Upload
esmond-matthews
View
216
Download
1
Tags:
Embed Size (px)
Citation preview
1
Contractual Risk Allocation Provisions
Presented by:
Rolly Chambers & Gene Rash
Smith, Currie & Hancock, LLP
March 5, 2013
22
Presenter Biographies• Gene Rash and Rolly Chambers
– Partners in Charlotte, NC office of Smith Currie & Hancock, LLP
• Smith Currie & Hancock, LLP (http://www.smithcurrie.com)– 60 attorneys devoted exclusively to construction and
government contracts– Focus on construction business legal matters– Offices in Atlanta, Charlotte, Ft. Lauderdale, San
Francisco & Washington, D.C.
33
Risk-Shifting Provisions
• What will we cover?– Differing Site Conditions & Site Inspection
Provisions– Delays and No-Damage-For-Delay Clauses – Indemnity Provisions– Disclaimers of Implied Warranty of Plans & Specs– Green Warranties
44
Risk-Shifting Provisions
• Why be concerned? – Clients might not account for them because they
may:• Overlook them in the rush of bidding• Misunderstand or misinterpret them• Believe them to be unenforceable• Not willing to risk losing the contract
– You can help with knowledge and expectations
55
Differing Site Conditions
• What is a differing site condition? – A physical condition– Encountered during the work– Not known when contract was formed– Materially different from the condition believed to
exist when bid was prepared
66
Differing Site Conditions
• What is a differing site condition?– Not readily apparent, hidden from view
• Examples:– Poor soils– Concealed Rock– Unknown subsurface piping– Unanticipated groundwater
77
Differing Site Conditions
• Who bears the risk?– The General Common Law Rule: contractor bears
risks associated with his performance – The general rule creates problems:
• If GC bears all risk, GC must account for an unknown• Owner may overpay if GC includes a large contingency• If contingency was too small, GC incurs a loss
88
Differing Site Conditions
• The Solution – changed conditions clause– Shifts at least some risk to owner for changed
(differing) site conditions– The shifted risks depend on the clause itself– May limit the types of conditions covered– May limit categories of costs recoverable
99
Differing Site Conditions
• Changed Conditions Clauses:– Type I changed condition is a condition materially
different from those indicated in the contract documents (FAR 52.236.2; p. 257 of CSCL)• Need to have some representation indicated in the
contract documents regarding the condition at issue
1010
Differing Site Conditions
• Type II changed condition is:• an unknown physical condition at the site, • of an unusual nature, • which differs materially from those ordinarily
encountered and recognized as inherent in work of the character provided for in the contract
1111
Differing Site Conditions
• Type 1 Changed Condition Recovery:– Certain conditions indicated by contract docs– Contractor relied on those physical conditions– Nature of conditions encountered was materially
different from what was indicated– Proper notice given– Additional costs or time incurred
1212
Differing Site Conditions
• Type II Changed Condition Recovery– Conditions encountered were:
• Unusual & Materially different from those anticipated given–The locale–The nature of the work
• Notice + Damages• Totality of the circumstances analysis
1313
Differing Site Conditions
• Obstacles to Recovery– Site investigation provisions– Exculpatory Clauses
• Disclaiming liability for accuracy of contract docs
– Notice requirements– No Changed Conditions Clause
1414
Differing Site Conditions
• In the absence of a Changed Conditions clause:– Misrepresentation?– Mutual mistake?– Does Spearin doctrine apply?
1515
Spearin Doctrine
• What is it?– Party furnishing design impliedly warrants its
adequacy and sufficiency
• Shield/Sword– Defensive use – if Contractor complies with design– Offensive use – for additional costs/time
1616
Spearin Doctrine
• Chipping away at Spearin– Site inspection provisions– Require Contractor review/verification of
plans/specs– Express disclaimers– Design/Build– Performance specifications
1717
Delay Issues
• Delays are a major source of disputes• Understanding delay analysis:
– Excusable delays– Nonexcusable delays
• Excusable – depends on contract terms– Fault of owner or its agent– Not contractor's (or its subcontractors’) fault and
recognized by contract terms as excusable
1818
Delay Issues
• Excusable delay examples:– Design errors– Owner’s failure to provide site access– Owner’s interference– Unusual Weather?
• Nonexcusable means no right to additional time or money
1919
Delay Issues
• Excusable delays may be:– Compensable or Non-compensable
• Compensable:– Delay is fault of owner or its agent– Contractor entitled to time and money so long as
contract provisions do not shift risk to Contractor
2020
Delay Issues
• Non-compensable but excusable– Usually not owner’s fault (unless risk shifting
clause renders an owner caused delay non-compensable)
– Not contractor’s fault– Contractor entitled to an extension of time, but no
additional monetary compensation
2121
Delay Issues
• Multiple, overlapping delays?– Considered “concurrent delays” if excusable and
non-excusable delays occur in the same timeframe– Traditional rule is neither party bears responsibility– Modern trend is to attempt to apportion
responsibility if possible
2222
Delay Issues
• Delay Risk Shifting – The No-Damage-For-Delay provision– Common in prime and sub contracts– Generally enforceable– Exceptions to enforceability vary by jurisdiction
2323
Delay Issues
• Exceptions to enforceability of NDFD clause– Varies by jurisdiction– Fraud or misrepresentation– Active interference– So unreasonably long as to justify abandonment– Gross negligence– Not contemplated by the parties– Might be drafted in violation of anti pay-if-paid
statutes
2424
Indemnification Issues
• Contractual Indemnity Agreements– Promise by indemnitor to hold harmless another
for certain future losses, liabilities or damages. – Indemnitor does not have to be at fault– Heavily favors party with greater bargaining power– Potential for substantial liability
2525
Indemnification Issues
• Contractual Indemnity Agreements– Strictly construed by most courts– Some states have statutory limitations such as:
• Sole negligence of indemnitee• Partial negligence of indemnitee (less common)
– Prefer provisions with comparative negligence
2626
Warranty Issues
• Surety’s potential warranty liability– Performance issue, or– Material defect warranty (sealants, roofing….)
• Green issues:– 3rd party certification (USGBC/GBCI re: LEED)– Performance requirements mandating specific
energy reductions
2727
Warranty Issues
• Design/Build or performance based solicitation with extended energy reduction warranty obligation– Ripe for claims– Is the risk too high?
2828
Contractual Risk Allocation Provisions
QUESTIONS?If you do not have the opportunity to have your question addressed during the session, you may contact the presenters directly:
Gene Rash & Rolly ChambersCompany: Smith, Currie & Hancock, LLPPhone: 704-334-3459Email: [email protected]: [email protected]: 1023 W. Morehead St., Suite 301
Charlotte, NC 28208