874.85
7Urat Front Banner Processing Park (Xianfeng Town) Sewage
Treatment Reuse Works 32.4(530) 14013.21
8 Wuliangsu Lake Ruralized Grid Watercourse Works —— ——
9
Wuliangsu Lake Bio-transition Zone Artificial Wetland and
Non-point Source Pollution Control Demonstration
Promotion Works—— 1118223
(3) Construction WasteThe construction waste will be generated due to consumption and desertion of stones,
clinkers and building materials during construction of all works. If the construction waste is
not be handled promptly, it is not only unsightly and influence the landscape of the city, but
also be blown to generate the dust raise phenomenon in gale and dry weather.
The soil and construction waste of the works transported outward is common solid
waste without the toxic and harmful content. The waste can be used for filling the foundation
of construction works specified by the municipal and planning departments, filling the swag
or greening along the river for disposal. Rest waste can be delivered to local landfill site.
Generally, disposal of the discard will not take the adverse impact on environment.
(4) Domestic Waste
In accordance with that the construction period is 36 months and the waste is
1.16kg/person·d, the domestic waste volume during construction period of all works is as
shown in table 5.1-12. The total domestic waste output during construction is 977.4t which is
delivered to the site specified by Environmental Sanitation Administration for disposal.
Table 5.1-12 Domestic Waste Volume during Construction of All Works
No
.Works name
Number
of
construct
or
Domestic
waste volume
(t/d)
Total domestic
waste volume
(t)
1Urat Rear Banner Processing Park Reclaimed Water Supply
Works90 0.10 108.0
2Ganqimaodu Port Processing Park Reclaimed Water
Supply Works100 0.12 129.6
3 No. 3 Drainage Line Reclaimed Water Supply Works 80 0.093 100.44
4 No. 7 Drainage Line Reclaimed Water Supply Works 80 0.093 100.44
5Urat Rear Banner Processing Park (Huhe Town) Sewage
Treatment Reuse Works90 0.10 108
6Ganqimaodu Port Processing Park (Delingshan Town)
Sewage Treatment Reuse Works100 0.12 129.6
7Urat Front Banner Processing Park (Xianfeng Town)
Sewage Treatment Reuse Works120 0.14 151.2
8 Wuliangsu Lake Ruralized Grid Watercourse Works 50 0.058 62.64
9
Wuliangsu Lake Bio-transition Zone Artificial Wetland and
Non-point Source Pollution Control Demonstration
Promotion Works
70 0.081 87.48
Total 977.4
During construction, daily life of the constructors will generate domestic waste at
certain quantity. If the waste is not disposed promptly, at proper temperature, it will breed
mosquitoes and insects, generate fetidity and transmit diseases, resulting in adverse impact on
ambient environment. Therefore, the domestic waste shall be promptly delivered to the site
specified by Environmental Sanitation Administration for disposal to avoid the impact on
ambient environment.
5.1.5 Analysis of Ecological Impact5.1.5.1 Project Construction
Impact of this project on ecological environment mainly refers to the damage of soil
and natural vegetation caused by works construction and pipe-laying.
(1) Impact of Permanent Land Occupation
The construction the reclaimed water treatment facilities, the sewage treatment reuse
facilities and the Wuliangsu Lake artificial wetland belongs to the permanent land
occupation. The vegetation shall be rooted up for construction of the reclaimed water
treatment facilities and the sewage treatment reuse facilities, resulting in reduction of
vegetation coverage rate, which easily causes soil and water loss at little quantity. Besides,
the earth excavation and filling change the soil structure, reduce the soil maturation degree,
impact the productivity of soil after reclaim, but will not change the land utilization type. The
permanent land occupation of the reclaimed water treatment facilities and the sewage
treatment reuse facilities mainly is the wasteland and some is the agricultural land, which will
reduce the farm land at certain degree. The construction method of Wuliangsu Lake artificial
wetland is artificial intensification of the existing reed field without changing the original
utilization features of the land. The permanent land occupation of this works takes little
ecological impact.
(2) Impact of Temporary Land Occupation
Construction of the pipeline network belongs to the temporary land occupation. The
vegetation within 1-8m of the pipe trench is severely impacted. The crops will be recovered
in a short time, but the trees and other vegetation will be recovered in a long time. During the
temporary land occupation construction, strict topsoil protective measures shall be carried out
to avoid unrecoverable impact. During excavation, the top soil (suggested thickness 30 ~50cm) shall be collected and stacked separately and the soil and water loss control measures
shall be adopted. After construction, firstly fill the subsurface soil back, and then cover the
top soil on the surface, and level up the site so as to reduce the impact on soil quality. As long
as there is rational planning during construction, timely site cleaning and greening after
construction, the adverse impact can be effectively controlled.
The disturbance of pipe-laying is low frequent and linear. Its impact is partial,
temporary and recoverable after construction.
(3) Impact on Landscape Ecology
The coverage of this project is large. During the construction of pipeline network and
lake area treatment works, the excavation and soil stacking will make the pipeline network
laying area in disorder. Although there is the disclosure, the construction site will make the
disorder impression; the spill of discarded soil during outward transportation will not only
dirty the roads and but also raise the dusts, which will take adverse impact on surrounding
landscape. Therefore, the cleaning work on construction site is very important. The impact on
landscape during construction is short-term and recoverable.
5.1.5.2 Analysis of Soil and Water Loss
The impact of general project on soil and water loss mainly includes the following two
aspects: vegetation damage during excavation of ground surface, resulting in soil and water
loss in rainfall; damage of original vegetation caused by the temporary land occupation,
resulting in increase of soil and water loss. If the raw material yard and discarded soil
temporary stacking yard are not properly managed, soil and water loss phenomenon in form
of sheet erosion and shallow ditch erosion etc. may easily happen.
The construction stages of this project in which the soil and water loss may happen
mainly refer to ground excavation during pipe-laying, construction of reclaimed water
facilities, sewage treatment reuse facilities and Wuliangsu Lake artificial wetland and
earthwork excavation.
In accordance with the soil and water conservation scheme of all works, the predicted
results of soil and water loss are as follows:
1) Urat Rear Banner Processing Park Reclaimed Water Supply Works
Area of original topography and ground vegetation damaged during the construction of
Urat Rear Banner Processing Park Reclaimed Water Supply Works is 41.31hm2, total area of
soil and water conservation facilities damaged is 41.31hm2, total possible soil and water loss
is 29,300 t and the newly increased soil and water loss is 20,200 t.
2) Urat Rear Banner Processing Park Sewage Treatment Reuse Works
Area of original topography and ground vegetation damaged during the construction of
Urat Rear Banner Processing Park Sewage Treatment Reuse Works is 13.47hm2, total area of
soil and water conservation facilities damaged is 13.36hm2, soil erosion caused by
disturbance of the works is 50180t including 49084.96t soil and water loss during
construction (including preparation period) and the newly increased soil and water loss is
24192.1 t.
3) No. 3 Drainage Line Reclaimed Water Supply Works
Area of original topography and ground vegetation damaged during the construction of
No. 3 Drainage Line Reclaimed Water Supply Works is 19.66hm2, total area of soil and water
conservation facilities damaged is 17.21hm2, soil erosion caused by disturbance of the works
is 2208.89t (including spontaneous recovery period) and the newly increased soil and water
loss is 826.81t.
4) No. 7 Drainage Line Reclaimed Water Supply Works
Area of original topography and ground vegetation damaged during the construction of
No. 7 Drainage Line Reclaimed Water Supply Works is 42.39hm2, total area of soil and water
conservation facilities damaged is 39.89hm2, soil erosion caused by disturbance of the works
is 5062.26t (including spontaneous recovery period) and the newly increased soil and water
loss is 2160.89t.
5) Ganqimaodu Port Processing Park Reclaimed Water Supply Works
The soil and water loss type of Ganqimaodu Port Processing Park Reclaimed Water
Supply Works during construction is complex erosion by wind and water (mainly the wind).
The important predicted stage of the soil and water loss is the construction period and the
operation period. The total disturbed ground area during construction is 62.93hm2, total area
of soil and water conservation facilities damaged is 51.77hm2, total possible soil and water
loss is 17810.25t, and the newly increased soil and water loss is 12660.02t.
6) Ganqimaodu Port Processing Park Sewage Treatment Reuse Works
Area of original topography and ground vegetation damaged during the construction of
Ganqimaodu Port Processing Park Sewage Treatment Reuse Works is 55.76hm2, total area of
soil and water conservation facilities damaged is 55.76hm2, soil erosion caused by
disturbance of the works is 12976.20t and the newly increased soil and water loss is 5131.45t.
7) Urat Front Banner Processing Park Sewage Treatment Reuse Works
The soil and water loss type of Urat Front Banner Processing Park Sewage Treatment
Reuse Works during construction is complex erosion by wind and water (mainly the wind).
The important predicted stage of the soil and water loss is the construction period. The total
disturbed ground area during construction is 13.85hm2, soil and water loss area during
construction (including preparation period) is 13.85hm2, and that during spontaneous
recovery is 7.94hm2. Total possible soil and water loss is 1354.39t, increased by 556.69t; soil
and water loss during construction is 586.60t, increased by 312.94t and during spontaneous
recovery is 767.79t, increased by 243.75t.
8) Wuliangsu Lake Bio-transition Zone Artificial Wetland and Non-point Source Pollution
Control Demonstration Promotion Works
Area of disturbed original topography and damaged ground vegetation is 6680.27hm2.
During prediction, total soil and water loss caused by the works is 6239.80t including
4161.50t during construction and 2078.30t during spontaneous recovery, and the newly
increased soil and water loss is 2312.80t.
9) Wuliangsu Lake Grid Watercourse Works
In accordance with the prediction, area of original topography and ground vegetation
damaged during the construction of this works is 688.47hm2, total area of soil and water
conservation facilities damaged is 3.87hm2, soil erosion caused by disturbance of the works is
58016.64t including 20152.84t during preparation and construction and 37863.8t during
spontaneous recovery; the newly increased soil and water loss is 33760.27t including
14127.17t during preparation and construction and 19633.1t during recovery.
The soil and water loss of all works is as shown in table 5.1-13.
Table 5.1-13 The Soil and Water Loss of All Works
No. Works name Soil and water loss volume (104t)
1 Urat Rear Banner Processing Park Reclaimed Water Supply Works 2.93
2 Ganqimaodu Port Processing Park Reclaimed Water Supply Works 1.78
3 No. 3 Drainage Line Reclaimed Water Supply Works 0.22
4 No. 7 Drainage Line Reclaimed Water Supply Works 0.51
5Urat Rear Banner Processing Park (Huhe Town) Sewage Treatment
Reuse Works4.91
6Ganqimaodu Port Processing Park (Delingshan Town) Sewage
Treatment Reuse Works1.3
7Urat Front Banner Processing Park (Xianfeng Town) Sewage
Treatment Reuse Works0.14
8Wuliangsu Lake Bio-transition Zone Artificial Wetland and Non-point
Source Pollution Control Demonstration Promotion Works0.62
9 Wuliangsu Lake Grid Watercourse Works 1.41
5.1.5.3 Impact of Wuliangsu Lake Treatment Works
1) Wuliangsu Lake Grid Watercourse Excavation Works
Suspended matters generated during grid watercourse construction will form a high
density distributed zone around the construction site, resulting in species and quantity
reduction of plankton and zooplankton. However, this impact is reversible. After completion
of the works, the impact will eliminate soon. The disturbance of construction of grid
watercourse on benthonic habitat will cause damage of habitat for zoobenthos, resulting in
stable reduction of biocoenosis structure. Noise and air pollution generated by the
construction of grid watercourse will take impact on birds and reduce the species and quantity
of plankton and zooplankton, resulting in impact on wading birds. The mud yard and
hydraulic fill works will damage original terrestrial vegetation, resulting in the loss of
vegetation in species and quantity.
2) Wuliangsu Lake Artificial Wetland Works
Impact of the works on vegetation mainly refers to the damage of reed caused by land
occupation. During construction, channel dredge and trench excavation excavate the subsoil
out, which totally change the soil mass structure. During construction, vegetation on the
excavation area is all damaged, and the vegetation at both sides of the trench is damaged and
impacted at different degree; in the area with severe damage, not only the vegetation but also
the soil is damaged, which will impact the further growth of vegetation; in moderate
impacted area, during excavation, rolling and trample of machinery, vehicles and personnel
and stack of excavated soil will cause severe damage of the plants and also slightly impact
the soil; in slightly impacted area, activities of machinery, vehicles and personnel reduce and
the corresponding impact is slight.
The wetland restoration works is at least 5km away from the core area of Wuliangsu
Lake Waterfowl Natural Reserve. The construction area is outside the buffer zone of the
natural reserve and will not directly impact the birds and their habitat, but during
construction, there will be many machineries and constructors entering peripheral region of
the reserve. If the protection is not strengthened, increase of noise of machineries and
activities of constructors will indirectly impact the normal foraging and habitat of birds and
the reserve.
Suspended matters generated during construction of stabilization and sedimentation
pond will form a high density distributed zone around the construction site, resulting in
species and quantity reduction of plankton and zooplankton. However, this impact is
reversible. After completion of the works, the impact will eliminate soon. The disturbance of
construction on benthonic habitat will cause damage of habitat for zoobenthos, resulting in
stable reduction of biocoenosis structure. Noise and air pollution generated by the
construction will take impact on birds and reduce the species and quantity of plankton and
zooplankton, resulting in impact on wading birds.
5.1.6 Social Environmental Impact Analysis 5.1.6.1 Impact on Traffic
Impact on traffic during construction mainly includes the following three aspects: ①
road break for pipeline network holds up the traffic; ② stacking of soil and road excavation
hold up the traffic; ③ transportation vehicles increase the traffic flow.
Main impact of construction on traffic is on road traffic, detailed in table 5.1-14.
Table 5.1-14 Impact of Construction on Traffic
Construction
ItemWorks with Impact Impact on Traffic Mitigation Measures
Material
transportationAll works
Increase ① the traffic flow of city
proper and impact the traffic smooth.
②Spill of soil, stones and sands
during transportation impacts the
safety of traffic and damage the
pavement.
①Strengthen the traffic
dispatch and control to avoid
peak traffic.
②Strengthen the education of
drivers, prohibit to over load,
promptly clean the spilled
material.
Pipeline
construction
Reclaimed water supply
and processing park
sewage treatment reuse
works
Damage pavement, soil is stacked,
impact the traffic
①Construct in stages, and try to
complete excavation and
backfill in a short period.
②Set up temporary road and
warning marks and appoint
special person to relieve the
traffic
Impact of construction of pipeline network on traffic is obvious. Although the staged
construction method can be adopted, during construction, there is always some soil to be
stacked temporarily, which will impact the traffic along the pipeline and plant area. When
pipelines cross the roads, if adopt the trenching method, it may block the vehicles, resulting
in great impact on traffic. Therefore, if the geology and soil conditions are applicable, pipe
jacking construction method will reduce the impact of road excavation during construction.
During this period, bearing force (supporting capacity) of the roads will reduce, and therefore
the truck shall be prohibited in a short period, which will impact the traffic. According to
estimation, 20 days are needed for pipeline crossing every road, and thus the impact on traffic
of this road will last 20 days. Therefore, detailed planning and speed-up construction shall be
needed, try to adopt the pipe jacking construction method, work out the temporary route with
the local traffic administration before construction, inform the residents in impacted area in
advance, set up warning plates on construction site and appoint special person to relieve the
traffic. Beside, adopt management strengthening during construction and construction period
shortening and other measures to avoid traffic jam.
The transportation of raw material (sandstones, cement etc.) and discarded soil will
increase the traffic flow in a short period. Therefore, the transportation shall not be carried
out in traffic peak, especially the morning and evening peak.
5.1.6.2 Health and Safety
This works includes many works, such as reclaimed water supply works, sewage
treatment reuse works and Wuliangsu Lake comprehensive treatment works. The construction
sites are in different banners and counties. The works not only includes reclaimed water
treatment facilities and sewage treatment reuse facilities, but also includes pipelines of
rainwater, sewage and reclaimed water, water fetching and supply pump stations, and
excavation of Wuliangsu Lake grid and artificial wetland construction. Therefore, there are
many constructors from all corners of the land and the mobility is strong. Because the
construction places and construction sites of all works are not centralized. Living and sanitary
conditions are poor and labor intensity is strong, and therefore diseases may be easily
transmitted. In order to guarantee the construction safety, complete physical examination
shall be carried out for all constructors. Constructors with infectious diseases are prohibited
to enter the construction site. Regular physical examination shall be carried out for the
personnel in canteen of all works. If the personnel has the infectious disease, the personnel
shall be promptly cured and not work in the canteen to prevent the disease transmission. The
centralized water supply facilities shall be equipped in each construction site. The water
source shall be sterilized and monitored. The construction site shall be provided with the
medical facilities. Labor protection measures shall be carried out for constructors to protect
their health and safety so as to make the construction smooth.
5.2 Environmental Impact Analysis of Operation Period
5.2.1 Reclaimed Water Supply Works5.2.1.1 Impacts on Water Resources
The water sources of the reclaimed water supply works are consist of sewage
treatment plant effluent, drainage ditch drainage and underground water. See table
5.2-1 for the water source and consumption of reclaimed water supply works.
Table 5.2-1 Water Source and Intaking Amount of Reclaimed Water Supply Works
SN. Works Name Water SourceWater Intaking Amount
(10,000m3/a)
1
Urat Rear Banner Processing
Park Reclaimed Water Supply
Works
Urat Rear Banner Processing
Park Sewage Treatment Works658.8
Main Drainage Ditch 597.4
Yongmingmeizi 70.0
Underground Water 211.0
Total 1537.2
2No. 3 Drainage Line Reclaimed
Water Supply Works
No. 3 Drainage Line Sewage
Treatment Plant439.2
No. 3 Drainage Ditch 512.4
Underground Water 256.2
Total 1207.8
3No. 7 Drainage Line Reclaimed
Water Supply Works
No.7 Drainage Line Sewage
Treatment Plant481.7
No. 7 Drainage Ditch 483.12
Underground Water 242.98
Total 1207.8
4
Ganqimaodu Port Processing
Park Reclaimed Water Supply
Works
Main Drainage Ditch 2067.6
Total 2067.6
The water intaking amount of this project of reclaimed water supply works using
effluent of sewage treatment plants as source is 15.797 million m3/a, which will not
only save a great amount of water resources, improve the utilization but reduce
emission of pollutants.
The water intaking amount of Urat Rear Banner and Ganqimaodu port
processing park reclaimed water supply works from the main drainage ditch is 26.65
million m3/a and that of No. 3 and 7 reclaimed water supply works from No. 3 and 7
drainage ditches are 512.4 and 48.312 million m3/a. The water intaking amount of
reclaimed water supply works in winter is 7.1018 million m3/a.
According to the research report on the reasonable allocation of Bayannur City
water resources, the available water resources of Bayannur in normal years is 6.23
billion m3, among which the normal average annual water taking from Yellow River
is 5.2 billion m3, the degree of mineralization of industrial, agricultural and urban
populous area is 2g/l and exportable groundwater is 0.85 billion m3. In 2002, the practical
exportable groundwater for industrial and agricultural purposes reached 0.58 billion
m3. In 2003, because of water shortage of Yellow River and fighting for drought, the
production volume in Hetao Area and along-mountain region was 0.78 billion m3,
which was very close to the available volume. Some areas have become overdraft
hopper zone. By 2010, except over-intaking water from Yellow River for agriculture,
the ecological water shortage is 0.303 billion m3. And the demand of underground
water will increase to 1.118 million m3 from 0.58 million m3. The gap of underground
water with mineralization less than 2g/l will reach 0.268 billion m3. The gap will also
reach 35 million m3 even using the water with mineralization between 2-5g/l. The
water shortage problem will be the principal contradiction that restricts the economic
and social development of Bayannur city.
Therefore, the implementation of this project may reduce a groundwater
exploitation of 52.4022 million m3 protecting underground water, releasing the
shortage of water resources and promoting the economic and social development of
Bayannur.
5.2.1.2 Environmental Impact Analysis of Surface Water
The effluent discharge of the reclaimed water supply works are consist of
sedimentation tank muddy water, back flushing water of filter tank, filter-pressing
waste water of sludge and domestic sewage. In addition, the effluent discharge of
Ganqimaodu port processing park and No. 7 drainage line reclaimed water supply
works also include ultra-filtration reverse osmosis tail water because of reverse
osmosis workshop.
(1) The muddy water from sedimentation tank and back flushing water from
filter tank of the reclaimed water supply works are discharged into plant sludge pool
for sedimentation concentration, dewatered by the filter press in dewatering room and
carried out in form of mud cake, leaving the supernatant solution back flow into
flocculating setting tank along with new water for treatment. The filter-pressed waste
water from dewatered room makes back-flow into front distribution well along with
new water for treatment after settlement.
(2) The ultra filtration reverse osmosis tail water of No. 3 and 7 drainage lines
and Ganqimaodu port processing park reclaimed water supply works are all treated by
coagulating sedimentation and then piped into front distribution well along with new
water for restoration process, leaving the waste water un-discharged.
(3) The domestic water of this reclaimed water supply works is treated with
different methods and ways based on the surrounding infrastructure conditions. The
domestic water from Urat Rear Banner processing park reclaimed water supply works
will be diverted to its sewage treatment works for treatment and that of No. 3 and 7
drainage lines are diverted to their corresponding Hangjin Rear Banner and Wuyuan
County Sewage Treatment Plants, leaving that of Ganqimaodu Port to be treated by
the plant ground-embedded biochemical treatment equipment in accordance with the
requirements of The Reuse of Urban Recycling Water.—Water Quality Standard for
Miscellaneous Water Consumption (GB/T18920-2002)without drainage.
Therefore, this project has no effluent discharge making no impact on the surface
water environment.
5.2.1.3 Environmental Impact Analysis of Waste Gas
The reclaimed water supply works will not bear any odor, yet, produce slight
odor in the sludge tank, thickener tank and sludge thickening dewatering room. In
addition, the reclaimed water supply works of pr-eaeration unit also produces odor.
Since the water source of this reclaimed water supply works are inevitable in bringing
slight pollution of water. Therefore, the odor is too slight to making environmental
hazard. And since the sludge treatment area of this reclaimed water supply works is
equally distributed at the down-wind direction of water treatment plant along with
green isolated area to separate production and living areas, therefore, waste gas will
not have any impact on the plant production and living.
5.2.1.4 Acoustic Environmental Impact Assessment
According to the property and environmental characteristics of sound, the
corresponding computation schema shall be used to calculate the sound level of sound
source for future position. Efforts shall be also made to estimate the acoustic
environmental impact of the project after completion.
(1)Acoustic Environment Quality Forecast Mode
The forecast mode selected based on requirements of acoustic environment
assessment guide rules shall be simplified according to concrete conditions.
① Octave band pressure level of outdoor point sound source for future position
a. Octave band pressure level of one point sound source for future position
Among which:Loct(r)——Octave band pressure level of point sound source for
future position;Loct(r0)——Octave band pressure level of reference position r0;r——Distance from future position to sound source,m;r0——Distance from reference position to sound source,m;ΔLoct——Decrement caused by all kinds of factors, including acoustic barrier,
air absorption and ground effect.
b. If the octave band pressure level (Lw cot) of sound source is known and
considering source is above ground, then
Lcot=Lwcot-20lgr0-8
c.Caculaitng the sound level A (LA) of this sound source by all octave band
pressure levels:
Among the formula, Δli stand for the correction value of weighing networks A.
d. Synthesis of sound level of sound sources for future position
② Prediction of indoor point sound source
a. Octave band pressure level of sound source for near building enclosure:
Among the formula : r1 is the distance from indoors sound source point to
building enclosure;R is room constant;Q is directional factor.
b. Total octave band pressure level of outdoors sound source for near building
enclosure:
c. Total sound pressure level of outdoors near building enclosure:Loct,1(T)=L o ct,1(T)-(Tloct+6)
d. Conversing the outdoor sound pressure level into equivalent outdoors sound
source:Lw oct=Loct,2(T)+10lgS
Among the formula:S is area of acoustic permeability.
e. Since the equivalent outdoors sound source is the position of building
enclosure and its octave band sound power level is Lw oct, the sound level of
outdoors equivalent sound source for future position is calculated according to
outdoors sound source method.
③ Superposition of Sound Level
(2)Predictions
The noise equipment of proposed works is all indoors. The above forecast mode
shall be used to calculate the noise level of plant boundaries and predicate the acoustic
environmental impact upon the superposition with current noise value. See table 5.2-2
for the results.
Table 5.2-2 Predictions of Acoustic Environment Quality at Test Points of Plant Boundary (dB (A))
Works Name Test Points
Days and Nights Night
Current
SituationImpact
Superposition
Current
SituationImpact
Superposition
Urat Rear Banner
Processing Park
Reclaimed Water Supply
Works
East plant boundary 38.8 37.2 41.1 35 37.2 39.3
South plant boundary 46.5 41.4 47.7 38.3 41.4 43.1
West plant boundary 46.9 37.2 47.3 41.9 37.2 43.2
North plant boundary 41.5 41.4 44.5 35.2 41.4 42.3
No. 3 Drainage Line
Reclaimed Water Supply
Works
East plant boundary 55.1 37.2 55.2 48.2 37.2 48.5
South plant boundary 50.9 42.1 51.4 42.3 42.1 45.2
West plant boundary 50 42.1 50.7 41.3 42.1 44.7
North plant boundary 54.3 48.6 55.3 46 48.6 50.5
No. 7 Drainage Line
Reclaimed Water Supply
Works
East plant boundary 52.9 40.2 53.1 49.1 40.2 49.6
South plant boundary 50.7 37.2 50.9 46.1 37.2 46.6
West plant boundary 49.6 40.2 50.1 46.0 40.2 47.0
North plant boundary 52.1 46.7 53.2 48.9 42.9 49.9
Ganqimaodu Port
Processing Park
Reclaimed Water Supply
Works
East plant boundary 42.6 43.8 46.3 33.9 43.8 44.2
South plant boundary 42.3 40.7 44.6 35.6 40.7 43.1
West plant boundary 42.8 31.7 43.1 38.5 31.7 39.3
North plant boundary 41.1 38.0 42.8 34.0 38.0 39.5
It can be seen from table 5.2-2 that the noise level of reclaimed water supply
works within plant has meet the Class Ⅱ domain standard specified in Environmental
Quality Standard for Noise(GB3096-2008)after using all kinds of noise reduction measures.
5.2.1.5 Solid Waste
The reclaimed water treatment process may bring about sludge, which is free of
dangerous chemicals and position and is of high water content but with some organic
matters and pathogen and parasitic ovum. If untreated properly, the secondary pollution may be
caused.
The gravity thickening mechanical dewatering process is used for the reclaimed
water supply process according to the property of sludge, which may conduct
decrement of sludge, reduction of water content and reduction of sludge volume for
the convenience of transportation and treatment. The treated sludge may be comprehensively
used, such as sandy landfill mulching soil, backfill or brick making of road of city planning and
sanitary landfill based on the physical circumstances. In addition, the sludge treatment area is
located at the downwind direction of plant, which is far from living area and hardly to bring any
adverse effect on plant production and living.
The domestic garbage will be timely and effectively handled by environmental
sanitary division without causing secondary pollution.
According to the analytic result of solid waste of this project for environmental
impact, following measures are suggested to remove or reduce the impact:
① During plant piling and out-transportation, the sludge shall be timely and
effectively handled to reduce its contact with environment and avoid any pollution on
surrounding environment.
② The dewatered sludge shall use partially closed tipper for out-transportation in
case of sprinkling and secondary pollution.
③ The domestic garbage shall be timely cleaned and handled in case of
secondary pollution.
5.2.2 Sewage treatment and recycling engineering in Processing Park5.2.2.1 Prediction and Analysis of malodor Environmental Effect
(1) Pollutant concentration prediction
The evaluation is to predict pollutant concentration, taking Sewage treatment and
recycling plant in Processing Park in Urat Front Banner as an example. Pollutant
concentrations in the other two plants is the same or lower than this sewage treatment
plant, so the prediction can be analyzed as a reference for the other 2 plants.
According to the prediction of pollutant sources of NH3 and H2S in the previous
section, SCREEN estimation model, recommended by Technical Guidelines for
Environmental Impact Assessment Atmospheric Environment (HJ2.2-2008), is adopted
to predict the sphere of influence of discharge concentration. Point source and point
source prediction results are shown in Table 5.2-3 and 5.2-4.
Table 5.2-3 predictions under point source estimation model
Source 1: NH3 Source 2: H2S
Predict downwind concentrations of Ci1 (μg/m3) predict downwind concentrations of
Ci1 (μg/m3)
downwind Distance from the source center D (m)
Pollution Source 1: NH3 Pollution Source 2: H2SPredicted concentration downwind Ci1(μg/ m3)
Predicted concentration downwind Ci1(μg/ m3)
10 0.2688E-17 0.1792E-18100 0.07 0.005200 0.09 0.006300 0.10 0.007500 0.08 0.006
1000 0.05 0.0041500 0.06 0.0042000 0.05 0.003Table 5.2-4 Predictions under Area Source estimation model
downwind Distance from the source center D (m)
Pollution Source 1: NH3 Pollution Source 2: H2SPredicted concentration downwind Ci1(μg/m3)
Predicted concentration downwind Ci1(μg/m3)
10 1.143 0.114
100 11.37 1.137 200 10.54 1.054300 9.911 0.991500 9.266 0.926
1000 4.826 0.4821500 2.883 0.2882000 1.943 0.194
According to Table 5.2-3 and Table 5.2-4, the largest point source concentration
of NH3 and H2S is 0.10 × 10-3mg/m3 and 0.007 × 10-3mg/m3, accounting for 0.05%
and 0.07% of the maximum allowable emission of the harmful substances in “ health
standards Industrial Enterprises Design”(TJ36-1979 ). The largest area source
concentration of NH3 and H2S is 0.011g/m3 0.001mg/m3, accounting for 5.5% and
10% of the maximum allowable emission of harmful substances in atmosphere in "
health standards Industrial Enterprises Design " (TJ36-1979 ).
In Totalmary, the concentration of NH3 and H2S emissions of the sewage
treatment plants is low, thus have little influence on the surrounding atmosphere.
(2) Health protection distance
According to "Municipal Sewage Treatment Plant Pollutant Emission Standards"
(GB18918-2002), the new site (including reform, expansion) of urban Sewage
treatment plant should be consistent with the overall planning requirements of local
urban and rural construction. Green belt should be built around urban sewage
treatment plants, and certain protective distance should be kept, the size of which is
determined by the environmental impact assessment.
The evaluation is to calculate the Health Protection distance based on the example
of sewage treatment plant in Urat Front Banner. The scale of pollution Source of the
other two plants is the same, so the health protection distance is applied accordingly.
The calculation method, which is about unorganized harmful gas emissions of health
protection distance given in" local technical methods of air pollutant emission
standards (GB/T3840-91) ", is adopted, and it is as follows:
The meaning of symbols and units are shown in Table 5.2-5.
Table 5.2-5 List of symbols
NO Symbol Meaning Unit1 Qc control level of non-organization emissions standards kg/h2 Cm Standard concentration limits mg/Nm3
3 LRequired Health Protection distance of industrial
enterprisesm
4 R Equivalent radius of emission sources in production unit m5 A 、B、C、D Calculation parameters of Health Protection distance
Table 5.2-6 List of source concentration parameter
NH3 H2SQc 0.15kg/h 3.39×10-3kg/hCm 0.20mg/Nm3 0.01mg/Nm3
L 15 35S 800
A 、B、C、D A=350、B=0.021、C=1.85、D=0.84According to the prediction, health protection distance of NH3 and H2S is
calculated as 15m and 35m. According to the relevant provisions of technical methods
of development of local air pollution emission standard (GB/T3840-91), health
protection distance of the sewage treatment plant is 50m.
All the sewage treatment plant sites selected in the project are 500m away from
residents, so the impact of the project on the surrounding residents is within the
permission of the state. According to forecasts and integrated analysis of analog, the
project has little effect on the regional air environment and will not have a significant
impact on the neighborhood.
5.2.2.2 Water environment impact analysis
(1) Surface water environment impact analysis
The water process link of various sewage treatment and recycled water is water
sedimentation, sludge thickening, filter backwash water and cleaning life water and
water for equipment. The wastewater of this part goes from the sewage pipes in the
plant and then will be collected and processed in the sewage treatment without
discharging and have no impact on surface water.
In addition, the scale of sewage treatment and water recycling project in
Ganqimaodu Port processing park is 30,000 m3 / d, the scale of renewable water
treatment is 2.4 m3/ d, and the remaining 6,000 m3 / d water discharge into the main
channel as a landscape of water; Urat Front Banner sewage treatment and reuse of the
wastewater capacity is 30,000 m3 / d, and the scale of renewable water treatment is 2
m3 / d, and the remaining 10,000 m3/ d water discharge into the fourth channel as a
landscape. The above two sewage treatment plants is implemented according to
standard A of "Municipal Sewage Treatment Plant Pollutant Emission Standards," and
also meet the need of landscape water requirements. It will not be drained totally and
has little impact on the water quality of the fourth channel. The treated wastewater of
Urat Rear Banner Processing Park goes into sewage treatment plants of Urat Rear
Banner to be recycled without discharging.
Meanwhile, due to the sewage treatment and the construction project of
regenerated water cycling, it enhances the industrial wastewater treatment, increases
water reuse rate, reduce pollutants load from processing parks effectively and
decrease the quantity of pollutant discharged into rivers and benefit water quality
improvement in the project area. After the project of wastewater treatment and
recycling is completed, according to sewage treatment capacity of 80,000 m3/ d, reuse
water of 64 000 t / d, it can save water 22.63 million m3/ a, reduce water pollutants
CODcr 14271t / a, BOD8694t / a, ammonia 697t / a. It is of great importance to
reduce regional water pollutants discharge load. In Totalmary, after the project of the
sewage treatment and reclaimed water reuse project is completed and operated, it can
effectively reduce the regional emissions, and can promote regional water
environment with little impact on surface water bodies.
(2) Analysis of groundwater environmental impact
After the completion and operation of sewage treatment plants, domestic sewage
and industrial sewage of all processing parks will be discharged into the sewage
treatment plant. The construction of pipe network collection and harmless treatment
of sewage reduces the bad effect of water infiltration on underground water pollution
in processing parks. Therefore, the implementation of the project has a positive
influence on regional groundwater environment. However, in the course of operation
of the project, strict measures should be taken to prevent leakage of sewage pipes and
sewage treatment facilities and avoid leachate into the groundwater in the course of
dumping sludge. Seepage coefficient is less than 10-7 cm / s, the sludge generated by
the project will be removed periodically, and sludge-dumping ground will be seepage
proofing to ensure the effective protection of groundwater sources.
5.2.2.3 Acoustic Environmental Impact Prediction and Analysis
(1) Prediction model
In accordance with HJ/T2.3-95 “environmental impact assessment technology
guidance Acoustic Environment”, the noise source is regarded as a state of semi-free
point source. It is tested in noise source coordinate system and floor plan to identify
noise sources position, forecast positions, the distance between forecast position and
sound source according to forecasts point. Equivalent sound level of sound pressure at
any point LeqdB (A) is calculated with accordance of air attenuation model of
acoustic energy in the environment.
1 the effect of single point sound source on predicted position, the mode of
calculation is as follows:
LA (r) = LA (r0)-20lg (r/r0)
The formula: LA (r) - sound level value from sound source r, dB (A);
LA (r0) - sound level value from reference position r0, dB (A);
r - distance between predicted point and sound source, m; distance between
reference position and sound source, 1m.
2 noise sound level of more than one sound source to a certain predicted position on
the T-time, the mode of calculation is as follows:
The formula: Leq (T) - the total sound level of predicted position, dB (A);
n - the number of outdoor sound source.
(2) Environmental noise prediction of sewage treatment plant
Judged from the distribution of noise source, noise source are all in the plant.
Blowers and all kinds of pumps are fixed in a separate device room, and the after the
room acoustic shielding, green noise and distance attenuation effects, noise made by
the equipment can be attenuated. Noise prediction results of various projects can be
seen in Table 5.2-7.
Table 5.2-7 Noise Prediction of Sewage Treatment Plant and surrounding Area
Project Measuring point Daytime Night
Noise at boundary Noise at boundary
Urat Urat Banner Processing Park (Huhe Township)Sewage treatment project
East boundary 53.4 53.4South boundary 54.2 54.2
West boundary 52.4 52.4North boundary 53.6 53.6
Ganqimaodu Port Processing Park(Delingshan Township)sewage treatment and recycling project
East boundary 52.7 52.7South boundary 53.4 53.4
West boundary 54.6 54.6North boundary 54.2 54.2
Urat Front Banner Processing Park (Xianfeng Township)sewage treatment recycling project
East boundary 52.8 52.8South boundary 53.4 53.4
West boundary 52.4 52.4North boundary 52.7 52.7
According to the above table, noise at plant boundary of the sewage treatment
plants confirm to three functional areas standard criteria of daytime and night: 65dB
(A ) and 55dB (A) provided by “Industrial enterprises plant boundary noise emission
standard” (GB12348-2008). Moreover, no people live within 500 meters around the
sewage treatment plants and there is little noise impact on the surrounding
environment.
5.2.2.4 Analysis of Solid Waste Environmental Impact
1) Impact of sludge dewatering process on the environment
Before dewatered, generally speaking, sludge should be concentrated.
Concentration tank often exudes stench, especially in the hot Totalmer months, there
are floating mud on the pool surface, and it is easy to infest mosquitoes.
When concentrated sludge is dewatered, the dewatering room will emit foul smell;
in case of spilling in the process of dewatering sludge, environment will be polluted.
2) Impact of sludge dumping on the environment
Dewatered sludge should be timely removed. The sludge, which cannot be
transported in time, should be put in temporary stacking areas. Dewatered sludge is
easy to turn into slurry with water, which is of good fluidity and wash away easily;
when it rains, water integrates with a large number of pollutants, polluting surface and
groundwater. Therefore, the dehydrated sludge can not be cluttered, but should be
treated with the impermeable layer of the temporary dumping place specially, and
then stamp rain-shelter; In addition, the dehydrated sludge is not completely stable,
long-term stacking will produce sludge anaerobic digestion. H2S odor produced by
such substances will affect air quality; dehydrated sludge stack place is the breeding
ground for mosquitoes, and have an undesirable effect on environmental health. For
these reasons, sludge should be removed after dewatering time to avoid piling up in
the factory.
3) Impact of sludge transportation on the environment
Although the sludge in the plant have been treated to various extend, the sludge
still has some harmful pollutants. The sludge of the project in various sewage
treatment plant is only concentrated and dehydrated and fail to meet the requirement
of sludge stabilization and harmless condition. The sludge contains large amounts of
perishable organic matter and coli, ascaris eggs and other pathogens microorganisms.
Therefore, transportation process of sludge is a very important environmental issue.
At present, the main transportation of sludge is trucks. If the sludge hangs on the
body and wheels of trucks in the handling process, or the vehicles are poor sealed, the
trucks will spill sludge around sewage treatment plant and along the road, which
cause pollution along the road. Muddy water flowing and malodorous spreading
should be prevented in the process of sludge transportation. Sewage Treatment Plant
should use special closed vehicles to prevent water leakage, mud leakage and
scattering. Meanwhile, the sludge transportation time should be strictly controlled,
trying to avoid heavy traffic times. In short, the sludge transportation is a very
important problem to be taken seriously.
4) Sludge treatment program of sewage treatment plant
Sludge is the product of the sewage process and it is an important component of
the sewage treatment. Sludge treatment aims to decrease the sludge moisture content
and sludge volume to stabilize its nature and then create conditions for further
disposal and comprehensive utilization. The general process includes “concentration -
Dehydration –Disposal” or “concentration- digestion - Dehydration – Disposal”.
According to feasibility study report, due to biological nutrient removal
technology adopted by the sewage treatment, sludge age is a little longer and the
sludge is relatively stable, so there is no need to carry out nitrification. In the case of
nitrification, a digestion pool, heating, stirring and a series of gas treatment and
utilization structures and equipment are needed while investment increases. However,
land area in the sewage treatment park is limited, so sludge nitrification system cannot
be built.
According to analog data, sludge components of the sewage treatment plant
relate with water quality of sewage. Generally, excess sludge of industrial waste water
in sewage treatment plant contain high amount of heavy metals, far beyond the
agricultural sludge standard, therefore it should be safely landfill ed instead of being
used as agricultural fertilizer.
5) Disposal of bar screen material and sediment
Bar screen material and sediment in grit chamber are rubbish of the sewage
treatment plant, and they should be properly collected, stored, and shipped. They are
suggested to be transported to the reuse landfill together with domestic garbage.
Specific stacking, packaging, and transportation process should be strictly enforced in
accordance with relevant provisions. Although its output is not large, it will be
harmful to the environment if it is neglected. Light plastic bags and other packaging
waste will scatter by the wind to the wastewater treatment plant; sediment or scum
should be removed promptly, otherwise it will smell bad, and breed mosquitoes and
odor.
6) Impact of domestic garbage on the environment
The proposed sewage treatment plant produce less domestic garbage, so it can be
cleared and transported with bar screen material and grit chamber sediment with no
need to treat separately. However, clearance and transport must be done timely or
garbage-piling stacking will become mosquito breeding grounds and have adverse
effects on plant sanitation. In the process of clearance and transportation, strict health
and safety procedures should be taken to avoid spilling along the road and releasing
into the atmosphere, causing environmental pollution.
5.2.2.5 Ecological environmental impact analysis
(1) Land use and soil restoration
Since the original crops, natural vegetation are replaced by various types of
buildings, roads, green belt and other land. The function of land-use changes greatly.
After completion of the project, discarded soil can be reused to build green belt of the
plant. At the same time, ground hardening and green belt building can hold the soil,
reduce soil erosion; and it can also be used to cover soil in reuse landfill.
(2) Vegetation cover
After completion, the plant’s green area with trees on both sides of the road, the
total green vegetation coverage rate will be higher than before. It keeps soil and water
as well as beautifies the environment. The greening rates of all projects are seen in
Table 5.2-8.
Table 5.2-8 Green rates of the projects
NO. ProjectPlant area
(m2)Green
coverage
(m2)Green rate
(%)1
Ganqimaodu Port Processing Park(Delingshan
Township)sewage treatment and recycling project111000 53125.6 47
2Urat Rear Banner Processing park (Huhe Township)
Sewage treatment project70000 39074.5 55
3Urat Front Banner Processing Park (Xianfeng
Township)sewage treatment recycling project111000 53380 46
(3) Landscape Ecological Analysis
Before project construction, landscape patterns are simple, the degree of
connectivity is poor, and the degree of heterogeneity is low. After completion of the
project, there are various types of buildings, roads, green belt, and other kinds of
combination. As there are more tree species, species diversity increased,
correspondingly landscape heterogeneity increases. However, trees introduced by
manual work require a certain process of selection and adaptation to the environment.
When the project has just completed, the variability of trees is large and anti-
interference ability is poor, but all of these will greatly improve over time.
5.2.3 Wuliangsu Lake Lake Administration Project The project is non-polluting eco-projects. There is non-permanent structures
existing and operating during the project operation period. Environmental impact of
project operation is mainly reflected in Wuliangsu Lake Lake flow and improvement
of water quality.
5.2.3.1 Wuliangsu Lake biological transition zone manmade wetland project
1) Impact on Atmospheric Environment
The proposed project emissions are mainly produced by microbial
decomposition of CO2, as well as stench of decaying animal and plant and other
microbial life. The quantity is small, and the concentration produced can reach the
maximum allowable concentration of secondary standards given by “municipal
wastewater treatment plant emission standards” (GB18918-2002) factory sector.
2) Noise
Noise generated by the project is mainly from mechanical noise made by
pumping equipment. Source intensity noise value is about 80dB (A). By status
monitoring and predicting (predicting model: use HJ/T2.4-1995 “Environmental
Impact Assessment Technical Guide: sound environment” indoor point source model
and outdoor plane source model are recommended), Sound Pressure Level prediction
of different distance pumping equipment is shown in table 5.2-9
Table 5.2-9 List of sound pressure level projections at different distance of running pumping
equipment
Distance (m) 100 200 300 400 500 600 700 800 9001000
1050
Noise value dB (A) 66.7
61.3
58.3
56.3
54.853.6
52.6
51.7
50.9
50.3 50
As it can be seen from Table 5.2-9, due to using pump in operating period, noise
value is high, the impact is strong, and some has long duration and accompanied by a
strong shock. Since the core construction area is 5-10 km from the nature reserve area,
it will not affect birds nesting, foraging, courtship and incubation of birds of national-
level protection.
3) Impact on water environment
(1) Changes in the local water cycle
After the completion of the proposed project, wetlands treatment system will
have certain impact on groundwater environment, water balance is seen in the
following table 5.2-1.
降水 rainfall, 蒸发 evaporation, 地表进入 surface access, 排出 discharge, 土壤 soil,
渗透 infiltrating, 地下水 groundwater, 单位:万m3/a unit: ten thousand m3/a
5.2-1 Wuliangsu Lake water balance
According to the soil permeability, the annual infiltration of water of the
proposed project is 1.518 million m3, which is a supplement of groundwater. The
raising of water level may cause groundwater level rise of surrounding farmland,
while infiltration and penetration will lead to soil salinization, affecting the normal
cultivation of farmland, so outside of wetland reed field is treated by vertically
burying plastic technology to prevent leakage.
(2) in-lake water quality improvement
Wuliangsu Lake biological transition zone manmade wetland project removal
rate condition is shown in Table 5.2-10. As ice is not stable, microbial effect is weak,
and removal efficiency will be greatly reduced, but it reduces pollution load of ice to a
certain extent, and it plays an important role in cutting down the total pollution into
the lake. After the project’s completion, the trend of serious pollution of Wuliangsu
Lake will be initially halted, and quality of water flowing back into Yellow River from
Wuliangsu Lake Lake will be greatly improved.
Table 5.2-10 biological transition zone manmade wetland pollutant removal rate
Wetland programNon-frozen season(%) Frozen season(%)
CODCr TN TP CODCr TN TP
General Drainage Canal 78 70 83 30 15 10
Drainage Canal 8 71 65 76 - - -Drainage Canal 9 75 70 80 - - -
Inlet load of General Drainage Canal, Drainage Canal 8, Drainage Canal 9 and
predicted reductions of biological transition zone after treatment is shown in Table
5.2-11-Table 5.2-13. Data of General Drainage Canal come from May 2008 ~ April
2009. Due to lack of information of Drainage Canal 8 and Drainage Canal 9, averaged
data in July 2008, November 2008 and March 2009 are used and water outlet data are
taken the average value from 1988 to 2008.
Table 5.2-11 Pollutants Reduction situation of General drainage after artificial wetland sewage treatment
TimeInlet load (t) Outlet water reduction(t)
CODCr TN TP CODCr TN TP08/5 2283.50 513.79 64.70 1141.75 456.7 60.89
08/6 1286.72 168.26 36.13 296.94 94.03 31.1808/7 3268.51 212.71 25.42 1712.08 134.89 20.2308/8 2813.38 148.34 11.77 1278.81 71.61 6.6508/9 2027.64 279.22 33.24 33.24 179.50 26.59
08/10 539.56 31.58 4.08 144.76 11.84 2.7608/11 4159.31 380.28 39.22 594.19 202.02 27.3308/12 2881.89 411.46 80.63 864.57 61.72 8.0609/1 1910.58 297.66 62.30 573.17 44.65 6.2309/2 1670.00 381.39 79.55 501.00 57.21 7.9609/3 2047.38 484.28 65.75 614.21 72.64 6.5809/4 1959.28 353.47 27.01 587.78 53.02 2.70Total 26847.75 3662.45 529.79 8342.50 1439.84 207.17
Table 5.2-12 Pollutants Reduction situation of Drainage Canal 8 and Drainage Canal 9 after artificial wetland sewage treatment
Drainage Inlet load t/a Outlet water reduction t/a
CODCr TN TP CODCr TN TPDrainage Canal 8
2283.50
513.79
64.70
1141.75
456.7
60.89
Drainage Canal 9
1286.72
168.26
36.13
296.9494.
0331.
18According to data in the table, it is expected to bring CODCr, TN, TP of about
29102.42 t / a, 3816.8 t/a and 541.92 t/a by annual draining of water, and after
biological transition zone-manmade wetland treatment it can be cut down to about
9781.19 t/a, 1990.57t/a and 299.24 t /a respectively. It can be seen from data in the
table, as Drainage Canal 8 and Drainage Canal 9 have small amount of water quantity
as well as small pollutant concentration, the main pollutant reduction pressure lies on
the General Drainage wetlands.
After wetland ecotone is completed, water quality of non-frozen season can
reach Grade standard (on average) of national “Surface Water EnvironmentalⅣ
Quality Standard GB3838-2002” predicted by the model, that is, the concentration of
pollutants in water status can be reduced to CODCr 30mg / l, TP 1.5mg / l and TP
0.1mg / l.
4) Biological diversity
After construction, improvement of water quality in Wuliangsu Lake makes
water body clear. Phytoplankton, zooplankton, and benthic fauna, which tend to live
freely in clear water, are likely to increase, changing from dirt resistance type to clear
water type. Changes of plankton have an influence on population structure and
distribution of fish bait, shifting from a single type (crucian) to multi-species
succession. The increasing quantity of fish, which favor to live in clear water and feed
on phytoplankton, brings out positive development of Wuliangsu Lake aquatic
ecosystems and ecosystem stability in the region. Structural changes of fish stocks
and increasing quantity lead to population change of birds, which feed on fish. It is
favorable to promote birds’ reproduction and feeding in nature reserves, enriching
biodiversity of Wuliangsu Lake.
5.2.3.2 Wuliangsu Lake Grid waterway project
1) Improvement of flow field in Wuliangsu Lake
Simulation analysis adopts one-dimensional river model (MIKE11) two-
dimensional lake model (MIKE21) and one-dimensional and two-dimensional
coupled hydrodynamic and water quality model (MIKE FLOOD) developed by
Danish Hydraulic Institute.
Simulation analysis of flow and lake water quality adopts two-dimensional
hydrodynamic model MIKE21 and sea waterways grid design adopts MIKE FLOOD.
Wuliangsu Lake flow field change before and after construction is shown in Figure
5.2-2.
(a)no canal design; (b) drainage canal design; (c) drainage canal + branch canal
design
Figure 5.2-2 Lakes flow field simulation results (no wind in Totalmer)
(1) It can be seen from the simulation graph: compared with the current flow field
situation, implementation of the project improves flow field of the reservoir area
obviously. Stagnant water areas of East Beach and other large areas of water are
eliminated. In the case of no wind, stagnant water area is reduced by about 30-40 km2;
(2) Flow rate of southern main Lake District increases slightly after implementation
of the canal dredging extension. It has a little effect on flow condition of northern and
western lake. overall improvement of the lake is limited;
(3) In reed field of Lake District, the mainstream flow field becomes more smooth
and overall flow pattern of the Lake improves greatly, as channels are connected,
main canal and branch canal are excavated, and water stagnation area is reduced by
more than 10 km2.
2) Effect of grid waterway project on improvement of water quality of Wuliangsu
Lake
Wetland water quality concentration of inlet and outlet in non-frozen season and
frozen season is shown in Table 5.2-14. The simulation pictures of 5.2-3 and 5.2-4
show water quality of two seasons.
Table 5.2-14 water quality concentration of inlet and outlet: Wetland project
Drainag
e
Non-frozen season Frozen season
CODCr TN TP CODCr TN TP
inlet outlet inlet outlet inlet outlet inlet outlet Inlet outlet inlet outlet
General
Drainag
e
Wetland
44.4 10 4.78 1.5 0.60 0.1 134.9 87 26.1 20 4.2 3.0
Drainag
e Canal
8
Wetland
36 10 2.3 1.5 0.22 0.1 - - - - - -
Drainag
e Canal
9
Wetland
35.1 10 2.4 1.5 0.31 0.1 - - - - - -
Table 5.2-3 Prediction of water quality of Non-frozen season
Table 5.2-4 Prediction of water quality of frozen season
Table 5.2-15 Statistical analysis of prediction of CODcr, TN and TP in lake
Index
CODCr TN TP
Status quo
simulationStatus quo
simulationStatus quo
simulation
Frozen season
Water area above Grade IV(km2) / / / / 57.3 109.2
Water area Grade / 113.0 / 38.9 25.4 21.5
IV(km2)Water area Grade
V(km2) 51.4 62.3 42.0 28.6 58.2 37.0
Water area below Grade V(km2) 195.5 70.1 204.9 179.6 48.6 27.6
Non-frozen season
Water area above Grade IV(km2) / 27.0 / / 57.4 50.8
Water area Grade IV(km2) / 97.1 / / 15.5 121.7
Water area Grade (km2) 13.6 127.1 / 119.5 58.8 101.3
Water area below Grade V(km2) 238.3 / 251.9 132.1 56.4 29.1
From prediction of lake water quality, the following conclusion can be made. (Table
5.2-15):
(1) Compared with status quo program, COD concentration in the lake greatly
improves. Water area of Inferior Grade V decreases by about 121 km2 in frozen season.
COD concentration greatly reduces in non-frozen season. Inferior Grade V area is
basically eliminated in the whole lake water. Water area of Grade V is 100-128 km2,
water area of Grade IV is 86-97 km2, and water area of Grade III is 26-39 km2.
(2) Compared with status quo program, TN of the lake improves. In frozen season,
water area of inferior Grade V decreases by about 25-41 km2, and water area of Grade
IV increases by 28-49 km2. In non-freezing season, TN is significantly improved while
water area of inferior Grade V decreases by 101-121 km2.
(3) Compared with status quo program, TP of the lake improves, and in frozen
season water area of above Class III increases by 18-54 km2. In non-frozen season, TP
improves significantly; water area of below Grade V is eliminated in the whole lake,
and water area of above Class III increases by 90-110 km2.
Table 5.2-16 Programs of outlet water quality prediction
Programnon-frozen season COD non-frozen season TN non-frozen season TP
Concentration Grade Concentration Grade Concentration Grade
(mg/L) (mg/L) (mg/L)Status quo0
39.73 Grade V 2.78Inferior Grade
V0.021 Grade II
Program 2-2
31.77 Grade V 1.93 Grade V 0.013 Grade II
Program
Frozen season COD Frozen season TN Frozen season TP
Concentration (mg/L) Grade
Concentration (mg/L) Grade
Concentration (mg/L) Grade
Status quo 0
35.68 Grade V 1.64 Grade V 0.007 Grade I
Program 2-2
23.15 Grade IV 1.21 Grade IV 0.004 Grade I
The followings can be known from water quality prediction results:
(1) Compared with the status quo, in non-frozen season, outlet COD concentration of
the program falls down to 31.77 mg / L with a decrease of 7.96 mg / L, and is equal to
Grade V of water quality. In frozen season, it falls down 12.53 mg / L, and the overall
water quality improves and reaches Grade IV of water quality stably.
(2) Compared with the status quo, in non-frozen season, TN concentration of water
outlet of the program falls by 0.85 mg / L, maintaining Grade V of water quality, and
the overall of water quality improves a grade. In frozen season, it declines about 0.43
mg / L and reaches Grade IV of water quality stably.
(3) Compared with the status quo, in non-frozen season, water outlet TP
concentration of the program falls 8 ug / L, maintaining Grade II of water quality, and
water quality improves. In frozen season it falls down 3 ug / L, remaining Grade I of
water quality;
3) Ecological landscape pattern analysis of Lake District channel system
Landscape spatial pattern is arrangement of landscape patches of different sizes and
shapes in space, and it is an important manifestation of landscape heterogeneity.
Meanwhile it is also the result of a variety of ecological processes at different scales.
Landscape spatial pattern analysis of wetland landscape is significant to the wetland
landscape study of spreading species, flowing energy and transporting material.
Based on latest topography data of Wuliangsu Lake(2009), supported by GIS spatial
analysis function, we analyze landscape pattern status of Wuliangsu Lake, landscape
change after channel excavation and its ecological impacts. Since the excavation of
Wuliangsu Lake waterways (especially the newly added waterway) may interfere with
Wuliangsu Lake landscape pattern, and then may lead to a series of ecological
problems. Therefore, focus should be placed on landscape pattern changes before and
after channel excavation.
(1) Technical methods
According to the latest topographic maps of Wuliangsu Lake, landscape distribution
vector diagram is got by coordinate registering, digitization in mapinfo 7.5, as is shown
in Figure 5.2-5. By using geographic information system software Arcgis 9.0, vector
files are analyzed in term of topology and spatial database of various landscape types
and its associated attribute database are generated. All polygons corresponding with
landscape type are assigned certain property values, generating basic database, which is
needed to meet the characteristic indicators for calculation. Based on Arcgis 9.0
platform, the Spatial Analysis extension transforms vector diagram into raster charts,
and then it uses analysis software Fragstats3.3 of landscape pattern to compute the
landscape metrics.
Left: before excavation; right: after excavation
Table 5.2-5 Lake district landscape pattern chart of Wuliangsu Lake
(2) Ecological landscape pattern analysis of channel excavation
① Landscape analysis of type
Calculated by Fragstats software, the main types of landscape indices (class
metrics) (Table 5.2-17) are obtained. Analysis of the landscape index shows that:
I. Reed land and open water, two types of landscape, take up 54.9% and 45.1%
respectively. After channel excavation, open water will increase by 0.7%, while reed
land will decrease slightly.
.After waterway excavation, some waterways will be split by reed land, and theⅡ
number of reed land plaque will increase to 40 from the present 25 and the maximum
plaque index will drop from 7 to 5.8; the open water connects through watercourse, and
the number of plaques reduces significantly, and the largest patch index rise to 45.8
from 45.1. It is beneficial to maintain the integrity of the ecosystem and reduce swamp
formation due to expansion of the reed.
III. Through the newly added branch waterways, both numbers of Total Edges and
Edge Density of reed land and open water landscape have significantly increased,
indicating the effect increased obviously. It is beneficial to material exchange, energy
flow, purifying the entire water in Lake District, and increase habitat diversity in
Wuliangsu Lake.
IV. Landscape shape index refers to shape index of perimeter and reflects the
complexity of patch boundaries. After channel excavation, two types of landscape
shape index and average fractal dimension increases significantly, especially the status
quo value of 3.45, the average fractal dimension value of open water, will raise to 7.7,
increasing the acting surface and acting time of lake and reed land. It is favorable to
help water purification.
V. Plaques contiguity index (contiguity index), clumpy index (CLUMPY), plaque
cohesion degree (COHESION), division (DIVISION), and degree of polymerization
(AI) calculations show that the two kinds of reed land and open water landscape have
high degree of connection and low degree of fragmentation. Compared with the status
quo landscape pattern, landscape indices after waterway excavation will not change
significantly. It is indicated that although waterway excavation splits part of the reed
land, the internal space pattern of two types of landscape does not change greatly.
Table 5.2-17 landscape index of type
Type index
Reed land Open water
Status quo
After excavatio
n
Status quo
After excavatio
nPercentage of landscape /(%)(PLAND) 54.9 54.2 45.1 45.8
Number of plaque(NP) 25 40 8 3Plaque Density (PD) 0.18 0.29 0.07 0.03
Largest Plaque index (LPI) 7 5.8 45.1 45.8
Total Edges(TE) 46.3 53.7 32.8 40.2
Edge Density(ED) 0.33 0.38 0.29 0.35
Landscape Shape Index(LSI) 9.47 11.1 7.39 9.0
Fractal number(FRAC_MN ) 0.53 0.7 3.45 7.7Area weighted mean plaque shape index (SHAPE-
AM(SHAPE-AM) 1.97 1.80 1.79 3.67
Plaque contiguity index(contiguity index) 0.83 0.89 0.29 0.473 Pattern analysis of landscape standard
Analyze landscape pattern change of Wuliangsu Lake before and after excavation
from the view of landscape standard. Landscape index can be seen in Table 5.2-18, and
the analysis shows:
I. The number of landscape plaque of status quo is 33, and the number of plaques
increases to 43 after excavation, which mainly results in waterways’ splitting of reed
land. Accordingly plaque density rises from 0.13 / km2 to 0.17 / km2. Compared with
other lakes of the similar area, the plaque density is higher. The number of total
landscape edge rises from the current 47.8 to 55.5, which is beneficial to internal
exchange of landscape material and energy flow. The increase of plaque number and
edge number may have a negative effect on spatial distribution of reed. However, it is
significant to slow down the swamp formation trend.
. Sea district landscape shape index after waterway excavation was 8.41, which isⅡ
significantly higher than the status quo of 7.25. It indicates that landscape complexity
has increased significantly after excavation and it is beneficial to help increase habitat
diversity.
III. Perimeter area of the score dimension is another measure of landscape shape
index, and it mainly analyzes plaque type and the entire landscape fragmentation before
and after channel excavation. Perimeter fractional landscape area of the score
dimension (PAFRAC) is small, indicating landscape fragmentation of the entire sea
area is of a low degree, and the overall integrity of the landscape will not be affected
deeply.
IV. Contag (CONTAG) and division (DIVISION) are used to characterize the
degree of landscape fragmentation. Contag (CONTAG) of more than 50% shows a low
degree of fragmentation and more large plaques; division (DIVISION) value is low and
it shows that the distance between plaques is short. Currently landscape cantag of
Wuliangsu Lake is more than 66% and division is 0.77. It indicates that sea district
landscape type is relatively gathered and it has good connectivity and the degree of
overall landscape fragmentation is relatively low. After channel excavation, landscape
cantag will only decreased from 66.6% to 66.2%, and it will not affect the overall
landscape greatly.
V. From the aspect of landscape diversity, landscape before and after the
watercourse excavation has no significant difference, Shannon diversity index is 0.98-
0.99, Simpson evenness index is 0.99, and it indicates high uniformity of landscape
before and after excavation. However, landscape diversity is low. Largest plaque index
increases slightly because the watercourse connects with the isolated watercourse.
Table 5.2-18 Landscape index of landscape standard
Landscape index Status quoAdded
watercourse
Total Area /( km2) (TA) 254 254
Number of Plaque(NP) 33 43
Plaque Density(PD) 0.13 0.17
Largest Plaque Index(LPI) 45.1 45.8
Total Edges(TE) 47.8 55.5
Edges Density(ED) 0.19 0.22
Landscape Shape Index (LSI) 7.25 8.41
Shape Mean Number(SHAPE_MN) 1.93 1.93
Landscape Cohesion Index(COHESION) 99.90 99.90
Contag(CONTAG)% 66.6 66.2
Division(DIVISION) 0.77 0.77
AI(AI) 99.4 99.2
Shannon Diversity Index(SHDI) 0.98 0.99
Simpson IEI(SIEI) 0.99 0.99(3) Impact of waterway system on ecological landscape pattern of Wuliangsu Lake
Fragstats (analysis particle size is 10 m) analyzes landscape type and index of
landscape standard of ecological landscape systems in Wuliangsu Lake, and it makes
analysis and evaluation of Wuliangsu Lake landscape from a quantitative and macro
point of view. The results shows:
Open water area increases after channel excavation, forms habitat landscape type①
with open water and narrow channels to meet the habitat choice of different groups of
waterfowl.
② Although part of reed land is segmented by channel excavation, the number of
plaques and edges increased significantly, landscape spatial pattern in Wuliangsu Lake
(aggregation, connectivity, etc.) has not changed greatly, and it will not increase the
degree of landscape fragmentation significantly.
4 After waterway excavation, the acting surface of reed land and open water surface
increases significantly, which is beneficial to internal exchange of landscape
material and energy flow in Wuliangsu Lake. It is also favorable to help water
purification and increase biodiversity.
5 New added branch channel will split the local landscape. The increasing plaque
density and edge density have a negative impact on the spatial expansion of reed,
but it will help retard swamp formation of sea area.
5.2.4 Analysis of the sewage treatment plant and recycling plant after
completion
1) The quantity of inlet water in recycling plant
Water Environment Improvement Project of Bayannur City includes sewage treatment
plant and recycling water plant project. Among them, all outlet water of sewage
treatment plant will be recycled, with no water discharging into the drain. Water
recycling plant intakes water from general drainage canal, drainage canal 3 and
drainage canal 7, and water of drainage canal 3 and drainage canal 7 eventually flows
into general drainage canal. Table 5.2-19 shows monthly quantity of water of recycling
plant from general drainage canal, drainage canal 3 and drainage canal 7.
Table 5.2-19 Monthly quantity of water of recycling plant from general drainage canal,
drainage canal 3 and drainage canal 7(ten thousand m3)Month 1 2 3 4 5 6 7 8 9 10 11 12 Total
Urat Rear Banner Processing Park water
recycling & supply project
18.2
13.4 18.2 15.874.4
7274.4
74.4
7274.4
7218.2
451
Ganqimaodu port Processing Park water recycling & supply project
193.8
181.3
193.8
187.5
193.8
187.5
193.8
187.5
187.5
193.8
187.5
193.8
1900.3
Drainage canal 3 water supply project
- - - 6365.1
6365.1
65.1
6365.1
63 - 384.3
Drainage canal 7 water supply project
- - - 61.459.4
61.4
61.4
59.4
61.4
59.4
61.4
- 364.4
Total 212.
0194.
7212.
0327.
7392.7
383.9
394.7
386.4
383.9
392.7
383.9
212.0
3100
2) Change of inlet water quantity after the completion of water recycling plant
(1) Final drainage amount of general drainage canal
Water recycling plant intakes water from general drainage canal, drainage canal 3 and
drainage canal 7, and water of drainage canal 3 and drainage canal 7 eventually flows
into general drainage canal. Therefore, water quantity of water recycling plant
subtracted from general drainage canal is eventually water quantity flowing into
Wuliangsu Lake, as is shown in Figure 5.2-6. The water quantity is the total monthly
amount of inlet water of manmade wetland with February as the month of the smallest
amount of water of 4.892 million m3 and November as the month of the largest amount
of water of 71.699 million m3. As is shown in Figure 5.2-7, after completion of water
recycling plant, change rate of water draining into the Wuliangsu Lake is 4.7% -29.4%
with January, February, March and April as the high water change months,
respectively, 23.5%, 29.4%, 23.0% and 28.6%. It is mainly because these months fall
on dry season with small amount of total drainage, while inlet water quantity of water
recycling plant is stable. There is little change in other months.
Figure 5.2-6 monthly change of the total amount of water draining into Wuliangsu Lake
before and after completion of water recycling plant
(in the figure monthly mean quantity in 1996-2005 is given before the completion of
water recycling plant )
0
1000
2000
3000
4000
5000
6000
7000
8000
1 2 3 4 5 6 7 8 9 10 11 12Month
Before the completion of water recycling plant
After the completion of water recycling plant
Wat
er
qua
ntit
y cha
nge
rate ( % )
Wat
er q
uant
ity (t
en th
ousa
nd m
3 )
Figure 5.2-7 monthly change of the total amount of water draining into Wuliangsu Lake
before and after completion of water recycling plant
3) Effect of water recycling plant construction on Wuliangsu Lake ecological water
demand
In Wuliangsu Lake irrigation drainage has been regarded as ecological water
supplement. until 2015 after the implementation of this project and taking water-saving
measures, it is temporarily considered that agricultural water drainage will decrease by
10% , and drainage quantity of general drainage canal, drainage canal 8 and drainage
canal 9 is 415 million m3 and 62 million m3 respectively. 31 million m3 of the total
drainage into the sewage has been recycled, and the water quantity of general drainage
canal, drainage canal 8 and drainage canal 9 back into Wuliangsu Lake is 446 million
m3.
Four water Canels (Tarbes Canal, Changji Canal, Tongji Canal and Yihe Canal)
inlet water from the Yellow River into Wuliangsu Lake in ice flood season, 44 million
m³ of water is supplement water, and unchanged drainage of Wuliangsu Lake into the
Yellow River is 154 million m3. Therefore, net water quantity into Wuliangsu Lake is
446 million m³. In order to maintain 515 million m³ of ecological water in Wuliangsu
Lake, 69 million m³ of water replenishment is needed from the four canals in ice flood
season. According to Hetao irrigation district of Yellow River and Inner Mongolia anti-
0
5
10
15
20
25
30
35
1 2 3 4 5 6 7 8 9 10 11 12
Month
ice flood emergency flood diversion and preliminary design of Wuliangsu Lake flood
diversion project, flood diversion volume is 161 million m3, of which Wuliangsu Lake
takes up 100 million m3, and drainage canal in Hetao irrigation district and natural
lakes in northern edge takes up 61 million m3. So flood diversion in ice flood season
can guarantee supplement water of Wuliangsu Lake; the design has been approved by
Water Resources Department of Inner Mongolia Autonomous Region ("approval of
preliminary design about anti-ice emergency in Hetao irrigation district of Yellow River
and Inner Mongolia and flood diversion of Wuliangsu Lake (internal water construction
and management〔2009〕No.170). During ice flood season four canal drainage does not
take indicators of inletting water from the Yellow River. It is taken as ecological water
supplement of Wuliangsu Lake, in accordance with relevant national and local
provisions.
5.2.5 Water environmental impact prediction and assessment of the
project’s implementation
5.2.5.1 Reduction amount of pollution load
Bayan nur water environment comprehensive management implementation
improves water discharged into Wuliangsu Lake greatly. In accordance with water
quality design requirements of the sewage treatment plants and water supply plants in
processing park, this project forecast the amount of after completion, and the results are
shown in Table 5.2-20:
Table 5.2-20 pollution load reduction forecast of sewage treatment plant and water recycling
plant
Project
Water
quantityInlet water quality(mg/L) Reduction quanity(t/year)
(ten
thousand
t/d)COD NH3-N TP BOD5 COD NH3-N TP BOD5
Water recycling and supply project of
Urat Rear Banner processing park2 20 0.3 0.3 15 146 2.19 2.19 109.5
Sewage treatment project of Urat Rear
Banner processing park(Huhe
Township)
2 300 25 3 150 2190 182.5 21.9 1095
Water recycling and supply project of
Ganqimaodu port Processing
Park(Huhe Township)
4 80 10 2 60 1168 146 29.2 876
Sewage treatment project of
Ganqimaodu port Processing
Park(Delingshan Township)
3 500 25 3 300 5475 273.75 32.85 3285
Sewage treatment project of Urat Front
Banner Processing Park(Xianfeng
Township)
3 300 25 3 150 3285 273.75 32.85 1642.5
Water recycling and supply project
Drainage canal 32 88 21 2.5 24 642.4 153.3 18.25 175.2
Water recycling and supply project
Drainage canal 32 122 26 3 24 890.6 189.8 21.9 175.2
Total amount of reduction 13797.0 1221.29 159.14 7358.4
Inlet water loads of general drainage, drainage 8, drainage 9 and predicted
reduction after wetland treatment through biological transition zone can be seen in
Table 5.2-21.
Table 5.2-21 Pollutant reduction situation after biological transition zone and manmade wetland
treatment of Wuliangsu Lake
Drainage Inlet load t/a Outlet water reduction t/a
CODCr TN TP CODCr TN TPGeneral drainage
26847.75 3662.45 529.79 8342.50 1439.84 207.17
Drainage 8 2283.50 513.79 64.70 1141.75 456.7 60.89Drainage 9 1286.72 168.26 36.13 296.94 94.03 31.18
Total 30417.97 4344.5 630.62 9781.19 1990.57 299.24
According to data in the table, reduction amount through biological transition zone and
manmade wetland treatment are CODcr 9781.19 t / a, TN 1990.57t / a, and TP 299.24t /
a. It can be seen from the data in the table that water quantity as well as pollutant
concentration of drainage eight and drainage nine is small, the pressure of pollutants
reduction mainly lies in the general drainage of wetland.
In Totalmary, after the project is completed, it is expected to cut down the total
pollution load of Wuliangsu Lake, that is, CODcr will be reduced to 23578.19t /a, and
TP 458.38t / a.
5.2.5.2 The prediction and analysis on the improvement of water quality in Ulansuhai
Nur Lake area
1)Simulation solutions
In order to survey the improvement of water quality in Ulansuhai Nur Lake area
by implementing the project by World Bank, a 2-year simulation has been conducted
for these two solutions set out in Table 5.2-22 based on the hydrodynamics and water
quality models set up by this project. During this simulation, the load variation of the
general drainage canal affecting the improved performances of water quality in
Ulansuhai Nur Lake area has just been taken into consideration due to less flow
discharge of the eighth and ninth drainage canals compared with that of the general
drainage canal. The solution II in Table 5.2-22 represents the waterexit load flowing
into the wetland from the general drainage canal in the wetland design program. And
the load in Solution I represents the inflow load from the general drainage canal in the
wetland design program plus the reduction amount of load from upper reach industrial
zones, which is used as the inflow load from the general drainage canal without the
project by World Bank, where the two solutions of the water amount from the general
drainage canal keep in line.
Table 5.2-22: Simulation solutions for the improved performance of the water quality in Ulansuhai
Nur Lake area
Month,
Year
Solution I, without inflow load from
the project by World Bank (t)Solution II, with inflow load from the
project by World Bank (t)Discharge from
general drainage
canal(ten thousand
m3)CODCr TN TP CODCr TN TP
May, 2008 3433.25 615.56 77.96 1141.75 57.09 3.81 4912.80
June, 2008 2436.47 270.03 49.39 989.78 74.23 4.95 4315.60
July, 2008 4418.26 314.48 38.68 1556.43 77.82 5.19 3726.50
Aug, 2008 3963.13 250.11 25.03 1534.57 76.73 5.12 2468.70
Sept, 2008 3177.39 380.99 46.50 1994.40 99.72 6.65 2199.80
Oct, 2008 1689.31 133.35 17.34 394.80 19.74 1.32 6161.00
Nov, 2008 5309.06 482.05 52.48 3565.12 178.26 11.89 6656.00
Dec, 2008 4031.64 513.23 93.89 2017.32 349.74 72.57 2290.10
Jan, 2009 3060.33 399.43 75.56 1337.41 253.01 56.07 965.90
Feb, 2009 2819.75 483.16 92.81 1169.00 324.18 71.59 691.80
March,
20093197.13 586.05 79.01 1433.17 411.64 59.17 913.90
April, 2009 3109.03 455.24 40.27 1371.50 300.45 24.31 1016.70
Note: the total reduction amount of the industrial zones is distributed into 12 months in equal proportion,
incorporating into the design inflow load of the wetland, which is used as the inflow load without the project by
World Bank.
The status in quo of the water quality in lake area refers to the monitoring data of
status in quo in Table 4.2-19, the status in quo of the water quality to simulate each
grid are acquired by the interpolation of surface divisions of Ulansuhai Nur Lake as
the initial value of the model simulation.
This simulation is the prediction conducted based on the information data learned
from the status in quo and the inflow data of the general drainage canal is configured
according to the monthly mean data from a thorough year from May, 2008 to April,
2009, and the acquired data for the general drainage canal is also monthly mean data
while the outflow configuration of Ulansuhai Nur Lake is conducted based on the
existing and simple information data. According to the status in quo, this simulation
predicts two kinds of solutions, simulates the relative variation of the water quality in
Ulansuhai Nur Lake, so as to survey the effects of the project by World Bank.
However, since the continued impact of the inflow of the pollutants load before May
2008 has not been taken into account, what has been simulated is the contrast of the
two solutions, which can’t stand for the true value, but basically reflect the effects of
the project by World Bank. The hydrodynamic conditions of the simulated lake area
are under the circumstance that the planned grid water channels exist.
2) Simulation results
The key to Ulansuhai Nur Lake is the issue of eutrophication and the monitoring data
of the existing NH3-N concentration indicates that the water quality basically exceeds
Grade V water. Therefore, the simulation results contrast of the two solutions will be
represented by NH3-N concentration for contrastive analysis. The ratio of the water
body area with different water quality accounting for the total lake area referred to
NH3-N concentration after various time periods is shown in Table5.2-23. The
distribution contrast of NH3-N concentration is shown in Fig 5.2-8-5.2-13.
The contrastive analysis on the results indicates that, generally, the implementation of
the project by World Bank will remarkably improve the water quality in Ulansuhai Nur
Lake and the water quality of the status in quo will be gradually turning to above Grade
IV water for the better, which will be faster that the solution without the project by
World Bank. With the time going by and the diffusion mobility of the pollutants, the
effects of Solution II will gradually be reflected; the simulation effects on 240 th day,
300th day and 36oth day indicate that (Table 5.2-23, Fig 5.2-11-5.2-13) the
implementation of the project by World Bank will have remarkable improved
performances to the water quality in Ulansuhai Nur Lake; the ratio of Grade Ⅴ water
accounting for the lake area will reach 0.231-0.283, lower than that of Solution I by
0.053-0.075;the ratio of Grade III water accounting for the lake area will reach 0.538-
0.573, higher than that of Solution I by 0.301-0.436. But because of the poor reduction
amount of pollution in Nov and Dec in 2008, the inflow pollution load is far mare than
that in Oct; and because of the poor hydrodynamic force conditions within the inflow
area of Solution II, the pollutants can’t rapidly diffuse, which, as a whole, results in the
NH3-N concentration within the inletting area of the lake of Solution II obviously on
the high side.
As stated previously, in order to increase the effects of the project, it is suggested in
this environment assessment that the construction of gird water channels at the outflow
port of the inflow wetland of the general drainage canal should be increased, namely at
the lower reach of inlet port from wetland into Ulansuhai Nur Lake and the northern
part of East Big Beach (the red ellipse area in Fig 5.2-14), so as to improve the
hydrodynamic force at the inlet port, meanwhile, to strengthen the pollution control in
Nov and Dec to take best advantage of the implementation effect of the project by
World Bank.
Table 5.2-23: The ratio of different water quality and water body area polluted by NH3-N accounting
for the lake area in two solutions after simulation of different time periods
NH3-N pollution 60 th day 120th day 180th day 240th day 300th day 360th day
Solution I
Grade I water 0 0 0 0 0 0
Grade II water 0.015 0.001 0 0 0.002 0.005
Grade III water 0.004 0.007 0 0 0.102 0.272
Grade IV water 0.004 0.005 0 0.102 0.589 0.387
Grade V water 0.977 0.986 1 0.898 0.306 0.336
Solution II
Grade I water 0 0 0 0 0 0
Grade II water 0.021 0.006 0.01 0.025 0.057 0.053
Grade III water 0.006 0.018 0.011 0.06 0.538 0.573
Grade IV water 0.005 0.013 0.012 0.54 0.175 0.09
Grade V water 0.968 0.963 0.967 0.374 0.231 0.283
Fig 5.2-8: Contrastive table of NH3-N concentration distribution on 60th day
NH3-N concentration distribution on60th day
NH3-N concentration distribution on 60th day
Without the project by World Bank
With the project by World Bank
Fig 5.2-9: Contrastive table of NH3-N concentration distribution on 120th day
NH3-N concentration distribution on 120th day
NH3-N concentration distribution on 120th day
Without the project by World Bank
With the project by World Bank
Fig 5.2-10: Contrastive table of NH3-N concentration distribution on 180th day
NH3-N concentration distribution on 180th day
NH3-N concentration distribution on 180th day
With the project by World Bank
Without the project by World Bank
Fig 5.2-11: Contrastive table of NH3-N concentration distribution on 240th day
NH3-N concentration distribution on 240th day NH3-N concentration
distribution on 240th day
With the project by World Bank
Without the project by World Bank
Fig 5.2-12: Contrastive table of NH3-N concentration distribution on 300th day
NH3-N concentration distribution on 300th day
NH3-N concentration distribution on 300th day
Without the project by World Bank
With the project by World Bank
Fig 5.2-12: Contrastive table of NH3-N concentration distribution on 360th day
NH3-N concentration distribution on 360th day
NH3-N concentration distribution on 360th day
Without the project by World Bank
With the project by World Bank
Fig 5.2-14: Sketch map of the suggested channel area to be added to based on the
planned channels to be constructed
Planned channelsOriginal channels
Water area
Reeds
Legend
The suggested channel area to be added to
5.3 Mitigation Measures
5.3.1 Mitigation Measures in Construction Period
5.3.1.1 Mitigation Measures for Environmental Air Contamination
Main atmospheric contaminants generated in construction period for this
project are malodor and dust.
(1)Control Measures for Malodor
Construction for the grid-like watercourse work of Wuliangsu Lake area will①
be done in dry season section by section. The excavated sediments and wastes
shall be transported to local landfill in time for harmless disposal.
If the excavated sediments and wastes can not be transported in time, to avoid②
the effects on the life quality of nearby residents, the sediments shall be loaded into
the straw bags for storing to reduce the release of dust and malodor.
The transporting of the sediments shall be closed to prevent them from③
scattering along the road for which will affect the image of the city.
Attention shall be paid to the personal protection of the construction staff as④
well as the inspection work and first aid.
(2)Control Measures for Dusts
Project management shall be strengthened and the construction being①
civilized. Loading and unloading for building materials shall be proper and gentle.
The soil adhered to the surface of vehicles shall be removed as much as possible
before they leaving from construction sites. When transport limes, aggregates,
cement, fly ash and others, transporting vehicles shall be covered with tarpaulin, for
which are very easy to generate dusts.
Dusts in construction sites and construction roads can be controlled by②
watering and cleaning. If only do the watering and then cleaning, the amount of dusts
can reduce 70 to 80%, while first do the cleaning and then watering, the efficiency of
dust control can reach 90%. Tests show that each day do the watering 4 to 5 times to
control the dusts in construction site, the dust contamination can be reduced from the
scope of 20 ~ 50m. One sprinkling truck shall be provided for each construction site.
In addition, lime, sand and others can not be stockpiled in the open as much as
possible. If these materials must be stockpiled in the open, watering shall be done for
these stockpiled materials to improve their surface water content for which can also
play a dust control effect.
The selected construction unit shall have a certain strength/qualification,③
which use commercialized plant-mixed cement and closed-transporting vehicles.
For temporary and scattered cement mixing sites, the selection of the site shall④
consider as far as possible away from the residential buildings.
The spoil shall be transported to the low-lying site appointed by the municipal⑤
administration department for filling disposal or to the landfill as soon as possible.
For the temporary used land, vegetation cover shall be restored to against soil⑥
erosion once the work is finished.
Dust contamination shall be controlled in construction period, for the residential
areas being distributed around each construction site of this project.
5.3.1.2 Mitigation Measures for Water Environmental Contamination
(1)A sedimentation tank shall be built by the construction unit in construction
period. With the tank, waste water, piling mud water and standing water and others
generated in construction can be discharged outside after precipitating and meeting
the requirements.
( 2) Simple living facilities built on construction sites mainly are temporary
canteens and temporary toilets. The waste water from the canteen shall be pretreated
by grease trap before combining with domestic sewage. All waste water shall be sent
into the nearby sewage treatment plant for treatment and discharging outside after
meeting the requirements. If there is no nearby sewage treatment facility, necessary
classification shall be done for the waste water generated from the project
construction and pipeline construction through the collecting pools, sand pools, drains
and other water treatment structures. And the nearby farmers can take them as
agricultural fertilizer.
(3)During construction, construction workers shall make use of the existing
living facilities near the construction site as much as possible. The contractor shall
take all necessary measures to prevent the untreated waste water directly flowing into
the existing drainage canals or other surface water bodies.
(4)The management of construction site shall be strengthened. The working
field and the stockpiling slope of the earthwork shall be keep tidy and in order, so that
the earth can be reduced to flow into the nearby rivers.
(5)To reduce the amount of generated waste water, materials loss, scattering
and overflowing shall be controlled as much as possible.
(6)Construction of gird-like watercourse for Wuliangsu Lake area shall select
a proper plan, so that the decline of water environmental quality for part of Wuliangsu
Lake area caused by the release of excavated contaminants can be minimized.
( 7 ) Construction materials such as cement, sand and lime shall be
concentrated for stockpiling. Note such material can be stockpiled near the rivers or
other water bodies, it is better that the stockpiling site is far away from the rivers with
some water against measures being taken. Scattered materials for the above during
transporting shall be cleaned in time, so that the materials can be avoided being
washed into the water bodies by rainwater. Environmental management shall be
strengthened. Note the oil leakage or waste oil dumping for construction machines or
construction vessels shall be avoided, for the oil can cause water pollution after
entering into water bodies. It is recommended that the leaked oil from construction
machines shall be received by some means.
( 8 ) All construction waste water is strictly forbidden to discharge into the
ground surface water body near the construction site without treatment.
5.3.1.3 Mitigation Measures for Noise Contamination
According to the acoustic environmental impact analysis of construction period,
we can see that noise from the construction site has a greater effect on surrounding
acoustic environment. Moreover, there are a lot of sensitive points being distributed
around each worksite. Therefore, corresponding noise control measures shall be taken
by construction units to minimize noise effects on the environment.
( 1 ) Strengthening project management and arranging construction schedule
properly
A scientific schedule shall be prepared with construction work time being
arranged properly and noise control regulations for the construction being observed
strictly. Note the high noise equipments shall not be applied intensively at the same
time as much as possible. The construction is not allowed from 11 pm to 6 am of the
next day, if the worksite is ≤ 200m to the residential areas. Furthermore, low noise
machines shall be considered in the selection of construction equipments and plans as
much as possible. Construction time for high noise equipments shall be arranged in
the day time and minimize their working time at night. For some of working sites, if
the construction must be done at night with the noise affect the environment of the
surrounding residents greatly, a permit shall be obtained from the local environmental
protection authorities in advance, and this permit shall be posted.
(2)Arranging the construction site properly
To avoid noise level for part of place being too high, the powered mechanical
equipments shall not be arranged in one place intensively.
Preparation work shall be well done before the concrete need continuous pouring
work. The running time for the mixer shall be minimized.
(3)Reducing equipment noise level
The selection of equipments shall consider low-noise equipments as much as①
possible, for example, use the hydraulic machines to replace the fuel oil one, and the
vibrator use the high-frequency type. Moreover, low noise construction methods shall
be considered as much as possible.
The noise for stationary machines and earth excavation & transporting②
equipments such as excavators and bulldozers can be reduced by exhaust silencer and
isolation of engine vibration components.
As the noise level for mechanical equipments can be increased due to the③
vibration of loose part or the damage of silencer, the maintenance of construction
equipments shall be strengthened in the construction, so that the increasing of noise
level caused by the poor performance can be avoided.
The idle equipments should be closed immediately, and transporting vehicles④
entering into the site should be slowed down and reduced the times of whistle
(4)Reducing man-made noise
The operation of equipments shall be in accordance with specification. And in①
the process of dismantling for baffles and supports, operational guideline shall be
observed to reduce the impact noise.
The use of whistle, bell and flute and others shall be minimized in work②
commanding, while modern equipments shall be applied.
(5)Establishing of temporary sound barrier
Around the high-noise equipment, a temporary cover shall be established. And
for the location being relatively fixed equipments, these equipments shall be put into
the shed as much as possible. Otherwise, a single sound barrier shall be established
properly for these equipments outside the shed.
(6)During construction, the noise level along the road will be increased for
the operation of transporting vehicles. Therefore, the management of transporting
vehicles shall be strengthened. The number of vehicles and traffic density on worksite
shall be minimized and the whistle for vehicles will be controlled. And the
commissioning for equipments shall be done in the day time.
Besides the above noise reduction measures for the construction site, good
relationship also have to be established with the peripheral units and residents. Before
the construction, the units and residents shall be informed in advance if their living
affected by the work. To seek a common understanding, the construction progress and
the noise reduction measures taken in the construction shall be reported to them.
Proper compensation shall be paid to some of units and residents if the construction
affects their living greatly. In addition, a telephone hotline shall be established for the
complaints from the affected residents, and the complaining information shall be
handled actively.
5.3.1.4 Mitigation Measures for Soil Erosion
During construction period, because the excavation amount for the ground
surface is very large with lots of spoil and serious damage to vegetation cover, proper
measures have to be taken for this situation. Otherwise, soil erosion will appear with a
several-fold increasing trend for the project site. Therefore, strict environmental
protection measures shall be taken to control the soil erosion effectively.
(1)The excavation work shall avoid rainy season as much as possible.
(2)The earthwork in the construction shall be done properly. Excavated earth
shall be used for backfilling of the construction site as much as possible. Besides for
backfilling, the spoil generated from pipe-laying and construction shall be sent to
other construction sites for filling and greening work soil or sending to the landfill.
( 3 ) Temporary stockpiling site shall select flat field. After the work, the
vegetation cover shall be restored as much as possible.
( 4 ) Project construction shall be done in phases and area by area. Do not
spread the work fully to shorten the single completion period, especially the pipe-
laying work. Measures shall be taken for the excavated exposed ground surface, and
the exposed time shall be minimized to reduce the soil erosion.
(5)To fully consider the effects of greening work on soil erosion control, it is
recommended that the construction of each work for individual structure shall be done
one by one if possible. To minimize the soil erosion, the greening work shall be done
based on worksite greening plans as soon as the work finished.
( 6 ) Stockpiling of the earthwork in construction sites shall be considered
properly. A certain distance shall be kept with the underground surface water body. To
reduce the effects of soil erosion on rivers and rainwater pipe network, the possibility
of the earth flowing into the river and drainage shall be minimized. Around the sand
and gravel stockyard, straw bags shall be piled up to keep the sand. And around the
stockyard, simple drain ditch shall be excavated for the water discharge.
5.3.1.5 Mitigation Measures for Solid Waste Contamination
The wastes include the wastes generated from the construction, the garbage
created from the living of construction staff and the sediments excavated from grid-
like watercause of lake area.
( 1 ) To avoid the effects on living of nearby residents, excavated sediments
shall be transported to the other places. If the sediments can not be transported in
time, then the sediments shall be loaded into the straw bags for storing to reduce the
release of dust and malodor. The transporting of sediments shall be closed to prevent
them from scatter along the road for which will affect the image and sanitary of the
city.
(2)Sediments shall be sent to local landfill for sanitary burying. The leachate
treatment facilities shall be well-managed to ensure the discharge meeting the
requirements.
(3)Spoil and construction wastes shall be filled in appointed site according to
the requirements of municipal administration department and planning department. If
the backfill site is not used temporarily, vegetation cover shall be cultured to prevent
the soil erosion.
(4)Abandoned material in the construction such as gravel, building materials,
steel, packaging materials shall be recovered by special people. And the working face
shall be cleaned timely without any sequelae left.
( 5 ) To prevent secondary pollution, domestic garbage shall be collected
specially and sent to landfill regularly for proper disposal. Huddle and throw is
forbidden strictly. In addition, to ensure the living environment and hygienic quality
of the surrounding environment for the workers, the contractor shall strengthen the
education of construction staff that waste can not be thrown at their will.
( 6 ) When confront hazardous wastes in the construction, the work shall be
stopped temporarily,. And the local environmental protection department and health
department shall be contacted in time. After handling measures being taken, the
construction can be started again.
5.3.1.6 Protection Measures for Ecological Environment
The effects in construction period on the environment mostly are temporary, and
these effects will be disappeared with the end of construction. However, some of
effects may result in irreversible and long-term impact if without proper handle. It is
necessary that effective environmental protection measures being taken in the process
of construction. The proposed project construction shall take the following measures:
( 1 ) Before the construction of each engineering facility and the pipe work,
conditions of underground engineering geology and underground obstacles shall be
understood firstly, for which is the prerequisite and basis of a project.
(2)The construction of each engineering facility and the pipe work shall avoid
the rainy season. And drainage channels shall be built of the construction sites with
serious soil erosion. The construction will take methods of stratified excavation,
layered stacked and layered backfill. After completion, the landscape will be restored
and the construction shall be in accordance with the design requirements of water-soil
conservation strictly. During the construction of water intake work for the reclaimed
water supply project, this work shall be done in dray season in order to avoid the
effects of wet season for which is a flood season and last from June to August.
(3)The planning and design shall be considered properly. The existing roads
shall be used fully with no or less construction road working.
( 4 ) To reduce construction errors and increase work efficiency, the
information based construction shall be strengthened.
(5)To avoid the effects on aquatic environment, the construction of gird-like
water cause for lake area shall use scientific and reasonable construction methods as
much as possible.
(6)Note the construction equipments and machines can not be washed in the
nearby water bodies. The maintenance of construction machines shall be strengthened
to prevent the oil leakage of construction machines. If there is a leakage, the leaked
oil shall be collected in time and handled centrally after receiving by special vessels.
(7)No camp will be built by the construction teams. The existing residential
facilities shall be used fully. Through renting, the construction staff can scattered live
in the local residential building with the general domestic sewage and garbage being
discharged into the civilian facilities of the residence.
(8)Building materials like cement are not allowed to stockpile near the water
bodies, canopy cover and fence shall be set to prevent the rainwater washing them
into the water bodies. Appropriate sites shall be selected for the construction wastes
(including spoil and abandoned stone) to backfill or stockpile after consultation with
the local people. The spoil and abandoned stone shall be used as much as possible for
road foundation work and soil conservation project.
(9) If the pipeline construction faces these items such as high voltage pole,
overpass, main traffic road, municipal pipe network and relevant road, reports have to
submit to the relevant management departments. Based on their approvals, the work
can be performed. The supports for the nearby buildings (structures) like residential
areas and bridges for which are in the scope of the pipeline construction effects shall
be considered, especially the effects on ground settlement, nearby buildings
(structures) and existing underground pipeline.
(10)During construction, the damage to vegetation cover shall be minimized.
After construction, measures like planting tree and grass shall be done to speed up the
recovery process of vegetation with some engineering measures also being taken for
protection. To protect the integrity of the ecosystem, the original land surface height
shall be maintained and the landform be restored as original after the completion of
construction.
( 11 ) Before construction, the construction unit shall prepare detailed
construction plans and establish environmental management systems. Special people
have to arrange to responsible for the environment protection work during
construction. Corresponding control measures and disposal methods shall be made for
the “three wastes” generated in the construction. The environment management shall
be in accordance with the national environmental guidelines, policies, regulations and
standards. To be rule-based and scientific management, various environmental
management system shall be established which take post responsibility as the center.
(12)To be civilized and cleaned construction, the education of construction
staff shall be strengthened with environmental regulations and environmental
knowledge being learned.
5.3.1.7 Mitigation Measures for Social Environmental Impact
(1)The reasonable acquired land compensation for the villagers shall be in
accordance with the land acquisition and resettlement policy and compensation
approach of the relevant national government and local government. The villagers’
opinion shall be listened carefully. The working and living conditions for the villagers
shall be guaranteed that not lower than the current level.
(2)Construction for pipeline and lake area shall be done section by section.
The excavation and backfilling shall be done as soon as possible. The construction
sites, which near the public facilities such as hospital, school and bus station, shall
have temporary pavements and warning signs. During the rush hour, traffic policemen
shall give guide and dispatch to ensure smooth flow of pedestrians and vehicles. To
reduce the pressure of urban traffic, the transporting of materials shall avoid the rush
hour.
( 4 ) Awareness training and education of cultural-relics protection for the
management and construction staff shall be strengthened. According to field survey
information, no cultural-relics have been found currently in the project area. However,
if find any cultural-relics in the construction, the local conservation department shall
be informed immediately. The site shall be preserved in time and the construction
shall be stopped before the proper handling done by the conservation department.
(5)To reduce the possibility of traffic jam and the effects on traveling of the
residents, the transporting of building materials and waste earth shall be done at night
or avoiding the rush hour.
5.3.1.8 Human Health
To ensure the construction safety, the contractor shall prepare the health and
safety approved by the relevant project management unit (PMU).
The contractor shall prepare the induction training program for the construction
staff. The facilities like cranes, supports and other shall be fixed rigidly. To avoid the
occurrence of personnel casualties, the construction staff shall observe the
construction specifications such as Code of Design on Building Fire Protection and
Prevention and Specification of Building Safety strictly and wear the personal
protection equipments like safety helmet.
During construction, the contractor shall avoid transporting the materials in rainy
day or at the time of go on/off shift to against traffic jam or accident. To avoid public
casualties, proper isolation and protection facilities shall be installed and warning
device shall be set up for dangerous sites with special personnel for caring.
An effective organization responsible for environment supervising and
monitoring shall be established, which can start a fast and efficient procedure for any
violation.
Detailed environmental and social impact specifications shall be prepared for the
contractor and which shall be included into the tender documents. And the obligation
for environment must be taken as part of the contract documents.
5.3.2 Mitigation Measures in Operation Stage
5.3.2.1 Reclaimed water supply Project
1)Analysis on Water Pollution Control Measures
(1)Pollution control measures of Reclaimed water supply project
The pollution control measures of this reclaimed water supply project mainly
include pollution control method of industrial wastewater and domestic wastewater.
The settling tank sludge water, filter backwashing water and pressure-filtered①
water from sludge dewatering chamber of this reclaimed water supply project shall be
settled then flow back to front distributing well and be treated together with source
water.
Ultra-filtered and reverse-osmosis tail water from reclaimed water supply②
projects of Drainage Cannel 3, Drainage Cannel 7 and Ganqimaodu Port Processing
Park be send to front distributing after coagulation & and settling treatment and
reclaimed with source water from reclaimed water treatment plant; the wastewater
will not be drained outside.
The process of reverse-osmosis tail water treatment is: tail water → coagulation
→ settling → effluent→ reclaimed water treatment device. The main buildings and
structures of reverse osmosis tail water treatment are indicated in diagram 5.3-1
5.3-1 Main buildings & structures of reverse-osmosis tail water treatment
Sn Buildings & Structures Specification Remarks
1 Regulation tank L×B×H =6m×5m×5m
2 Coagulation Tank
L×B×H=5m×5m×3m
Chemicals adding device 2 sets, speed reducing mixing device 1 set
3 Settling Tank L×B×H=13m×6m×5m
Mud scraper 2 sets, sludge discharge valve 4 sets
4 Reservoir L×B×H=10m×8m×5m Clean water pump 3 sets
The domestic wastewater of this reclaimed water supply project will be sent to③
Urat Rear Banner Processing Park Wastewater Treatment Plant together with
domestic wastewater from water supply project of Urat Rear Banner Processing Park.
The domestic wastewater of Drainage Cannel 3 reclaimed water supply project will be
sent to Hangjin Rear Banner Wastewater Treatment Plant. The domestic wasterwater
of Drainage Cannel 7 reclaimed water supply project will be sent to Wuyuan Country
Wastewater Treatment Plant. The domestic wastewater of Ganqimaodu Port
Processing Park reclaimed water supply project will be treated in underground
treatment equipments in factory to meet standard of Reuse of urban recycling water--
Water quality standard for urban miscellaneous water conTotalption (GB/T18920-
2002 ) , be used as miscellaneous water for factory but shall not be discharged
outside.
(2)Feasibilities Analysis of Water Pollution Control Measures of Reclaimed
Water Supply Project
The pollutants components of settling tank sludge water, filter backwashing①
water and pressure-filtered water from sludge dewatering chamber of this reclaimed
water supply project are rather simple and main of them are SS. So, after settling, the
water quality will be improved greatly, meanwhile rather little sewage will be
generated. This will take a small proportion of the scale of the whole reclaimed water
supply project; also, this will have little effect on inlet water quality of reclaimed
water plant but will not cause shocks to normal operation of reclaimed water supply
facilities.
In consideration of brine wastewater caused by ultra-filtered and reverse-②
osmosis technologies applied in reclaimed water supply project of Drainage Cannel 3,
Drainage Cannel 7 and Ganqimaodu Port Processing Park, the wastewater will be
coagulated settled then sent to front distribution and be reclaimed together with source
water of reclaimed water plant; such wastewater will not drained outside.
Suspended matter and salt content of tail water after reverse-osmosis treatment
are rather high, but after neutralization, coagulation and settling treatment, not only
the suspended matter but also the salt content will be reduced. After treatment, such
wastewater will be reclaimed together with resource water to fully utilize and save
water resources. So, this method is feasible to treat brine water.
The Urat Rear Banner Processing Park wastewater treatment plant, which is③
related to this project, is also a project benefit from the World Bank loan; now this
plant is under construction and the designed scale is 20,000 m3/d (recent-term);
ICEAS process is applied and the construction will be performed from May, 2010 to
Feb 2010. Drainage Cannel 3 wastewater treatment plant is located at the south of the
Drainage Cannel 3 reclaimed water supply project; A2/O process is applied and this
plant is completed and in trial operation, the designed scale is 20,000 m3/d. Drainage
Cannel 7 reclaimed water treatment plant is located at the south of the Drainage
Cannel 3 reclaimed water supply project; this plant is under construction and the
designed scale is 22,000 m3/d in recent term and 44,000 m3/d in future term; active
sludge Biolak wastewater treatment process is applied. The domestic wastewater
drained quantity of Urat Rear Banner reclaimed water supply project, Drainage
Cannel 3 reclaimed water supply project and Drainage Cannel 7 reclaimed water
supply project take a rather small proportion of the quantity. Meanwhile the pollutant
of such domestic wastewater is single and the content is rather low. When the water
flows to the plant, it will take little effect on designed inlet water quantity and quality
of the wastewater treatment plant.
Therefore, it is feasible that the domestic wastewater caused by reclaimed water
supply project engineering and operation is sent to wastewater via network treatment
plant nearby and to be treated
(3)Proposal for Water Pollution Control Measures of Reclaimed Water Supply
Project
People shall strengthen management to ensure normal operation of equipments①
in design, construction and operation. Standby equipments shall be set. Accident
prevention program shall be prepared to prevent serious consequences caused by
problems.
People shall strengthen management of project construction and operation to②
ensure the sewage treatment facilities and the efficiency meet the design standard and
requirement, also to ensure long-term, stable and normal operation and qualified tail
water discharge.
People shall set up sound environmental management rules & regulations and③
fully implement staff training program.
People shall maintain and keep the equipments in good conditions to reduce④
abnormal running to avoid unqualified discharge and accident discharge risk.
2) Measures of Noise Pollution Control
The noises of this project when running may come from the water intake pump
chamber, lift pump chamber of reclaimed water plant, sludge dewater system and
clean water lift pump station. Noise elimination, vibration elimination and noise
isolation measures will be applied to control noise, like low-noise equipments,
vibration-reduce method and noise isolated buildings, etc.
There are no residents in 50m around the reclaimed water project. Silencers and
bumpers are applied in this water in-take pump chamber. The pump chambers are
sealed; also double-layer silence doors & windows are equipped. Measures such as
installing silencers, bumpers and isolation booth on the noise sources of reclaimed
water plant to ensure the noise level in the plant is qualified and meet 2 class as per
Standard of noise at boundary of industrial enterprises, ie. 60dB(A)in day and
50dB(A) in night.
If lift pumps are added, to reduce noises, it is required that:
( 1 ) Sound isolation test shall be performed in the plant to ensure that the
sound isolation performance shall not be lower than 25dB(A).
(2)Low power and low noise type pumps and ventilators shall be selected.
Flexible joints shall be applied to connect the equipments and pipes to avoid
vibration. Low noise and low vibration equipments shall be selected in procurement.
( 3 ) Make a good layout in consideration of the direction of sound, the
shielding function of building and noise-absorbs ion of green plants to reduce noise
hazard to staff.
( 4 ) Double-layer windows and wall materials with good sound absorption
performance shall be applied in the Central Control Room. In structure, dumper
ceiling, damper wall and damper floor shall be selected to avoid transmission of
noises.
(5)Bumper cushions shall be installed in equipments with serious noises as
noise-reduce treatment: All pumps and ventilators shall be equipped with bumper
base and connected with pipes with flexible joints. All machines and pumps shall be
installed on independent bases to avoid noises caused by resonance.
( 6 ) Vibration-proof and shock-proof shall be considered in arranging,
designing pipes and selecting brackets to abate noises to environment
(7)Install silencers to reduce noises of ventilators.
( 8 ) Make a good and reasonable layout of the plant. Pay high attention of
noise distance; arrange the noise sources centralized and away from office area.
(9)Pay high attention to greening work. Make a three-dimensional isolation
belt near the reclaimed water plant and pump chamber with flowers, grasslands,
woodlands and trees. Grow more high and dense trees to abate noises to
circumstances.
Noises from equipments can be abated effectively to meet concerned national
standard by above methods.
3) Solid Wastes Control Measures
(1)Solid wastes control measures of reclaimed water supply project
Solid wastes caused by this reclaimed water supply water project mainly means
reclaimed water sludge and domestic wastes.
Reclaimed water sludge will be centralized and dewatered till the water content
is less than 80%. Then the sludge will be comprehensively utilized as landfill soil,
municipal engineering filling soil or brick manufacturing.
Domestic wastes will be collected and loaded by environmental sanitation
department as per the agreement with such department to ensure domestics wastes are
removed and treated timely and effectively and to prevent secondary pollution.
(2)Proposal for reclaimed water project solid waste control
Solid wastage of wastewater treatment plant, especially the sludge shall not①
disposed casually but be collected and stored properly, and be sent to an agreeable
domestic waste landfill site periodically.
It is forbidden to discharge sludge of reclaimed water plant to any ground②
waters, valleys, depressed land, caves or farmland but not exclusive discharge site.
In temporary sludge deposit site of reclaimed water plant, foundation anti-③
seepage, rain proof, odor concentrating and emission and secondary pollution control
measures shall be taken.
Sludge shelter shall be rain-proof; the ground to deposit sludge shall be④
hardened. Coffer wall, draining and collection well shall be arranged near the shelter.
The collected sewage from the deposit sludge shall be fed back to reclaimed water
treatment system.
The dewatered sludge and solid waste of wastewater treatment plant shall be⑤
loaded and removed timely. Sludge shall be transported by closed tank trucks.
The sludge shall be transported punctually and when the traffic is not so heavy⑥
if possible.
The advance concentrating and dewatering equipments shall be used to reduce⑦
the water content to 75 ~80%, so as to reduce the quantity of sludge and facilitate
utilization. It is suggested that the sludge shall be comprehensively utilized after
dewatering process (water content less than 10%).
The sludge attached on the trucks and wheels shall be removed when the solid⑧
waste storage and transportation vehicles leave the plant (pump station). Also, please
check if the vehicle can be well closed or not to avoid pollution to roads.
It is suggested that the construction enterprises shall cooperate with agriculture⑨
and landscape department to study the sludge serving as greening fertilizer so as to
realized recycling of solid waste.
4)Safety measures of Chlorination Room
Chlorine leakage accident is the biggest potential pollutant. The leakage will
cause hazard to production stuff member and even some influence to circumstances
outside the plant.
Natural ventilation conditions shall be utilized, if natural ventilation is not
practical, mechanical ventilation shall be applied. The ventilation frequency shall be
8~12 times per hour as per standard to ensure fresh air in the room. Meanwhile, the
chlorine leakage alarm and absorption systems are equipped. As soon as leakage is
happen, the chlorine detecting gauges will detect. If the detected leakage is higher up
to preset value, the fan of leakage absorption system and alkaline liquid pumps will
run to neutralize the leaked chlorine.
Installation of chlorine leakage detecting and alarming devices, layout, quantities
and installation method shall comply with concerned regulations in Specification for
the Design of Combustible Gas and Toxic Gas Detection and Alarm for
Petrochemical Enterprises (SH3063-1999). The auto-alarm system shall act when
chlorine content in air is up to 2~3ppm.
The chlorination room shall equip with protection devices such as gas mask for
staff members in case of accidents.
To avoid chlorine accident caused by wrong operation, the chlorination staff
shall be strictly trained; they can work only if they are aware of safety in using
chlorine and detailed chlorination operation. All possible measures shall be taken to
avoid bursting, oozing, dripping, leaking chlorine. Only operation staff members are
allowed to enter chlorination room
Check the equipments periodically to ensure they are in good conditions.
Chlorination chamber shall open externally and equip with easy-handle locks to
ensure quick escape in emergency situation.
5) Greening
To ensure a graceful environment in the reclaimed water supply project plant,
double-layer greening program around building and beside roads shall be
implemented to increase greening area maximally, while the green-cover percentage
shall be higher than 30%. Select good tree species combined with flowers & grasses,
fountain, the sculpture & artistic creation and flower beds to make a good layout and
graceful environment. Arrange the tree species reasonably and three-dimensional tree
belt organically combined with trees & shrubs, grasses and flowers to form a multi-
layer greening environment and seasonal beauty of color. Make use of tanks, which
are higher than ground, to let climbing plants climb up. Expand the flower bed to
make a three-dimensional greening to form an all-season, graceful and beautiful
garden-like factory.
Set up sanitary protection isolation belt in each reclaimed water supply plants.
Use the isolation odor & protection function of greening belt, and especially isolate
the living & administration area (front factory area) from production area by greening
belt to create a good environment. Grow high and evergreen arbors around the
production area and sludge treatment area to make the environment better.
6 ) List of “Three Simultaneousness” Environment Protection Measures
Acceptance
“Three Simultaneousness” measures, results and investment estimation are
indicated in diagram 5.3-1
5.3-1 List of “Three Simultaneousness” Environment Protection Measure Acceptance
Item Measures and equipments to controlInvestment(10,00
0 RMB)
Wastewater neutralization、coagulation、settling buildings and facilities 80
Sludge Sludge treatment facilities 1300
Noise Noise isolation, vibration and noise abatementList and get from
equipments
Greening Trees, flowers & grasses 560
DetectorPollutant detectors, sign board of sewage discharge port and solid
waste site, .etc.100
Net work
constructionClean & waste water network 25
Chlorine
leakage
accident
Set up chlorine leakage detect & alarm device and chlorine absorption
device in chlorine chamber. Set up chlorine leakage detect &
alarm device in chlorination room
800
Construction
period
Control and management measures for wastewater, odor and ecology
during construction period200
Total 4115
5.3.2.2 Mitigation Measures of Wastewater Treatment and Re-use Project in
Processing Park
1)Measures to Mitigate Air pollution to Circumstances
The wastewater treatment plants have effects on environments, mainly it means
odor, but odor is insufferable for people. So, control measures must be taken to reduce
the effect of odor. In this project, biological de-odor device is designed to remove
odor, so as to control generated odor effectively, therefore, following supplementary
measures are represented in this EIR report:
( 1 ) Strengthen greening construction in factory area. Green coverage in
factory shall not be less than 30%. Greening shall be executed mainly around the grid,
sludge treatment system and factory boundary. Generally, high arbors shall be mainly
selected as greening trees; also, low shrubs can be supplementary. The green belt
around the factory boundary shall be bigger than 5m.
( 2 )加 Strengthen management of each treatment system of wastewater
treatment plant and remove deposited sludge. When the sewage tanks are stopped to
maintenance, the sludge will be emerged, so that the odor will come out. The sludge
shall be removed timely to reduce odor.
(3)The sanitary protection distance of this project is 50m. The sources of odor
are 10m or farther to factory boundary. It is recommended that 40m distance away
from the boundary shall be arranged as plan control area, in this area, no civil building
or other sensitive permanent buildings are allowed to be built.
2) Measures to Mitigate Water Pollution
After this project is completed, the water quality of general drainage cannel in
Hetao District will be improved tremendously. To ensure normal operation of
wastewater treatment plant, following measures shall be taken during plant operation:
(1)Reform the heavy pollution enterprises on-site. Close, stop, merge, change
or shift unqualified enterprises.
(2)To ensure normal operation and qualified tail water to be discharged as per
national standard, enterprises in the Park shall discharge their wastewater to network
before their wastewater is treated respectively as well as the industrial feature
pollutants are removed. The wastewater to be discharged shall meet Discharge
standard for municipal wastewater (CJ3082-1999). The sewage from sludge de-water
chamber and domestic wastewater shall be collected in wastewater network and then
be send to treatment process.
( 3 ) The wastewater from heavy pollutant enterprises shall be pretreated in
their factories before being discharged. An accident reservoir shall be built to void
high load shock to wastewater treatment plant so that the treatment efficiency and tail
water quality being affected.
( 4 ) To prevent risk of accidents, starting from design and management,
practicable measures shall be taken and accident emergency disposal system shall be
established.
(5)Strengthen water pollution monitoring. Install online monitoring devices,
which are linked with local environment protection department, in inlet and outlet of
wastewater treatment plant. All wastewater treatment plant shall equipped with
accident emergency reservoir.
(6)Operation management and operation responsibility system shall be well
established; Staff members shall be well trained and technical evaluation files shall be
set up for them. The unqualified staff shall not work.
3)Measures to Mitigate Noise Pollution
The noises of wastewater treatment project mainly come from the equipments, which include mechanical equipments like sewage pump and ventilators, in wastewater treatment plant and sewage lift pump station. Following measures can be applied to control noise pollution.
(1)To select low-noise ventilator, sewage pump.
(2)Compound impedance silences are applied in the inlet and outlet.
(3)Use Isolation booth to control noises.
(4)Take measures like vibration elimination, noise isolation and underground
channel ventilation for aeration tank ventilator room.
(5)The ventilator room control can be realized in Central Control Room so
that the operators are not required to work in the ventilator room.
(6)A greening belt with certain width is required in the factory boundary.
Arrange tri-layer arbor-shrub-arbor green belt and grassland under trees to eliminate
the noises.
4)Measures to Mitigate Solid Waste Pollution
(1)Sludge
There are several methods to treat sludge, major of them are landfill, compost
and incineration.
Sanitary Landfill①
Landfill treatment is one of the normal ways and it is commonly used in many
large-scale wastewater treatment plants. The procedure requirement of sludge landfill
is similar to solid waste landfill. The sludge without dry & incineration treatment shall
be filled in different layers and in small scale. The thickness of raw sludge layer shall
be less than 0.5m while the thickness of digested sludge layer shall be less than or
equal to 3m. A layer of sand soil with thickness 0.5m shall be put on sludge layer.
Both kinds of layers are interlaced. Ventilation units are required. The seeped liquid
from landfill site is highly concentrated sewage; it shall be centralized and treated.
Guardrail shall be set and concerned measure shall be taken to control insects.
A lot of lands are required for landfill. Odor may be generated in the landfill site;
meanwhile, if anti-seepage methods do not work well, the ground water may be
polluted. In another aspect, there are a lot of organic matters, which will act and digest
and lead to marsh gas, in sludge. In case that the pressure of marsh gas is too high to
release or the marsh gas is fired, explosion will happen. Therefore, the disadvantages
of sanitary landfill method are too much land occupation, difficult site selection and
potential secondary pollution.
Agricultural Compost②
Sludge compost can be performed singly or combined with other solid waste.
The solid waste to be composted with sludge may be domestic waste, straw and sew
powder. The combined compost method is popularly used because it will reduce time.
The weight proportion of sludge and domestic waste normally is 1:2; the two kinds of
materials are put in a pile in different layers. The height of pile can be 1.5~2.0m, and
the surface of pile shall be smoothened via coating or pressing. Ventilation conditions
shall be realized in a compost pile. The composting time is normally 3~6 weeks; after
composting, mix the materials and pile again. After at least 3 month, they will be
mature and become to effective fertilizer. To realize quicker and better control,
mechanical composting equipments, which include vertical and horizontal stirring and
oxygen supply system, can be applied. The fermentation process may be completed in
5~6 days, the temperature during fermentation may be up to about 65 .℃
Agricultural disposal is an ideal method to dispose sludge. There are a lot of
elements like NPK, microelement and humic substances which are essential for
growing. The nitrogen in sludge can help the growth of leaves and stems; the nitrate
nitrogen can be uptaken by plants directly, while ammonia nitrogen is uptaken by
plants after being converted to nitrate nitrogen in soil. The organic nitrogen will be
utilized only after being destroyed and oxidized in soil. The tests indicate that, certain
quantity of municipal domestic sludge will improve the organic matters, humic
substances and soil structure. Fertility of soil may be improved if reasonable qualified
sludge is used. For agricultural use of sludge, the conditions shall meet standards in
Control standards for pollutants in sludge from agricultural use (GB4284—84), in
this standard, the maximal limits of 11 pollutant contents are regulated. Also, there are
6 principles listed in GB4284-84. Therefore, the sludge shall be composted to kill
germs and parasitic ova before agricultural use, meanwhile the harmful substances
shall be removed.
Incineration Treatment③
Incineration is one of the most popular ways used in oversea countries. By means
of incineration, the volume of sludge will reduce to minimum (about 5% of before).
Sludge incineration is a high temperature treatment technology. Excess air and sludge
to be treated act in oven, so that all organic matters and pathogens can be destroyed by
oxidization and pyrolysis in 800 ~1200 high temperature. Meanwhile, the heavy℃
metal in sludge will be oxidized to stable oxide, which is good raw material for
haydite and ceramic brick manufacturing, and to be comprehensively utilized. But, the
incineration system have problem or the incineration is not completed and the s waste
gas, noises, heat and radiation may cause secondary pollution. If the incineration
system is well controlled to realize complete incineration and the overheat is well
utilized, this is a rather good method to realized harmless, quality-reducing, and
recourse-recovery treatment.
Ashes come from incineration are water-absorbing and solidifiable, so they can
be used for soil improving or road building. Also the ashes can be served as fine
fillings of concrete. A kind of granular fuel made from the sludge can be burned well,
and of which the heat value is equal to brown coal; meanwhile the harmful gas
generated will be lower than incineration process. The remains can be used in
construction industry.
Over energy in exhaust gas can be obtained to generate power when incineration.
Compound fuel made from de-watered sludge, along with additives, like detonator,
catalyst, loosening agent and sulfur-fix agent. This kind of fuels can be used in
industrial and domestic boilers. With stable combustion, excellent thermal and
environmental test, this is an ideal way to realized effective sludge utilization.
(2)Analysis of Sludge Treatment Method
There is no available final disposal method stipulated clearly. But according to
analog data, the components of sludge of wastewater treatment plant are related to the
properties of wastewater to be treated. Normally, the sludge from a wastewater
treatment plant, which mainly take up industrial wastewater, contains high level heavy
metal content which is much higher than standard for agricultural sludge. Therefore,
the sludge from processing park shall not be utilized as agricultural fertilizer. Instead,
it shall be disposed by means of safety landfill. Inner Mongolia Baotou (Mid-west
area of Inner Mongolia) Hazardous Waster Disposal Center will be assigned to treat
such sludge.
Inner Mongolia Baotou (Mid-west area of Inner Mongolia) Hazardous Waster
Disposal Center is according to National Construction Planning of Hazardous Waste
and Medical Waste Disposal Facilities, which is authorized by national State Council,
issued in 2003 by State Environmental Protection Department and National Develop
and State Commission of Development and Reform. The overall investment is 198
million RMB and the site is located in the west of Hatamen Valley, Agarusutaimu,
Jiuyuan District, Baotou City. The hazardous substances from eight cities and leagues,
including Baotou City, Hohhot City, Erdos City, Wuhai City, Xilin Gol City, Ulan Qab
City, Bayannur City, Alashan League, and medical waste disposal facilities of Baotou
City will be disposed safely here. This center (1st stage) takes coverage of 36 thousand
m3 and the overall capacity is 203367m3 The annual landfill quantity is 28760m3/a.
The disposing capacities include: incineration 10,800t/a, waste acid 30,000t/a,
physical & chemical disposing 5,000t/a and curing process 15,500t/a. Because that
sludge produced in this processing park wastewater treatment plant is only 4,307t/a,
Inner Mongolia Baotou (Mid-west area of Inner Mongolia) Hazardous Waster
Disposal Center is capable to treat sludge from this processing park wastewater
treatment plant. This disposal method is feasible. See hazardous and waste treatment
agreement of this project in attachment
(3)Scum from Screenings
Scum halted by coarse screens and fine screenings are solid blocks, including
both inorganic and organic substance. The properties of scum is similar to domestic
solid waste, so it can be treated, pressed and transported with sands from setting tank.
(4)Domestic Waste
All domestic waste will be bagged and collected by special people, then sent to
waste pot appointed by Bayannur City Government. Then the waste collecting truck
will send the waste to solid waste disposal center to treat timely. The waste shall be
well sealed during transportation to ensure daily removal.
5) Measure to Protect Ecological Environment
The green coverage may reduce owing to construction. Greening in factory,
including greening belt around the factory, grassland in factory and trees beside the
roads, shall be performed as compensation. Following measures are recommended to
take during greening construction:
(1)Pay Attention to Proportion of Arbors, shrubs and grasslands.
Keep a certain hierarchical structure. As per greening equivalence defined by
ecological service function, an arbor or shrub is equal to 1.5m2 of dense grassland. So,
if we enhance the proportion of arbors and shrubs in certain area, the ecological
service function will be improved. Meanwhile, a plant community structure including
three layer arbor—shrubs—grasses has higher anti-interference abilities. Normally,
the green projected area of arbors shall take a proportion higher than 50%, while
shrubs 30% at least and grassland 50%(overlapped percentage 130%)
(2)Select Mixed Forest Instead of Single-specie Forest
Multiple tree species formed by coniferous and broadleaved mixed forest may be
applied in greening. Do not use single-specie forest. Economic tree species like
poplar, willow and elm are suitable trees to be grown in factory.
(3)Use Indigenous Species As Possible
The indigenous species fit with local circumstances better and the survival rate is
higher. With stronger adaptabilities and capabilities for resisting natural disasters, the
indigenous species are preferred tree (grass) species for greening. Local shrubs and
grass species shall be selected with sand fixation function..
(4)Strengthen Management
The factory people shall appoint special people for greening and management,
also, concerned rules and regulations shall be stipulated to protect grassland and
ecological circumstances.
5.3.2.3 Mitigation Measures of Wuliangsu Lake Project
The operation stage of Wuliangsu Lake regulation project is focusing on noise of
man-made wetland engineering and solid waste.
1)Measures to Mitigate Noise Pollution
The noises of this project mainly come from the pumps of water lift station and
compressor of aeration tank. Following measures may be taken to control noise
pollution.
( 1 ) Double-layer windows and wall material with good sound absorption
performance shall be applied in the pump chamber and compressor chamber. In
structure, dumper ceiling, damper wall and damper floor shall be selected to avoid
transmission of noises. The sound isolation performance shall not be lower than
25dB(A).
(2)Low power and low noise type pumps and ventilators shall be selected.
( 3 ) All pumps and ventilators shall be equipped with bumper base and
connected with pipes with flexible joints. All machines and pumps shall be installed
on independent bases to avoid noises caused by resonance.
(4)Install silencers to reduce noises of ventilators
(5)Make a good layout as per the direction of sound, the shielding function of
building and noise-absorbs ion of green plants to reduce noise hazard to staff.
( 4 ) Vibration-proof and shock-proof shall be considered in arranging,
designing pipes and selecting brackets to abate noises to environment.
(5)Pay high attention to greening work. Make a three-dimensional isolation
belt near the reclaimed water plant and pump chamber with flowers, grasslands,
woodlands and trees. Grow more high and dense trees to abate noises to
circumstances.
Noises from equipments can be abated effectively to meet concerned national
standard by above methods.
2)Measures to Mitigate Solid Waste Pollution
Solid wastes produced in lake area regulation project operation mainly include
sludge in settling tank and domestic solid waste.
Solid wastes produced in man-made wetland mainly include sludge in settling
tank. The sludge shall be removed every 5-10 years and it can be served as fertilizer
for farmland. In transportation, some measures shall be taken to prevent secondary
pollution caused by leakage.
Domestic wastes will be collected and loaded by environmental sanitation
department as per the agreement with such department to ensure domestics wastes are
removed and treated timely and effectively and to avoid secondary pollution.
6. Environmental Risk Analysis and Relief Measures
6.1 Environmental Risk Analysis and Relief Measures of
Reclaimed Water Supply Works
6.1.1 Environmental Risk Analysis of Reclaimed Water Supply
Works
The failure of individual equipment of the planned reclaimed water supply works
will have no impact on the reclaimed water disposal system by and large; two-way
power supply can prevent power cut-off accident and in case of failure of power
supply, standby electric generators will timely discharge the untreated reclaimed water
into surrounding surface water system for ensuring the safety of reclaimed water
supply works while the surrounding surface water system is to be influenced to some
extent. Therefore, we’d strengthen the management and maintenance of reclaimed
water supply works, and compile an emergency handling proposal for preventing
pollution accident of water environment.
Chlorine dioxide is used in the planned reclaimed water supply works for
disinfection. Sodium chlorate and muriatic acid are purchased for producing chlorine
dioxide, with a little chlorine gas as the by-product. Moreover, another key
environmental risk of reclaimed water supply works is accident caused by the failure
of chlorine dioxide generator in the disinfection. On the basis of the analysis on the
damage of the accident, reasonable and feasible prevention measures are put forward
for minimizing accident rate, loss and environmental damage of the construction
project.
Chlorine dioxide, a yellowish red gas with irritative smell can scatter on the
ground and is usually diluted to a solution with lower than 10% concentration in use
and storage; and with high oxidizability, it may have an explosion reaction with many
chemical substance, is extremely sensitive to heat, shock, hit and friction and tends to
decompose and explode.
Chlorine gas, a yellowish green poisonous gas with irritative smell has a relative
density 1.47(0℃, 369.77kPa), melting point -101℃ and boiling point -34.5℃, and is
dissolved in water and lye. It produces hypochlorous acid and muriatic acid with
water, where the hypochlorous acid is then decomposed into muriatic acid nascent
chlorine, oxygen, chlorine gas density 2.49, and vapor pressure 506.62kPa
(5atm10.3℃) and acid. Chlorine and carbon monoxide produces phosgene in
intensively heat case. Chlorine gas is non-combustible gas while can support
combustion, and explode in mixing with combustible gas in daylight and cause
inflammation and explosion with many substances.
The chlorine dioxide generator of the project has extremely low output of
chlorine dioxide & chlorine gas in abnormal working status. Moreover, chlorine
adding workshop is equipped with a lye spraying and absorbing device with
processing efficiency of over 98%. Therefore, the accident of the project has a small
scope, and in case of accident, timely measures will alleviate the impact rapidly in a
short period.
In sum, perfect accident handling measures can minimize environmental risk of
this project.
6.1.2 Environmental Risk Relief Measures of Reclaimed Water
Supply Works
6.1.2.1 Environmental Risk Counter-measures
(1) Prevention Measures against Environmental Risk and Accident taken in
Design
① Strictly define the production danger area of reclaimed water plant, set up the
plan under the principle of safety and sanitation, take into account wind direction, safe
protection distance and other factors, and select corresponding flameproof electric
equipment.
② Set up relevant fire-prevention, explosion-proof, poison prevention, and
monitoring, and alarming and other safety facilities for the equipments and pipelines
in use according to the properties of chlorine dioxide and chlorine gas.
③ Chemical adding room should be set up with lye spraying system as well as
automatic chlorine gas monitoring alarm system.
④ Chemical adding room should be set up with a closed operating cabin of the
accident disposal system and waste gas alkaline collecting device in handling
accident.
(2) Risk & Accident Prevention Measures in Operation and Management
① Sophisticated automation system should be used for chemical adding device
for effectively controlling production process, timely feeding back the information
and shutting down the device in case of accident, so as to reduce the leakage of
chlorine dioxide and chlorine gas caused by the accident.
② Strictly implement the operating regulations, keep to the post, closely monitor
the change of process parameters of the equipment, timely report and take effective
measures in case of any failure.
③ Chlorine adding room should be provided with forced ventilating equipments.
④ Strictly put an end to the leakage of pipeline system, especially the joint
between the valve and pipe, as well as flexible hose and equipment; and carry out
regular inspection over pressurized vessel and pressurized component and material.
⑤ Set up lightning-proof system and fire prevention system;
⑥ Set up cofferdam around the muriatic acid tank with switching device, and
build up one accident collection basin with more than 2m3 volume. In case of leakage
accident of muriatic acid, the accident should stay in empty status as usual.
⑦ The reclaimed water plant should be set up with emergency accident rescue
system covering monitoring, early-warning communication, command, first-aide
repair and rescue;
6.1.2.2 Relief Measures of Risk Accident
(1) Emergency Handling Measures
Evacuate the people in leakage polluted area to higher windward position, and
close off till the gas completely disappears. Cut off the sources of fire and gas, spray
water for diluting, carry out forced ventilation (indoor) or ventilation (outdoor). Gas
leaking vessel cannot be reused, for which technical treatment is required for
eliminating the remaining gas.
(2) Protective Measures
Protection of respiratory system: gas mask is required in case of high
concentration in the air. In emergency rescue or withdrawal, positive-pressure self-
supported respirator is recommended.
Protection of eyes: chemical safety protective glasses are required.
Protection of body: working clothes required.
Protection of hand: chemical gloves are required for possible touch with
poisonous substance.
Others: no smoking on the working site. Bath and re-dressing after work, and
good sanitation habits are required.
(3) First-aide Measures
Skin touch: put off the polluted clothes, and rinse with much flowing fresh water
for at least 15min. See a doctor.
Eye touch: open the upper & lower eyelids, rinse with much flowing fresh water
or physiological salt solution for at least 15min. See a doctor.
Inhalation: rapidly leave the site and move to the area with fresh air. Keep
smooth breath. Have oxygen therapy in case of difficult breath. See a doctor.
6.2 Environmental Risk Analysis and Relief Measures of Sewage
Treatment and Recycling Works
The operation of sewage disposal plant is usually stable. To minimize the failure,
some emergency measure should be defined for sewage disposal plant and operating
management should be strengthened. Several possible cases are analyzed as follows.
6.2.1 Potential Environmental Risk and Accident
(1) Emergency Accident
Quality problem or improper maintenance of sewage treatment equipment and
facility will cause failure of the equipment and facility. As a result, sewage treatment
efficiency declines and sewage may be directly discharged instead of any treatment;
or some force majeure, such as power shutdown and sudden natural disaster may
interrupt the operation of sewage treatment facility, and a lot of untreated sewage is
directly discharged. This case is extremely abnormal emission of sewage disposal
plant. In case of abnormal operation of sewage treatment facility caused by electric
power failure, sewage can only be directly discharged into and pollute the surface
water system through overflow pipes.
(2) Equipment Failure
The failure of sewage or sludge treatment system lowers the treatment capacity
of sewage. The indicators of outlet water quality fail to comply with the design or
sludge fails to timely shrink and dehydrate. As a result, sludge is fermented, and the
storage tank is completely packed and smells unfavorably.
(3) Impact on Inlet Water Quality
The treatment effect of sewage disposal plant is greatly subject to the inlet
sewage capacity, water quality and other parameters of the plant. According to the
State’s statutes on the environmental protection, the emission of industrial wastewater
of various enterprises must comply with the standards and the requirements of sewage
disposal plant. In case of sudden accident of sewage disposal plant of enterprises e.g.
power cut-off, its sewage may be discharged into the sewage pipeline of the
processing area with no treatment and enter a sewage disposal plant of newly built
processing area. In case that inlet waste water causes excessively high impact load,
pH value exceeding the scope of 6-9 and the non-decomposable organic poisonous
substance higher than the criteria, biochemical and microbe activity of sewage
disposal plant will decline. More seriously, biota is damaged, and sludge is swollen.
Finally, outlet water quality deteriorates and exceeds emission standards of the State,
and causes decisive unfavorable impact upon water environment and ecological
system.
(4) Risk and Accident in Normal Operation
Due to the suddenness of risk and accident of sewage treatment system, it may
bring vital damage to the personnel maintaining the system and even endanger their
lives. In case of environmental risk and accident, the health and safety of the working
personnel in sewage disposal plant are firstly influenced. In case of accident of one
construction of sewage system, the accident must be immediately eliminated. In this
case, repair workers should enter sewage pipe, inlet well or sewage basin, where
poisonous H2S gas tends to exist and accumulate and with no protective measures,
repair personnel may breathe in poisonous gas due to bad ventilation and suffer from
symptoms such as swirl, unsmooth breath and death in serious case. The sewage or
sludge contains various pathogeny bacteria and helminth eggs. In direct touch with
sewage or sludge, operators may suffer from some intestines diseases and verminosis
if sanitation conditions are terrible.
6.2.2 Prevention Countermeasure and Measures of Risk and
Accident
6.2.2.1 Prevention Countermeasure of Source Accident
Source accident means if the production of enterprise producing sewage is
consecutive, outlet water quality is stable and pretreatment device on the site runs
smoothly. The abnormal emission of individual enterprise may cause sharp increase
of relevant sewage concentration and finally influence stable operation of sewage
disposal plant. Therefore, source enterprise should notify sewage disposal plant timely
in the construction start, in order to take some measures. Production limit or shutdown
proposal should be implemented for a plant with accident if necessary, for reducing
the load and environment risk of sewage disposal plant.
(1) Carry out technical treatment for the reason of abnormal emission, add
nutritional substance to aerobiosis basin in case of swelling trend of sludge for
improving the properties of the sludge, and strictly control the air quantity of van so
as to resolve the swelling problem of sludge on very start.
(2) Control the quality of the wastewater of the pipe-connected enterprises, and
carry out strict inspection and monitoring of the quality of wastewater, and control
water quality in anaerobic hydrolysis basin according to the load design, and ensure
the normal operation of anaerobic hydrolysis basin.
(3) Clean production should be taken for reducing the arbitrary emission of
stench. Production source of stench is to be regularly eliminated. Strengthen the
adjustment of gas capacity of aeration basin for reducing arbitrary emission of stench.
6.2.2.2 Accident Countermeasure & Measure of Sewage Disposal Plant Itself
The accident of sewage disposal plant itself comes from equipment failure,
overhaul or change of process parameter, which deteriorates the efficiency of
treatment. With serious water pollution, an accident should be prevented and some
emergency measures be prepared.
(1) To enable sewage disposal plant to restore production in the accident status
rapidly, main buildings should be provided with relevant buffer capacity and the
equipment (e.g. backflow pump, backflow pipe, valve and instrument).
(2) Top quality equipments are selected. Top-quality products with low failure
rate and easy maintenance should be selected as various machines, instruments and
other equipments of sewage disposal plant. Key equipments should run with one in
standby. Wearing parts should be prepared for timely renewal in case of accident.
(3) Strengthen the monitoring and control of accident symptom, carry out regular
patrol inspection, adjustment, maintenance and repair. Timely find out the symptoms
that may cause accident, and eliminate potential accident.
(4) Strictly control the process parameters of various disposal units such as water
quantity, water quality, residence time and load strength, and ensure the stability of
treatment effect. Provide some automatic water flow and quality analyzing and
monitoring instruments, and carry out regular sampling and determination. The
operators should timely adjust and keep the equipment in good status.
(5) To strengthen technical management work of sewage disposal plant, and
improve the treatment efficiency of different process segments are main items of the
work for ensuring qualified emission. Sewage disposal plant shall try to import talents
proficient in sewage treatment technique and management, and meet technical
demand of the plant and realize scientific and regularized management. The
managerial staff of sewage disposal plant should have high technical level and
management capability. Main operators should have strict trainings on theory and
practical operation before work start.
(6) Strengthen the operating management and the monitoring of inlet and outlet
water. Prohibit any discharge of unqualified sewage before treatment.
(7) Rainwater pipeline outlet and sewage outlet should be equipped with cut-off
control valve. Turn off the valve in case of accident so as to timely hold back the
sewage and prevent the direct entrance of sewage into water system.
6.2.2.3 Emergency Handling Proposal for Risk and Accident
(1) Classification and Organizational Structure of Emergency Handling Proposal
In case of accidental emission of the sewage, the leadership group of the plant
for emergency rescue should make judgment on the impact and damage of the
accident according to the accident information from the duty room of the emergency
rescue command center. For an average accident, only Class-III emergency rescue can
be actuated. The head of plant on duty, the person on duty on the site and technical
operator should establish a Class-III emergency team for carrying out the rescue
action. For large-scale accident with serious damage, the leadership group of the plant
for emergency rescue should rapidly set up a field emergency rescue command center
comprising the director and deputy director of the sewage plant and technical,
instrument and equipment engineers. According to the demands of rescue on the site
of the accident, on the basis of part-time rescue workers of the plant, special teams
e.g. rescue, medical service, security guard, communication & information release
should be set up and mobilized for emergency rescue action.
According to the harm of an accident and emergency rescue required, the
emergency rescue actions are divided into three classes: Class-III emergency (early
warning emergency, for average accident), Class-II emergency (field emergency, for
big accident) and Class-I emergency (overall emergency, for major accident).
1. Class-III emergency: in case of controllable abnormal event or sudden event to
be easily controlled e.g. small-size sewage leakage, and equipment failure, sewage
plant carries out emergency actions such as leakage stopping, medical service, repair
and rescue according to the preset procedures;
2. Class-II emergency: in case of any large-size sewage leakage, sharp increase
of pollutant concentration of inlet water and power cut-off of sewage plant, the harm
and impact of the accident exceed the handling capability of Class-III emergency
rescue and need the whole emergency rescue force of the plant for disposal;
3. Class-I emergency: the impact of an accident goes outside the bound of
sewage plant and requires the leadership institution of the plant for emergency rescue
to coordinate surrounding enterprise or surrounding emergency rescue authorities for
obtaining the support of social rescue force and organizing the traffic control, and
withdrawal and evacuation of the pedestrians nearby and the support of rescue team,
for the purpose of minimizing the personal death, economic loss and social impact of
the accident.
The organizational institutions of emergency handling for Class I, II & III are
included in Figure 6.2-1-6.2-3.
Accident site
Duty room Emergency rescue personnel
Leadership Group for Emergency RescueGroup head: director of factoryDeputy group head: vice director of factory Member: chief of the Department of Environmental Protection and etc.
On-duty personnel of factory director office
On-duty personnel of central control room
Person of repair on duty
Person of fire pump room on duty
Person of environmental protection department on duty
Driver on duty
Figure 6.2-1 Organizational Institution of Emergency Handling for Class III
Figure 6.2-2 Organizational Institution of Emergency Handling for Class II
Accident site
Duty room Emergency rescue personnel
Leadership Group for Emergency RescueGroup head: director of factoryDeputy group head: vice director of factoryMember: chief of the Department of Environmental Protection and etc
Factory director office
Central control room
Repair team
Fire pump room
Department of Environmental Protection
Driver team
Alarm
Emergency Rescue HQGeneral director: director of factoryVice General director: vice director of factoryMember: chief of the Department of Environmental Protection and head of rescue personnel.
Set up technical team
Export team
Environment monitoring team
News report team
After-treatment team
Production restoration team
Rescue and repair team
Accident survey team
Communication and liaison team
Logistics supply team
Traffic and security guard team
Figure 6.2-3 Organizational Institution of Emergency Handling for Class I
(2) Alarm and Communication
① Alarm and Communication
The whole plant area runs in a mode of integrated manual and telephone alarm
system.
In case of emergency or accident, alarming personnel can start the alarm button
for giving alarm to the central control room. The plant area is equipped with one
central control room presenting centralized monitoring & managing for the plant area
itself and sewage disposal facilities.
② Communication Facility
The telecom cable lines of the plant area include speaker talk-back lines and
wireless talk-back lines, in which cables of different systems are separate and make
up independent systems. The communication facilities in plant area including: two
Accident site
Duty room, factory director room
Leadership Group for Emergency RescueGroup head: director of factoryDeputy group head: vice director of factoryMember: chief of the Department of Environmental Protection and etc
Alarm
Emergency Rescue HQGeneral director: director of factoryVice General director: vice director of factoryMember: chief of the Department of Environmental Protection and head of rescue personnel.
Set up
Town Government
Export team
Environment monitoring team
News report team
After-treatment team
Production restoration team
Rescue and repair team
Accident survey team
Communication and liaison team
Logistics supply team
Set up technical team
sets of speaker talk-back telephones, and two pairs of wireless talk-back telephones.
③ Alarm Procedure
In case of accident or dangerous condition, the first finder should give an alarm
to the duty room of emergency rescue command center (in the central control room)
as soon as possible, and report the accident to the head of the shift in charge of the
production on the day. Alarm mode including: ① press the alarm button near to the
accident site, and notify the central control room; and ② notify the duty room.
After receiving an alarm, the emergency rescue personnel should rapidly prepare
for response. The on-duty personnel of emergency rescue command center should
report to the leadership group of the plant for emergency rescue in combination with a
field report on the accident and the information of safety monitoring system. The
leadership for emergency rescue should determine the actuation of emergency
handling proposal according to the scale of accident.
In case of grave sudden environment pollution accident in the plant area, the
emergency rescue command center will directly contact local government,
environmental protection department and fire prevention authorities for alarm, and
request information and technical supports.
(3) Emergency Handling Measures
Both rainwater pipeline outlet and sewage discharge outlet are equipped with
cut-off control valves. Immediately turn off the valve, and timely cut off the sewage
and prevent the sewage from directly flowing into the water system in case of
accident.
In case that the sewage flows into reception water system i.e. Xibei Canal due to
the untimely cut-off of the valve, local governments and environmental protection
authorities at district or municipal level should be timely notified. The government
will run as temporary rescue headquarters and command the production shutdown of
various sewage pipe-connected enterprises; and the environmental protection
authorities will set up emergency rescue team and build up cofferdam for blocking up
outlet of sewage disposal plant immediately. Moreover, monitoring personnel should
be sent out for immediate monitoring of pollution belt from the outlet of tail water to
2km lower reach of Xibei Canal and analyzing the water quality parameters of the
water system according to the standards.
6.3 Sea Area Treatment Works of Wuliangsu Lake
6.3.1 Winter Wetland Operation Analysis
6.3.1.1 Extended Wetland System in High and Cold Conditions
The inlet water of Wuliangsu Lake has the features as follows: big water volume,
low organic substance content, terrible biochemical properties and high nutritional salt
content. Such inlet water makes traditional anaerobic pond and facultative pond
hardly realize their functions in respect of no matter land occupation, construction
costs or eliminating effect of hydrogen and phosphor. Especially in cold area in winter
with frozen conditions, traditional stabilization pond usually doesn’t run and only
plays the role of water storage (such as the stabilization pond of Kelamayi
Municipality, Xinjiang). Wuliangsu Lake features high inlet water capacity in winter.
It’s calculated that present wetland area isn’t adequate in storage. Moreover, in frozen
period, inlet water pollutant especially nutritional nitrogen & phosphor salt is huge in
quantity. Objectively, eliminating efficiency of wetland in winter should be
guaranteed.
The survey of the departments of US on best management performance (BMPs)
of wetland in cold climate reveals that some special considerations are required for
the design and operation of wetland in frozen and snow blanket conditions. This is
because: in frozen condition, the depth and volume of water system will decline at
least by half, and the frozen earth layer of the surface of wetland is nearly water
resistant; water forcedly flows through water system and erodes substrate sludge; DO
declines, and water quality problem appears; and processing efficiency declines
sharply. Moreover, the initial thawed water of wetland features terrible water quality
and requires special treatment. Figure 5.1 includes the change of water flow and
substrate sludge in frozen condition.
Figure 9.1-1 Change of Water Flow and Substrate Sludge in Frozen Conditions
For shallow-water wetland (swamp), the ice layer of Wuliangsu Lake can reach
the thickness of 0.6-1.0 m, and is frozen by and large, where water is unable to flow.
Therefore, the cold condition is inapplicable. Pond and wetland system can be
applicable after renovation. In light of frozen condition in winter, extended pool
expands its depth and volume. Adequate flowing water layer is available under the ice
cover. The sewage treatment in ice cover condition is applicable. Generally, the
minimum extended storage capacity is no less than 25%, and extended pool should
have 50% storage capacity at least. Moreover, ice cover makes extremely low content
of dissolved oxygen in lower layer of water system. Aeration & re-oxygenation
measures can be taken for promoting the biological decomposing and transformation
of microbes. The comparison of different wetland systems is included in Table 6.3-1.
Table 6.3-1 Comparison of Different Wetland Systems in Cold Condition
Wetland
system
Over-wintering
performance Schematic diagram of wetland system
Shallow
water swamp Hard use in cold area
Pool
+wetland
system
Renovation required for
used in cold area
extended
wetland system
Good use in ice cover
condition
With expanded water depth & storage volume, the extended pool system has the
characteristics of anaerobic pond and facultative pond. Moreover, the aeration and re-
oxygenation in proper areas can not only improve eliminating efficiency of organic
substance but also facilitate nitration and anti-nitration of nitrogen and phosphor
dilution and absorption. Extended pool in cold area has the advantages as follows: (1)
good head preservation, lower layer with good over-wintering capability under the
impact of ice cover; (2) long residence time of water force, good pollutant eliminating
capability; (3) deep facultative pond is able to reduce the movement of oxygen; (4)
the multi-level small while deep ponds has low SS concentration of outlet water; (5)
deep pond facilitates the substrate sludge to become denser; and, (6) flexible
operation.
Wuliangsu Lake ices in November and thaws in March of next year with ice
cover period of over four months. In this period, total emission of pollutants is huge.
The calculation results of water quality and quantity data in May 2008- April 2009
reveal that in five months from December to April, the emissions of organic
substance, ammonia nitrogen, total nitrogen and total phosphorus are 0.6, 2.4, 1.1 and
1.5 times of the total in other months respectively.
6.3.1.2 “Ice Layer-Air Layer” Thermal Insulation Technique
Artificial wetland usually has terrible treatment effect in winter. To improve the
pollutant eliminating efficiency in low temperature conditions, “ice layer-air layer”
thermal insulation technique can be used. For example, in Figure 9.1.2, when ice layer
takes shape in some thickness in winter, the water lifting pump station is started, and
the operating water level of wetland declines by about 10-20cm for realizing the
purpose of preventing the heat dissipation of water system and improving the velocity
of biochemical reaction of microbes.
6.3.1.3 Oxygen Adding Technique under Ice The study proves that the aeration in front or back of wetland system can
obviously improve dissolved oxygen concentration in wetland, impact resisting load
capability of the system and eliminating efficiency of organic substance by over 10%.
The eliminating efficiency of NH4+-N and TN is obviously improved along the
direction of elevation and reaches up to about 60%. Relevant studies prove that
artificial aeration measures play obvious role in improving sewage treatment effect in
winter. J. Nivala holds that in winter, aeration measure and thermal insulating measure
can realize best treatment effect if applied together, where the eliminating rate of
BOD, COD and NH4+-N reaches up to 88%, 44% and 93% respectively.
An under-ice aeration device can be set up in Wuliangsu Lake wetland for
improving the eliminating efficiency of pollutants especially in frozen period in
winter. Under-ice aeration technique can be used according to local condition.
Figure 6.3.2 Schematic Diagram of Ice Layer-Air Layer Thermal Insulation and Under-ice
Aeration
6.3.1.4 Wetland Plant Configuration
In small sea-area land of Wuliangsu Lake, reed is outstanding variety and plays a
dominant role. Existing reed can be directly used as the wetland plant, instead of more
expenses for new plant. To improve the tourism value of local from the angle of
landscape, a series of landscape plants can be configured.
Wetland renovation needs higher water level in operation. The water level should
be controlled for realizing optimal pollutant eliminating water depth and maintaining
the growth rule of reed. According to the results of observations on three sampling
points of Wuliangsu Lake at 37 times, the distribution of reed at water depth of 0-
0.5m, 0.5-1.0m and 1-1.5m is 19%, 35% & 36% respectively, with an average of
0.91+0.13 m (95% reliable scope). It proves that reed isn’t fit for the area with 0-0.5m
water depth, and most reeds are fit for water depth of 0.5-1.0m. Therefore, the water
depth of wetland should be controlled at 0.5-1.0m.
6.3.1.5 Workflow of Extended Wetland System
The schematic diagram of the section of compound wetland is included in Figure
6.3-.3.
Figure 6.3-3 Schematic Diagram of the Section of Compound Wetland System
6.3.2 Inlet Water Quantity of Wetland in Winter and Water Quality
Analysis
6.3.2.1 Water Quantity Analysis
In winter, among three wetlands, only the general trunk ditch wetland runs.
Figure 6.3-4 presents the monthly quantity change of water that Liufenqiao of general
trunk ditch discharged into Wuliangsu Lake in 1996-2005. Figure 6.3-5 presents
monthly quantity change of water that Honggebo Water Lifting Station of general
trunk ditch discharged into Wuliangsu Lake in May 2008-April 2009. Due to the
impact of irrigation water consumption of Hetao Irrigation Area, the water quantity of
the general trunk ditch features obvious monthly change. The statistics on water
quantity in the following two charts reveals that the change of water quantity can be
roughly divided into three stages. In irrigation period of May-September, the quantity
of water discharge is huge. From June 2008 to September 2009, the quantity of
discharge remains at 49.50-66.48 million m3 monthly by and large; it’s highest in
October (less in October 2008) and November, and reaches up to 119 million m3 in
November 2008, accounting for nearly 24% of the total discharge of general trunk
ditch; and in non-irrigation period from December to April, the quantity of discharge
is least and about 10 million m3 monthly.
0
1000
2000
3000
4000
5000
6000
7000
8000
12月 1月 2月 3月 4月 5月 6月 7月 8月 9月 10月 11月
月份
水量(万方)
Figure 6.3-4 Monthly Quantity Change of Water that Liufenqiao of General Trunk Ditch
discharged into Wuliangsu Lake in 1996-2005
(The data in the figure is average value of the same months in one decade)
0
2000
4000
6000
8000
10000
12000
14000
2008年
5 月
2008年
6 月
2008年
7 月
2008年
8 月
2008年
9 月
2008年
10月
2008年
11月
2008年
12月
2009年
1 月
2009年
2 月
2009年
3 月
2009年
4 月
日期
水量(万方)
Figure 6.3-5 Monthly Quantity Change of Water that Honggebo Water Lifting Station of General
Trunk Ditch discharged into Wuliangsu Lake in May 2008-April 2009
6.3.2.2 Water Quality Analysis
Pollutant concentration of wastewater that general trunk ditch discharged into
Wuliangsu Lake in July, 2008-June 2009 is included in Table 6.3-2. The table proves
that pollutant concentration of the water has obvious seasonal change. The months
with obvious concentration increase are December to April of next year mainly
(where December is the transitional month from low pollutant concentration to high):
CODCr concentration is 86.5-186 mg·L-1, with an average of 135.3 mg·L-1; ammonia
nitrogen concentration is 8.7-35.6 mg·L-1, with an average of 22.5 mg·L-1; TN
concentration is 12.35-36.9 mg·L-1, with an average of 26.25 mg·L-1; TP concentration
is 2.04-7.05 mg·L-1, with an average of 4.2 mg·L-1. The change of pollutant
concentration in other months is stable: CODCr, TN and TP are 26-72 mg·L-1, 2.4-13.6
mg·L-1 and 0.23-1.7 mg·L-1 respectively, with average value of 44.4 mg·L-1, 4.81
mg·L-1 and 0.61 mg·L-1 respectively.
Table 6.3-2 Quality of Water that General Trunk Ditch discharged into Wuliangsu Lake from April
2008 to August 2009 (mg/L)
Month CODammonia
nitrogen TN TP
2008.4 186 18.2 6.15
2008.5 60 1.20 13.5 1.70
2008.6 26 1 3.4 0.73
2008.7 63 1.75 4.10 0.49
2008.8 55 1.60 2.90 0.23
2008.9 30.5 1.60 4.20 0.5
2008.10 41 0.80 2.40 0.31
2008.11 35 2.4 3.20 0.33
2008.12 86.5 8.7 12.35 2.42
2009.1 138 15 21.5 4.50
2009.2 148 32.8 33.8 7.05
2009.3 156 35.6 36.9 5.01
2009.4 148 20.4 26.7 2.04
2009.5 52 1.6 5.09 0.72
2009.6 37 1.6 8.29 0.67
2009.7 72 8.3 13.6 1.13
2009.8 57 12.2 16 0.61
The calculation results of water quality and quantity data in May 2008- April
2009 reveal that in five months from December to April, the emissions of organic
substance, ammonia nitrogen, total nitrogen and total phosphorus are 0.6, 2.4, 1.1 and
1.5 times of the total in other months respectively.
6.3.3 Accident analysis on Abnormal Operation
6.3.3.1 Risk Accident Simulation
According to the identification of risk source of this project, inlet water is
directly discharged with no treatment when wetland doesn’t run. According to the
inlet water quantity and quality analysis of wetland, there’re two cases: the 1st is non-
freezing period, and the 2nd is freezing period.
1)Risk Analysis Model
Hydraulic mathematical model has 0D, 1D, 2D & 3D equations. 0D model is
used for water quality prediction in most simple and ideal status. 1D model is used in
average flow parameter of a section, takes into account the change of parameters
along the vertical direction. 2D model not only has the features of 1D model but also
considers the change of parameters along the horizontal direction. 3D model using
“point” flow parameter takes into account the change of parameters not only along the
vertical and horizontal directions but also the perpendicular direction. Obviously, 3D
model is much more complicated than other models.
When the ratio between sewage and clean water is 1:10 or over 1:20, only
dilution instead of decomposing is considered. Completely uniform mixture is
realized within the section. In this case, the issue is 0D. The daily inlet water of
wetland is 0.333-2.116 million m3, much less than water quantity of the whole sea
area. Therefore, 0D hydraulic mathematical model is selected.
2) 0D Basic Hydraulic Equation
If we treats one water body such as one river, one reservoir, lake or water area as
complete system, various water masses in the system are completely mixed evenly.
The substance flowing into the system is immediately scattered in the whole system.
This closed consecutive flow & completely mixed reaction system is an ideal status.
The following mass balance relationship under the mass conservation principle is
(Figure 6.3-6)
Figure 6.3-6 Calculation Cell of 0D Model
Where,
V—volume of the system, m3;
C0, C—pollutant concentration of the system and inside the system, mg L-1;
S—Other source and loss of the system, mg d-1;
k—Reaction rate constant of pollutant in the system, d-1.
The equation (9.3-1) is the basic equation of hydraulic 0D model. With no other
source and loss in the system, S=0, and the equation formula becomes:
Formula 1 becomes:
Where Q is flow amount, m3 s-1.
After sewage enters the river, pollutants are completely uniformly mixed on the
section when inlet water from upper reach isn’t equal to zero. Pollutant indicator
value no matter dissolved status, particle status or total concentration can be derived
under node balance principle. The node balance principle includes node mass balance
and water quantity balance i.e. the sum of inlet water quantity and mass of the node
equal to the sum of outlet water quantity and mass of the node.
For point source, the dilution & mixing equation of river water and sewage is:
Where: C—water quality concentration of complete mixture (mg L-1);
Qp, Cp, —upper-reach inlet water quantity and quality concentration (m3 s-1, mg L-
1);
Qe, Ce, —sewage discharge flow amount and discharge concentration (m3 s-1, mg L-
1).
Due to linear overlay of pollution source functions, the emission impact of more
than one pollution source on node is equal to a sum of individual impacts of various
pollution sources. This complies with the linear overlay relationship.
6.3.3.2 Predictions on the Result of Risk and Accident
1) Prediction on the Result of Risk and Accident in Winter
The wetland system of general trunk ditch annually discharges 424 million m3
water into Wuliangsu Lake, including 63.6 million m3 in winter, accounting for 15%
of the total. In case of risk and accident, untreated sewage is directly discharged into
Wuliangsu Lake through rubber dam, with discharge amount of 5 million m3, with
CODCr concentration of 112.7mg/L, NH3-N concentration of 18.9mg/L, TN
concentration of 21.6 mg/L and TP concentration of 3.86 mg/L(9.2-1). The water
storage capacity of Wuliangsu Lake is 360 million m3, with CODCr concentration of
67.1mg/L, NH3-N concentration of 15.9mg/L, TN concentration of 19.9 mg/L, TP
concentration of 0.77 mg/L (5.2-1). If the above-said values are used in the formula
9.3-3, the concentrations of CODCr, NH3-N, TN and TP are 67.7 mg/L, 15.94mg/L,
19.92 mg/L and 0.81 mg/L respectively. Obviously, leakage has no decisive impact
upon the water quality of sea area.
2) Prediction on the Result of Risk and Accident in Summer
The wetland system of general trunk ditch annually discharges 424 million m3
water into Wuliangsu Lake including 2756 million m3 in summer, accounting for 65%
of the total. In case of risk and accident, untreated sewage is directly discharged into
Wuliangsu Lake through rubber dam, with discharge amount of 10 million m3 with
CODCr concentration of 73.2mg/L, NH3-N concentration of 8.82mg/L, TN
concentration of 13.94 mg/L and TP concentration of 1.034 mg/L(9.2-1) . The water
storage capacity of Wuliangsu Lake is 560 million m3, with CODCr concentration of
38.1mg/L, NH3-N concentration of 0.955mg/L, TN concentration of 2.83 mg/L, and
TP concentration of 0.098 mg/L (5.2-1) . If the above-said values are used in the
formula 9.3-3, the concentrations of CODCr, NH3, TN & TP are 38.4 mg/L, 1.06mg/L,
2.94 mg/L & 0.106 mg/L respectively. Obviously, leakage has no decisive impact
upon the water quality of sea area.
7 Comparison, selection and analysis of substitute plans
7.1 Content and principle of comparison, selection and analysis
Comparison, selection and analysis of substitute plan of this project shall mainly
be done by three aspects: (1) Comparison, selection and analysis of zero plan; (2)
Comparison, selection and analysis on construction site of plant; (3) Comparison,
selection and analysis on technical plans.
The general principles of comparison, selection and analysis of substitute plans
are:
(1) Quantized comparison and selection principles: As to each substitute plan,
the impact of project execution to environment shall be quantized to the greatest
extent.
(2) Integrated comparison and selection principle: The integrated comparison
and analysis shall be carried out from the aspects of environment, technology,
economy, society, etc.;
(3) Consistency comparison and selection principle: The selected plan shall meet
the related plan and standard requirements, and meet local conditions.
7.2 Comparison, selection and analysis on zero plan
(1) Plan 1: Integrated treatment plan of water environment.
(2) Plan 2: No action and no project plan.
Advantages and disadvantages of above two plans are shown in Table 7.2-1.
Table 7.2-1 Comparison on execution of project and no execution of project
Advantages and
disadvantagesPlan 1 Plan 2
Advantages
1. Improve water environment, ecological
environment and investment environment
of Bayannur City, improve living
environment quality of people, and
promote the sustainable development of
Bayannur City;
2. Promote the improvement of waste
water treatment rate of Bayannur City,
reach the requirement of “notice on
strengthening urban water supply, water
saving and water pollution prevention and
protection work”; improve water
environment quality of Wuliansu Lake,
and protect the water environment of
Huanghe River;
3. Comprehensively dispatch and
distribute the water resource, improve the
utilization rate of water resource, and
improve the investment environment;
4. Meeting general planning requirement
of Bayannur City is one of the main
measures to control the water pollution;
5. Increase the investment of capital
construction, boost the demand of related
industry, provide more employment
opportunities, and promote the economic
development;
6. Most responder common people
support construction of this project, and
construction of project meets the
requirement of common people.
Maintain the water resource utilization
current situation, and waste water
treatment current situation and land
utilization current situation of processing
zone, and avoid various impacts of
construction period and operation period
in plan 1.
Disadvantages 1. Minor dust, waste water, noise, and
solid waste, etc., generated during
construction period shall destroy the
ground surface vegetation and incur soil
erosion; it temporarily increases the
transport pressure and destroys the
landscape of construction site;
2. Water reclamation plant, waste water
treatment plant and pump room, etc.
permanently occupy part land, and
1. With the industrial development of
Bayannur City, the sewage quantity is
increasing, a large number of sewage
without treatment shall be directly
discharged into the ground surface water
system, the pollution of water system shall
be worsened continually, and it shall
impact the living quality of residents and
sustainable development of economy.
2. The treatment rate of industrial sewage
change the utilization mode for such land.
The pollutant as waste water, noise,
offensive odor and sludge, etc., during
run of intended project construction shall
incur certain impact to environment in the
circumference;
2. Improve the treatment cost of water
supply and sewage, increase the outlay of
water consumption of enterprise;
is far below the environment protection
requirement of China, and this seriously
restricts the economic development of
Bayannur City;
3. The groundwater is exploited greatly,
the level of groundwater is continually
decreased, forming underground funnel. If
this situation is continued for a long term,
in the future there shall have no water for
exploitation, water environment quality
shall be further worsened, and this shall
impact the residential environment of
residents in the circumference of drainage
area.
4. The worsening of water quality of water
environment of Wuliansu Lake is speeded
up, paludification process is speeded up,
wetland function disappears, and
destruction speed of ecological
environment is speeded up, and this
threats the safety of water environment of
Huanghe River.
5. It does not meet the requirement of
general planning.
According to table 7.2-1, after execution of plan 1, although it shall incur certain
environmental impact during construction and operation of this project, these impacts
are limited by time and space aspects, through various measures the impact can be
eliminated or reduced to the greatest extent, and shall not incur unfavorable impact of
large area to regional environment, furthermore, execution of plan 1 can change the
current situation of pollution of water environment of Bayannur City,
comprehensively dispatch and distribute the water resource, improve regional
ecological environment, improve the living environment quality of people, promote
the sustainable development of Bayannur City, and this also meets the requirement of
vast common people. Thus plan 1 is deemed as reasonable during this appraisal.
7.3 Comparison, selection and analysis on substitute plan of
reclaimed water supply project
7.3.1 Comparison, selection and analysis on zero plan of reclaimed
water supply project
The key point of analysis of this plan is to compare the impact degree of
execution/non-execution of this project to the environment according to viewpoint of
improvement of environment.
Plan 1: Plan of reclaimed water supply project
Plan 2: No action and no project plan
The advantages/disadvantages of above two plans are shown in Table 7.3-1.
Table 7.3-1 Comparison on plans of execution/non-execution of project
S/
NPlan 1 Plan 2
1
Build up the reclaimed water supply project,
reduce the mining quantity of groundwater,
ensure the water consumption of industry, and
promote the development of each processing
zone.
The groundwater is exploited in large
number, forming underground
funnel, if this situation is continued
for a long time, it shall have no water
for exploitation.
2
Improve the situation of gradual drop of
groundwater level, reduce discharge of
pollutant, improve water environment quality
of Wuliansu Lake, and improve living
environment of drainage area in the
circumference.
When economy is developed, the
groundwater level gradually drops,
quality of water environment is
further worsened, and this shall
impact the living environment of
residents in the circumference of
drainage area.
3
It meets the general planning requirement of
Bayannur City, the water resource is generally
dispatched and distributed to improve the
utilization of water resource and improve the
investment environment.
Maintain the current situation, in the
development of next step it shall
impact the local investment
environment.
4
Improve the industrial water supply issue,
promote the economic development of
Bayannur City, improve the living quality of
local resident, and this shall be in favor of
good development of social relationship.
Maintain the current situation, if it is
continued for a long term it may
impact the local economic
development, and not be in favor of
social development and progress.
5 Minor dust, waste water, noise, and solid
waste, etc., generated during construction
No
period shall destroy the ground surface
vegetation and incur soil erosion; it
temporarily increases the transport pressure
and destroys the landscape of construction site;
6
The new building structure permanently
occupies part land, and change the utilization
mode of such land.
No
According to Table 7.3-1 it can be seen that, after execution of plan 1, it may
incur certain environmental impact to project construction and operation, but these
impacts are limited by time or space, through various measures the impacts can be
eliminated or reduced to the greatest extent, and shall not incur unfavorable impact to
large area of regional environment. Furthermore, execution of plan1 shall reduce the
exploitation of groundwater resource by 51.024 m3 and avoid the further drop of
groundwater level, reduce the funnel of groundwater. The water resource shall be
generally dispatched and distributed to ensure the water consumption of industry.
Furthermore, execution of plan 1 can improve the water environment current situation
of Bayannur City, after completion of project, it can reduce the discharge to drainage
area by CODcr 2847.0t/a 、 BOD 1335.9 t/a , ammonia nitrogen 491.29t/a, and
improve the regional ecological environment; Improve quality of living environment
of people, promote sustainable development of Bayannur City, and this also meets the
requirement of vast common people. Thus in this appraisal, this project is deemed as
reasonable.
7.3.2 Comparison, selection and analysis on restoration process of
reclaimed water supply project
The process of reclaimed water is generally fairly matured.
Under precondition of ensuring quality of effluent water, following two water
treatment process plans are selected to carry out comparison, selection and analysis
thereof:
Plan 1. General treatment process flow:
Raw water→ coagulating→ settling→ filtering→ sterilization
Plan 2. Membrane treatment process flow:
Raw water→ micro pore filtering→ sterilization
According to process flow charts of two plans it can be seen that, the difference
of two plans is that, the selection of main process is different. In plan 1 it adopts the
three section treatment process of flocculation, settling, filtering, and sterilization,
while in plan 2, it adopts the membrane technology. The following is comparison on
difference of two processes.
7.3.2.1 Comparison on technology
The flocculation, settling and filtering process can ensure the supply of
qualified treating water in the whole year, since the settling basin relieve the burden of
filtering basin, even the water quality is worst in winter, the filtering basin can also be
of normal run, the filtering period is over 10 hours, and the quality of treating water
can reach the stated water quality requirement.
The process is also the main reclaimed water treatment process widely utilized
in domestic and abroad, considering of low temperature of winter in local region, the
treatment effects of flocculation, settling, filtering and sterilization (old three sections)
are compared, and the details are shown in Table 7.3-2. Table 7.3-2 Treatment efficiency of coagulating, settling and filtering
Item
Treatment efficiency (%)Effluent water quality
(mg/l)Coagulating and
settlingFiltering Add up
Turbidity 50~60 30~50 70~80 3~5NTU
SS 40~60 40~60 70~80 5~10
BOD5 30~50 25~50 60~70 5~10
CODcr 25~35 15~25 35~45 40~75
Total nitrogen 5~15 5~15 10~20 -
Total phosphorus 40~60 30~40 60~80 0.5
Fe 40~60 40~60 60~80 0.3
In recent years, membrane technology (plan 2) application is wider and wider,
and the membrane for water treatment contains following types osmosis membrane
(RO), nanometer membrane (NF), ultrafiltration membrane (UF) and micro-filtration
membrane (MF).
Fig. 7.3-1 Sketch of membrane treatment technology
CMF membrane is one of the micro filtration membranes; it is the hollow fiber
with outer diameter of 550μ and inner diameter of 300μ. The wall of hollow fiber is
composed of multi-pore materials, the pore size is all below 0.2μ, and area of pore
accounts for over 70% of fiber wall. The water without containing foreign substance
can easily penetrate the CMF fiber wall, and it only needs the work pressure of 20kPa
(2m water head). When the water containing foreign substance runs through the MF
hollow fiber membrane from outside to inside, the particle over 0.2μ is 100%
captured in the outer surface of membrane, and the one less than 0.2μ is also captured
by different proportions, and its work pressure is between 40~100KPa.
During work of CMF membrane, the captured foreign substance particles shall
gradually accumulate on the outer surface of hollow fiber, the pore is also gradually
covered, the resistance over the water gradually rises. In order to timely eliminate the
foreign substances captured, and reduce the resistance over the water, the hollow fiber
needs to be timely back flushed by cleaned air. The work status and back flush status
are shown in Fig. 7.3-2.
Water after filtration
Water before filtration Air
Captured foreign substance Eliminated
foreign substance Fig. 7.3-2 Work status and back flush status sketch
After each time back flush of air, the work pressure of membrane shall not
completely restore to its original status, and work pressure shall gradually rise. The
rising of this pressure is caused by the organic matter and scale formation attached on
the membrane surface, when pressure rises to certain value, it needs to carry out
chemical purge to surface of membrane, so as to eliminate the organic matter, Fe and
calcium scaling.
The indicators as strong bacteria elimination, water quality perception, and
hygiene, etc., of this process are superior to traditional process. Nevertheless, it has a
lot of one time investment with fairly high run cost, and it shall basically not improve
the indicators as soluble total solid, total hardness, total alkalinity, etc. Generally it is
reused for residential quarters or pretreatment of reverse osmosis and it is the rising
and new technology of China at present.
7.3.2.2 Comparison on economy Economies of plan 1 and plan 2 are compared, details refer to table 7.3-3.
Table 7.3-3 Comparison on economies of plans
process
ItemPlan 1 Plan 2
Total investment (ten thousand Yuan) 1573.13 3883.61
Total cost (ten thousand Yuan) 355 654.6
Unit treatment cost (Yuan/m³· water) 0.468 0.897
Operation cost (ten thousand Yuan) 275 434.36
Unit operation cost (Yuan/m³· water) 0.377 0.595
Power consumption (kwh/ m³· water) 0.19 0.24
According to comparison on technology and economy as above mentioned, it is
know that in plan 1 it has fairly good treatment effect, it can ensure the water quality
of reclaimed water with a little higher investment, in plan 2 the treating water quality
is good, but the investment and operation cost are both too high. According to
requirement of effluent water of reclaimed water supply work of this project, mainly
applying the process flow of plan 1 can meet the requirement. As above mentioned,
the process flow of plan 1 is to adopt the process of coagulating, settling, filtering and
sterilization as the main treatment of reclaimed water supply works. According to
water consumption requirements of enterprises of the processing zone, the reverse
osmosis process unit may be added appropriately. This process is featured by stable
and reliable treatment effect, appropriate investment and fairly low cost, and the
process flow of this project finally determined is shown in 7.3-3.
Fig. 7.3-3 Sketch of reclaimed water treatment process
7.3.3 Comparison, selection and analysis on process plans of
reclaimed water supply project
(1) Flocculation basin
Grid flocculation basin is the new type system developed in recent years with
application of turbulent flow theory, its plane layout is similar to perforated swirling
flow flocculation basin and is in series connected by multiple grids of vertical shafts.
The flocculation basin is divided to square grids with same or similar areas. The flow
sequence of influent water is from the first grid to the next one, and the flow is
alternated from up to down opposite angles up to the outlet. In the grids accounting
for 2/3 of the whole basin, the grid is setup via the vertical water flow direction, when
it passes through the grid pore, the water current is narrowed, after passing through
the mesh the water current is enlarged, constituting good flocculation condition, and
thus it can decrease the addition quantity of flocculation reagent and shorten the
flocculation time. The grid flocculation basin has good effect and little loss of water
head, flocculation time is fairly short. The disadvantage is that, it has the sludge
accumulated in the end basin bottom.
Bent plate flocculation basin is a new type and high efficiency flocculation
facilities developed in 1980s. The bent plate flocculation basin is to adopt the bent
plate placed in the flocculation basin, thus water current flows up and down between
the bent plates in-series connection. Relying on the partial eddy flow generated by
turning, narrowing and enlargement, the collision opportunity of particles in the water
Grid
flocculation basinLifting
pump
station
Sloping
plate settling basin
Filtration
basin
Contact
basin ClO2
Raw water Effluent water
PAM
current is increased, thus the fairly even energy consumption can be obtained along
the way, so as to constitute fairly ideal flocculation process. The bent plate
flocculation basin has the high utilization efficiency of energy, and short flocculation
time, nevertheless its availability to raw water with fairly great change of water
quality and water quantity shall be fairly bad.
After comparison on advantages/disadvantages of above two basin types, the
grid flocculation basin is finally selected as the design basin type of reclaimed water
supply works of this project.
(2) Settling basin
Horizontal flow settling basin has fairly wide application, and is especially
utilized in the water plant of urban area. The horizontal flow settling basin is the
rectangular one, the upper part is settling area and the lower part is sludge area, the
front area of basin is influent water area, and the rear part of the basin is the effluent
water area, after coagulating, the raw water flows into the settling basin, and is then
evenly distributed in the whole section of influent water area, it enters the settling area
and slowly flows into the outlet area. The particle in the water settles in the basin
bottom, the accumulated sludge is continually or periodically discharged outside the
basin. It has the advantages of simple structure, shallow basin depth, convenient
operation and maintenance, and strong adaptability to water quality and water
quantity of raw water, low consumption of drug and energy, and convenience of
sludge discharge, etc., in the big and middle level water plants it is widely utilized.
The disadvantage is that, the land occupancy is too great.
The slope plate settling basin is the one developed on the basis of shallow basin
theory. Various slope plates forming certain angle with horizontal plane are placed in
the settling basin, the water flows from downward to upward, and the particles settle
in the bottom of slope plate. When particles accumulated reach certain level, they
shall automatically slide down. The advantage of slope plate settling basin is that, the
settling efficiency is high, the volume is small, and the land occupancy area is small.
The disadvantage is that, the anti-impact capacity is inferior to that of horizontal flow
settling basin, with more material consumption and higher cost.
After comparison on advantages/disadvantages of above two basin types, the
slope plate settling basin is finally selected as the design basin type of this project.
(3) Filtration basin
The four valves filtration basin is the traditional one of filtering process of water
cleaning plant, till now it has over 100 years history, nevertheless it is also one of the
basin types with widest application till now. Its characteristic is that, it has stable work
status, good quality of effluent water, matured run experience, its operation is stable
and reliable, and it adopts the programmable controller to realize the one-step
operation; The shortcoming of the four valves filtration basin is that, the basin volume
is fairly great, the back flush water consumption is fairly great with more inlet and
outlet water valves and great work volume of maintenance. Adopting electrical valve
can realize the one-step automatic operation, but it cannot finely adjust the openness
of outlet water valve and control the filtering speed of filtration basin.
V type filtration basin is a new type one, and its advantage is that, the filtering
period is long, the fairly coarse and thick filtering material layer has high utilization
rate, the filtering speed is fairly high, and the water quality after filtering is good, with
the utilization of air-water back wash, the back wash effect is good with minor water
consumption. According to variation of water level of filtration basin, the openness of
outlet water valve can be finely adjusted, so as to reach the purpose of controlling
filtering speed of filtration basin. V filtration basin also has the advantages of good
quality of effluent water and fairly small volume of filtration basin. Its shortcoming is
that, it has fairly high automatic control requirement, with more back wash
equipments and fairly higher cost.
After comparing the advantages and disadvantages of above two basin types,
finally the V type filtration basin is selected for this design of this project.
7.3.4 Selection of sterilization mode
The microorganisms in the water are mostly attached on the suspended particles,
after treatment of coagulating, settling and filtering, the bacteria and virus in the water
can be greatly eliminated. Nevertheless, in order to ensure the bacteriology indicator
of drinking water, the sterilization process is necessary.
The sterilization treatment of water is usually the last work sequence of drinking
water treatment. The purpose of sterilization is to eliminate the hazard pathogenic
microbe (pathogenic bacteria, virus, etc.) in the water, and prevent from the hazard of
waterborne infection. It consists of chemical method and physical method, the
chemical method is to add chemical agent in the water, such as chlorine, ozone, heavy
metal and other oxidizing agent, etc. The physical method is to carry out heating
sterilization and ultraviolet ray sterilization, etc., instead of adding drug agent in the
water. The comparison on properties of various disinfectants is shown in Table 7.3-4. Table 7.3-4 Comparison on property of disinfectant
Disinfectant Property
Chlorine, and
bleaching powder
Chloramines chlorine dioxide Ozone Ultraviolet
radiation
Sterilization and bacteria elimination
ExcellentMiddle level,
inferior to chlorine
Excellent Excellent Good
Germ elimination Excellent Bad Excellent Excellent Good
Inactivation effect of
microorganism
3rd level 4th level 2nd level 1st level
Residual sterilization effect in the
water distribution
pipe network
Some
The residual chlorine
quantity can be kept for a fairly long
term
It has longer residual
sterilization time than chlorine
No, it needs to be added by chlorine
No, it needs to be added by
chlorine
Generation of byproduct
THM
It can be generated not probably not probably not probably not probably
Situation of domestic
application
Wide application
With minor application
With minor application With minor application With minor
application
Appropriate condition
Most water plants adopt
chlorine sterilization
, and bleaching powder is
only applicable to small
water plant.
When it has a lot of organic substances in the raw water, and the water
supply pipeline is
fairly long, it is appropriate
to adopt chloramines sterilization.
It is appropriate for
organic substance, for example, when
the phenol pollution is
serious, it shall be prepared at
site, and directly utilized.
The water treatment cost is high, and it is appropriate for the serious pollution of
organic substance. Since it does not have
continual sterilization effect, in the water of
inlet pipe network, minor chlorine shall be added for sterilization.
In the pipeline it does not have
continual sterilization effect. It is
appropriate for water treatment of centralized
users as industrial and
mining enterprises, etc.
According to above comparison and analysis, and considering of economy,
practicality and environmental impact, etc., the reclaimed water supply works of this
project adopt the chlorine dioxide for sterilization.
7.3.5 Comparison and selection on sludge treatment plans of
reclaimed water supply works
1) Selection on thickening and dehydration of sludge
Solid content of discharged sludge water of the settling basin of water plant is
usually only 0.2~1.0%, the sludge volume shall be reduced after thickening thereof,
and then the thickened sludge shall be sent to subsequent process to carry out
dehydration of sludge. Usually it is required that solid content of thickened sludge
shall be over 3%, so as to meet the requirement of the dehydrator for high efficiency
dehydration of sludge.
The general sludge thickening and dehydration contains two modes of gravity
thickening/mechanical thickening, and mechanical thickening/ mechanical hydration.
The gravity thickening is essentially a settling process and belongs to compression
settling. Prior to thickening, concentration of sludge is fairly high with mutual contact
and support among the particles. After thickening process is started, under the gravity
effect of the particles of upper layer, the water in the clearance of the particles of
lower layer is extruded from the interface, and congestion of particles is closer.
Through the congestion and compression process, the concentration of sludge is
further improved, so as to realize the sludge thickening. The advantage of the gravity
thickening and mechanical dehydration mode is that, the thickening basin greatly
reduces the volume of the sludge in need of hydration, and effectively decreases the
number of dehydrators, the equipment investment is greatly saved, the power
consumption is lowered, the concentration of dehydrated sludge is fairly even, and
dehydrator operation is stable. Its shortcoming is that, it needs to build up the
thickening basin, the civil cost is fairly high, and land occupancy area is fairly great.
While the mechanical thickening and mechanical dehydration mode is just the other
way, the thickening basin can be cancelled to save the land utilization area, reduce
civil cost, nevertheless, since the sludge number in need of dehydration is great with
low and uneven concentrations, the treatment capacities of thickening and
dehydration equipments are decreased, the number is increased, and thus the
equipment cost is greatly increased, with increase of power consumption, and the
solid content of the sludge cake is not stable.
As above mentioned, the technology of gravity thickening and mechanical
dehydration is superior to mechanical thickening and mechanical dehydration mode.
Civil cost of gravity thickening and mechanical dehydration is fairly high but
equipment cost fairly low, its total cost is lower than that of the mechanical thickening
and mechanical dehydration, although gravity thickening increases the land
occupancy area, in this project the high concentration thickening basin is adopted to
improve the effective settling area of the thickening basin, this saves the land
utilization without additional requisition of land. In this project, it intends to adopt the
gravity thickening and mechanical dehydration mode to carry out thickening and
dehydration treatment of sludge.
2) Basic structure and characteristic of sludge dehydration equipment
At present it mainly adopts three types of sludge dehydration machines as plate-
and-frame press filter, centrifugal dehydrator and Band type press filter. The basic
characteristics of three types of sludge dehydration equipments are respectively
briefed as below:
a. Plate-and-frame press filter
Plate-and-frame press filter is the pressurization and filtering equipment of
clearance operation and is widely utilized in the sectors of sugar making, pharmacy,
chemical industry, dyeing, metallurgy, coal washing, food and water treatment, the
solid and liquid are separated via the filtering mode, and this is a large/middle
separator with fairly wide adaptability for materials.
Box type press filter has fairly low requirement to solid content of the incoming
sludge, and 2%-3% shall usually be appropriate, while the solid content of outgoing
sludge is higher than that of band type press filter and centrifugal dehydrator, the run
process is the intermittent process of periodic operation of pump-in, pressing and
filtering of sludge, and elimination of sludge. Its shortcoming is that, the continual
operation is not available, according to blocking situation of filtering board, the filter
cloth needs to be washed by one time after certain run period, the filtering board or
rubber diaphragm are easy of damage and need to be frequently replaced, and the
equipment volume is large with high price.
b. Centrifugal dehydrator
Horizontal spiral sludge dehydrator is a complete set of unit consisting of
principal machine and auxiliaries. The unit is full closeness structure without leakage
and is available for continual run of 24 hours, its main structure characteristic is that,
it adopts fairly large length-to-diameter factor to extend the staying time of material
and improve the elimination rate of solid substance. It adopts the exclusive spiral
structure to reinforce the extrusion strength of spire upon the sludge cake, and
improve the solid content of solid cake. It adopts the advanced dynamic balance
technology to reduce the vibration; it adopts the unique differential rotation speed
regulation technology to increase the discharge torsion moment of spire and load
capacity.
The centrifugal equipment has high efficiency, small land occupancy, the
environment of machine room is clean, the complete set of unit adopts the advanced
automatic integration and control technology, the rotation speed and differential
rotation speed are stepless and adjustable. It has the safety protection and automatic
alarm devices, and its run is stable and reliable. The main shortcoming is that, the
noise is great, power consumption is high, the rotation blade, etc., has high
requirement of wearing resistance, the requirement for quality of manufacturing
material and processing accuracy is rigid, and the price is expensive.
c. Band type press filter
Band type press filter is a high efficiency solid and liquid separation equipment,
and its theory is that, the sludge after flocculation is repeatedly extruded and
compressed through the varied-direction bend between the roller systems, and tension
effect of filter band, shear force is generated accordingly and thus there is a relative
displacement for the sludge particles, and the free water and capillary water in the
sludge are separated to obtain the sludge cake with fairly high solid content, so as to
realize the dehydration of sludge. Its characteristic is that, it has high dehydration
efficiency, great treatment capacity, continual filtering, stable property, simple
operation, small volume, and small area of land occupancy.
The treatment capacity of band press filter is determined by the band speed and
filter band tension of dehydrator, and dehydration property of sludge, while the band
speed tension is also determined by the dehydrating effect required. Its disadvantage
is that, when the incoming sludge quantity is too great, or solid load is too high, it
shall lower the dehydrating effect. The homemade band dehydrator usually has fairly
small treatment capacity, sludge solid load is only 150 ~250kg/m·h, and treatment
capacity of imported high quality band dehydrator can be up to 250~400kg/m·h.
3) Type selection of sludge dehydration equipment
The above three sludge dehydrators have their own advantages and
disadvantages, during type selection it shall combine with project scale, site condition,
management level, and capital condition, etc., and mainly take into account the
reliability of equipment run, automatic degree of system, dehydrating effect of sludge,
building investment and treatment cost, etc., for reasonable selection of equipment
type.
Comparison on property of several common dehydrators is shown in Table 7.3-5.
Table 7.3-5 Comparison on properties of general dehydrators
M
odel
Item
Plate-and-frame press filter Band type press filter centrifugal dehydrator
Dehydrating
theoryPressure filtering
Gravity filtering and
pressurized filtering
Solid and liquid
separation is caused by
centrifugal force
Work status Intermittent Continual type Continual type
Adjustment
method
Regulate the pressurization time
and pressure size
Regulate the tension of
filter cloth and travel speed,
as well as the sludge layer
thickness entering pressure
area.
Regulate the rotating
drum and spiral conveyor
rotation speed difference,
and regulate the depth of
liquid ring.
Difficulty of
management
It is fairly complicated (the filter
cloth shall be replaced
periodically)
It is fairly convenient (the
filter cloth shall be
periodically replaced)
It is convenient (the
blade of spiral conveyor
is easy of wearing)
Environment
and hygiene
condition
The hygienic condition is
relatively bad
Open type, and hygienic
condition is bad
The full closeness
hygienic condition is
good
Noise Small Small Large (since the rotation
speed is high)
Land
occupancy area
and civil
requirement
Since its own volume is large
with a lot of auxiliaries, it has
large area of land occupancy, and
the civil requirement is high.
Compared with plate-and-
frame press filter, the land
occupancy area is fairly
small
Equipment is compact,
and land occupancy area
is small
Auxiliary
equipment
Air compressor system, filter
cloth flush high pressure flushing
pump system
Air compressor system,
filter cloth flush high
pressure flushing pump
system
It does not need the
auxiliaries
Automatic
degree
It has certain difficulty to realize
full automatization
It has certain difficulty to
realize automatization
It is easy to realize full
automatization
Solid content
of sludge cake30%-35% About 20% About 25%
Solid content
of filtered
liquor
Small (only about 0.02%) High (>0.05%)Fairly high (about
0.05%)
Stability of
sludge cakeGood Fairly bad Fairly good
Energy
consumption
(kwh/tDS)
20-40 10-25 30-60 (fairly high)
flocculating
agent
consumption
20%~30%CaO/SS Polyelectrolyte 3~4kg/tDSPolyelectrolyte 2
~3kg/tDS
The efficiency of sludge dehydration is directly related to selection of
dehydrating equipment, etc., the detailed selection of dehydrator type shall be
reasonably made after generally analyzing and determining the factors of technology,
economy, environment and management, etc., according to characteristics of sludge
and site condition.
The result of comparison and analysis on part configuration of dehydrator
equipment, solid content requirement of incoming sludge, solid content concentration
of dehydrated sludge, run status, operation environment, land occupancy of
dehydrator, flush water quantity, and replacement of wearing parts during actual run
of equipment, etc., shows that the discharged sludge of water plant has the
characteristics of relatively low solid content of compressed and dense sludge, and
fairly fine particle size of sludge, etc., among three machine types, price for plate and
frame machine is highest, and in turn is centrifugal dehydrator and band dehydrator.
According to treatment situation of sludge of water plant of China at present, and due
to the consideration of economic power of Bayannur City, band dehydrator is herein
recommended.
7.3.6 Comparison and selection of pipe material
Selection of pipe material has great impact to water supply quality, project cost
and water supply safety, thus it is very critical to select the pipe material, hereinafter
is the comparison on characteristics and properties of various pipe materials.
At present, the transportation and distribution water pipes generally utilized in
domestic and abroad mainly consist of steel pipe (SP), ductile iron pipe(DIP), glass-
reinforced plastic pipe(RPMP), prestressed steel concrete pipe(PCP), prestressed
concrete cylinder pipe(PCCP), etc. Various pipe materials have different
characteristics:
(1) spiral-seam submerged-arc steel pipe (SP)
SP has fairly good mechanical strength, and has great advantage in the aspects of
anti-bend, anti-tension, toughness, impact resistance, and anti-vibration, etc., and can
withstand the fairly high internal pressure and appropriate external pressure.
According to operation requirement it can be machined to different sizes, different
bores and different wall thicknesses, the joint forms are diversified, the holding and
jointing are convenient with great flexibility, and the construction is easy.
Nevertheless, its inner wall is easy of incurring scaling and impacts the water quality.
The internal insulation must be done well, such as cement liner. The biggest
shortcoming of SP is its bad anti-corrosion property, if the internal and external
insulation and electrochemistry protection is not perfect, the service life shall be fairly
short (20 years). The toughness of steel pipe is fairly great, at present, after general
cement coating and lining, the n value of roughness coefficient is usually considered
as 0.013 (manning formula) for design.
SP pipe has good mechanical strength and is available for machining, thus it has
great advantage when the geological condition is bad and when passing through
obstacles, and it is especially used for sunken pipe, pipe bridge (crossing over river)
and jacking of pipe (crossing over the road).
(2) Ductile iron pipe(DIP)
Raw material of DIP is also pig iron with carbon constituent of 3.5-4.0%.
Through spheroidization and annealing treatment after molding of pipe casting, the
stable and even fine texture is obtained with fairly high specific elongation.
According to standard of ISO2531, its specific elongation, tensile strength and water
pressure test, etc., are all equivalent to steel pipe, and its anticorrosion is superior to
that of steel pipe. The burying service life can be up to 50 years. DIP wall thickness is
fairly thin and is only about 55% of that of the grey cast iron pipe. Inner wall is coated
and sealed by cement. The roughness coefficient n is considered as 0.013(manning
formula) for this design. At present, the diameter of DIP pipe produced in domestic is
DN100~2600, it adopts the T form slide-in interface with water stop rubber ring, in
general foundation condition the base shall not be treated, the mechanical and
machining property is good, it can be welded, cut and bored.
(3) glass-reinforced plastic pipe(RPMP)
RPMP is a composite material pipe consisting of unsaturated polyester resin,
glass fiber and quartz sand filler. The pipe wall is divided to external protection layer,
reinforced layer, structure layer and liner layer according to different roles. The
mechanical strength can be sorted according to design requirement, and its nominal
rigidity is 2500 ~ 20000N/m2 and work pressure 0.4 ~ 2.5MPa. RPMP has small
specific gravity (only 1700 ~ 2200kg/m3) since the weight is light it is relatively
convenient for transportation and construction. The layer of inner wall contacting with
water is polyester resin, it has fairly small roughness, and n value is 0.0095~0.01 for
this design. Thus it can greatly lower the loss of water head and is not easy of scaling
and corrosion, it has no impact to water quality, and has no need of internal and
external insulation treatment. According to introduction, its service life shall be over
50 years. Joint of RPMP is usually socket connected or sleeve connected, with rubber
ring or reversely grouted by rubber for water-stop, it is not easy of incurring water
leakage and pipe explosion. Since the weight is light, it is more in favor of pipe laying
and installation, in most foundation condition, it has no need to make base, and it is
one of the ideal pipe materials for long distance water transportation.
RPMP consists of two processes of short fiber outer formwork centrifugal
manufacturing and long fiber inner formwork winding manufacturing, the rigidity of
the previous one is superior to the latter one, while the uneven settling resistance of
the latter is superior to the previous one. Both of them can meet the general operation
requirement of rigidity and withstanding of internal pressure, while the uneven
settling of pipe foundation is usually one of the main causes of pipe accident, at
present, the long fiber inner formwork winding manufacturing of RMPM has more
utilization in domestic.
(4) Prestressed steel concrete pipe(PCP)
PCP is composed of longitudinal and loop prestressed steel wire (reinforcement)
and coagulating earth, and its wall thickness is usually fairly large. Although its
mechanical strength is inferior to SP, it can withstand fairly great internal pressure, at
present, the common internal work pressure is below 1.0MPa, during ex-factory test,
the external pressure (bending) can be over 1000MPa. PCP has best anticorrosion
property without internal and external insulation, the service life is long and can be
over 50 years. According to report, the PCP with good manufacturing shall seldom
have the phenomenon of pipe explosion; hydraulic roughness of PCP is relatively
small, at present the designed flow speed coefficient C is 130 (Hazen-Williams
formula). In addition to corrosion resistance, the pipe is also not easy of incurring
scaling, and has no impact to water quality. The joint usually adopts the socket
connected type, with rubber ring water stop and convenient pipe laying, nevertheless
weight of PCP is great and not in favor of transportation and hoisting. Under general
foundation condition it may not be set by base.
PCP pipe price is fairly cheap, when the pipe diameter is less than or equivalent
to DN1000 and pipe work pressure less than 0.5MPa, it is an available pipe material.
(6) Prestressed concrete cylinder pipe (PCCP)
PCCP manufacturing is similar to PCP, and its difference is that, it adopts the
integrated steel sleeve (fairly thin) to substitute the longitudinal prestressed
reinforcement of PCP, thus it has better watertightness and is mostly of pipe of large
diameter, such as DN1400-DN4000; usually the wall thickness is fairly large, as
above mentioned, the wall thickness is respectively 100 and 270mm. the large
diameter PCCP adopts the double rubber ring for water stop, and this is greatly in
favor of water pump test. Other physical and chemical characteristics and construction
requirements of PCCP are similar to that of PCP.
Price of PCCP pipe is fairly cheap, with simple laying at site. It is a pipe material
with fairly good application for large diameter pressure water transportation pipe
works.
According to characteristics, anticorrosion and construction conditions, etc., of
above pipes, safety and reliability of water supply, water transmission pipe diameter
and laying condition for this project, the comparison on property of spiral-seam
submerged-arc steel pipe (SP), ductile iron pipe(DIP), glass-reinforced plastic
pipe(RPMP) and prestressed concrete cylinder pipe are shown in Table 7.3-6.
Table 7.3-6 Comparison on properties of various pipe materials
Item
Pipe material
spiral-seam
submerged-arc
steel pipe
Centrifugal ductile
iron pipe
Prestressed concrete
cylinder pipe
Fiberglass
reinforced
plastics sand
pipe
Water stop property Good Good Good Good
Construction site Small Large Fairly large Larger
Quality guarantee Good Good Good Fairly good
Construction
progressFast Slow Fairly fast Fairly fast
Acceptance test Easy Easy Easy Fairly easy
Service life Long Long Long Long
Friction resistance Fairly small Fairly small Fairly small Small
coefficient
Pipe material
transportationConvenient Difficult Fairly difficult Convenient
According to comparison and selection on properties and prices as above
mentioned, the centrifugal ductile iron pipe has the highest integrated cost, and in turn
is the spiral-seam submerged-arc steel pipe, and price of prestressed concrete cylinder
pipe and glass reinforced plastics sand pipe is cheapest. Considering of the safety and
reliability of water supply main pipe, ductile ion pipe is recommended for use.
7.3.7 Comparison, selection and analysis on plant site plan of
reclaimed water supply plant
Requirement and basic principle of plant site selection
(1) It shall to the greatest extent meet the requirement of near term planning and
development of the zone.
(2) It shall to the greatest extent shorten the distance between the intake pump
room and water supply area, thus the water supply layout is reasonable, this is in favor
of saving investment, lowering energy consumption and improving economic benefit.
(3) It has fairly good waste water discharge condition and meets the
environmental protection and ecological balance requirement.
(4) It has good engineering geological condition with minor relocation and does
not occupy or occupy less farmland.
(5) On the basis of convenience of construction and production, it shall to the
greatest extent take into account the convenience of work and living of employee.
(6) It is near to external power supply and this is in favor of saving the cost of
external power supply line.
7.3.7.1 Reclaimed water supply works of processing zone of Urat Rear Banner
According to industrial development and industrial water supply planning of
processing zone of Urat Rear Banner, at present there are two locations for selection
of reclaimed water supply plant, and general situation of two plant sites are described
as below:
(1) Near the pile No. 1800 of water transmission pipeline from general drainage
canal to processing zone (Plant site 1)
The plant site is about 3km away from the processing zone, in the circumference
it is all waste land, thus it shall not occupy the basic farmland, the landform is
smooth, and the relief condition is fairly simple. At the side of the selected plant site
is a road with convenient transportation condition.
(2) South east side of processing zone (Plant site 2)
The plant site is located in the south east side of processing zone, and is closely
adjacent to the planned sewage treatment works of the processing zone of Urat Rear
Banner, and is the planned land of sewage treatment of the processing zone, the
landform is fairly smooth, relief condition is fairly simple, it is closely adjacent to
processing zone with convenient transportation condition.
Two plant sites are analyzed by factors of technology, economy and
environment, etc.
Table 7.3-7 Comparison on advantage/disadvantage of intended plant sites
advantage/disadvantage Plant site
plan
Advantage Disadvantage
Plant site 1
①It is fairly near to water intake point, and the
turbid water transmission pipeline is short;
②The site is open and can meet the
requirement of extension of water plant in the
future; ③ The transportation is fairly
convenient.
①It is far away from the
processing zone, and the water
distribution pipeline is long;
②It is fairly far away from the
power plant, transmission and
distribution line is long and
cost is high; ③In the
circumference there is no water
channel and water ditch nearby,
and this is not in favor of
discharge of waste water of
plant site.
Plant site 2 ①The site is open without obstacle or
relocation; ②It is closely adjacent to planned
road with convenient transportation; ③It is
closely adjacent to processing zone, and the
water distribution pipeline is short; ④It is
closely adjacent to planned sewage treatment
①Its distance apart from intake
point is farther than that of
plant site 1, and turbid water
transmission pipeline is long.
plant, and this is in favor of discharge and
treatment of waste water of plant area; ⑤It is
fairly nearer to substation, transmission and
distribution line is short, and this saves the
investment.
According to comparison on plant site 1 and plant site 2, it can be seen that
advantage of plant site 2 is apparent, and the selection of plant site of this project is
located in the south east side of processing area, and is in the side of the planned
sewage treatment plant.
7.3.3.2 Reclaimed water supply works of drainage canal 3
Whether selection of water plant site is proper involves the reasonableness of the
whole water supply system, and shall directly impact the project investment,
construction period, operation and maintenance, etc.
According to site survey, the plant site of water reclamation plant of drainage
canal 3 is located in the downstream of the sewage treatment plant of drainage canal 3
and is adjacent to drainage canal 3. It is 800mm away from Shan-Qing Highway. The
plant site has following apparent advantages:
(1) The water quantity can be guaranteed, plant site does not suffer the threat of
flood, rainwater discharge inside the plant area is smooth. Plant site is closely adjacent
to drainage canal 3 and can contain the tail water of sewage treatment plant of
drainage canal 3, water quantity of water reclamation plant can be guaranteed, it is
close to industrial zone, and this is in favor of containing water for pipe network of
reclaimed water.
(2) The land utilization condition is good, the intended plant site is open and is
appropriate for long term development.
(3) The engineering geological condition is good.
(4) The hygienic and environment condition is fairly good and is in favor of set
up protection and prevention area. The planning in the circumference is mainly of
greening work, and it is forbidden to build up the project with fairly great pollution.
(5) It does not occupy the good farm land, the land utilization is basically of
waste land, land requisition and foundation treatment cost is relatively low, and it also
meets the national policies.
(6) The transportation is convenient, and construction, run and maintenance are
convenient.
7.3.3.3 Reclaimed water supply works of drainage canal 7
According to site survey, in this feasibility research report, the site of water
reclamation plant of drainage canal 7 is located in the downstream of sewage
treatment plant of Wuyuan County and is adjacent to drainage canal 7. The plant site
has the following apparent advantages:
(1) Water quantity can be guaranteed, the plant site does not suffer the threat of
flood. Plant site is closely adjacent to drainage canal 7 and can quickly contain the tail
water of sewage treatment plant of Wuyuan County, water quantity of water
reclamation plant can be guaranteed,
(2) The land utilization condition is good, the intended plant site is open and is
appropriate for long term development.
(3) The engineering geological condition is good.
(4) The hygienic and environment condition is fairly good and is in favor of set
up protection and prevention area. The planning in the circumference is mainly of
greening work, and it is forbidden to build up the project with fairly great pollution.
(5) It does not occupy the farm land, the land utilization is basically of waste
land, land requisition and foundation treatment cost is relatively low, and it also meets
the national policies.
(6) The transportation is convenient, and construction, run and maintenance are
convenient.
Thus in the environmental appraisal report, it is deemed as the better selection of
plant site for water reclamation plant of drainage canal 7.
7.3.3.4 Reclaimed water supply works of processing zone of Ganqimaodu port
According to industrial development and industrial water supply planning of
processing zone of Ganqimaodu port, at present there are two locations for selection
of reclaimed water supply plant, and general situation of two plant sites are described
as below:
(1) Near Wangba reservoir (Plant site 1 )
The plant site is about 14km away from the processing zone, in the
circumference it is all waste land, thus it shall not occupy the basic farmland, the
landform is smooth, and the relief condition is fairly simple. At the side of the
selected plant site is a road with convenient transportation condition.
(2) Within the processing zone (Plant site 2)
The plant site is located in the south east side of processing zone, and is closely
adjacent to the planned sewage treatment and reuse works of the processing zone of
Ganqimaodu Port, the landform is fairly smooth, relief condition is fairly simple, it is
closely adjacent to processing zone with convenient transportation condition.
Two plant sites are analyzed by factors of technology, economy and
environment, etc. as below:
Table 7.3-8 Comparison on advantage/disadvantage of intended plant sites
Advantage/disadvantage Plant site
plan
Advantage Disadvantage
Plant site 1
①It is fairly near to water intake point, and the
turbid water transmission pipeline is short;
②The site is open and can meet the
requirement of extension of water plant in the
future; ③ The transportation is fairly
convenient; ④There are a lot of waste lands in
the circumference, and this is in favor of
building up evaporation pond and lower the
cost thereof.
①It is far away from the
processing zone, and the water
distribution pipeline is long.
Plant site 2
①It is closely adjacent to processing zone, and
the water distribution pipeline is short; ②It is
closely adjacent to planned sewage treatment
plant, and this is in favor of discharge and
treatment of waste water of plant area.
①Its distance apart from
intake point is farther than that
of plant site 1, and turbid water
transmission pipeline is
long.②The land requisition
cost is more than that of plant
site 1.
As above mentioned, when compared with plant site 2, the advantage of plant
site 1 is apparent, and the plant site of the project is located in the circumference of
Wangba reservoir.
7.4 Comparison, selection and analysis on substitute plan of
sewage treatment and reuse item
7.4.1 Comparison and selection on zero plan
In this plan, the key point is to compare the impact degree of execution/non-
execution of this project to the environment according to viewpoint for improving
environment.
(1) Plan 1: Sewage treatment plant and reuse works plan
(2) Plan 2: No action and no project plan.
Comparison on advantages/disadvantages of above two plans is shown in Table
7.4-1.
Table 7.4-1 Comparison on plans of execution/non-execution of this project
S/N Plan 1 Plan 2
1
Perfect drainage network of zone, relieve the short
supply of local water resource, and ensure the
standard discharge of urban sewage.
The sewage is directly discharged without
treatment, and this is far below the national
environmental protection requirement.
2Improve the water quality of each drainage and
irrigation channel of Hetao Region.
Maintain the current situation and impact the
living environment of residents of the drainage
area.
3
Minor dust, waste water, noise, and solid waste,
etc., generated during construction period shall
destroy the ground surface vegetation and impact
the ecological environment as well as destroy the
landscape of construction site;
No
4
The project construction permanently occupies
part land, and changes the utilization mode for
such land.
No
According to table 7.4-1, after execution of plan 1, although it shall incur certain
environmental impact during construction and operation of this project, these impacts
are limited by time and space aspects, through various measures the impact can be
eliminated or reduced to the greatest extent, and shall not incur unfavorable impact of
large area to regional environment, furthermore, execution of plan 1 can reduce the
discharge of pollutant of drainage area by CODcr 10950.0t/a, BODcr6022.5t/a, and
ammonia nitrogen 730.0t/a, it is in favor of improving regional water environment
and investment environment of urban area, extending the business invitation and
investment attraction, and sustainable and stable development of economy. According
to viewpoint for promoting social and economic development and protection of
environment, plan 1 is superior to plan 2, and the construction of project is necessary.
7.4.2 Comparison and selection on sewage treatment process plan
According to feasibility research report, the discharge of effluent water of
sewage treatment plant conforms to A standard of grade 1 of “pollutant discharge
standard of sewage treatment plant of urban area”, after grade2 treatment of the
sewage, it needs to be further treated to meet the discharge standard of standard A of
grade 1. Effluent water quality indicator of sewage treatment plant is compared with
indicator of reclaimed water, and effluent water after further treatment can meet the
reuse standard of reclaimed water.
7.4.2.1 Comparison and selection on grade 2 biological treatment process
According to the predicted influent water quality of sewage treatment plant of
this project in feasibility research report, and the discharge standard requirement of
effluent water, in this project it adopts the grade2 biological treatment process with
functions of eliminating organic pollutant and suspended solid, as well as nitrogen
and phosphorus elimination.
According to development of sewage treatment technology in abroad and abroad,
the various processes of A2O process, oxidation ditch process, and SBR process, etc.,
not only have the function of eliminating organic pollutant, but also have different
nitrogen elimination effect. In the “urban sewage treatment and pollution protection
and prevention technical policy” printed and issued by construction ministry, national
administration of environmental protection, and science and technology ministry, it is
recommended that A2O process, oxidation ditch process, and SBR process shall be
used for grade2 biological treatment process aiming at sewage treatment plant with
scale of sewage quantity below 100000m³/d.
According to various technical properties of processes, construction scale of this
project, influent water characteristics, treatment requirement and local situation, in
this appraisal it intends to select the SBR series CAST process and composite A/A/O
process as the comparison and selection plan for sewage grade 2 treatment of this
project.
(1) CAST process (Plan 1)
Periodic circle type activated sludge method (CAST process) is a transformation
of intermittent activated sludge method. The biological degradation and sludge water
separation processes are completed in one or multiple ponds with parallel run and
variable reaction volume. Thus in this process it does not need to set the separate
settling basin. In this system, activated sludge is continually repeated by “aeration—
non-aeration”. In the stage of aeration it is mainly to complete the biological
degeneration process, in the non-aeration stage, although it has part biological effect,
it is mainly to complete the sludge water separation process. In circulated activated
sludge method process, the treatment process is completed as per sequence of “water
filling— discharge” and “aeration—non-aeration”, it belongs to sequencing batch
activated sludge method.
Each operation circulation of this process is composed of influent water/aeration
stage, settling stage, decantion stage and idle stage, each state constitutes a circulation
and is continually repeated. When the circulation is started, the incoming of sewage
enables the water level in the pond start to rise from the lowest level. After some
time’s aeration and mixing, the system stops the aeration so that the activated sludge
in the reactor carries out flocculation settling, and activated sludge shall settle in the
static environment. After completion of settling stage, the supernatant at the upper
part of the pond is discharged outside the system by decanter, at the same time the
level shall drop to initial depth. Then the system shall repeat the above processes.
Main advantages of CAST process:
①The process is advanced and simple; the treatment building structure is small
and equipment number is small. Compared with A/A/O process it does not have
secondary settling basin, the SBR process sludge adopting delay aeration is relatively
aerobic and stable, and has no need to carry out treatment of anaerobic digestion, thus
it has no need to set up building structures of anaerobic digestion system for sludge,
etc., the operation management is convenient; it has very high phosphorus and
nitrogen elimination effect, the process run is stable, and effluent water quality is
good.
②It does not have expansion of sludge, and growth of filamentous bacteria can
be restricted.
③It has the double advantage of complete mixing type and plug flow aeration
basin, and can bear the fairly great impact load of water quantity and water quality
change, and the treatment effect is stable.
④The output of sewage is small, the sludge can be gradually aerobic and stable,
the number of sewage treatment building structure is small, and the sludge only needs
to be thickened and dehydrated.
Main disadvantage of CAST process:
①In the periodic circular activated sludge method, the reaction basin has fairly
high requirement of automatic control, and high requirement of reliability of
equipment.
② The run effect in the low temperature is not stable.
③Idle rate of equipment is high.
(2) A/A/O process (Plan 2)
A/A/O process is anaerobe—oxygen deficient—aerobic activated sludge method.
In front of aerobic area it is designed by oxygen deficient area and anaerobe area
which shall respectively realize the anti-nitration nitrogen elimination and phosphorus
elimination function. When the sewage passes through three different function areas,
under the effect of different microorganism bacteria group, the pollutants in the
sewage as organic substance, nitrogen and phosphorus, etc., are eliminated.
When it has sufficient sludge age condition, BOD5 in the sewage shall at first be
degenerated in the aerobic basin, and at the same time the nitration is completed, the
sewage after nitration is lifted by reflux pump into the oxygen deficient basin to carry
out anti-nitration and nitrogen elimination. Through the effect of backflow sludge for
greatly absorbing phosphorus, the element of phosphorus is eliminate. The integral
process includes following processes:
Assimilation process, some part of ammonia and nitrogen in the sewage are
assimilated into new cell substance, and eliminated via the form of residual sludge.
The assimilation works is the process to eliminate the organic substance, and some
part of nitrogen can be eliminated even there is no specific biological nitrogen
elimination measure.
Nitration process; The nitrifying bacteria shall oxidize the ammonia and nitrogen
in the sewage into nitrate nitrogen.
Anti-nitration process, in the oxygen deficient environment and with
participation of denitrify bacteria, the nitrate is deoxidized to nitrogen and emitted to
atmosphere. The nitrogen effect of anti-nitration design is determined by the reflux
ratio of activated sludge, usually 100%~150% can meet the requirement.
At the same time under the anaerobic condition, the phosphorous accumulating
bacteria in the sludge is activated to release the phosphate in its body, so as to
generate the energy to absorb the organic substance which can be quickly
degenerated, and then it shall be converted to PHB for storage. After entering the
aerobic area and when the oxygen is sufficient, the phosphorous accumulating
bacteria consumes the PHB stored in its body to generate the energy, which shall be
used for cell synthesis and phosphorus absorption, the sludge containing high
concentration of phosphorus is generated, and shall be discharged outside the system
together with the residual sludge, so as to reach the purpose of biological elimination
of phosphorus.
Since the treatment of sewage is mainly of industrial waste water, it has bad
biological and chemical treatment ability, sometimes it may have the deficiency of
carbon and nitrogen source and has great impact load. During early stage the water
quantity is small, water quality is low, according to local climate condition and on the
basis of A/A/O, part filler and chemical auxiliaries are added to meet the high
treatment effect, stable and low energy consumption status under different conditions.
(3) Integrated comparison
For the convenience of comparison on two plans, it is compared and analyzed by
two aspects as technology and economy, details refer to Table 7.4-2.
7.4-2 Integrated comparison on technology and economy
S/N Comparison on items CAST process (Plan 1)
A/A/O process (Plan 2)
Economic indicators
Total investment of project (ten thousand Yuan)
13782 13492
Employment fixed number (person) 32 32Tonnage water and power consumption (KWH/m³)
0.39 0.37
Land occupation (hectare) 11 11Annual production cost (ten thousand 1690 1654
S/N Comparison on items CAST process (Plan 1)
A/A/O process (Plan 2)
Yuan)Production cost (Yuan/ m³) 1.83 1.79
Annual operation cost (ten thousand Yuan)
937 917
Unit water quantity production cost (Yuan/ m³)
1.01 0.99
Technical indicator
Process flow Simple SimpleTreatment effect Stable StableEffluent water quality Good GoodPhosphorus and nitrogen elimination effect
Good Good
Impact load resistance capacity Strong StrongOperation management Fairly
complicated Simple
Requirement to technical level of operation personnel
Fairly high Fairly low
Building structure Small More Machine and equipment Fairly small Fairly small
According to above analysis it is know that, two processes can both meet the
effluent water quality requirement of sewage treatment plant, nevertheless, A/A/O
process has strong impact load resistance capacity, adapts to cold climate of project
area, and has low technical requirement to operation personnel, furthermore, when
compared with CAST process, A/A/O process has lower total investment of project,
and lower annual operation cost and annual run cost, etc., thus in this project, it is
recommended that A/A/O process of plan 2 is utilized for each sewage treatment
works of processing zone.
7.4.2.2 Comparison and selection on plans of reclaimed water treatment process
In this project, the sewage treatment works of processing zone adopts the three
section process (coagulating, settling, filtering) for reclaimed water treatment, each
section of process can be selected, and comparison on each section of process is
below:
(1) Coagulating
Coagulating process contains mixing and reaction.
①Mixing
Mixing is the precondition to obtain the good coagulating effect, and also the key
to save the agent quantity. It usually adopted the mechanical fast mixing and hydraulic
mixing, in recent years it mostly adopts the tubular static mixer which is a equipment
with small land occupation and good mixing effect, and is widely utilized in domestic.
The engineering practices prove that, this mixing unit has a lot of advantages, and
thus the tubular static mixer is herein recommended.
②Reaction
The reaction and flocculation process is the most critical link of water supply
treatment, and effect of flocculation shall directly impact the settling effect, gas
flotation effect and quality of effluent water. In this project it adopts the vertical
mechanical reaction basin, bent plate reaction basin, small mesh grid reaction basin to
carry out comparison on plans, details refer to 7.4-3.
7.4-3 Comparison on plans of reaction basinBasin type Item
Vertical mechanical
reaction basinBent plate reaction basin Small mesh grid reaction basin
Technical comparison
Main advantages
1. It has very strong
adaptability to change of raw
water
1. It has wide application, and is
featured by new type, high efficiency, small
land occupancy, appropriate investment,
and fairly high consumption of reagent.
2. It adopts the fixed type ABS product with fairly long service life
and convenient installation.
3. It does not need to be added by equipment,
and the maintenance and management are
convenient.4. It has strong anti-
impact capacity, and the appropriate scope of water quality is wide.
1. It is featured by new type, high efficiency, small land occupancy,
low investment, low agent consumption, and potential.2. It has strong anti-impact
capacity, and the appropriate scope of water quality is wide.
3. It does not need the mechanical equipment, and the maintenance and management are convenient.
4. It adopts the ethylene-propylene copolymers plastics grid board with same specs in
favor of installation and maintenance.
5. The reaction basin already has the matured design, installation
and run experience.
Basin type Item
Vertical mechanical
reaction basinBent plate reaction basin Small mesh grid reaction basin
Main disadvantage
s
1. land occupancy is
great.2. The power
consumption is higher than that of other basin
types.3. It has
mechanical equipments,
and the maintenance work volume
and run cost are added.4. The
investment cost is high.
1. The construction and installation are troublesome.
1. The application time of this technology is relatively short.
According to above comparison it is know that, the advantage of vertical
mechanical reaction basin is not apparent in this project, in addition to high total
investment and great power consumption, it is added by a lot of maintenance and
management work, and its land occupancy is great, thus it is not recommended. The
mesh grid reaction basin has the advantages of new type, high efficiency, potential,
small land occupancy, low investment and low reagent consumption, furthermore, this
system has been successfully run in the north regions of Moudanjiang City, Daqing
City, and Dalian City, etc., thus in this project, the small mesh grid reaction basin is
recommended.
(2) Settling
The settling means the process to eliminate the solid particle in the suspension
liquid via the precipitating action of gravity. In the water cleaning process, in order to
reach the purpose it usually adopts the treatment building structures as horizontal flow
settling basin, slope tube settling basin, slope plate settling basin, and comparison on
plans of three basin types are shown in Table 7.4-4.
7.4-4 Comparison on plans of settling basin.Basin type Item
Horizontal flow settling basin Slope tube settling basin Slope plate settling basin
Technical comparison
Main advantages
1. The treatment effect is stable, and the adaptability to raw water is strong. 2. The run experience is rich and the management is convenient. 3. It is easy of arrangement in the narrow and long plant site.
1. The treatment effect is good and the land occupancy is small. 2. It is placed in indoor conditions, and the investment is lower than horizontal flow settling basin.
1. It has very good treatment effect, settling time is short, land occupancy is small, and hydraulic condition is good. 2. The water id distributed at the short side, and the water is collected at tail end by same process and same resistance, and the collection tank in the basin can be cancelled. 3. The settling basin has matured experiences of design, installation, and run.
Main disadvantages
1. It has great land occupancy, and great basin body as well as high investment cost. 2. The open basin shall be frozen during winter, when it is placed in indoor condition, the investment cost shall be greatly increased.
1. Its adaptability to raw water is inferior to that of horizontal flow settling basin. 2. It has high requirement to reaction effect, and evenness of water distribution. 3. The plastic slope pipe has the problem of replacement for aging.
1. The application time of this technology is relatively short.
According to above comparison it can be seen that, slope plate settling basin has
more advantages of economy and other aspects when compared with horizontal flow
settling basin and slope tube settling basin. The slope plate settling basin is the new
type and high efficiency one developed in 1990s, and its characteristics are: effluent
water quality is good and stable, it has strong adaptability to change of raw water
temperature and quality, hydraulic condition is good, settling time is short, land
occupancy is small, potential of output water is great, and slope plate settling basin
has been widely utilized in the north regions as Moudanjiang City, Daqing City and
Dalian City with very good effect of operation, thus slope plate settling basin is
recommended for this project.
(3) Filtering
Filtering is the most critical work sequence of water supply treatment, at
present it usually adopts the fast filtering basin to eliminate the residual flocculants
and foreign substances after coagulating and settling of raw water. According to
different structure forms of the filtering basin, at present it usually adopts the general
fast filtering basin, double valve filtering basin, siphon filtering basin, movable hood
backwash filter basin, and V type filtering basin, etc. In this project it intends to select
the general fast filtering basin and V type filtering basin. Comparison on plans is
shown in Table 7.4-5.
7.4-5 Comparison on plans of filtering basins Basin type
Item V type filtering basin General fast filtering basin
Main advantages
1. The filtering speed is high, basin body is small and land occupancy is small.
2. The waste water discharge quantity is low, energy consumption is low and investment cost is low.
3. The effluent water gate is controlled by level of filtering basin liquid, so as to control the filtering speed.
1. The run is stable and reliable and has matured operation experience.
2. It adopts the sand filtering material, the material can be easily obtained and the price is cheap.
3. It adopts the large resistance water distribution system, the single basin area can be fairly great, and basin depth is appropriate.
4. It adopts the decelerated filtering and water quality is fairly good.
Main disadvantages
1. It is added by water supply equipment, and this increases the infrastructure construction investment and increases the work volume of maintenance.
2. The basin structure is complicated, especially it has high accuracy requirement to water distribution and gas distribution system, and this adds the difficulty of construction.
3. The area if single basin is averagely greater than unit basin area of general filtering basin, but it is not comprehensively utilized, because the discharge tank in the middle position occupies a part of area, and in fact, the actual filtering area is smaller than single basin area.
4. The back flush operation is complicated especially in case of manual operation.
1. It has a lot of valves with expensive price and valve can be easily damaged.
2. It must be set by complete set of flushing equipments.
According to above comparison it is know that, the general fast filtering basin
has more stable and reliable operation than V filtering basin, its process is simple with
low technical requirement to operation personnel, and can meet the actual situation of
local area of this project located. Furthermore, the general fast filtering basin has been
widely utilized in the deep processing works of sewage of China. Thus in this project,
the general fast filtering basin is recommended.
7.4.4 Comparison and selection on sludge treatment processes
During sewage treatment process it shall generate a large number of sludge
containing various hazard and toxic substances, thus it shall be timely treated and
disposed. It usually has the following processes of sludge treatment: anaerobic
digestion, aerobic digestion and direct thickening and dehydration.
When anaerobic digestion is adopted, it can recover the energy, but its capital
cost is fairly high, with operation and maintenance problem, great land occupancy,
and safety hidden trouble, furthermore, it shall decrease the effect of biological
elimination of phosphorus and increases the quantity of reagent addition.
According to statement of “503 Standard of Sewage and Sludge Treatment ” of
EPA of U.S.A., the treatment effect of aerobic digestion for sludge with staying time
of 60 days in 15℃, and 40 days in 20℃ is only equivalent to the anaerobic digestion
treatment effect of 35℃ and 15 days of moderate temperature. Apparently, it is not
economic to realize the stable aerobic digestion in the large and middle urban sewage
treatment plant, the data shows that, sludge aerobic stabilization technology is only
utilized for the sewage treatment plant below the capacity of 20000 m³/d.
Since the sludge age of sewage treatment is fairly long, and has aerobic
stabilization for some extent, the generated sludge quantity is fairly small. The
biological nitrogen and phosphorus elimination process has been utilized for many
completed sewage treatment plants in domestic and abroad, the generated sludge is
directly thickened and dehydrated, the operation is stable, and this proves that, the
direct thickening and dehydration are feasible.
As above mentioned, in this project, it is recommended to adopt the direct
thickening and dehydration for sludge treatment.
7.5 Comparison, selection and analysis on substitute plan of
treatment works of Wuliansu Lake
7.5.1 Comparison, selection and analysis on constructed wetland
7.5.1.1 Regional location of constructed wetland
Constructed wetland is located in the west part and north part of Wuliangsuhai
lake area, which shall respectively treat the lake influent water of general drainage
canal , drainage canal 8 and drainage canal 9, the regional location is shown in Fig.
7.5-1. No.2, No.3, and No.4 areas are respectively located in the north west area of
Wuliangsuhai and mainly for treatment of drainage water of general drainage canal.
No.5, No.6 and No.7 areas are located between drainage canal 8 and drainage canal 9,
and in the south side of drainage canal 9, which are used for treating drainage water of
drainage canal 8 and drainage canal 9.
Fig. 7.5-1 Construction location of constructed wetland
7.5.1.2 Selection of wetland model
With PREWET model, waste water cleaning effect of constructed wetland is
simulated and computed. All parameters of model are inputted via “input data”
module of main menu, in this module it consists of four sub-modules of system
parameter, constituent selection, constituent parameter, influent concentration.
According to characteristics of wetland of Wuliangsuhai, constructed wetland system
is divided to three subsystems: Stabilization pond subsystem and surface flow reed
area subsystem. Finally two wetlands are regarded as integrity for simulation (Fig.
7.5-2).
1
23
4
5
6
7
8
Fig. 7.5-2 Input interface of model parameter
7.5.1.3 Main design parameter
(1) Design of water quantity and water quality
Waste water treated by constructed wetland is the drainage of drainage canal 8
and drainage canal 9, according to water quantity statistics for years (1998-2008),
total drainage water into the lake is 460million m3, considering of impact to water
quantity after completion of waste water plant and reuse water in the upper reaches, it
is predicted that total drainage quantity into the lake is 424million m3, after
completion of waste water treatment plant and reuse water plant, it shall not be
discharged to general drainage canal, thus it does not have impact to water quality of
total drainage.
Annual mean discharge water quantity is 42million m3 for Drainage canal 8 and
22million m3 for Drainage canal 9, totally 64million m3, after completion of waste
water plant and reuse water plant at upper reaches, it shall not take water from or
discharge water into Drainage canal 8 and Drainage canal 9, thus it shall not impact
water quality and water quantity of No.8 and Drainage canal 9.
The Design flow of delay wetland system adopts the annual mean daily flow,
wherein, pump and water gate, etc., in the wetland system are computed as per
maximum monthly flow.
Water quality of general drainage canal shall adopt the mean value from Dec., to
Apr. of next year, nevertheless, considering of influent water quality and quantity of
Wuliansu Lake, specific local climate condition and specific condition of wetland, the
design water quality shall be subject to maximum concentration of non-icebound
season from May to Nov., as shown in Table 7.5-1.
Table 7.5-1 Designed water quality of influent water of constructed wetland
Indicator CODCr BOD5 NH3-N TN TP
Value (mg/L) 60 - 2.4 13.5 1.7
Note: BOD5 lacks measured data.
(2) Elimination rate
In the wetland, elimination of biochemical oxygen demand can be described by
following order 1 reaction dynamics, with apparent correlation (P<0.1) .
Wherein, Ce ——Influent water BOD5,mg/L;
Co ——Exfluent water BOD5,mg/L;
KT ——First order reaction constant, d-1;
t ——Hydraulic power staying time, d.
(2) Hydraulic load and staying time
According to the elimination rate predicted, the above formula can be used to
compute the hydraulic power staying time required for wetland.
In the delay wetland, since great growth of reed occupies a part of space, and the
staying time is the function of wetland porosity, during calculation, porosity n shall be
taken into account.
(3) Area and water depth of delay wetland system
In the wetland system, water depth of stabilization pond is about 2.0m, water
depth of wetland is controlled by about 1.0m.
(4) Water flow status
In the wetland system, length to width ratio of hydraulic unit has important
impact to hydraulic characteristic. Since area of reed field is very great with irregular
form, during design of flow channel, it shall to the greatest extent adopt the diversion
dam to make the water flow status gradually approach to plug-flow mode, hydraulic
characteristic is improved to increase the elimination rate.
(5) Accumulation depth and clearing period of sludge of pond bottom
Accumulated depth of sludge is 0.3m, it shall be cleared for interval of every 5-
10 years.
7.5.1.4 Plan 1
In plan 1 it adopts 2#, 3#, 4#, 5#, 6# and 7# reed field, wetland of general
drainage canal is 2#, 3# and 4# reed field. Wetland of Drainage canal 8 is 5# and 6#
reed field, wetland of Drainage canal 9 is 7# reed field. Total land occupancy area is
116914 mou.
(1) General drainage canal wetland
Wetland of general drainage canal adopts the 2#, 3# and 3# reed field as shown
in Fig. 7.5-3, and its total area is 90514 mou. Returned water is lifted by Honggebu
pump station and then enters reed field of 4# military area farm via the diversion
sluice, through the diversion dam set in the reed field, it is diverted and enter 2# reed
field and then 3# reed field via the water channel with width of 1000m in the inner
side of lake dam, wherein, the incoming water of Yihewu channel has small quantity
and seasonality as well as also directly enter wetland system, finally, through three
outlets at the connection between reed field and lake, it enters grid water channel of
big lake area via the rubber dam.
At present, water level of reed field is lower than level of lake area, effluent
water of wetland enters lake area (mostly relies on self flow), therefore it shall run by
raising the water level, on the basis of existing water level it shall be raised by 50-
70cm. In the branch current from general drainage canal to 4# reed field it is built up
by a water interception gate (rubber dam) to control the water current into 4# reed
field. When the incoming water of upper reaches during flood season is fairly great, or
when water quality is fairly good, the water quantity can be directly regulated for
entering the lake. Effluent water of wetland mainly relies on self flow, facilities at
location of three outlets comprehensively takes into account the requirement for
improving hydraulic power condition of lake area, and water quantity distributed is
respectively 20%, 20% and 60%.
If the dam in the circumference of reed field needs to be reinforced and
heightened, it may be done on the previous foundation. The border-in position
between reed field and lake is the lake dyke, width of previous lake dyke is mostly
about 2.0-2.5m and height 1019.0-1019.6 m, and there is no lake dyke at individual
section. Elevation of normal lake water level is 1018.5m, maximum elevation of lake
level is 1019.3m, thus designed elevation of lake dyke is determined as 1020.0m; Its
width shall take into account the stability and transport requirement in the water, dyke
top width is 5.0m, slope 1:2.0, and height is 2.5m.
Rising water level may incur rise of groundwater level of farm in the
circumference and impact normal farming work, at the outside of reed field of
wetland it shall adopt vertical plastic laying technology for reverse osmosis treatment.
Vertical plastic laying burying depth is about 8m, along a circle of periphery of
constructed wetland it shall be set by vertical plastic laying facilities for reverse
osmosis purpose, and its total length is 40km.
At the water outlet is set by one discharge station with flow of 30 m3/s playing
the role of drainage of wetland and lowering wetland level.
Since run level of wetland is raised, during icing in winter, the ice layer cannot
reach the bottom of wetland, and there is also a part of flow cross-section remained,
thus freezing period of wetland of general drainage canal can continue with its run.
Nevertheless, oxygen cannot reach water system beneath the ice due to blockage of
ice layer, in order to improve elimination rate in winter, in the stabilized pond it is set
by aerating apparatus.
(2) Drainage canal 8 wetland
Wetland of Drainage canal 8 adopts No.5 wetland and No.6 wetland with area of
15300mou. Incoming water enters 5# reed field to raise the water level for its run.
Through culvert pipe it enters 6# reed field via Changji channel. Since water level is
raised for run, in the periphery of reed field it is done by reverse osmosis treatment
via the method of vertical plastic burying, and its length is 4.7km.
Drainage canal 8 during winter basically does not have incoming water and has
no operation in winter, and aerating pond shall not be set up. Prior to coming of
freezing period, water of reed field can be discharged to rear pond of pump station
and then into the lake, so as to lower the level of wetland and to the greatest extent
avoid the reduction of output of reed.
(3) Drainage canal 9 wetland
Wetland of Drainage canal 9 adopts part area in No.7 reed field with area of
11100 mou. Incoming water enters 7# reed field to raise the water level for its run, it
in turns passes through reed field and then enters the lake via south west corner of
reed field. It is set by vertical laying of plastics of 8.5km.
After raising the water level it shall impact the output of reed, prior to coming of
freezing period the water in the reed field shall be discharged to rear pond of pump
station of Drainage canal 9 and then into the lake, so as to reduce water level in the
reed field and avoid reduction of output of reed.
Drainage canal 9 basically has no incoming water in winter, and is not run in
winter, and aerated pond is not setup.
Fig. 7.5-3Plan 1 Layout mode of wetland7.5.1.5 Plan 2
In plan 2 it adopts 2#, 3#, 4#, 5#, and 7# reed field, wetland of general drainage
Influent water of drainage Canal 9
Influent water of Drainage Canal 8
Influent water of General Drainage Canal
20%
60%1
3
2
20%
5
6
Vertical burying of plastics
8
Vertical burying of plastics
7
4
canal is 2#, 3# and 4# reed field. Wetland of Drainage canal 8 is 5# reed field, wetland
of Drainage canal 9 is 7# reed field. Total land occupancy area is 10183 mou, as
shown in Fig. 7.5-4.
(1) General drainage canal wetland
Wetland of general drainage canal is completely same as that in Plan 1.
(2) Drainage canal 8 wetland
Wetland of Drainage canal 8 only adopts 5# reed field with area of 8569mou.
Incoming water enters reed field to raise the water level for run, it in turn passes
through wetland along direction of diversion dam, and finally enters the lake area
from the diversion sluice (as shown in location of Fig.). Since it is run with rising of
water level, in the periphery of reed field it shall be done by reverse osmosis treatment
via the vertical plastic burying method.
After raising the water level it shall impact the output of reed, prior to coming of
freezing period the water in the reed field shall be discharged to front pond of pump
station of Drainage canal 8 and then enter lake via the pump station, so as to reduce
water level in the reed field and maintain output of reed.
Drainage canal 8 basically has no incoming water in winter, and is not run in
winter, and wind energy aerated pond is not setup.
(3) Drainage canal 9 wetland
Wetland of Drainage canal 9 is completely same as that in Plan 1.
Fig. 7.5-4 Layout mode of wetland of plan 27.5.1.6Plan 3
In plan 3 it adopts 1#, 2#, 3#, 5#, and 7# reed field, wetland of general drainage
canal is 1#, 2# and 3# reed field. Wetland of Drainage canal 8 is 5# reed field, wetland
Influent water of drainage Canal 9
Influent water of Drainage Canal 8
Influent water of General Drainage Canal
20%60%1
3
2
20%
6
Vertical burying of plastics
8
Vertical burying of plastics
7
5Vertical burying of plastics
4
of Drainage canal 9 is 7# reed field. Total land occupancy area is 125460 mou.
(1) General drainage canal wetland
Wetland of general drainage canal adopts the 1#, 2# and 3# reed field as shown
in Fig. 7.5-5, (4# shall not be utilized), and its total area is 105791 mou. Returned
water is lifted by Honggebu pump station and then enters 2# reed field along water
channel between 4# reed field and lake via the diversion sluice, through the diversion
dam set in the reed field, it is diverted and enter 3# reed field, finally, through three
diversion sluices between 3# reed field and lake it enters 1# area of the lake, and then
enters grid water channel of lake via the water outlet. Since wetland is in the lake with
fairly great difficulty of construction, it shall not be made by diversion dam works.
(2) Drainage canal 8 wetland
Design of wetland of Drainage canal 8 is same as that in Plan 2.
(3) Drainage canal 9 wetland
Design of wetland of Drainage canal 9 is same as that in Plan 2.
Fig. 7.5-5 Plan 3 Layout mode of wetland7.5.1.7 Comparison and selection of plan
The above three plans are analyzed, compared and selected by aspects of land
Influent water of drainage Canal 9
Influent water of Drainage Canal 8
Influent water of General Drainage Canal
1
3
4
2
6
Vertical burying of plastics
8
Vertical burying of plastics
5
7
occupancy area, cleaning efficiency, work volume, difficulty of project, economy
capacity and availability of reed utilization, etc.
(1) Comparison on land occupancy area
Land occupancy areas of three plans are shown in table 7.5-2.
Land occupancy area of Plan 1 is 116914 mou, wherein, in small lake area it is
102580 mou, in big lake area it is 14325 mou; Land occupancy area of Plan 2 is
101839 mou, wherein, in small lake area it is 95858 mou, in big lake area it is 14325
mou; Land occupancy area of Plan 3 is 125460 mou, in small lake area it is 73742
mou, in big lake area it is 51718 mou.
Plan 2 has smallest area of land occupancy, in the big lake area the land
occupancy is same as that of Plan 1, in the small lake area the area is smaller than that
of Plan1 and more than that in Plan3. Total land occupancy area of Plan 1 is
equivalent to plan2, nevertheless, in the small lake area, the area is larger than that in
plan2 and plan3. In the big lake area of plan 3, the land occupancy area is far above
other two plans.
In three plans, it all adopts 2# reed field of the lake. The result of lake area model
simulation shows that, utilization of 2# reed field is very critical to improve hydraulic
power condition of whole lake, due to this consideration, in all plans, 2# reed field is
utilized.
2# reed field in the lake has minor impact to lake since it is separated from the
main lake area. Nevertheless, 1# lake area has great impact to the lake. It greatly
reduces the area of Wuliangsu Lake area, and wetland project scope is greatly
adjacent to core area and buffer area of the lake, and this is not in favor of protection
of core area.
According to viewpoint of land occupancy, plan 2 is optimal.
Table 7.5-2 Land occupancy area of three plans
Scope Plan 1( mou) Plan 2( mou) Plan 3( mou)
Small lake area 102589 95858 73742
Big lake area 14325 14325 51718
Total up 116914 110183 125460
Due to raised-level run of wetland of general drainage canal, in the periphery of
wetland it needs to be done by reverse osmosis treatment, and it may adopt two
methods. One method is to excavate the seepage interception ditch, and the other
method is to adopt vertical burying of plastics for reverse osmosis. Depth of seepage
interception ditch is about 3m and width 10m. Depth of vertical burying plastics is
about 5m. After computation, investment cost for applying seepage interception ditch
is about 400000RMB, while investment cost of vertical burying plastics is about
200000RMB. Furthermore, seepage interception ditch has great land occupancy area
and reduces farm land, as well as needs economic compensation. Seepage interception
ditch has fairly serious soil erosion and needs to be periodically dredged. Relatively
speaking, construction of vertical burying of plastics is simple with small land
occupancy and without subsequent issue. Thus it adopts the plastics vertical burying
method to prevent from seepage.
(2) Comparison on cleaning effect of wetland
Wetland elimination rate of three plans is respectively shown in Table 7.5-
3~Table 7.5-5. Data of the table is mean value. Wherein, Drainage canal 8 and
Drainage canal 9 do not have operation during freezing period.
Table 7.5-3 Plan 1: Elimination rate of pollutant of wetland
Wetland planNon-frozen season(%) Freezing season (%)
CODCr TN TP CODCr TN TP
General
drainage canal
wetland
79 71 84 32 15 10
Drainage canal
8 wetland78 73 80 - - -
Drainage canal
9 wetland75 71 80 - - -
Table 7.5-4 Plan 2: Elimination rate of pollutant of wetland
Wetland plan Non-frozen season (%) Freezing season (%)
CODCr TN TP CODCr TN TP
General
drainage canal
wetland
79 71 84 30 15 10
Drainage canal
8 wetland 70 69 75 - - -
Drainage canal
9 wetland 75 71 80 - - -
Table 7.5-5 Plan 3 Elimination rate of pollutant of wetland
Wetland planNon-frozen season (%) Freezing season (%)
CODCr TN TP CODCr TN TP
General
drainage canal
wetland
72 70 80 30 15 8
Drainage canal
8 wetland70 63 75 - - -
Drainage canal
9 wetland75 71 80 - - -
According to above table, design of plan 1 and plan 2 for wetland of general
drainage canal are consistent with same elimination effect. Elimination effect of plan
3 is slightly lower, because 1# wetland is in the lake and has not setup of diversion
dam, thus water current can easily incur short current and section current and cannot
comprehensively play the effect of space of wetland. As to Drainage canal 8, since it
has great land occupancy, elimination effect of plan 1 is best, and effect of plan 2 and
plan 3 is of the same. Design of three plans for Drainage canal 9 is consistent with
same elimination effect.
(3) Current situation of reed field and feasibility demonstration of utilization
Constructed wetland project of biological transitional area of Wuliangsu Lake
must integrate and utilize the existing reed field in the north and west part of lake
area. Hetao Water Supply Group visited and surveyed 47 villager groups of 10
administrative villages of three farms (Xishanzui Farm, Xin’an farm, and military
area farm), and two towns (Xin’an Town, and Dashetai Town), the result showed that,
reed field of north part and north west part of lake area is difficult for utilization. The
utilization mode for reed field is most feasible, while the renting mode has the
problems of great cost and great difficulty. In plan 2 and plan 3, the reed field area of
wetland of drainage canal 8 is reduce, and it can also ensure the elimination rate of
pollutant, and thus can be regarded as preferred plan.
(4) Comparison on work volume and project difficulty
In Plan 1, area of reed field is biggest with biggest work volume. Drainage canal
8 adopts 5# and 6# reed fields, between them is Changji Channel, when water flows
into 6# reed field from 5# reed field it needs to be made by culvert pipe for passing
through Changji Channel, the work volume is increased, and construction difficulty is
also increased.
In Plan 2, the area of reed field is smallest. Drainage canal 8 only adopts 5# reed
field, Drainage canal 9 adopts 7# reed field, and at present in the rear pond of pump
station of No.8 and Drainage canal 9, it is set by drainage ditch for these two
wetlands. It can be utilized by making slight modification, and water current shall not
cross over Changji Channel. Since the area is small, the work volume of pond and
diversion dam in the wetland is also decreased.
Area of plan 3 is slightly larger than that of plan 1, nevertheless it adopts the reed
area of north side of big lake area, and the difficulty for excavation, dam building and
construction of diversion sluice in the lake area is far above that on the land. The main
issue is that, it occupies area of lake and reduces area of Wuliangsu Lake area,
periphery of wetland is adjacent to core area and buffer area, and this is not in favor of
environmental protection of core area and buffer area.
Work volume of three plans is shown in table below, according to Table 7.5-6,
work volume of plan 2 is smallest.
Table 7.5-6 Comparison on main work volumes of three plans
Description of works Plan 1 Plan 2 Plan 3
Coffer dam and dyke 91.2 km 81.6 km 85.8 km
Lift pump station 1set 1set 1set
Stabilization pond 124.3万m3 165.2 万m3 180.4万m3
Diversion dam 46.3 km 44.6 km 49.7 km
Diversion sluice 2sets 2sets 5sets
Effluent water gate 7sets 6sets 2sets
Ventilation water channel 16.8 km 18.8 km 18.8sets
Aerating pond 1set 1set 1set
Slope of soil and biological works 24 km 21 km 21 km
Vertical burying of plastics 70 km 70km 70 km
(5) Comparison on economy
Project cost of three plans is shown in Table 10.7-6, and it can be seen that plan 2
is most economic.
Table 7.5-7 Comparison on cost of three plans
Cost description Plan 1 Plan 2 Plan 3
Engineering cost (ten thousand Yuan) 14865.2 13044.19 13951.234
Engineering investment (ten thousand
Yuan)18889.8 16667.68 17783.83
(6) Integrated comparison
As shown in table 7.5-8, according to comprehensive comparison on land
occupancy, cleaning effect, work volume and difficult extent, land occupancy
feasibility, and economy, etc., plan 2 is optimal.
Table 7.5-8 Integrated comparison on three plansDescription of
projectPlan 1 Plan 2 Plan 3
Land occupancy
total area is fairly great (116914
mou)
total area is minimum (110183
mou)
total area is maximum (125460
mou)
Small lake area (102589 mou) Small lake area 95858 mou Small lake area 73742 mou
Big lake area (14325 mou) Big lake area (14325 mou) Big lake area (51718 mou)
Max. occupancy of small lake
areaAppropriate
Biggest area of lake area
occupancy
Work volume Max. Min. Middle level
Construction
difficulty
The work in small lake with
water channel crossing over
Changji Channel, and difficulty is
slightly great
The work in small lake with
minimum difficulty
The work in lake area with
greatest difficulty of construction
Cleaning effectDuring Non-freezing period the
cleaning effect is best
Middle level, but during Non-
freezing period it can meet the
quality requirement of effluent
water.
worst effect
Investment
estimateMax. (188.898 million Yuan) Min. (166.6768 million Yuan)
Middle level (177.8383t million
Yuan)
Social and
environmental
impact
Max.; it involves most peasant
households with fairly great
conflict and compensation
Fairly small; 6# reed field shall
not be utilized, and this relieve
the social impact
The reed field area is minimum
in small lake, with minimum
social impact relatively,
nevertheless it has impact to core
area.
Impact to area of
lakeIt adopts the 2# reed field of lake It adopts the 2# reed field of lake
In addition to 2# reed field, it
additionally adopts 1# area of
lake, and this reduces area of
lake.
7.5.2 Comparison and selection on execution plans of grid water
channel
7.5.2.1 Design plan on grid water channel system of lake area 1) Lake-entry location and flow setup plan of wetland According to lake-entry flow statistics and analysis of each drainage cannel of
lake area in recent years, the treated water quantity of each wetland plan is shown in Table 7.5-9.
Table 7.5-9 Designed treatment capacity of each wetland plan
Wetland plan Lake-entry flow (ten thousand m3/d)
May- Sep. Oct.- Nov. Dec. –Apr. of next year
Wetland plan 1
General
drainage canal150 250 73.3
Drainage
canal 810.7 38.3 /
Drainage
canal 95.87 28.0 /
Wetland plan 2
General
drainage canal150 250 73.3
Drainage
canal 810.7 38.3 /
Drainage
canal 95.87 28.0 /
Wetland plan 3
General
drainage canal150 250 73.3
Drainage
canal 810.7 38.3 /
Drainage
canal 95.87 28.0 /
2) Design plan of channel
In order to improve the flow status of lake area, and due to general consideration of factors of water channel treatment planning and core protection area, etc., as well as after repeated computation and test via hydraulic model, the design of water channel of lake area with relation to each wetland plan are shown in Table 7.5-10, Fig. 7.5-6 and Fig. 7.5-7.
Table 7.5-10 各Wetland plan 对应的湖区水道设计方案
Wetland plan
Drainage canal design Drainage canal design
Drainage canal
plan
Channel
bottom
width
(m)
Slope
(m)
Channel
length
(km)
Drainage
canal plan
Channel
width
(m)
Slope
(m)
Channel
length
(km)
Wetland plan 1Drainage canal
plan 145 1:6 40.0
Drainage
canal plan 110 1:2 99.30
Wetland plan 2Drainage canal
plan 145 1:6 40.0
Drainage
canal plan 210 1:2 100.0
Wetland plan 3Drainage canal
plan 145 1:6 40.0
Drainage
canal plan 310 1:2 68.20
Fig. 7.5-6 Layout plan of drainage canal
Drainage canal and drainage canal plan 1 Drainage canal and drainage canal plan 2
Drainage canal and drainage canal plan 3
(The broken line area is the buffer area and core area)
Fig. 7.5-7 Layout plan of drainage canal and branch canal
7.5.2.2 Flow field simulation and analysis of water channel system to lake area 1) Zero plan In the zero plan condition, the flow field simulation result of lake area is shown
in Fig. 7.5-8.
Fig. 7.5-8 Simulation result of flow field of lake area of current situation (no wind in
summer)
2) Plan 1The result of flow field simulation of lake area in plan 1 is shown in Fig. 7.5-9.
No channel design Plan 1
Drainage canal design plan 1
Drainage canal+branch canal Plan 1
Fig. 7.5-9 Wetland plan 1: Simulation result of flow field of lake area (no wind in summer)
3) Plan 2
The result of flow field simulation of lake area in plan 2 is shown in Fig. 7.5-10.
No channel design plan 2
Drainage canal design plan 2
Drainage canal+ branch canal design Plan 2
Fig. 7.5-10 Wetland plan 2: Simulation result of flow field of lake area (no wind in summer)
4) Plan 3
The result of flow field simulation of lake area in plan 3 is shown in Fig. 7.5-11.
No-canal design plan 3
Drainage canal design plan 3
Drainage canal+ branch canal design Plan 3
Fig. 7.5-11 Wetland plan 3: Simulation result of flow field of lake area (southeaster in
summer)
5) Comparison on flow field simulation
According to above simulation results, the dead water area of lake area in three
plans are shown in Table 7.5-11.
Table 7.5-11 Dead water area of lake area in three plans
Wetland plan Water channel design planDead water area (Km2)
No wind in summer
Plan of current situation No 182.40
Wetland plan 1Drainage canal and drainage canal
plan 1147.55
Wetland plan 2Drainage canal and drainage canal
plan 2146.11
Wetland plan 3Drainage canal and drainage canal
plan 3142.52
According to simulation result of flow field simulation of lake area of three plans and Table 7.5-11, the following conclusions can be made:
(1) Compared with zero plan of flow field with current situation, three diversion plans can apparently improve the flow status of reservoir area, and the dead water area of large area of Dongdatan water area, etc., is basically eliminated, under the non wind condition, the dead water area can be reduced by about 30-40 km2;
(2) It only dredges and extends the drainage canal, the flow speed of main flow area of south part of lake area is slightly increased, it has minor impact to flow status of north part and west part of lake area, and the improvement effect of integrity of lake area is limited.
(3) In the reed area of the lake, the water channel is dredged and extended, the drainage canal and branch canal are executed, dead water area of lake area is reduced by over 10 km2, main flow field of lake area is smoother, and integral flow status of lake is greatly improved.
(4) Dead water area of plan 1 is basically equivalent to that of plan 2, compared with plan 1, dead water area of plan 2 is reduced by 1.40 km2 without apparent difference. The dead water area of plan 3 is minimum, because the 1# area of lake area is occupied by wetland and lake area is accordingly reduced. According to viewpoint of optimization of flow field of lake area, plan 2 is optimal, and is related to water outlet plan of wetland.
8. Analysis on Environmental and Economic Loss and Profit
The integrated water environmental improvement works of Bayannur
Municipality with WB loan is important component of the infrastructure of the city,
which has far-reaching significance in improving the water environment of Bayannur
Municipality, dispatching water resources, maintaining the normal operation of urban
functions and promoting the harmonious development of the society, economy and
environment.
8.1 Project Development Target and Impact Analysis
The development target and overall impact of the project are included in Table
8.1-1.
Table 8.1-1 Development Target and Overall Impact of the Project
Development target of the project Predicted project impact
Reclaimed water supply works, sewage treatment and
recycling works of processing park and sea area
treatment works of Wuliangsu Lake will cut off the
pollutants discharged into the lake, alleviate the
deterioration trend of water environment of
Wuliangsu Lake, and provide necessary urban
environment and infrastructure for the development of
Bayannur Municipality and finally support the
sustained development of economy from the
environment
Dispatch water resources, improve utilization rate of
water resources
Cut off pollutant, improve the quality of water
environment
Improve the water circulation of lake, strengthen the
self-purifying capability of lake, and retard the
process of paludification
Improve water environment and quality of Wuliangsu
Lake, and protect the safety of ecological water
environment of the Yellow River
8.2 Economic Benefits
(1) Economic Benefits of Reclaimed Water Supply Works
The unit water sale price of different reclaimed water supply works of the project
is calculated with VAT, urban maintenance & construction tax, additive education fee
and others expenses plus proper profits on the basis of total costs. The reclaimed
water supply works can realize annual average operating incomes of RMB79.7525
million & total annual average profits of RMB19.3925 million after completed.
Financial analysis reveals that the net profit rate of all the investments of various
reclaimed water supply works is 5.16% on average, the period of the returns on
investment is 12.9-13.32 years, various financial indicators are predicted as good and
the balance point of profit and loss is safe. It proves that the project still has some
economic benefits from the angle of financial evaluation although the project is urban
infrastructure.
(2) Economic Benefits of Sewage Treatment and Recycling Works of Processing
Park
According to Interim Regulations on the Charges for Drainage Facilities of the
Ministry of Construction, with reference to the experiences of relevant cities, in
combination with the practical situation of this works, the collection of the charges for
disposing pollutants enables this works to realize some economic benefits. The
sewage treatment and recycling works of processing park of the project can realize
annual average operating incomes of RMB61.612 million, and total annual average
profits of RMB18.032 after completed. The financial analysis shows that the net profit
ratio of all investments of sewage treatment and recycling works of processing park is
5.20% on average, and the period of investment recovery is 14.21 years. Various
financial indicators are predicted as good and the balance point of profit and loss is
safe. It proves that the project still has some economic benefits from the angle of
financial evaluation although the project is urban infrastructure.
Indirect economic benefits of the investment of the sewage treatment and
recycling works of processing park are also obvious, and mainly realized via less
economic loss of the society produced by emission reduction of pollutants, with main
forms as follows:
① Industrial Enterprises
Additional investments and operation managing expenses of the industrial
enterprises for scattered in-depth sewage treatment can be reduced and the
environmental protection burden of enterprises can be alleviated; and project
construction includes domestic sewage disposal system in service area and as a result,
the project will exert the large-scale and low-cost advantages of the whole works,
reduce sewage disposal construction cost of individual enterprise and promote the
construction and development of the enterprise in processing park after completed.
② Agriculture
After the project is implemented, the waste water of sewage disposal plant is
used in industrial enterprises of processing park after in-depth treatment. As a result,
the project can save water resources and adjust the conflict between industrial water
consumption and agricultural water consumption.
③ Personal Health
The project can improve the water quality of the general trunk channel and
Wuliangsu Lake, boost up local sanitation conditions, reduce the morbidity of
diseases, cut off medical care and service expenses, and promote the labor
productivity after completed.
The sewage treatment and recycling works of processing park, important
component of urban infrastructure is one public welfare project protecting the
environment and benefiting the people. Direct and indirect economic benefits of the
project are very obvious. It can improve water quality of trunk channels and
Wuliangsu Lake, the water environment status of the project area and the investment
environment of Bayannur Municipality, and promote the land value increment of
potential area. Therefore, the implementation of the project has certain benefits for
national economy, and plays an important role in improving water environment
quality of Bayannur Municipality and promoting harmonious development of society,
economy and environment.
(3) Economic Benefits of Sea Area Works of Wuliangsu Lake
The economic benefit of the sea area works of Wuliangsu Lake is realized
mainly through the incomes of the reed industry, fishery and tourism of artificial
wetland works of Wuliangsu Lake:
In virtue of reed land of artificial wetland, annual reed output can increase from
120,000t to 150,000t, and as per RMB150 unit price, additional RMB4.5 million
incomes can be created; the fish culture in stabilization pond of artificial wetland can
add breeding area of 1000mu and create an additional output of 1000t, and as per
RMB5000/t unit price, RMB7.5 million can be created; and the improvement of
ecological environment of the wetland of Wuliangsu Lake could provide better
conditions for ecologic tourism. It’s predicted that the area can accommodate 100,000
tourists/time, and realize annual operating income of RMB35 million and annual
average after-tax profits of about RMB14 million. Therefore, sea area treatment works
of Wuliangsu Lake has good economic benefits.
The construction of artificial wetland works can obviously improve water quality
and eutrophication of the whole Wuliangsu Lake. Sewage flows into the lake after
wetland treatment and is able to improve water quality by one grade. Inlet water
quality of wetland in summer is Cat-IV or better Cat-IV by and large. In frozen
season, the pollutant in water is largely cut off. Sea area grid works can obviously
improve the self-purifying capability and environment capacity of Wuliangsu Lake.
Artificial wetland and sea area grid works can greatly reduce the probability of the
pollution accident of Wuliangsu Lake and the Yellow River, avoid the direct and
indirect loss of the accident, and cut off pollution treatment expenses of the accident.
8.3 Social Benefits
The project as urban infrastructure construction project will improve urban
infrastructure level, better the quality of regional water environment and play a key
role in beautifying the city after completed. Moreover, the construction of the project
will improve investment environment, facilitate foreign investment, and play active
role in promoting sustainable development of the economy.
The reclaimed water supply works can adjust water resources, alleviate the water
consumption conflict between industry and agriculture, inconsistency of the demand
and inadequate water supply of processing park, improve the investment environment
of the processing park, and ensure the sustainable development of processing park as
per the overall planning after completed.
The sewage treatment and recycling works will improve the surface water
quality of the trunk channels and Wuliangsu Lake, avoid or reduce the loss of industry
& agriculture caused by sewage and play important role in preventing various
infectious and common diseases and bettering people’s health after completed.
In the implementation of the integrated sea area improvement works of
Wuliangsu Lake, the construction of artificial wetland will cut off surface source
pollution of agriculture, improve water environment quality, and promote the growth
of fish culture and reed output, and increase the work opportunities and incomes of
residents; the control demonstration and popularization project of surface pollution
source can promote the agricultural development of the valley of Wuliangsu Lake,
improve agricultural incomes and maintain local living habit; grid waterway works
will improve water circulation of the lake, and strengthen self-purifying capability of
lake, retard paludification, and protect and restore unique biologic value of Wuliangsu
Lake. Therefore, the implementation of the works can not only improve the water
environment quality of Wuliangsu Lake, protect the safety of water biologic
environment of the Yellow River, but also boost up the living level of local people,
and help the people live in peace and contentment, and maintain the stability of the
society.
8.4 Environmental Benefits
The project, key public-welfare infrastructure for maintaining sustainable
development of economy, protecting water resources and preventing the water
pollution, is the construction project improving ecologic environment, ensuring the
health of people and benefiting society. The environmental benefits of the project are
as follows:
8.4.1 Improving Hydraulic Conditions of Sea Area
At present, reed grows widespread in Wuliangsu Lake. Especially in the
northwest of the sea area, reed nearly covers the lake besides the open water surface
in Xidatan. With the prevalence of reeds and increase of water flow resistance, large-
size backwater area shapes in reed growing part. Simulated results prove that the
water flow is weak in lake under the impact of incoming and outcoming flow. Besides
3mm/s-8 mm/s flowing speed in main flow area, a flowing speed of 1mm/s-1cm/s
exists in most water areas. The backwater area in existence causes unsmooth water
flow and bad water exchange conditions, and tends to create anaerobic and anoxic
environments. As result, the organic substance is fermented, and lake water smells
unfavorably.
With the implementation of grid waterway works of Wuliangsu Lake, water flow
condition of sea area is obviously improved. The main flow area of lake is smoother.
Especially, the large-size backwater area in Dongdatan and other parts is eliminated
by and large. In no-wind conditions, the size of backwater area can decline by 30-40
km2. The whole hydraulic conditions of the lake are largely improved.
8.4.2 Cutting off Pollutants
The reclaimed water supply works is able to reasonably dispatch water resources,
improve utilization rate of water resources, reduce the exploitation of underground
water resources by 51.024 million m3, protect underground water resources, alleviate
the continuous decline of underground water level, and prevent the expansion of
funnel area, reduce the emission of CODcr, BOD and ammonia nitrogen by 2847.0t/a,
BOD 1335.9 t/a & 491.29t/a respectively, and improve the regional ecologic
environment.
Sewage treatment and recycling works of processing park can improve the
degree of industrial wastewater treatment as well as sewage recycling rate, better the
present water quality of the trunk channels and Wuliangsu Lake, and reduce or avoid
the economic loss caused by sewage emission to industrial and agricultural
production. The swage treatment and recycling works of the project can save water
resources by about 22.63 million m3/a if 80,000m3/d sewage treatment capability and
64,000t/d reclaimed water calculated, reduce pollutant emission of the valley i.e.
CODcr by 10950.0t/a, BODcr by 6022.5t/a, ammonia nitrogen by 730.0t/a, and play
significant role in cutting off the total pollutant emission of the region after
completed.
After completed, ecologic-transitional-belt artificial wetland of Wuliangsu Lake
can reduce surface source pollutant of agriculture, cut off CODCr, TN and TP by
9781.19 t/a, 1990.57t/a and 299.24t/a respectively through its treatment, and largely
improve the quality of water flowing into the lake. In summer, outlet water quality of
wetland is Cat-IV or better than Cat-IV by and large. In frozen season, the pollutant in
water is largely cut off as well. It plays significant role in gradually improving
eutrophication status of sea area, boosting water quality of lake area, and bettering
water environment.
8.4.3 Improving Water Quality of Sea Area of Wuliangsu Lake
The grid waterway system will improve water quality of sea area by itself after
implemented. Because the hydraulic conditions are improved and water exchange is
strengthened after the implementation of trunk and branch canal waterway system, the
isotropic function of quality of water system is reinforced and overall water quality of
lake area is improved. In non-frozen period, Cat-V water area with organic substance
declines by 17 km2, and water area better than Cat-IV increases by 8%, and the Cat-IV
water area increase by about 3%; the inferior Cat-V water area with TN decreases by
14.2 km2, and Cat-IV water area increases by about 6.1 km2; better Cat-IV water area
with TP increases by 8.2 km2, and Cat-IV water area decreases by about 12 km2.
The most important function of sea-area grid waterway for water quality
improvement is the optimal configuration of water outlet position and quantity of
artificial wetland. After grid waterway reasonably configures wetland outlet position
and quantity, COD concentration of the lake is largely improved. In the frozen period,
inferior Cat-V water area decreases by about 123 km2. In non-frozen period, COD
concentration largely declines, and inferior Cat-V water area is nearly eliminated in
the whole lake, Cat-V water area is 100-127 km2, Cat-IV water area is 86-98 km2,
Cat-III water area reaches 26-41 km2. In frozen period of the lake, inferior Cat-V
water area with TN decreases by about 25-40 km2, Cat-IV water area increases by 28-
50 km2; and in non-frozen period, TN improvement effect is obvious. Inferior Cat-V
water area decreases by 101-120 km2. In frozen period of the lake, better Cat-III water
area with TP increases by about 18-55 km2; and in non-frozen period, TP
improvement effect is obvious as well. In the whole lake, lower-than-Cat-V water area
is eliminated by and large. Inferior Cat-III water area increases by 90-110 km2.
9. Public Participation and Information Disclosure
9.1 Goal of Public Participation
(1) To investigate and visit general public affected by the project environment;
strengthen the bilateral conmmunication between construction project and the public;
understand support level and suggestions of the public to the construction project,
such as environmental protection measures; potect residents affected by the
construction project from harmless impacts; and reduce environment disputes caused
by the construction project after project operating.
(2) To introduce related situation of the project to the public; collect feedback, in
order to find existing problems; provide related remedial measures and suggestions;
draw the whole society’s attention to environment protection industry; improve
environment rationality and society acceptability of the project; and provide decision-
making suggestions and action basis for environment protection departments and
construction unit.
(3) To publicize policies of environment protection; increase degree of openness
of environment pollution and administration, ecology damage and protection; and at
the same time, increase environment protection awareness of the public around the
project, so that the public could know and participate in the policy decision of
environment impacts.
9.2 Mode of Public Participation
This project is a socially useful project of environment protection. It consists of 9
subprojects, distributed in 5 counties of Bayannur. It has a wide area of evaluation. To
fully understand opinions and attitude on subprojects and the lead project of people
living around subprojects, and provide basis for decision making of project
examination and approval, according to the requirements of Law of the Peoples
Republic of China on Evaluation of Environmental Effects and Safeguard Policies of
the World Bank(OP4.01), this project has 2 turns of public participation.
The first turn is in the preparation stage of the project. We ask for opinions,
suggestions and requirements from the public, especially the group directly affected
by this project, mainly through publishing related information on website and
newspaper, posting official notice, giving out personal and group questionnaires,
asking for advices from experts and officials, and other methods. Environment
evaluation unit, project organization unit and representative of residents negotiate
about central issues rose by the public, and put the solutions into the report.
The second turn is in the completion stage of first draft of report. We ask for
advices from villager representative, enterprise representative, environment protection
expert and officials; communicate about central issues and mitigating measures
concerned by the public in the first turn of public participation, and put into the report;
and promise to the public and accept supervision of the public.
9.3 Media Announcement-Direct Information Feedback
According to related regulations of Regulation for Public Participation in the
Environmental Impact Assessment (State Environmental Protection Administration
2006 No.[28]), environment impact evaluation information is published to the public
for 2 times in the preparation stage of evaluation report.
(1) The first information publishment: During the beginning stage of the
environment impact evaluation, engineering content of the project is informed to the
public, to allow them to have an elementary understanding.
(2) The second information publishment: After the completion of conclution of
evaluation report, the conclution shall be included in the evaluation report. The public
is allowed to have a clear understanding of environment impact of the construction
project through Internet, newspaper, questionnaire and other methods.
9.3.1 Time and Details of the First Media Annoucement
The first media announcement of this project was made on Inner Mongolia
Channel of xinghuanet.com (URL:
http://www.nmg.xinhuanet.com/nmgwq/2009-11/26/content_18341728.htm ) on
November 26th 2009 and Bayannur Daily on November 26th 2009. The
announcement mainly includes the followings:
(1) Name and summary of the construction project;
(2) Possible impacts to the environment;
(3) Protection policies of environment impacts;
(4) Working procedures and main content of environment impact evaluation;
(5) Name and contact information of construction unit and environment evaluation
unit; and
(6) Range and main items when asking for the public’s advices.
Website screenshot of the first media announcement is shown in Figure 9.3-1. See the
announcement published on Bayannur Daily in attachment.
Figure 9.3-1 The first announcement of the project
9.3.2 Time and Details of the Second Media Annoucement
The second media announcement of the project will be made by the end of 2010
after the completion of the first draft of Environment Impact Evaluation Report, to ask
for advices from the public and provide abridged edition of Environment Impact
Evaluation Report. For simplified edition of EIA Report, please visit
http://58.18.55.42:8888/sw/show.asp?id=793. This announcement mainly includes the
followings:
(1) Name and summary of the construction project;
(2) Possible impacts of the construction project to the environment and environment
protection measures;
(3) Main conclution of Environment Impact Evaluation Report of the project;
(4) Name and contact information of construction unit and environment evaluation
unit; and
(5) Range and main items when asking for the public’s advices.
9.3.3 Summany
During the publishment of the two times announcement, construction unit,
environment impact evaluation unit and local related departments didn’t receive any
call, letter or visit from local people and groups. Therefore, we can think that local
people and groups are not against the construction of the project. The environment
impact evaluation accepts this conclusion.
9.4 Results and Conclusion of Questionaires
The public shall participate in the investigation according to the following
principles:
(1) The interviewee is a volunteer;
(2) The investigation sample is general, typical and scientific;
(3) The investigation shall be based on facts, and could introduce general
information and possible environment impacts during the construction and operation
to the interviewees faithfully; and
(4) Statistics and subtotal shall show opinions, suggestions and requirements of
the interviewees practically.
Public participation of investigation mainly includes: informing the interviewees
environment problems caused by construction and operation of the project; conclusion
of initial analysis of environment impact evaluation; planned measures to reduce
environment impacts, results and other public concerned problems; whether the
interviewees understand and support the construction project; related suggestions and
requirements; etc. Therefore, we designed an investigation form, and introduced the
general information to the interviewees in writing form. The recovery percent of
investigation form is above 95%.
The interviewees are villagers living around the planned project location,
representatives of nearby enterprises, related experts, related enterprises,
representatives of related administration departments, etc.
9.4.1 Results and Conclusion of Individual Questionaires
The environment impact evaluation unit gave out questionnaires to people living
around 9 construction sites of the project from November 17th 2009 to November
22th 2009. (See details of investigation form form in attachement.) Totally 305
questionnaires were given out and 305 were recovered. The recovery percent was
100%. See interviewee and number in Table 9.4-1.
Table9.4-1 Number of Interviewees in the projects
No
.Project Name Announcement Publishing and Investigation Sites
Number of
Interviewee
s
Proportion
%
1
Water Supply
Project of
Wulatehouqi
Industry Park
Animal product team, Red Flag Village, Green Mountain
Town, Wulatehouqi; Group 1, Big Tree, Huhe Town; Group
1 of Inner Mongolia Union; Staff of Green Mountain
Industry Park
36 11.8
2
Water Supply
Project of
Ganqimaodu
Port Processing
Park
Sheep Sea Farm of Bayannur, Sheep Sea Plant 1 18 5.9
3
Sanpaigan
Recycled Water
Supply Project
Raising Community, Big Tree Bay Village, Hanghoushankan
Townl; Staff of Hangjinhouxi Dashun Industry Park 33 10.8
4 Qipaigan 5-Star Team 1 and team 3 of Longxingchang Town; Group 1, 36 11.8
Recycled Water
Supply ProjectOld City, Longxingchang Town
5
Sewage
Disposal Project
of Wulatehouqi
Industry Park
Staff of Green Mountain Industry Park; Agricuture team,
Red Flag Village, Green Mountain Town, Wulatehouqi;
Group 1, Big Tree, Huhe Town; Group 1 of Inner Mongolia
Union
37 12.1
6
Sewage
Recycling
Project of
Ganqimaodu
Port
Siyitang, Lingshan Town, Wulatezhongqi 19 6.2
7
Sewage
Recycling
Project of
Wulateqianqi
Industry Park
Wulashan Town, Wulateqianqi; Group 8, Xingzhong,
Shaqitan Village, Hieliuzi Town; Bayannur Steel Reduced
Iron LLC
35 11.5
8
Wuliangsuhai
Comprehensive
Project
Wuliangsuhai Fish Field 3, Wuliangsuhai Fish Field 5, Xinan
Village 8, Yangfangzi Village in Xinan Town, Guangyi
Station in Dayutai Town; Mapuzi Village in Dayutai Town
91 29.8
Total 305 100
This investigation on public responses is required to cover all kinds of occupations,
education and ages, to show opinions and suggestions from people of different levels to the
construction of the project. See the site pictures in Figure 9.4-1. As different construction sites are
far from each other, questionnaires for water supply and sewage disposal were given out
independently. Wuliangsuhai Garden Gridding Channel Project and Wuliangsuhai Man-made
Humid Land Project in bio-transitional Zone are combined as Wuliangsuhai Comprehensive
Project for questionnaires.
Figure 9.4-1 Site Photos of Public Questionaire
9.4.1.1 Water Supply Project Questiohnaire Survey of Wulatehouqi Industry
Park
1) Statistical analysis of questionnaire interviewees
In this project questionnaire, totally 36 individual questionnaire forms were
given out. 36 were recovered. The recovery pencent was 100%. See statistics of
interviewees in Table 9.4-2.
Table 9.4-2 List of Interviewees
ItemsSex Age
Male Femal 18~30 31~40 41~50 >50
Number 27 9 7 7 12 10
Proportion% 75.0 25.0 19 19 34 28
Items
Education
Junior College
and above
Senior Middle School
and Technical Secondary
School
Junior
Middle
School
Primary
SchoolNot filled
Number 7 4 10 11 4
Proportion
%19 11 28 31 11
ItemsOccupation
Worker Farmer Cadre Others Not filled
Number 11 24 0 0 1
Proportion
%31 67 0 0 2
From the above statistics, we can see that areas around this project are mainly
agriculture areas. Local residents have different education background. 59% have
junior middle school and primary school education. Interviewees are mainly workers
and farmers around Wulatehouqi Industry Park. It accords with the real situation of
local people.
2) Statistical analysis of Questionnaire Results
See Questionnaire statistic results of this project in Table 9.4-3.
Table 9.4-3 Questionnaire Survey Statistical Form of the Project
No. Investigation content Options
Numbe
r of
people
Proportion
(%)
1
1. Are you satisfied with current living environment quality?
A. Very satisfied 24 66.7
B. Relatively satisfied 9 25.0
C. Dissatisfied 3 8.3
D. No idea 0 0
2
Are you understanding / aware of this project?
A. Do not know 4 11.1
B. Know a little 22 61.1
C. Know nothing 10 27.8
3
What do you think of the biggest problem presently affecting the environmental quality?
A. Air pollution 22 61.1
B. Water environment pollution 18 50.0
C. Noise 3 8.3
D. Solid waste 9 25.0
E. Not clear 19 52.8
A. Air pollution 1 2.8
4
What do you think of
the project’s
improvement to the
development of local
economy?
A. Great 28 77.8
B. General 5 13.9
C. No impact 1 2.8
D. Not clear 2 5.6
5
What do you think of
the function of this
project to
comprehensive
administration of
regional environment?
A. Great 28 77.8
B. General 3 8.3
C. No impact 1 2.8
D. Not clear 4 11.1
6
What impact do you
think this project have
on your life, study,
work and
entertainment?
A.Good impact 11 30.6
B.Little impact 21 58.3
C.Bad impact 1 2.8
D.No impact 3 8.3
7 The environmental
impact of this project is
mainly in the
A. Construction dust 16 44.4
B. Domestic waste and waste water during Construction
14 38.9
construction phase,
what do you think of
the biggest negative
C.Construction noise 7 19.4
D . Damages to existing vegetation and habitats
16 44.4
E.Others 2 5.6
8
What do you think of
the biggest negative
impact on environment
during the operation of
this project?
A.Foul smell in the recycled water plant 13 36.1
B.Noise of water intake pump station 10 27.8
C . Domestic garbage and other solid wastes
in the plant10 27.8
D. Others 10 27.8
9
What problem do you
think should be solved
by the environment
evaluation?
A. Air pollution 21 58.3
B.Water environment pollution 22 61.1
C.Noise 10 27..8
D.Solid waste 8 22.2
E.Ecological environment 17 47.2
F.Not clear 1 2.8
10
Based on above, what is your overall attitude to this project?
A. Support 34 94.4
B. Do not support 0 0
C. No opinion 2 5.6
11
Do you have any
suggestions and
requirements on
environment protection
of this project?
None
(1) Most people are very satisfied with current living environment quality. 72%
of interviewees know the project well or know a little. We can see that publicity of the
project has some impact in the local area. It is widely spread.
(2) Most people in the investigated group think that the biggest problems
presently affecting the environmental quality are air pollution, water environment
pollution and damage of ecological environment. Most people think construction of
the project has positive function to the development of local economy and
improvement of environmental quality. 89% of people think this project has good
impact or no impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include construction dust (44%) , domestic waste and
waste water during construction(39%), construction noise(19%)and damages to
existing vegetation and habitats (44%). The main environmental problems caused
by operation of this project include foul smell in the recycled water plant (36%),
noise of Water Intake Pump Station(28%)and Domestic garbage and other solid
wastes in the plant ( 28% ) . During the implementation of this project, these
problems should be considered, and effectively controlled and dealed with.
(4) The public thinks that problems that should be solved by the environment
evaluation include Water environment pollution ( 61% ) , air pollution ( 58% ) ,
ecological environment(47%), noise(28%)and solid waste(22%). Therefore,
the above suggestions of the publis should be considered during the environmental
evaluation of this project.
(5) In the investigated group, 94% support the construction of this project. No
one is against the construction of this project. 6% shows no opinion. Therefore, it is
adviced to make further explanation to the project to some people, help them have a
better understanding to the project and take their suggestions as reference.
9.4.1.2 Water Supply Project Questionnaire of Ganqimaodu Port Park
1) Statistical analysis of questionnaire interviewees
In this project questionnaire, totally 18 individual questionnaire forms were
given out. 18 were recovered. The recovery pencent was 100%. See statistics of
interviewees in Table 9.4-4.
Table 9.4-4 List of interviewees
ItemsSex Age
Male Femal 18~30 31~40 41~50 >50
Number 11 7 0 8 8 2
Proportion
%61 39 0 44 44 12
Items
Education
Junior College
and above
Senior Middle School
and Technical
Secondary School
Junior
Middle
School
Primary
SchoolNot filled
Number 2 4 5 4 3
Percentag% 11 22 28 22 16.7
ItemsOccupation
Worker Farmer Cadre Others Not filled
Number 3 13 1 1 0
Percentag% 16 72 6 6 0
From the above statistics, we can see that areas around this project are mainly
agriculture areas. Local residents have different education background. 50% have
junior middle school and primary school education. Interviewees are mainly workers
and farmers living around the project. It accords with the real situation of local
people.
2) Statistical analysis of Questionnaire Results
See questionaire statistic results of this project in Table 9.4-5.
Table 9.4-5 Questionnaire Survey Statistical Form of the Project
No.Investigation
contentOptions
Number
of
people
Proportion
(%)
1
Are you satisfied with current living environment quality?
A. Very satisfied 3 16.7
B. Relatively satisfied 11 61.1
C. Dissatisfied 2 11.1
D. No idea 2 11.1
2
Are you understanding / aware of this project?
A. Do not know 3 16.7
B. Know a little 5 27.8
C. Know nothing 10 55.6
3
What do you think of the biggest problem presently affecting the environmental quality?
A. Air pollution 1 5.6
B. Water environment pollution 14 77.8
C. Noise 0 0
D. Solid waste 0 0
E. Not clear 1 5.6
A. Air pollution 2 11.1
4 What do you think of A. Great 8 44.4
the project’s
improvement to the
development of local
economy?
B. General 5 27.8
C. No impact 0 0
D. Not clear 5 27.8
5
What do you think of
the function of this
project to
comprehensive
administration of
regional
environment?
A. Great 4 22.2
B. General 3 16.7
C. No impact 4 22.2
D. Not clear 7 38.9
6
What impact do you
think this project
have on your life,
study, work and
entertainment?
A.Good impact 3 16.7
B.Little impact 12 66.7
C.Bad impact 1 5.6
D.No impact 2 11.1
7
The environmental
impact of this project
is mainly in the
construction phase,
what do you think of
the bigest negative
impact on the
environment during
construction?
A. Construction dust 4 22.2
B. Domestic waste and waste water during Construction
14 77.8
C.Construction noise 0 0
D . Damages to existing vegetation and habitats
0 0
E.Others 2 11.1
8
What do you think of
the biggest negative
impact on
environment during
the operation of this
project?
A.Foul smell in the recycled water plant 11 61.1
B.Noise of Water Intake Pump Station 3 16.7
C.Domestic garbage and other solid wastes in
the plant3 16.7
D. Others 4 22.2
9
What do you think of the biggest problem presently affecting the environmental quality?
A. Air pollution 2 11.1
B.Water environment pollution 15 83.3
C.Noise 0 0
D.Solid waste 0 0
E.Ecological environment 1 5.6
F.Not clear 2 11.1
10
What is your attitude if the project needs to expropriate part of land?
A. Support 2 11.1
B. Do not support 13 72.2
C. No opinion 3 16.7
11 Based on above, A. Support 12 66.7
what is your overall attitude to this project?
B. Do not support 0 0
C. No opinion 6 33.3
12
Do you have any
suggestions and
requirements if the
construction of this
project needs you to
move and expropriate
your land?
None
13
Do you have any
suggestions and
requirements on
environment
protection of this
project?
None
Statistical results of questionnaire show that:
(1) Most people are very satisfied with current living environment quality. 44%
of interviewees know the project well or know a little. 56% know nothing about the
project. We can see that we should strengthen the publicity of this project in the local
areas, so that more people will provide opinions and suggestions for the project.
(2) In the investigated group, 78% of people think that the biggest problem
presently affecting the environmental quality is water environment pollution. 44% of
people think that the construction of the project can develop local economy. 28% are
not clear. 39% of people think that the project has positive function to the
improvement of local environmental quality. 22% of people think that it has no
impact. 39% of people are not clear. 83% of people think that this project has good
impact or no impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include domestic waste and waste water during
construction ( 78% ) and construction dust ( 22% ) . The main environmental
problems caused by operation of this project include foul smell in the recycled water
plant (61%) , noise of water intake pump station (17%)and domestic garbage
and other solid wastes in the plant ( 17% ) . During the implementation of this
project, these problems should be considered, and effectively controlled and dealed
with.
(4) The public thinks that problems that should be solved by the environment
evaluation include water environment pollution(83%), air pollution(11%) and
ecological environment(6%). When asked for opinions on expropriating their land,
11% of people accept to be expropriated according to related policies. 72% of people
agree to push for reasonable compensation. 17% are not willing to be expropriated.
Therefore, the above suggestions of the public should be considered during the
environmental evaluation of this project.
(5) In the investigated group, 67% support the construction of this project. No
one is against the construction of this project. 33% show no opinion. Therefore, it is
adviced to make further explanation to the project to some people, help them have a
better understanding to the project and take their suggestions as reference.
9.4.1.3 Recycled Water Supply Project Questiohnaire Survey of Sanpaigan
1) Statistical analysis of questionnaire interviewees
In this project questionnaire, totally 33 individual questionnaire forms were
given out. 33 were recovered. The recovery pencent was 100%. See statistics of
interviewees in Table 9.4-6.
Table 9.4-6 List of Interviewees
ItemsSex Age
Male Femal 18~30 31~40 41~50 >50
Number 22 11 6 13 7 7
Proportion
%67 33 19 39 21 21
Items
Education
Junior College
and above
Senior Middle School
and Technical
Secondary School
Junior
Middle
School
Primary
SchoolNot filled
Number 10 7 8 7 1
Proportion
%30 21 25 21 3
ItemsOccupation
Worker Farmer Cadre Others Not filled
Number 3 21 3 2 4
Proportion
%9 64 9 6 12
From the above statistics, we can see that areas around this project are mainly
agriculture areas. Local residents have different education background. 46% have
junior middle school and primary school education. It accords with the real situation
of local people.
3) Statistical analysis of Questionnaire Results
See questionaire statistic results of this project in Table 9.4-7.
Table 9.4-7 Questionnaire Survey Statistical Form of the Project
No. Investigation OptionsNumbe
r
Proportion
%
1
Are you satisfied
with current living
environment quality?
A.Very satisfied 3 9.1
B.Relatively satisfied 12 36.4
C.Dissatisfied 17 51.5
D.No idea 1 3.0
2
Are you
understanding /
aware of this project?
A. Do not know 2 6.1
B. Know a little 21 63.6
C. Know nothing 10 30.3
3
What do you think of
the biggest problem
presently affecting
the environmental
quality?
A. Air pollution 18 54.5
B.Water environment pollution 21 72.7
C.Noise 1 3.0
D.Solid waste 3 9.1
E.Ecological environment 6 18.2
F.Not clear 4 12.1
4
What do you think of
the project’s
improvement to the
development of local
economy?
A. Great 13 39.4
B. General 14 42.4
C. No impact 1 3.0
D.Not clear 5 15.2
5 What do you think of
the function of this
project to
comprehensive
administration of
A. Great 11 33.3
B. General 16 48.5
C. No impact 2 6.1
D.Not clear 4 12.1
regional
6
What impact do you
think this project
have on your life,
study, work and
entertainment?
A.Good impact 9 27.3
B.Little impact 13 39.4
C.Bad impact 0 0
D.No impact 11 33.3
7
The environmental
impact of this project
is mainly in the
construction phase,
what do you think of
the bigest negative
impact on the
environment during
construction?
A.Construction dust 14 42.4
B . Domestic waste and waste water during
Construction7 21.2
C.Construction noise 13 39.4
D . Damages to existing vegetation and
habitats 7 21.2
E.Others 7 21.2
8
What do you think of
the biggest negative
impact on
environment during
the operation of this
project?
A.Foul smell in the recycled water plant 14 42.4
B.Noise of Water Intake Pump Station 1 3.0
C.Domestic garbage and other solid wastes
in the plant5 15.2
D. Others 16 48.9
9
What do you think of the biggest problem presently affecting the environmental quality?
A. Air pollution 11 33.3
B.Water environment pollution 19 57.6
C.Noise 4 12.1
D.Solid waste 1 3.0
E.Ecological environment 4 12.1
F.Not clear 8 24.2
10
What is your attitude
if the project needs to
expropriate part of
land?
A.To handle it by policy 19 57.6
B.To push for reasonable compensation 14 42.4
C.Not willing to be expropriated 0 0
11
Based on above,
what is your overall
attitude to this
project?
A. Support 31 93.9
B. Do not support 0 0
C. No opinion 2 6.1
12
Do you have any
suggestions and
requirements if the
construction of this
project needs you to
move and expropriate
your land?
1. Reasonable remedies
2. According to the normal procedures and requirements of project in the
area. Implemented according to land expropriating program.
13
Do you have any
suggestions and
requirements on
environment
protection of this
project?
Make sure that everything is perfect. Good for comprehensive treatment of
water environment in our area. Create better conditions for the
improvement of living environment and entering of foreign enterprises.
Statistical results of questionnaire show that:
(1) In the invested group, 46% are very satisfied or relatively satisfied with
current living environment quality. 52% are dissatisfied. 70% of interviewees know
the project well or know a little. We can see that publicity of the project has some
impact in the local area. It is widely spread.
(2) In the investigated group, most people think that the biggest problems
presently affecting the environmental quality are air pollution, water environment
pollution and damage to ecological environment. 82% of people think that the
construction of the project has positive impact on the development of local economy
and improvement of local environmental quality. Most people think that this project
has good impact or no impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include construction dust (42%) , domestic waste and
waste water during construction(21%), construction noise(39%)and damages to
existing vegetation and habitats (21%). The main environmental problems caused
by operation of this project include foul smell in the recycled water plant (42%),
domestic garbage and other solid wastes in the plant ( 15% ) and noise of water
intake pump station ( 3% ) . During the implementation of this project, these
problems should be considered, and effectively controlled and dealed with.
(4) The public thinks that problems that should be solved by the environment
evaluation include water environment pollution ( 58% ) , air pollution ( 33% ) ,
noise (12%) , ecological environment (12%)and solid waste (3%) . When
asked for opinions on expropriating their land, 58% of people accept to be
expropriated according to related policies. 42% of people agree to push for reasonable
compensation. Nobody is not willing to be expropriated. Therefore, the above
suggestions of the public should be considered during the environmental evaluation of
this project.
(5) In the investigated group, 94% support the construction of this project. No
one is against the construction of this project. 6% show no opinion. Therefore, it is
adviced to make further explanation to the project to some people, help them have a
better understanding to the project and take their suggestions as reference.
9.4.1.4 Recycled Water Supply Project Questiohnaire Survey of Qipaigan
1) Statistical analysis of questionnaire interviewees
In this project questionnaire, totally 36 individual questionnaire forms were
given out. 36 were recovered. The recovery pencent was 100%. See statistics of
interviewees in Table 9.4-8.
Table 9.4-8 List of Interviewees
ItemsSex Age
Male Female 18~30 31~40 41~50 >50
Number 22 14 0 12 20 4
Proportion
%61 39 0 33 56 11
Items
Education
Junior College
and above
Senior Middle School
and Technical
Secondary School
Junior
Middle
School
Primary
SchoolNot filled
Number 3 6 12 11 4
Proportion
%8 17 33 31 11
ItemsOccupation
Worker Farmer Cadre Others Not filled
Number 0 29 0 0 7
Proportion
%0 80.6 0 0 19.4
From the above statistics, we can see that areas around this project are mainly
agriculture areas. Local residents have different education background. 64% have
junior middle school and primary school education. The interviewees are mainly
farmers living around the project. It accords with the real situation of local people.
4) Statistical analysis of Questionnaire Results
See questionaire statistic results of this project in Table 9.4-9.
Table 9.4-9 Questionnaire Survey Statistical Form of the Project
No. Investigation OptionsNumbe
r
Proportion
%
1
Are you satisfied with
current living
environment quality?
A.Very satisfied 4 11.1
B.Relatively satisfied 2 5.6
C.Dissatisfied 30 83.3
D.No idea 0 0
2
Are you
understanding / aware
of this project?
A. Do not know 2 5.6
B. Know a little 33 91.7
C. Know nothing 1 2.8
3
What do you think of
the biggest problem
presently affecting the
environmental
quality?
A. Air pollution 17 47.2
B.Water environment pollution 24 66.7
C.Noise 0 0
D.Solid waste 0 0
E.Ecological environment 0 0
F.Not clear 3 8.3
4
What do you think of
the project’s
improvement to the
development of local
economy?
A. Great 33 91.7
B. General 0 0
C. No impact 0 0
D.Not clear 3 8.3
5
What do you think of
the function of this
project to
comprehensive
administration of
regional
environment?
A. Great 29 80.6
B. General 2 5.6
C. No impact 0 0
D.Not clear 5 18.9
6 What impact do you
think this project have
A.Good impact 22 61.1
B.Little impact 10 27.8
on your life, study,
work and
C.Bad impact 2 5.6
D.No impact 2 5.6
7
The environmental
impact of this project
is mainly in the
construction phase,
what do you think of
the bigest negative
impact on the
environment during
construction?
A.Construction dust 11 30.6
B . Domestic waste and waste water during
Construction27 75.0
C.Construction noise 1 2.8
D.Damages to existing vegetation and habitats 1 2.8
E.Others 3 8.3
8
What do you think of
the biggest negative
impact on
environment during
the operation of this
project?
A.Foul smell in the recycled water plant 9 25.0
B.Noise of Water Intake Pump Station 0 0
C.Domestic garbage and other solid wastes in
the plant22 61.1
D. Others 5 18.9
9
What do you think of the biggest problem presently affecting the environmental quality?
A. Air pollution 11 30.6
B.Water environment pollution 32 88.9
C.Noise 0 0
D.Solid waste 0 0
E.Ecological environment 2 5.6
F.Not clear 1 2.8
10
What is your attitude
if the project needs to
expropriate part of
land?
A.To handle it by policy 4 11.1
B.To push for reasonable compensation 32 88.9
C.Not willing to be expropriated 0 0
11
Based on above, what
is your overall
attitude to this
project?
A. Support 35 97.2
B. Do not support 0 0
C. No opinion 1 2.8
12
Do you have any
suggestions and
requirements if the
construction of this
project needs you to
move and expropriate
your land?
None
13 Do you have any
suggestions and
requirements on
environment
None
protection of this
project?
Statistical results of questionnaire show that:
(1) In the invested group, 83% are dissatisfied with current living environment
quality. 97% of interviewees know the project well or know a little. We can see that
publicity of the project has some impact in the local area. It is widely spread.
(2) In the investigated group, most people think that the biggest problems
presently affecting the environmental quality are water environment pollution
(67%)and air pollution(47%). 86% of people think that the construction of the
project has positive impact on the development of local economy and improvement of
local environmental quality. Most people think that this project has good impact or no
impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include domestic waste and waste water during
construction(75%) , construction dust (32%) , construction noise (3%)and
damages to existing vegetation and habitats ( 3% ) . The main environmental
problems caused by operation of this project include domestic garbage and other solid
wastes in the plant (61%) and foul smell in the recycled water plant, (25%) .
During the implementation of this project, these problems should be considered, and
effectively controlled and dealed with.
(4) The public thinks that problems that should be solved by the environment
evaluation include water environment pollution(89%), air pollution(31%)and
ecological environment ( 6% ) . When asked for opinions on expropriating their
land, 11% of people accept to be expropriated according to related policies. 89%
agree to push for reasonable compensation. No one is not willing to be expropriated.
Therefore, the above suggestions of the public should be considered during the
environmental evaluation of this project.
(5) In the investigated group, 97% support the construction of this project. No
one is against the construction of this project. 3% show no opinion. We can see that
this project is supported by most people.
9.4.1.5 Sewage Disposal Project Questiohnaire Survey of Wulatehouqi Industry
Park
1)Statistical analysis of questionnaire interviewees
In this project questionnaire, totally 37 individual questionnaire forms were
given out. 37 were recovered. The recovery pencent was 100%. See statistics of
interviewees in Table 9.4-10.
Table 9.4-10 List of Interviewees
ItemsSex Age
Male Female 18~30 31~40 41~50 >50
Number 29 8 6 9 12 10
Proportion
%79 21 16 24 33 27
Items
Education
Junior College
and above
Senior Middle School
and Technical
Secondary School
Junior
Middle
School
Primary
SchoolNot filled
Number 7 3 7 9 11
Proportion
%19 8 19 24 20
ItemsOccupation
Worker Farmer Cadre Others Not filled
Number 11 25 0 0 1
Proportion
%30 68 0 0 2
From the above statistics, we can see that areas around this project are mainly
agriculture areas. Local residents have different education background. 19% have
junior college and above education. 8% have senior middle school and technical
secondary school education. 64% have junior middle school and primary school
education. The interviewees are mainly workers in the Wulatehouqi Industry Park and
farmers living around. It accords with the real situation of local people.
2)Statistical analysis of Questionnaire Results
See questionaire statistic results of this project in Table 9.4-11.
Table 9.4-11 Questionnaire Survey Statistical Form of the Project
No. Investigation OptionsNumbe
r
Proportion
%
1
Are you satisfied with
current living
environment quality?
A.Very satisfied 24 64.9
B. RELATIVELY SATISFIED 9 24.3
C.Dissatisfied 4 10.8
D.No idea 0 0
2
Are you
understanding / aware
of this project?
A. Do not know 3 8.1
B. Know a little 23 62.2
C. Know nothing 11 29.7
3
What do you think of
the biggest problem
presently affecting the
environmental
quality?
A. Air pollution 25 67.6
B.Water environment pollution 21 56.8
C.Noise 3 8.1
D.Solid waste 9 24.3
E.Ecological environment 20 54.1
F.Not clear 0 0
4
What do you think of
the project’s
improvement to the
development of local
economy?
A. Great 30 81.1
B. General 4 10.8
C. No impact 1 2.7
D.Not clear 2 5.4
5
What do you think of
the function of this
project to
comprehensive
administration of
regional
environment?
A. Great 28 75.7
B. General 3 8.1
C. No impact 1 2.7
D.Not clear 5 13.5
6
What impact do you
think this project have
on your life, study,
work and
entertainment?
A.Good impact 13 35.1
B.Little impact 20 54.1
C.Bad impact 1 2.7
D.No impact 3 8.1
7 The environmental
impact of this project
is mainly in the
construction phase,
A.Construction dust 19 51.3
B . Domestic waste and waste water during
Construction15 40.5
C.Construction noise 8 21.6
what do you think of
the bigest negative
impact on the
D.Damages to existing vegetation and habitats 16 43.2
E.Others 1 2.7
8
What do you think of
the biggest negative
impact on
environment during
the operation of this
project?
A.Foul smell in the recycled water plant 14 37.8
B.Noise of Water Intake Pump Station 8 21.6
C.Domestic garbage and other solid wastes in
the plant10 27.0
D.Others 11 29.7
9
What problems do
you think the
environmental
evaluation should
solve?
A. Air pollution 20 54.1
B.Water environment pollution 14 37.8
C.Noise 8 21.6
D.Solid waste 7 18.9
E.Ecological environment 17 45.9
F.Not clear 0 0
10
Based on above, what
is your overall
attitude to this
project?
A. Support 36 97.3
B. Do not support 0 0
C. No opinion 1 2.7
11
Do you have any
suggestions and
requirements on
environment
protection of this
project?
The construction must be implemented according to requirements of the
country.
Statistical results of questionnaire show that:
(1) Most people are satisfied with current living environment quality. 70% of
interviewees know the project well or know a little. We can see that publicity of the
project has some impact in the local area. It is widely spread.
(2) In the investigated group, most people think that the biggest problems
presently affecting the environmental quality are air pollution, water environment
pollution and air damages to ecological environment. Most people think that the
construction of the project has positive impact on the development of local economy
and improvement of local environmental quality. 89% think that this project has good
impact or no impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include construction dust (51%) , damages to existing
vegetation and habitats ( 43% ) , domestic waste and waste water during
Construction ( 41% ) and construction noise ( 22% ) . The main environmental
problems caused by operation of this project include foul smell in the recycled water
plant (38%), domestic garbage and other solid wastes in the plant (27%) and
noise of water intake pump station ( 22% ) . During the implementation of this
project, these problems should be considered, and effectively controlled and dealed
with.
(4) The public thinks that problems that should be solved by the environment
evaluation include air pollution(54%) , ecological environment (46%) , water
environment pollution(38%), noise(22%)and solid waste(19%). Therefore,
the above suggestions of the public should be considered during the environmental
evaluation of this project.
(5) In the investigated group, 97% support the construction of this project. No
one is against the construction of this project. 3% show no opinion. We can see that
this project is supported by most people.
9.4.1.6 Sewage Disposal Recycling Project Questiohnaire Survey of Ganqimaodu
Port
2) Statistical analysis of questionnaire interviewees
In this project questionnaire, totally 19 individual questionnaire forms were
given out. 19 were recovered. The recovery pencent was 100%. See statistics of
interviewees in Table 9.4-12.
Table 9.4-12 List of Interviewees
ItemsSex Age
Male Female 18~30 31~40 41~50 >50
Number 8 11 5 6 8 0
Proportion
%42 58 26 32 42 0
Items
Education
Junior College
and above
Senior Middle School
and Technical
Secondary School
Junior
Middle
School
Primary
SchoolNot filled
Number 0 7 11 0 1
Proportion
%0 37 58 0 5
ItemsOccupation
Worker Farmer Cadre Others Not filled
Number 0 15 0 3 1
Proportion
%0 79 0 16 5
From the above statistics, we can see that areas around this project are mainly
agriculture areas. Local residents have different education background. 37% have
senior middle school and technical secondary school education. 58% have junior middle
school and primary school education. The interviewees are mainly farmers living
around. It accords with the real situation of local people.
2) Statistical analysis of Questionnaire Results
See questionaire statistic results of this project in Table 9.4-13.
Table 9.4-13 Questionnaire Survey Statistical Form of the Project
No. Investigation OptionsNumbe
r
Proportion
%
1
Are you satisfied with
current living
environment quality?
A.Very satisfied 0 0
B. RELATIVELY SATISFIED 3 15.8
C.Dissatisfied 16 84.2
D.No idea 0 0
2
Are you
understanding / aware
of this project?
A. Do not know 0 0
B. Know a little 5 26.3
C. Know nothing 14 73.7
3 What do you think of
the biggest problem
presently affecting the
A. Air pollution 17 89.5
B.Water environment pollution 11 57.9
C.Noise 0 0
environmental
quality?
D.Solid waste 7 36.8
E.Ecological environment 2 10.5
F.Not clear 0 0
4
What do you think of
the project’s
improvement to the
development of local
economy?
A. Great 16 84.2
B. General 1 5.3
C. No impact 0 0
D.Not clear 2 10.5
5
What do you think of
the function of this
project to
comprehensive
administration of
regional
environment?
A. Great 16 84.2
B. General 2 10.5
C. No impact 0 0
D.Not clear 1 5.3
6
What impact do you
think this project have
on your life, study,
work and
entertainment?
A.Good impact 10 52.6
B.Little impact 4 21.1
C.Bad impact 2 10.5
D.No impact 3 15.8
7
The environmental
impact of this project
is mainly in the
construction phase,
what do you think of
the bigest negative
impact on the
environment during
construction?
A.Construction dust 3 15.8
B . Domestic waste and waste water during
Construction6 31.6
C.Construction noise 4 21.1
D.Damages to existing vegetation and habitats 7 36.8
E.Others 7 36.8
8
What do you think of
the biggest negative
impact on
environment during
the operation of this
project?
A.Foul smell in the recycled water plant 7 36.8
B.Noise of Water Intake Pump Station 2 10.5
C.Domestic garbage and other solid wastes in
the plant6 31.6
D.Others 7 36.8
9
What problems do
you think the
environmental
evaluation should
solve?
A. Air pollution 17 89.5
B.Water environment pollution 12 63.2
C.Noise 0 0
D.Solid waste 8 42.1
E.Ecological environment 2 10.5
F.Not clear 0 0
10 Based on above, what
is your overall
A. Support 18 94.7
B. Do not support 0 0
attitude to this C. No opinion 1 5.3
11
Do you have any
suggestions and
requirements on
environment
protection of this
project?
None
Statistical results of questionnaire show that:
(1) In the investigated group, 26% know the project well or know a little. 74%
know notihng about the project. We can see that we should strengthen the publicity of
the project in local area, so that more people will provide opinions and suggestions to
the project.
(2) Most people are satisfied with current living environment quality. Most people think that the
biggest problems presently affecting the environmental quality are air pollution, water
environment pollution and solid waste pollution. Most people think that the
construction of the project has positive function to the development of local economy
and improvement of local environmental quality. 74% think that this project has good
impact or no impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include damages to existing vegetation and habitats
(37%), domestic waste and waste water during construction(32%), construction
noise(21%) and construction dust (16%) . The main environmental problems
caused by operation of this project include foul smell in the recycled water plant
(37%), domestic garbage and other solid wastes in the plant (32%) and noise of
water intake pump station(11%). During the implementation of this project, these
problems should be considered, and effectively controlled and dealed with.
(4) The public thinks that problems that should be solved by the environment
evaluation include air pollution(90%), water environment pollution(63%), solid
waste(42%)and ecological environment (10%). Therefore, the above suggestions
of the public should be considered during the environmental evaluation of this project.
(5) In the investigated group, 95% support the construction of this project. No
one is against the construction of this project. 5% show no opinion. Therefore, it is
adviced to make further explanation to the project to some people, help them have a
better understanding to the project and take their suggestions as reference.
9.4.1.7Sewage Disposal Recycling Project Questiohnaire Survey of Wulateqianqi
Industry Park
1)Statistical analysis of questionnaire interviewees
In this project questionnaire, totally 35 individual questionnaire forms were
given out. 35 were recovered. The recovery pencent was 100%. See statistics of
interviewees in Table 9.4-14.
Table 9.4-14 List of Interviewees
ItemsSex Age
Male Female 18~30 31~40 41~50 >50
Number 22 13 14 4 14 3
Proportion
%63 37 40 11 40 9
Items
Education
Junior College
and above
Senior Middle School
and Technical
Secondary School
Junior
Middle
School
Primary
SchoolNot filled
Number 14 6 9 6 0
Proportion
%40 17 26 17 0
ItemsOccupation
Worker Farmer Cadre Others Not filled
Number 10 18 0 1 6
Proportion
%29 51 0 3 17
From the above statistics, we can see that local residents have different education
background. 40% have Junior College and above education. 17% have senior middle school
and technical secondary school education. 43% have junior middle school and primary
school education. The interviewees are mainly workers in the Wulateqianqi Industry
Park and farmers living around. It accords with the real situation of local people.
2)Statistical analysis of Questionnaire Results
See questionaire statistic results of this project in Table 9.4-15.
Table 9.4-15 Questionnaire Survey Statistical Form of the Project
No. Investigation Options NumberProportion
%
1
Are you satisfied with
current living
environment quality?
A.Very satisfied 9 25.7
B. RELATIVELY SATISFIED 17 48.6
C.Dissatisfied 7 20.0
D.No idea 2 5.7
2Are you understanding
/ aware of this project?
A. Do not know 5 14.3
B. Know a little 20 57.1
C. Know nothing 10 28.6
3
What do you think of
the biggest problem
presently affecting the
environmental
quality?
A. Air pollution 26 74.3
B.Water environment pollution 26 74.3
C.Noise 1 2.9
D.Solid waste 2 5.7
E.Ecological environment 9 25.7
F.Not clear 1 2.9
4
What do you think of
the project’s
improvement to the
development of local
economy?
A. Great 24 68.6
B. General 6 17.1
C. No impact 0 0
D.Not clear 5 14.3
5
What do you think of
the function of this
project to
comprehensive
administration of
regional environment?
A. Great 24 68.6
B. General 7 20.0
C. No impact 0 0
D.Not clear 4 11.4
6
What impact do you
think this project have
on your life, study,
work and
entertainment?
A.Good impact 22 62.9
B.Little impact 7 20.0
C.Bad impact 0 0
D.No impact 6 17.1
7 The environmental
impact of this project
A.Construction dust 20 57.1
B . Domestic waste and waste water during 14 40.0
is mainly in the
construction phase,
what do you think of
the bigest negative
Construction
C.Construction noise 7 20.0
D . Damages to existing vegetation and
habitats 7 20.0
E.Others 4 11.4
8
What do you think of
the biggest negative
impact on
environment during
the operation of this
project?
A.Foul smell in the recycled water plant 23 65.7
B.Noise of Water Intake Pump Station 8 22.9
C.Domestic garbage and other solid wastes
in the plant12 34.3
D.Others 2 5.7
9
What problems do you
think the
environmental
evaluation should
solve?
A. Air pollution 27 77.1
B.Water environment pollution 25 71.4
C.Noise 3 8.6
D.Solid waste 3 8.6
E.Ecological environment 7 20.0
F.Not clear 1 2.9
10
Based on above, what
is your overall attitude
to this project?
A. Support 33 94.3
B. Do not support 0 0
C. No opinion 2 5.7
11
Do you have any
suggestions and
requirements on
environment
protection of this
project?
1. Real problems should be solved.
2. All the citizens should participate. Implementation time should be
shortened. Make good use of investment period.
3. Loan shall be used by people. For the good of people.
Statistical results of questionnaire show that:
(1) Most people are very satisfied or relatively satisfied with current living environment
quality. 71% of interviewees know the project well or know a little. We can see that
publicity of the project has some impact in the local area. It is widely spread.
(2) In the investigated group, most people think that the biggest problems presently
affecting the environmental quality are air pollution, water environment pollution and
damages to ecological environment. Most people think that the construction of the
project has positive function to the development of local economy and improvement
of local environmental quality. 83% think that this project has good impact or no
impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include construction dust (57%) , domestic waste and
waste water during construction(40%), construction noise(20%) and damages
to existing vegetation and habitats ( 20% ) . The main environmental problems
caused by operation of this project include foul smell in the recycled water plant
(66%), domestic garbage and other solid wastes in the plant (34%) and noise of
water intake pump station(23%). During the implementation of this project, these
problems should be considered, and effectively controlled and dealed with.
(4) The public thinks that problems that should be solved by the environment
evaluation include air pollution ( 77% ) , water environment pollution ( 71% ) ,
ecological environment (21%), noise (9%)and solid waste(42%). Therefore,
the above suggestions of the public should be considered during the environmental
evaluation of this project.
(5) In the investigated group, 94% support the construction of this project. No
one is against the construction of this project. 6% show no opinion. Therefore, it is
adviced to make further explanation to the project to some people, help them have a
better understanding to the project and take their suggestions as reference.
9.4.1.8 Comprehensive Project Questiohnaire Survey of Wuliangsuhai Area
1)Statistical analysis of questionnaire interviewees
In this project questionnaire, totally 91 individual questionnaire forms were
given out. 91 were recovered. The recovery pencent was 100%. See statistics of
interviewees in Table 9.4-16.
Table 9.4-16 List of Interviewees
ItemsSex Age
Male Female 18~30 31~40 41~50 >50
Number 73 18 7 20 46 18
Proportion
%80 20 8 22 50 20
Items
Education
Junior College
and above
Senior Middle School and
Technical Secondary
School
Junior
Middle
School
Primary
SchoolNot filled
Number 8 18 43 13 9
Proportion
%9 20 47 14 10
ItemsOccupation
Worker Farmer Cadre Others Not filled
Number 57 30 2 0 2
Proportion
%63 33 2 0 2
From the above statistics, we can see that local residents have different education
background. 9% have Junior College and above education. 20% have senior middle school
and technical secondary school education. 61% have junior middle school and primary
school education. The interviewees are mainly workers and farmers around
Wuliangsuhai. It accords with the real situation of local people.
2)Statistical analysis of Questionnaire Results
See questionaire statistic results of this project in Table 9.4-17.
Table 9.4-17 Questionnaire Survey Statistical Form of the Project
No. Investigation OptionsNumbe
rProportion%
1
Are you satisfied with
current living
environment quality?
A.Very satisfied 1 1.1
B. RELATIVELY SATISFIED 3 3.3
C.Dissatisfied 86 94.6
D.No idea 0 0
2Are you understanding
/ aware of this project?
A. Do not know 1 1.1
B. Know a little 78 85.7
C. Know nothing 12 13.3
3 What do you think of
the biggest problem
presently affecting the
A. Air pollution 1 1.1
B.Water environment pollution 87 95.6
C.Noise 0 0
environmental
quality?
D.Solid waste 2 2.2
E.Ecological environment 3 3.3
F.Not clear 0 0
4
What do you think of
the project’s
improvement to the
development of local
economy?
A. Great 82 90.1
B. General 7 7.7
C. No impact 2 2.2
D.Not clear 0 0
5
What do you think of
the function of this
project to
comprehensive
administration of
regional environment?
A. Great 83 91.2
B. General 4 4.4
C. No impact 0 0
D.Not clear 4 4.4
6
What impact do you
think this project have
on your life, study,
work and
entertainment?
A.Good impact - 61.0
B.Little impact - 18.7
C.Bad impact - 3.8
D.No impact - 16.5
7
The environmental
impact of this project
is mainly in the
construction phase,
what do you think of
the bigest negative
impact on the
environment during
construction?
A.Construction dust 1 1.1
B . Domestic waste and waste water
during Construction16 17.6
C.Construction noise 64 70.3
D . Damages to existing habitats in
Wuliangsuhai7 7.7
E.Others 3 3.3
8
What problems do you
think the
environmental
evaluation should
solve?
A. Air pollution 0 0
B.Water environment pollution 82 90.1
C.Noise 0 0
D.Solid waste 3 3.3
E.Ecological environment 6 6.6
F.Not clear 0 0
9
What impact do you
think the construction
of this project have on
the local tourism
industry?
A.Increase 90 98.9
B.Decrease 1 1.1
C.No impact 0 0
D.Not clear 0 0
10
What is your attitude
if the project needs to
expropriate part of
land?
A.To handle it by policy 67 73.6
B.To push for reasonable compensation 24 26.4
C.Not willing to be expropriated 0 0
11
Based on above, what
is your overall attitude
to this project?
A. Support 91 100
B. Do not support 0 0
C. No opinion 0 0
12
Do you have any
suggestions and
requirements if the
construction of this
project needs you to
move and expropriate
your land?
1. By negotiation;2.To push for reasonable compensation。
13
Do you have any
suggestions and
requirements on
environment
protection of this
project?
1. Try our best not to damage habitats of birds.
2. Water quality should be improved.
Statistical results of questionnaire show that:
(1) In the investigated group, most people know the project well or know a little.
We can see that publicity of the project has some impact in the local area. It is widely
spread.
(2) 95% of interviewees are dissatisfied with current living environment quality. 96%
think that the biggest problem presently affecting the environmental quality is water
environment pollution. Most people think that the construction of the project has
positive function to the development of local economy and improvement of local
environmental quality, and they also think that this project has good impact or no
impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include construction noise(70%), domestic waste and
waste water during construction(18%)and damages to birds’ habitats (8%). Therefore,
during the implementation of this project, these problems should be considered, and
effectively controlled and dealed with.
(4) The public thinks that problems that should be solved by the environment
evaluation include water environment pollution(90%)and ecological environment
(7%). When asked for opinions on expropriating their land, 74% of people accept
to be expropriated according to related policies. 26% agree to push for reasonable
compensation. No one is not willing to be expropriated. Therefore, the above
suggestions of the public should be considered during the environmental evaluation of
this project.
(5) In the investigated group, 100% support the construction of this project. No
one is against the construction of this project. We can see that this project is supported
by most people.
9.4.1.9 Summary
The public participation survey shows that interviewees commonly have some
environmental protection awareness. Most people think that the construction of this
project has good economic benefits and social effects. They support the construction of the
project. But effective measures should be taken to reduce environmental effects of the project.
Some people don’t care. The report shows that the survey result reflects the public’s willingness. It
is generally accords with the project. We should pay much attention on problems showing up in
the survery, and gradually eliminate hidden troubles by strengthing management and acting
according to law.
9.4.2 Statistical analysis of Group Questionnaire
9.4.2.1 Group Interviewees
Environmental impact evaluation unit gave out group questionnaire to the
following units from November 22th 2009 to December 31th 2009.
Bayannur’s Political Consultative Conference
Bayannur People's Congress
Bayannur Environmental Protection Bureau
Bayannur Linhe District Environmental Protection Bureau
Bayannur Environmental Monitoring Station
Bayannur Environmental Monitoring Unit
Bayannur Research Academy of Environmental Sciences
Administration of Inner Mongolia Hetao Irrigation District, Bayannur
In this group questionnaire, 60 forms were given out. 59 were recovered. The
recovery rate was 99%.
9.4.2.2 Group Survey Results
See the statistical results of group questionnaire in Table 9.4-18.
Table 9.4-18 Group Questionnaire Survey Statistical Form
No. Investigation OptionsNumbe
rProportion%
1
Are you satisfied with
current living
environment quality?
A.Very satisfied 10 16.9
B. RELATIVELY SATISFIED 43 72.9
C.Dissatisfied 6 10.2
D.No idea 0 0
2Are you understanding
/ aware of this project?
A. Do not know 19 32.2
B. Know a little 34 57.6
C. Know nothing 6 10.2
3
What do you think of
the biggest problem
presently affecting the
environmental
quality?
A. Air pollution 33 55.9
B.Water environment pollution 41 69.5
C.Noise 16 27.1
D.Solid waste 10 16.9
E.Ecological environment 17 28.8
F.Not clear 0 0
4
What do you think of
the project’s
improvement to the
development of local
economy?
A. Great 47 79.7
B. General 9 15.3
C. No impact 2 3.3
D.Not clear 1 1.7
5
What function to you
think this project has
on comprehensive
environment
administration in
Wuliangsuhai?
A. Great 49 83.1
B. General 7 11.9
C. No impact 1 1.7
D.Not clear 2 3.3
6 What impact do you
think this project have
on your life, study,
work and
A.Good impact - 24.1
B.Little impact - 55.9
C.Bad impact - 4.4
D.No impact - 15.3
entertainment?
7
The environmental
impact of this project
is mainly in the
construction phase,
what do you think of
the bigest negative
impact on the
environment during
construction?
A.Construction dust 28 47.5
B . Domestic waste and waste water
during Construction32 54.2
C.Construction noise 31 52.5
D . Damages to existing habitats in
Wuliangsuhai10 16.9
E.Others 15 25.4
8
What problems do you
think the
environmental
evaluation should
solve?
A. Air pollution 30 50.8
B.Water environment pollution 44 74.6
C.Noise 13 22.0
D.Solid waste 6 10.2
E.Ecological environment 27 45.8
F.Not clear 0 0
9
What impact do you
think the construction
of this project have on
the local tourism
industry?
A.Increase 51 86.4
B.Decrease 1 1.7
C.No impact 6 10.2
D.Not clear 1 1.7
10
What is your attitude
if the project needs to
expropriate part of
land?
A.To handle it by policy 43 72.9
B.To push for reasonable compensation 15 25.4
C . not willing to be expropriated
1 1.7
11
Based on above, what
is your overall attitude
to this project?
A. Support 56 94.9
B. Do not support 0 0
C. No opinion 3 5.1
12
Do you have any
suggestions and
requirements if the
construction of this
project needs you to
move and expropriate
your land?
1. Save lands and protect the existing farmland area;
2. Give the residents maximum economic remedies. Solve social security,
medical security and other problems. Try not to influence residents’ normal
life;
3. Provide more remedies. Make expropriation known to the public and
make move easy.
13 Do you have any
suggestions and
requirements on
environment
protection of this
project?
1. As a comprehensive project, this project is good for water environment
protection. During the implementation of project, environment protection
measures and disturb impact shall be paid attention to in the process of
construction.
2. Protect plants around during the construction process.
3. During the construction process environmental problems shall be paid
attention to. Decrease damages to ecological environment to minimum.
4 Make government finance know to the public. Invite bids
according to regulations. Reasonable staff distribution.5. Protect gardens and water. Solve waste water emission reasonably.
Statistical results of group questionnaire show that:
(1) This project has big impact in the investigated area. 90% of people in the
investigated units know the project well or know a little.
(2) 95% of interviewees are vert satisfied or relatively satisfied with current living
environment quality. Interviewees think that the biggest problem presently affecting the
environmental quality are water environment pollution ( 70% ) , air
pollution ( 56% ) , ecological environment ( 29% ) , noise ( 27% ) and solid
waste(17%) . Most people think that the construction of the project has positive
function to the development of local economy and improvement of local
environmental quality, and they also think that this project has good impact or no
impact on their daily life.
(3) The public thinks that the main environmental problems caused by
construction of this project include domestic waste and waste water during
construction(54%) , construction noise(53%) , construction dust(48%)and
damages to birds’ habitats in Wuliangsuhai ( 17% ) . Therefore, during the
implementation of this project, these problems should be considered, and effectively
controlled and dealed with.
(4) The interviewees think that problems that should be solved by the
environment evaluation include water environment pollution ( 75% ) , air
pollution(51%), noise(22%), solid waste(10%) and ecological environment
(7%). When asked for opinions on expropriating their land, 73% of people accept
to be expropriated according to related policies. 25% agree to push for reasonable
compensation. 2% is not willing to be expropriated. Therefore, the above suggestions
of the public should be considered during the environmental evaluation of this project.
(5) In the investigated group, 95% interviewees support the construction of this
project. No one is against the construction of this project. 5% show no opinion.
At the same time, the investigated groups provide the following opinions and
suggestions:
(1) When the construction of project needs to expropriate the residents’ land, the
expropriation shall be made known to the public. Give the residents maximum
economic remedies. Solve social security, medical security and other problems. Try
not to influence residents’ normal life. Try not to influence residents’ normal life.
Save the land and protect the existing farm area.
(2) This project is a comprehensive project. It is good for the protection of water
environment. During the implementation of project, environmental protection
measures shall be paid attention to. Control disturbing impact during construction
process.
(3) Environmental problems shall be paid attention to during construction. Protect
plants around and decrease damages to ecological environment to minimum.
(4)Protect gardens and water. Solve waste water emission reasonably.
9.4.2.3 Summary
In a word, the investigated groups have strong environmental protection
awareness. They know possible causes of environmental pollution well. Therefore,
local environmental department and construction unit should pay attention the above
problems. During different stages of construction, related environmental protection
laws and regulations shall be strictly followed. Increase impact on local
environmental quality to the minimum.
9.5 Public Participation Forum
For the investigation result of the first turn of public participation, to fully
understand and ask the public for advices to the project, after the first draft of EIA
Report was completed, the EIA unit held Implementing Bayannur Water Environment
Comprehensive Administration Project with World Bank Loan Environmental Impact
Public Forum in conference room of Inner Mongolia Bayannur Hetao Water Group
Co. Ltd. on February 1st 2010.19 people participated in the conference, including
resident representatives of subprojects, representative of Bayannur Hetao Area
Administration Bureau and experts of Bayannur Environmental Protection Bureau.
See name list of participants in Table 9.5-1.
Table 9.5-1 Name list of forum participants
No. Name Title Working place/Living place
1 Yang Zhen Environmental
protection expert
Bayannur Environmental Protection Bureau
2 Liu Jing Environmental
protection expert
Bayannur Environmental Protection Bureau
3 Xue Zhiguo Officer of Water
Bureau
Water Law Department, Bayannur Water Bureau
4 Liu Xinli Officer of Water
Bureau
Water Law Department, Bayannur Water Bureau
5 Bai Bo Officer of Water
Bureau
Water Law Department, Bayannur Water Bureau
6 Zhao Ping Enterprise
representative
Director of Wulatehouqi Zijin Corperation
7 Liu Bingjun Enterprise
representative
Person in Charge of Wuyuan Hetao Wine Corporation
8 Gao Guangyin Resident
representative
Village Director, Dengcundian, West Xiaozhao Town,
Wulateqianqi
9 Zhang Eryong Resident Representative, Hongqipu Village, Xinan
Town, Wulateqianqi
10 Su Yue Resident Representative, Yangshuhao Village, Xinan
Town, Wulateqianqi
11 Wang Saikou Resident Representative, Xinfeng Village, Dulun
Town, Wulateqianqi
12 He Ru Resident Representative, Hongqipu Village, Shulinzi
Town, Wulateqianqi
13 Guan Li Resident Representative, Sheep Sea Farm,
Wulatezhongqi
14 Zhang Jun Resident Representative, Guangtieqidan Village,
Denglingshan Town, Wulatezhongqi
15 Yang San Resident Representative, Wuzhen Village,
Denglingshan Town, Wulatezhongqi
16 Kang Long Resident Representative, Menglian Village, Green
Mountain Town, Wulatehouqi
17 Hao Limin Resident Representative, Old City Village,
Longxingchang Town, Wuyuan County
18 Li Sanhong Resident Representative, Xinhong Village, Shahai
Town, Hangjinhouqi
19 Li Ping Resident Representative, Sizu Village, Dashun City,
Hangjinhouqi
The forum lasted for 3 hours. The representatives showed their opinions and
suggestions on this project. Experts from Hetao Group Corparation, Chinese
Academy of Sciences and Environmental Protection Bureau explained and
communicated about the problems. The conference was nervous and impassioned.
Problems, opinions and suggestions provided by representatives include:
(1)Operation of project will reduce total drain. It is adviced to analyze impact
of water reduce on total drain and water quality in Wuliangsuhai.
(2)It is adviced to analyze economic benefits and ecological effects.
(3)Control the project’s impact on underground water.
(4)To effectively reduce or prevent environmental impact during construction
and operation of project, reasonable and effective measures shall be provided.
( 5 ) For Wuliangsuhai Area Administration Project, it is adviced to analyze
basic characteristics of bottom mud in Wuliangsuhai, how to implement the
construction to reduce bottom mud data’s impact on environment in Sea Area, and
how to deal witth the mud dugged out.
Public representatives in this forum were concered with environmental problems. They
provided opinions, suggestions and hope actively. More important, they accepted this project’s
positive function on environmental protection. They thought there were more advantages than
disadvantages. Therefore, the construction unit shall pay much attention to and actively adopt
opinions and suggestions of public representatives.
Figure 9.5-1 Photos of forum site
9.6 Public Participation Summary and Public Opinion Adoption
9.6.1 Public Participation Summary
This project carries out public participation work by giving out questionnaires to
the public, holding conferences, posting official notice, publishing related information
on website and newspaper, asking for advices from experts and officials, and other
methods. Investigated people include people affected by the project within the range
of the project, groups interested in the project, government officers, expert
representatives, and other people. A large amount of public information has been
collected. The conclusion is as below:
(1)Survey result shows 95% people support this project. No one is agaist the
project.
( 2 ) Interviewees consider waste water, noicse, dust, rubbish, construction
land, damages to plants, damages to habitats in Wuliangsuhai and other problems.
( 3 ) Construction unit should strengthen environmental protection
administration, ensure normal operation of environmental protection facilities and
control emission of pollution.
( 4 ) Administration and supervision shall be strengthed. Prevent emergency
accident and made contingency plan.
( 5 ) Most people think that the biggest problem presently affecting the
environmental quality is water environment pollution. But they think the construction
of this project has positive impact on the area. To some degree, it can improve the
quality of water environment, ecological environment and the development of local
economy.
( 6 ) Local people think that environmental education can strengthen
environmental awareness. According to the report, investigation of public participation reflects willingness
of the public well. Problems showing up in the investigation should be paid attention
to. In different stages of the construction, related regulations and rules of environment
protection should be strictly complied with. Impact to local environmental quality
should be reduced to the minimum.
9.6.2 Public Opinion Adoption
During the EIA, EIA unit analyzed problems concerned by the public and
brought forth corresponding mitigating measures to reduce environmental impact of
construction to acceptable degree. See detailed in Table 9.6-1.
Through the different forms of public participation, construction unit shall
provide the following adoption suggestions for opinions and suggestions feedback by
the public.
(1) Environmental administration must be strengthened. Normal operation of
environmental protection facilities shall be ensured. Control emission of
pollution, prevent emergency accident and made contingency plan. At the same
time accept supervision from people around.
(2) Strengthen environmental protection measures during construction. Prevent
dusts, keep roads clean, prevent water loss and soil erosion, reduce noise and
bottom mud’s impact on ecological environment in Wuliangsuhai, strengthen
environmental protection supervision during construction and accept supervision
from people around.
Table 9.6-1 EIA Feedback of Public Participation
No. Time of Public Participation
Main Problems Concerned by the Public EIA Feedback
1
The first turn of public participation(Time of personal
questionnaire:from November 17th 2009 to November 22 nd
2009;Time of group
questionnaire:from November 22 nd 2009
to December 31st
2009)
It is hoped that the project can be carried out on the basis of ecological protection idea.
During the construction of project, there will be different degrees of impact on ecological environment. Detailed measures have been established in Environmental Monitoring Plan to ensure that regional ecological environment will be recovered as soon as possible after completion of the project.
2
During the construction of project, the project should not affect residents living around. The construction should always protect wetland, serve as ecological forest, and improve the environment.
Different prevention measures have been established for different environmental impact factors during the construction. There should be no impact on relocated residents.
3
Construction team should promote civilized construction during the construction. Environmental health and waste disposal of temporary living area of construction personnel. Dust and noise pollution during construction should be avoided.
The construction party is required to made detailed construction plan. Closed vehicle must be used in the transport of earth, dirt and construction waste. Main construction roads must be hardened. Construction site should use covering, curing, greening, sprinkling and other effective measures. Using of much equipment with high noise at the same time should be avoided. Construction with high-noise equipment should be during day time.
4
Construction unit should have environmental protection construction ability. During dredging process, impact on ecological environment around the project, especially Wuliangsu Lake, should be strictly controlled. Measures should be taken to deal with solid mount. Solid soil should be used reasonably during the last stage.
Detailed mitigation measures of pollution problems have been established in the EIA.
5
The second turn of public participation(February 1st,
2010)
Operating of the project will reduce the total amount of drainage water. It is suggested that impact of water amount reduction on total drainage and water quality of Wuliangsu Lake should be analyzed.
In the EIA Report, this problem has been analyzed. And corresponding suggestions and measures have been established.
6It is suggested that economic effect and ecological effect should be analyzed in detail
In the EIA Report, this problem has been analyzed in detail.
7This project should control impact on underground water under the ground of the project.
In the EIA Report, impact on underground water in this project has been analyzed in detail. And corresponding measures have been established.
8
To effectively reduce or avoid environmental impact during the construction and operating of the project, effective control measures should be brought forth.
In the EIA Report, environmental impact during the construction and operating of the project has been analyzed in detail. And corresponding migration measures have been established.
10. Social Impact and Migrant Resettlement
10.1 Social Impact Analysis
10.1.1 Project Impact and Service Scope Various sub-projects of the project totally involve five banners (counties) of Bayannur
Municipality i.e. Wulatehou Banner, Wulateqian Banner, Hangjinhou Banner, Wuyuan
County and Wulatezhong Banner, four administrative villages of four towns (townships), one
state-owned farmland and one state-owned range land. The construction of the project will
exercise negative impact upon local area such as land requisition and relocation unavoidably.
According to the design fruits of feasibility study report of various projects, 758.00mu land of
different types is to be purchased for the project, including 190.50mu cultivated land,
165.00mu construction land and 397.50mu unused land. 271.73mu land of different types is to
be temporarily purchased, including 68.33mu cultivated land and 203.40mu unused land.
Moreover, the process of the engineering construction will cause some negative impact on
local environment. In project implementation, the project employer unit and relevant design
units will define a reasonable migrant resettlement proposal and environmental protection
plan according to national and local laws and statutes for reducing negative impact of project
construction upon the local.
However, the construction of the project has a great positive impact on the local social
and economic development and environments. Particularly, local water environments will be
obviously improved. The implementation of project will effectively promote the development
and utilization of coal, iron and copper and other mineral resources in Mongolia adjacent to
the project area, boost up regional international economic cooperation, purify water system of
Wuliangsu Lake, an important wetland in Northwest China and protect the Yellow River
against pollution. Therefore, it’s integrated treatment project with outstanding environmental
effect, social and economic benefits. The visit survey on the site reveals that the residents in
the area under project impact highly support the construction of the project.
Main service scope of various sub-projects is the enterprises in industrial park of the
banner (county) that the project involves. The commencement of the project will reduce the
water consumption, improve the utilization efficiency of water resources and better water
environment.
10.1.2 Project Impact Analysis 10.1.2.1 Analysis on Status Quo of Project Impact Area
According to Plan Report of Migrant Resettlement Action of the project, four villages in
the scope of project impact are investigated. All households in the area under the impact of
land requisition and other households under the potential impact are investigated in random
interview and questionnaire modes. The distribution of investigation samples is included in
Table 10.1-1. Table 10.1-1 List of the Distribution of Samples
Town (township)
Administrative village under
impact (village)
Administrative village in
investigation (village)
Total of households
under impact (household)
Qty of investigation households (household)
Inside project impact area
Outside project impact area
Delingshan Town 1 1 3 26
Qingshan Town 1 1 44
Shanba Town 1 1 5 5 22Longxingchang
Town 1 1 32
Total 4 4 5 8 124Note: the quantity of impact households refers to the household with permanent land
requisition; and random sampling investigation is done for the village with permanent land
requisition.
1) The Profile of Villages under Project Impact
The impact of the project involves Wuzhen Village of Delingshan Town (for temporary
land use in the construction only), Hongqi Village of Qingshan Town, Shawan Village of
Shanba Town & Jiucheng Village of Longxingchang Town. The field visit survey reveals that
four villages under the impact of the project all mainly rely upon traditional agriculture, of
which Hongqi Village and Shawan Village features good animal husbandry.
A. Wuzhen Village of Delingshan Town
Wuzhen Village, about 13km in the west of Delingshan Town, bordering the 5th Wengeng
Team, and Hongqi Village and Muyang Lake Rangeland of Delingshan Town, Dasheng
Village of Delingshan Town and Shengli Village of Delingshan Town on the north, west, east
and south respectively features convenient traffic conditions. The village with totally 14
communities, and over 1900 households in total, population of 8137 and cultivated area of
10900mu mainly plants wheat, corn and sunflower; and the animal husbandry mainly includes
pig and sheep breeding. In 2008, the whole village has realized total agricultural incomes of
RMB28.5 million and total animal husbandry incomes of RMB1.14 million.
B. Hongqi Village of Qingshan Town
Hongqi Village Committee located in about 12km east of Qingshan Town, is the final
village on the east of Qingshan Town, and borders Wulagacha of Bayinbaoli Town on north
and is adjacent to Xinguang Village of Hangjinhou Banner on the south. The village has
totally two villager groups, population of 801 including 221 households at the end of 2008,
cultivated area of 5517mu and per-capita cultivated land of 6.89mu/person. There’re totally
651 persons as labor force, 81.27% of the total population.
C. Jiucheng Village of Longxingchang Town
Jiucheng Village, about 11km in the northwest of Longxingchang Town features
convenient traffic conditions, and borders the 1st and 2nd groups of Wuxing Village, Lianfeng
Village, Zhongqi Road of Wuyuan County and Yihe Trunk Canal on the north, west, east and
south respectively. The village has four groups, 412 households and population of 1309 and
658 persons as labor force in total. With cultivated area of 5000mu, it mainly plants
sunflower, corn and tomato; and animal husbandry is mainly cattle and sheep. In 2008, the
village has realized total agricultural incomes of RMB4.80 million, animal husbandry
incomes of RMB120,000. Net per-capita incomes of farmers are RMB4800.0.
D. Shawan Village of Shanba Town
Shawan Village, about 3km in the northwest of Shanba Town features convenient traffic
conditions, and borders Zhongguang Village, Yongsheng Village, Chenguang Village and
Jiatong Village on the north, west, east and south respectively. The village has four
communities, over 295 households, population of 1200 and 540 persons as labor force in
total. With cultivated area of 4000mu, it mainly plants sunflower and corn; and animal
husbandry is mainly cattle and sheep. In 2008, the village has realized total agricultural
incomes of RMB7.6 million and animal husbandry incomes of RMB820,000. Net per-capita
incomes of farmers are RMB7016.
2) Analysis on Basic Information of Households under Project Impact
(1) Population Profile
Profile of Household Population The migrants involved in the project are five
households and 22 persons in total, in which there are 10 females, accounting for 45.5% of
the total, 12 males, accounting for 54.5%, and one is Mongolian nationality and the rest all
are Han nationality.
Age Distribution of Household Population Among 22 persons, there’re two under 18,
accounting for 9.1% of the total; 18 from 18-60, accounting for 81.8%; two over 61,
accounting for 9.1%.
Household Scale In respect of the scale of households under impact, the minimum is 4
persons while the maximum is 5 persons. Each household has 4.4 persons on average.
Distribution of the Educational Background Among the population under land requisition
impact, there’re 5 illiterates, accounting for 22.7%; one preschool person, 4.5%; 5 with
elementary school education, 22.7%; 9 with junior high school education, 40.9%; and 2 with
senior high school education, 9.1%.
(2) Possession of Land Resources
The survey statistics reveal that five sample households with 22 persons have total
contracting farmland of 90mu, 4.09mu per capita and mainly plant wheat, corn and sunflower.
(3) Living and Residential Conditions
The survey on five households under the impact reveals that the houses of all households
are brick-wood structure, total area is 480m2, per-capita housing area is 21.82m2 and the
housing area of each household is about 80-120m2.
The living conditions of the household in project impact area are included in Table 10.1-
2. Table 10.1-2 List of the Survey on Living Conditions of Households in Project Impact Area
Survey indicator UnitIndicator
qtySurvey indicator
Uni
t
Indicator
qty
I. Profile 3. Other incomesRM
B0
1. Total household
populationPerson 22 III. Total household outlays
RM
B189150
Including: female Person 10 1. Agricultural outlaysRM
B62230
2. Total contracting
farmland areaMu 90 Including: planting
RM
B45000
3. Per-capita farmland
area
Mu/
person4.09 Livestock farming/aquatic breeding
RM
B17230
4. Livestock grow-up Animal 1062. Staple and non-staple food
outlays
RM
B68720
5. Housing area m2 480 3. Clothes outlaysRM
B18800
6. Per-capita housing area m2/人 21.82 4. Medical care outlaysRM
B7500
II. Total household
incomesRMB 243970
5. Traffic and communication
outlays
RM
B11900
1. Agricultural incomes RMB 122370 6. Education outlaysRM
B4000
Including: planting RMB 77370 7. Other outlaysRM
B16000
Livestock
farming/aquatic breedingRMB 45000 8. Tax
RM
B0
Forest and fruit RMB 0
2. Labor incomes RMB 121600IV. Annual net per-capita incomes
of household
RM
B8260.91
(4) Production and Operation Mode
The survey and analysis show that the main production mode of nearly all households
under impact is agriculture and animal husbandry, mainly planting wheat, corn and sunflower,
breeding pig and sheep. Three of all households under impact have member for local or non-
local labor output.
(5) Household Incomes
The survey and statistics on economic
incomes of five households under the impact
of cultivated land requisition show that in
2008, per-capita income is RMB11090, in
which per-capita planting income is
RMB3517, accounting for 31.7%; per-capita
Livestock farming/aquatic breeding income
RMB2045, 18.5%; and per-capita labor
income RMB5527, 49.8%.
(6) Household Outlays
项目影响户家庭支出结构图
01000020000300004000050000600007000080000
单位:万元
The above table can reflect the outlays of the households under project impact in 2008 in
staple and non-staple food, clothes, medical care, traffic and communication, and education.
In 2008, the per-capita outlay of the household under project impact is RMB8597,
including per-capita staple & non-staple food outlay RMB3124, accounting for 36.3 %; per-
capita clothes outlay RMB855, 9.9%; per-capita medical care outlay RMB341, 4.0%; per-
capita traffic & communication outlay RMB541, 6.3%; per-capita education outlay RMB182,
2.1%; per-capita agricultural outlay RMB2829, 32.9%; other per-capita outlay RMB727,
8.5%.
项目影响户家庭收入结构图
31. 7%
18. 4%
49. 8%
种植业收入 牧业收入 劳务收入
(7) Impact of Land Requisition of Project Construction upon Economic Incomes of the
Household
The survey and statistics on the impact of land requisition of the project show that totally
five households are involved in the impact of land requisition of the project. The analysis
proves that the economic incomes of these five households are mainly from the contracting
farmland and labor output and the farmland under impact accounts for 33.3% of their total
contracting land. The initial estimate reveals that the land requisition for project construction
would cause an annual agricultural income decrease of about RMB25.79 million for migrant
households, accounting for about 12.9% of total agricultural incomes of the households.
3) Social Status of Women in Project Impact Area and Project Participation
In the rural households of project impact area, women enjoy the same right for the land.
Both husband and wife usually negotiate and determine the issues of their household jointly.
It’s universally known through visit, discussion and questionnaire that the
implementation of the project could better the environment and water quality, reduce the
diseases, indirectly lower the expenses of the underprivileged for medical treatment and
alleviate economic burden of household. After knowing the significance of project
construction, the women in the area with indirect project impact have expressed their strong
support for project construction. Some hold that the land requisition has severe impact upon
their household and expect reasonable resettlement and compensation from the State.
4) Social Status of Minority in Project Impact Area and Project Participation
Bayannur Municipality is the minority region with Mongolian nationality as principal
part while a majority of Han nationality. The residents of Mongolian nationality take part in
various aspects of the production and living of the region. Through informal discussions with
the Minority Affairs Commission of various banners, we know that each minority in
Bayannur Municipality has long history, his own religious beliefs, cultures, arts, habits and
customs while in long social development, the nationalities have adequately exchanged in the
fields such as society, economy and culture and been gradually integrated together. For
example, Mongolian nationality has their own language and uses the language inside their
nationality while speaks Chinese in talking with the outside. The integration of various
minorities is as follows:
Firstly, Chinese is common and official language of various minorities. The minorities
i.e. Mongolian nationality, Hui nationality and Manchu nationality in the region use Chinese
as written language. On the occasion of major festivals, the people of different nationalities
will celebrate e.g. Spring Festival of Han nationality and “Nadamu” Festival of Mongolian
nationality.
Secondly, the minorities not only enjoy the same right in society, economy and culture as
Han nationality but also the preferential policies in education, employment and financial
support. Bayannur Municipality offers a policy-based preference for poverty-stricken
minority villages and minority enterprises.
Thirdly, the people of different nationalities keep in close touch, and give no highlight to
nationality status. The marriage between different nationalities widely exists.
Therefore, the minorities in the project area presently are integrated with Han and other
nationalities by and large.
Among all households under land requisition impact, one person is the resident of
Mongolian nationality. The survey shows the Mongolian resident actively supports the project
construction, and expects more development opportunities from the project construction.
10.1.2.2 Analysis on Impact of Project Construction on Local Residents
The project construction will have varying impacts on various aspects of local
residents including production, living and social economy. Such impacts are divided into
positive impact and negative impact.
Positive impacts mainly include:
(1) The construction and operation of the project will improve the level of infrastructure
in the project area, boost up the sewage disposal capability and industrial water supply
capacity of different banners and counties and provide reliable water resources guarantee for
the development of regional economy.
(2) The implementation of the project can improve the sewage disposal capability of the
enterprises in industrial park, effectively control the sewage discharged into the drainage
channel, and consequently better water quality of various drainage channels indirectly, change
negative impact on residents around the drainage channel and finally boost up the health level
of residents.
(3) The implementation of the project can directly improve water quality of various
drainage channels. Better water quality in drainage channels can alleviate the purifying
pressure of Wuliangsu Lake and improve the ecological environment of Wuliangsu Lake,
retard the swamping process, and gradually restore the biodiversity of wetlands, enable water
quality of drainage system in Hetao irrigation zone to reach relevant national criteria,
effectively change water quality of the Yellow River in Bayannur Municipality, and finally
protect the water system of the Yellow River against pollution damage.
(4) The implementation of the project can enable the industrial parks of five
banners/counties to have reclaimed water supply and sewage treatment and recycling works,
so as to improve infrastructure level and industrial base service capability of various
banners/counties, facilitate the work of attracting foreign investments and better overall
investment environment of Bayannur Municipality.
(5) In construction period of the project, surrounding residents can have the opportunities
for providing labor or trade services, so as to increase their incomes. Moreover, the
improvement of investment environments in project area can attract more enterprises to
develop in Bayannur, which as a result, will provide more jobs for the residents in the project
area.
Negative impacts mainly include:
(1) The construction of the project must unavoidably take over some land for use
permanently or occupy temporarily. A field survey and interview show that local villages
attach great attention to the land requisition and relocation. Therefore, the work of relevant
compensation and resettlement is decisive to the smooth implementation of the project.
(2) The construction of the project may cause noises pollution, dust, traffic accident and
other potential problems to the residents and enterprises around: for example, the pavement of
pipelines may destroy existing infrastructure of the farmers, intercept or occupy some road,
hinder the passage of residents in villages and trigger off noises, dust and public security
problems during the construction. Moreover, temporary land occupation in the construction
period may impact the cultivation of farmland. These issues require some proper construction
arrangement by project employer and construction unit in order to minimize the impact upon
residents.
10.1.3 Determination of project affected area
10.1.3.1 Measures to reduce resettlement tasks
1) During Project planning and design phase
Land expropriation, removal and resettlement required for the construction of works
will inevitably affect the original production and living conditions of the local residents.
During the planning and design phase of the Project, when conducting the scheme
optimization and comparison, considerations shall be taken to the influence of the
construction of the Project on the local society and economy, and such consideration shall be
the key factors for optimization and comparison of schemes. For the purpose of reduction of
land expropriation and resettlement as for as possible, some effective measures have been
taken by the design institute and the Owner of this Project. As far as scheme selection and
other supporting facilities concerned, efforts shall be made to keep away from the residential
area, to occupy less farm land and to satisfy the local planning and the opinions of local
governments.
(1) The routing and location of pipelines shall follow the existing roads and planned
roads. Efforts shall be made to keep the pipelines away from the concentrated residential areas
and to reduce the removal tasks.
(2) Attention shall be paid to environmental protection, the land occupation layout,
distribution of rivers, landform, geological conditions, prevailing wind direction and other
factors of the industrial area shall be considered comprehensively and certain protection space
between the industrial area and the residential area shall be set.
(3) The construction design shall be optimized and construction period shall be
shortened as far as possible. The construction phases shall be arranged reasonably to reduce
the impact of construction of works. For example, in general, land expropriation shall be
conducted after the crops are harvested.
2) During construction phase
(1) Strengthen the public participation mechanism
Prior to construction of the works, the commencing date and construction schedule shall be
publicized by means of notice in the project affected area. The compensation policies relating
to land expropriation and resettlement shall be publicized as well to facilitate the supervision
by immigrants; During the construction stage, the local materials shall be prior choice. If
technology is allowed, local transportation service and labor force shall have priority so as to
have the personnel affected by the works benefited from the construction of works.
(2) Select reasonable construction time and methods
The construction time shall be combined with the farming time of local farmers and shall be
within the slack farming seasons so as to avoid the impact on local farming and production. If
any pipe network shall cross any drain ditch, irrigation channel and other Irrigation and water
conservancy facilities or houses of local residents, pipe jacking technique will be applied to
avoid the reconstruction of water conservancy facilities and houses.
(3) Strengthen construction management
The construction organization shall, during the construction, according to the soil treatment
plans, carry away the soil and ensure no overloading happens during the transportation, no
soil falls from the vehicle. The vehicle shall be cleaned of the mud on the wheel before
running out of the construction site to prevent the falling of soil from the vehicle. During the
construction, the excavation of channels, the trumpet of the vehicle, the sound of engine, the
sound of concrete mixer and the sound of road roller will cause noise. For the purpose to
soften impact of such noise on nearby residents, the construction in the area 200 away from
the residential houses is prohibited during o’clock 11 in the evening and o’clock 6 in the next
morning. Meanwhile, priority shall be given to low-noise construction equipment and
methods. If construction at night is required and will affect the sound environment near the
residential area, then noise reduction measures shall be taken on the construction machines,
meanwhile, temporary equipment such as sound barrier may be established near the
construction site or the concentrated residential area so as to guarantee the quality of sound
environment in the residential area.
⑷ Civilized construction and environmental protection are encouraged.
Construction organization shall make efforts to reduce the impact of construction on nearby
residents, plants, and school, etc. Civilized construction is encouraged. Liaison meeting
between construction organization, street administration authority, and owners shall be
organized to conduction in timely manner consultation on the issues such the impact of
construction on environment; The Owner of this Project and the construction organization
shall contact the local environmental protection authority, and shall clear off the domestic
wastes on the construction site. The construction organization shall strengthen the instruction
for construction personnel about avoidance of littering so as to guarantee the quality of of the
living and working environment of workers.
3) Land expropriation, removal and resettlement plans and implementation phase
(1) The fundamental data shall be collected adequately for the analysis and study of local
social and economic conditions. Feasible resettlement plans shall be formulated by
combination with the local conditions to reduce the impact on the construction of works and
to ensure that the living level of personnel affected by the Project will not be lowered by the
construction of this Project.
(2) Internal supervision and outsider independent supervision shall be strengthened,
smooth and efficient information feedback channels shall be established and the time of
information treatment shall be shortened so as to ensure that any problem during the
construction of this Project will be solved in time manner.
4) After completion of Project
For the purpose to reduce the unfavorable impact of this Project on the production and life of
local residents during the construction of this Project and after completion of this Project,
following measures will be taken after completion of this Project:
(1) After completion of this Project, all wastes and abandoned materials, equipment and
machines on the construction site shall be cleaned properly. The areas excavated during the
construction shall be leveled timely.
(2) During operation of this Project, the main pollutants mainly include noise and odor.
Therefore, the wastes generated during the operation of sewage treatment shall be cleaned off
or buried timely, the rubbish fallen on the entrance access and road shall be cleaned out so as
to prevent such rubbish being raised by the wind. Meanwhile, proper trees, grasses and other
greening measures shall be taken; management and maintenance shall be strengthened.
Currently existing trees and tree belt shall be kept as far as possible to beautify the
environment, purify the air and reduce the noise.
10.1.3.2 Permanent expropriated land
Land expropriated permanently for the Project includes the land for following works: the
sewage treatment work in Urad Back Banner Industrial Party (Huhe Town), regenerated water
supply work in Urad Back Banner, sewage treatment and recycling work in Ganqimaodu Port
Industrial Park (Delingshan Town), regenerated water supply work in Ganqimaodu Port
Industrial Park, Sanpaigan regenerated water supply project, Qipaigan regenerated water
work, sewage treatment and recycling work in Urad Front Banner Industrial Park (Xianfeng
Town).The area within the expropriated land is the area affected by the land expropriation and
removal of this Project. The area affected by land expropriation and removal of this Project is
determined on the site according to the design results in the Feasibility Study Report prepared
by China Municipal Engineering Design & Research Institute (Southwest). According to the
on-site investigation and the inquiry with local land administrative bureau, the land
permanently expropriated by this Project mainly belongs to uncultivated land (uneven land)
and farm land. No basic farmland is expropriated.
10.1.3.3 Temporary land expropriation for construction
Temporary land expropriation includes the land necessary for construction of main works
and the land occupied by pollutant interception pipeline, and water supply pipeline.
According to the on-site investigation and the inquiry with local land administrative bureau,
the land permanently expropriated by this Project mainly belongs to uncultivated land
(uneven land) and farm land. No basic farmland is expropriated.
10.1.4 Impact indicator of Project
Totally four towns (streets), four villages and one state owned farm and one state owned
pasture in five banners (counties) of Bayan Nur City are affected by this Project. Five
households, totally 22 residents, are affected by the land expropriation, no resettlement is
required. No house will be removed. Totally 3597.25 mu of land of various types are taken
over for use temporarily or expropriated, where land expropriated covers 758.00mu, land
taken over for use temporary covers 2839.25mu, and 150 fruit trees are also expropriated.
Impact indicator of land expropriation is shown in Table 3.3-1.
10.1.4.1 Land expropriation
Totally 758mu of land of various types will be expropriated permanently by this
Project, including 195.50 mu of farmland, 165.00mu of construction land, and 397.50 mu of
uncultivated land (wild grass land). According to the on-site investigation, 90.00mu of
uncultivated land in Hongqi Village, Qingshan Town will be expropriated for the water supply
project in Urad Back Banner Industrial Park, 105.00mu of uncultivated land in Hongqi
Village, Qingshan Town will be expropriated for the sewage treatment and recycling project
in Urad Back Banner Industrial Park, 157.50mu of farmland in Muyanghai Pasture will be
expropriated for the water supply project in Ganqimaodu Port Industrial Park, 165.00 mu of
construction land will be expropriated for the water supply project in Ganqimaodu Port
Industrial Park, 38.00 mu of farm land in Shawan Village, Shanba Town will be expropriated
for Sanpaigan regenerated water supply project, 37.50 mu of uncultivated land (wild grass
land) in Jiucheng Village, Longxingchang Town will be expropriated for Qipaigan
regenerated water supply project, and 165.00 mu of uncultivated land (wild grass land) in
Zhongtan Farm will be expropriated for the sewage treatment and recycling project in Urad
Front Banner Industrial Park. 10.1.4.2 Land acquisition
Land acquisition refers to the land taken over temporarily during construction of works,
such as the temporarily occupied land for pipeline. During the construction of this Project,
totally 2839.25 mu of land will be acquired temporarily, including 201.50 mu of farmland and
2637.75 mu of uncultivated land (wild grass land). The average acquisition period is 2
months. Temporary land acquisition for each work is shown in Table 10.1-3. The investigation
results on temporary land acquisition of this Project are detailed in Table 10.1-4.
Table 10.1-3 Details of land expropriation for each work of Comprehensive Water Environment Treatment
Project in Bayan Nur City
S/N Work Unit Total Farmland Construction land
Uncultivated land Ownership of land
1 Water supply work in Urad Back Banner Industrial Park
mu 90.00 90.00 Hongqi Village, Qingshan Town, Urad
Back Banner2Sewage treatment and
recycling work in Urad Back Banner Industrial Park
mu 105.00 105.00
3Water supply work in
Ganqimaodu Port Industrial Park
mu 157.50 157.50 Muyanghai Pasture, Urad Middle Banner
4
Sewage treatment and recycling work in
Ganqimaodu Port Industrial Park
mu 165.00 165.00 Ganqimaodu Industrial Park
5 Sanpaigan regenerated water supply work mu 38.00 38.00
Shawan Village, Shaba Town, Hangjin
Back Banner
6 Qipaigan regenerated water supply work mu 37.50 37.50
Jiucheng Village, Longxingchang Town,
Wuyuan County
7Sewage treatment and
recycling work in Urad Front Banner Industrial Park
mu 165.00 165.00 Zhongtan Farm
Total mu 758.00 195.50 165.00 397.50
Table 10.1-4 Details of temporary land acquisition for each work of Comprehensive Water Environment
Treatment Project in Bayan Nur City
S/N Work
Temporary land acquisition (mu)
Ownership of landTotal Farmlan
dUncultivate
d land
1 Water supply work in Urad Back Banner Industrial Park 534.75 534.75
Industrial Park and Hongqi Village, Qingshan Town, Urad
Back Banner and Industr
2Sewage treatment work in Urad
Back Banner Processing Park (Huhe Town)
114.15 114.15 Hongqi Village, Qingshan Town, Urad Back Banner
3 Regenerated water supply work in Ganqimaodu Port Processing Park 530.75 23.60 507.15
Muyanghai Pasture, Siyitang Village and Wuzhen Village,
Delingshan Town, Urad Middle Banner
4Sewage treatment and recycling
work in Ganqimaodu Port Processing Park (Delingshan Town)
761.70 0.60 761.10Wuzhen Village, Delingshan
Town, Urad Middle Banner and Ganqimaodu Processing Park
5 Sanpaigan regenerated water supply work 241.65 99.15 142.50
Shawan Village and Dashuncheng village, Shanba Town, Hangjin Back Banner
6 Qipaigan regenerated water supply work 581.70 130.20 451.50
Jiucheng Village, Longxingchang Town, Wuyuan
County
7Sewage treatment and recycling
work in Urad Front Banner Processing Park
74.55 0.00 74.55 Zhongtan Farm and Urad Front Banner Industrial Park
Total 2839.25 253.55 2585.70
10.1.4.2 Population affected by Project
The population affected by project in this report refers to the rural residents whose farmland is
expropriated by this Project. Since there is no house will be removed for this Project, there is
no population affected by house removal. According to the investigation and analysis
household by household, totally 5 households and 22 persons will be migrated for this Project.
They are all residents living in Shawan Village, Shaba Town, Hangjin Back Banner. The
statistics of population affected by Comprehensive Water Environment Treatment Project in
Bayan Nur City is shown in Table 10.1-5.
Table 10.1-5 Statistics of population affected by Comprehensive Water Environment Treatment Project in
Bayan Nur City
Banner/CountyTownship/
TownVillage
Head of househodl
Land expropriation without house removal Remark
sNumber of household Population
Hangjin Back Banner
ShanbaTownShawa
n Village
Shan Baolin 1 4
Hangjin Back Banner
ShanbaTownShawa
n Village
Wang Fugui 1 4
Hangjin Back Banner
ShanbaTownShawa
n Village
Chen Shuijin 1 4
Hangjin Back Banner
ShanbaTownShawa
n Village
Wang Erhu 1 5
Hangjin Back Banner
ShanbaTownShawa
n Village
Hao Zhen 1 5
Total ShanbaTownShawa
n Village
5 22
10.1.4.3 Trees or forest
Trees and forest affected by this Project include those trees cut for the land expropriation
for construction and construction of works. Totally 150 trees will be cut, including 120 mature
trees and 30 baby trees.
Table 10.1-6 List of Indicators of things affected by land expropriation for construction of Comprehensive Water Environment Treatment Project in Bayan Nur City
S/N
Description
Unit
Total
Urad Back Banner Urad Middle BannerHangjin Back
BannerWuyuan County Urad Front Banner
Total
Qingshan Tow
n
Urad B
ack Banner
Industrial Park
Total
Delingshan Tow
n
Muyanghai Pasture
Ganqim
aodu Industrial Park
Total
ShanbaTown
Total
Longxingchang Tow
n
Total
Zhongtan Farm
Urad B
ack Banner
Industrial Park
1 Land expropriation 1.1 Farmland mu 195.50 157.50 157.50 38.00 38.00 1.2 Construction land mu 165.00 165.00 165.00 1.3 Uncultivated land mu 397.50 195.00 195.00 37.50 37.50 165.00 165.00 2 Land acquisition 1.1 Farmland mu 201.50 24.20 0.60 23.60 47.10 47.10 130.20 130.20 1.2 Uncultivated land mu 2637.75 648.90 648.90 453.15 1268.25 422.63 84.53 761.10 194.55 194.55 451.50 451.50 74.55 26.55 48.00
3 Trees or forest 1.1 Timber tree Unit 150 110 110 40 40 1.1.1 Mature tree Unit 120 90 90 30 30 1.1.2 Baby tree Unit 30 20 20 10 10
10.1.4.4 Vulnerable groups
Investigation has been made village by village during the process of investigation of
impact of this Project to analyze the ethnical issue, age structure, education, employment and
other information of the members of all households affected by the land expropriation and
house removal. Comparison and analysis on the member of households and the data known
from local civil affairs authority and property relief office have been made to determine the
vulnerable groups affected by this Project. No vulnerable groups who need special supports is
found in the area affected by land expropriation for construction during this phase. No special
support is needed. However during the resettlement, if the vulnerable groups are concerned,
corresponding support and care will be afforded by the Owner of this Project and relevant
governmental authority.
10.1.5 Analysis on impact by land expropriation 10.1.5.1 Analysis on impact by permanent land expropriation
To analyze the impact on local residents by expropriation of farmland, the Owner of this
Project has organized relevant personnel to conduct deep investigation on the towns,
townships, villages and the existing land resources of the farms and pastures may be affected
by this Project, has conducted painstaking analysis on the degree of impact on each indicator
of things affected by this Project. Totally four towns (streets), four villages and one state
owned farm and one state owned pasture in five banners (counties) of Bayan Nur City are
affected by the permanent land expropriation for this Project. Five households are affected by
the permanent land expropriation in Muyanghai Farm in Urad Middle Banner and Shawan
Village in Shanba Town of Hangjin Back Banner. For other villages, only uncultivated land is
expropriated. Farmland affected is shown in Table 10.1-7.
Table 10.1-7 Analysis of farmland affected by land expropriation for Comprehensive Water Environment
Treatment Project in Bayan Nur City (mu)
Banner/
County
Township/
Town
Village
Sub-village
Population
Number of farmland before
expropriation
Num
ber of land
expropriated
Average
farmland of
each resident after
expropriation
Impact %
Total
Per person
Urad Middle Banner
Muyanghai Pasture 1442 36000 24.97 157.5 24.86 0.44%
Hangjin Back Banner
ShanbaTown Shawan Village
Culturing plant 46 340 7.39 38 6.57 11.18%
1) Impact of land expropriation on Urad Back Banner
Totally 195.00 mu of uncultivated land (wild grass land) in Hongqi Village, Qingshan Town
will be expropriated for the water supply work and sewage treatment and recycling work in
Urad Back Banner Industrial Park. No farmland will be expropriated. According to the on-site
investigation, the main income sources of local residents are stock raising and agriculture. At
present, all villagers have certain number of farmland. Stocks are raised in the pasture. No
impact on the agricultural production will be caused by the expropriation of uncultivated land.
2) Impact of land expropriation on Urad Middle Banner
Totally 157.50 mu of farmland in Muyanghai Farm will be expropriated for the construction
of water supply work and sewage treatment and recycling work in Ganqimaodu Industrial
Park. According to the onsite investigation in the planned migrant group, the land in
Muyanghai Pasture belongs to state-owned land and land affected is small, therefore the
degree of impact is low. The land affected only covers 0.44% of total farmland. Meanwhile,
the users of the land expropriated will be afforded new land, therefore no impact will be
caused by the land expropriation on the normal agricultural production in the Pasture.
3) Impact of land expropriation on Hangjin Back Banner
Totally 38.00 mu of farmland in the Culturing Plant in Shawan Village, Shanba Town,
Hangjin Back Banner will be expropriated for the construction of Sanpaigan regenerated
water work. According the on-site investigation, the average farmland of the residents in the
Yangzhi Sub-vilage in Shawan Village is 7.39 mu, and 6.57 mu after land expropriation. The
farmland affected by the land expropriation covers 11.18% of total farmland. Comparing with
other villages affected, the degree of impact is high. Totally 5 households (Shan Baolin, Wang
Fugui, Chen JIinyong, Wang Erhu, and Hao Zhen) and 22 persons of Yangzhi Sub-village of
Shawan Village are affected by the land expropriation. The planning team has conducted
detailed investigation concerning these 5 households affected. According to the analysis, the
degree of impact on all farmlands of these households reaches more than 20%. The degree of
impact is high. Households affected by land expropriation are shown in Table 10.1-8.
Table 10.1-8 Brief introduction to production and living of households in Shawan Village affected by land
expropriation
Description UnitShan
BaolinWang Fugui
Chen Jinyong
Wang Erhu
Hao Zhen
Number of householdPerso
n4 4 4 5 5
Total area of contracted farmland mu 20 15 20 20 15
Average area of farmland per person
mu 5 3.75 5 4 3
Area of farmland expropriated mu 5 4 5 8 8
Percentage of decrease of farmland % 25.00 26.67 25.00 40.00 53.33
4) Impact of land expropriation on Wuyuan County
Totally 37.50 mu of uncultivated land in the first sub-village of Jiucheng Village,
Longxingchang Town, Wuyuan County will be expropriated for the construction of Qipaigan
regenerated water work. According to the on-site investigation, Longxingchang Town is the
original location of Wuyuan County government. The residents of Jiucheng Village are
involved not only in agricultural production, but also secondary industry and tertiary industry.
Only small number of uncultivated land in the first sub-village is affected by the land
expropriation, therefore, on impact will be caused on the production and living of local
farmers.
5) Impact of land expropriation on Urad Front Banner
Totally 165.00 mu of uncultivated land in Zhongtan Farm in Urad Front Banner will be
expropriated for the construction of sewage treatment and recycling work in Urad Front
Banner Industrial Park. According to the on-site investigation, the land affected by land
expropriation belongs to state-owned land, and belongs to uncultivated land, neither the
production and operation of the farm, nor the living and production of farmers in nearby
villages will be affected by the land expropriation.
10.1.5.2 Analysis on impact of temporary land occupation
Totally 2839.55 mu of land will be temporarily occupied by the pipeline and the
construction of this Project, including 253.55 mu of farmland, 2585.70 mu of uncultivated
land. According to the data provided by the owners of each work and the on-site investigation,
the construction of pipeline will be completed in 30-60 days. Except the pipeline crossing
Sanpaigan, Qipaigan and Yihe Channel, no other pipeline will cause impact on roads or
channels. Meanwhile, all pipelines are set away from the residential area to some extent.
For the purpose to avoid and mitigate the impact on the channels and production of local
residents by the construction of pipelines the Owner of this Project will compensate properly
the residents whose production is affected by land expropriation against the crops, meanwhile,
the construction will be arranged at spare time of local residents. For the pipelines crossing
drain channels, irrigation channels and other water conservancy facilities or houses of local
residents, pipe jacking will be applied to avoid the repeated construction of water conservancy
facilities and houses. In addition, the Owner of this Project will help farmers carry out land
leveling or land improvement by taking advantage of the transportation of earthwork.
Meanwhile, for the purpose to reduce the impact of excavation of road and deposit of
earthwork on the nearby environment and local residents, the construction organization will
establish retaining wall around the construction site to prevent the dust flying with the wind.
Owner of this Project will define the modes of temporary use of land and recovery
requirements, etc, during execution of construction contract with the Contractor.
In addition, according to the on-site investigation by East China Institute, the
construction of these works is supported by local residents. After they are informed of the
impact on their living and production and are compensated in accordance with the law, almost
all residents accepting the investigation show that they will conquer the impact by the
construction and support the construction of this Project.
10.2 Migration and resettlement plans
The preparation of the migration and resettlement plans concerning this Project and the
future implementation will follow relevant laws and regulations of Inner Mongolia and the
requirements of OP4.12 Business Policy of World Bank. The implementation of land
expropriation, removal and resettlement tasks will strictly follow the resettlement
compensation standard and relevant policies. If change happens during implementation, the
Owner of this Project will prepare corresponding special reports to the World Bank. Such
report may into operation only approved by World Bank.
10.2.1 Policy basis
The resettlement plans of this Project are based on the policies mainly listed in Table
10.2-1.
Table 10.2-1 Main policy basis for migration and resettlement plans
Name of policy Remarks
National level
(1) Land Administrative Law of the People’s Republic of China 2004.8.28.(2) Interim Rules on Tax of Occupation of Arable Land 2007.12.1(3) Notice on Printing of “Interim Administrative Measures for Collection and Use of Plant Recovery Fees”
Cai Zone [2007] No. 73
(4) Decisions of State Council on Deepening Reform and Strengthening Land Administration
2004.10.21
(5) Implementation Rules of Land Administrative Law of the People’s Republic of China
1998.12.27
(6) Rural Land Contracting Measures of the People’s Republic of China 2002.8.29(7) Administrative Rule of Urban House Removal 2001.6.6(8) Property Law of the People’s Republic of China 2007.3.19Notice on Printing of “Guiding Advice on Optimization of Compensation and Resettlement Policies Concerning Land Expropriation”
Guo TU Zi Fa [2004] No. 238
Autonom
ous
region level
(9) Measures of Inner Mongolia Autonomous Region on “Land Administrative Law of the People’s Republic of China”
2000.10.15
(10) Implementation Measures of Inner Mongolia Autonomous Region on Tax of Arable Land Occupation(10) Regulations of Inner Mongolia Autonomous Region on Standard, Management and Use of Charges of Forestry Land Occupation and Acquisition
World
Bank
(12) Operational Polices for Involuntary Resettlement OP4.12 and its attachments(13) Involuntary Displacement and Resettlement BP4.12 and its attachments
10.2.2 Resettlement policies applicable to this Project
According to above mentioned national and local laws, regulations and relevant policies
of World Bank, combined with the actual conditions of the area affected by the
Comprehensive Project, and based on the adequate consultation with the people affected, the
Resettlement Office of this Project has formulated following resettlement plans applicable to
this Project.
10.2.2.1 Compensation for various kinds of land affected
(1) The local governments of the area affected by this Project is preparing the uniform
standard of annual production value of this region, however, such standard has not yet
approved by Inner Mongolia Autonomous Region, therefore, the production value per mu of
farm land applied for calculation of land compensation will be determined based on relevant
statistic data and combined with the on-site investigation. The magnification of compensation
for farm land expropriated is 10 times and that of subsidy for resettlement is 6 times.
(2) If there are crops in the land expropriated, the compensation for crops will be 1 time
of the annual production value of this tract of land; no compensation will be given for
uncultivated land such barren mountain, wild land, and barren sand
(3) Compensation for fruit trees will be determined according the type, age, and size o
trees. Since only timber trees are affected by the land expropriation, referring to the nearby
project completed recently, the compensation standard for mature trees is 100Yuan/tree and
50Yuan/tree for baby trees.
(4) Compensation for temporary land occupation (wasted soil yard, access and
construction camp, etc) will be calculated according to the annual production value and the
actual occupation time. One-year term will be applied if the time is less than 1 year. The
construction organization shall be responsible for recovery of temporary occupied land.
10.2.2.2 Resettlement of rural residents affected
(1) If the village or sub-village committee has adjusted the land or explored the land to
have the household whose land is expropriated obtain new land or other production materials,
then the land compensation and resettlement subsidy shall be managed and utilized by the
village committee. If the village or sub-village committee has not adjusted the land or
explored the land and the households affected do not obtain any production materials, then the
village committee shall pay the resettlement subsidy to the households whose land is
expropriated, the land compensation will be managed and utilized by village committee, and
will be distributed and utilized according to the decision of general meeting of villagers.
(2) During construction, new employment opportunity will be given, and priority will be
given to the people affected by this Project. These employment opportunities will benefit the
local residents.
10.2.2.3 Public consultation and information disclosure
(1) Public consultation meeting
Irregular official consultation meeting will be held by the Resettlement Office.
Resettlement Office will organize such meeting irregularly according to the actual conditions
of land expropriation and resettlement. The theme, scale, participants of the meeting will be
determined as the change of demands, and will be supervised by independent outsider
supervising institute.
(2) The use plans of land funds will be made via public consultation, and may be put into
implementation upon approval by the general meeting of villagers.
(3) Resettlement information system based on computer will be applied to strengthen the
management of resettlement and ensure the consistence between the implementation of
resettlement and the policy concerning resettlement. Resettlement information will be
publicized from time to time to set up a bridge between the Resettlement Office and the
people affected. Feedback of immigrants will be collected and any possible bias will be
remedied in timely manner.
10.2.3 Compensation standard
10.2.3.1 Compensation standard for land acquisition and expropriation
1) Annual production value of farmland
The local governments of the area affected by this Project is preparing the uniform
standard of annual production value of this region, however, such standard has not yet
approved by Inner Mongolia Autonomous Region, therefore, the production value per mu of
farm land applied for calculation of land compensation will be determined based on relevant
statistic data and combined with the on-site investigation. The production amount per mu of
farmland will be calculated as per the average production amount per mu in recent three years
from 2006 to 2008. According to the on-site investigation and combined with the similar
project completed recently, the price of farm products will be calculated as per the price of
second quarter of 2009. After calculation, the average annual production value of farm land in
Urad Front Banner, Urad Middle Banner, Urad Back Banner, Hangjin Back Banner and
Wuyuan County in recent three years is 1129 Yuan/mu, 765Yuan/mu, 810Yuan/mu,
1331Yuan/mu and 1384 Yuan/mu respectively.
2) Compensation standard for rural collectively-owned land
According to the relevant provisions on land compensation provided in “Implementation
Measures of the Land Administrative Law of the People’ Republic of China”, the
compensation for land will be 6-10 times of the average annual production value of recent
three years and the resettlement subsidy for each rural resident will be 4-10 times of average
annual production value of farmland of recent years. According to the investigation by the
Owner and related designer of this Project, the magnification of compensation for farm land
expropriated is 10 times and that of subsidy for resettlement is 6 times. The sum of these two
items is 16 times of production value per mu of farm land.
Therefore, the compensation standard for collectively-owned farmland expropriated in
Hangjin Back Banner is 1331oYuan/mu, resettlement subsidy is 7986Yuan/mu, the total of the
two items is 21296Yuan/mu.
The compensation standard for uncultivated land expropriated will refer to the similar
project completed recently in each banner on temporary basis and the compensation for crops
in the farmland expropriated will be calculated as per the production value of crops in the first
quarter. According to the on-site investigation, the banners and counties involved in the rural
collectively-owned land expropriated by this Project are Urad Back Banner, Hangjin Back
Banner and Wuyuan County respectively. The compensation standard for expropriation of
rural collectively-owned land in each banner (county) is shown in Table 10.2-2.
Table 10.2-2 List of compensation standard for expropriation of rural collectively-owned land by
Comprehensive Treatment Project in Bayan Nur
Area Type of land Unit
Land expropriation compensation
RemarksTotal
Compensation standard
Compensation for crops
Urad Back Banner
Uncultivated land
Yuan/mu
2000 2000 /
Hangjin Back Banner
FarmlandYuan/mu
22627 21296 1331
Wuyuan County
Uncultivated land
Yuan/mu
9000 9000 /
3) Compensation standard for state-owned land
The compensation standard for construction land in Ganqimaodu Port in Urad Middle
Banner will be determined according to the consultation between the Owner and the industrial
park involved in the construction of this Project. According to the data provided by Owner
and the on-site investigation, the compensation standard is 9167Yuan/mu.
According to the introduction made by local land administration authority, Owner shall pay
land compensation for paid use of farmland or uncultivated land in state-owned land, and
shall pay royalty for use of new construction land; If the land belongs to profit-oriented
mining and industrial enterprises, then Owner shall pay state-owned land grant fees according
to “Minimum Price Standard for Sale of State-owned Industrial-purpose land”, which may be
deducted with the land compensation and royalty for use of new construction land paid in
advance. Therefore, the only thing is to make up the deficiency.
Since the Project belongs to infrastructure construction project, and is a non-profit
project, for the sate-owned land in Zhongtan Farm and Muyanghai Pasture involved in this
Project, only land compensation and royalty for use of new construction land are included
currently. According to site investigation and calculation, since there is on state-owned land
compensation standard in effect in each banner (county) involved in this Project currently, the
compensation standard for state-owned land in Urad Middle Banner and Urad Front Banner
will refer to that for rural collectively-owned land, that is, the compensation standard for the
state-owned farmland in Urad Middle Banner is calculated by 16 times, that is,
12240Yuan/mu, and that for crops takes 765Yuan/mu. Details of compensation standard for
state-owned land expropriation in each banner are shown in Table 10.2-3.
Table 10.2-3 List of compensation standard for expropriation of state-owned land by Comprehensive
Treatment Project in Bayan Nur
Area Type of land Unit
Land expropriation compensation
RemarksTotal Compensation
standard
Compensation for crops
Urad Middle Banner
Farmland Yuan/mu 13005 12240 765 Muyanghai Pasture
Construction land Yuan/mu 9167 9167 / Ganqimaodu Industrial
ParkUrad Front Banner
Uncultivated land Yuan/mu 2000 2000 / Zhongtan Farm
4) Compensation standard for temporary land occupation
The temporary land acquisition involved in this Project concerns two types land,
farmland and uncultivated land. According to the opinions of Owner and the villages and sub-
villages affected, compensation shall be made for temporary occupation of various types of
land. The construction organization shall recover the land after completion of this Project.
Since the comparatively short construction period, the compensation of acquisition of
farmland mainly involves two items, compensation for crops and costs for land recovering
works. The compensation for crops is calculated as per the production value per year and
costs for land recovering works is calculated as per 25—Yuan/mu. Compensation for
uncultivated land is calculated as per 300Yuan/mu. Compensation standard for temporary
occupation of land in each banner and county is shown in Table 10.2-4.
Table 10.2-4 List of compensation standard for temporary acquisition of land by Comprehensive
Treatment Project in Bayan Nur
Area Type of land Unit Land expropriation compensation Remark
sTotal Costs for land recovery works
Compensation for crops
Urad Front Banner
Farmland Yuan/mu
3629 2500 1129 Uncultivated land
Yuan/mu
800 800 / Urad Middle
Banner
Farmland Yuan/mu 3265 2500 765
Uncultivated land
Yuan/mu 800 800 /
Urad Back Banner
Farmland Yuan/mu 3310 2500 810
Uncultivated land
Yuan/mu 800 800 /
Hangjin Back Banner
Farmland Yuan/mu 3831 2500 1331
Uncultivated land
Yuan/mu 800 800 /
Wuyuan County
Farmland Yuan/mu 3884 2500 1384
Uncultivated land
Yuan/mu 800 800 /
10.2.3.2 Compensation for trees
Compensation for fruit trees will be determined according to the type, age, and size o
trees. Since only timber trees are affected by the land expropriation, referring to the nearby
project completed recently, the compensation standard for mature trees is 100 Yuan/tree, and
50 Yuan/tree for baby trees.
The above compensation standard is made according to the relevant national and local
polices and regulations, combined with the requirements of World Bank, and has been
recognized by the local residents and relevant organization.
10.2.4 Resettlement and compensation plans
Under the coordination and support by Bayan Nur Municipal government, the Bayan
Nur Hetao Water Co., Ltd, each level of government involved in this Project, and East China
Survey and Design Institute have conducted the planning of resettlement works of the
Comprehensive Treatment Project according to current policies, laws, and regulations in
effect and the requirements of World Bank on Resettlement based upon the planning and
schemes of resettlement delivered by each town, township and village affected by this Project.
10.2.4.1 Objective and tasks of planning
1) Objective
According to the characters of impact caused by this Project, the objective of
resettlement planning is to: mitigate the impact on the living and production conditions of
migrants, and make the production and living level of them not lower than the original level
or be improved to some extent.
2) Tasks
According to the investigation and statistics, the no household will be involved in house
removal of this Project. For the uncultivated rural collectively-owned land of villages and
sub-villages and the state-owned farm expropriated for this Project, cash compensation and
resettlement subsidy will be offered according to relevant policies and the opinions of relevant
villages and sub-villages. For the five households, totally 22 persons, affected by the
expropriation of farmland in Shawan Village, Shaba Town, Hangjin Back Banner, cash
compensation combined with land adjustment within the villages and sub-villages will be
applied.
10.2.4.2 Production and resettlement recovery planning
Based upon the full consultation with each village, organization, representative of
villagers and immigrants affected, to respect the choice of majority of immigrants, cash
compensation will be applied.
According to the on-site investigation, except a small number of villagers, almost all of
the villagers investigated prefer to the cash compensation for settlement. The final
resettlement plans are determined according to the opinions of majority of immigrants. If any
immigrant chooses to continue to live on farming, the Owner of each work in each banner
(county) will allocate flexibly the collectively-owned land for them or help them obtain the
land from those households who are unwilling to live on farming.
According to the resettlement means by cash compensation, the compensation for land
will be paid via payment channel directly to each relevant village, organization and individual
affected for their free disposal The resettlement plans for each village are detailed respectively
as follows:
① Hongqi Village, Qingshan Town, Urad Back Banner
Totally 195.00 mu of uncultivated land in Muye Sub-village in Hongqi Village is
expropriated for the water supply and sewage treatment and recycling works in Urad Back
Banner Industrial Park. No house will be removed. According to the on-site investigation
conducted by resettlement planning team, the land affected by the expropriation for
construction belongs to uncultivated land collectively owned by Muye Sub-village in Hongqi
Village, and the farming and production of local residents are not affected. After soliciting the
opinions of relevant sub-village and representatives of villagers, the villagers committee
decides, after mutual discussion, that cash compensation will be applied, the land
compensation will be transferred directly to the sub-villages, which will be used for the
construction of roads, water conservancy, farmland restructuring in the sub-village.
② Jiucheng Village, Longxingchang Town, Wuyuan County
Totally 37.5 mu of uncultivated land in Jiucheng Village, Longxignchang Town will be
expropriated for the Qipaigan regenerated water supply work. No house will be removed.
According to the on-site investigation conducted by resettlement planning team, the land
affected by the expropriation for construction belongs to uncultivated land collectively owned
by Jiucheng Village, and the farming and production of local residents are not affected. After
soliciting the opinions of relevant sub-village and representatives of villagers, the villagers
committee decides, after mutual discussion, that cash compensation will be applied, the land
compensation will be transferred directly to the sub-villages. Land compensation will be used
for the construction of roads, water conservancy, farmland restructuring in the sub-village.
③ Shawan Village, Shaba Town, Hangjin Back Banner
Totally 38.00 mu of farm land in Yangzhi Sub-village in Shawan Village, Shanba Town
will be expropriated for the Sanpaigan regenerated water supply work. No house will be
removed. Total five households (Shan Baolin, Wange Fugui, Chen Jinyong, Wang Erhu and
Hao Zhen) or 22 residents of Yangzhi Sub-village of Shawan Village will be affected by the
land expropriation. On-site investigation and analysis of these five households have been
made by the Owner of Project and resettlement planning team. The details of living and
producing conditions of each household affected are shown in Table 10.2-5.
Table 10.2-5 Details of production and living conditions of households in Shawan Village affected by
land expropriation
Description Unit Shan Baolin Wang Fugui Chen Jinyong Wang Erhu Hao Zhen
I. Basic information 1. Members of household Perso
n 4 4 4 5 5
Where: female Person 2 2 2 2 2
2. Total area of contracted farmland mu 20 15 20 20 15
3. Average area of farmland per person mu 5 3.75 5 4 3
II. Total income of household Yuan 49150 43050 50820 48800 52150
1. Income from agriculture/ratio Yuan/%
17150
34.89
13050
30.31
17420
34.28
15800
32.38
13950
26.75
2. Income from stock raising/ratio
Yuan/% 8000 16.2
8 1000
023.2
3 7000 13.77
13000
26.64 7000 13.4
2
3. Income from service/ratio Yuan/%
24000
48.83
20000
46.46
26400
51.95
20000
40.98
31200
59.83
III. Total expenditure of household Yuan 33440 34455 32961 40460 38464
1. Expenditure for agriculture Yuan 8000 6000 8000 8000 6000
2. Expenditure for stock raising Yuan 3940 2955 2561 4560 2364
3. Expenditure for staple and non-staple food Yuan 12700 12900 12600 16200 16400
4. Expenditure for clothing Yuan 2800 3100 3200 3800 4100
5. Expenditure for medical treatment and healthcare Yuan 1000 1000 1200 1400 1100
6. Expenditure for transportation and communicaton Yuan 2000 2000 2400 2500 3000
7. Expenditure for education Yuan 0 2500 0 0 1500
8. Other expenditures Yuan 3000 4000 3000 4000 4000
IV. Saving of household at end of year Yuan 15710 8595 17859 8340 13686
V. Per capital net income per year Yuan 9302.5 8523.75 10064.75 7248 8757.2
VI. Impact of land expropriation 1. Area of farmland expropriated mu 5 4 5 8 8
2. Reduction of income from agriculture Yuan 4287.5 3480.0 4355.0 6320.0 7440.0
3. Degree of impact on general income % 8.72 8.08 8.57 12.95 14.27
From Table 10.2-5, the impact on the living and production and the general income of
households affected by land expropriated is not so significant. For the purpose of preparing
reasonable and practicable production and resettlement recovery plans, the planning team has
conducted informal discussion with the villagers during on-site discussion, to fully understand
the demands of immigrants. It is found in the discussion that among the five households
affected, only those at the age of 50-60 are involved in traditional agricultural production,
meanwhile, it takes only three km from Shawan Village to Shaba Town, the location of
government of Hangjin Back Banner, large number of young labor force from the village
works in Shaba Town and stay in city as worker in most of time of a year and return to village
to do farm work in busy season, therefore, the degree dependence of this young labor force on
land is low. During the discussion, certain number of immigrants expresses their aspiration to
do business or investment, and is troubled for lack of money, therefore, for the land
compensation means; all five households choose the cash compensation. They want to
expand their accumulation of capital from the land compensation, which will afford them
opportunity to do business in secondary and tertiary industry in the future. For the impact on
their income for the loss of land, they will spend some of the land compensation to open up
new farmland in the village to increase the income. Therefore, after soliciting the opinions of
relevant sub-villages and immigrants, the villagers committee decides, after mutual
discussion, that cash compensation will be applied; the land compensation will be transferred
directly to the villagers. In addition, Shawan Villager Committee commits that if resettled
households request to obtain new land, Villager Committee will help the regional adjustment
of farmland in the sub-village.
④ Zhongtan Farm and Muyanghai Pasture
Totally 165.00 mu and 157.50 mu of state-owned land in Zhongtan Farm and Muyanghai
Pasture will be expropriated for the sewage treatment and recycling work in Urad Front
Banner Industrial Park and sewage treatment and recycling work in Ganqimaodu Pork
Industrial Park respectively. No house will be removed. According to the relevant regulations
of Bayan Nur, land compensation will be paid directly to Zhongtan Farm and Muyanghai
Pasture.
4) Temporary occupied land recovery plan
Temporary occupied land for construction refers to the land lent in temporary manner
within construction period. For this Project, it refers to the land occupied for construction of
pipelines and no house will be removed. After completion of this Project, the Owner of this
Project shall recover such land according to relevant requirement at the expense of land
reclamation fees. The compensation for crops in the land temporarily occupied for the Project
will be paid directly to the owner these crops.
During the design, the design institute of this Project shall try best to lay the pipes along
the existing roads or channels so as to avoid the disturbance on the normal life of residents.
5) Management and application of compensation
According to the Measures of Inner Mongolia Autonomous Region on Implementation
of the Law on Villagers’ Committee of the People’s Republic of China and the
Implementation Regulation on Land Administrative Law, the application scheme of
compensation for land expropriation must be submitted by Villagers’ Committee for
discussion by the Meeting of Representatives of Villagers. For those who will not be resettled
uniformly, their resettlement subsidy will be paid directly to them.
According to above regulations, the application schemes of the land compensation are
determined after fully discussed by Villagers’ Committee based upon the opinions solicited
from the immigrants:
If farming households are affected by land expropriation, the land compensation will be
paid to the immigrants whose farmland is expropriated in full-amount manner. If no
household is directly affected by the land expropriation, the land compensation will be paid
directly to relevant sub-villages and will be used for future construction of infrastructure. The
compensation for attachments to the land or crops will be paid directly to their owners. The
compensation will be paid by the land expropriation organization to relevant owners via a
payment channel.
6) Protection of women’s rights and interests and participation in Project
In the villages affected, women have participated in the economic activities extensively.
They do farm work, and some work part-time for others. The economic activities involved by
women have became the important source of their households, meanwhile, in the daily life,
they undertake more household duties. The land expropriation and house removal will cause
loss to the livelihood of women and increase the economic difficulty facing the women.
Therefore, it is very important to take the gender issues into consideration in the
implementation of resettlement plans. In this Project, the main problems facing the women
are the payment of compensation and recovery of production. The Project Office will,
together with local governments and NGOs, make efforts to promote the gender equality and
increase the income of women.
(1) Create employment opportunity for women. During the construction of this Project,
employment opportunity will be given each year. The service work relating to the
construction fits the local women better; therefore propriety will be given to women for such
posts. Since unemployment is the main cause of the poverty of women, these employment
opportunities will benefit them to large extent.
(2) Safeguard the participation by women. The participation in the discussion by women
must be ensured. The special demands of women must be taken into consideration in all
resettlement plans. All kinds of information shall be disclosed to women. The Project Office
will organize meeting of representatives of women during implementation of this Project to
discuss and solve the problems facing the women during resettlement.
(3) Local governments and resettlement office will ensure that women enjoy same rights
with men with respect to land and property. The divorced or widowed women still have the
right to obtain land and enjoy land compensation. The Resettlement Office will require all of
the co-owners of land or house to sign their names.
(4) Eliminate the gender discrimination and encourage the entrepreneurship of women
The Project Office is established partnership with local governments and NGOs to make
efforts to increase the opportunity and living quality of women. First, Resettlement
department must employ female employees to help women and solve problems facing women
in all aspects of resettlement, To help women participate extensively in the resettlement
planning, management and operation, employment and income recovery and other activities;
Secondly, local governments, resettlement office will cooperate with NGOs to eliminate the
gender discrimination existed in investment environment, and to encourage the women to
participate in the work of official organization to promote the development of private
enterprises run be women and exert fully the potential of women.
7) Organization and management of resettlement.
The implementation of resettlement plans will be under the leadership of leaders' team of
municipal project coordination teams. All banners (counties) affected by the construction of
this Project have designated special personnel to form the Project Office to be responsible for
the preparation of resettlement policies, the relocation of immigrants and the publicity,
mobilization, organization and implementation of resettlement activities. Meanwhile, the
Project Office will be main channel for immigrants to express their concerns. The Project
Office shall hear, collect and classify the opinions and problems of immigrants in timely and
adequately manner, and report such opinions and problems timely to higher department or
competent authorities, meanwhile feed back the treatment results to the immigrants in timely
manner.
10.2.5 Estimate of compensations for land expropriation and house
removal
The total estimate of resettlement compensations for each work of Comprehensive
Treatment Project is 18.0097 million Yuan, where, compensation investment for rural
compensation is 8.3670 million Yuan, covering 44.46%, other expenses are 0.8367 million
Yuan, covering 4.65%, contingent funds are 0.9204 million Yuan, covering 5.11%, other tax
costs are 7.8856 million Yuan, covering 43.79%. Details of total budget estimate of
compensation for resettlement of this Project are shown in Table 10.2-6.
Table 10.2-6 Details of total budget estimate of compensation for resettlement of this Project (ten
thousand Yuan)
S/N Description TotalUrad Back
Banner
Urad Middle Banner
Hangjin Back
Banner
Wuyuan County
Urad Front
BannerPercentage
1 Compensation for rural area 836.70 90.91 466.44 119.94 120.44 38.96 46.46%
1Compensation for land expropriation and acquisition
818.24 90.91 453.40 114.53 120.44 38.96 45.43%
2Compensation for crops and trees
18.46 13.05 5.41 1.02%
2 Other expenses 83.67 9.09 46.64 11.99 12.04 3.90 4.65%
3 Contingent funds 92.04 10.00 51.31 13.19 13.25 4.29 5.11%
4 Other tax costs 788.56 130.00 363.20 106.36 35.00 154.00 43.79%
Total static investment of this Project
1800.97 240.00 927.59 251.49 180.73 201.15 100.00%
10.2.6 Implementation plans of resettlement works
10.2.6.1 Implementation procedure
A. Land expropriation and compensation
Land expropriation and compensation will be completed by relevant department. The
detailed procedure is as follow:
a. Project design institute provides the detailed map of land expropriation scope, which
shall be verified jointly by the Project Office, Owner of Project and each local government,
local land administrative department, and the organization (individual) affected by this
Project, to define the scope and quantity of land expropriation and house removal;
b. Owner of Project applies to relevant local land administrative departments for land
expropriation;
c. Relevant land administrative department replies the application for land
expropriation;
d. The Owner of this Project and local land administrative departments conduct
consultation on the issues with respect to land compensation, enter into land compensation
agreement and transact relevant land acquisition procedures;
e. Banner (county)-level land administrative departments and each township (town),
village affected affirm the scope and quantity of land expropriation;
f. Banner (county)-level land administrative department enters into “Land
Expropriation Agreement” with each township (town) affected;
g. Relevant party pays the compensations;
h. Relevant party transacts legal procedures;
i. Relevant parties implement the land expropriation procedure.
B. Production recovery
Production and relocation recovery will be implemented by relevant Villagers’
Committee. The working procedure is as follow:
a. The sub-village with the task of resettlement organizes the meeting of representatives
of villagers to discuss and make the distribution schemes of land compensations;
b. The Villagers’ Committee discloses the distribution schemes of land compensations
to solicit further the opinions of all villagers and immigrants in its sub-village;
c. The Villagers’ Committee distributes the land compensations.
10.2.6.2 Schedule
The schedule of implementation of land expropriation and re-settlement of this Project
will be made according to the construction schedule of works. Detailed schedules shall follow
following principles:
(1) All land expropriation works shall be completed prior to commencement of works of
each bid section;
(2) The land compensation schemes shall be subject to the full consultation with
villagers;
(3) Efforts shall be made to complete the land expropriation after the crops are
harvested;
(4) The payment of land compensation shall be completed prior to the expropriation of
land;
According the overall schedule of this Project, the schedule of land expropriation and
house removal of this Project is shown in Table 10.2-6.
Table 10.2-6 Schedule of land expropriation for each work of Comprehensive Water Environment Treatment Project in Bayan Nur City
Description
Water supply work in Urad Back
Banner Industrial Park
Sewage treatment and recycling
work in Urad Back Banner Industrial
Park
Water supply work in Ganqimaodu Port
Industrial Park
Sewage treatment and recycling
work in Ganqimaodu Port
Industrial Park
Sanpaigan regenerated water
supply work
Qipaigan regenerated water
supply work
Sewage treatment and recycling work in Urad Front Banner
Industrial Park
I. Land expropriation
1. Determination of land to be expropriated 2009.5 2009.5 2009.5 2009.5 2009.5 2009.5 2009.5
2. Preparation and investigation of physical data of land
expropriation2009.7 2009.7 2009.7 2009.7 2009.7 2009.7 2009.7
3. Consultation and determination of land
compensation standard2009.7--2009.9 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9
4. Payment of land compensations. 2010.10--2010.12 2010.2--2010.3 2010.10--2010.12 2010.2--2010.3 2010.10--2010.12 2010.10--2010.12 2010.2--2010.3
5. Transaction of land expropriation procedure 2011.1--2011.2 2011.3--2011.4 2011.1--2011.2 2011.3--2011.4 2011.1--2011.2 2011.1--2011.2 2011.3--2011.4
II. Production recovery
1. Consultation of land compensation schemes 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9 2009.7--2009.9
2. Payment of land compensations. 2010.10--2010.12 2010.2--2010.3 2010.10--2010.12 2010.2--2010.3 2010.10--2010.12 2010.10--2010.12 2010.2--2010.3
10.2.7 Organization and structure
10.2.7.1 Organization structuring
1) Departments to be established
To ensure the smooth construction of each work of Comprehensive Treatment
Project in Bayan Nur, relevant coordination department will be established by Bayan
Nur People’s Government, the governments of each banner (county) affected and the
Owner of Project to coordinate and supervise all activities relating to resettlement.
Departments responsible for the land expropriation, house removal, and resettlement
relating to each work of Comprehensive Treatment Project in Bayan Nur include:
(1) Leaders’ Team of Municipal Project Coordination Teams
(2) Office of Leaders’ Team of Municipal Project Coordination Teams
(3) Project Office of banner (county) affected by this Project
(4) Owner’s organization
(5) Villagers’ Committee and sub-villages
(6) Independent outsider supervision and evaluation institute
2) Constitution and duty of each department
A. Leaders’ Team of Municipal Project Coordination Teams
For the purpose to strengthen the tasks of Comprehensive Treatment Project and
to promote the approval and implementation of this Project, the municipal
government decides, according to the change of leaders of municipal government of
project member organizations, that the Project Coordination Leadership Team
(“Leadership Team”) set up pursuant to original Ba Zheng Ba Zi [2006] No. 355 file
will be adjusted. The Leadership Team is the decision-making body of this Project
will make decision on all material issues. Its main duties are:
(1) Determine the construction scale, contents of this Project according to the
demands of social and economic development of whole city;
(2) Give instruction to the performance of activities such as project application,
project verification and project implementation according to the requirements of
project invested by domestic and foreign investors;
(3) Coordinate with each member organization of this Project to complete the
preliminary work and the construction, management and operation of this Project;
(4) Be responsible for the verification and approval of construction schemes, the
award of commencement order, and the acceptance of this Project;
(5) Be responsible for the financing and repayment of loans and other material
decisions.
The Leadership Team will hold at least one working meeting per half year to
discuss and make decision on relevant issues.
B. Office of Project Coordination Leadership Team
Office of Project Leadership Team will be established. The Office will be located
in Hetao Water Group and includes general office, administrative department,
financial department, engineering and technical department, tendering and purchase
department. Duties of each department will be defined clearly and the responsibility
system of special personnel will be applied. The main duties of Owners' Office are:
(1) Carry out the decision of Project Leadership Team and organize the
promotion activities of this Project;
(2) Coordinate with each member organization to carry out the project
application and verification, and organize the implementation of detailed tasks;
(3) Report to Leadership Team in regular or irregular manner.
C. Project Office of banner (county) affected by this Project
The principal leaders of each banner (county)’ people’s government will be take
charge of the Project Office of each banner (county) affected. All of them will be
located in water authority. Members include the leaders of water bureau, development
and reform commission, construction bureau, land administrative bureau and relevant
townships and towns. The main duties are to assist in the implementation of this
Project, coordinate and solve relevant major issues.
(4) Owner’s organization
The duties of Owner's organization concerning land expropriation, removal and
resettlement include:
(1) Authorize design institute to define the area affected by Project, and
authorize local resettlement authorities to conduct social and economical investigation
and statistics, and storage of data;
(2) Be responsible for the financing of resettlement funds and transfer of funds;
(3) Prepare activities and schedule of implementation of resettlement;
(4) Guide, coordinate and supervise each resettlement authority to implement the
resettlement plans as required in “Resettlement Plans”;
(5) Coordinate the inner supervision activities and preparation of reports;
(6) Coordinate the outside supervision activities.
E. Villagers’ Committee and sub-villages
The main leaders of Villagers' Committee and sub-villages will form a
resettlement working group. Its main duties include:
(1) Participate in social, economical investigation and the investigation of impact
of Project;
(2) Organize the public to consult and publicize the land expropriation and
removal policies;
(3) Afford help for households in hardship;
(4) Select place for resettlement and arrange house site for households whose
houses are removed;
(5) Carry out the adjustment of land, and organize production and development
and other resettlement activities;
(6) Be responsible for management and distribution of funds;
(7) Report the opinions and suggestions of immigrants to higher-level
authorities;
(8) Report the resettlement implementation progress.
F. Resettlement supervision and evaluation institutes
The outside independent supervision and evaluation work of this Project will be
undertaken by the independent outsider supervision and evaluation institutes
recognized by the Owner of this Project. Independent outsider supervision and
evaluation institute will implement all supervision and evaluation tasks by providing
technical help to relevant department and carrying out investigation on the migrants
and the living standard of personnel affected by this Project. Their main duties
include:
(1) As an independent supervision institute, supervise the planning and
implementation of resettlement and submit resettlement supervision and evaluation
report to the Owner, and World Bank. This duty will be detailed in relevant chapters
in Independent Outsider Supervision and Evaluation;
(2) Provide technical consultancy concerning data investigation and treatment of
inner supervision for Owner and other relevant departments.
3) Staffing
To safeguard the smooth implementation of this Project and resettlement tasks,
large number of material and human resource has been input by Bayan Nur People’s
Government, people’s governments of relevant banner (county) and Owner of this
Project. Resettlement teams have been established and relevant personnel have been
staffed.
10.2.7.2 Intercommunication between different departments
During the land expropriation, removal and resettlement process, each
resettlement department will enter into authorization contracts or agreements to define
the working contents and duties of each department. Execution of authorization
contract/agreement will be made as follow:
(1) Owner of this Project enters into “Agreement on Land Expropriation,
Removal and Resettlement” with project office of each banner (county) of Bayan Nur
respectively;
(2) Owner of this Project enters into “Contract of Independent Supervision and
Evaluation Tasks Concerning Resettlement" with outsider supervision and evaluation
institutes;
(3) Project office of each banner (county) enters into “Agreement on Land
Expropriation, Removal and Resettlement” with Villagers’ Committee;
(4) Villagers’ Committee enters into “Resettlement Compensation Agreement"
with transmigrated households.
11 Abstracts of Environmental Management Plan
11.1 Environmental Management System
As the main body for the administrative management & administrative law
enforcement of the environmental protection nationwide, the Ministry of
Environmental Protection of the People’s Republic of China shall supervise the
implementation of the project. Under The Law of the People’s Republic of China on
Environmental Protection & The Regulations on Environmental Protection of
Construction Projects, the environmental impact appraisal report of the project shall
be approved by the Department of Environmental Protection of Inner Mongolia
Autonomous Region. Bayannur Municipal Bureau of Environmental Protection is the
environmental management unit of the project, of which the main functions include
the submission of environmental protection demands according to the environmental
impact appraisal report of the project, the coordination of environmental protection
management between different branches and the liability for organizing a “three-
simultaneity” inspection over the implementation of environmental protection
facilities. Within the framework of overall administrative managing organs of the
project, the WB loan project office at different levels is liable for the management of
the whole project and is under the leadership of Bayannur Municipal Government and
banner (county) government. Under the project office, the employer of the project will
carry out their own sub-projects respectively. To guarantee the smooth
implementation of the environmental management of the project, the project office,
project employer, and contractor and operator are staffed with several full- or part-
time environment managing personnel for implementing the environmental
management plan. The WB Loan Project Office of Bayannur Municipality shall be
liable for the planning and design of the project, supervise the procedures of the
environmental protection and organize and carry out technical trainings for
environmental managing personnel of the project within the whole region; the main
functions of the project office and Bureau of Environmental Protection of the banner
(county) include the implementation of the project proposal and various technical
criteria of the project and daily supervision of environmental management; under the
authorization of the project employer, the environment monitoring station of the
banner (county) is liable for monitoring environment quality of the project region in
the period of project construction and operation; and the environment supervising
engineer authorized by the employer is liable for environment supervision on project
construction. The project employer is to be staffed with full-time environmental
management personnel liable for the environmental management of the project on
different stages; implement the statutes and plans on environmental protection;
inspect the implementation of environmental protection measures of the project;
popularize the application of sophisticated techniques and experiences on
environmental protection; and organize and carry out some technical training on
environmental protection for relevant personnel of sub-projects so as to improve the
accomplishment of the personnel. The environmental management items of the
project sharply vary in the construction period and operating period, which features
temporary and long-term time limit on working hours respectively. Therefore, the
contractor and operator shall set up institutional framework according to different
stages, and break down the liability by stages. After the construction period is over,
the managing institution of the construction shall be cancelled immediately, and the
operation managing institution shall start to run. According to the specific situation, a
transitional period is allowed. The chart of organizational institution is included in
Figure 11.1-1. The environmental protection supervising plan of the project is
included in Table 11.1-1.
国家层面 国家环保部 世 行
巴彦淖尔市环保局 巴彦淖尔WB 贷款项目办
乌拉特后旗环保局
乌拉特前旗环保局
杭锦后旗环保局
乌拉特中旗环保局
五原县环保局
乌拉特后旗项目办
乌拉特前旗项目办
杭锦后旗项目办
乌拉特中旗项目办
五原县项目办
设计单位旗县环境监测站
建设承包商
环评单位环境监理工程师
旗县环境监测站
业主或运营商
项目业主
旗县层面
企业层面
巴彦淖尔市层面
环境监督机构 设计与施工期环境管理执行机构 营运期环境管理执行机构Figure 11.1-1 Schematic Diagram of Organizational Institution for Environmental Protection of
the Project
国家层面 National level
国家环保部 The Ministry of Environmental Protection
世 行 WB
巴彦淖尔市层面 Level of Bayannur Municipality
巴彦淖尔市环保局 Bayannur Municipal Bureau of Environmental Protection
巴彦淖尔WB 贷款项目办 Bayannur WB Loan Project Office
旗县层面 Level of Banner/County
乌拉特前旗环保局 Wulateqian Banner Bureau of Environmental Protection
乌拉特中旗环保局 Wulatezhong Banner Bureau of Environmental Protection
乌拉特后旗环保局 Wulatehou Banner Bureau of Environmental Protection
杭锦后旗环保局 Hangjinhou Banner Bureau of Environmental Protection
五原县环保局 Wuyuan County Bureau of Environmental Protection
乌拉特前旗项目办 Wulateqian Banner Project Office
乌拉特中旗项目办 Wulatezhong Banner Project Office
乌拉特后旗项目办 Wulatehou Banner Project Office
杭锦后旗项目办 Hangjinhou Banner Project Office
五原县项目办 Wuyuan County Project Office
项目业主 Project Employer
企业层面 Level of Enterprise
旗县环境监测站 Environment Monitoring Station of Banner/County
环评单位 Environment Appraisal Unit
设计单位 Design Unit
建设承包商 Building Contractor
环境监理工程师 Environment Supervising Engineer
旗县环境监测站 Environment Monitoring Station of Banner/County
业主或运营商 Employer or Operator
环境监督机构 Environment Supervision Institution
设计与施工期环境管理执行机构
Environment Management Implementing Institution in Design and Construction Period
营运期环境管理执行机构 Environment Management Implementing Institution in Operation Period
Table 11.1-1 Environmental Protection Supervising Plan of the Project
Stage Institution Supervision items Supervision purpose
Feasibility study stage
The Ministry of Environmental Protection Municipal Bureau of Environmental Protection WB
1. Verify the environmental appraisal outlines; 2. Verify environment impact report; 3. Verify EAP.
1. Guarantee all-inclusive environmental appraisal items, proper topic setup and highlight; 2. Ensure the reflection of probable major and potential problems of the project;
3. Guarantee feasible specific implementing plan of the measures reducing the environment impact.
Design and construction stage
The Ministry of Environmental Protection Municipal Government Municipal Bureau of Environmental Protection County Government County Bureau of Environmental Protection Cultural Relics Bureau of the County
1. Verify preliminary design and EAP of environmental protection; 2. Inspect the restoration of temporary land occupation, vegetation and environment; 3. Inspect control measure against dust and noises pollution, and determine the construction time; 4. Inspect the emission of air pollutants; 5. Inspect the emission and disposal of domestic sewage and waste engine oil on the construction site; 6. The restoration and disposal of soil taking and dumping place;
7. Inspect the disposal of silt; 8. Inspect if there are cultural relics under the ground.
1. Strictly implement “three simultaneity”; 2. Ensure the compliance of these places with environmental protection requirements;
3. Reduce the impact of the construction on surrounding environment, and implement relevant regulations and standards on environmental protection;
4. Reduce the impact of the construction on surrounding environment, and implement relevant statutes and standards on environmental protection;
5. Ensure no water pollution of inland river; 6. Ensure no serious damage of landscape and land resources, and prevent land erosion;
7. Ensure proper disposal of silt; 8. Protect cultural relic resources against damage.
Operation stage
Municipal Bureau of Environmental Protection Banner/County Bureau of Environmental Protection Fire Prevention Authorities of
1. Inspect the implementation of EAP in operation period; 2. Inspect the implementation of monitoring plan; 3. Inspect sensitive points in need of more environmental protection measures (unpredictable environment problem may occur); 4. Inspect environmental quality of environment sensitive points in
1. Implement EAP; 2. Implement monitoring plan; 3. Protect the environment faithfully; 4. Strengthen environmental management, and sincerely protect the health of people; 5. Ensure the emission of pollutants in conformity with the standards.
Banner/County
conformity with the governing quality criteria; 5. Strengthen supervision, prevent sudden accident, work out the proposal against sudden accident, and eliminate the danger in case of any accident.
11.1.1 Organization of Environmental Protection in Construction
Period
11.1.1.1 Organization
Technical level: on the technical level of environmental management, the
municipal project office will employ five experts for project management.
Project office level: the municipal project office will send an environment
manager for the project, who will supervise implementation of environmental
management plan and be liable for all the issues related to the World Bank and the
environment. The project office of county/banner shall be staffed with one
environment manager, who is liable for the implementation of environmental
management plan of the project in its area and the communication on relevant
environment issues with the municipal project office.
Contractor level: one or two environment managing coordinators will be
provided by itself, liable for supervising the implementation of environmental
protection measures in construction period, and negotiating with surrounding
residents for resolving environment issue and communicating with the project office
and environment authorities.
Operator level: each enterprise is set up with an environmental managing
division comprising two full-time environmental protection engineers. Other
employees of the corporation will assist these two engineers in carrying out the
environmental management in operation period. The corporation will provide Internet,
telephone and other communication facilities for keeping in touch with the
environmental management authorities.
The level of environment supervising engineer: each project employer will
employ one environment supervising engineer for the project, who will present field
supervision on the site in the construction period.
11.1.1.2 Position and Liability
A. Technical Environment Expert
Technical environment expert, the technical support of local project office will
track the whole course of the project in the first six months and offer regular service
of two weeks quarterly within four years after the project implemented. Technical
environment expert will ensure that all compulsory requirements are met when the
project starts and environmental management rules effectively implemented in
conformity with the environment laws and regulations and the safety rules of the
World Bank.
(1) Provide necessary training for environment managers of project office, and
environmental managing personnel & environment supervising engineers of
contractor and operator.
(2) Offer expert consulting service for project office, employer, contractor and
operator.
(3) Assist environmental managing personnel of enterprise in organizing
monitoring activities.
B. Project office: Environment Manager
The municipal project office, Hangjin Banner, Wulatehou Banner, Wulatezhong
Banner, Wulatehou Banner and Wuyuan County each are set up with one environment
manager. The environment manager of the municipal project office is the expert liable
for reporting to WB and supervising project environment. Environment manager of
project office of banner/county is liable for the supervision of local project and
reporting to the municipal project office. Environment manager will assist land
authorities and immigration authorities in preventing the above-said from obstructing
the implementation of the project, with liabilities as follows:
(1) Provide training for managers in charge of environmental management with
the help of assistant.
(2) Define monitoring plan with the help of assistant.
(3) Communicate with managers in chare of environmental management and
construction workers, with methods as follows:
—Provide regular monitoring report for project office and the World Bank
monthly.
—Provide special non-conformity report in case of the 2nd and 3rd cases;
—Communicate orally with the staff of construction unit and operating unit and
jointly define a solution proposal in case of any solution to the problem available;
—Present remedy measures with environmental managing engineer and the
manager in charge of environmental management jointly in case of non-conformity
(4) Attend the joint meeting that the environment engineers of the project office
and manager in charge of environmental management of the corporation, construction
unit and operating unit take part in.
(5) Coordinate the communication & report of environmental management
experts with the World Bank.
C. Project Employer: environment manager coordinator EMC
The employer is provided with EMC liable for environment monitoring, who
reports environmental protection implementation of the construction unit and
operating unit to the project office of banner/county and governmental institutions.
Detailed liabilities of EMC are as follows:
(1) Compile the detailed rules on environmental protection, and detailed
monitoring rules and environmental protection procedures of construction unit and
operating unit, and collect the outlines of managing and design personnel of the
project on the preliminary stage of the project with the help of technical assistant.
(2) Authorize the items in need of special equipments for monitoring, such as air,
water environment quality monitoring.
(3) Provide monthly monitoring update for project office, implementation of the
project and feasibility study and the remedy measures. Organize meetings with the
project office for reporting project monitoring, and discuss conformity of the project.
(4) Select experts and counselors from the universities and institutions for
consulting on training methodology and technology as per the demands.
(5) Organize the special study and public survey related to special building
requirement or compulsory alteration according to the actual situation of the project.
(6) Report solution and emergency handling measures to environment manager
of the project office and environment supervising authorities in case of any non-
conformity with the feasibility study report.
(7) Information Disclosure through Meeting and Local Media.
D. environment supervising engineer
Environment supervising engineer is mainly responsible for architectural
engineering activities of the supervising party and other related activities such as land
occupation and resident relocation. It’ll guarantee that the above-said activities
comply with the environmental protection requirement, environmental protection
investment and protection target. It’s liable for coordinating the land authorities,
migration and relocation authorities and environment monitoring & control authorities
on the site. The main liabilities of environment supervising engineer are as follows:
(1) Ensure the implementation of all project licenses and requirements and
environmental management plans before commencement of the project.
(2) Check and verify that all employees of construction unit and operating unit
have implemented environmental protection measures as per the contract.
(3) Compile standard report statements on monthly remuneration as per their
qualification in light of the contribution of construction unit and operating unit to
environmental protection activities of the project.
(4) Compile the documents on environmental protection monitoring.
(5) Identify the case in need of special study and activity, communicate with
EMC, and implement effective special measures regularly.
(6) Communicate with the construction personnel for explaining the field
environment requirement; provide proposal on remedy measures, offer some remedy
measures for the items not in conformity with the original purpose of the project; and
issue very formal guide to construction unit and operating unit as required.
(7) Communicate with the construction unit, operating unit and building
consultant for strengthening information exchange; obtain some other points of view
on special issues for the purpose of rapidly feeding back some problem in the
construction to the building managing engineer so as to facilitate solution of the
problem; and shutdown should be immediately applied for in case that the project
causes potential damage to sensitive targets or serious non-conformity case in the
existence of the project.
(8) Communicate with building supervising engineer of the project and the
building workers; compile regular monitoring weekly update; compile records on
non-conformity, and bring forward remedy measures with project designer if
necessary in case of non-conformity of the project with the design.
11.1.2 Environmental Management Organ in Operation Period
Project operator will have a special-purpose environmental management division
that is liable for the implementation of the environmental management plan in
operation period. Detailed liabilities of the environmental management division are:
(1) Manage the implementation of environmental protection measures of the
project;
(2) Coordinate relevant environment problem with environment authorities and
surrounding residents;
(3) Authorize monitoring station of banner/county for regular monitoring of three
wastes discharged by the facilities of the project and environment quality in the
region;
(4) Implement emergency handling of the environment risk in case of any
environment risk;
(5) Report environmental management-related information of enterprise in time
to Bureau of Environmental Protection of the Prefecture/Municipality and provincial
project office;
(6) Be liable for sorting out the environmental management archives of
enterprise and putting in archives.
11.1.3 List of Environmental Management Organs of Sub-project
The list of environmental management organs of sub-project are included in
Table 11.1-2 and Table 11.1-3.
Table 11.1-2 Setup of Environmental Management Personnel of Project Office
Organ Environment manager Environment expert
Bayannur Municipal Project Office 1 5
Hangjin Banner Project Office 1 1
Wulatehou Banner Project Office 1 1
Wulatezhong Banner Project Office 1 1
Wulateqian Banner Project Office 1 1
Wuyuan County Project Office 1 1
Total 6 10
Table 11.1-3 Personnel Setup of Environmental Management Organ of the Sub-project
Project name
Building contractor Operator
Sub-totalEnvironment manager
coordinator
Environment supervising
engineer
Environmental management
personnel
Emergency risk
handling personnel
Water supply works of Wulatehou Banner
Industrial Park 1 1 1 0 3
Sewage treatment and recycling works of
2 1 2 1 6
Wulatehou Banner Industrial Park
Water supply works of Processing Park of Ganqimaodu Port
1 1 1 0 3
Sewage treatment and recycling works of Processing Park of Ganqimaodu Port
2 1 2 1 6
Sanpaigan reclaimed water supply works 1 1 1 0 3
Qipaigan reclaimed water supply works 1 1 1 0 3
Sewage treatment and recycling works of Wulateqian Banner
Industrial Park
2 1 2 1 6
Landscape grid waterway works of
Wuliangsu Lake 2 1 2 0 5
Artificial wetland works of transitional biological belt of Wuliangsu Lake
2 2 3 1 8
Total 14 10 15 4 43
11.2 Implementation of Environmental Management Plan
11.2.1 Detailed Tasks of Environmental Management Plan
The project has impact upon the environment in both construction period and
operation period. In light of different characteristics of environment impact in
construction period and operation period, relevant environmental protection measures
should be taken for minimizing various impacts. To ensure the role of environmental
countermeasures, environmental managing and monitoring procedures are defined.
Besides its managing function for the project, WB project office will track and
report the monitoring of the environment measures. Average environment measures
and the liability of relevant units are introduced in this chapter. In the project, the
project office is liable for tracking and reporting the implementation of various
environment monitoring measures. The list of behaviors managing and monitoring
environment countermeasures is included in Table 11.2-1.
Table 11.2-1 List of Detailed Activities of Environmental Managing Organization
Plan ActivityPerson liable
NotesImplemen
tationSupervisi
on Investment
Early stage of the construction
1 yearSet up environmental
management organ of the project
PMU PMU PMUConvene the personnel,
select office, purchase traffic equipment and raise funds
1 yearSelect environment supervisor
for each CSE and carry out training
EMD CSE CSE
1 yearCompile and implement the
training plan for EMD & PMO environment manager
TA PMO PMO Carry out overall training of the part of the project
1 year Compile work plan for EMD and environment supervisor TA PMO PMO
Including the definition of the role and liability of EMD and environment
supervisor
1 year
Compile work document: standard, field inspection list, and different activity report
formats
EMD PIUs/PMO PMO
Carry out necessary adjustment for the mode of
the original document in field use
1 year Compile emergency handling proposal for EMD TA PIUs/
PMO PMO
1 year
Work out technical introduction on environmental
and social evaluation for contractor
TA&ESD PMU PMUInclude various technical introduction articles in the public bidding document
1 year
Take part in bid evaluation and contract negotiation of environmental and social
evaluation part
TA&PMU PMO/WB PMU
1 year Coordinate compensation for land purchase PMU
Land Manage
ment Bureau &
Bureau of
Environmental
Protection
PMO& others
ESD ensures the implementation of the measures and the land
usability by stages
Construction period
1 year(0-3
months)
Environment supervisor and EMD discuss the adjustment and revision of project file
and measure
PMU PMO - Adjustment made for improving the efficiency
1 year(0-3
months)
Engineering contractor designates one person liable for environment work, who will coordinate with PMU
contractor PMU contractor
1 year
Construction and operating units organize the working personnel for studying the
common knowledge on environment
contractor
EMD/environm
ent superviso
r
contractorEMD will introduce field management and relevant
environment issues
1 year Organize the public for communication and provide
TA&EMD contractor
PMO Put up bulletins on the construction site and
support materialssurrounding areas, issue the exchange rules and process,
and release on the media
1 yearRegularize the cooperation with other provincial and
municipal institutionsEMD PMU PMO/PMU
Operation period
Confirm the procedures for reporting environment
problem in operation periodemployer
Relevant bureau of environm
ental protectio
n
Confirm that solid waste in the project is piled up
together and safely handledemployer
Relevant bureau of environm
ental protectio
n
Monitor the outlet water of sewage treatment plant and
reclaimed water plant
operating unit
Relevant bureau of environm
ental protectio
n
operating unit
Monitor the water quality of artificial wetland and the growth of aquatic living
beings
operating unit
Relevant bureau of environm
ental protectio
n
operating unit
11.2.2 Contractual Requirement on Environmental Management
In project construction, the contractor will play a key role in environmental
management, pollution control and the prevention measure implementation. As a
result, the requirements for the contractor are as follows:
(1) Qualified contractor is selected for ensuring effective implementation of
environmental management plan;
(2) The contractor and construction supervisor must receive the trainings on
environment protection and environment management before construction;
(3) The environmental impact reducing measures in construction period in above
should be included in the bidding document of the contractor and finally in the
construction contract as contractual requirement of project contractor.
(4) The contractor should monitor its environment activity, daily or weekly
submit an environmental performance record report. The project office and the
construction supervising team will supervise and verify these records.
(5) The contractor should provide at least one full-time employee liable for the
environment for each sub-project. These employees liable for environment must
receive the training as scheduled so as to be competent for their job.
(6) In the construction, the contractor should communicate and negotiate with the
people in the region of the project, set up bulletin at each construction unit for
announcing specific construction activities, time, contact and telephone so that the
public can present their complaint or proposal for the construction activity.
(7) A deposit for environmental management and etc. should be planned in the
contractual funds of the project of the contractor as per annual budget, with a
proportion of about 3% of the budgetary funds.
11.2.3 Information Exchange and Solution to Non-conformity Case
In environment monitoring, information needs to be disclosed to the field
environment supervisor, environmental management manager of enterprise and
project office. To focus the attention of management on the most important issues, the
non-conformity of the project is divided at three levels as follows as per the difference
of importance.
Level 1: definition: the non-conformity status is defined as non-conformity with
the original requirement while is deemed to have no short-term impact on very
important resources. The repetitive occurrence of Level 1 may cause the appearance
of Level 2 if not properly handled. Measures: proper cooperation and regular
communication can deal with the case of Level 1. For example, the construction unit
discusses with the employees of operating unit. As a result, remedy measures can be
implemented soon. The formal communication mode is typically a weekly report that
environment supervising engineer submits to environmental management manager
and field building manager of enterprise.
Level 2: definition: the non-conformity status doesn’t produce an obvious
damage or inconvertible impact for the sensitive and important resources while needs
immediate remedy and field disposal for preventing above-said impact. The repetitive
occurrence of Level 2 may cause the appearance of Level 3 if not properly handled.
Measures: In case of the event of Level 2, environmental management manager of the
enterprise must report to environment manager of project office and field building
manager on the day of occurring and remedy measures should be defined as soon as
possible. Generally, remedy measure must be submitted in one week upon the
occurrence.
Level 3: definition: the level includes a damage to sensitive target in focus or
predictable and instant damage. Special behaviors prohibited internationally are also
included in Level 3. Measures: In case of the event of Level 3, environmental
management manager must report to environment manager of project office and field
building manager on the site immediately and remedy measures should be defined as
soon as possible. Generally, remedy measure must be submitted in three days upon
the occurrence except special cases in need of more time. If necessary, the
environmental management manager of the enterprise can require the building
manager to stop some special works in order to protect the resources before
implementation of remedy measures.
11.2.4 Training—Necessary Capability Development and Means
Development
11.2.4.1 Training Requirement
The main target of environmental capability development is environmental
management personnel & environment supervisor. Their training is component of the
technical support of the project. Training courses are provided for the construction
party and workers as well in the implementation of the project. Before
commencement of project construction, all construction units, operating units and
building supervisors must take part in the compulsory trainings on environment,
health and safety.
11.2.4.2 Training Items
(1) Environmental Management Personnel and Environment Supervising
Engineer
The training is organized by the municipal project office one year before the
implementation of the project for environment manager of project office of
banner/county, environment manager coordinator, environment supervising engineer
of sub-project and other personnel. Technical environment experts will be liable for
detailed implementation. Training items are included in Table 11.2-2.
Table 11.2-2 Training for Environment Manager and Environment Supervising Engineer
Theme Training items Time
Operating capability
(environment manager and
Rapidly browse and identify hotkey function of Word, Excel and 4 days
environment supervisor)
PowerPoint;
Learn the security policies of the World Bank;
Intensively study the detailed rules on environmental protection
designated for the construction party. After technical consultant
compiles a list of environmental protection, each list includes the notes
on monitoring.
Study environment impact of the project and environment items in need
of monitoring.
Conformity monitoring
(environment manager and
environment supervisor)
Training on the field monitoring processes of the project (including
organization, communication, role and liability, decision making
process, report, and standard observing procedures).
1 day
Emergency team
(environment manager and
environment supervisor )
Knowledge on dangerous materials on the site;
Potential disclosure and overflow;
Disclosure and overflow environment and personal impact ;
Emergency reaction process, including priority reaction;
Location and use of reaction facilities;
Communication and reporting facilities.
1/2
days
Emergency treatment and
medical care (environment
manager and environment
supervisor )
The process of seeking medical assistance in emergency and non-
emergency status, and seeking other related medical care. (such trunk
call, medical consulting)
1/2
days
Dangerous material and
waste management,
including the disposal of
explosive wastes
(environment manager and
environment supervisor )
Correct use and storage process;
Correct use process includes fuel adding workflow, dosage calculation
and effective use of equipments;
Correct disposal of used storage tank;
Storage process of dangerous waste;
Borrowed land and cut-over land management;
Non-dangerous waste management;
Medical problem exposed in dangerous wastes;
Emergency process.
1/2
days
Health and safety
inspection and declaration
process (environmental
management manager and
environment supervisor )
Health and safety issue;
Health and safety requirement;
How to implement health and safety inspection;
Problem reporting and resolving process
1 day
Traffic safety
(environmental
management manager and
environment supervisor )
Traffic rules;
Safe driving training ;
Vehicle repair and maintenance process;
Fuel adding process;
Emergency reaction process.
1/2
days
Water quality, air and
noises monitoring and
analysis (environmental
management manager and
environment supervisor )
The use of equipments includes standard, testing, method, sample
transport and digital monitoring;
Monitoring and reporting requirement
1/2
days
(2) Contractor and Building Worker
The project office of banner/county or construction employer of sub-project will
organize relevant personnel and carry out training at the site of the project before the
implementation of the engineering works. Environmental management experts or
well-trained environment manager of enterprise can be liable for specific
implementation. Specific training items and periods are included in Table 11.2-3.
Table 11.2-3 Training for Construction Personnel
Training mode Training items Training period
Average
environment
knowledge for
building workers
Introduction to environment-related environment impact factor
and environmental protection measures;
Introduction to extremely environment-sensitive areas and
problems in the building area, and introduction to adjacent
areas in building area;
Role and liability of environmental managing and design
engineer, environment supervisor and building supervisor, and
the report outlines of environmental problem;
Waste management of construction camp and construction site;
Pollution control measures of construction site;
Cultural heritage issue;
Penalty for violating the laws and statutes
Half-day
training
course at each
site
Average health and
safety of building
workers
Including the channel of propagation and protection for
preventing HIV/AIDS and STD;
Prohibit alcohol and narcotics;
Process of seeking medical assistance in emergency and non-
emergency status, and seeking other related medical care. (e.g.
STD detection and consulting);
Common knowledge on health and safety includes some basic
Half-day
training
course at each
site
process: traffic safety, electricity use safety, explosion, fire
and dangerous waste management;
Use personal protective apparatus;
Penalty for violating the laws and statutes.
(3) Operator (Table 11.2-4)
Table 11.2-4 Training for Environmental Management Personnel of the Operator
Target Training items Training period
Environmental management personnel
WB project management procedures; Mechanism for environment information archiving, disclosure, exchange and report;Emergency handling of environment risk; Health and safety inspection and declaration process.
One-day training course in Bayannur
Sophisticated process and environmental management survey
Survey on up-to-dated public utility works at home
Working personnel of environment
The use of equipments includes standard, testing,
method, sample transport and digital monitoring;
Monitoring and reporting requirement
Two-day training course in Bayannur
11.2.4.3 Funds Budget for Personnel Training
The funds budget for the capability development of the project is included in
Table 11.2-5.
Table 11.2-5 Training Plan for Environmental Protection Personnel of Various Sub-projects
Stage Category Qty (person) Time Fund/RMB10,000
Construction period
Environment manager training 6 2010 24
Project manager coordinator 14 2010 28
Environment supervising engineer 10Before the
implementation of the project
20
Building workers All workers of contractor
Before commencement 24
Sub-total 96
Operation period
Training for full-time environmental management personnel of the enterprise
15Before
enterprise operation
60
Emergency environment risk handling personnel 4
Before enterprise operation
8
Skill training for working personnel of enterprise Several
Before enterprise operation
20
Subtotal 88
Total funds 184
11.3 Environment Monitoring Plan
11.3.1 Monitoring Purpose
Environment monitoring includes two stages of the project: construction period
and operation period. The purpose of monitoring is to obtain pollution update of the
planned project in an all-around way in time, find out the change of environment
quality of the region of the project caused by the construction of the project, impact
scope and environment quality trend of operation period, and feed back information to
the authorities in time and provide scientific basis for the environmental management
of the project.
11.3.2 Environment Monitoring Organ
The environment monitoring station of banner/county where the project is
located authorized by project contractor or operator will undertake environment
monitoring in construction period and operation period. The implementing units all
are attested by national environment quality monitoring system, equipped with
complete equipments and powerful technical strength, and able to carry out the
environment monitoring task smoothly.
The sensitive highlight points with obvious pollution according to the result of
the predictions on environmental impact are used as monitoring points for tracking
and monitoring the pollution of the project in construction period and operation
period. Noises, air and surface water environment with high impact on the
environment are selected as monitoring items. Monitoring factors are defined
according to the pollution feature factor of the project. The monitoring analysis
method is subject to Technical Criteria on Environment Monitoring of the State
Bureau of Environmental Protection. Evaluation standards should be governed by the
national criteria confirmed in the environmental appraisal in each sub-project.
Detailed key steps for effective monitoring of construction site and activity are
listed in Table 11.3-1.
Table 11.3-1 Monitoring in Operation Period and Construction Period
Plan Activity Liability Notes
Implementation
Supervision
Funds raising
Construction period
1 year (1-2 months)
Compile field environmental management plan
the contract
party
EMC/PIU/ EPB
the contract
party
Plan defined within one month after the contract is signed, finally completed within two months, and appraisal and approval by EMC
construction period
Project construction unit and operating unit of the project present the boundary of project implementation for each site for approval
the contract
party
EMC/PIU/ EPB
-
Construction unit and operating unit should compile a map before project implementation
1 year (1-3 months)
Compile pollution control plan, air pollution and trend
the contract
party
EMC/PIU/ EPB
the contract
party
EMC appraisal and approval available after consulting with relevant institutions and residents
Construction period
Air, noises and water monitoring Referring to special parts
Construction period
The pollution control plan also includes the implementation of all pollution control measures mentioned by CSEM, and all retarding measures required for construction unit and operating unit must be done. All surrounding construction camps and facilities must be inspected
the contract
party
EMC/PIU/ EPB
-CSEE daily inspects construction camps and facilities, EMC bi-monthly
Construction period
Environmental protection measures of construction unit and operating unit should be filled in monthly statement and reported
the contract
party
EMC/PIU/ EPB
-The suggestion of CSE is final payment basis of PIU/PMO
Construction period
Report is based on categories as per different processes and pollution levels
the contract
party
EMC/PIU/ EPB
Level 1: EMCLevel 2: EMC and PIULevel 3: EMC, PIU, PMO
Construction period
Determine delay or rejection of engineering payment for construction unit and operating unit
the contract
party
EMC/PIU/ EPB
Construction period
Ensure the land purchase process in conformity with the building plan
the contract
party
POIU and Migration Bureau
Construction period
Traffic information involved in the building process must be provided
the contract
party
EMC/PIU/ EPB
the contract
party
The construction party of the project provides the traffic information update, which CSEE & EMC will check up with the traffic authorities and EMC finally approves
Construction period
Necessary traffic lights are required around the construction site
the contract
party
Traffic authorities
the contract
party
Construction period
A bulletin on suspension of public facility service at least three days in advance is required
the contract
party
EPB and relevant departments
the contract
party
The construction party provides the up-to-dated plan, which relevant institutions and EMC will evaluate jointly
Construction period Daily declaration Inspector
EMC/PIU/ EPB
Weekly field report, monthly SRS report
Construction period Weekly declaration
the contract
party
EMC/PIU/ EPB
Weekly field report, monthly SRS report
Construction period Monthly declaration
the contract
party
EMC/PIU/ EPB
Weekly field report, monthly SRS report
Construction period
Quarterly declaration the
contract party
PIU
Declaration provided if
required by other relevant
organizations
Construction period Semiyearly declaration
the contract
party
EMC/PIU/ EPB
Declaration provided if required by other relevant organizations
Construction period is
over
Restoration of temporary land occupation, withdrawal of all building materials and equipments
the contract
party
EMC/PIU/ EPB
the contract
party
construction period is
over
Replanting of trees felled in
construction contracto
r PIUs
the contract
party
At least the same planting
quantity as the felling
Operation period
One year after the restoration
of temporary site when the
construction is completed
operator EPB
PIU
Claim for the remaining
payment if no non-
conformity in the
declaration
The experiences of the
project is summed up for
applying in similar projects
operator EPB
Standardized process, and
participation in training
courses of intermediate
institutions, revealing the
results and incomes of the
project
11.3.3 Environment Monitoring Plan
The monitoring equipments required in monitoring plan of sub-project are owned
by monitoring unit. Sub-project employer units should pay equipment depreciation
charges at proper amount, instead of any new purchase, which is included in
monitoring expenses. The estimate on monitoring charges of each sub-project is
included in Table 11-3-2. According to the feature of engineering and environment,
environment monitoring items in the construction period and operation period are
included in Table 11-3-3.
Table 11.3-2 Estimate on Monitoring Expenses of Each Sub-project Unit: RMB10,000
Name of project
Monitoring expenses in constructio
n period
Monitoring expenses
in operation
period
Contingency monitoring
expenses for accident
Water supply works of Wulatehou Banner
Industrial Park 19 21 0
Sewage treatment and recycling works of
Wulatehou Banner Industrial Park 23 27 5
Water supply works of Processing Park of
Ganqimaodu Port 28 33 0
Sewage treatment and recycling works of
Processing Park of Ganqimaodu Port 16 34 5
Sanpaigan reclaimed water supply works 12 14 0
Qipaigan reclaimed water supply works 16 16 0
Sewage treatment and recycling works of
Wulateqian Banner Industrial Park 9 17 5
Landscape grid waterway works of
Wuliangsu Lake 7 0 0
Artificial wetland works of transitional
biological belt of Wuliangsu Lake 10 23 5
Total 140 185 20
Table 11.3-3 Environment Monitoring Plan
Sub-
project
Monitorin
g period
Environment
factor Monitoring point Monitoring items Monitoring frequency
Reclaimed
water
supply and
midwater
recycling
works constructio
n period
Environmenta
l air
Residential locations around
construction site and both sides of
road
TSP6 periods/year, 2 days/period, 2
times/day
Water quality
Catch sink of construction wastewater pH, SS, COD, BOD5, NH3-N, TP, petroleum 6 periods/year, 1 day/period, 1 time/day
Upper and lower 500m of reception
water system
temperature, pH, conductivity, DO, COD, BOD5, NH3-
N, TP, TN
3 periods/year, one period in dry,
monsoon and average period
respectively, 3 days/period, 1 time/day
Noises Boundary of construction site Leq dB (A)
6 periods/year, 1 day/period, 2
times/day, one time in day and night
separately
operation
period
Water quality Water outlet of factory
pH, SS, turbidity, chroma, BOD5, COD, Fe, Mn, Cl-,
SiO2. total hardness, total alkalinity, sulfate, NH3-N, TP,
total resolvable solid, petroleum category, active agent
on the surface of negative ion, chloride residue, total
coliform group
Automatic online monitoring
Noises Factory area and pump station
boundary
Leq dB(A) 4 periods/year, 1 day/period, 2
times/day, one time in day and night
separately
Substrate
sludge Sludge discharged from sludge sink Heavy metal (As, Hg, Pb, Cr, Cd, Cu) 2 periods/year, 1 day/period, 1 time/day
Sewage
treatment
works
constructio
n period
Environmenta
l air
Residential locations around
construction site and both sides of
road
TSP6 periods/year, 2 day/period, 2
times/day
water quality
Catch sink of construction wastewater pH, SS, COD, BOD5, NH3-N, TP, petroleum 6 periods/year, 1 day/period, 1 time/day
Upper and lower 500m of reception
water system
temperature, pH, conductivity, DO, COD, BOD5, NH3-
N, TP, TN
3 periods/year, one period in dry,
monsoon and average period
respectively, 3 days/period, 1 time/day
noises Boundary of construction site Leq dB (A)
6 periods/year, 1 day/period, 2
times/day, one time in day and night
separately
operation
period
environmental
air Boundary of factory area Stench concentration, NH3. H2S, CH4
4 periods/year, 2 days/period, 2
times/day
water quality
Monitoring points set up on inlets and
outlets of sewage treatment plant
pH, DO, SS, COD, BOD5, NH3-N, TP
Automatic online monitoring
Monitoring sections set up on upper
and lower 500m of reception water
system
3 periods/year, one period in dry,
monsoon and average period
respectively, 3 days/period, 1 time/day
noises Factory area and pump station
boundary
Leq dB (A) 4 periods/year, 1 day/period, 2
times/day, one time in day and night
separately
substrate
sludge Sludge discharged from sludge sink Heavy metal (As, Hg, Pb, Cr, Cd、Cu) 2 periods/year, 1 day/period, 1 time/day
Sea area
treatment
works of
Wuliangsu
Lake
constructio
n period
environmental
air
Residential locations around
construction site and both sides of
road
Stench concentration, TSP6 periods/year, 2 days/period, 2
times/day
water quality
Catch sink of construction wastewater pH, SS, COD, BOD5, NH3-N, TP, petroleum 6 periods/year, 1 day/period, 1 time/day
Upper and lower 500m of reception
water systemtemperature, pH, conductivity, DO, COD, BOD5,
NH3-N, TP, TN
3 periods/year, one period in dry,
monsoon and average period
respectively, 3 days/period, 1 time/day
noises Boundary of construction site Leq dB(A)
6 periods/year, 1 day/period, 2
times/day, one time in day and night
separately
operation
period
water
quality
Monitoring points set up on inlet and
outlets of sea area pH, DO, SS, COD, BOD5, NH3-N, TP Automatic online monitoring
14.4 Estimates on Environmental Management Expenses and
Source of Capital
14.4.1 Budget Distribution
The implementation of EMP measures involves many units. As a result, different
sources of capital exist. Most environmental protection activities are engineering
measures. Therefore, the construction unit and operating unit of the project should
provide the expenses and include in their engineering costs, which are defined and
listed in their bidding documents.
The expenses in EMP are mainly used in environmental management in
construction period and operation period, primarily including: environment
monitoring expenses, environment supervisor expenses, personnel training expenses,
running costs of environmental management institutions as well as risk preventing
expenses in some projects. EMC activities will be included in the international project
management expenses of PMO and PIUs. So does the monitoring of water quality,
atmosphere and noises, CSEE and EFSI. The CSEE monitoring and supervising
activity is part of building and supervising expenses. Local environment monitoring
stations will monitor water, noises and atmosphere in the operation of project as
authorized by project employer, where project employer pays the monitoring
expenses. If regular monitoring of local environmental protection authorities
synchronizes with the project, their data of regular monitoring can be used.
14.4.2 Capital Source and EMP Budget
Table 11.4-1 is a list of environmental management expenses (excluding
contingency monitoring expenses for accident) of sub-project in construction period
and operation period.
Table 11.4-1 List of Environmental Management Budget of Sub-project
Ref.
Name of
sub-
project
Annual average expenses in construction period
(RMB10,000) Pollution
prevention
and control
in
construction
period
Treatm
ent
expens
es of
substra
te
sludge
Training
for
environm
ental
protection
personnel
Years of
construc
tion
period
Total
expense
s in
construc
tion
period
Annual expenses in operation
period (RMB10.000) Pollution
prevention
and control
expenses in
operation
period
Sludge
treatme
nt
expense
s
Training for
environmen
tal
protection
personnel
Expenses
in five-
year
operation
period
Total
PMU operation environ
ment
monitori
ng
environ
ment
supervis
or
PMU operation Environ
ment
monitori
ng
Wa
ge
Office
expen
ses
Traffi
c
expen
ses
Wa
ge
Office
expen
ses
Traffi
c
expen
ses
1
Water
supply
works of
Wulateho
u Banner
Industrial
Park
3.6 5 1.5 2.40 5 3..98 6 8 149.98 3.6 5 1.5 4.24 4.82 30.77 6 256.65406.6
3
2
Sewage
treatment
and
recycling
works of
Wulateho
u Banner
Industrial
Park
7.2 5 1.5 2.86 6 5.29 8 8 193.7710.
85 1.5 5.47 4.82 44.14 12 370.65
564.4
2
3
Water
supply
works of
Processin
g Park of
Ganqima
odu Port
3.6 5 1.5 3.56 6 4.21 6 8 167.49 3.6 5 1.5 6.55 6.39 6.34 6 152.9320.3
9
4
Sewage
treatment
and
recycling
works of
Processin
g Park of
Ganqima
odu Port
7.2 5 1.5 2.01 8 3.77 8 8 201.4510.
85 1.5 6.88 7.04 59.93 12 467.75 669.2
5
Sanpaiga
n
reclaimed
water
supply
works
3.6 5 1.5 1.52 3 0.98 6 8 123.94 3.6 5 1.5 2.89 7.04 3.46 6 123.45247.3
9
6 Qipaigan
reclaimed
water
3.6 5 1.5 1.98 4 2.39 6 8 137.03 3.6 5 1.5 3.24 7.04 5.79 6 136.85 273.8
8
supply
works
7
Sewage
treatment
and
recycling
works of
Wulateqia
n Banner
Industrial
Park
7.2 5 1.5 1.14 5 4.15 8 8 170.8710.
85 1.5 3.38 4.91 59.93 12 439.6
610.4
7
8
Landscap
e grid
waterway
works of
Wuliangs
u Lake
7.2 5 1.5 0.83 3 0.3 57.38 8 8 205.92 7.2 5 1.5 0 10 78.5284.4
2
9 Artificial
wetland
works of
transition
al
biological
belt of
Wuliangs
7.2 5 1.5 1.21 5 0.37 10 8 169.65 14.
4
5 1.5 4.64 16 143.7 313.3
5
u Lake
Tota
l
50.
445 13.5 17.51 45 21.29 57.38 66 1520.1
68.
445 13.5 37.29 42.05 210.36 86 2170.05
3690.
15
According to the construction time limit of the project, the annual budget for every
construction period must be guaranteed. Some building payment in the budget is the deposit for
construction unit and operating unit to complete the relevant management requirement. The deposit
weight of different activities is listed in Table 11.4-2 as percentage of contractual funds of the
construction.
Table 11.4-2 Percentage Distribution of the Deposits for Environmental Management and etc. in the Budget of the Construction Party
Ref. Requirement for construction party
Percentage of funds budget of each sub-project Capital source
1 Environmental protection management 0.5
2Labor organization and
occupational health management
0.5
3 Public safety management 1
4 Social management 1
11.5 Information Management of Environmental Management Plan
11.5.1 Information Exchange
Environmental management demands a necessary information exchange among different
departments and posts of project offices inside organization, employer, contractor and operator and
moreover, an information disclosure to the outside (related parties and the public). Internal
information exchange can be done in meeting, internal update and other modes, for which at least
one formal meeting is monthly required. All information in the exchange must be recorded and put
in archives. External information exchange should be done semiyearly or yearly. The information
exchange with cooperation units must be recorded in a summary and put in archives.
11.5.2 Recording Mechanism
To ensure the effective operation of environmental management system, a perfect recording
system must be set up for maintaining the records in the fields as follows:
(1) Requirements of the laws and statutes;
(2) License;
(3) Environment factor and related environment impact;
(4) Training;
(5) Inspection, verifying and maintaining activities;
(6) Monitoring data;
(7) Validity of rectifying and prevention measures;
(8) Information of related parties;
(9) Approval;
(10) Appraisal.
Moreover, a necessary control over the above-said records must be done, including the links:
record identifying, collection, catalogue, archiving, storage, management, maintenance, inquiry,
storage period and disposal.
11.5.3 Report Mechanism
Contractor, operator, monitoring unit, environment supervising engineer and project office
should record the progress of project, EMP implementation and environment monitoring result in
the project implementation and report to relevant departments in time, including six major parts as
follows:
(1) The environment supervising engineer of the project compiles detailed monthly records on
EMP implementation, and timely submits the weekly and monthly reports to the project employer
and the project office of banner and county. The weekly and monthly reports should comprise the
implementation of environmental protection measure and environment monitoring as well as
monitoring data.
(2) Contractor and operator compiles detailed quarterly records on project progress and EMP
implementation, submits the quarterly report to the project office in time, and sends a copy of the
report to the bureau of environmental protection of banner and county.
(3) The monitoring unit submits a monitoring report to contractor (operator) and environment
supervising engineer in time after completing the authorized monitoring task.
(4) The project office of banner and county submits the report on project progress to the
municipal project office in time, and sends a copy of the report to Municipal Bureau of
Environmental Protection. A report on project progress compiled by the project office (monthly,
quarterly and yearly) must comprise EMP progress, such as EMP implementing progress and result,
especially the environment monitoring result.
(5) In case of any violation of the regulations in environmental protection, the environment
supervising engineer and the project office will notify the local environmental protection authorities
and report level-by-level if necessary.
(6) Annual EMP implementation report of the project must be completed and submitted to WB
before March 31 of the following year. EMP implementing report can include the items as follows:
a. The implementation of training plan;
b. Project progress, such as riverway improvement works, garbage burial yard, sewage
treatment plant, and completed length and construction progress of pipelines;
c. The implementation of environmental protection measures of the project, environment
monitoring and main monitoring results;
d. Main items of the complaints from the public, solution and satisfaction of the public if any;
e. EMP implementing plan of the next year.
12 Conclusion of Environmental Appraisal
12.1 Relevant Policies and Conformity with the Planning
The reclaimed water supply works and sewage treatment and recycling works of the project
belong to “brackish water, bad quality water, seawater development and utilization and seawater
desalting works” and “three wastes” integrated utilization and treatment works within the category
of encouraging environmental protection and integrated resources saving and utilization in the
national guide inventory of the industrial structure adjustment (Version 2005) respectively; the sea
area treatment works of the project, a water environment treatment works aims at protecting &
restoring wetland function of Wuliangsu Lake, and is implemented in buffer zone and test area,
instead of core area. As per Circular of General Office of the State Council for Strengthening
Wetland Protection Management (GOSC [2004] No.50), wetland protection & wetland function
restoration as one priority in improving living conditions and building a well-off society in all-
around way should be strengthened. Sea area treatment works of Wuliangsu Lake complies with the
laws and statutes of the State.
According to the environmental appraisal policies (OP 4.04) of the World Bank, it supports the
protection, maintenance and restoration of natural habitat and its function, and assists and expects
the borrowing party in taking defense measures in natural resources management for guaranteeing
the sustainable development of environment. It provides assistance funds for natural habitat and
ecologic function protection project helpful for the development of the country and region, and
advocates restoring and rebuilding work for natural habitat with deteriorating environment.
In the “11th Five-Year Plan” period, the economic and social development planning of
Bayannur Municipality brings forward the construction of resources saving & environment friendly
society. On one hand, integrate water resources, plan and utilize the water of the Yellow River,
surface water, underground water and rainwater in unified way, and try to realize the circulated use
of water resources. On the other hand, strengthen the protection and treatment of water environment
and construction of urban sewage disposal facility and auxiliary pipelines, and gradually realize the
emission of urban and industrial sewage in conformity with the standards, and cut off the pollution
source for the Yellow River and underground water. Moreover, plan treatment works of Wuliangsu
Lake, urban road and pipeline, water supply and drainage, garbage disposal and sewage treatment
works as key infrastructure construction projects in the “11th Five-Year Plan” period.
The implementation of various works of the integrated water environment treatment projects of
Bayannur Municipality with WB loan complies with overall urban planning and city planning with
regard to the site selection, and is also important measures for realizing the urban target of overall
urban planning and city planning of Bayannur Municipality, water resources configuration and the
environment protection targets.
In sum, the construction of the project complies with not only industrial policies, laws and
statutes of the State and environmental appraisal polices of the World Bank for the loan project but
also the national economy and social development planning, overall urban planning and city
planning of Bayannur Municipality.
12.2 Analysis on Water Resources Balance
Total annual average water resources in Bayannur Municipality in many years are 5.5742
billion m3, including surface water resources 4.7791 billion m3. Water resources are mainly used in
industrial and agricultural production, domestic and ecologic water consumption of urban and rural
residents. As per the water resources allocation plan approved by the State and the autonomous
region, the quota of water that Bayannur Municipality imports from the Yellow River is 4 billion
m3. Due to historic reasons and actual situation of agricultural water consumption of Hetao
irrigation area, annual average quantity of water imported from the Yellow River in many years is
4.6748 billion m3. At present, Hetao irrigation area imports 674.8 million m3 water of the Yellow
River more than the quota annually.
The water demand and supply of the primary, secondary, third industries, domestic purpose
and ecologic environment are predicted. The result shows that the annual water demand in 2010-
2030 is 4.0965025 billion m3, and the water supply available includes the water from the Yellow
River, underground water and reclaimed water. The annual average supply of water is predicted as
4.0965025 billion m3.
The analysis on water quantity balance of Wuliangsu Lake reveals that in case of the net
quantity of water that irrigation area discharges into Wuliangsu Lake more than 515 million m³,
present ecologic water consumption and the water area of Wuliangsu Lake can be kept. After the
project is implemented in 2015 and water-saving measures are taken in agriculture, if the water
break of farmland decreases by 10%, the water break of general trunk ditch as well as Bapaigan and
Jiupaigan is 415 million m3 and 62 million m3 respectively. After the project is implemented, if 31
million m3 is reused, water return from general trunk ditch and Bapaigan and Jiupaigan into
Wuliangsu Lake is 446 million m3. To maintain the ecologic water demand of Wuliangsu Lake at
515 million m³, it requires Shiganqu to provide makeup water of 69 million m³ in ice flood season.
According to the preliminary engineering design of the works of Inner Mongolia for diverting the
flood of the Yellow River to Hetao irrigation area & Wuliangsu Lake in the emergency ice flood
control proposal, the flood diverting amount is defined as 161 million m3, including 100 million m3
for Wuliangsu Lake and 61 million m3 for the trunk channel of Hetao irrigation area and natural lake
in the north of irrigation area. Therefore, the flood diversion in ice flood season can ensure the
water makeup quantity of Wuliangsu Lake; the preliminary design of the project has already won
approval of the Department of Water Resources of Inner Mongolia Autonomous Region (Approval
for Preliminary Engineering Design of the Works of Inner Mongolia for Diverting the Flood of the
Yellow River to Hetao Irrigation Area & Wuliangsu Lake in the Emergency Ice Flood Control
Proposal IWRCM [2009] No.170). Moreover, the water import through Shiganqu in ice flood
season isn’t included in the quota, and complies with the national and local regulations as ecologic
makeup water of Wuliangsu Lake.
12.3 Appraisal Result of Present Environment Quality
12.4 Appraisal Result of Environmental Impact
12.4.1 Environmental Impact in Construction Period
(1) Appraisal Result of Water Environmental Impact
The main pollutants for water system in construction period are: domestic sewage of
construction personnel and construction wastewater. With proper measures, the impact upon
environment can be controlled within allowed limit.
A backhoe sludge excavating ship & bucket-grab sludge excavating ship are used in the grid
waterway works of Wuliangsu Lake for excavating grid waterway, and can effectively reduce
pollutants and secondary pollution of SS scattering around. Moreover, sludge excavating ship
operates at fixed position with little disturbance for the substrate sludge of sea area, where the
leakage of substrate sludge is little, and the construction impact on water environment is within the
scope of 50-60m. The sludge excavation works will promote the removal of pollutants such as
nutritional salt and heavy metal and exercise a negative impact on water environment quality. In the
dredging period and short time after the dredging is over, the content of total suspended solid,
poisonous heavy metal ion, nitrogen and phosphor nutritional salt in water will increase, and the
transparency of water will decline. Such environmental impact features some duration. However,
one year after dredging, the quality of water system improves, and various indicators are lower than
the level before dredging. As a result, the substrate sludge excavation will promote the improvement
of water quality of the lake.
(2) Conclusion of the Analysis on Atmospheric Environmental Impact
On the construction stage, air pollution mainly comes from the flying dust of construction
vehicle in running, pile-up yard and agitation as well as tail gas of vehicles. The analysis and
preliminary estimate prove that the flying dust in the construction will cause some impact upon the
resident, school, enterprises and government-sponsored institutions around the construction site and
the construction personnel, in which the impact upon construction personnel is the biggest.
However, after necessary measures taken, the impact of flying dust in construction can be
minimized. Moreover, such impact is temporary. After the construction is over, the impact will
decline rapidly with the implementation of greening and replanting works and even disappear. The
tail gas of construction machine and transport vehicles includes nitrogen oxide, carbon monoxide
and hydrocarbon mainly. Such pollutant can easily be diluted and scattered due to less emission
strength and open site.
(3) Appraisal Conclusion of Sound Environmental Impact
In the construction, the noises of construction machine are main source. Sanbaigan reclaimed
water supply works will cause impact on the surrounding environments of Shanba Husbandry
Union and Sanbaigan Sewage Disposal Plant nearby; Qibaigan reclaimed water supply works has
impact on Wuyuan Brick Plant and other enterprises; the sewage treatment and recycling works of
processing park of Wuleteqian Banner has impact upon sound environments of adjacent Shagedan
Village; sea area works of Wuliangsu Lake has some impact on sound environment of the sea area;
and other planned works have less environment sensitive points around and the impact of
construction noises is little. Do lower the artificial noises, take proper sound insulation measures
and set up construction enclosure, and reasonably arrange the running time of high-noise equipment
and avoid operation at night for reducing environmental impact in the construction of the project.
Moreover, select proper positions for equipments, leverage national conditions for reducing noises
so as to minimize the noises impact in construction period.
(4) Appraisal Conclusion of Environmental Impact of Solid
Domestic and construction garbage should be timely transported to a site designated by
environment and sanitation authorities for disposal, in order to avoid environmental impact around.
Try to use the waste soil of the works in the construction of various works of the project; contact
local muck authorities for arranging disposal for the unused waste soil. If waste soil is piled up on
the yard, ecologic greening should be immediately done after the construction over, and moreover,
anti-flood ditch is required for preventing land erosion.
The construction area of the sea area grid excavation works of Wuliangsu Lake is
2.451×106m2, where about 2.295×105m3 substrate sludge is produced. With high water content, the
excavated sludge may cause secondary pollution with no proper protective measures. The
Environment Monitoring Station of Bayannur Municipality has monitored the heavy metal content
of the substrate sludge of the sea area of Wuliangsu Lake. According to the result of monitoring,
heavy metal content of substrate sludge on various monitoring points all aren’t higher than the
standard in Control Criteria on Pollutants in Agricultural Sludge (GB4284-84) of the State.
Therefore, the substrate sludge excavated in sea area grid works of Wuliangsu Lake can be used as
fertilizer, and upper layer of substrate sludge is used in improving alkaline saline soil; and lower
layer is the parent soil with no pollution, about 2.17 million m3, and can be used in piling up
artificial island in the lake area, instead of shipment.
(5) Appraisal Conclusion of Ecologic Environmental Impact
The impact of project construction upon ecologic environment is mainly the damage of soil
and natural vegetation caused in the construction of various works and laying of pipelines. The
construction of the reclaimed water disposal facility, sewage disposal & recycling facility and
artificial wetland of Wuliangsu Lake with permanent land occupation is done mainly on wasteland
and partly on farmland, and will reduce the land of farmers to some extent; present reed land is
manly used in artificial wetland construction of Wuliangsu Lake, instead of any nature change of
present land, and ecologic impact of permanent land occupation is little. The construction of project
pipelines features temporary land occupation, and produces partial and temporary impact and is
restorable after the construction is over. The unfavorable impact upon landscape in the construction
period of the project is short-term and restorable.
The construction segments of the project with probable land erosion are mainly ground
excavation in pipeline laying, and the construction of reclaimed water facility, sewage disposal and
recycling facility and artificial wetland of Wuliangsu Lake as well as earthwork excavation. The
land erosion impact of pipelines construction on the construction stage strictly in conformity with
the water and land conservation proposal and managing measures defined by various works is under
control.
Floating substance of sea area grid waterway works of Wuliangsu Lake in the construction will
shape a high-density floating substance distribution zone in some scope around the construction
site, which may consequently cause a decline of aquatic plankton, zooplankton variety and quantity.
However, such impact is reversible. With the completion of the engineering construction, such
impact will disappear soon. Floating substance of stability pond and deposition pond of artificial
wetland works of Wuliangsu Lake in construction will shape a high-density floating substance
distribution zone in some scope around the construction site, which may consequently cause a
decline of aquatic plankton, zooplankton variety and quantity. However, such impact is reversible.
With the completion of the engineering construction, such impact will disappear soon.
(6) Appraisal Conclusion of Social Environmental Impact
The impact upon traffic in construction period has three aspects: ① road is broken in pipeline
construction and the traffic is hindered; ②earthwork pile-up and road excavation hinder the traffic;
and, ③ transport vehicles will increase the vehicle flow on the road. For ensuring construction
safety, overall medical examination is required for all construction persons on the site, and any
person with infectious diseases should be prohibited on the construction site; regular medical
examination is required for the working staff of mess, and any person with epidemic disease should
be timely treated and transferred out of the mess immediately for preventing the prevalence of the
disease. The construction site should be provided with centralized water supply facility. Water
source should be sterilized and monitored. Medical service facilities should be available on
construction site. Proper labor protection should be provided for construction personnel for their
health and safety and smooth implementation of the project.
12.4.2 Environmental Impact in Operation Period
12.4.2.1 Air Environmental Impact
In the operation period of the planned reclaimed water supply works, the sludge disposal area
will emit some stench, and the sterilizing device may emit chlorine dioxide and chlorine gas in
abnormal working status. Chlorine adding room is equipped with alkaline solution spraying facility.
Therefore, no obvious impact will occur on atmospheric environment.
The site of sewage treatment and recycling works of the project is within relevant processing
park. Analogy analysis reveals that stench substance will have no impact upon surrounding villages.
A preset 150m sanitation protection distance is reasonable. Moreover, the most adjacent sensitive
target is 200m away from the boundary of sewage treatment & recycling works of processing park
of Wulateqian Banner. The impact of stench pollutant is slight.
The waste gas of the artificial wetland works of the sea area the project of Wuliangsu Lake
mainly includes CO2 in microbe decomposition as well as the stench from rotten plant & animal
and living microbes, is little and has emission concentration in conformity with the Grade-II
standard of the allowed highest concentration of plants in Emission Standards on Pollutants of
Urban Sewage Disposal Plant (GB18918-2002).
12.4.2.2 Water Environmental Impact
Sewage treatment and recycling works of the project produces reclaimed water for industrial
enterprises in processing park with no wastewater, is able to save 22.63 million m3/a water
resources, reduce a pollutant emission of the valley i.e. CODcr by 10950.0t/a, BODcr by 6022.5t/a
and ammonia nitrogen by 730.0t/a at designed wastewater scale and plays significant role in cutting
off total water pollutants of the region after put into operation.
The planned reclaimed water supply works can reasonably dispatch water resources, boost
utilization efficiency of water resources, reduce exploitation of underground water resources by
51.024 million m3, protect underground water resources, alleviate the continuously declining status
of underground water, and prevent the expansion of funnel area. Moreover, it can cut off the
emission in the valley i.e. CODcr by 2847.0t/a, BOD by 1335.9 t/a & ammonia nitrogen by
491.29t/a, and improve water environment of the region. Backwash water of filtration sink, sludge
water of deposition sink, waste water in sludge pressure filtration produced in the operation of
various works of the project are recycled. The ultra-filtration and hyper-filtration tail water in
Sanbaigan reclaimed water supply works, Qibaigan reclaimed water supply works and reclaimed
water supply works of Ganqimaodu Port Processing Park all is sent to the front water distribution
terminal after deposition treatment for recycling treatment with the raw water of reclaimed water.
Waste water isn’t discharged. Different disposal measures and modes are applied for the domestic
sewage of reclaimed water supply works according to the infrastructure around the works. The
sewage of reclaimed water supply works of processing park of Wulatehou Banner is sent to the
sewage disposal works of the processing park of Wulatehou Banner for treatment; domestic sewage
of Sanbaigan reclaimed water supply works is sent to Sanbaigan sewage disposal plant to the north
of the works for treatment; domestic sewage of Qibaigan reclaimed water supply works is sent to
Qibaigan sewage disposal plant to the north of the works for treatment; and the domestic sewage of
reclaimed water supply works of Ganqimaodu Port Processing Park is treated in underground
biochemical treatment equipment in conformity with Urban Sewage Recycling—Quality of Urban
Water for Different Purposes (GB/T18920-2002), and used for different purposes in the plant,
instead of any emission.
After completed, ecologic-transitional-belt artificial wetland of Wuliangsu Lake of the project
can cut off the pollutants discharged into the lake: CODcr by 9781.19 t/a, NH3-N by 1990.57t/a &
299.24t/a. The model predicts that in non-frozen period, outlet water quality could reach Cat-IV
standard (average) of the State’s Quality Criteria on Surface Water Environment GB3838-2002.
That is to reduce pollutant concentration of water: CODCr 30mg/l, TP 1.5mg/l and TP 0.1mg/l.
In sum, after the project is completed, the total reduction of pollution loads of Wuliangsu Lake
is: COD by 23578.19t/a, TP by 458.38t/a. Therefore, the project has no negative impact upon the
surface water environment. With the implementation of the project, the trend of serious pollution of
Wuliangsu Lake will be preliminarily controlled. The quality of water returning from Wuliangsu
Lake into the Yellow River will be largely improved.
12.4.2.3 Sound Environmental Impact
The predicted plant noise values of reclaimed water supply works and sewage treatment and
recycling works all comply with Grade-II standards in Criteria on Plant Noises of Industrial
Enterprises (GB12348-90). The results of overlapping with present noises prove that with no
densely populated point around the plant site, the impact of various noises upon prediction points
aren’t exceeding the standard at daytime and night after the project is completed. As a result, in
operation period, the equipment noises of reclaimed water supply works and sewage treatment and
recycling works have little impact upon the surrounding environmental.
Water pumps of sea-area artificial wetland of Wuliangsu Lake in operation period produce high
noises value and strong strike, and some may last for long time with violent shock. With the
construction area 5-10km away from natural protection zone, the impact will occur for the birds in
the region in nidification, food seek, wooing and hatching under national protection.
12.4.2.4 Solid Waste Impact
(1) The solid wastes of the reclaimed water supply works in operation may include domestic
garbage and dehydrated sludge. The output of solid waste of various reclaimed water supply works
is included in Table 3.3-5. The plant area is set up with garbage station, where domestic garbage and
dehydrated sludge will be piled up together, and regularly cleaned & transported to local garbage
plant for burial treatment. Therefore, it has no impact upon the environment.
(2) The solid waste of sewage treatment & recycling works of processing park after put into
production mainly includes domestic garbage, bar residue, deposited sand and biochemical sludge.
The output of solid waste of sewage treatment and recycling works of processing park is included in
3.3-12.
① The plant area is set up with garbage station, where domestic garbage will be piled up
together, and regularly cleaned & transported to local garbage plant for burial treatment. Therefore,
it has no impact upon the environment.
② The bar residue, deposited sand and biochemical sludge of sewage treatment and recycling
works of processing park will be treated as different categories. Set up bar residue and deposited
sand drying yard for lowering the water content; set up a sludge-piling shed for temporary storage
of sludge with canopy on top. The ground of piling shed must be completely hardened, and
cofferdam, drainage ditch and collecting well should be set around piling shed. The drainage in
sludge piling process should be sent back to the sewage disposal system for circulation and
treatment. The impact of sludge piling upon shallow underground water around the plant site should
be prevented. Sludge is regularly transported to Baotou Dangerous Waste Disposal Center of Inner
Mongolia (in the middle and west of Inner Mongolia) for burial treatment.
Closed tank is used for sludge transport in order to avoid public hazard in the transport.
12.5 Relief Measures of Environmental Impact
The environmental protection measures of the project involve two stages i.e. construction
period and operation period, including the relief measures of water environmental impact, ecologic
environment, atmospheric environmental impact and noises pollution as well as water & soil
conservation measures.
Generally speaking, the relief measures of environmental impact of the project are feasible by
and large. If relief measure of environmental pollution of the project is well-prepared, pollutant
emission can comply with the standard. The investment of the project for the environment
protection is RMB63.8675 million, accounting for 6.41% of the total investment of the project.
12.6 Conclusion of Analysis on Environmental Benefits
The project through the construction of reclaimed water supply works and sewage treatment
and recycling works of processing park and implementation of integrated sea-area improvement
works of Wuliangsu Lake can dispatch the water resources comprehensively, improve utilization
rate of water resources, adjust a water demand conflict between industry and agriculture, and
promote and drive regional economic cooperation and development; cut off pollutant emission,
improve water environment quality of Wuliangsu Lake, protect and restore ecologic environment of
Wuliangsu Lake, and have decisive impact on urban infrastructure construction, ecologic
environment protection and even the development of national economy and society in the project
area.
The project can (1) improve the water environment quality of Bayannur Municipality, and
protect and restore water ecologic environment of Wuliangsu Lake; (2) improve the production and
living conditions of local residents, and living quality and health level of the people; (3) promote
the development of reed industry, fishery and tourism in project region through the improvement of
water ecologic environment of Wuliangsu Lake; (4) promote market-oriented construction and
management of the infrastructure of Bayannur Municipality through importing and referring to
sophisticated technique and management experiences at home and abroad, and realize the favorable
self-development of urban infrastructure; (5) boost up harmonious development of environment,
economy and society of Bayannur Municipality, and create favorable condition for the sustainable
development strategy and overall development of well-off society of Bayannur Municipality. The
project with good environment, social and economic benefits complies with the national and local
national economy development planning, and is able to promote the sustainable development of
Bayannur Municipality.
12.7 Conclusion of Public Participation
The results of surveys on public participation in several rounds reveal that 95% of the public
support the project and hold no objection. Main opinions and proposals include: waste water,
noises, flying dust, garbage, land occupation in construction, and the damage to vegetation and
wildlife habitat of Wuliangsu Lake must be considered in project construction and operation;
construction unit should strengthen the supervision over environmental protection, ensure normal
operation of environmental protection facility, control pollutant emission; strengthen the
management and supervision, prevent “sudden accident”, and define emergency handling proposal.
12.8 General Conclusion
In sum, the project complies with the industrial policies, laws and statutes, relevant
environmental appraisal policies of the World Bank, and overall urban development planning,
environmental function zone and ecologic environment function zone planning of Bayannur
Municipality, and features reasonable site selection by and large. After it is completed, the project is
predicted with good environmental benefits, economic benefits & social benefits and can dispatch
water resources reasonably, improve utilization rate of water resources, save water resources; and
after implemented, the project can cut off total pollutant emission in lake water i.e. COD by
23578.19t/a and TP by 458.38t/a, improve water environment quality of Bayannur Municipality and
the water circulation of sea area of Wuliangsu Lake, retard paludification process, and protect and
restore ecologic water environment. Through environmental protection and prevention measures,
the pollutant emission is controlled within allowed limit, and water environment quality of
Wuliangsu Lake can be obviously improved.
Obviously, the project is feasible with regard to environmental protection after the substitute proposal, relief measures, environment management plan, public negotiation and other countermeasure and measures submitted by the project are employed.