05/07/12 – 5/13/12. Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started. 05/07/12 – 5/13/12. Demolition at 1927 wing nearing completion. 05/07/12 – 5/13/12. Phase 1 Air Handler Units removed. 05/07/12 – 5/13/12. Field Measured Phase 3 Rotunda - PowerPoint PPT Presentation
Citation preview
05/07/12 – 5/13/12
Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started
05/07/12 – 5/13/12
Demolition at 1927 wing nearing completion
05/07/12 – 5/13/12
Phase 1 Air Handler Units removed
•Field Measured Phase 3 Rotunda
•Completed Electrical Shutdown to relocate Main Electrical Panel
Exterior
•Complete drilled piers•Form and Pour Footings at South Side
Interior
•Continue with MEP in 1927 Wing•Prep for floor cut at main electrical room
•Wall off existing area at Spartan Grille to facilitate Taco Bell/C-Store Relocation
During the break…
NEXT WEEK LOOK AHEAD
Phase 3 Rotunda Field Measurement and Verification