30
08-July-2019

08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

08-July-2019

Page 2: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 2 of 30

CREDAI Bengal Daily News Update | 08.07.19

Refund to buyers should be with interest at par with home loan rates:

NCDRC

The apex consumer commission has said builders have to pay compensation and litigation cost

to homebuyers who seek refund.

In order to ensure that homebuyers recover all the money invested by them, including interest paid on

home loans, the National Consumer Disputes Redressal Commission (NCDRC) has said builders

should refund money for delayed projects with interest at the rate at which a nationalised bank

like SBI gave home loan during the corresponding period.

HIGHLIGHTS

The National Consumer Disputes Redressal Commission (NCDRC) has said builders should refund

money for delayed projects with interest at the rate at which a nationalised bank like SBI gave home

loan during the corresponding period

The apex consumer commission has said builders have to pay compensation and litigation cost to

homebuyers who seek refund.

The apex consumer commission has said builders have to pay compensation and litigation cost to

homebuyers who seek refund. In the absence of any uniformity in the decisions delivered by various

consumer forums on the issue of interest rate, a bench of S M Kantikarand Dinesh Singh has said

linking it with rate of interest of home loan was ―appropriate and logical‖.

The commission passed the order on a plea of 20 homebuyers who had invested around Rs 10 crore in

Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had

promised to hand over possession of flats within three years but failed to complete construction in the

last seven years.

―In so far as refund of the amount deposited by the complainant with the builder is concerned, there

can be no two opinions. The refund in full has necessarily to be made by the builder to the

complainant. In respect of the interest on the amount deposited, it is always desirable and preferable,

to the extent feasible and appropriate in the facts and specificities of a case, that some objective

logical criteria be identified and adopted to determine an apt rate of interest,‖ the NCDRC said.

―The rate of interest cannot be arbitrary or whimsical, some reasonable and acceptable rationale has to

be evident, subjectivity has to be minimised. In our considered view, bearing in mind that the subject

unit in question is a residential dwelling unit, in a residential housing project, the rate of interest for

Newspaper/Online ET Realty (online)

Date July 08, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/refund-to-buyers-should-be-with-interest-at-par-with-home-loan-rates-ncdrc/70121216

Page 3: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 3 of 30

house building loan for the corresponding period in a scheduled nationalised bank (take, State Bank of

India) would be appropriate and logical, and, if floating/varying/different rates of interest were/are

prescribed, the higher rate of interest should be taken for this instant computation,‖ it added.

It also directed the builder to pay Rs 1 lakh as compensation and Rs 1 lakh as cost of litigation to each

homebuyer. The commission also slapped a fine of Rs 5 lakh on the company for indulging in unfair

trade practices and directed it to deposit all the money within four weeks.

The NCDRC said homebuyers were ―put to loss and injury, a continuous position of mental agony and

physical harassment, hardship and difficulty, uncertainty and helplessness‖ even after paying

substantial amount and the builder has to refund the principal amount deposited by them with

equitable interest besides the lumpsum compensation and cost of litigation.

_________________________________________________________________________________

Page 4: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 4 of 30

HC raps MHADA over Mumbai's Esplanade Mansion

A division bench of Justices S C Dharmadhikari and Gautam Patel had last month directed

Mhada to take steps to secure the area around the building.

Does human life mean nothing, the Bombay High Court on Friday asked after it was informed that

the Maharashtra Housing Area Development Authority (MHADA) was yet to entirely secure the 150-

year-old dilapidated Esplanade Mansion in south Mumbai. A division bench o f Justices S C

Dharmadhikari and Gautam Patel had last month directed Mhada to take steps to secure the area

around the building.

The court was on Friday informed by MHADA lawyer Prakash Lad that barricades have been put

around the building and a separate way had been made for pedestrians to walk and for vehicular

movement.

The bench then sought to know if any portion hanging from the top of the building collapsed whether

it would collapse on the road or inside the barricades put up.

When Lad said the debris would fall on the road, the bench asked MHADA to put up netting covering

the entire building.

"We want netting around the entire building. Does human life mean nothing to you (MHADA)? All

this should have been done by now. The hanging portions are not going to give prior notice to Mhada

before collapsing," the court said.

The court suggested MHADA take assistance from those contractors who undertake work of netting

of mountains and hills during the monsoon season on the Mumbai-Pune Expressway to prevent

landslides.

"We are not satisfied with the safety measures undertaken. We want measures that cover the building

from top to bottom. Our primary concern is that in this rainy season there should be no untoward

incident," the court said.

The bench directed a senior officer from the traffic police department to visit the area and make

necessary suggestions to MHADA.

The occupants of the 150-year-old heritage structure in south Mumbai were evicted after the building

was declared dangerous.

The five-floor Esplanade Mansion, formerly known as Watson's Hotel, was built with cast iron

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/hc-raps-mhada-over-mumbais-esplanade-mansion/70100759

Page 5: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 5 of 30

fabricated in England and was enrolled in the list of '100 World Endangered Monuments'.

As per earlier directions from HC, the India Institute of Technology Bombay had conducted a

structural audit of the building and had recommended its demolition.

MHADA, in May this year, filed an application seeking a go-ahead from the HC to implement IIT's

recommendation.

However, the BMC's Heritage Committee and the Indian National Trust for Art and Cultural Heritage

(INTACH) were of the opinion that the building need not be demolished and can be repaired and

restored.

The bench on Friday said it would decide on this issue at a later stage, and that presently ensuring the

area around the building is secured was of importance.

The court also said that heritage experts and conservationists who are now coming forward and saying

the building should be repaired and restored should have done so when the condition of the building

had started deteriorating.

_______________________________________________________________________________

Page 6: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 6 of 30

Maharashtra: 51% consent for housing society redevelopment now

It had slashed consent for redevelopment of old, dilapidated cessed buildings, as also for slum

rehabilitation projects and smaller societies by bringing in an amendment to Maharashtra

Apartment Ownership Act (MAOA) in 2017.

To ease redevelopment of cooperative housing societies, the state government has reduced the consent

required from 70% to 51%.

It had slashed consent for redevelopment of old, dilapidated cessed buildings, as also for slum

rehabilitation projects and smaller societies by bringing in an amendment to Maharashtra Apartment

Ownership Act (MAOA) in 2017. The government resolution (GR) issued on Thursday by co-

operation department is applicable to cooperative housing societies. There are nearly one lakh

societies in Maharashtra, mostly in Mumbai and Thane.

"The decision was taken to ensure that redevelopment of housing societies can be expedited. Many

societies' redevelopment is stuck due to the developer not getting 70% consent. This will make the

process faster," said an official. But experts said it could go against residents and it was a pro-builder

move. They said it could lead to more litigation. "It could lead to more litigation as the number of

disgruntled members will be more. The 51% consent may lead to making the minority group more

vulnerable, giving the developer a free run,'' said advocate Manoj Shinde.

The GR also said that the developer should deposit 20% of the total project cost with the society and

should complete it in three years.

________________________________________________________________________________

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/residential/maharashtra-51-consent-for-housing-society-redevelopment-now/70103136

Page 7: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 7 of 30

Land titling bill to be introduced in winter session of Maharashtra

assembly

The land title bill was supposed to ensure greater transparency in all land transactions.

The much-awaited land titling bill, cleared by the Maharashtra state cabinet, will now be passed in the

winter session of the state assembly, official sources said.

The bill was cleared by the cabinet but because of some technical issues it has been pushed to the next

session. Officials stated that the bill will have to be re-introduced before the house in the winter

session.

The land title bill was supposed to ensure greater transparency in all land transactions.

The bill proposes to make all land title records available in one office with the coordination of the

property registration department as well as the revenue department.

By bringing all records pertaining to immovable properties currently available with different agencies

— registration department, survey and land records — under one office, the government wants to

make it easier for citizens to access the information.

Pilot projects can be rolled out in the districts once the proposal for the Maharashtra Land Titling

Act is cleared but now it will have to wait, stated officials.

The Act will provide a single-window mechanism for authentication of land titles. At present, it is left

to an individual to ascertain the title of a property. Under the proposed system, the title registration

officer will carry out the process of preparation, maintenance and updating of the title register,

officials said.

State settlement commissioner and director of land records, S Chockalingam, who was instrumental in

pursuing this initiative, said it would enable ease of doing business and bring about transparency in

the process but now it will be re-introduced in the coming session.

_______________________________________________________________________________

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/land-titling-bill-to-be-introduced-in-winter-session-of-maharashtra-assembly/70100880

Page 8: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 8 of 30

Delhi HC to hear builders' plea to bar buyers from approaching

consumer forums

While admitting the two cases, a single judge bench of Justice Yogesh Khanna had issued

notices to the respondents and the court is scheduled to hear the cases on Monday.

In yet another effort to bar homebuyers from approaching consumer forums to seek refund or

compensation in delayed incomplete projects, two builders have approached the Delhi high court

pleading that complaints relating to ongoing projects should only be referred to the Real

Estate RegulatoryAuthority (RERA) and not to consumer forums.

While admitting the two cases, a single judge bench of Justice Yogesh Khanna had issued notices to

the respondents and the court is scheduled to hear the cases on Monday. The HC had put proceedings

before the National Consumer Disputes Redressal Commission(NCDRC) on hold.

In both cases, the NCDRC has decided in favour of the buyers and the builders have challenged them

in the HC.

The two builders — Today Homes & Infrastructure Ltd and Ramprastha Promoters & Developers Pvt

Ltd — have asked whether NCDRC or any other consumer fora are ―precluded‖ from dealing with the

grievances of the customers of ―ongoing projects‖ which fall under RERA. The law came into force

from May 1, 2017, and it specifies that RERA provisions are applicable to all incomplete or ongoing

projects across the country.

The petitioners have submitted that Section 71 of RERA says if a complaint is pending before any

consumer fora, then the consumer with the permission of the forum ―may‖ withdraw the pending

complaint and ―may‖ file an application before the real estate regulator. They have submitted that

Section 79 of the Act bars jurisdiction of courts to entertain any compliant after the Act has come into

force. They have pleaded that since in both the cases the complaints against builders were filed before

NCDRC after the law came into force, the commission had no jurisdiction to entertain them.

Earlier, some state government-appointed real estate regulators had suggesting barring homebuyers

from approaching consumer forums to seek compensation and refund. They had claimed that

consumer forums were more liberal in ordering refund, which jeopardised the chance of completing

projects.

Newspaper/Online ET Realty (online)

Date July 08, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/delhi-hc-to-hear-builders-plea-to-bar-buyers-from-approaching-consumer-forums/70121233

Page 9: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 9 of 30

However, despite such demands, the Union cabinet has included ―real estate‖ as a service under the

proposed Consumer Protection Bill. This enables homebuyers to approach consumer forums.

Abhay Upadhyay of Fight for RERA, an NGO that campaigned for passage of the law, said all

sections of RERA were discussed at length by Bombay high court which heard the matter on direction

of Supreme Court when builders challenged its constitutional validity. ―This is now settled that

Section 71 only provides option to complainant to withdraw its complaint and file it before RERA and

it is not a mandatory provision. Section 79 only bars civil courts and not consumer forums,‖ he added.

______________________________________________________________________________

Page 10: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 10 of 30

Pune wall collapse: Magisterial remand for Kanchan Group partners

A total of 15 construction workers and their family members were killed after the retaining wall

of Alcon Stylus caved in on eight huts at an under-construction site of Kanchan Group project,

Royal Exotica, on June 29.

The Pune cantonment court on Saturday sent two partners of a realty firm, who were arrested in

connection with the wall collapse in Kondhwa, in magisterial custody remand for 14 days.

A total of 15 construction workers and their family members were killed after the retaining wall of

Alcon Stylus caved in on eight huts at an under-construction site of Kanchan Group project, Royal

Exotica, on June 29.

The Kondhwa police had arrested partners Vivek Agarwal (32) and Vipul Agarwal (30) under

sections 304 (culpable homicide not amounting to murder) and 34 (common intention) of the IPC.

Police later invoked sections 308 (attempt to commit culpable homicide) of the IPC and 3 (2), (L), 2

(m) and 13 (1) of the Maharashtra Ownership Flat Act in the FIR registered against the

builders/developers/partners of Alcon Landmarks and Kanchan Group, and others.

The Agarwal brothers were produced before the court after their police custody remand ended on July

6. The police filed a remand report for seeking extension of their custodial remand for four days on

the grounds that they were involved in serious crime. The prosecution told the court that their

custodial interrogation was essential to arrest others on the run.

Opposing the prosecution plea, defence lawyer Sanjay Agarwal told the court their custodial

interrogation was not essential as the court had given sufficient time to police to conduct investigation

since their arrest on June 29. After hearing both sides, the court sent them to magisterial remand. The

Agarwal brothers are expected to file bail plea at sessions court on Monday.

_________________________________________________________________________________

Newspaper/Online ET Realty (online)

Date July 07, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/pune-wall-collapse-magisterial-remand-for-kanchan-group-partners/70112168

Page 11: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 11 of 30

Kolkata civic body needs more building demolition squads

According to the practice prevalent in the KMC buildings department, every time a dilapidated

building collapses, department officials send an SOS to a private contractor for demolition of

the insecure parts.

The recent death of a demolition worker of a private agency engaged by the KMC buildings

department to raze an insecure building in a north Kolkata locality has prompted the civic brass to

create a building demolition cell of its own.

According to the practice prevalent in the KMC buildings department, every time a dilapidated

building collapses, department officials send an SOS to a private contractor for demolition of the

insecure parts. Apart from demolishing insecure buildings, the contractor needs to pull down illegal

buildings from time to time.

The overstressed demolition contractor has been reeling under severe manpower shortage and lack of

modern equipment. ―The time has come to set up our own demolition squad borough-wise to get rid

of hassles,‖ said a KMC buildings department official.

Last week, senior officials of the department had taken stock of a number of rickety buildings as the

monsoon has set in and a section of such buildings carry the risk of collapse due to heavy rain. ―We

have spotted many wobbly buildings in six boroughs and have asked the borough officials to keep a

constant watch on these buildings through the monsoon. We need to pull down some badly damaged

parts of some of these buildings right now to save lives,‖ said a KMC building department official.

Some of these buildings that need immediate demolition are located in areas like Cossipore, Paikpara,

APC Roy Road, MG Road, Chittaranjan Avenue, Chitpore, Burrabazar, Bhowanipore, Metiabruz,

Rashbehari Avenue and Tollygunge, among others.

However, a section of civic officials feel the absence of multiple demolition squads will make it an

uphill task for the buildings department to pull down insecure structures in case of collapses. A KMC

official recalled that the private demolition squad had to pull down as many as 10 structures in three

days last monsoon. ―It is indeed a tough task and we should set up demolition squad in each borough

to prevent disasters,‖ a civic official said. A past proposal for setting up demolition squad for every

borough had remained on paper.

_____________________________________________________________________________

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/kolkata-civic-body-needs-more-building-demolition-squads/70103295

Page 12: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 12 of 30

NGT slams inaction against illegal buildings in South Delhi

According to a status report filed by Mehrauli SDM, the encroachment removal drive was to

start on August 10, 2017, however it stated that around 3,000 people have encroached the forest

land which is creating difficulty.

The National Green Tribunal (NGT) has rapped the AAPgovernment over its inaction against

unauthorised constructions in south Delhi's Jaunapur and Dera Mandiforest areas. The tribunal said

that despite a December 2015 order, which directed removal of illegal constructions in the Ridge

areas, no action had been taken.

According to a status report filed by Mehrauli SDM, the encroachment removal drive was to start on

August 10, 2017, however it stated that around 3,000 people have encroached the forest land which is

creating difficulty. A bench headed by NGT chairperson Adarsh Kumar Goel said the tribunal could

not be stalled by a counsel who is not available when the case is taken up.

________________________________________________________________________________

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/ngt-slams-inaction-against-illegal-buildings-in-south-delhi/70102324

Page 13: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 13 of 30

Kochi flat demolition: Outrage grows against builders, erring officials

Builders, with the aid of local body officials, went ahead and constructed these structure despite

pending legal disputes. Most flat owners are of the view that they were kept in the dark about

these developments.

On Friday, the Supreme Court bench headed by Justice Arun Mishra– which had ordered demolition

of flats in Kochi for violating CRZ guidelines – disapproved a vacation bench‘s order staying the

demolition for six weeks. Now, there is a growing demand on social media to act against the builders

who executed the project and local body officials who issued permits.

―The then secretary of Maradu panchayat (now municipality) is responsible for issuing approvals and

building permits despite the violation of CRZ norms. State government should initiate disciplinary

action against the erring official,‖ said advocate Harish Vasudevan. In case other officials are

involved in giving sanctions to these structures, they too should also face disciplinary action.

Builders, with the aid of local body officials, went ahead and constructed these structure despite

pending legal disputes. Most flat owners are of the view that they were kept in the dark about these

developments.

Meanwhile, Vasudevan said the district collector can approach the chief judicial magistrate (CJM)

with a chargesheet stating it has been found that builders or companies have constructed these

buildings violating CRZ norms and the Supreme Court has ordered their demolition. ―Legal

proceeding can be initiated under Section 19 of Environment Protect Act. If found guilty, CJM can

slap jail terms or fine,‖ he said.

Former chairman of Kerala State Biodiversity Board VS Vijayan said that flat owners should be given

compensation. ―The compensation should be raised from those who issued permits and others who

constructed the structure. They are responsible for this CRZ violation. There is a need to execute the

SC order as it will send a strong message to government officials and builders who violate

environment norms,‖ he said.

When flat owners – through senior advocate Ajith Kumar Sinha –requested a vacation bench of

Justices Arun Mishra and MR Shah to extend the deadline for demolition of flats so that they can

make alternative arrangements, the bench dismissed it saying, ―You (flat owners) can move

appropriate forum to claim compensation against the builders.‖

Newspaper/Online ET Realty (online)

Date July 07, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/kochi-flat-demolition-outrage-grows-against-builders-erring-officials/70112271

Page 14: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 14 of 30

However, Vasudevan said that seeking compensation from builders will remain a tough task under

existing norms. ―There will be a need to check the clauses in the agreement made between the buyer

and the builder,‖ he said.

Meanwhile, sources within the district administration said that collector S Suhas is keenly studying

the issues related to Maradu apartments. ―It is learnt that the collector has spoken to his predecessor

about the issue and the SC order,‖ said the source, adding that he would soon take a decision.

______________________________________________________________________________

Page 15: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 15 of 30

Talegaon Dhabade civic body to conduct structural audit of old

buildings

The move follows two wall collapses in Kondhwa and Ambegaon, which claimed 21 lives.

The Talegaon Dhabade Municipal Council (TDMC) on Saturday directed developers to conduct

structural audit of 30-year-old and above buildings and submit the report within a fortnight.

The move follows two wall collapses in Kondhwa and Ambegaon, which claimed 21 lives. ―There are

several old structures, mainly in the old areas of the town, which were constructed in 1990‘s.

Therefore, it is necessary to carry out structural audit of these buildings for ensuring safety of the

residents,‖ chief officer Vaibhav Avare Aware of TDMC told TOI.

―Earlier, we had sent notices to the residents of old structures to vacate them, which failed to evoke

any positive response. This monsoon again, we have again sent notices, urging them to vacate these

structures,‖ Aware said.

As per TDMC records, there are over 100 dilapidated structures in its limits. ―Due to consistent

political interference and lack of support from elected members, we could not launch any eviction

drive in the past. We have categorically informed people that if any tragedy takes place, the TDMC

will not be held responsible,‖ a civic official said.

_______________________________________________________________________________

Newspaper/Online ET Realty (online)

Date July 07, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/talegaon-dhabade-civic-body-to-conduct-structural-audit-of-old-buildings/70112193

Page 16: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 16 of 30

Chandigarh housing board to hold another outstanding rent collection

campaign

Last month, the authorities had organised special camps for 10 days and collected Rs 6.5 crore

from 2,300 defaulters.

The authorities of Chandigarh Housing Board have decided to organise a three-day campaign (from

July 10 to July 12) at various locations in the city to collect outstanding rent from defaulting owners

of small flats.

The authorities said they had to collect more than Rs 20 crore in outstanding from the defaulters. The

camps will be organised between 8 am and 1 pm on the aforementioned dates.

Last month, the authorities had organised special camps for 10 days and collected Rs 6.5 crore from

2,300 defaulters.

The camps were set up at seven locations in Chandigarh - Dhanas, Ramdarbar, Maulijagran, Sector 38

West, Sector 49, Sector 56 and Industrial Area Phase I.

Chandigarh Housing Board has issued final showcause notices to 250 allottees and first-time notices

to 6,000 allottees, who have failed to clear their dues.

They have been given 15 days to clear the outstanding amount, failing which allotments will be

cancelled and eviction process will be initiated.

The detail of outstandings against each allottee/licensee of small flats is available on

www.chbonline.in.

In case there is any discrepancy, dispute, the allottee/licensee may pay the admitted outstanding dues

and contact the colony branch at the office of Chandigarh Housing Board (Recovery Section, Block

'C') along with the proof of payment for reconciliation.

______________________________________________________________________________

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/chandigarh-housing-board-to-hold-another-outstanding-rent-collection-campaign/70100988

Page 17: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 17 of 30

SC issues notice after Maharashtra challenges HC order for demolition

of lakhs of illegal construction

The SC will hear both sides after six weeks now but in the meantime the state’s special counsel

Anil Sakhare told the SC that it won’t be taking any action of demolition till then.

Maharashtra government on Friday said occupants in lakhs of illegal structures built on government

land or lands reserved under the Development plan (DP) across state would face demolition by a

Bombay high court and sought a stay from the Supreme Court. The SC bench headed by Chief

Justice Ranjan Gogoi and comprising Justices Deepak Guptaand Aniruddha Bose admitted the state‘s

special leave petition (SLP) and issued notice on its plea for interim relief of stay of the HC order.

The SC will hear both sides after six weeks now but in the meantime the state‘s special counsel Anil

Sakhare told the SC that it won‘t be taking any action of demolition till then.

The stay, was earlier refused by the HC. The SC order of issuance of notice to original petitioners who

had filed public interest litigation (PIL) against the new law, comes as a huge relief to occupants of

such unauthorised structures.

The state legal team of Sakhare, Nishant Katneshwarkar and Rohan Mirpuri sought the interim relief

as it said regularisation specifically was provided by the new amendment.

The HC had last November read down a provision added by the state in 2017 by introduction of

section 52A under the MRTP Act, to mean that regularization was impermissible and directed

identification and demolition of all such illegal structures across Navi Mumbai, CIDCO and MIDC

areas.

A PIL filed in HC had challenged the validity of new section 52A of the Maharashtra Regional and

Town planning Act, 1966 which provides for enbloc regularization of a very large number of illegal

structures built in Maharashtra on or before December 31, 2015.

If there is illegal construction on government land or a plot reserved under the DP, those construction

prior to introduction of section 52 A could not be regularized but the amendment under section 52 A

provided a special ‗non obstante‘ clause which said with a no objection certificate (NOC) from a

concerned department or by shifting the original reservation, constructions could be regularized.

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/regulatory/sc-issues-notice-after-maharashtra-challenges-hc-order-for-demolition-of-lakhs-of-illegal-construction/70100669

Page 18: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 18 of 30

Such ‗non obstante clause is usually used to indicate that its provision should prevail over any other

contrary provision in law.

The HC had directed CIDCO, MIDC and Navi Mumbai Municipal Corporation to carry out a survey

within their respective jurisdictions as Planning Authorities for identifying and locating the total

number of illegal constructions. The survey was to be done in a year.

The first report of quarterly reports sought on demolition was to be submitted on March 31, 2019.

The HC judgment by Justice Abhay Oka in November 2018 had even quoted Socrates to say, 'By far

the greatest and most admirable form of wisdom is thatneeded to plan and beautify cities and human

communities' and accepted argument that the new law would defeat the very concept and purpose of

town planning.

The HC judgment, had significantly said, ―We hold that section 52A of the MRTP Act shall be read

down to mean that non obstante clause in subsection (1) of section 52A does not enable the Planning

Authorities or the State Government to compound unauthorized developments which are contrary to

the provisions of the Development Plans/Regional Plans under the MRTP Act and the Development

Control Regulations framed under the MRTP Act. Hence, by exercising the power undersection 52A,

unauthorised development which is contrary to the provisions of the Development Plans/Regional

Plans under the MRTP Act and the Development Control Regulations framed under the MRTP Act

shall not be declared as a compounded structure (regularised).‖

______________________________________________________________________________

Page 19: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 19 of 30

Housing ministry gets Rs 48,000 crore in Budget 2019, sees about 12%

hike

The Pradhan Mantri Awas Yojana (Urban) has been given Rs 6,853.26 crore as against Rs 6,505

crore in 2018-19.

The Housing and Urban Affairs Ministry's budgetary provisions were pegged at Rs 48,000 crore in the

Union Budget 2019-20, a hike of nearly 12 per cent from 2018-19.

The Pradhan Mantri Awas Yojana (Urban), an ambitious programme of the Modi government, has

been given Rs 6,853.26 crore as against Rs 6,505 crore in 2018-19.

There has been an increase of nearly 25 per cent in the allocation to metro projects across the country.

A sum of Rs 17,713.93 crore has been allocated in this regard in the Budget against Rs 14,864.60

crore in 2018-19.

"Under the Pradhan Mantri Awas Yojana (Urban), over 81 lakh houses with an investment of about

Rs 4.83 lakh crore have been sanctioned of which construction of about 47 lakh houses has started,"

Finance Minister Nirmala Sitharaman said.

"Over 26 lakh houses have been completed of which nearly 24 lakh houses delivered to the

beneficiaries," she said.

The Delhi Metro Rail Corporation (DMRC) has been given Rs 414.70 crore grant as against Rs 50

crore in 2018-19.

The government has set aside Rs 19,152 crore for the Mass Rapid Transit System (MRTS) as against

the previous financial year's budgetary allocation of Rs 15,600 crore.

The Atal Mission for Rejuvenation and Urban Transformation (AMRUT) scheme, which aims at

ensuring robust sewage networks, water supply and other infrastructure to improve the quality of life

in urban areas, has been given Rs 7,300 crore. The allocation was Rs 6,400 crore in 2018-19.

The Smart Cities Mission, under which the government has selected 100 cities, has been granted Rs

6,450 crore as against Rs 6,169 crore in the 2018-19 financial year.

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/allied-industries/housing-ministry-gets-rs-48000-crore-in-budget-2019-sees-about-12-hike/70100582

Page 20: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 20 of 30

Allocation to another flagship programme of the government, Swachh Bharat Mission, has been

increased to Rs 2,650 crore from Rs 2,500 crore in the previous financial year.

________________________________________________________________________________

Page 21: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 21 of 30

Nagpur: Mhada took Rs 118 crore 5-7 years ago, yet to hand over flats

As per the CAG report, Mhada started construction of High Income Group (HIG) Housing

Project with 320 flats at Empress Mill land on Subhash Road, Ganeshpeth, in December 2010 at

a cost of Rs56.08 crore.

Around 5-7 years ago, 314 people purchased flats from Nagpur board of Maharashtra Housing and

Area Development Authority (Mhada) by paying a whopping Rs 118.33 crore but are yet to get

possession of the flats. Left with no option, around 50 people have started to reside in the flats after

completing remaining works at their own expense.

The Comptroller and Auditor General of India (CAG) audit report submitted in the state legislature on

the concluding day of budget session on July 2 rapped Mhada for not giving possession of flats

despite recovering payments 5-7 years ago.

As per the CAG report, Mhada started construction of High Income Group (HIG) Housing Project

with 320 flats at Empress Mill land on Subhash Road, Ganeshpeth, in December 2010 at a cost of Rs

56.08 crore. ―Tenements were not handed over to the beneficiaries since Occupancy Certificate (OC)

was not obtained from Nagpur Municipal Corporation (NMC). The board applied for OC in March

2014 but was not given it for lack of environment clearance (EC). The board obtained EC in April

2017. EC made construction of sewage treatment plant (STP) mandatory, which the board is yet to

take up,‖ CAG said.

In reply to CAG, Mhada said the EC was not initially applicable to the project. ―EC became

mandatory following a notification of April 2011. And, condition of STP came up in April 2017,‖

Mhada said.

Finding Mhada‘s reply not tenable, CAG said NMC refused OC over pending EC, which was

mandatory as per notification dated September 2006. ―The failure on the part of Mhada to obtain EC

and install STP has resulted in denial of tenements to beneficiaries despite payment of sale price,‖

CAG said.

The CAG report notes Mhada is yet to give possession of all flats. A visit to the project, however,

revealed people residing in some 50 flats. The road connecting the flat scheme to Subhash Road is

incomplete. There are no whereabouts of commercial complex, podium garden, open spaces,

swimming pool, club house etc. Water can be seen accumulated in parking area in the basement and

ground floor. Sewage is leaking from pipelines and accumulated in parking area.

Secretary of one of the two housing societies Ramesh Londhe told TOI Mhada is yet to give the

Newspaper/Online ET Realty (online)

Date July 08, 2019

Link https://realty.economictimes.indiatimes.com/news/residential/nagpur-mhada-took-rs-118-crore-5-7-years-ago-yet-to-hand-over-flats/70121271

Page 22: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 22 of 30

registered sale deed. ―Mhada should have invited applications after completion of all works. But

applications were invited in 2012 with assurance to give possession in December same year. We made

payments as we did not want to lose the chance to own flat at such a location. There are no basic

amenities. Around 50 people are occupying the flats. They were paying rent elsewhere and also

installment for housing loans. They completed interior electrification and water works on their own,‖

he said.

Londhe said the two societies are also executing maintenance works with the help of contribution of

flat owners. ―Half of the lifts are not operational. There was no drinking water supply and we got it

recently from NMC after hard efforts. Also, quality of all types of works is suspect. Flat buyers have

approached various legal forums demanding compensation and immediate possession,‖ he said.

Mhada has also not completed works on fire systems, and not obtained fire compliance certificate.

Mhada chief officer Sanjay Bhimanwar said no possession of flats has been given till date. ―We have

completed physical works. Process to get fire compliance is underway. Project got delayed due to EC.

Also, works were completely halted for 2-3 years,‖ he said.

Shockingly, Mhada had planned the project in 2003. Work to build 320 flats was given to a private

company in 2010 with a deadline of two years.

INFO

Project: Purchased 7.75 hectare Empress Mill land for Rs 24.13 crore in September 2003. Housing

project with 500 flats planned with 320 in phase-I and 180 in phase-II along with a commercial

complex. It was approved in 2005. Private company appointed for 320 flats in 2010 with deadline of

two years. Works yet to be completed. Works on phase-II started some months ago

Flats: 220 flats are 3 BHK measuring 103-225 sq m and costing Rs 40-65 lakh. 100 flats are 2-BHK

measuring 74-173 sq m and costing Rs 26-43 lakh

Delay: Mhada was to invite applications after completion of works. But applications were invited in

2012, Rs 118.33 crore payment taken from 314 people. Possession assured in December 2012 but not

yet given. Sale deeds too still awaited. Around 50 people residing in flats for last 1-2 years

Problems: Contractor failed to complete works. Mhada took environment clearance very late, in 2017,

after NMC asked for it. Mandatory STP as per EC yet to be constructed. Fire compliance certificate

awaited. Work on podium garden, swimming pool, club house, commercial complex etc yet to begin.

Flat owners allege interior works of inferior quality. Road works also not completed.

__________________________________________________________________________________

Page 23: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 23 of 30

Flats with imported tiles, bath fittings to cost up to Rs 5 lakh more in

Lucknow

According to experts, these imported items are generally used in high-end houses costing more

than Rs 50 lakh. Buyers of these properties prefer luxury fittings and furniture.

High-end apartments and row houses in the city are set to become more expensive with the decision of

the finance minister to impose 5% customs duty on imported tiles, marble, metal fittings, furniture and

windows. The impact will mean escalation in the cost of around 2,800 high-end flats and bungalows

under construction in the city.

According to experts, these imported items are generally used in high-end houses costing more than

Rs 50 lakh. Buyers of these properties prefer luxury fittings and furniture. The cost of imported tiles,

marbles, furniture, windows and bathroom fittings is around 40% of the total cost of the house,

depending on the quantity and quality of the products used. The overall cost of such under-

construction houses can now go up by up to Rs 5 lakh.

Prakhar Khanna, a government employee, said, ―My 4BHK house is under construction

in Gomtinagar Extension. I was planning to get Italian marble flooring in my house. However, now I

have decided to drop the idea because imposition of customs duty will increase the prices, taking them

beyond my budget.‖Businessman Jatin Krishna said, ―My family and I were planning to purchase

imported furniture, but won‘t be able to now as the increase in taxes has taken the price out of my

reach."

According to officials of Lucknow Development Authority, more than 1,200 highend flats being

constructed by it will be affected by the decision. Flats with total area of 1,200 sq ft or above made for

higher income group (HIG) buyers will now see an increase in price.

Confederation of Real Estate Developers Association of India (Lucknow Chapter) told TOI that as

many as four big private projects coming up in Chinhat and Matiyari and on Dewa Road and Sitapur

Road with around 1,600 flats in them will see a 5% increase in the principle amount.

The budget of underconstruction government and private buildings to be used as offices or for other

commercial purpose would also go up, experts said.

_______________________________________________________________________________

Newspaper/Online ET Realty (online)

Date July 07, 2019

Link https://realty.economictimes.indiatimes.com/news/residential/flats-with-imported-tiles-bath-fittings-to-cost-up-to-rs-5-lakh-more-in-lucknow/70112316

Page 24: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 24 of 30

Karnataka is fifth in Smart City implementation: U T Khader

Speaking at the DC office here on Friday, Khader said the government was taking steps to

increase the pace of works and enter the top three in the next six months.

Urban development minister UT Khader refuted allegations of the opposition that the state

government was purposely delaying Smart City works. He said the state was at the fifth place in the

country in implementing the project.

Speaking at the DC office here on Friday, Khader said the government was taking steps to increase

the pace of works and enter the top three in the next six months.

The minister said the Smart City Project was delayed due to tough rules and procedures of the Union

government. ―Initially, objection by MLAs and MPs for excluding them from the Smart City

committee also caused delays. Under this project, both the state and centre contribute Rs 100 crore for

the development of cities,‖ he said.

"It is a myth that cities will get smart just by the Rs 500 crore contribution of the Centre in five years.

In cities like Bengaluru, works of over Rs 3,000 crore are ongoing on behalf of the state government

and situation is similar in most cities,‖ he added.

Khader said the project of providing 24X7 water to entire Belagavi at a cost of Rs 420 crore will start

in the next three months by floating a tender notification.

He said the district has a good source of water and only needs to strengthen the supply chain.

Stating that the government has taken several measures to increase the income of urban local bodies

including computerization of property records, which Khader said had brought more than 9,000

properties under the tax net just in Belagavi City Corporation limits.

Khader warned builders of taking strict action against the illegal constructions. ―Many constructions

are coming up without any layout or sites and it is unacceptable. We will take strict action against

those engaged in constructing buildings at non-NA sites on the outskirts of Belagavi,‖he said.

When asked about illegal commercial activities at basements of buildings in the main market which is

causing traffic problems, the minister said he would check the facts with officials. He said the

government can‘t vacate such establishments suddenly without following proper procedure. Apart

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/infrastructure/karnataka-is-fifth-in-smart-city-implementation-u-t-khader/70103191

Page 25: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 25 of 30

from infrastructure development, there is also a need for making Belagavi as a safe city, he added.

Minister identifies substandard work

Khader found the quality of the gym being built at Ashok Nagar to be substandard during an

inspection of ongoing works in the city on Friday. The minister said the building had many leaks and

that water was seeping into its walls.

He instructed officials not to pay the contractor until proper work is done.

Khader also inspected the badminton court and swimming pool being built under the Smart City

Project on the same premises.

He directed officials to consider developing a football stadium as the available space was huge. Later,

he inspected the ongoing work of KPTCL Road in Shivbasav Nagar.

During a review meet of Smart City works, Khader suggested officials to install vigilance cameras

and speakers on the roadsides in the city to make Belagavi a smart and safe city. He said people will

be able to see Smart City works on four LED TVs to be installed at different parts of the city at a cost

of Rs 70 lakh.

Belagavi rural MLA Laxmi Hebbalkar, Belagavi North MLA Anil Benake, former MLA Firoz Sait

and Belagavi City Corporation commissioner Shashidhar Kurer accompanied him.

_____________________________________________________________________________

Page 26: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 26 of 30

With tunnelling to begin soon, Bengaluru Metro Rail Corporation takes

steps to ensure building safety

Data sourced by TOI revealed that 19 buildings developed cracks during Phase 1.

With giant tunnel boring machines (TBMs) set to drill and cut through the underbelly of Bengaluru‘s

commercial areas, the Bangalore Metro Rail Corporation (BMRCL) is taking preventive measures to

reduce any damage to buildings.

Data sourced by TOI revealed that 19 buildings developed cracks during Phase 1. Of these, 18 cases

were reported during the construction of Green Line, particularly the underground sections

between Sampige Road and KR MarketMetro stations.

It was also found that BMRCL paid Rs 2.8 crore compensation to owners of the 19 buildings for the

damage. Landmark buildings like Vani Vilas Hospital and Victoria Hospital had developed cracks

during the construction of Phase 1. In February 2018, a building near Ragigudda tilted during work on

the upcoming Yellow Line.

Allaying fears, a senior BMRCL official said they are taking steps to prevent any damage to

buildings, particularly during the tunnelling work.

―We‘ve begun a pre-building condition survey of buildings within the influence zone of work,

especially along the city‘s longest underground Metro corridor between Dairy Circle and Nagawara

(14km). We‘re carrying out ground improvement by advance surface grouting along the alignment

and also undertaking structural supporting and bracing for structurally unsafe buildings. We have

formed a round-the-clock monitoring team for tunnelling work,‖ he added.

The official said they are using devices like crack meter, tilt meter, seismograph, surface settlement

marker (pavement/soil) and building settlement point to monitor vibrations during construction.

There are also concerns regarding safety of old and weak structures in areas like Shivajinagar,

Tannery Road and Pottery Town. In fact, members of 150-year-old All Saints Church were worried

that vibrations caused by underground tunnelling may affect the building.

Structural experts said underground construction causes vibrations that penetrate the surface and

affect weak structures. ―Underground construction involves a lot of vibration. So if a building has

cracks, they could widen. Houses are built with concrete, brick and mortar. So if you are trying to

Newspaper/Online ET Realty (online)

Date July 06, 2019

Link https://realty.economictimes.indiatimes.com/news/infrastructure/with-tunnelling-to-begin-soon-bengaluru-metro-rail-corporation-takes-steps-to-ensure-building-safety/70102383

Page 27: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 27 of 30

cause any movement, it becomes difficult for the material to handle and as a result, it cracks,‖ said an

expert.

______________________________________________________________________________

Page 28: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 28 of 30

No agency keeping count of construction site deaths in Pune

Also, based on official interactions, it is evident that each of the agencies depends on somebody

else and none of them has an independent mechanism to collect data.

There is no single agency — the police, the labour department or Credai, the industry body — keeping

a record of the number of people killed in accidents at construction sites. As a result, the data is both

inadequate and confounding.

While the labour department in Pune has filed prosecutions in 27 cases involving 60 worker deaths in

the past 3.5 years, Nitin Pawar, the general secretary of the Bandhkam Mazdoor Sabha, said number

of worker deaths per year easily crosses the 100-mark in the PMRDA region alone. ―Every month,

about 8-10 deaths are reported in newspapers,‖ he said.

Also, based on official interactions, it is evident that each of the agencies depends on somebody else

and none of them has an independent mechanism to collect data. This, experts feel, hinders policy-

making and a systematic effort to curb construction-related deaths.

The labour office depends on data collected from reported accidents, police FIRs, newspaper clippings

and information received from non-governmental organisations (NGO). However, construction work-

related deaths are often under-reported.

―Many developers do report accidents. Some don‘t. It is, however, mandatory,‖ said Vikas Panvelkar,

deputy labour commissioner of Pune.

The labour department has, of late, taken some steps to get more workers registered. ―The

registrations require the worker to be working at a site for 90 days, have a bank account and an

Aadhaar number for direct benefit transfer,‖ said Panvelkar.

Most agencies, however, focus on providing benefits like education, health, social security benefits to

the workers and their families. Much of the labour department‘s spend has been on this and little

money has been allocated to safety. Even Maharashtra building and construction worker‘s welfare

board and Credai-Kushal focus on skilling. Satish Magar, a member, said the board‘s role was limited

to workers‘ welfare and not to monitor safety procedures.

Newspaper/Online ET Realty (online)

Date July 07, 2019

Link https://realty.economictimes.indiatimes.com/news/allied-industries/no-agency-keeping-count-of-construction-site-deaths-in-pune/70112346

Page 29: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 29 of 30

Infrastructure key to $5-trillion goal

For financing the infrastructure sector, Credit Guarantee Enhancement Corporation will be

set-up in 2019-20

Finance minister Nirmala Sitharaman presented her first budget outlining the vision for achieving a $5

trillion economy by 2024-25, driven by investments. The push for investments will be from the

infrastructure sector, in particular roads, railways, airports and inland waterways, through higher

government and private investments.

For financing the infrastructure sector, Credit Guarantee Enhancement Corporation will be set-up in

2019-20. Affordable housing, too, will benefit under Pradhan Mantri Awaas Yojana (PMAY) and tax

incentives.

―Make in India‖, too, got a boost with the likely rationalisation of labour laws into four codes.

For MSMEs, the finance minister has raised the ceiling of 25 per cent tax rate to a revenue of Rs 400

crore (Rs 250 earlier) and introduced a platform to discount bills. This should ease the liquidity for

MSMEs.

For incentivising domestic production, custom duties have been increased selectively. In line with the

ambition of a cleaner and greener India, customs duties on E-vehicles have been reduced and tax

deduction on interest paid on such loans has been introduced.

The minister also outlined the need to bring in a new education policy. For the real estate sector, a

model tenancy law will be circulated to the states.

In order to kickstart growth, the finance minister has allocated Rs 70,000 crore to recapitalise Public

Sector Banks (PSBs), which will boost credit delivery in the economy. For increasing liquidity to

NBFCs, the government will provide one-time partial credit guarantee to PSBs for first loss up to 10

per cent. Given the inter-connectedness between NBFCs, HFCs and banks, HFCs will now be under

the supervision of the Reserve Bank of India.

On the revenue front, the finance minister‘s revenue assumptions are quite realistic. Given the

difference between actual tax collections in 2018-19 and interim budget estimates, markets were

worried about fiscal slippage in the year.

Newspaper/Online The Telegraph

Date July 08, 2019

Link https://www.telegraphindia.com/business/union-budget-2019-infrastructure-key-to-5-trillion-goal/cid/1694024?ref=business_business-page

Page 30: 08-July-2019€¦ · Wave Garden housing project in Mohali in 2012. The builder — Country Colonisers Pvt Ltd — had promised to hand over possession of flats within three years

Page 30 of 30

Tax revenues are now estimated at Rs 24.6 lakh crore in 2019-20 compared with Rs 25.5 lakh crore in

the interim budget. Income tax and GST collection target for 2019-20 has been pared down, in line

with GST collections in the first two months of the year. At the same time, revenue from customs and

excise duties has been revised upwards on the back of higher custom duties and excise duty/ cess on

petrol and diesel (Rs 2/litre).

While the Centre‘s tax revenue target for 2019-20 has been reduced by Rs 55,500 crore (from the

interim budget), the non-tax revenue target has been revised upwards by Rs 40,500 crore as the

government now expects a higher income from dividends, railways and the 5G auction.

Disinvestments receipts are now expected at Rs 1.05 lakh crore in 2019-20 compared with an earlier

target of Rs 80,000 crore since the government has decided to reduce the shareholding in non-

financial undertakings to less than 51 per cent on a case-by-case basis.

On the expenditure side, the budget has more or less retained the estimates of the interim budget. The

agriculture sector has got the maximum boost followed by health and education.

_________________________________________________________________________________