0168paper Long

Embed Size (px)

Citation preview

  • 7/27/2019 0168paper Long

    1/8

    Abstract

    Schedule delays commonly occur in construction projects and often result in delay claims. However,

    there is no well recognized and acceptable claim resolution approach for solving construction

    schedule delays. Most available methodologies are processes-based approaches but not computerized,

    which should be executed by schedule analysts manually. To solve schedule delay problems related

    with lost productivity, a previous study proposed a delay analysis method that integrated a lost

    productivity calculation approach into the collapsed as-built method. The purpose of this study is to

    implement the developed methodology on a project management system. This study first detailed the

    processes of delay analysis, which provided a fundamental to select a suitable development tool for

    implementing delay analysis processes. Second, this study evaluated the potential tools in

    implementing delay analysis methodology. One of popular project management systems was selected

    because it provided flexible program development functionality and it had high performance in

    schedule management. Based on the results of process analysis and development tool selection, this

    study then developed a system prototype for solving the schedule delay problems with lostproductivity. The developed system not only calculated accurate delay amounts for each activity and

    clear delay liability for contract parties, but also reduced analytical time due to computerizing tedious

    computational processes. Finally, the practicability of developed system had been examined by a

    simplified real case. In sum, this study developed a prototype system to help schedule analysts to

    solve their schedule delay problems on project management system.

    Keywords: Schedule Delay Analysis, Construction Project, Project Management System.

    1 IntroductionSchedule delays commonly occur in construction projects and often result in delay claims. However,there is no well recognized and acceptable claim resolution approach for solving construction

    schedule delays. Several studies have proposed different schedule delay analysis methodologies for

    performing delay analysis systematically. The common used methodologies include global impact, net

    impact, adjusted as-built CPM, as-planned expanded, but-for, snapshot, time impact, windows,

    isolated delay type techniques and isolated collapsed but-for delay analysis methodologies (Ng,

    Skitmore et al., 2004; Mohan and Al-Gahtani, 2006; Yang and Yin, 2009). In general, by using the as-

    planned or as-built schedules as baseline schedules, available methodologies calculate schedule

    impacts of delayed events according to the differences between the baseline schedules and some

    entitled impacted schedules that are derived from delayed events. Furthermore, most available

    Implementing schedule delay analysis methodology on projectmanagement system

    Jyh-Bin Yang

    Graduate Institute of Construction Engineering & Management, National Central UniversityKuei-Mei HuangPh.D. Program of Technology Management, Chung Hua University

    Ciou-Mei Chen and Shao-Chu LiuDepartment of Construction Management, Chung Hua University

  • 7/27/2019 0168paper Long

    2/8

    methodologies are processes-based approaches, which are executed by schedule analysts manually. In

    other words, if project schedules are complex, the processes for completing required delay analyses

    are tedious and time-consuming. Most of the methodologies mentioned above are not computerized.

    That is, the schedule delay analysts should complete their works manually although their available

    schedules are generated by professional scheduling systems or project management systems.

    Lost productivity means completing planned work at less planned rate of production (Trauner,2009). In construction projects, contractors often suffer certain damages from lost productivity when

    delaying as-planned schedules. To solve schedule delay problems associated with lost productivity, a

    previous study has proposed a delay analysis method that integrated a lost productivity calculation

    approach into the collapsed as-built method (Yang et al., 2011). Similar to available common

    schedule delay analysis methodologies, the approach proposed by Yang et al. (2011) required

    schedule analysts with professional skills to spend pretty time in analysis. Namely, using that

    approach to solve schedule delay problem with lost productivity is still tedious and time-consuming.

    Based on above introduction to research background and motivation, the purpose of this study is to

    implement a delay analysis method with considering lost productivity on a project management

    system. This paper is organized as follows. Section 2 discusses the processes for delay analysis, which

    provides a fundamental to select a suitable development tool for implementing delay analysis

    processes. Section 3 evaluates the potential tools for implementing delay analysis methodology.Section 4 introduces the developed system prototype for solving the schedule delay problems with

    lost productivity, and the implementation of developed system on a simplified real case. Section 5

    concludes some findings and potential future research directions.

    2 Processes of delay analysis2.1 General delay analysis processesFor solving encountered schedule delay problems, Schumacher (1995) proposed four questions to

    help delay analysts clarifying their delay problems: What was supposed to happen?, What did

    happen?, What were the differences? and How did they affect the project schedule?. Based onthe viewpoint of Schumacher, Kao and Yang (2009) organized delay analysis as a four-phase task.

    The phases consist of determining baseline schedules, building updated schedules, executing delay

    analysis and allocating responsibilities of delays.

    Before executing delay analyses mentioned above, delay analysts should select a suitable delay

    analysis methodology based on their available delay-related information and documents. Each

    methodology has different information and document requirements. However, the as-planned and as-

    built schedules are necessary for most methodologies. Furthermore, previous studies (Arditi and

    Pattanalitchamroon, 2006; Kao and Yang, 2009) proposed certain guidelines (for example,

    availability of information, time of analysis and capabilities of the methodology) for helping delay

    analysts screening suitable methodologies. If one methodology was selected, detailed delay analysis

    processes regarded to the methodology should be followed in executing necessary analyses.

    2.2 Delay analysis with lost productivityIt is well known that many diversified delay factors might cause individual activities be completed

    behind original schedules and consequently delayed project completion. Previous studies have

    identified many common factors of delaying schedules in all stages of construction projects. For

    example, the causes of late drawings and specifications delivery, slow inspection by clients

    representative and unforeseen site conditions in a projects construction stage were identified

    previously (Yang and Ou, 2008). Notably, above delay factors might make activities suspended or

    influence them partially. The former situation is easy to quantify its impact; the latter situation is hard

  • 7/27/2019 0168paper Long

    3/8

    and complicated to quantify its impact, which is usually considered as the problem of lost

    productivity.

    In managing a construction project, a contractor usually suffers certain damages by lost

    productivity caused by the owner or the third party. Lost productivity, resulting from some actions

    with owners or third partys responsibility, may not be easily detected. How to calculate the schedule

    impacts by lost productivity plays a key role for solving a delay claim with lost productivity.Although various lost productivity calculation methodologies have been developed (Lee et al.,

    2005; Lee et al. 2011), a contractor suffering the problem of lost productivity might have no

    appropriate method to quantify its damages. Furthermore, most available delay analysis

    methodologies concentrated on calculating the impact of identified delay events on project duration.

    They did not include delay evidence in their delay analyses. Namely, before performing delay

    analysis by available delay analysis methodologies, schedule analysts should identify delayed events

    and even quantify delay impacts in duration.

    2.3 Simulated delay analysis proceduresA study tried to eliminate some pitfalls existed in previous delay analysis methodologies with

    considering lost productivity, and proposed an innovative delay analysis method (Yang et al., 2011).The proposed analysis procedures were summarized as follows.

    Step 1: to collect the as-planned schedule, as-build schedule and construction daily reports. Step 2: to clarify whether the delayed activity has the impact of lost productivity. Step 3: to collect productivity-related information, including resource usage, finished item with

    quantity, and minutes.

    Step 4: to identify delayed schedule caused by lost productivity. Step 5: to calculate regular and impacted productivities. Step 6: to calculate impacted as-built schedule. Step 7: to calculate the variance between the impacted as-built schedule and the as-built schedule. Step 8: to summarize all schedule variances.

    Based on above steps and the methodology proposed by Yang et al. (2011), this study tried tosimulate whole schedule delay analysis approach for a construction project with lost productivity

    problems.

    3 Tools evaluation for system developmentSome software packages/programs for professional schedule delay analysis have been developed and

    commercialized. Yang (2005) reported the results of a performance comparison between Claim

    Digger (now incorporated into Oracles Primavera P6 system) and Schedule AnalyzerTM Professional.

    That study concluded that existed packages/programs had some limitations including limited schedule

    delay analysis methodologies involved. The discussed packages/programs in that study provided end-

    users fixed functionalities for executing. Therefore, using such packages/programs to implement delayanalysis methodology discussed previously is impossible due to their capabilities of programmable by

    end-users.

    Recently, project management systems are popular gradually due to the wide and quick

    development and promotion of project management professionals. Many project management systems

    were developed for construction project scheduling. For example, Oracles Primavera P6,

    BuilderTREND, and HeadsUp iCPM were evaluated as best systems for construction projects

    (Software Advice, Inc., 2012). These systems were designated to help users to planning and

    controlling construction projects, especially on project schedules.

  • 7/27/2019 0168paper Long

    4/8

    Considering the futures of system price, system programmability, user interfaces and easy-to-use,

    this study evaluated several project management systems, which are popular in Taiwans construction

    industry. The evaluated systems include Oracles Primavera (P3 and P6), Delteks Open Plan TM

    Professional and Microsoft Project. Based on the criterion of system programmability, this study

    selected the Microsoft Project version 2007 (Microsoft Corp., 2011a) for implementing selected

    methodology. Microsoft Project

    provides a programming language, the Microsoft Visual Basic forApplications (VBA), for users to customizing their specific requirements. In comparison with other

    development tools, the Microsoft Project

    and VBA offers useful assistance, including embedded

    logistical rules and mathematical functions, direct Macro recording, on-line tutorial documents, and

    real-time debugging description.

    In sum, for improving the system usability of developed prototype, this study developed the

    system prototype based on the Microsoft Project 2007 Professional version, in which programmer

    can use the VBA macro tool to coding. The end-users can run developed system on the environment

    of Microsoft Project

    2007 and incorporate existed project schedules according to the format of

    Microsoft Project 2007. This decision of tool evaluation diminishes the barriers of system

    development and system usage for developer and end-user, respectively.

    4 System prototype for solving lost productivity delay problems4.1 System prototypeUsing the Microsoft Project 2007 traditional Chinese version as system development platform, this

    study developed a system prototype for solving lost productivity delay problems in constriction

    projects. Figure 1 shows the user interface of developed system prototype. The system prototype

    provides six steps designed in different tabs, respectively. A user can finish his/her analyses after

    completing these steps consequently. All steps are illustrated as follows:

    Figure 1. Example system dialog for developed prototype.

    First, the user should upload three schedules (as-planned schedule, as-built schedule with lostproductivity impacts and a benchmarking schedule without lost productivity impacts) into the

    system. When all schedules were uploaded completed, the system identified delayed activity

    automatically.

    Second, for each delayed activity, the user should input its start and finish dates of delay eventsrelated to lost productivity. The system customized a data sheet for data input and calculation.

    Notably, although the Microsoft Project

    2007 Professional version provides a working space for

    user to identify resources for cost management and resource-related scheduling, it has many

  • 7/27/2019 0168paper Long

    5/8

    limitations in use. For productivity calculation, the information stored in Microsoft Project

    for

    general cost management and resource-related scheduling is not enough. This study organized a

    new data sheet for productivity calculation. Figure 2 shows the customized data sheet on Microsoft

    Project.

    Figure 2. Customized data sheet for data input and calculation.

    Third, for each delayed activity, the user should input its productivity-related information. Forexample, planned and actual resources inputs, and planned and actual complete units are required.

    In general, this productivity-related information can be retrieved from construction daily reports.

    Fourth, after checking the completeness of required data, the system automatically calculated thedelayed days caused by lost productivity. The system calculated the schedule impact of lost

    productivity based on a proven methodology which was not discussed in this study. The result

    shown in this step is the answer for schedule delay analysis with considering lost productivity.

    Fifth, if the user can identify the liability (excusable delay or non-excusable delay) of scheduledelays for each delayed activity in this step, the system allocated all delay liabilities to the owner

    and the contractor, respectively.

    Last, the system will display final analytical results, including the total delayed duration on aproject and the delayed amounts allocated to the owner and the contractor, respectively.

    4.2 System evaluationFor demonstrating its practicability of developed system prototype, this study examined the system

    using a simplified real case. Table 1 shows the basic information for the demonstration project.

    Notably, this project encountered the problems of land acquisition and moving existing conduits,

    those made the contractor losing his planned construction productivity.

    Table 1. Basic information for demonstrated project.

    Feature Information

    Project Name AAA Road Construction Project

    Location Taichung, Taiwan

    Contract Price NT$ 2,598,000,000Construction duration 1,218 calendar days

    Penalty rate for delay 1/1000 of contract price per day

    Identified delay events Typhoon, land acquisition, moving existing conduits

    Due to the complete project schedule for the demonstration project is huge and complex, this study

    extracted two independent activities for demonstration. Table 2 shows the study activities, two

    drainage culvert activities. The activity N1 is a normal activity and activity D1 is a delayed activity.

    Complete information for their planned and actual start and finish dates are provided in Table 2.

    Figure 3 shows the complete schedule for study activity D1.

  • 7/27/2019 0168paper Long

    6/8

    For calculating the impact of lost productivity on a delayed activity, the user should provide some

    productivity-related information, including planned resource, work quantity, actual resource used and

    actual work quantity completed. Figure 4 shows the user interface for productivity information entry.

    Table 2. Schedule information for study delayed and normal activities.

    Type Activity Dur.

    (day)

    Critical Start

    date

    Finish

    date

    Dur.

    (day)

    Actual

    start

    date

    Actual

    finish

    date

    Delayed

    duration

    Delayed D1 72 Yes 08/03/14 08/05/24 94 08/03/14 08/06/15 22

    Normal N1 80 Yes 08/06/17 08/09/04 80 08/06/17 08/09/04 0

    Figure 3. Complete schedule for study activity D1.

    Figure 4. Productivity information input interface.

    Furthermore, this demonstration project encountered delay problems with lost productivity. Within

    this demonstration case, all delayed events were caused by the force majeure which was proposed by

    the contractor. Based on the viewpoint of the contractor, these delays are non-excusable delays. While

    the information was identified and input, the system performed complete delay analysis. Figure 5

    shows the final analytical results for the demonstration case, in which, among the twenty-two delay

    days, roughly twenty-one days are entitled to the owner and one day to the contractor.

  • 7/27/2019 0168paper Long

    7/8

    As illustrated previously, a user can use the developed prototype system to calculate the delay

    liability quickly by providing necessary information. Based on the developed system, the user

    performs required schedule delay analyses by easy-to-use interfaces. Namely, through the developed

    system, completing delay analysis is easy and time-saving.

    Figure 5. Final analytical results for demonstration case in developed prototype system.

    5 Conclusions and SuggestionsSchedule delays commonly occur in construction projects and often result in delay claims. Most

    available methodologies are processes-based approaches and not computerized, which should be

    executed by schedule analysts manually and make delay analyses tedious and time-consuming. Based

    on a delay analysis methodology that integrates a lost productivity calculation approach into the

    collapsed as-built method, this study implemented the methodology on a project management system.

    Through a popular project management system, the Microsoft Project 2007 Professional version,

    this study developed a prototype for delay analysis. For demonstrating the capability of developed

    prototype, this study used a simplified real case to perform delay analysis. The developed system does

    not only calculate accurate delay amounts for each activity as well as clear delay liability for contract

    parties, but also reduces analytical time due to computerizing tedious computational processes. This

    proves that the developed prototype system can help users to solve their schedule delay problems on a

    project management system.

    Based on the study results, two potential research issues can be performed in the future, those

    include:

    Providing more user-friendly interfaces for end-users. The developed prototype limited the user toinput productivity information through a customized data sheet and to provide project schedules in

    the format of Microsoft Project

    2007. This limitation makes the user must be famous with the

    project management system in advance.

    Examining the prototype using additional complicated cases. This study tested the prototype usinga simplified real case only. More examinations by using additional complicated cases provide

    more convince evidence to prove the capability of developed system.

    Acknowledgements

    The authors would like to thank the National Science Council, Taiwan, ROC, for financially

    supporting this research under Contract No. NSC-100-2221-E-008-117.

  • 7/27/2019 0168paper Long

    8/8

    References

    ARDITI D, PATTANALITCHAMROON T. 2009, Selecting a delay analysis method in resolving construction claims.International Journal of Project Management, 24(2), 145-155.

    KAO, C.K. and YANG, J.B., 2009, Comparison of windows-based delay analysis methods, International Journal of ProjectManagement, 27(4), 408-418.

    LEE, H.S., RYU, H.-G., YU, J.-H. and KIM, J.-J., 2005, Method for calculating schedule delay considering lost productivity,Journal of Construction Engineering and Management, 131(11),1147-1154.

    LEE, J.S. and DIEKMANN, J.E., 2011, Delay analysis considering production rate, Canadian Journal of Civil Engineering,38(4), 361-372.

    MOHAN, S.B., and AL-GAHTANI, K.S. 2006. Current delay analysis techniques and improvements. Cost Engineering,48(9), 12-21.

    NG, S.T., SKITMORE, M., DENG, M. Z. M., and NADEEM, A. 2004. Improving existing delay analysis techniques for theestablishment of delay liabilities. Construction Innovation, 4(1), 3-17.

    SCHUMACHER, L. 1995, Quantifying and apportioning delay on construction projects. Cost Engineering, 37(2), 11-3.

    SOFTWARE ADVICE, INC. 2012. Construction Project Scheduling Systems, Available online:http://www.softwareadvice.com/construction/project-scheduling-software-comparison/, Last accessed: Feb. 2012.

    TRAUNER, T.J. 2009. Construction Delays Understanding Them Clearly, Analyzing Them Correctly. Amsterdam; Boston:Butterworth-Heinemann.

    YANG, J.B. 2005. Comparison of delay analysis software for construction projects. In: 33rd Annual Canadian Society forCivil Engineering (CSCE) Conference, 2-4 June, 2005, Toronto, Canada.

    YANG, J.B. and OU, S.F. 2008, Using structural equation modeling to analyze relationships among key causes of delay inconstruction, Canadian Journal of Civil Engineering, 35(4), 321-332.

    YANG, J.B. and YIN, P.C. 2009. Isolated Collapsed But-For Delay Analysis Methodology. Journal of ConstructionEngineering and Management, ASCE, 135(7), 570-578.

    YANG, J.B. HUANG, K.M., LEE, C.H. and CHEN, S.M., 2011. Delay Impact Analysis Method for Lost Productivity inConstruction Projects, In: International Symposium on Automation and Robotics in Construction 2011 (ISARC 2011,28th ISARC), June 29- July 2, 2011, Seoul, Korea.