4/28/16 10:47 AM Page 1 of 2
MGM SPRINGFIELD CONSTRUCTION ACTIVITIES - 04/26/16-05/10/16
WORK HOURS: 7:00 AM - 7:00 PM
FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected]
FULL CONSTRUCTION BUILD OUT
ZONE LOCATION STATUS
1 95 and 101 State Street Interior demolition is ongoing. Load testing inside the building is underway.
2 Hotel Backfilling Edisonia basement. Exterior abatement at Union Chandler is underway.
3 Casino Bracing the façade of 73 State Street
4 Da Vinci Park No work anticipated
5 Dave's Furniture No work anticipated
6 Armory Demolition of the rear portion anticipated to begin the week of May 2nd.
7 Plaza Loading out demolition debris from former YWCA Building is underway
8 Church Church building has been relocated to Union St. New foundation installation is anticipated to begin the week of May 2nd.
9 Entertainment No work anticipated
10 Parking Garage Site clearing and dust monitoring is underway. Bulk excavation is underway. Some noise and vibration should be anticipated throughout this process. Dust control measures will be implemented as necessary.
11 Support Area No work anticipated
12 MGM Way No work anticipated
STREET WORK
State Street No work anticipated
Main Street No work anticipated
4/28/16 10:47 AM Page 2 of 2
Union StreetInstallation of isolation valves anticipated to begin week of May 2nd. The road will be closed to thru traffic while this work is being performed. A police detail is anticipated. Access to Milano's parking lot and Pride Gas Station will be maintained throughout the process. Work on Union Street is anticipated to continue through Friday May 6th and could extend into the week of May 9th.
East Columbus Avenue No work anticipated
Bliss Street No work anticipated
Howard Street Turn Around No work anticipated
Howard Street Installation of new water main is underway.
UTILITY ACTIVITY
UTILITY PROVIDER WORK TO BE PERFORMED
Eversource No work anticipated
Verizon No work anticipated
Comcast No work anticipated
Columbia Gas No work anticipated
Springfield Water & Sewer Springfield Water and Sewer will be conducting work along Main Street from State Street to Union Street. Please note that this work is unrelated to the MGM Springfield project.
MISCELANEOUS ACTIVITY
LOCATION WORK TO BE PERFORMED
MGM Springfield Site Soil removal work is underway.
MAIN STREET
STAT
E ST
REET
EAST COLUMBUS AVENUE
BLIS
S ST
REET
UNIO
N ST
REET
HOW
ARD
TURN
ARO
UND
195/101 STATE
2HOTEL
3CASINO
12MGM WAY
7PLAZA
6ARMORY
8CHURCH
5DAVE’S
FURNITURE
4DA VINCI
PARK
9ENTERTAINMENT
10PARKING GARAGE
11SUPPORT
AREA
HOW
ARD
STRE
ET
VALVE INSTALLATION MAY CAUSE STREET CLOSURE THROUGHFRIDAY MAY 6 AND COULD EXTEND INTO THE WEEK OF MAY 9. POLICE DETAIL ANTICIPATED.
STREET CLOSED FOR WATER MAIN WORK THROUGH MAY 6.