09 July 20151
EHN1 civil engineering project status (JUNE)
Summary:• Updating of the activities carried out on-site (Done) in JUNE • List activities on going (Next steps) and scheduled for JULY• Final consideration
Extension of Building 887 - 24th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
(1) MICRO PILESVertical & inclined drilling along TT85: (100% completed)
EHN1 civil engineering project status (JUNE)
Crown beam execution: (100% completed).
Done (1/4):
09 July 20152
TASK
COMPLETED
Extension of Building 887 - 24th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
(2) DIAPHRAGM WALLS -73 panels-
Execution EAST side: (91% completed)
EHN1 civil engineering project status (JUNE)
Execution SOUTH/WEST side: (50% completed)
Done (2/4):
09 July 20153
Guide walls allowing DW excavation: (87% completed)
Execution NORTH/WEST side: (100% completed)
~79% TOTAL PANELS
EAST
N/W
S/W
Extension of Building 887 - 24th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
Done (3/4):
(3) TECHNICAL GALLERY -70 meters-
EHN1 civil engineering project status (JUNE)
Earthworks: (100% completed). After excavation of Type 3 portionExecution TG: (35% completed). Type 3 portion startedBackfilling: (25% completed). Type 2, facing TT85 enlargement
09 July 20154
Extension of Building 887 - 24th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
Done (4/4):
(4) PITS EXECUTION
EHN1 civil engineering project status (JUNE)
Crown beam execution: (0% completed). Excavation first ties level: (0% completed).
09 July 20155
Excavation head DW level: (15% completed). Started with the East side
Excavation second ties level: (0% completed). Only for certain DW panels …Others
First ties level execution: (0% completed).-step by step-
Task in “cohabitation” with the DWs last panels execution!!
Extension of Building 887 - 24th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
Next Steps: Activities scheduled for July (2) DW: Prepare new lower guide walls close to EHN1 allowing panels excavation. Whole panels completion within end-July
(3) TG: Advancement on Type 3 portion. Work site preparation for Type 1 execution
(4) PITS: Excavation/Execution crown beam + Excavation/Execution for ties installation East side portion
EHN1 civil engineering project status (JUNE)
09 July 20156
02/07/2015
Extension of Building 887 - 24th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
Final Consideration:
- New long-term schedule received updated with the current on-site situation.
- The compatibility/duration of the upcoming tasks will be assessed.
- CE tasks have to be carried out in parallel. Execution of the two pits launched before DWs panels completion to avoid further delays.
- Likely (but too early to say) CE first phase completion while metallic contractor are already on-site. Risky, but feasible thanks to the Consortium.
- CE Handover unchanged for the moment (Jul-2016)
- Next status of the works end-July.
EHN1 civil engineering project status (JUNE)
09 July 20157
Extension of Building 887 - 24th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi