3 [24-July-2013] [CMWG] «BE-RF-PM» TBM Prototype Summary Table 3 Component3d2dFabrication StatusScheduledExpected DB supporting system100% READY-- MB supporting system100% READY-- AS mock-up *100% BrazingJun-13Sep-13 PETS mock-up **100% BrazingJun-13Sep-13 RFN mock-up **100% BrazingJun-13Sep-13 VNW100% READY DBQs mock-ups100% READY DBQ supports100% READY Cooling tubes and fittings100% READY U-clamps100% READY Vacuum Pumpscommercial MODULE ASSEMBLY Jun-13Sep-13..Oct-13

Citation preview

Page 1: 1 [24-July-2013] [CMWG] «BE-RF-PM» CLIC TBM Prototypes Status EDMS №[Number] Dmitry Gudkov 1

1[24-July-2013] [CMWG] «BE-RF-PM»

CLIC TBM Prototypes Status

EDMS №[Number]

Dmitry Gudkov

1

Page 2: 1 [24-July-2013] [CMWG] «BE-RF-PM» CLIC TBM Prototypes Status EDMS №[Number] Dmitry Gudkov 1

2[24-July-2013] [CMWG] «BE-RF-PM» 2

Contents

1. TBM Prototype T0#2@LAB

2. TBM Prototype T1@LAB

3. TBM Prototype T0@CLEX

Page 3: 1 [24-July-2013] [CMWG] «BE-RF-PM» CLIC TBM Prototypes Status EDMS №[Number] Dmitry Gudkov 1

3[24-July-2013] [CMWG] «BE-RF-PM» 3

TBM Prototype T0#2@LAB. Summary Table

Component 3d 2d Fabrication Status Scheduled Expected DB supporting system 100% 100% READY - -MB supporting system 100% 100% READY - -AS mock-up * 100% 100% Brazing Jun-13 Sep-13PETS mock-up ** 100% 100% Brazing Jun-13 Sep-13RFN mock-up ** 100% 100% Brazing Jun-13 Sep-13VNW 100% 100% READY DBQs mock-ups 100% 100% READY DBQ supports 100% 100% READY Cooling tubes and fittings 100% 100% READY U-clamps 100% 100% READY Vacuum Pumps commercial commercial MODULE ASSEMBLY Jun-13 Sep-13..Oct-13

Page 4: 1 [24-July-2013] [CMWG] «BE-RF-PM» CLIC TBM Prototypes Status EDMS №[Number] Dmitry Gudkov 1

4[24-July-2013] [CMWG] «BE-RF-PM» 4

TBM Prototype T1@LAB. Summary TableComponent 3d 2d Fabrication Status Scheduled Expected Procurement/design resp.

DB supporting system (cradles) 100% 100% Production * Jun-13 Aug-13 H. Mainaud DurandMB supporting system (girder, cradles) 100% 100% Production Jul-13 Jul-13 H. Mainaud Durand/ N.

GazisClamping frames 0% 0% Design Dec-13 Nov-13 M. ShahAS mock-up 100% 100% Design updates Sep-13 Sep-13 I. KononenkoPETS mock-up 100% 100% Brazing Sep-13 Sep-13 N. Mouriz IrazabalRFN mock-up 100% 100% Parts production Sep-13 Sep-13 I. KononenkoInterconnection chain VACOM XS40 (x3) C C Ordered I. KononenkoInterconnection chain VACOM XS63 (x3) C C Ordered I. KononenkoCompact loads mock-ups 100% 100% Brazing Jul-13 Sep-13 I. KononenkoVNW 100% 100% Production Sep-13 Jul-13 C. GarionDBQs mock-ups 100% 100% READY M. ModenaDBQ supports 50% 0% design Nov-13 Nov-13 M. SosinCooling tubes and fittings 100% 95% design Dec-13 Dec-13 V. SoldatovVacuum Pumps (11 minipumps) C C To be ordered C. GarionDB BPM 100% 100% READY IFICDB BPM drift tubes 100% 100% Production Sep-13 Apr-13 C. GarionMBQ mock-up Nov-13 Nov-13 Kurt ArtoosMBQ BPM/Vacuum chamber READY Lars SobyMBQ support ST0441220_01 Nov-13 Nov-13 Kurt ArtoosASSEMBLY Dec-13 Dec-13

Page 5: 1 [24-July-2013] [CMWG] «BE-RF-PM» CLIC TBM Prototypes Status EDMS №[Number] Dmitry Gudkov 1

5[24-July-2013] [CMWG] «BE-RF-PM» 5

TBM@CLEX

Component 3d 2d Production Status Scheduled Expected Procur./design resp.Supporting system 100% 100% Production Jul-13 Jul-13 N. GazisClamping frames 50% 0% design Oct-13 Oct-13 M. ShahSAS 100% 100% Production See AnS See AnS A. SolodkoPETS#1 100% 100% READY, tested RF, Vacuum CIEMATPETS#2 100% 100% Production, 1st octant ready Sep-13 Oct-13 CIEMATRFN 100% 90% Design Oct-13 Oct-13 O. GumenyukRFN additional waveguides 100% 90% Design Oct-13 Oct-13 O. GumenyukVacuum Chamber (x2) 100% 100% Production Sep-13 Sep-13 C. GarionDBQs 100% 100% READY M. ModenaDBQ supports 50% 0% design Nov-13 Nov-13 M. SosinHigh-power loads supports 100% 0% To be inquired, Bosch Sep-13 Sep-13 I. KononenkoCooling tubes and fittings 80% 0% design Oct-13 Oct-13 V. SoldatovVacuum Pumps (10 minipumps) C C To be ordered Sep-13 Sep-13 C. GarionDB BPM 100% 20% Drawings Nov-13 Nov-13 V. SoldatovMB drift tubes 100% 100% Production Sep-13 Sep-13 C. GarionPETS CF63-35 Adapter Flange (4 pcs)

100% 100% To be produced Sep-13 Sep-13 C. Garion

Tee VACOM (2 pcs) C C To be ordered Sep-13 Sep-13 C. GarionVGV VAT 54132-GE02 (x3) C C To be ordered Sep-13 Sep-13 C. GarionLoads 100% 100% procurement Sep-13 Sep-13 I. KononenkoASSEMBLY IN LAB Oct-13 Nov-13 Dmitry Gudkov