Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
1. ANTICIPATED CAPACITY – FS/SD
Title Name Minuteman HS
Occupy 2019 Fields Closing
out end of October 2021
Attleboro HS
Occupy Fall 2022
Demo/Fields Close out December
2023
Lowell HS Full
Occupy Fall 2026
Arlington HS
OccupyPh1: 2022Ph2: 2023 Ph3: 2024
Acton/ Boxborough
Occupy Fall 2022
Total commitment on non-MSBA
projects
Project at current OPM
Panel
NashobaFeasibility Study 20-24 Months
December 2023
Principal-in-Charge
Dale Caldwell N/A 5% 5% 5% 5% 10% 3%
Project Director
Mary Ann Williams 2% 25% 20% N/A N/A N/A 30%
Sr. ProjectManager Sy Nguyen 5% N/A N/A 65% N/A N/A 30%
Project Manager
Megan O'Connell N/A N/A N/A N/A N/A 80% 20%
Project Representative
Bob Charest
N/A 35% N/A N/A N/A City of Boston 60%
5%
Assist. Project Manager
Iryna Nos N/A N/A N/A N/A 70% N/A 30%
Please explain the anticipated capacity for the proposed project team, including commitments on other MSBA projects.
2. The Nashoba Regional School District, Nashoba Regional High School
Projected Project Timeline*
Forming the Project Team
Feasibility Study Schematic Design
Designer Selection
11/30 and 12/14/2021
Feasibility Study 20 – 24 Months
Schematic DesignDuration and Target
June 28, 2023
*All dates are tentative and subject to change based on district and MSBA schedules
MSBA Board Approval of
Proposed Project & issuing of the
Project Scope and Budget agreementTarget Board DateAugust 30, 2023
District approval &
votesFall 2023
Funding the Project
3. Discuss a recent MSBA project, similar in size and scope to the Nashoba Regional High School project, and review any particular challenges or lessons learned, and how they were managed. Please use the template slide titled “Project Update”, to summarize this information. Please provide one slide for each project you intend to discuss.
MSBA High School Experience: Skanska has served as the owner’s project manager for the following High School projects in Massachusetts:
Taconic High School Minuteman Regional Vocational High School Attleboro High School
3. Current Status for Minuteman RVTHS
Challenges Identified at the Panel:
Current Projected Project Timeline:Please gray out area already completed and identify current standing. Add dates, actual and anticipated, for the key activities noted below.
Forming the Project Team
Feasibility Study Schematic Design
Designer Selection11/15 and
11/30/2021
Schematic DesignDuration and Target
June 28, 2023
Updates to Project Include:
MSBA Board Approval of Proposed Project &
issuing of PSBAAugust 30, 2023
District approval & votesFall 2023
Appeared at December 2012, OPM Review Panel
Funding the Project
∙ Regional High School (Multi-community approval) ∙ Goals & Challenges for an innovational learning environment (CTE specialty spaces)∙ DESE early visits ∙ Community partnership
∙ Photovoltaics∙ Additional Fields
4. The OPM contract requires that the OPM assist the District to negotiate the fee for the designer. Please explain your firm’s negotiating strategy used in previous projects as well as the approach you would use for the District and note any detail that you require in order to finalize the fee.
∙ We review study requirements, scope and level of effort required. ∙ Ask for a workplan tied to a timeline and associated costs for activities required. ∙ Review the specialty and or sub-consultants required for a “true” Feasibility Study.∙ Complexity of project: site reviews, approvals, permitting, phasing, relocation of
utilities, constraints, etc. ∙ Track Design Fees from other projects for relative comparison
Please provide a list of each school project that you have worked on and provide the agreed upon fee for the basic services as a percentage of the construction project for each project listed.
5. What have been the effects of COVID on your projects and what approaches have you taken to overcome the challenges? ∙ Identify pandemic related bottlenecks – Develop COVID Work Plan and Budget∙ Preplanning for longer material lead times or Material/Labor shortages∙ Accelerated MEP coordination as to create more space for workers to spread out∙ Preparing for material lead times and supply chain delays∙ Review alternates∙ Local sourcing of materials
Discuss the steps your projects have taken to keep personnel safe and what delays or extensions your projects have experienced.∙ Develop Site-specific COVID Safety Plan (CDC/State/Federal/OSHA Guidance)∙ Site monitoring orientation, daily compliance, self-certification plan, etc.)∙ COVID Response Team in place/Mandatory Reporting∙ Notification of positive contact tracing system ∙ Developed COVID Strategy, risk assessment and mitigation plan to keep COVID
spread down on site and minimize worker to worker transmission∙ Proper PPE∙ Additional cleaning protocols
6. Describe the steps your firm has taken to meet minority and women workforce participation requirements for the Designer and the Contractor.
Agenda: Owner, CM, and Design Team engagement ∙ Project Advisory 66, January 2021
∙ Diversity Plan per M.G.L. c. 149, section 44A(2)(G) and Administration & Finance Administrative Bulletin (A&F 14)
∙ CM/GC Compliance Officer∙ RFS and Bid documents to include reference to goals for:
∙ MBE/WBE Firms (Percent of contract dollars)∙ Workforce Participation Goals (percent of hours not percent of workers)
Resources available: Unions/Building Pathways/PGTI
Tracking:∙ Checklists, Structure form and reporting process; Certified Payroll
Other Opportunities for increasing numbers and participation∙ CM – Certified Payroll and diverse workforce∙ Certified Payroll Outreach ∙ Subcontractors and 2nd Tier Subcontractor (Sub of Subs)∙ Outreach
6. What has been and is the track record for minority and women workforce participation on past and current projects?
Lowell High School:CM MBE Percentage 5% Actual Percentage 0.8%CM WBE Percentage 5% Actual Percentage 1.7%
CM Workforce Participation Minority Percentage 15.3%CM Workforce Participation Female Percentage 6.9%______________________________________________Attleboro High School:CM MBE Percentage 6.4% Actual Percentage 0.3%CM WBE Percentage 4% Actual Percentage 2.3%
CM Workforce Participation Minority Percentage 21.3%CM Workforce Participation Female Percentage 1.9%______________________________________________Arlington High School:CM MBE/WBC Percentage 10.4% CM MBE Actual Percentage 0.18%
CM WBE Actual Percentage 3.11%
CM Workforce Participation Minority Percentage 20.4%CM Workforce Participation Female Percentage 3.8%