1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

Embed Size (px)

Citation preview

Page 1: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

1 BROOKHAVEN SCIENCE ASSOCIATES

Presentation to ASAC

R. Casey

Radiation Shielding: Assumption and Design

April 24, 2007

Page 2: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

2 BROOKHAVEN SCIENCE ASSOCIATES

Preliminary Shielding Design Documents for NSLS II

1. Linac, NSLS II- TN 122. Booster & Storage Ring, NSLS II – TN 133. Storage Ring Supplemental Shielding – TN 214. Beamlines and Front Ends, NSLS II – TN 145. Ray Tracing Standards, NSLS II – TN 206. Activation Analysis, NSLS II – TN 15 & 16

Page 3: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

3 BROOKHAVEN SCIENCE ASSOCIATES

Radiation Safety Workshop was Recently Conducted

• March 27 – 28, 2007

• Membership• S. Rokni (Chair) – SLAC• R. Donahue – ALS• P. Berkvens – ESRF• D. Beavis – BNL• C. Schaefer - BNL

Page 4: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

4 BROOKHAVEN SCIENCE ASSOCIATES

Rad Safety Workshop

• Committee reviewed:• Shielding methodology & assumptions• Interlocks, Critical Devices, and Area Radiation Monitoring

plans.

• Committee concluded:

“Given the status of the project, the design of the bulk shielding of the accelerator complex is well developed and is based on sound principles and reasonable assumptions. “

Page 5: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

5 BROOKHAVEN SCIENCE ASSOCIATES

Desired Shielding Outcome

• Compliance with DOE Orders, Part 835, and BNL Administrative Controls

• < 25 mRem/year (.25 mSv) on-site to non-NSLS-II personnel; < 5 mrem/year (0.05 mSv) at site boundary

• Radiation exposure to users and staff ALARA – an administrative control level of 100 mRem/year (1 mSv) is desired

• We plan to achieve this through shielding and engineering controls; & supplemental administrative controls

• Based on current experience, we expect annual radiation exposures < < 100 mRem/year (1 mSv) to NSLS staff and users

• After verification, we expect short-term visitors will not be required to have dosimeters routinely

Page 6: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

6 BROOKHAVEN SCIENCE ASSOCIATES

Shielding Policy

• Accelerator and beam line enclosures will be shielded to reduce exposure at the exterior surface of the shield during typical operation to 0.25 mRem/hr (2.5 uSv) in normally occupied areas to limit the maximum exposure to 500 mrem/year (5 mSv) (assuming 2000 hours occupancy).

• The storage ring outer wall will be shielded to 0.5 mRem/hr (5 uSv/hr) in direct contact with exterior; no full-time occupancy is expected or will be permitted within 1 meter of wall.

• This policy satisfies DOE Design Goals identified in 10 CFR 835.1002

Page 7: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

7 BROOKHAVEN SCIENCE ASSOCIATES

Shielding Policy (cont.)

• Shielding calculations will use conservative source terms and attenuation factors

• Abnormal operating conditions, including Maximum Credible Incidents (MCI), will be evaluated

• Additional engineering or administrative controls will be specified based on severity of radiation levels under fault or non-typical conditions.

• Shielding and controls are considered adequate if MCI has low potential for exceeding 100 mRem (1 mSv) and can not exceed 2000 mRem (20 mSv)

Page 8: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

8 BROOKHAVEN SCIENCE ASSOCIATES

Shielding Policy (cont.)

Engineering control options include:• Additional shielding (e.g. shadow shields, localized shields)• Beam loss monitors with alarm in control room and (perhaps)

interlock function• Beam current monitors with alarm in control room and

(perhaps) interlock function• Area radiation monitors at the occupied areas with alarm

locally and in control room and interlock function

Page 9: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

9 BROOKHAVEN SCIENCE ASSOCIATES

Shielding Policy (cont.)

Supplemental Administrative control options include:• Operational procedures for operators and ESH staff

during injection and routine operations • Commissioning and shielding verification procedures• Shielding configuration control• Review of accelerator and beam design modifications• Survey and posting procedures• Passive area monitors

Page 10: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

10 BROOKHAVEN SCIENCE ASSOCIATES

Bulk Shielding Calculation Methodology

Page 11: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

11 BROOKHAVEN SCIENCE ASSOCIATES

Radiation Dose Equivalent Factors at 900

(comparison)

Radiation Component

Dose equivalent factors(mrem.m2/J)

(Swanson)

Dose equivalent factors(mrem.m2/J)(Sullivan)

Dose equivalent factors(mrem.m2/J)(Shield 11)

Bremsstrahlung 2.80 1.39 1.12

Giant Resonance Neutrons

0.63 0.27 0.257

High Energy Neutrons

0.075 0.043 0.068

Page 12: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

12 BROOKHAVEN SCIENCE ASSOCIATES

Radiation Attenuation FactorsUsed in Calculations

Page 13: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

13 BROOKHAVEN SCIENCE ASSOCIATES

Accelerator Operating Conditions used in Calculations

• Linac• 200 MeV• 20 nC/pulse• I hz operation

• Booster• 3.6 GeV• 15 nC per pulse• 1 pulse / minute (typical operation) • 1 hz operation for 500 hours per year considered

• Storage Ring• 3.6 GeV• 500 mA

Page 14: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

14 BROOKHAVEN SCIENCE ASSOCIATES

Beam Loss Assumptions for Normal Operations

• Linac – 1% distributed loss at 200 MeV

• Linac to Booster injection efficiency – 50%

• Booster losses – 2% loss at any point at 3.6 GeV

• Booster to storage ring injection efficiency – 80%

• Non-injection region – 10% of stored beam losses at any point

• Stops in linac and booster designed for 100% loss at 1 hz

Page 15: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

15 BROOKHAVEN SCIENCE ASSOCIATES

LINAC Bulk Shielding Estimates

Page 16: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

16 BROOKHAVEN SCIENCE ASSOCIATES

Booster Bulk Shielding Estimates1

Inboard wall(cm)

Outboard wall(cm)

Roof(cm)

Booster Injection Region2

108 108 98

BoosterNon-injection Region

95 95 80

1 The Inboard and Outboard walls are at 1 m and the roof at 2 m from the beam2 Supplemental lead shielding will be required around injection septum for 1 hz operation

Booster shielding still in progress as adjacent occupancies are under discussion.

Page 17: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

17 BROOKHAVEN SCIENCE ASSOCIATES

Storage Ring Bulk Shielding Estimates

Page 18: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

18 BROOKHAVEN SCIENCE ASSOCIATES

LINAC - Credible Radiation Incidents

• 100 % of maximum accelerated beam is lost at some location in the linac enclosure, (20 nC/s is continuously lost)

Dose Rate = 37.5 mRem/h (0.37 mSv/h) (at the exterior of shield on contact)

• 100 % injected beam to the booster is continuously lost at the linac-booster injection septum at 1 Hz.

Dose Rate = 30 mRem/h (0.3 mSv/h)

Mitigation/ control to prevent significant exposure• Area Radiation Monitors with beam shut off capability• Beam current monitors in the LINAC• Additional supplementary shielding at the septum/stop (lead/poly)• Operating procedures for operators during injection

Page 19: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

19 BROOKHAVEN SCIENCE ASSOCIATES

Storage Ring (Credible Radiation Incidents)

• 100 % injected beam from the booster to storage ring is lost at any location in the storage ring (15 nC/s is continuously lost at some location other than injection region)

Dose Rate = 300 mRem/h (3 mSv/h) (at the exterior of the experimental floor wall on contact)

• 100 % injected beam from the booster to storage ring is lost at any beamline front end due the shorting of a bending magnet (15 nC/s is continuously lost at a front end component)

Dose Rate = ~ 500 mRem/h (5 mSv/h) (at the exterior of the ratchet wall ~ 0.5 m from the FE) (peak bremsstrahlung shielded with shadow shields)

• 100% of stored beam is lost at a point - ~ 8 mRem (0.08 mSv)

Mitigation/controls to prevent significant exposure

• Area Radiation Monitors with beam shut off capability• Beam loss monitors inside the Storage Ring• Additional Supplementary Shielding (Shadow Shields)• Operating procedures for operators defining actions during injection

Page 20: 1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007

20 BROOKHAVEN SCIENCE ASSOCIATES

Bulk Shielding Comparison

Bulk Shield at Experimental Floor Side

020406080

100120140

SOLEIL

DIAM

ONDAPS

BESSYII

ELETTRA

SPRING8

ESRF

NSLSII

Concrete

HD Concrete