  • DOCUMENT TITLE :

    3/10/2012 0

    DOCUMENT NUMBER : SHT. 1 OF 6 REV.

    ORIGINATOR:

    Descon PROJECT :

    Descon Engineering FZE

    DATE REV.NO. DESCRIPTION

    PROJECT :

    INSPECTION AND TEST PLAN

    RM

    Des-XXXX-QA&QC-01

    Issued for Client Review / Comments

    0

    SK SK

    PREPARED BY CHECKED BY APPROVED BY

  • PO No.:

    1

    1.1 PIM Agenda H

    1.2 ITP & Applicable Code H

    1.3 ASME Sec.1 H

    1.4 ASME IX, B31.1 , H

    1.5 ASME IX H

    1.6 ASME Sec.V H

    1.7 ASME Sec.VIII Div.1 & Sec.I H

    1.8 ASME Sec.VIII Div.1 & Sec.I H

    1.9 ASTM / SSPC / Swedish H

    1.10 Certificates / SNT-TC-1A H

    2

    2.1 Drawings/ P.O/ ASME Sec.II Part A H

    2.2 Drawings/ P.O/ ASME Sec.II Part A H

    3

    3.1 ASME Sec.VIII Div.1+ DWG H

    Material Inspection / Verification / Certificate review QC Material Inspector

    Inspection of Dish End QC Material Inspector

    Material inspection report / MTC'S

    Controlling of Heat Number and stamp transfer for pressure parts and those which are directly weld with pressure parts / Traceability check

    QC Material Inspector Material traceability report / MTC'S

    End User

    DESCON DOC No.:

    Coating Inspector

    DOCUMENTATION

    INSPECTION BY

    DES-PROP-QA&QC-01

    DES-QA&QC/FRM-40

    QC Engineer

    QC Engineer

    Welding Engineer

    MATERIAL CONTROL

    STATUS SIGN SIGN

    QC ACTIVITY

    STATUS

    JZNOBO (CE Marking)

    STATUS

    Weld Repair Proceudre

    SIGNATURE

    DESCON PROJECT No.:

    SIGN

    Hydrostatic and Pneumatic test procedure

    PROJECT

    COMPANY DOC No:

    ASME Authorized Inspector

    COMPANY

    DES-PROP-QA&QC-01

    ITEM TAG

    REFERENCE DOCUMENTS / ACCEPTANCE CRITERIA

    PREPARED BY

    SAKET KUMAR

    VERIFYING DOCUMENT

    STATUSSIGNSTATUS SIGN

    Welding Book

    DESCON ENGINEERING FZE

    CLIENT

    MANUFACTURER

    INSPECTION AND TEST PLAN (ITP)

    RASHID MAHMOOD

    DESCON QA/QC

    REVIEWED BY

    I/C Product Engineering

    PRIME RESPONSIBILTY

    -

    APPROVED BY

    LEGEND: H - HOLD, W - WITNESS, SW - SPOT WITNESS, R - REVIEW OF RECORD, RW-RANDOM WITNESS, A - APPROVAL , M - MONITORING

    I/C QA&QC Minutes of meeting

    Qualification Certificates

    DISH END FORMING

    NDE Operator Qualification

    Surface Preparation & Painting Procedure

    ITEM

    SAKET KUMAR

    Inspection and Test Plan

    Welding Book Welding Engineer

    S.P & Painting Procedure

    Weld Repair Prcoedure

    Pre- Inspection Meeting

    Drawings and Design Calculations

    Welders Qualification Record

    NDE Procedures

    Approved drawings

    QC Engineer

    Hydro static and Pneumatic test procedure

    RT,MT,UT DPT Procedures

    NDE Engineer

    QC Engineer

    Inspection Report

    Doc. No. : DES-QA&QC/FRM-05ARev.: 01Date: April 22, 2010

    Do not duplicate. controlled copy if stamped in red.Descon Engineering FZE

    2 of 6

  • End User

    INSPECTION BY

    STATUS SIGN SIGN

    QC ACTIVITY

    STATUS

    JZNOBO (CE Marking)

    STATUS SIGN

    ASME Authorized Inspector

    REFERENCE DOCUMENTS / ACCEPTANCE CRITERIA VERIFYING DOCUMENT

    STATUSSIGNSTATUS SIGN

    DESCON QA/QCPRIME RESPONSIBILTYITEM

    3.2 ASME Sec.VIII Div.1 + DWG H

    3.3 ASME Sec.VIII Div.1 + DWG H

    4

    4.1

    4.2 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.3

    4.4 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.5 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.6 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.7 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.8 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.9 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.10 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.11 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.12 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.13 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.14

    4.15

    4.16 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.17

    MUD DRUM

    Rolling Inspection

    Rolling / Re Rolling of Shell Course

    QC Inspector

    Marking of tube holes on the shell of Mud Drum

    Marking of tube holes on the shell of Steam Drum QC Inspector

    Physical verification / Signed ITP for recordQC Inspector

    QC Inspector Physical verification / Signed ITP for record

    Physical verification / Signed ITP for record

    QC Inspector

    Physical verification / Signed ITP for record

    Fit up of Tubes with Steam Drum Shell

    Fit up Inspection

    Rolling / Re Rolling of Shell Course

    Nozzles and Stubs Fit-up

    Physical verification / Signed ITP for record

    Tubes Expansion report

    LS and CS Fit-up of shell course. QC Inspector

    QC Inspector Physical verification / Signed ITP for record

    Physical verification / Signed ITP for record

    QC Inspector

    Rolling Inspection

    FABRICATION

    Thickness Check of Head QC Material Inspector Thickness Report

    QC Material Inspector MT ReportMT on Knuckle radius

    Holes drilling in Steam Drum and Mud Drum

    Insertion of Tubes in Tube Holes in the Shell of Steam Drum and Mud Drum

    QC Inspector Physical verification / Signed ITP for record

    QC Inspector

    STEAM DRUM

    Physical verification / Signed ITP for record

    Fit up of Tubes with Mud Drum Shell QC Inspector Physical verification / Signed ITP for record

    Expansion of tubes

    QC Inspector Physical verification / Signed ITP for record

    Fit up Inspection

    Fit up of Saddles

    Do not duplicate. controlled copy if stamped in red.Descon Engineering FZE

    3 of 6

  • End User

    INSPECTION BY

    STATUS SIGN SIGN

    QC ACTIVITY

    STATUS

    JZNOBO (CE Marking)

    STATUS SIGN

    ASME Authorized Inspector

    REFERENCE DOCUMENTS / ACCEPTANCE CRITERIA VERIFYING DOCUMENT

    STATUSSIGNSTATUS SIGN

    DESCON QA/QCPRIME RESPONSIBILTYITEM

    4.18 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.19 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.20 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.21

    4.22

    4.23 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.24

    4.25 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.26 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.27 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.28

    4.29 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.30 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.31 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    4.32 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.33

    4.34 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.35 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    4.36

    4.37 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    4.38

    SUPER HEATER HEADER

    Hydrostatic test of Header as per approved drawing QC Inspector Physical verification / Signed ITP for record

    Final Visual and Dimensional inspection of Coil QC Inspector Physical verification / Signed ITP for record

    NDE as per apporved drawing QC Inspector Physical verification / Signed ITP for record

    Final Visual and Dimensional inspection of Header QC Inspector Physical verification / Signed ITP for record

    PIPING SPOOLS

    Fit Up Inspection of Piping Spools QC Inspector Physical verification / Signed ITP for record

    NDE as per approved Drawings QC Inspector Physical verification / Signed ITP for record

    QC Inspector Physical verification / Signed ITP for record

    QC Inspector

    Final visual and dimensional Inspection of Ladders and Platforms QC Inspector

    Physical verification / Signed ITP for record

    Nozzles and Stubs Fit-up

    FLASH VESSEL

    Rolling Inspection

    QC Inspector Physical verification / Signed ITP for record

    Fit up Inspection

    Nozzles and Stubs Fit-up QC Inspector Physical verification / Signed ITP for record

    Physical verification / Signed ITP for record

    Rolling / Re Rolling of Shell Course

    LS and CS Fit-up of shell course.

    Physical verification / Signed ITP for record

    QC Inspector

    Marking of Tube holes on the shell of Steam Drum

    QC Inspector

    Marking of Tube holes on the shell of Steam Drum QC Inspector Physical verification / Signed ITP for record

    Physical verification / Signed ITP for record

    LADDERS AND PLATFORMS

    LS and CS Fit-up of shell course.

    Trial Assembly of Ladders and Platforms

    Do not duplicate. controlled copy if stamped in red.Descon Engineering FZE

    4 of 6

  • End User

    INSPECTION BY

    STATUS SIGN SIGN

    QC ACTIVITY

    STATUS

    JZNOBO (CE Marking)

    STATUS SIGN

    ASME Authorized Inspector

    REFERENCE DOCUMENTS / ACCEPTANCE CRITERIA VERIFYING DOCUMENT

    STATUSSIGNSTATUS SIGN

    DESCON QA/QCPRIME RESPONSIBILTYITEM

    4.39 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    5

    6.4 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    6.6 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications W

    6.7 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications W

    6

    6.1 PWHT Specification ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    6.2 PWHT Report and Graph (Chart) ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    6.3 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    7

    7.1

    7.2 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    7.3 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    7.4 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications , ASME Sec.V H

    7.5 10 % MT of LS & CS weld joints ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    7.6 10 % MT on Fillet Welds ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    7.7 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    7.8

    7.9 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    7.10 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    7.11 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    7.12 10 % MT of LS & CS weld joints ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    7.13 10 % MT on Fillet Welds ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    WELDING INSPECTION

    DES-QA&QC/FRM- 62

    NDE Inspector DES-QA&QC/FRM-63 + 62

    Complete compliance of approved WPS

    PWHT

    DES-QA&QC/FRM-74

    DES-QA&QC/FRM-56

    BEFORE PWHT

    DES-QA&QC/FRM-63 + 62

    DES-QA&QC/FRM-61 + 62

    Final weld visual Inspection

    Welding Inspector

    UT of Nozzle to Shell welds NDE Inspector

    RT as per approved Drawings

    NDE Inspector DES-QA&QC/FRM- 62

    NDE Inspector

    DES-QA&QC/FRM-60 + 62

    AFTER PWHT

    10 % MT or PT on all nozzle welds and welded accessories NDE Inspector

    NDE Inspector

    DES-QA&QC/FRM-63 + 62

    DES-QA&QC/FRM-62

    RT as per approved Drawings NDE Inspector DES-QA&QC/FRM-60

    100 % MT on Lifting Lugs100% UT on Lifting Lugs (Full Penetration Joints) NDE Inspector

    NDE Inspector

    UT of Nozzle to Shell welds

    DES-QA&QC/FRM-63 + 62

    Welding Engineer

    Hardness test of welds after PWHT

    Welders Qualification Welding Inspector

    NDE Inspector DES-QA&QC/FRM-61 + 62

    Welding Inspector

    Physical verification / Signed ITP for record

    Weld visual Inspection report

    Physical verification / Signed ITP for record

    NDE

    MPT / DPT after grinding smooth temporary welds

    Welding Engineer

    Welding Engineer

    Hardness test report

    NDE Inspector

    NDE as per approved Drawings QC Inspector Physical verification / Signed ITP for record

    Do not duplicate. controlled copy if stamped in red.Descon Engineering FZE

    5 of 6

  • End User

    INSPECTION BY

    STATUS SIGN SIGN

    QC ACTIVITY

    STATUS

    JZNOBO (CE Marking)

    STATUS SIGN

    ASME Authorized Inspector

    REFERENCE DOCUMENTS / ACCEPTANCE CRITERIA VERIFYING DOCUMENT

    STATUSSIGNSTATUS SIGN

    DESCON QA/QCPRIME RESPONSIBILTYITEM

    7.14 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications, ASME Sec.V H

    8

    8.1 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    8.2 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    8.3 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    8.4 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    8.5 Verification of Close out of NCR's (if any) ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    8.6 ASME Sec.VIII Div.1 / Sec.I H

    8.7 ASME Sec.VIII Div.1 / Sec.I H

    8.8 ASME Sec.VIII Div.1+Sec.I + DWG + Project Specifications H

    9

    9.1 ASME Sec.VIII Div.1 / Sec.I H

    9.2 ASME Sec.VIII Div.1 / Sec.I H

    10

    10.1 SSPC / Swedish H

    11

    11.1 Packing and Shipping Instructions H

    11.2 Packing and Shipping Instructions H

    11.3 Release Note H

    11.4 Final Data Book H

    QC Inspector / QA Engineer NDE Summary sheet

    DES-QA&QC/FRM-62

    Visual Inspection after PWHT QC Inspector Dimensional inspection report

    Dimensional inspection reportQC Inspector

    Physical verification / Signed ITP for record

    100 % MT on Lifting Lugs100% UT on Lifting Lugs (Full Penetration Joints) NDE Inspector

    Draining & Drying after Hydrostatic test

    NDT Verifications

    FINAL INSPECTION

    NDE Summary sheet

    SURFACE PREPARATION AND PAINTING

    Flange Protection inspection Physical verification / Signed ITP for record

    MDR

    QC Inspector Physical verification / Signed ITP for record

    PRE-SHIPMENT INSPECTION AND DOCUMENTATION

    Final Coat DFT and Final Colour Check

    QC Inspector

    Manufacturer data record book

    QC Inspector

    QC Inspector

    Inspection of packing of shipment QC Inspector

    Final Data Book

    Stamping & Attachment of name plate QC Inspector Name plate copy

    Signing of Manufacturer Data Report

    IRCIssuance of inspection release note QC Inspector

    Packing List

    Coating Inspector

    Leak test on RF Pads QC Inspector

    Final visual and dimensional Inspection

    DES-QA&QC/FRM-52Hydrostatic testing QC Inspector

    NAME PLATE

    QC Inspector

    Internal Inspection before Hydrostatic test

    Painting inspection report

    DES-QA&QC/FRM-52

    QC Inspector

    Do not duplicate. controlled copy if stamped in red.Descon Engineering FZE