1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION

1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

Embed Size (px)

Citation preview

Page 1: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

1

BUYING LIGHTNING DATA

LESSONS LEARNED

AND

FUTURE CHALLENGES

TO AVOID ANTI-DEFICIENCY

DAN CLEVER

DIRECTOR

NWS ACQUISITION DIVISION

6/15/05

Page 2: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

2

PURPOSE

1. To provide acquisition support to NWS by acquiring lightning data for use by NOAA and other government agencies.

2. To provide an update of the status of our current Lightning Data contract.

3. To ensure that our contracts are in compliance with all applicable laws and regulations.

Page 3: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

3

DEFINITIONS

• Incremental Funding:

The provision or recording of budgetary resources for a program or project based on obligations estimated to be incurred within a fiscal year when such budgetary resources will not cover all the program’s or project’s obligations. Contracts that cannot be separated for performance by fiscal year may not be funded on an incremental basis without statutory authority.

-GAO Accounting and Financial Management Division

Page 4: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

4

DEFINITIONS

• Full Funding:

The provision of budgetary resources to cover the total estimated cost of a program or project at the time it is undertaken (regardless of when the funds will actually be obligated).

-GAO Accounting and Financial Management Division

Page 5: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

5

Applicable Laws & Regulations

• The Anti-Deficiency Act (31 U.S.C. 1341)

• Adequacy of Appropriations Act (41 U.S.C. 11)

• Preparation, Submission and Execution of the Budget

(OMB Circular A-11)

• Federal Acquisition Regulation (FAR) Subpart 32.7

• Applicable Agency Guidance

Page 6: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

6

The Problem

The practice of incrementally funding our Lightning Data contracts is placing NWS at risk of violating federal statutes. It is also preventing us from paying the contractor in a timely manner.

Page 7: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

7

Why Is Incremental Funding

A Problem?

While ample guidance exists for the incremental funding of cost-type contracts, there is no specific statutory, regulatory, or agency guidance authorizing the application of this budgetary practice to Fixed Price contracts.

Page 8: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

8

What Does the Law Say?

The Anti-Deficiency Act (ADA) tells us that:

“An officer or employee may not make or authorize an obligation or expenditure that exceeds an amount available in an appropriation or fund.”

Page 9: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

9

What Does the Law Say?

The Adequacy of Appropriations Act tells us that:

“No contract or purchase on behalf of the United States shall be made, unless the same is authorized by law or is under an appropriation adequate to its fulfillment.”

Page 10: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

10

What Does the FAR Say?

FAR Subpart 32.702 tells us that:

Before executing any contract, the Contracting Officer shall –

Obtain written assurance from responsible fiscal authority that adequate funds are available

or Expressly condition the contract upon availability of funds in accordance

with FAR 32.703-2

(Only for Operations and Maintenance, Continuing Services and non-stock funded Supplies, which are necessary for normal operations, and for which Congress has consistently appropriated funds).

Page 11: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

11

SO HOW DO WE FUND OUR LIGHTNING DATA CONTRACTS

AND STAY WITHIN OUR BUDGETARY CONSTRAINTS?

1. Plan ahead. Send NWS AD your FULLY FUNDED Procurement Request before your current Contract/Delivery Order expires.

2. Ensure that your Budget Office programs all of your Lightning Data Contract funding for NWS obligation early in the new FY.

Page 12: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

12

- SO WHAT IF I CAN’T GET ALL OF MY AGENCY’S LDP FUNDING AT

ONCE?

Fund “Stand-Alone Stages” of the contract or project.Project Managers should request NWS AD procure Lightning Data for their agency for just that time period that they have $$ for. We can procure the project in smaller “pieces”, depending on funds availability.

Additional “pieces”, comprising the remainder of the performance period, can be included in the contract as options, and funded later, if funds become available.

Employing this technique, we are fully funding each segment, as funds become available to us.

Page 13: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

13

A “STAND-ALONE STAGE” IS:

A component of a project that:

• Provides information which allows for planning, design, and assessment of costs, benefits, and risks of a potential acquisition

OR

• Results in a usable asset for which the benefits exceed the costs even if no further funding is provided

Page 14: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

14

When is Incremental Funding OK?

R&D High Technology Acquisitions Program Funded Incrementally by Congress Hazardous/Toxic Waste Remediation Multi-Year Contracting Cost-Type Contracts

Page 15: 1 BUYING LIGHTNING DATA LESSONS LEARNED AND FUTURE CHALLENGES TO AVOID ANTI-DEFICIENCY DAN CLEVER DIRECTOR NWS ACQUISITION DIVISION 6/15/05

15

RECOMMENDATIONS

Our current practice of incrementally funding our fixed price Lightning Data contract and Delivery Orders places us at risk of violating the Anti-Deficiency Act.

To avoid this, and still acquire the services we need, we must plan ahead, and award contracts and Delivery Orders which obligate only those funds which are made available to us. The contractor CANNOT be required to provide data unless they have been awarded a Delivery Order for it. NWS AD will no longer write these D.O.s without funding from the agencies who will be receiving the data.

We should consider re-writing the Interagency Agreements between NOAA/NWS and the other Government Agencies to clarify our funding requirements.

We should seek additional obligation authority to fully fund acquisitions which cannot reasonably be subdivided into smaller stand-alone stages.