ID Activities Time Scale Start Finish InterdependenciesPerson Responsible1 Security 62 days Mon 14/02/11 Mon 16/05/11
2 Submission of updated security planto reflect requirements of the delivery proposals for the MandatoryWork Activity
11 days Mon 14/02/11 Mon 28/02/11 Regional Compliance Manager
3 Independent CESG penetration test 4 days Mon 28/02/11 Thu 03/03/11 Nettitude
4 Review and implementation of new policies and procedures required (ISO27001 Standard)
5 days Mon 28/02/11 Fri 04/03/11 3 Regional Compliance Manager
5 FIPS 140-2 Encryption software introduced
4 days Wed 11/05/11 Mon 16/05/11 Regional Compliance Manager
6 Submission of final security plan 1 day Mon 09/05/11 Mon 09/05/11 Regional Compliance Manager
7 Approval for access to PRaP information / Final security plan sign off
1 day Mon 16/05/11 Mon 16/05/11 6 DWP
8 Implementation of new policies and procedures required from penetration test and final security plan sign off
5 days Thu 28/04/11 Fri 06/05/11 7 Regional Compliance Manager
9 Case Management System and
Installation
62 days Mon 14/02/11 Mon 16/05/11
10 Initial commencement of the development of Case Management System (CMS) including Customer Relationship Management (CRM)
1 day Mon 14/02/11 Mon 14/02/11 Regional Compliance Manager
11 Process map and formal proceduresdeveloped
15 days Mon 04/04/11 Fri 22/04/11 Data Information Manager
12 BETA walk through testing of CMS 5 days Mon 09/05/11 Fri 13/05/11 10 Data Information Manager
13 Additional systems licences for BEST
1 day Tue 12/04/11 Tue 12/04/11 12 Cognisoft Implementation Manager
14 Pre go live role play week and final sign off
2 days Thu 12/05/11 Fri 13/05/11 13 Human Resource Manager,Regional Compliance Manager15 Placement Provider Partners 25 days Wed 06/04/11 Mon 16/05/11
16 Group meeting with all placement provider partners to inform of success and next steps
1 day Wed 27/04/11 Wed 27/04/11 Operations Director
17 Compile and issue terms and conditions for placement provider partners
11 days Wed 13/04/11 Fri 29/04/11 39 Operations Director
18 Compile and issue final Contract based on DWP MWA contract with BEST for all placement provider partners
5 days Mon 09/05/11 Fri 13/05/11 39 Operations Director
19 Individual meetings with all placement provider partners
1 day Mon 16/05/11 Mon 16/05/11 Operations Director
20 Signed contracts in place with call off placement provider partners
1 day Fri 06/05/11 Fri 06/05/11 40 Operations Director
21 Strategic Management Steering Group (SMSG) formed and first meeting conducted draft terms of reference compiled and implementation activity agreed
1 day Wed 11/05/11 Wed 11/05/11 Regional Performance Manager
22 Update BEST Placement directory with placement provider partners placements for North,East Yorkshireand Humber
5 days Thu 28/04/11 Fri 06/05/11
23 Premises 1 day Fri 06/05/11 Fri 06/05/11
24 Health and Safety vetting of each centre, including subcontractor sites
4 days Tue 03/05/11 Fri 06/05/11 DCO
25 Staff Training 45 days Wed 09/03/11 Mon 16/05/11
26 Training needs analysis of BEST 21 days Fri 25/03/11 Fri 22/04/11 Human Resource Manager
27 Creation of training packages and resources
5 days Thu 28/04/11 Fri 06/05/11
28 Job matching from current post to new posts
6 days Wed 20/04/11 Fri 29/04/11 26 Human Resource Manager
Regional Compliance Manager
Nettitude
Regional Compliance Manager
Regional Compliance Manager
Regional Compliance Manager
DWP
Regional Compliance Manager
Regional Compliance Manager
Data Information Manager
Data Information Manager
Cognisoft Implementation Manager
Human Resource Manager,Regional Compliance Manager
Operations Director
Operations Director
Operations Director
Operations Director
Operations Director
Regional Performance Manager
DCO
Human Resource Manager
Human Resource Manager
06 Dec '10 10 Jan '11 14 Feb '11 21 Mar '11 25 Apr '11 30 May '11 04 Jul '11
Activity Summary
Activities
Milestones and Critical Path
Manual Summary
Start Activity
Finish Activity
Activity Progress
BEST Ltd Yorkshire & Humber Mandatory Work Activity
Page 1
Project: final gantt chart 17-02-11Date: Mon 18/04/11
ID Activities Time Scale Start Finish InterdependenciesPerson Responsible29 Workshops for placement providers
partners and BEST staff2 days Thu 05/05/11 Fri 06/05/11 27 Human Resource Manager
30 Webyeti IT training for case management system for BEST
2 days Mon 09/05/11 Tue 10/05/11 14 Cognisoft Implementation Manager
31 Pre go live role play week 4 days Tue 10/05/11 Fri 13/05/11 Regional Compliance Manager,Human Resource Manager
32 Marketing 47 days Mon 07/03/11 Mon 16/05/11
33 Website updates 3 days Wed 11/05/11 Fri 13/05/11 Business Development Manager
34 Develop marketing Literature 6 days Wed 27/04/11 Fri 06/05/11 Business Development Manager
35 Local stakeholder events 1 day Tue 10/05/11 Tue 10/05/11 Business Development Manager
36 JCP awareness campaign 10 days Thu 28/04/11 Fri 13/05/11 Business Development Manager
37 Contract Award 19 days Thu 14/04/11 Mon 16/05/11
38 Preferred bidder notified 1 day Fri 01/04/11 Fri 01/04/11 DWP
39 Confirmation of Contract Award 1 day Thu 28/04/11 Thu 28/04/11 38 DWP
40 Signed Contract with DWP and BEST
1 day Fri 06/05/11 Fri 06/05/11 39 DWP,Managing Director
41 Milestones / Critical Path
42 Final sign off of Health and Safety atall premises including sub contractors
0 days Fri 06/05/11 Fri 06/05/11
43 Sign off of security plan by DWP 0 days Mon 16/05/11 Mon 16/05/11
44 Full availability of IT system CMS and CRM
0 days Fri 06/05/11 Fri 06/05/11
45 Signed Contracts with supply chain 0 days Fri 06/05/11 Fri 06/05/11
46 Go Live role play for all staff 0 days Fri 13/05/11 Fri 13/05/11
47 The BEST MWA goes Live 0 days Mon 16/05/11 Mon 16/05/11
48
49
50
Human Resource Manager
Cognisoft Implementation Manager
Regional Compliance Manager,Human Resource Manager
Business Development Manager
Business Development Manager
Business Development Manager
Business Development Manager
DWP
DWP
DWP,Managing Director
06/05
16/05
06/05
06/05
13/05
16/05
06 Dec '10 10 Jan '11 14 Feb '11 21 Mar '11 25 Apr '11 30 May '11 04 Jul '11
Activity Summary
Activities
Milestones and Critical Path
Manual Summary
Start Activity
Finish Activity
Activity Progress
BEST Ltd Yorkshire & Humber Mandatory Work Activity
Page 2
Project: final gantt chart 17-02-11Date: Mon 18/04/11
1 SecurityOur planning processes have created a responsive MWA model with an early start date of the 18th April. Building on our existing infrastructure we are well placed to offer DWP effective implementation by this date. In order to meet a start date of the 18th April we have made some assumptions in terms of submitting security requirements. In order to provde DWP with a responsive approach we will submit our security plan to DWP after notification of preferred bidder status rather than waiting until 20 days after contract signing. This will facilitate our ability to meet the attached implementation milestones.
15 Placement Provider PartnersIn response to our start date committment of the 18th April we made an assumption that DWP will be able to issue us with the MWA contract award within two weeks of preffered bidder status on the 4th April 2011.