Upload
joan-lamb
View
214
Download
0
Embed Size (px)
DESCRIPTION
In the Design-Bid-Build (DBB) process, a designer, hired by ODOT or ODOT, prepares project plans. ODOT then uses these plans to solicit bids for a separate construction contract. In the Design-Build (DB) process, ODOT hires a Design-Build Team (DBT) to complete both the design and construction elements of a project as part of a single contract. 3
Citation preview
ODOT’STwo Step – Least CostDESIGN BUILD PROCESS
HAM-71-3.81 (PID 77628)
1
What is Design-Build?
Design-Build is a project delivery process in which the design and construction phases of a project are combined in a single contract.
The consultant designer and construction contractor function as a Design-Build Team, working concurrently on the design and construction phases of a project. 2
How does Design-Build differ from Design-Bid-Build?
In the Design-Bid-Build (DBB) process, a designer, hired by ODOT or ODOT, prepares project plans. ODOT then uses these plans to solicit bids for a separate construction contract.
In the Design-Build (DB) process, ODOT hires a Design-Build Team (DBT) to complete both the design and construction elements of a project as part of a single contract.
3
Why Design-Build?
Perceived Downfalls Checks and Balances on design Owner losses ultimate design control▪ Scope Compliance▪ Stated Minimums are the standard
Why Design-Build?
Benefits of Design-Bid-Build Unit Cost: 6% Cheaper*
Construction Speed: 12% Faster*
Project Delivery Speed: 33% Faster*
Cost Growth: 5.2% Less*
Schedule Growth: 11.4% Less*
One point of responsibility Design Risk Transfer
*Source: Konchar and Savindo (1999)
Legislative Authority5517.011 Combining design and construction elements of highway or bridge project into single contract.“…the director of transportation may establish a program to expedite the sale and construction of special projects by combining the design and construction elements of a highway or bridge project into a single contract. The director shall prepare and distribute a scope of work document upon which the bidders shall base their bids. “
6
Design Build
ODOT has the authority to do $1 Billion per fiscal year.
Have constructed +200projects to date – total $1.5 Billion: Ave project size = $5.7million
Majority of DB projects in Ohio (+200) using Low Bid DB
Average: 1.9% by # of projects Averaging 11.3% by $
Legislative Authority (Continued) An amendment to the ORC 5517.011 (6/29/2011)
…” Notwithstanding any provision of Chapter 5525. of the Revised Code, the director may use a value-based selection process, combining technical qualifications and competitive bidding elements, including consideration for minority or disadvantaged businesses that may include joint ventures, when letting special projects that contain both design and construction elements of a transportation project into a single contract.
8
Quality Based Design Build
ODOT allowed to combine technical qualifications and competitive bidding elements
“Value-Based” DB CUY-90: Cleveland Innerbelt Bridge –
CCG1 Fra-71/670: Columbus Crossroads –
Project 1
Full VB DB Previous Value-Based Design-Build
CUY-90: Cleveland Innerbelt Bridge – CCG1 ($360 mill)
Fra-71/670: Columbus Crossroads – Project 1 ($240 mill)
Technical Proposal▪ Defines the amount of Details requested on actual design▪ Defines the requested detail on proposed solutions
Further definition of proposed team▪ Large SOQ (+50 pages) and Proposal required (+200
pages 11x17)
What is the difference between ODOT’s traditional DB process and the Two-Step Least-Cost?
Low DB process: Contract is awarded to the lowest bidder. The prequalified bidder must fulfill all conditions of DB scope.
Two-Step Least-Cost DB process: Only the most qualified Bidders allowed to bid. Contract awarded based cost from most qualified bidders. Price evaluated for responsiveness.
11
Scope Development Scope of Services development
Project requirements must be established Risk items to be determined Contractual items need defined (removal of
preferences without damaging innovation and flexibility) ▪ Level of Innovation dependent upon the amount of
allowed flexibility Defined outcomes from the DBT must be
clearly stated Not Confidential
12
Short Listing of Contractors Request for Qualifications
Defines what and how the proposers are to give ODOT to be shortlisted
Typically request Team, demonstrated Capability, and Project approach
Requested information dependent upon how much information available at RFQ
Only opportunity to define what the important team selection items are to be.
13
Short Listing Selection Process
1. ODOT publishes a Request for Qualifications (RFQ)
RFQ includes DRAFT Project Scope and Appendices.
14
Short Listing Selection Process (Continued)2. Unlimited number of potential
bidders submit a CONFIDENTIAL Statement of Qualifications (SOQ) outlining their project understanding, qualifications and experience.All DBTs must be prequalified.
SOQ is evaluated by two groups: Technical-Level SOQ group.Executive-Level SOQ group.
15
Short Listing Selection Process (Continued)3. ODOT short-lists Design Build Teams (DBTs)
based on their respective Statements of Qualifications. Typically, three DBTs are short-listed.
Request for Proposals (RFP) is released. RFP includes “final” Project Scope and Appendices.(FHWA must approval final RFP)
16
Short Listing Selection Process (Continued)
4. Short-listed Bidders submit Price Proposals to ODOT.
5. Price verified for Responsiveness.
17
SOQ Evaluation Criteria
18
Topic Evaluation Criteria Maximum Points
Project Understanding and Approach
How well does the DBT demonstrate a preliminary understanding of the design and construction requirements of the project?
35
Design Build Project Team How well do the DBT’s qualifications, experience and time availability relate to the requirements of the project?
35
DBT Capabilities How well does the DBT’s SOQ communicate and domonstrate their design, construction and project management experience for this project?
30
Total 100
SOQ Evaluator Guidelines
Evaluators selected on the basis of professional expertise and knowledge of the project.
Must agree to sign Confidentiality Agreement
Use expertise to independently assess how each submittal has demonstrated the involved DBT’s ability to achieve project objectives as outlined in the bid documents. 19
Evaluator Guidelines (Continued) Evaluators must review all pertinent
bid documents (e.g., RFQ, draft Project Scope, Appendices, Addenda, etc.). Ensure that current documents are used.
Evaluation group should attempt to reach consensus. If consensus cannot be reached, a vote may be taken.
20
Evaluator Guidelines (Continued) Designated review areas will be
established. Documents and notes must be
strictly controlled. A numbered copy of the involved
document will be assigned. Discussions concerning confidential
items only with those agree to confidentiality
21
Evaluation Process
Individual Review
Reference Verifications
Scoring and Documentation
Evaluation Process
Teams Evaluated Against each other Highest evaluated team receives
maximum points for evaluation criteria Lesser teams receive scores in relation
to the highest ranked team Consensus Scoring preferredLimited Number of pages: 8 ½”X11”Approximately 9 week process – RFQ to Announcement (6week prep / 3week evaluation)
23
Alternative Technical Concepts Change which provides a solution
that is equal to or better than what is required by the scope as determined by the Department.
Shortlisted potential DBTs only. Allows for innovation, increased
flexibility, time reductions and cost savings to ultimately obtain the best value for the public.
24
ATCs Continued
Not intended to replace prebid questions
No new Design Exceptions No additional R/W acquisition No modifications to the IMS No NEPA Impacts
Pre-ATC meetings If held, non-binding and for information
only 25
ATCs Continued
Core group of ATC evaluators assisted by any number of technical specialists.
Responses: Approve Approve with conditions Reject Reject, may resubmit Not an ATC (should be a prebid)
26
ATCs Continued
If, during evaluation of an ATC proposal, the Department becomes aware of a deficiency in the Project Scope that would have an impact on the ability of the DBTs to make a best offer, the Department may, at its discretion, issue an addenda to correct this deficiency. For example - conflicts between sections
in the scope. 27
ATCs Continued
Ultimate Result: Contractor Specific final Scope of Services Inclusion within the Price
Potential for winning bidder to incorporate via change order
Approximately 10weeks from Shortlist to Final ATC response. Price approx 5weeks later.
15Weeks from Shortlist to Sale
Post Award
After award, all information (with the exception of true trade secrets) will be made public.
This includes: SOQs ATCs Scoring and Evaluation Information,
include evaluators comments
29
Stipend
Payment for Preparation of Responsive Preliminary Design Concept
Controlling Board Approval Allows ODOT to use DBTs ideas DBT does not have to accept
Size of Stipend should equal the amount of effort requested (Policy: 1/4% - 1% of estimate) 30
Questions
31