06019279

Embed Size (px)

Citation preview

  • 8/10/2019 06019279

    1/8

    1

    Abstract--In recent years, a substantial amount of photovoltaic

    (PV) generations have been installed in Japanese power systems.

    However, the power output from the PV is random andintermittent in nature. Therefore, the PV generation poses many

    challenges to system operation. To evaluate impacts of the

    behavior of PV on power supply reliability, we have developed

    power supply reliability evaluation model considering a large

    integration of PV generation into power system. As a result, the

    power supply reliability is getting worse as the PV penetration

    increases. To mitigate this issue, we have proposed that pumped

    storage hydro power plant (PSHPP) is used to improve the

    reliability. However, its operation may increase the power system

    operational cost. In this paper a new method for scheduling the

    effective operating pattern for PSHPP that makes it possible to

    improve both reliability and economy is presented.

    Index Terms--Genetic Algorithm, Monte Carlo Simulation,Optimal Scheduling, Photovoltaic Generation, Power Supply

    Reliability, Pumped Storage Hydro Power Plant, Surplus Power

    Problem, Tabu Search.

    I. INTRODUCTION

    HE role of renewable energy resources is remarkable in

    Low Carbon Society. In recent years, a large amount of

    photovoltaic (PV) and wind power generations have been

    installed in power systems around the world. However, Japan

    is not an appropriate site to install a large amount of wind

    power generations. Therefore, the Japanese government aims

    at installing a large amount of PV in power system.

    Since the power output from the PV is random andintermittent in nature, the PV generation poses many

    challenges to the power system operation. When the load

    demand is very small and at the same time the PV generates a

    large amount of power, the balance between power supply and

    demand cannot be maintained. This problem is called surplus

    power problem". In addition to the surplus power problem, it

    Ryota Aihara is with the Department of Electrical Engineering, The

    University of Tokyo, 7-3-1, Hongo, Bunkyo-ku, Tokyo 113-8656, Japan

    (email: [email protected]).

    Akihiko Yokoyama is with the Department of Advanced Energy, The

    University of Tokyo, 5-1-5 Kashiwanoha, Kashiwa, Chiba 277-8561, Japan.

    Fumitoshi Nomiyama and Narifumi Kosugi are with the Power System

    Engineering Group, Research Laboratory, Kyushu Electric Power Company,Inc., Fukuoka, 815-0032, Japan.

    is also necessary to consider the intermittent and uncertain

    output characteristic of PV.

    Therefore, various kinds of counter measures have been

    considered when a substantial amount of PV generation is

    installed into a power system. Though Battery Energy Storage

    System (BESS) could be considered as a solution of these

    issues, their high cost is preventing them from being

    considered as a solution in most situations. This paper

    proposes the effective use of Pumped Storage Hydro Power

    Plant (PSHPP). PSHPP is installed originally for load leveling

    within one day. The energy is stored in the form of water

    pumped up from a lower reservoir to an upper reservoir. The

    PSHPP is usually operated as a generator in the daytime and a

    pump in the nighttime. A new operation scheduling of PSHPP

    is proposed to solve this problem in this paper. It will be

    operated with the proposed pattern solving the surplus powerproblem caused by the PV generation. The authors have

    already proposed how the PSHPP operation pattern is changed

    effectively to improve the power system reliability in case of a

    large integration of PV into the power system [1]. However,

    the scheduling method for obtaining the optimal PSHPP

    operation pattern that makes it possible to improve both

    reliability and economy has not been developed yet. In this

    paper, we propose a new method for planning PSHPP

    operation pattern considering the surplus power problem,

    power supply reliability and fuel cost reduction, which is

    represented by pareto optimal solutions. The power supply

    reliability and the fuel cost are estimated for each PSHPP

    operation plan by using Monte Carlo simulation.

    II. POWER SUPPLY RELIABILITY EVALUATION MODEL

    A. Pumped Storage Hydro Power Plant

    In PSHPP, the energy is stored in upper reservoir in the

    form of water. Therefore, it should be operated within the

    capacity of the upper reservoir. In this paper, the amount of

    the stored water in the upper reservoir is considered as energy.

    It can be operated 6 to 8 hours continuously when the

    operation starts from the full capacity of the upper reservoir.

    Therefore, the capacity of the upper reservoir is assumed to be

    7-hour operation of the rated power at generator mode.

    Optimal Operation Scheduling of Pumped

    Storage Hydro Power Plant in Power System

    with a Large Penetration of Photovoltaic

    Generation Using Genetic AlgorithmRyota Aihara, Akihiko Yokoyama,Member, IEEE, Fumitoshi Nomiyama, and Narifumi Kosugi

    T

    Paper accepted for presentation at the 2011 IEEE Trondheim PowerTech

    978-1-4244-8417-1/11/$26.00 2011

  • 8/10/2019 06019279

    2/8

    2

    In general, there are two types of PSHPP, fixed speed one

    and adjustable speed one. The fixed speed PSHPP cannot

    adjust the input power when it operates as a pump. The

    adjustable speed one can adjust the input power. It is coming

    into the limelight because of its adjustable characteristics in

    the pump mode [2]. Therefore, the PSHPP is assumed to be anadjustable speed PSHPP in this paper.

    Fig. 1. Flowchart of Power Supply Reliability Calculation

    B. Reliability Evaluation Model

    The proposed evaluation method of the power supply

    reliability is summarized as a flowchart in Fig.1. In this paper,

    it is assumed that the operation schedule of PSHPP is planned

    for a week. The simulation period is a week and its sampling

    time is 1 hour. First, based on the available data, the

    generation schedule for 7 days is determined. The available

    data consist of load demand given by power system model,

    theoretical PV generation output and PSHPP operation pattern.

    The generation schedule is determined by solving

    optimization problem, which minimizes the fuel cost by using

    Dynamic Programming (DP). Next, Monte Carlo simulation is

    carried out considering uncertainties of load demand, PV

    output and generator failure. During the period of the

    simulation, when the power supply and demand imbalance

    occurs, the thermal generator outputs are adjusted and PSHPP

    is operated to avoid the imbalance. If it cannot be avoided,

    this period is regarded as supply interruption. We assume that

    both supply shortage and surplus power supply are defined asthe supply interruption.

    1) Generation Scheduling

    As mentioned before, generation scheduling is found by

    solving an optimization problem in which the fuel cost is

    minimized. In this paper, it is assumed that nuclear and hydro

    power plants are always operated at the rated power output.

    As a result, only the fuel cost of thermal plants is considered

    here. The fuel cost of a thermal plant is given in (1).

    iiiiii cPbPaF 2 (1)

    where ai

    , bi

    and ci

    are fuel cost coefficients of generator i.Pi

    ispower output of generator i.

    The optimization problem for one-week period is then

    formulated as follows:

    Minimize:

    })1()({ 1

    168

    1 1

    ii

    tt

    N

    i

    i

    t

    i

    t

    ii

    t SuuPFu

    (2)

    Subject to:

    tHN

    N

    i

    i

    tt PVPPPL 1

    (3)

    ii

    t

    i PPP maxmin (4)

    where is the total fuel cost of thermal power plants for one

    week. N is the number of thermal power plants. Pti is power

    output of generator iat time t. utiis state variable of generator

    i at time t (1: committed 0: stopped). Si

    is startup cost ofgenerator i.Ltis load demand at time t.PNis power output of

    nuclear power plant.PHis power output of hydro power plant.

    PVt is theoretical power output of PV at time t. Pimin is

    minimum output of generator i. Pimax is maximum output of

    generator i.

    To solve the optimization problem, Dynamic Programming

    (DP) [3] is used in this research. The merit order method is

    used in the unit commitment. The merit order is determined by

    using the fuel cost of generator at the rated output. The

    combination of committed generators is searched sequentially

    in ascending order of Cidescribed by (5).

    max

    max )(i

    iii

    P

    PFC (5)

    For simplification, the shutdown cost is not considered

    here. The PV output is assumed to be theoretical in generation

    scheduling because power system operator cannot predict its

    output precisely at this time. The theoretical power output of

    PV is shown in Fig. 2.

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    PVOu

    tput[%]

    Time Fig. 2. Theoretical PV Output

    2) Monte Carlo Simulation

    In this paper, we consider three types of probabilistic

    uncertainty concerning load demand, power output of PV and

    generator failure.

    The load demand model with a randomly fluctuating

    component is derived from (6). Ldt is load demand at time t

    considering probabilistic fluctuation. Lgt is load demand at

    time tgiven by the power system model and Fis the random

  • 8/10/2019 06019279

    3/8

    3

    number based on the normal distribution where the average is

    1 and the standard deviation is 3%.

    FLL gtdt (6)

    The power output of PV generation is also modeled with a

    randomly fluctuating component.

    FPVPV gtdt (7)

    where PVdt is PV output at time t considering probabilistic

    fluctuation,PVgtis PV output at time tgiven by the theoretical

    output and F is the random number based on the normal

    distribution considering weather changes shown in Table 1.

    TABLEI

    RANDOM CHARACTERISTIC OF WEATHER CHANGESWeather Average Standard Deviation [%]

    Sunny 1 3

    Cloudy 0.5 20

    Rainy 0.1 0.03

    The weather change is simply modeled at the probability of

    1/3 at time t. It is assumed that the weather is independent

    between before and after time t. The theoretical PV outputs

    for three kinds of weathers are shown in Fig. 3.

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    PVOutput[%]

    Time

    Sunny

    Cloudy

    Rainy

    Fig. 3. PV Output for Three Kinds of Weather

    The generator failure occurs during Monte Carlo

    simulation at the failure rate described by (8). In (8), MTBFi

    is the mean time between failure of generator iand MTTRiis

    the mean time to repair of generatori

    iiMTTR

    1,MTBF

    1 ii (8)

    3) Generator Re-dispatch

    During Monte Carlo simulation, if the generator failure

    occurs at time t, the other generators are re-dispatched

    immediately. Figure 4 shows how the generators are re-

    dispatched when generator G3 is tripped at time t, for example.

    First, Generator G1, G2 and G4 are re-dispatched immediately.

    If imbalance of power supply and demand cannot be avoided

    by the re-dispatching, PSHPP is operated immediately to

    avoid it as an emergency control. In the next time t+1, the

    remaining generators are committed to compensate for the

    unavailable generator. The tripped generator is restored at the

    restoration rateafter time t+1.

    Time t

    G1

    LoadDemand

    G2

    G3

    G4

    G1

    LoadDemand

    G2

    G4

    Supply Demand

    MaximumOutput

    Supply

    Shortage

    G1

    LoadDemand

    G2

    G4

    MaximumOutput

    Emergency

    Control

    PSHPP

    F ir st Step Second S tep

    Generators Re-dispatch

    G1

    LoadDemand

    G2

    G5

    G4

    Time t+1

    Supply Demand

    Generator Failure

    Fig. 4. Generator Re-dispatching

    4) Power Supply Reliability Calculation

    The power supply reliability is evaluated through LOLP

    (Loss of Load Probability) index which can be computed from

    (9). LOSS is the total supply interruption period. C is the

    number of trial. TIME is the simulation period. The trial is

    repeated until 10,000 times so that LOLP is converged to the

    steady-state value.

    TIMEC

    LOSSLOLP

    (9)

    5) Weekly Fuel Cost Calculation

    The weekly fuel cost is calculated at each trial during

    Monte Carlo simulation. If the power output of PV and load

    demand is constant, the weekly fuel cost is not changed from

    the cost which determined by DP. However, the PV output

    and the load demand could fluctuate randomly in Monte Carlo

    simulation. Therefore, the load dispatch of generators is

    changed and its operational cost rises or falls at each trial. In

    this paper, the weekly fuel cost is defined as the mean value of

    fuel costs of all trials excluding the trial where the generator

    failure occurs. This is because the fuel cost increase is the

    unexpected factor due to the generator failure. In other words,the outage cost is not determined uniquely.

    III. OPTIMAL OPERATION SCHEDULING OF PSHPP

    A. Pareto Optimal Solutions

    In general, improvement of power system reliability and

    reduction of operational cost are competing. Optimization of

    the PSHPP scheduling has no unique solution. This type of

    problem is a multi-objective optimization problem. In this

    paper, pareto optimal solutions are obtained.

  • 8/10/2019 06019279

    4/8

    4

    B. Algorithm Overview

    An algorithm overview of the proposed method is shown

    in Fig. 5.

    Fig. 5. Algorithm Overview

    In this study, PSHPP operation schedule is determined by

    Genetic Algorithm (GA) and Tabu Search (TS). GA is one of

    the evolutionary algorithms, which generates solutions to an

    optimization problem using techniques inspired by natural

    evolution, such as inheritance, mutation, selection and

    crossover. It generates multiple solutions simultaneously at

    each generation, and it is good at global search. However GA

    is not good at local search. Therefore, this paper proposes that

    GA and TS are combined to obtain pareto optimal PSHPP

    operation patterns. Tabu search is a local search technique

    which enhances the performance using memory structures

    named Tabu List. Once a potential solution has been

    determined, it is marked as "taboo" so that the algorithm does

    not visit that possibility repeatedly. The parameters of thealgorithm are summarized in Table 2.

    TABLEII

    PARAMETERS OF ALGORITHM

    Repeat GenerationsCmax 5000

    No. of Genes at Each Genaraion 64

    Mutation Rate m 0.05

    Repeat Times of Tabu Search 10

    No. of Neighborhood Solutions 64

    Length of Tabu List 8

    GA

    TS

    Pareto P reservation Strategy

    Roulette Selection

    Uniform Crossover

    Mutation

    Selection

    Reproduction

    C. Algorithm Details

    1) Quantization of PSHPP operation pattern

    The operation pattern of PSHPP is quantized by 6 steps at

    each time t. Figure 6 shows quantization of PSHPP operation

    pattern.

    OutputofP

    SHPP

    Time

    Pump

    Mode

    Gene

    ratorMode

    Stop

    100%

    -100%

    0

    75%

    50%

    25%

    5 4 4 3 1 0 0 1 1 5 4

    Gene Fig. 6. Quantization of PSHPP Operation Pattern

    2) Initial Solutions in GA

    The initial genes of the PSHPP operation patterns are

    generated by random number at each time period, which are

    quantized as mentioned above. If the solution can not satisfy

    the capacity constraint of the PSHPP, the solution is rejected

    and another solution is generated.

    3) Evaluation in GA

    Generated genes are evaluated by Power Supply Reliability

    Evaluation Model described in section II. The evaluation

    indexes are power supply reliability and the fuel cost.

    4) Determine the Pareto Optimal Solutions

    The pareto optimal solutions are determined from

    evaluated solutions. Solutions are labeled by pareto-ranking

    method [4]. The ranking is numbered sequentially from

    solutions closer to pareto optimal solutions

  • 8/10/2019 06019279

    5/8

    5

    5) Selection and Reproduction in GA

    To re-produce the descendants, we use pareto preserve

    strategy and uniform crossover. The pareto optimal solutions

    are inherited to the next generation as elite whose ranking is

    the best. The other descendants are produced by uniform

    crossover whose parents are selected by roulette selection.The parent genes are arranged in descending order of their

    ranking value. The probabilityPnat which the nth rank gene is

    chosen is determined by (10). g is no. of genes at each

    generation. Reproduction is implemented through uniform

    crossover, whereby each component is randomly selected

    from either parent with equal probability. Uniform crossover

    has a good characteristic of being unbiased with respect to the

    reproduction of genes [5]. Mutation is conducted at the rate m

    to prevent the solutions from going into a local optimal

    solution.

    (10)

    6) Tabu Search

    TS is conducted whenever GA is repeated 100 times. TS

    can optimize only single objective function, TS is repeated

    twice from each pareto optimal solutions. First, selecting one

    of the pareto solution, TS is carried out from it. The objective

    function of TS is LOLP improvement. Second, starting from

    the same pareto solution, TS is conducted with objective

    function for cost reduction. Figure 7 shows the searching from

    pareto optimal solutions. This process is repeated until all

    pareto optimal solutions are searched by TS and the pareto

    optimal solutions are revised. Then the process goes back tothe GA. It is repeated until the number of generations reaches

    Cmax.

    Power Supply Reliability

    WeeklyFuelCostofThermalPowerPlants

    Better

    Better

    :Tabu Search Direction for LOLP Improvement:Tabu Search Direction for Cost Reduction

    Fig. 7. TS Direction from Pareto Optimal Solutions

    IV. SIMULATION CONDITION

    A. Simulation Model

    The simulation is carried out on the modified IEEE 24-bus

    Reliability Test System (RTS) [6] with the generator data

    shown in the appendix. The system is modified by adding a

    300MW PSHPP in addition to the existing hydro power plants.

    Since this paper focuses on the power supply reliabilityevaluation, failures in transmission network are not considered.

    B. Simulation Condition

    Figure 8 depicts two different load conditions for two

    seasons, i.e. summer (August) and spring (May). The system

    peak load is 3200 MW. In the simulation, the amount of PV

    penetration is set to be 0MW and 1000MW.

    0

    500

    1000

    1500

    2000

    2500

    3000

    Sa t Sun Mon Tue Wed Thu F r i

    PowerDemand[MW]

    Day

    Summer (August)

    Spring (May)

    Fig. 8. Load Demand Curve

    V. SIMULATION RESULTS

    A. Pareto Optimal Solutions

    The pareto optimal solutions obtained by the proposed

    optimization method are shown in Figs. 9 and 10.

    PV 0MW

    2.9

    3

    3.1

    3.2

    3.3

    3.4

    3.5

    3.6

    3.7

    0 0.05 0.1 0.15 0.2 0.25

    WeeklyFuelCo

    st[Million$]

    LOLP

    PV0 MW

    PV1000 MW

    Fig. 9. Pareto Optimal Solutions (in Summer)

    PV 0MW

    1.1

    1.2

    1.3

    1.4

    1.5

    1.6

    1.7

    0 0.05 0.1 0.15 0.2 0.25

    WeeklyFuelCost[Million$]

    LOLP

    PV0 MW

    PV1000 MW

    Fig. 10. Pareto Optimal Solutions (in Spring)

    g

    k

    n

    k

    ngP

    1

    1

  • 8/10/2019 06019279

    6/8

    6

    In both summer and spring seasons, it can be seen that the

    pareto optimal solutions are located in a narrow range of Cost-

    LOLP space when PV penetration is 0MW. The pareto

    optimal solutions do not include various kinds of operations of

    PSHPP because there is no PV output. On the contrary, the

    pareto optimal solutions includes various kinds of operationpatterns when PV penetration is 1000MW in both summer and

    spring seasons.

    B. Operation Schedule of PSHPP

    The obtained operation schedule of PSHPP is shown in

    Figs. 11 to 14. The best solutions concerning LOLP and the

    fuel cost under each condition are discussed here.

    0

    500

    1000

    1500

    2000

    Sa t Sun Mon Tue Wed Thu Fr iCapacityofUpperReservoir

    [MWh]

    Day

    Best LOLP Best Cost

    Fig. 11. PSHPP Operation Pattern (in Summer with PV 0MW)

    0

    500

    1000

    1500

    2000

    Sa t Sun Mon Tue Wed Thu Fr iCapacityofUpperReservoir[MWh]

    Day

    Best LOLP Best Cost

    Fig. 12. PSHPP Operation Pattern (in Summer with PV 1000MW)

    0

    500

    1000

    1500

    2000

    Sa t Sun Mon Tue Wed Thu Fr iCapacityofUpperReservoir[MWh

    ]

    Day

    Best LOLP Best Cost

    Fig. 13. PSHPP Operation Pattern (in Spring with PV 0MW)

    0

    500

    1000

    1500

    2000

    Sa t Sun Mon Tue Wed Thu Fr iCapacityofUpperR

    eservoir[MWh]

    Day

    Best LOLP Best Cost

    Fig. 14. PSHPP Operation Pattern (in Spring with PV 1000MW)

    In summer, the PSHPP is operated as a pump in the

    nighttime and as a generator in the daytime on weekday to

    supply the heavy summer load when PV penetration is 0MW.

    The role of the PSHPP in this case is load leveling within a

    week. It is the conventional role of PSHPP in the powersystem. Compared with the operation patterns between LOLP

    best case and cost best case, they are not so much difference.

    The near optimal operation pattern is determined uniquely in

    summer season when PV penetration is 0MW. In contrast,

    when the PV penetration increases to 1000 MW in summer,

    the PSHPP is operated as a pump in the daytime and as a

    generator in the nighttime in the LOLP best case in spite of no

    surplus power. However, PSHPP is hardly operated in the cost

    best case.

    In spring, the PSHPP is hardly operated when the PV

    penetration is 0MW because the operation of the PSHPP does

    not contribute much to the fuel cost reduction. When the PV

    penetration increases to 1000 MW, PSHPP is hardly operated

    in the cost best case, either. The PSHPP has to be operated as

    a pump in the daytime both on the weekday and weekend in

    the LOLP best case. This pattern is similar to that of summer

    pattern.

    C. Weekly Generation Schedule

    The weekly thermal generation schedules for the PSHPP

    operation patterns are shown in Figs. 15 and 16. The cost best

    case in summer season when PV penetration is 0MW and the

    LOLP best case in spring season when PV penetration is

    1000MW are discussed here. In Fig. 15, the PSHPP pushes up

    the load demand in the nighttime and pushes it down in the

    daytime on weekdays. In Fig. 16, the PSHPP pushes up the

    load demand in the daytime and pushes it down in the

    nighttime. The deducted load demand shown by solid black

    line falls below the minimum output of thermal plants in the

    daytime, which shows that the surplus power occurs. However,

    in this case, the PSHPP can be operated for both PV output

    decrease and increase by emergency operation. It is concluded

    that modification of the operation pattern of the PSHPP is

    effective for the surplus power problem.

  • 8/10/2019 06019279

    7/8

    7

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    S a t S u n Mo n T u e We d T h u F r i

    PowerOutput/LoadDemand[MW]

    Day

    Maximum Output of Thermal Minimum Output of Thermal

    Hydro Nuclear

    Load Demand (w/o Pump) Load Demand (with Pump)

    Fig. 15. Generation Schedule (in Summer with PV 0MW, for Best Cost)

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    S a t S u n Mo n T u e We d T h u F r i

    Po

    werOutput/LoadDemand[MW]

    Day

    Maximum Output of Thermal Minimum Output of Thermal

    Hydro Nuclear

    Load Demand (w/o PV, w/o P ump) Load Demand (with PV, with Pump)

    Load Demand (with PV, w/o Pump)

    Fig. 16. Generation Schedule (in Spring with PV 1000MW, for Best LOLP)

    VI. CONCLUSION

    This paper presents a new method for determining an

    optimal PSHPP operation pattern which makes it possible to

    improve both reliability and economy in the power systems

    with a large integration of PV. The simulation results show

    that the proposed method is very effective in terms of the

    reliability of power system operation. The total fuel cost of

    thermal power plants increases in order to secure the power

    supply reliability using operation of the PSHPP in power

    system with a large penetration of PV. In this paper, the hot

    reserve capacity is not considered in scheduling of thermal

    power plants. In the future work, it is necessary to develop a

    cooperative scheduling method that optimizes both PSHPP

    operation and hot reserve capacity of thermal power plants.

    VII. APPENDIX

    The generator data of IEEE RTS is tabulated in Table 3.

    The cost curve and the startup cost of thermal power plants

    are shown in Table 4.

    TABLEIII

    GENERATOR DATA OF IEEERTS(MODIFIED)

    1 Thermal (Oil) 5 12 5000 20

    2 Thermal (Oil) 4 20 3000 50

    3 Hydro 4 50 5000 40

    4 Pumped Storage Hydro 1 300 - -

    5 Thermal (Coal) 4 76 3926 48

    6 Thermal (Oil) 3 100 3926 48

    7 Thermal (Coal) 4 155 4110 89

    8 Thermal (Oil) 3 197 4110 89

    9 Thermal (Coal) 1 350 5541 111

    10 Nuclear 2 400 7000 168

    Cap. of

    each

    Unit[MW]

    MTBF [h] MTTR [h]Generator

    Group Type

    No. of

    Unit

    TABLEIV

    THERMAL POWER PLANT DATA

    a b c

    Thermal (Oil) 5 12 6 16-20 0 .0646 16.8899 49.7108 181.6416

    Thermal (Oil) 4 20 10 21-24 0.025 43.5 200 13.356

    Thermal (Coal) 4 76 38 6-9 0.0533 9.2374 164.3492 1111.4208

    Therma l (Oil) 3 100 50 13-15 0. 0224 19.7128 287.4982 1511.8992

    The rma l (Coa l) 4 155 77. 5 2-5 0. 0067 10.2202 207.1786 1777.1544

    Therma l (Oil) 3 197 98. 5 10-12 0. 0081 20.2909 378.5918 2070. 18

    Thermal (Coal) 1 350 175 1 0.0032 10.102 350.6398 8331.9264

    Startup

    Cost [$]

    Minimum

    Output [MW]Type

    No. of

    Unit

    Maximum

    Output [MW]

    Cost Curve [$/hr]

    F(P) = a*P^2+b*P+cMerit

    Order

    VIII. REFERENCES

    [1] R. Aihara, A. Yokoyama, F. Nomiyama and N. Kosugi, Impact of

    Operational Scheduling of Pumped Storage Power Plant Considering

    Excess Energy and Reduction of Fuel Cost on Power Supply Reliability

    in a Power System with a Large Penetration of Photovoltaic

    Generations, inProc. 2010 International Conference on Power System

    Technology, Hangzhou, China, Oct. 2010.

    [2] T. Kuwabara, A. Shibuya, H. Furuta, E. Kita and K. Mitsuhashi, Design

    and dynamic response characteristics of 400 MW adjustable speed

    pumped storage unit for Ohkawachi Power Station, IEEE Transactions

    on Energy Conversion, vol. 11, No. 2, 1996.

    [3]

    Allen J.Wood and Bruce F.Wollenberg, Power Generation, Operation,and Control, John Wiley& Son, 1983

    [4] X. Gandibleux, M. Sevaux, K. Srensen and V. T'Kindt, Metaheuristics

    for multiobjective optimization, Springer, 2004.

    [5] D. Srinivasan and A.Tettamanzi, Heuristics-guided evolutionary

    approach to multiobjective generation scheduling, IEE Proceedings

    Generation, Transmission Distribution, vol. 143, No. 6, 1996.

    [6] Reliability Test System Task Force of the Application of Probability

    Methods subcommittee, IEEE RELIABILITY TEST SYSTEM, IEEE

    Transactions on Power Apparatus and Systems, vol. PAS-98, No. 6,

    1979.

    IX. BIOGRAPHIES

    Ryota Aihara was born in Tokyo, Japan, on

    September 20, 1984. He received B.S. Eng. fromSophia University, Tokyo, Japan in 2009 and M.S

    from The University of Tokyo in 2011. Currently

    he is pursuing the Ph.D. degree at The University

    of Tokyo. He is a student member of IEEJ.

  • 8/10/2019 06019279

    8/8

    8

    Akihiko Yokoyamawas born in Osaka, Japan, on

    October 9, 1956. He received B.S., M.S. and Dr.

    Eng. from The University of Tokyo, Tokyo, Japan

    in 1979, 1981 and 1984, respectively. He has been

    with Department of Electrical Engineering, The

    University of Tokyo since 1984 and currently a

    professor in charge of Power System Engineering.

    He is a member of IEEJ, IEEE and CIGRE.

    Fumitoshi Nomiyama was born in 1969. He

    received his B.Eng., M.Eng. degrees in electrical

    engineering from Doshisha University in 1992 and

    1994 respectively. He joined Kyushu Electric

    Power Company Inc. in April 1994.

    Narifumi Kosugi was born in 1970. He receivedhis B.Eng., M.Eng. degrees in electrical

    engineering from Osaka University in 1993 and

    1995 respectively. He joined Kyushu Electric

    Power Company Inc. in April 1995.