1 BROOKHAVEN SCIENCE ASSOCIATES

Insertion Device Status

Toshi Tanabe, ID Group Leader9th Accelerator Systems Advisory Committee Meeting

February 1-2, 2012

Page 2: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

2 BROOKHAVEN SCIENCE ASSOCIATES

Outline

• ID Table / Current Schedule • Progress since last ASAC review • Status on Each Device• R & D (IVMMS, VST, PrFeB) Progress• Summary

Acknowledgement:

ID group members: C. Kitegi, J. Rank, D.A. Harder, T. Corwin, P. Cappadoro, H. Fernandes, C. Rhein, B. Licciardi, P. He,

G. Rakowsky, M. Lehecka

Part-time members: O. Chubar, C. Spataro,

Accelerator Physics: J. Bengtsson, S. Krinsky, A. Blednykh, P. Ilinsky, Y. Li

Vacuum Group: Dick Hseuh, Charles Hetzel

Mechanical Group: V. Ravindranath

Page 3: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

3 BROOKHAVEN SCIENCE ASSOCIATES

NSLS-II Insertion Devices (Baseline Project Scope)

Name U20 U22(IXS) EU49 U21(SRX) DW-1.8T 3PW

Type IVU IVU EPU IVU PMW PMW

Photon energy range Hard x-ray (1.9-20keV)

Hard x-ray (9.1keV)

Soft x-ray (250eV-1.7keV)

Hard x-ray (1.9-20keV)

Broad band

(<10eV-100keV)

Broad band

(<10eV-100keV)

Type of straight section Short Long Short

(canted) Short

(canted) Long

(in-line) near 2nd Dipole

Period length (mm) 20 22 49 21 100 -

Length (m) & Number of Devices 3.0 x 2 3.0 2.0 x 2 1.5 3. 5 x 6 0.25

Number of periods 148 135 36 x 2 69 34 x 2 0.5

Magnetic gap (mm) 5 7.4 11.5 6.2 15.0 28

Peak magnetic field strength B (T)

1.03 0.78

0.57(Heli) 0.94 (Lin) 0.72(vlin)

0.41 (45°) 0.9 1.80 1.14

Keff

1.81 1.52

2.6(Heli) 4.3 (Lin) 3.2(vlin)

1.8 (45°) 1.79 18.0 -

h fundamental, eV

1620 1802 230 (Heli) 180 (Lin) 285(vlin)

400 (45°)

1570

h critical, keV 10.7 6.8

Total power (kW) 8.0 4.7 8.8 3.6 64.5 0.32

Page 4: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

4 BROOKHAVEN SCIENCE ASSOCIATES

DW, EPU and 3PW Schedules

Activity Name Dur Start Finish Dur

Damping Wiggler 1142 1-Oct-07 9-Jan-14 DW Design 249 1-Oct-07 31-Aug-09Prepare DW Procurement 42 1-Apr-09 15-Mar-10DW Procurement 15 15-Mar-10 7-Nov-10DW Contract Award 2 7-Nov-10 9-Nov-10DW Fabrication & Assembly 400 10-Nov-10 11-Jan-13DW Measurement & Correction 120 24-Aug-12 16-Mar-13DW - FLOAT 207 16-Mar-13 9-Oct-13DW Installation & Int. Testing 9-Oct-13 9-Jan-14

Jan-11 Jan-12 Jan-13 Jan-14

Damping Wiggler DW Design

Prepare DW ProcurementDW Procurement

DW Contract AwardDW Fabrication & Assembly

DW Measurement & CorrectionDW - FLOAT

DW Installation & Int. Testing IVU-20EPU 1615 1-Oct-07 9-Dec-13

EPU - Conceptual Design 125 1-Oct-07 29-Aug-08EPU - Magnetic Design 60 29-Aug-08 2-Feb-09EPU - Reference Design 249 2-Feb-09 11-May-10EPU - Prepare Procurement 42 13-May-10 29-Oct-10EPU - Procurement 70 30-Oct-10 26-Apr-11EPU - Contract Award 2 26-Apr-11 28-Apr-11EPU - Vendor Fabrication 650 29-Apr-11 7-Feb-13EPU - Measurement & Correction 90 17-Feb-13 18-May-13EPU FLOAT 145 18-May-13 10-Oct-13EPU Installation & Int. Testing 43 10-Oct-13 9-Dec-133-Pole Wiggler 1-Oct-07 20-Apr-133-Pole Wiggler - Design 360 1-Oct-07 1-Oct-093-Pole Wiggler - Write Specs & SOW 40 1-Oct-09 1-Dec-103-Pole Wiggler - Procurement 112 2-Dec-10 24-Mar-113-Pole Wiggler - Contract Award 2 26-Mar-11 28-Mar-113-Pole Wiggler - Vendor Fabrication 450 29-Mar-11 21-Jun-123-Pole Wiggler - Measurement 20 1-Jul-12 29-Jul-123-Pole Wiggler - Float 189 29-Jul-12 20-Apr-13

3-Pole Wiggler - Installation 15 5-Apr-13 20-Apr-13

EPUEPU - Conceptual Design

EPU - Magnetic DesignEPU - Reference Design

EPU - Prepare ProcurementEPU - Procurement

EPU - Contract AwardEPU - Vendor Fabrication

EPU - Measurement & CorrectionEPU FLOAT

EPU Installation & Int. Testing3-Pole Wiggler

3-Pole Wiggler - Design3-Pole Wiggler - Write Specs & SOW

3-Pole Wiggler - Procurement3-Pole Wiggler - Contract Award

3-Pole Wiggler - Vendor Fabrication3-Pole Wiggler - Measurement

3-Pole Wiggler - Float3-Pole Wiggler - Installation

Page 5: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

5 BROOKHAVEN SCIENCE ASSOCIATES

IVU (U20, U21 for SRX, U22L for IXS ) Schedules

Activity Name Dur Start Finish Dur Jan-11 Jan-12 Jan-13 Jan-14

Damping Wiggler IVU-20 1261 1-Oct-07 9-Jan-14IVU-20 Design 1033 1-Oct-07 30-Jul-10IVU-20 Prepare Procurements 230 8-Feb-10 29-Apr-11IVU-20 Procurement 70 2-May-11 21-Nov-11IVU-20 Contract Award 29 21-Nov-11 20-Dec-11IVU-20 Vendor Fabrication 500 21-Dec-11 4-May-13IVU-20 Measurement & Correction 60 14-Apr-13 13-Jun-13IVU-20 FLOAT 118 13-Jun-13 9-Oct-13IVU-20 Installation & Int. Testing 66 9-Oct-13 9-Jan-14IVU21 (SRX) 1124 3-Aug-09 24-Nov-13IVU21 - Design & Prepare Procurements 300 3-Aug-09 29-Apr-11IVU21 - Procurement 203 2-May-11 21-Nov-11IVU21 - Contract Award 29 21-Nov-11 20-Dec-11IVU21- Vendor Fabrication 465 21-Dec-11 30-Mar-13IVU21 - Measurement & Correction 30 9-Apr-13 9-May-13IVU21 FLOAT 30 9-May-13 25-Oct-13IVU21 - Installation & Integrated Testing 30 25-Oct-13 24-Nov-13IVU22 (IXS) 835 13-Oct-10 25-Dec-13IVU21 - Design & Prepare Procurements 300 13-Oct-10 1-Aug-11IVU21 - Procurement 60 4-Aug-11 3-Oct-11IVU21 - Contract Award 2 3-Oct-11 31-Mar-12IVU21- Vendor Fabrication 465 1-Apr-12 10-Jul-13IVU21 - Measurement & Correction 30 20-Jul-13 19-Aug-13IVU21 FLOAT 98 19-Aug-13 25-Nov-13IVU21 - Installation 30 25-Nov-13 25-Dec-13

IVU-20IVU-20 Design

IVU-20 Prepare ProcurementsIVU-20 Procurement

IVU-20 Contract AwardIVU-20 Vendor Fabrication

IVU-20 Measurement & CorrectionIVU-20 FLOAT

IVU-20 Installation & Int. TestingIVU21 (SRX)

IVU21 - Design & Prepare ProcurementsIVU21 - Procurement

IVU21 - Contract AwardIVU21- Vendor Fabrication

IVU21 - Measurement & CorrectionIVU21 FLOAT

IVU21 - Installation & Integrated TestingIVU22 (IXS)

IVU21 - Design & Prepare ProcurementsIVU21 - Procurement

IVU21 - Contract AwardIVU21- Vendor Fabrication

IVU21 - Measurement & CorrectionIVU21 FLOAT

IVU21 - Installation

Page 6: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

6 BROOKHAVEN SCIENCE ASSOCIATES

Progress since Last ASAC (May2011)

• Status of Each Baseline DevicePM Damping Wiggler (Six DWs)

FDR completed on June 7th, 2011. Control system prototype complete. Mechanical systems will be factory-tested by mid Feb. 2012.

In-Vacuum Undulators (U21 for SRX with options for two more & two U20) Both contracts were signed on Dec. 20th, 2011. CDR is scheduled on Jan.30th , 2012.

In-Vacuum Undulator (U22L for IXS) The dead line for the proposals was January 25th, 2012.

Elliptically Polarized Undulator (CSX-EPU) PDR completed in Oct. 2011. FDR is scheduled in Feb. 2012.

Three Pole Wiggler (3PW) FDR completed in June 2011. Design change of magnets resulted in delay.

Magnet Development Laboratory (Insertion Device Magnet Measurement Facility) The facility is ready for operation

Page 7: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

7 BROOKHAVEN SCIENCE ASSOCIATES

Damping Wiggler Status (Danfysik)

• Prototype of Mechanical Drive System has been tested successfully.• Construction continues on Structural Frames and Magnet Girders [60%].• Machining of Magnet Assembly parts and other special tooling has begun [15%].• Permanent Magnets order (Vacuumschmelze) part 1/3 is due next month. • Control scheme & rack layouts are developed; assembly continues. Subcontractor

needs to set up the proper BNL rack layouts (heat loads, internal fans, flow direction, ampacity). [80%]

• PDR completed on Jan. 10th for the contract for the Vacuum Chamber (FMB-Berlin) and supports. [25%]

Page 8: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

8 BROOKHAVEN SCIENCE ASSOCIATES

DWs: Structural Frames & Magnet Girders Machining and Fabrication by Nortemecánica

Page 9: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

9 BROOKHAVEN SCIENCE ASSOCIATES

DW Chamber Preliminary Design by FMB

Page 10: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

10 BROOKHAVEN SCIENCE ASSOCIATES

Damping Wigglers (6 x DW) Top Level Schedule

Page 11: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

11 BROOKHAVEN SCIENCE ASSOCIATES

EPU Status

• FDR scheduled in February 2012• Since PDR (October 2011) slight mechanical changes to

align the gap drive system along the vertical forces, which has resulted in two months delay.

• A separate RFP for its vacuum chamber has been issued.• Permanent magnets by Neomax have been shipped.

Courtesy of Kyma UndulatorTop Level Schedule

Page 12: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

12 BROOKHAVEN SCIENCE ASSOCIATES

EPU Vacuum Chamber Details

Page 13: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

13 BROOKHAVEN SCIENCE ASSOCIATES

SRP Requirement for ID Vacuum Chambers

Mis-steered E-beam

• “Steady State” Cases within Interlock limit• “Transient Cases” with possible maximum beam angle

Page 14: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

14 BROOKHAVEN SCIENCE ASSOCIATES

Ex. for a “Transient Case” Linear Horizontal ModeSr. NO ID Mode Source Element Element

Length (m)

Element misalignment(upstream)

Element misalignment(downstream)

Case Beam (translate

Beam(angle)(mrad)

Peak Temperature(Degree C)

Peak Power Density(W/mm2)

Power(Watts)

3 LH 2XEPU49

EPU Vac. Ch.

5 -1.5 -1.5 Transient 0 1.6 1367.2 46 5044

10msec

1msec

Page 15: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

15 BROOKHAVEN SCIENCE ASSOCIATES

3PW-Major Change (Nov/2011)

New dimensions of magnets and poles:

Main pole: 110mm x 23mm x 67mm (120mm x 23mm x 65mm/old dimensions) End pole: 90mm x 45mm x 82mm (101mm x 45mm x 86mm/old dimensions)

Main magnet: 150mm x 28.9mm x 100mm (120mm x 41mm x 90mm/old dimensions)

• New 3PW model

• The contract was originaly issued with 3,5 and 10 device options.• The manufacturer underestimated the price of magnets ($20,000 for

ten magnets in their estimate v.s. $150,000 in reality).• Instead of paying $130,000 extra, we have decided to use excess

magnets from DW contract and redesign the structure. • Slight cost addition for the design change (< $10k).

Page 16: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

16 BROOKHAVEN SCIENCE ASSOCIATES

IVU Status

• U21-1.5m for SRX (Hitachi Metal, USA) : • The original contract was signed by BNL on 11/21/2011• The final contract was signed by Hitachi Metal, USA on 12/20/2011• Options for two more identical (slight period change inclusive) devices, one set of

prices within 60 days from the start of the base contract, another set within 180 days.

• CDR was scheduled on January 31st , 2012.

• U20-3m (Hitach Metal, USA) : • The original contract was signed by BNL on 11/21/2011• The final contract was signed by Hitachi Metal, USA on 12/20/2011• CDR was scheduled on January 31st , 2012.

• U22L-3m for IXS (No source determined yet)• The proposal deadline was January 25th, 2012.• No options are included.

Page 17: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

17 BROOKHAVEN SCIENCE ASSOCIATES

ID-Magnetic Measurement Facility (MMF)

• Hall probe bench ready• Flip Coil system ready• RT-Calibration Dipole ready

(Cold version being prepared)• Helmholz Coil System ready

Calibration Dipole System

Hall Probe bench and Flip Coil system

Helmholz Coil System

Page 18: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

18 BROOKHAVEN SCIENCE ASSOCIATES

In-Vacuum Magnetic Measurement System (IVMMS)

• IVMMS contract with Toyama, Inc. , Japan)• Linear motor based design has

been adopted.• Various vacuum lubricants have

been tested without much success.• Next one to try is CVD coating of

MoS2 on balls for ball bearings.

• FDR is scheduled on Feb. 7th, 2012

• Test to measure the field of the SRX-IVU in vacuum will take place at the Neomax Engineering factory around October 2012.

Page 19: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

19 BROOKHAVEN SCIENCE ASSOCIATES

Vacuum Seal Test

• 4m long rectangular opening

• Two baking tests have been conducted with leak rate less than 1E-9 torr/l (Success)

• Leak starts after the third thermal cycle.

Page 20: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

20 BROOKHAVEN SCIENCE ASSOCIATES

Low temperature M-H measurement of High Coercivity PrFeB magnets at the Louis Néel laboratory

• An efficient 8 T extraction vector magnetometer with sample rotation for routine operation,

• D. Dufeu, E. Eyraud, and P. Lethuillier REV. SCI INS. VOL 71, NB 2

Page 21: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

21 BROOKHAVEN SCIENCE ASSOCIATES

PrFeB Arrays Baking Test

• Baking test of PrFeB arrays (lu=17mm) with 47CR• Repeatability test with a few detachment / attachment of arrays to the frame

Negligible variations

• Baking test (up to 100C) Less than 0.2% p-p field decrease• Cold field measurement using VTF is planned next, then increase the baking

temperature for further test.

Page 22: 1 BROOKHAVEN SCIENCE ASSOCIATES Insertion Device Status Toshi Tanabe, ID Group Leader 9 th Accelerator Systems Advisory Committee Meeting February 1-2,

22 BROOKHAVEN SCIENCE ASSOCIATES

Summary

• IVU• U21 for SRX : Contract signed on 12/20/11, 60/180 day options for two additional

devices.• Two U20-3m: Contract signed on 12/20/11, No option included.• U22L-3m for IXS: Proposals were due on 01/25/12.

• EPU• Two months behind the schedule due to mechanical design changes.• A separate RFP for the vacuum chamber has been issued..

• Damping Wigglers• On (revised) schedule. Revision was necessary due to the delay in magnet

procurement by the vendor.

• 3PW• A revised design using excess DW magnets has been adopted.

• ID-MMF• Ready for operation