Upload
agnihotri-vikas
View
226
Download
0
Embed Size (px)
Citation preview
Business Consulting Services
SCM APO TRAINING COURSE IN SUPPLY NETWORK PLANNING
Unit 3: Master Data
2
COURSE OVERVIEW DIAGRAM
1Course OverviewIntroductions
2SNP Overview
4SNP Transaction Data
5SNP Run Using Heuristics
3SNP Master Data
6SNP Run Using Optimizer
8Deployment Run Using Optimizer
7Deployment Run Using Heuristics
9Integration
3
SNP PROCESS FLOWPlanning Area Administration
Planning Method Determination & Profile Settings
Supply NetworkPlanning Run
Transport Load Building
Deployment Run
Conversion intoPP/DS orders
PP/DS Planning
Release of SNPPlan to DP
Interactive Planning
APO Master Data Setup
Model/Version Creation
Supply Chain Model Setup
Release of Demand Plan to SNP
Simulation
Management by Exception
4
MASTER DATA FOR SNP
• Locations• Products• Resources• Production Process Models• Transportation Lanes• Quota Arrangements
Contents:
Unit5: Master Data | 2005
5
MASTER DATA FOR SNP: UNIT OBJECTIVES
• Identify the master data required to support supply network planning
• Create locations, products, resources, and production process models
• Set up transportation lanes and quota arrangements
At the conclusion of this unit, you will be able to:
Unit5: Master Data | 2005
6
MASTER DATA FOR SNP: BUSINESS SCENARIO
• A Company bought a new production plant. This plant must be modeled in the Supply Chain Engineer.
• Products, resources and production process models must be created.
• Transport lanes to suppliers, distribution centers and quota arrangements must be added to the model.
Unit5: Master Data | 2005
7
MASTER DATA Master Data is the static data used
during planning (as opposed to transactional data)
We map the organization to the system using Master Data
Master Data is required to build a supply chain model and execute planning
It allows us to have standardized information across the entire enterprise
8
MASTER DATA Key master data
Locations Products Resources Production Process Models
Specific Master data for planning methods Directly created or transferred from an
OLTP system
9
MASTER DATA TRANSMISSION
• The Master Data in APO is directly correlated to that in SAP R/3.
• Initially, the data can be transferred from R/3 to APO with subsequent maintenance.
R/3 MASTERDATA Initial Transfer
Incremental transfer
APO MASTERDATA
• Product• Work Center• Plant/
Storage Location
• BOM/ Routing
• Product• Resource• Location
• PPM
Business Consulting Services
LOCATION
11
MASTER DATA -LOCATION
Produc tio n Distributio n Stora g e C ustome r Supp lie r
Loc a tion Typ e
• A Location is a place where you perform an activity.
12
A LOCATION IN THE SUPPLY NETWORK
Products can be stored at this location
Demands to be covered from this location
Storage, handling, supply and production capacities
Calendars for production and shipment
Storage cost per unit for each product Purchasing cost per unit for each product,
material per supplier
13
CREATE A LOCATION IN THE SC ENGINEER
Create Locations Type of Location Name of Location Geographical Information Time Zone
Supplier CustomerDCPlant
Business Consulting Services
PRODUCT/ MATERIAL MASTER
Unit5: Master Data | 2005
15
PRODUCT MASTER Product master is where we store
all static data related to the product (such as dimensions)
all data related to APO processing (such as Procurement Type)
Allows you to maintain Global or Location specific data
Unit5: Master Data | 2005
16
PRODUCT/ MATERIAL MASTER - GLOBAL
ATP Attributes
UOM Classification
SNP 1
Views
Unit5: Master Data | 2005
17
SNP RELEVANT DATA: GLOBAL VIEW
Attributes Gross weight Volume Material Group
Classification Units of measure
SNP 1 Penalty for non-delivery Delay penalty Maximum delay
ATP Data Product Allocation Procedure Sequence
Unit5: Master Data | 2005
18
PRODUCT/ MATERIAL MASTER LOCATION SPECIFIC
Administration Attributes
Unit of Measure Classification
SNP 1 ATP
SNP 2 PP/DS
Procurement GR/GI
Extra
Views
Demand Lot Size
19
SNP RELEVANT DATA: LOCATION VIEW
Administration Production Planner SNP Planner Demand Planner Transportation Planner
Attribute Stacking Factor Shelf Life
Unit Of Measure Classification
SNP 1 Penalty for non-delivery Delay penalty Maximum delay
20
SNP RELEVANT DATA: LOCATION VIEW
ATP Product Allocation Procedure Sequence Checking Mode Checking Horizon ATP Group Checking Horizon Calendar Display Unit/Measure
Demand Demand Profile Strategy Dependant Demand
Always collective requirements
Possible customer individual requirement
Collective order (fixed pegging)
21
EXAMPLE - DEMAND CONSUMPTION
A new sales orders reduce the forecast
Day 1 2 3 4 5 6 735 32 28 23 14 3 112 13 20 15 5 5 547 45 48 38 19 8 8
ForecastTotal Demand
Sales OrderSales Order
Mat 1 2 St 1.000 DMMat 2 5 St 7.500 DM
8.500 DM
Reduce the forecast
Increase the Sales orders
Unit5: Master Data | 2005
22
SNP RELEVANT DATA: LOCATION VIEW
Lot size Lot size profile Processes
Lot for Lot Fixed Lot Size By Period Reorder Point
Scheduling Safety Day’s Supply Available Data Indicator
Quantity Determination Min/Max Lot Size Target Stock Level Method Assembly Scrap Rounding Value Rounding Profile Target Day’s Supply
23
SNP RELEVANT DATA: LOCATION VIEW
SNP 2 SNP Demand profile SNP Supply profile Deployment profile Procurement info
Procurement Procurement
Procurement type Planned Delivery Time
Stock Procurement Costs Stock Costs
24
SNP RELEVANT DATA: LOCATION VIEW
Goods Receipt/Issue– Processing Time in Days
– Capacity Consumption
– Shipping
– Completion Confirmation
– Network Design
– Goods Issue Posting
25
PRODUCT/ MATERIAL MASTER - PROFILES
The relevant fields of the master data are populated by the data specified in the profiles selected.
If the data in the product master is changed, the product master can not be globally maintained via the profiles
26
EXERCISE 5 Carry out the exercises for Product
Master
Business Consulting Services
RESOURCES
Unit5: Master Data | 2005
28
RESOURCES The resources are used to define
Capacities of equipment, machines, personnel, means of transport, warehouses
Resource data are relevant for planning order dates, taking working time and the capacity of the resources into account
Resource types: Single activity/ Multi-activity resource Single Mixed and Multi-Mixed Resource
29
TYPES OF RESOURCES - PP/DS AND SNP CTM
1) SINGLE ACTIVITY/ MULTIPLE ACTIVITY RESOURCES :
These can be scheduled with an accuracy of a second. Scheduling in PP/DS determines the exact production dates of orders and operations. You define the capacity of these resources as a time capacity, based on work time data.
Unit5: Master Data | 2005
30
CAPACITY OF SINGLE & MULTI-ACTIVITY RESOURCES
Time Capacity
Shift sequences
Day 1
Sequence 1 Day 1 Day Day 3 Day Day 4 Day 2 Day
Sequence 2 Day Day
Sequence 3
Shift definitions
24:00
16:00
95 %
21:0020:00
16:0008:00
98 %
13:0012:00
93 %
05:0004:00 00:00
08:00
Sequence 3Sequence 1 Sequence 2
Intervals of the capacity variant
08/22/99 08/23/9908/01/9907/31/99
Break patterns
21:0020:0005:00
04:00
13:0012:00Shift factors
93 %95 %
98 %Individualresources Resource utilization
Day 6 Day 1
Unit5: Master Data | 2005
31
RESOURCE CATEGORIES
TransportProduction
Storage Handling
Unit5: Master Data | 2005
32
RESOURCE CATEGORIES Describes the usage of the resource
It is a purely descriptive characteristic that can be used for selecting resources for resource maintenance
It is not linked with a planning functionality
Unit5: Master Data | 2005
33
RESOURCE MASTER DATA
Standard Capacity
General Data
Planning Parameters
Short Text
Resource Master Data
Characteristic
Down Times
Unit5: Master Data | 2005
34
RESOURCE MASTER DATA
General Data Resource Category Location Time Zone Planner Planning Calendar Active Variant Reference Resource
Unit5: Master Data | 2005
35
PLANNING PARAMETERS Parameters in the resource that are
relevant to scheduling, which the system uses in PP/DS and SNP.
Used to control in detail how the system schedules orders to resources.
Examples: Overload, Bottleneck resource, activity overlap periods, etc.
Unit5: Master Data | 2005
36
RESOURCE MASTER DATA
Standard Capacity Down Times
Validity of down times Start and end time of down times Type of down time
Characteristics Short Texts
Business Consulting Services
PRODUCTION PLANNING MODEL
Unit5: Master Data | 2005
38
PRODUCTION PROCESS MODEL (PPM)
PPM summarizes Routing BOM
PPM supports Location-dependent (PPM ID) and
location-independent (Plan No.) Min/max lot sizes for the master material Operations
Set of different process steps (e.g. setup, etc.) Bucketed time intervals for each process step Resources assigned to production steps
Planning Order
Process
Unit5: Master Data | 2005
39
INPUT/OUTPUT COMPONENTS
Input Components Identification of “raw
material” Output components
Co-products Model bin splits No explicit head
material for processes
Co-products
Processes
R R
R R
Unit5: Master Data | 2005
40
TIME-DEPENDENT PROCESS PARAMETER
Time-dependent process parameters for Yield Duration Capacity consumption Quantities of input /
output components
yield 100%
yield 70%
yield 50%
yield 100%
Process
50 %
100 %
0 %Yield (learning curve) t
Unit5: Master Data | 2005
41
PRODUCTION PROCESS MODEL
Operations: Supply material Pre-assembly Final assembly Inspection
Activities: Setup Produce Tear down Queue time
Product Relationship Resources
In / Out
Resource consumption
Header: Costs, Lot size range $
Sequence
Unit5: Master Data | 2005
42
SNP MATERIAL FLOW LOGIC
• PPM rough cut plan
• Activity time bucket
1. timebucket
2. timebucket
Input Output
Orders:1001100510071009
Quantities:100200300100
Time bucket = 700
Unit5: Master Data | 2005
43
PPM - PROCESS FLOW
Create Operations Define Activities for each of the
operations Assign Resources to the
Operations Assign Components to the PPM Establish the activity
relationship Set up time dependant
parameters Perform the product plan
assignment
Unit5: Master Data | 2005
44
PPM - CONSISTENCY CHECK The consistency check function
analyzes the PPM and determines whether all of the logical assignments are correct.
It will give an alert to warn of incorrect assignments or missing elements.
Unit5: Master Data | 2005
45
EXERCISE 6 Carry out the exercises for Resources
and PPMs.
Business Consulting Services
TRANSPORTATION LANES
Unit5: Master Data | 2005
47
TRANSPORTATION LANES
Represent a business relationship between locations.
Can be created by dragging from the source location and dropping on the target location on the Supply Chain Model.
Unit5: Master Data | 2005 48
TRANSPORTATION LANES
Multiple transportation modes per lane
Products that can be carried by a transportation mode
Transportation capacity by volume, weight, pallets
Transportation costs per unit, product and transportation
mode
Unit5: Master Data | 2005
49
CREATE A TRANSPORT LANE IN THE SC ENGINEER
Maintain Transportation Lanes Transportation Methods Validity Period Transportation Duration Costs Material Independent Priority Transportation Resource TLB Profile
Business Consulting Services
QUOTA ARRANGEMENTS
Unit5: Master Data | 2005
51
WHAT IS A QUOTA ARRANGEMENTS ?
Forecasts,Customers orders
Sourcing Production &Purchasing
Requirements,Inventory levels
APO
Liste
Definition
Incoming quotas Production lead times Transportation lead times
Supply Chain Model
40%60%
Unit5: Master Data | 2005 52
QUOTAS IN THE SNP RUN Netting calculation (for
example, inventories, in transits)
Requirements are passed through the network, accounting for: Delivery times Incoming quota
arrangements Single-sourcing Multi-sourcing
Result: Production or procurement quantities
50
30
70
50
Unit5: Master Data | 2005 53
INCOMING QUOTAS
40%60%30%
70%
Incoming Quotas
Production Location Distribution Center (DC)
Quota
?Supplier
60% 40%
Product
Unit5: Master Data | 2005 54
OUTGOING QUOTAS
40%60%30%
70% Outgoing Quotas
Production Location Distribution Center (DC)
Quota
?Supplier
60% 40%
Product
Unit5: Master Data | 2005
55
MAINTAIN QUOTA ARRANGEMENTS
Determines what percentage of a certain product will be shipped to/ from a specific location
Quotas are location specific, but model independent
Quotas can be incoming or outgoing from a location
Expressed as a percentage Each quota arrangement has a priority Quota arrangement uses Lot Size Profile
Unit5: Master Data | 2005
56
CREATING A QUOTA ARRANGEMENT USING THE SC ENGINEER
Maintain quota arrangements for use in SNP heuristics Validity Period Location Quota % Material-Dependent Priority Lot Size Profile
60%
40%
Unit5: Master Data | 2005
57
EXERCISE 7 Carry out the exercises for
Transportation Lanes and Quota Arrangements
Unit5: Master Data | 2005
58
MASTER DATA FOR SNP: UNIT SUMMARY
Identify the master data required to support supply network planning
Create locations, products, resources, and production process models
Create transportation lanes and set up quota arrangements
You are now able to: