NO. FM# Road Name Type of Work FY 2018/19 FY 2019/20 FY 2020/21 FY 2021/22 FY 2022/23 TOTAL1 237650-6 SR 507 (BABCOCK ST) FROM MALABAR RD TO PALM BAY RD ADD LANES & RECONSTRUCT $3,392,500 $0 $0 $0 $8,381,924 $11,774,4242 243968-1 MOA - MELBOURNE ROUTINE MAINTENANCE $62,777 $62,777 $80,328 $80,328 $80,328 $366,5383 244003-1 MOA - COCOA BEACH ROUTINE MAINTENANCE $14,874 $14,874 $14,874 $14,874 $14,874 $74,3704 244004-1 MOA - CITY OF PALM BAY ROUTINE MAINTENANCE $38,695 $38,695 $38,695 $38,695 $38,695 $193,4755 244007-1 MOA - CITY OF ROCKLEDGE ROUTINE MAINTENANCE $28,036 $28,036 $28,036 $28,036 $28,036 $140,1806 244100-1 MOA - TITUSVILLE ROUTINE MAINTENANCE $62,300 $62,300 $62,300 $62,300 $62,300 $311,5007 244348-1 MOA - CITY OF COCOA ROUTINE MAINTENANCE $52,336 $52,336 $52,336 $52,336 $52,336 $261,6808 244706-2 MOA - BREVARD COUNTY ROUTINE MAINTENANCE $55,500 $55,500 $55,500 $55,500 $55,500 $277,5009 244729-1 MOA - INDIAN HARBOUR BEACH ON SR 513 ROUTINE MAINTENANCE $11,872 $11,872 $11,872 $11,872 $11,872 $59,360

10 406491-1 MOA - INDIALANTIC ROUTINE MAINTENANCE $6,772 $6,772 $6,772 $6,772 $6,772 $33,86011 413019-1 BREVARD TRAFFIC ENGINEERING CONTRACTS TRAFFIC SIGNALS $655,491 $655,491 $0 $0 $0 $1,310,98212 413615-4 LIGHTING AGREEMENTS LIGHTING $898,174 $925,131 $952,882 $981,456 $1,010,893 $4,768,53613 413761-1 SR 514 FROM WEBER RD TO COREY RD ADD LEFT TURN LANE(S) $305,000 $1,570,234 $130,000 $0 $0 $2,005,23414 415784-2 MOA - TOWN OF PALM SHORES ROUTINE MAINTENANCE $7,468 $7,468 $7,468 $7,468 $7,468 $37,34015 417958-1 BREVARD URBAN AREA UPWP TRANSPORTATION PLANNING $250,000 $150,000 $0 $0 $0 $400,00016 418104-1 BREVARD PRIMARY ROADWAYS INHOUSE ROUTINE MAINTENANCE $1,804,791 $1,804,791 $1,863,811 $1,863,811 $1,863,811 $9,201,01517 419939-1 DRAIN CLEANING VARIOUS LOCATIONS ROUTINE MAINTENANCE $167,084 $167,084 $167,084 $167,084 $0 $668,33618 420642-1 BREVARD-SPACE COAST AREA TRANSIT SCAT BUS SERVICE SR 520 TRANSIT SERVICE DEMONSTRATION $419,257 $436,027 $453,468 $426,416 $439,208 $2,174,37619 420643-1 BREVARD-SPACE COAST AREA TRANSIT SCAT A1A BEACH TROLLEY TRANSIT SERVICE DEMONSTRATION $419,257 $436,027 $453,468 $426,416 $439,208 $2,174,37620 422169-1 MOA - CITY OF WEST MELBOURNE ROUTINE MAINTENANCE $15,038 $15,038 $15,038 $15,038 $15,038 $75,19021 425678-1 PAVEMENT MARKINGS/ RPM'S VARIOUS LOCATIONS ROUTINE MAINTENANCE $1,830,200 $950,000 $0 $0 $0 $2,780,20022 425678-5 SIDEWALK/CONC REP VARIOUS LOCATIONS ROUTINE MAINTENANCE $175,640 $209,000 $209,000 $209,000 $0 $802,64023 426503-1 MOA - CAPE CANAVERAL ROUTINE MAINTENANCE $2,472 $2,472 $2,472 $2,472 $2,472 $12,36024 426904-3 I-95 INT AT ST JOHNS HERITAGE PKWY/PALM BAY PKWY N OF MICCO RD INTERCHANGE (NEW) $0 $770,000 $0 $0 $0 $770,00025 426904-4 I-95 INT AT ST JOHNS HERITAGE PKWY/PALM BAY PKWY N OF MICCO RD LANDSCAPING $406,934 $0 $0 $0 $0 $406,93426 426905-3 I-95 INT AT ELLIS RD (ST JOHNS HERITAGE PKWY) INTERCHANGE (NEW) $1,331,367 $1,250,000 $409,381 $0 $0 $2,990,74827 426905-4 ST JOHNS HERITAGE PKWY/ELLIS RD FROM JOHN RHODES BLVD TO W OF WICKHAM RD PRELIMINARY ENGINEERING $0 $0 $3,173,879 $2,666,993 $4,809,882 $10,650,75428 427693-1 PERFORMANCE AESTHETI CS ROUTINE MAINTENANCE $444,000 $888,000 $888,000 $888,000 $888,000 $3,996,00029 427836-1 UNPAVED SHOULDER REP ROUTINE MAINTENANCE $308,240 $0 $0 $0 $0 $308,24030 428930-1 BREVARD COUNTY ITS OPERATIONAL SUPPORT ITS COMMUNICATION SYSTEM $225,000 $225,000 $225,000 $225,000 $225,000 $1,125,00031 429276-1 DRAINAGE REPAIRS ROUTINE MAINTENANCE $360,000 $0 $0 $0 $0 $360,00032 429792-2 BREVARD-SPACE COAST REG SECURITY IMPROVEMENTS AVIATION SECURITY PROJECT $0 $500,000 $0 $0 $0 $500,00033 430136-1 SR 514 (MALABAR RD) FROM SR 507 (BABCOCK ST) TO US 1 (SR 5) PD&E/EMO STUDY $0 $5,000 $1,000,000 $4,088,900 $0 $5,093,90034 430202-4 SR A1A AT SR 520 INTERSECTION IMPROVEMENTS INTERSECTION IMPROVEMENT $1,531,564 $0 $0 $0 $0 $1,531,56435 430202-8 SR A1A FROM LONG POINT DR TO GEORGE KING BLVD MISCELLANEOUS CONSTRUCTION $2,020,000 $0 $0 $0 $0 $2,020,00036 430206-1 BREVARD COUNTYWIDE COMPLETE STREETS FEASIBILITY STUDY RESERVE CORRIDOR/SUBAREA PLANNING $59,724 $0 $1,377,669 $0 $0 $1,437,39337 431402-1 BREVARD-SECTION 5303 SPACE COAST TPO PLANNING STUDIES PTO STUDIES $177,830 $183,522 $190,856 $0 $0 $552,20838 431532-1 BREVARD-SCAT ECTION 5307 CAPITAL FOR FIXED ROUTE CAPITAL FOR FIXED ROUTE $8,375,000 $8,500,000 $8,754,000 $9,017,650 $9,288,179 $43,934,82939 432399-1 SR 406 FROM WEST OF FORRELL AVE NORTH TO WASHINGTON AVE (SR 5 NORTH) RESURFACING $1,555,726 $0 $0 $0 $0 $1,555,72640 433303-1 BREVARD-BLOCK GRANT OPERATING ASSISTANCE FOR FIXED ROUTE SEC 5307 OPERATING FOR FIXED ROUTE $3,338,000 $3,478,838 $3,652,782 $3,835,422 $0 $14,305,04241 433382-1 BREVARD COUNTY TRANSPORTATION ALTERNATES BIKE/PED & TRAIL PROJECTS BIKE PATH/TRAIL $0 $52,039 $558,911 $558,911 $558,911 $1,728,77242 433383-1 BREVARD COUNTY TRANSPORTATION ALTERNATE CAPACITY PROJECTS CORRIDOR/SUBAREA PLANNING $274,356 $2,767,578 $4,934,941 $6,692,610 $6,692,610 $21,362,09543 433605-1 SR 501 FROM MICHIGAN AVE TO INDUSTRY RD PD&E/EMO STUDY $5,000 $0 $0 $0 $0 $5,00044 433655-1 SR 500 (US 192) AT HOLLYWOOD BLVD ADD TURN LANE(S) $0 $0 $1,845,000 $2,015,000 $2,189,263 $6,049,26345 434862-1 BREVARD-SPACE FL HORIZONTAL LAUNCH CARGO PROCESSING SPACEPORT CAPACITY PROJECT $8,600,000 $0 $0 $0 $0 $8,600,00046 435320-1 BREVARD-SPACE FL LAUNCH COMPLEX IMPROVEMEN TS SPACEPORT CAPACITY PROJECT $10,000,000 $0 $0 $0 $0 $10,000,00047 435322-1 BREVARD-SPACE FL PROCESSING & RANGE FACILI TY IMPROVEMENTS SPACEPORT CAPACITY PROJECT $48,600,000 $14,000,000 $10,000,000 $12,000,000 $10,000,000 $94,600,00048 435652-1 SR 5 (US 1) AT HIBISCUS BALLARD AND US 192 INTERSECTIONS TRAFFIC SIGNAL UPDATE $1,267,821 $204,045 $66,810 $0 $0 $1,538,67649 435714-1 SPACE COAST AREA TRANSIT CAPITAL FOR FIXED ROUTE $833,653 $858,663 $0 $0 $0 $1,692,31650 436122-1 SR 405 SPACEPORT CONNECTOR SIS INTERSECTION IMPROVEMENTS ADD LEFT TURN LANE(S) $0 $2,303,313 $0 $0 $0 $2,303,31351 436123-1 SR 405 AT SISSON RD SPACEPORT CONNECTOR SIS INTERSECTION IMPROVEMENTS ADD LEFT TURN LANE(S) $310,000 $1,643,823 $0 $0 $0 $1,953,82352 436125-1 WICKMAN RD AT I-95 RAMP IMPROVEMENTS AND MAST ARMS ADD LEFT TURN LANE(S) $705,000 $0 $2,241,339 $0 $0 $2,946,33953 436187-2 SPACE COAST TRAIL FROM INDIAN RIVER AVE TO W OF MAX BREWER BRIDGE BIKE PATH/TRAIL $0 $0 $0 $0 $2,196,312 $2,196,31254 436187-3 COAST TO COAST TRAIL E OF MAX BREWER BRIDGE TO MERRITT ISLAND REFUGE BIKE PATH/TRAIL $364,594 $0 $0 $0 $0 $364,59455 436863-1 BREVARD-SPACE FLORIDA COMMOM USE INFRASTRUCTURE SPACEPORT CAPACITY PROJECT $31,800,000 $10,000,000 $11,000,000 $14,548,604 $19,446,344 $86,794,94856 437069-1 BREVARD-SPACE FL LAUNCH COMPLEX IMPROVEMENTS & PASSENGER/CARGO SPACEPORT CAPACITY PROJECT $18,000,000 $10,000,000 $8,000,000 $4,000,000 $10,000,000 $50,000,00057 437070-1 BREVARD-SPACE FL HORIZONTAL LAUNCH/LANDING FACILITIES SPACEPORT CAPACITY PROJECT $3,269,600 $10,000,000 $11,000,000 $20,000,000 $20,000,000 $64,269,60058 437093-1 SPACE COAST TRAIL FROM MAX BREWER CAUSEWAY TO ATLANTIC OCEAN BIKE PATH/TRAIL $0 $0 $0 $0 $4,799,360 $4,799,36059 437116-1 SR 5 (US 1) DRAINAGE OUTFALL FROM N OF CROSS RD TO INDIAN RIVER DR DRAINAGE IMPROVEMENTS $441,500 $90,000 $919,775 $0 $0 $1,451,27560 437203-1 HOLLYWOOD ST WIDENING FROM PALM BAY RD TO US 192 WIDEN/RESURFACE EXIST LANES $0 $8,171,206 $630,000 $0 $0 $8,801,206

TABLE 2FDOT TENTATIVE WORK PROGRAM - BREVARD COUNTY PROJECTS

FOR FISCAL YEARS 2018/19 - 2022/23

NOTE: Projects highlighted in BLUE are those that are mapped.Tentative Work Program data, as of October 4, 2017. 1 of 3

Page 3: 1 237650-6 SR 507 (BABCOCK ST) FROM … 2017-2018 Brevard - 62954...NO. FM# Road Name Type of Work FY 2018/19 FY 2019/20 FY 2020/21 FY 2021/22 FY 2022/23 TOTAL 1 237650-6 SR 507 (BABCOCK

NO. FM# Road Name Type of Work FY 2018/19 FY 2019/20 FY 2020/21 FY 2021/22 FY 2022/23 TOTAL

TABLE 2FDOT TENTATIVE WORK PROGRAM - BREVARD COUNTY PROJECTS

FOR FISCAL YEARS 2018/19 - 2022/23

61 437204-1 BABCOCK ST FROM ST JOHN HERITAGE PKWY TO MALABAR RD ADD LANES & RECONSTRUCT $0 $2,967,131 $0 $0 $0 $2,967,13162 437210-1 MALABAR RD FROM ST JOHNS HERITAGE PKWY TO MINTON RD PD&E/EMO STUDY $0 $1,000,000 $0 $0 $0 $1,000,00063 437302-1 SR 5 (US 1) 1ST ST TO POSPISIL AVE SIGNING/PAVEMENT MARKINGS $409,294 $0 $0 $0 $0 $409,29464 437343-1 SR 406/MAX BREWER MEMORIAL PKWY-FWCC DRIVEWAY TO MERRITT ISLAND REFUGE RESURFACING $425,129 $0 $0 $0 $0 $425,12965 437345-1 SR 50 (CHENEY HWY) FROM ORANGE COUNTY LINE TO I-95 SB ON RAMP RESURFACING $10,636,516 $0 $0 $0 $0 $10,636,51666 437594-1 COUNTRY CLUB RD SCHOOL SAFETY PROJ/FROM EDGEWOOD DR TO PEEKSKILL PL SIDEWALK $0 $570,000 $0 $0 $0 $570,00067 437801-1 PINEAPPLE AVENUE FROM MONTREAL AVE (SR 518) TO AURORA RD MISCELLANEOUS CONSTRUCTION $0 $788,783 $0 $0 $0 $788,78368 437802-1 FRONT ST/MELBOURNE AVE FROM MELBOURNE AVE TO NEW HAVEN AVE SIDEWALK $0 $386,084 $0 $0 $0 $386,08469 437937-1 SR 5 (US 1) FROM ERNEST SANDS RD TO TOPSAIL DR CONSTRUCT CULVERT $0 $876,952 $0 $0 $0 $876,95270 437983-1 SR 524 FROM FRIDAY RD TO INDUSTRY RD PD&E/EMO STUDY $1,763,000 $0 $0 $0 $0 $1,763,00071 438391-1 BREVARD-ARTHUR DUNN CONSTRUCT CORPORATE HANGAR AVIATION REVENUE/OPERATIONAL $0 $0 $0 $0 $2,500,000 $2,500,00072 438393-1 BREVARD-ARTHUR DUNN CONSTRUCT APRON AVIATION CAPACITY PROJECT $0 $0 $0 $200,000 $0 $200,00073 438397-1 BREVARD-ARTHUR DUNN REHABILITATE AIRPORT FACILITIES AVIATION PRESERVATION PROJECT $0 $0 $0 $250,000 $0 $250,00074 438398-1 BREVARD-ARTHUR DUNN AIRFIELD PAVEMENT IMPROVEMENTS AVIATION PRESERVATION PROJECT $0 $0 $0 $80,000 $720,000 $800,00075 438401-1 BREVARD-ARTHUR DUNN AIRPORT MASTER PLAN UPDATE AVIATION CAPACITY PROJECT $0 $0 $0 $0 $260,000 $260,00076 438404-1 BREVARD-ARTHUR DUNN REHABILITATE AIRPORT FACILITIES AVIATION PRESERVATION PROJECT $0 $0 $0 $0 $500,000 $500,00077 438452-1 BREVARD-MELBOURNE INTL TERMINAL BUILDING IMPROVEMENTS AVIATION PRESERVATION PROJECT $3,000,000 $7,950,000 $1,550,000 $7,000,000 $0 $19,500,00078 438453-1 BREVARD-MELBOURNE INTL CONSTRUCT PARKING GARAGE AVIATION REVENUE/OPERATIONAL $0 $0 $0 $0 $4,000,000 $4,000,00079 438457-1 BREVARD-MELBOURNE INTL TAXIWAY IMPROVEMENTS AVIATION REVENUE/OPERATIONAL $0 $500,000 $1,500,000 $0 $0 $2,000,00080 438458-1 BREVARD-MELBOURNE INTL LAND ACQUISITION AVIATION ENVIRONMENTAL PROJECT $0 $0 $0 $3,000,000 $0 $3,000,00081 438461-1 BREVARD-MERRITT ISLAND CONSTRUCT HANGARS AVIATION REVENUE/OPERATIONAL $0 $0 $625,000 $2,000,000 $0 $2,625,00082 438462-1 BREVARD-MERRITT ISLAND REHABILITATE SOUTH APRON AVIATION PRESERVATION PROJECT $0 $3,000,000 $0 $0 $0 $3,000,00083 438464-1 BREVARD-MERRITT ISLAND CONDUCT MASTER PLAN UPDATE AVIATION CAPACITY PROJECT $0 $0 $0 $235,000 $0 $235,00084 438468-1 BREVARD-MERRITT ISLAND HANGAR DEVELOPMENT AVIATION REVENUE/OPERATIONAL $400,000 $0 $0 $0 $0 $400,00085 438469-1 BREVARD-MERRITT ISLAND CONSTRUCT HANGARS AVIATION REVENUE/OPERATIONAL $0 $0 $0 $0 $1,500,000 $1,500,00086 438478-1 I-95 FROM NB REST AREA TO SB REST AREA REST AREA $0 $0 $26,422,345 $0 $0 $26,422,34587 438493-1 BREVARD-SPACE COAST REG TAXIWAY IMPROVEMENTS AVIATION PRESERVATION PROJECT $0 $230,000 $2,760,000 $0 $0 $2,990,00088 438494-1 BREVARD-SPACE COAST REG CONSTRUCT NEW ATCT AVIATION SAFETY PROJECT $0 $0 $90,000 $350,000 $3,500,000 $3,940,00089 438495-1 BREVARD-SPACE COAST REG CONSTRUCT HANGAR AVIATION REVENUE/OPERATIONAL $2,000,000 $3,600,000 $0 $0 $0 $5,600,00090 438498-1 BREVARS-VALKARIA CONSTRUCT AIRPORT ACCESS RD AVIATION REVENUE/OPERATIONAL $0 $315,500 $0 $0 $0 $315,50091 438499-1 BREVARD-VALKARIA TAXIWAY IMPROVEMENTS AVIATION SAFETY PROJECT $0 $0 $1,350,000 $0 $0 $1,350,00092 438501-1 BREVARD-VALKARIA INSTALL AWOS AVIATION SAFETY PROJECT $250,000 $0 $0 $0 $0 $250,00093 439146-1 SR A1A (S ATLANTIC AVE) AT JUPITER ST/PATRICK AIR FORCE BASE MAIN GATE TRAFFIC OPS IMPROVEMENT $0 $532,593 $0 $0 $0 $532,59394 439157-1 SR 3, NORTH COURTNEY PKWY AT MUSTANG WAY INTERSECTION MISCELLANEOUS CONSTRUCTION $0 $163,045 $150,000 $707,398 $81,262 $1,101,70595 439330-2 BREVARD/SPACECOAST FY 2018/2019-2019/2020 UPWP TRANSPORTATION PLANNING $1,477,287 $729,177 $0 $0 $0 $2,206,46496 439330-3 BREVARD/SPACECOAST FY 2020/2021-2021/2022 UPWP TRANSPORTATION PLANNING $0 $0 $729,177 $729,177 $0 $1,458,35497 439330-4 BREVARD/SPACECOAST FY 2022/2023-2023/2024 UPWP TRANSPORTATION PLANNING $0 $0 $0 $0 $729,177 $729,17798 439485-1 PIGEON AVE FROM CHARLES BLVD TO MALABAR RD/PORT MALABAR ELEMENTARY BIKE LANE/SIDEWALK $0 $174,231 $0 $0 $0 $174,23199 439486-1 SAN FILIPPO DR; ZANZIBAR RD FROM WACO BLVD; STEELE ST TO SALINA ST BIKE LANE/SIDEWALK $0 $452,972 $0 $0 $0 $452,972

100 439494-1 AMERICANA BLVD & ALCANTARRA ST FROM AVACADO RD TO ALMOND AVE SIDEWALK $0 $564,510 $0 $0 $0 $564,510101 439512-1 SR A1A (N MIRAMAR AVE) FROM US 192 (SR 500) TO SR 518 (EAU GALLIE BLVD) SAFETY PROJECT $0 $721,708 $0 $0 $0 $721,708102 439667-1 JACOBIN ST FROM DALLAM AVE TO GALLATIN AVE/DISCOVERY ELEMENTARY BIKE LANE/SIDEWALK $0 $817,535 $0 $0 $0 $817,535103 439677-1 MALABAR RD/GEARY ST/WALMSLEY ST-FROM HURLEY TO 650FT W OF JUPITER BLVD BIKE LANE/SIDEWALK $0 $1,683,133 $0 $0 $0 $1,683,133104 439777-1 SR520 (MERRITT ISL CSWY) - W OF NEWFOUND HARBOR DR TO E OF S BANANA RIV DR TRAFFIC OPS IMPROVEMENT $0 $690,241 $0 $0 $0 $690,241105 439778-1 SR518 (W EAU GALLIE BLVD) - E OF I-95 NB OFF RAMP TO W OF INT AT SARNO RD TRAFFIC OPS IMPROVEMENT $0 $0 $3,390,633 $0 $0 $3,390,633106 439779-1 SR518 (W EAU GALLIE BLVD) - JONES RD TO 200FT E OF I-95 INTERCHG RAMPS TRAFFIC OPS IMPROVEMENT $0 $0 $3,369,442 $0 $0 $3,369,442107 439853-1 SR 507 (BABCOCK ST) FROM EBER RD TO NASA BLVD (SR 508) ITS COMMUNICATION SYSTEM $155,000 $747,668 $0 $0 $0 $902,668108 439856-1 SR 500 (US 192) - NEW HAVEN AVENUE FROM DAIRY ROAD TO US 1 ITS COMMUNICATION SYSTEM $155,000 $609,896 $0 $0 $0 $764,896109 439857-1 SR 5 (US 1-HARBOR CITY BLVD) FROM UNIVERSITY BLVD TO BABCOCK ST ITS COMMUNICATION SYSTEM $235,000 $1,219,432 $0 $0 $0 $1,454,432110 439883-2 BREVARD COUNTY PEDESTRIAN LIGHTING BUNDLE B LIGHTING $163,667 $0 $0 $0 $0 $163,667111 439883-4 BREVARD COUNTY PEDESTRIAN LIGHTING BUNDLE A LIGHTING $75,000 $0 $0 $0 $0 $75,000112 439883-5 BREVARD COUNTY PEDESTRIAN LIGHTING BUNDLE B LIGHTING $300,000 $0 $0 $0 $0 $300,000113 439883-6 BREVARD COUNTY PEDESTRIAN LIGHTING BUNDLE C LIGHTING $450,000 $0 $0 $0 $0 $450,000114 440323-1 BREVARD-PORT CANAVERAL NORTH CARGO BERTH IMPROVEMENTS SEAPORT CAPACITY PROJECT $6,000,000 $20,000,000 $0 $0 $0 $26,000,000115 440771-1 BREVARD-SPACE COAST REG APRON AVIATION PRESERVATION PROJECT $0 $0 $0 $1,000,000 $0 $1,000,000116 440772-1 BREVARD-VALKARIA HANGARS AVIATION PRESERVATION PROJECT $0 $0 $0 $1,000,000 $1,250,000 $2,250,000117 440799-1 BREVARD-SPACE COAST TPO PLANNING STUDIES PTO STUDIES $0 $0 $0 $198,412 $267,170 $465,582118 440969-1 SR 520 EB & WB OVER INDIAN RIVER BRIDGE # 700061 & 70137 BRIDGE-REPAIR/REHABILITATION $1,386,459 $0 $0 $0 $0 $1,386,459119 441000-1 SR 5 (US 1) FROM 110' S OF JORDAN BLVD TO 85' N OR JORDAN BLVD TRAFFIC SIGNAL UPDATE $220,000 $0 $569,732 $0 $0 $789,732120 441013-1 SR 3 (N COURTENAY PKWY) FROM SR 528 TO KENNEDY SPACE CENTER GATE RESURFACING $1,110,000 $0 $13,465,270 $0 $0 $14,575,270

NOTE: Projects highlighted in BLUE are those that are mapped.Tentative Work Program data, as of October 4, 2017. 2 of 3

Page 4: 1 237650-6 SR 507 (BABCOCK ST) FROM … 2017-2018 Brevard - 62954...NO. FM# Road Name Type of Work FY 2018/19 FY 2019/20 FY 2020/21 FY 2021/22 FY 2022/23 TOTAL 1 237650-6 SR 507 (BABCOCK

NO. FM# Road Name Type of Work FY 2018/19 FY 2019/20 FY 2020/21 FY 2021/22 FY 2022/23 TOTAL

TABLE 2FDOT TENTATIVE WORK PROGRAM - BREVARD COUNTY PROJECTS

FOR FISCAL YEARS 2018/19 - 2022/23

121 441020-1 SR 519 FROM I-95 TO SR 520 RESURFACING $1,610,000 $0 $8,680,098 $0 $0 $10,290,098122 441168-1 US 192 OVER INDIAN RIVER BRIDGE # 700174 & 700181 BRIDGE-REPAIR/REHABILITATION $675,731 $0 $0 $0 $0 $675,731123 441205-1 CITY OF COCOA SIDEWALK PROJECT-DIXON BLVD, FORREST AVE, & VARR AVE SIDEWALK $10,000 $209,222 $0 $0 $0 $219,222124 441277-1 SRA1A (S ATLANTIC AVE) FROM SIGNAL SRA1A-PAFB FIRE STATION TO MP 28.025 TRAFFIC SIGNAL UPDATE $182,000 $0 $328,084 $0 $0 $510,084125 441449-1 JOHN RODES BLVD TO EAU GALLIE BLVD TO AURORA RD SIDEWALK $100,000 $0 $0 $0 $0 $100,000126 441584-1 BREVARD TRAFFIC MANAGEMENT CENTER - SR 404 TRAFFIC MANAGEMENT CENTERS $910,000 $0 $0 $0 $0 $910,000127 441778-1 FL COAST TO COAST PARRISH PARK TRAILHEAD BIKE PATH/TRAIL $250,000 $0 $2,000,000 $0 $0 $2,250,000128 441804-1 GRANT RD OVER I-95 BRIDGE #700158 BRIDGE-REPAIR/REHABILITATION $480,052 $0 $0 $0 $0 $480,052129 442440-1 PORT ST. JOHN BICYCLE, TRANSIT, CONNECTIVITY FEASIBILITY STUDY FEASIBILITY STUDY $250,000 $0 $0 $0 $0 $250,000130 442456-1 BREVARD-BLOCK GRANT OPERATING ASSITANCE SEC 5307 OPERATING FOR FIXED ROUTE $0 $0 $0 $0 $4,027,190 $4,027,190131 442463-1 BREVARD-SPACE COAST AREA TRANSIT SERVICE DEVELOPMENT TRANSIT SERVICE DEMONSTRATION $373,802 $0 $0 $0 $0 $373,802132 442478-1 BREVARD-VALKARIA SECURITY IMPROVEMENTS AVIATION SECURITY PROJECT $125,000 $0 $0 $0 $0 $125,000133 442479-1 BREVARD-VALKARIA AIRFIELD IMPROVEMENTS AVIATION PRESERVATION PROJECT $1,750,000 $0 $0 $0 $0 $1,750,000134 442480-1 BREVARD-ARTHUR DUNN AIRFIELD IMPROVEMENTS AVIATION PRESERVATION PROJECT $175,000 $0 $0 $0 $0 $175,000135 442481-1 BREVARD-ARTHUR DUNN SECURITY ENHANCEMENTS AVIATION SECURITY PROJECT $0 $150,000 $0 $0 $0 $150,000136 442482-1 BREVARD-MERRITT ISLAND SECURITY ENHANCEMENTS AVIATION SECURITY PROJECT $0 $250,000 $0 $0 $0 $250,000137 442554-1 NORTH MERRITT ISLAND PIONEER TRAIL FEASIBILITY STUDY FEASIBILITY STUDY $250,000 $0 $0 $0 $0 $250,000

NOTE: Projects highlighted in BLUE are those that are mapped.Tentative Work Program data, as of October 4, 2017. 3 of 3